participating generator (pg) certification process cdwr generation resource development workshop
DESCRIPTION
Participating Generator (PG) Certification Process CDWR Generation Resource Development Workshop 3/29/01 Kyle Hoffman. PG Certification Process. Overview Contracts ISO Metering & Energy Communication Network Telemetry Ancillary Services Certification Automated Dispatching System - PowerPoint PPT PresentationTRANSCRIPT
California Independent System Operator
Participating Generator (PG) Certification Process
CDWR Generation Resource
Development Workshop
3/29/01Kyle Hoffman
California Independent System Operator
PG Certification Process
• Overview– Contracts– ISO Metering & Energy Communication Network– Telemetry– Ancillary Services Certification– Automated Dispatching System– Certified Scheduling Coordinator
California Independent System Operator
PG Certification Process
• Applicable to:– New Generators – Restarts/Repowers
– “QF conversions” upon release from IOU Standard Offer contract
* ISO expediting PG Certification for Summer 2001 Reliability Generation
California Independent System Operator
PG Certification Process
• Execution of Contractual Agreements with the ISO– Participating Generator Agreement – Meter Service Agreement for ISO Metered Entities
– http://www.caiso.com/clientserv/agreements/
California Independent System Operator
PG Certification Process• ISO Metering Installation
– Metering Guidelines (http://www.caiso.com/clientserv/metering/guidelines/index.html)
– Installation of ISO Specification Metering by a certified installer
– Certification of meters by an independent certification company
– ISO Energy Communications Network (ECN) “ExtraNet” Connectivity
California Independent System Operator
PG Certification Process
• Energy Management System (EMS) Visibility – SCADA/Telemetry– Required of ALL generators 10 MW or greater– Required of generators 1 MW or greater
participating ISO Ancillary Services (A/S) Markets
– Telemetry Standards (http://www.caiso.com/thegrid/operations/gcp)
California Independent System Operator
PG Certification Process
• Ancillary Services (A/S) Certification– Required of generators participating in ISO Operating
Reserves Capacity or A/S Markets – A/S Certification Testing and Request Form
(http://www.caiso.com/thegrid/operations/opsdoc/gcp)– ISO Operating Procedure G-213 - “Management of
Ancillary Services Certification Testing”– Pmax, ramp rates, AGC response
California Independent System Operator
PG Certification Process
• Automated Dispatch System (ADS) Connectivity– ISO “Electronic Dispatch” system
(http://www.caiso.com/clientserv/ads)– Required of all “dispatchable” resources,
participating in ISO Real Time (RT) Energy Market
California Independent System Operator
PG Certification Process
• Select a Certified Scheduling Coordinator (SC) to Schedule Unit’s Operation within California ISO Control Area
- SC schedules generator’s power flow
- ISO reads meter via ECN
- ISO settles grid charges with generator’s SC
California Independent System Operator
ISO Market Services
• For information on the ISO Participating Generator Certification Process, please contact Client Relations at:
– 916-608-7059– http://www.caiso.com/clientserv/certification/