part of nsr program applicable to major sources in areas not attaining the naaqs nonattainment nsr...
TRANSCRIPT
Part of NSR Program Applicable to Major Sources in Areas Not
Attaining the NAAQS
Nonattainment NSR Program (NA NSR)
2
• Re-cap of Permitting Process
• Brief Description of NA NSR Program
• Main Requirements Summary
Presentation Outline
3Permitting Process Simplified
Start
Source not
subject toNSR
Source owner submits permit
application
Reviewing authority reviews:• Application
• Proposed/Required Control Technologies
• Compliance with other applicable requirements
Draft permit
developed
Final permitIssued
End
EPA issued permits may be appealed through EPA’s Environmental Appeals
Board (EAB). After EAB process, permits may be appealed in Federal Court.
APPL
ICAB
ILIT
YAP
PLIC
ATIO
NAP
PEAL
S
Are the source proposed emissions ≥
applicable thresholds or emission rates? (per
pollutant, may include fugitives)
Is the
permit for a new source or a
modification to an existing
source?
Is source in an area
that is attaining or nonattaining the
NAAQS?No
Yes
30 day comment
period
Public hearing
Usually appealed within
30 days of finalpermit decision
After appeal processends, permit is
finally approved orrevoked.
Is thesource
exempted?
4
• New sources locating in nonattainment areas with air emissions of 100 tpy or more– Lower thresholds apply depending on nonattainment
severity
• Modified sources located in nonattainment areas with a net emissions increase higher than the significant emissions rate
• Regulated pollutants: NAAQS only
Applicability: New and Modified Sources
5
• Emissions calculations are based on Potential to Emit, includes fugitive emissions if the source is part of the 28 source category list
• It can also consider limitations on source operation and emission controls
• Thresholds: 100 tpy or lower depending on nonattainment severity (See Presentation Appendix)
Applicability: New Sources
Start
Determine source’s
Potential to Emit (PTE)
(per pollutant, may include
fugitives)
Is PTE ≥ applicablethreshold?
(per pollutant)
Source not
subject toNA NSR
Yes
No
Source subject toNA NSR
6
• Emissions calculations are based on Actual Emissions – “day-to-day” emissions at the source– Actual emissions = projected emissions after the change – baseline
emissions before the change (actual-to-projected actual test)– Baseline emissions: average of any 24 consecutive months of
emissions within 10 yrs prior to project (5 yrs for electric utilities)– Projected emissions: max. annual emissions (tpy) that will occur
during any one of 5 yrs after project– If unit was unpermitted or is added, emission increase based on PTE
Applicability: Modifications
7
Applicability: Modifications (Continued)
YesStart
Are Proposed
modification emissions ≥
SER?(per pollutant)
Modification not
subject toMajor NSR
Determine Source’s NetEmissions Increase
(NEI),(per pollutant)
Is the NEI ≥ SER?
Modification is a major
modification and
subject toMajor NSR
Yes
NoNo
Major modification = one that results in (1) a significant emissions increase from the project and (2) a significant net emissions increase (NEI)• Significant Emission Rate (SER) – emissions rate limit in tpy, by pollutant• NEI = Sum of contemporaneous emissions increases and decreases to the
proposed modification emissions increase/decrease• Under Tribal NSR Rule, contemporaneous period starts 5 years before the source
commences construction and ends when the source commences operation
8
• As with the Tribal Minor NSR program, NSR applicability is determined for all new and modified units at the source– New units – applicability based on PTE– Modified units – applicability based on actual emissions
• Includes all NAAQS that the source emits • Source emissions are calculated using:
– On-site measurement (e.g. stack testing)– Vendor design capacity or rated capacity information – Material (i.e. mass balance) balance calculations – Emission factors
• The annual maximum emissions from all production processes/equipment are added for each regulated NSR pollutant
Applicability: Steps
Modification Example
10
• SO2 emissions from a proposed project are 80 tpy
• The SER for SO2 is 40 tpy
• First step, determine if source emissions are higher than the SER
• In this case, 80 tpy > 40 tpy SER for SO2
• Since project emissions > significant emissions rate (SER), source has to do second step, determine if its net emissions increase is higher than the SER
Applicability: 1. Determine the emissions increase from the proposed project
11
• To determine the source’s net emission increase, we need to define the contemporaneous period
– Under Tribal NSR rule, period starts 5 years before the source commences construction and ends when the source commences operation
• For example, if the SO2 source planned to commence construction in June 2012 and begin operation in September 2014, the contemporaneous period for Appendix S is defined as:
Applicability: 2. Determine the beginning and ending dates of the contemporaneous period
June 2012
Commence Construction
June 2011
June 2010
June 2009
June 2008
June 2007
June 2013
June 2014
Sept. 2014
Commence Operation
80 tpy
12
• Determine emission increases and decreases associated with a physical change or change in the method of operation at the source which did not require a permit
• For example, our SO2 source increased its SO2 emissions in 2009 and decreased its emissions in 2014
Applicability: 3. Determine which units experienced an increase or decrease in emissions during contemp. period
June 2012
Commence Construction
June 2011
June 2010
June 2009
June 2008
June 2007
Sept. 2014
Commence Operation
June 2013
June 2014
80 tpy
• An increase or decrease is not creditable if it has been previously relied on for issuing a permit and the permit is in effect during the review
• A decrease is creditable only to the extent that it:– Is “federally-enforceable” from the moment that the actual
construction begins – Occurs before the proposed emissions increase
• A source cannot take credit for:– A decrease that it has had to make, or will make, in order to bring an
emission unit into compliance– An emissions reduction from a unit which was permitted but never
built or operated
Applicability: 4. Determine which emissions are creditable
14
• On a pollutant by pollutant basis• Based on difference between old level and new level of emissions for
each unit (actual-to-projected actual test)• Past decreases and/or increases in actual emissions based on:
– Average of any two consecutive years in the past 5 for electric utilities– Average of any two consecutive years in the past 10 for non-utilities
• For example, SO2 emissions decreases and increases are:
Applicability: 5. Determine the amount of each contemporaneous emissions increase or decrease
June 2012
Commence Construction
June 2011
June 2010
June 2009
June 2008
June 2007
Sept. 2014
Commence Operation
June 2013
June 2014
80 tpy
40 tpy
25 tpy
15
• NEI = PME + CEI – CED where:– PME = Proposed modification emissions – CEI = Creditable emission increases– CED = creditable emission decreases
• For example, NEI = 80 + 25 - 40 = 65 tpy– 65 tpy > 40 tpy SO2 SER, project is a major modification
Applicability: 6. Sum all contemporaneous and creditable increases and decreases with the proposed modification
June 2012
Commence Construction
June 2011
June 2010
June 2009
June 2008
June 2007
June 2013
June 2014
40 tpy
80 tpy25 tpy
Sept. 2014
Commence Operation
16
• PTE less than thresholds• Source is
“grandfathered”• Source opted for
“synthetic minor” permit
Applicability: New or Modified Source not Subject to NA NSR
Potential to Emit (PTE)
Actual0
50
100
150
200
250
300
350
Synthetic Minor Source Emissions
Type of Emissions
Emiss
ions
(tpy
)
Major Source Threshold
17
• Main requirements:1. Install Lowest Achievable Emission Rate (LAER)
technologies2. Obtain emission offsets3. Perform alternative sites analysis4. Show statewide facility compliance w/air regulations5. Allow for opportunities for public involvement
• For Indian Country: same requirements as current NA Major NSR rules for areas lacking an implementation plan – 40 CFR Part 51, Appendix S
Application: NA NSR Permit Requirements
18Permitting Process Simplified
Start
Source not
subject toNSR
Source owner submits permit
application
Reviewing authority reviews:• Application
• Proposed/Required Control Technologies
• Compliance with other applicable requirements
Draft permit
developed
Final permitIssued
End
EPA issued permits may be appealed through EPA’s Environmental Appeals
Board (EAB). After EAB process, permits may be appealed in Federal Court.
APPL
ICAB
ILIT
YAP
PLIC
ATIO
NAP
PEAL
S
Are the source proposed emissions ≥
applicable thresholds or emission rates? (per
pollutant, may include fugitives)
Is the
permit for a new source or a
modification to an existing
source?
Is source in an area
that is attaining or nonattaining the
NAAQS?No
Yes
30 day comment
period
Public hearing
Usually appealed within
30 days of finalpermit decision
After appeal processends, permit is
finally approved orrevoked.
Is thesource
exempted?
19
• Rate that has been achieved or is achievable for a defined source
• Rate may be in a permit or regulation
• Requirement does not consider the following:– Economic– Energy– Environmental– Other factors
• RACT/BACT/LAER Clearinghouse– http://cfpub.epa.gov/rblc/index.cfm?action=Home.Home
Application: Lowest Achievable Emission Rate
20
• Emissions reductions from existing sources to balance emissions from proposed new or modified sources – Offset must be at least 1:1 (See Appendix)
• Emissions offsets reductions must be:– Quantifiable, Enforceable, Permanent and Surplus (QEPS)– From Actual Emissions – Real, No “paper” Reductions– Federally enforceable at the time of permit issuance – In effect before the new source can commence operation
Application: Emission Offsets
21
• We do not have the legal authority to waive the offset requirement under section 173 of the Act or under the Tribal Air Rule (TAR)
• Finalized EDZ offset waiver option for sources that satisfy qualifying criteria. Generally, tribes who develop TIPs and request EDZ designation
• We encourage states and tribes to work together in the creation and use of offset banks– E.g. Memorandums of Understanding (MOU)
• EPA can assist tribes interested in developing offset banks
Application: Emission Offsets (Cont.)
22
• Economic Development Zone (EDZ)– Zone targeted for economic development. – Usually participating communities demonstrate:
• pervasive poverty • high unemployment • general distress throughout the designated area
• Criteria for this waiver. Source emissions:– Consistent with the achievement of reasonable further progress – Will not interfere with attainment of the applicable NAAQS by the
attainment date
Application: Emission Offsets Waiver
23
• EPA addressing general lack of offset availability– e.g., Finalized rule that allows for the inter-pollutant and
inter-precursor trading of offsets between direct PM-2.5 emissions and its precursors (“Implementation of the New Source Review (NSR) Program for Particulate Matter Less Than 2.5 Micrometers” (73 FR 28340))
• We continue to explore non-traditional sources of offsets such as offsets from mobile sources and minor sources
Application: Emission Offsets (Cont.)
24
• An analysis by the source owner of:– Alternative sites– Sizes– Production processes– Environmental control techniques
• Analysis for such proposed source must demonstrate that benefits significantly outweigh:– the environmental impacts– social costs imposed as a result of source location, construction, or
modification
Application: Alternative Sites Analysis
25
• A certification by proposed source owner
• Must certify that all sources owned or operated by this source owner in the same state as the proposed source are:– In compliance or – On an approved schedule for compliance with all
applicable requirements
Application: Compliance Certification
26
• Reviewing authority is required to provide:– Public notice to the affected community and the general public on the
draft permit– At least a 30 day public comment period on the draft permit– Opportunity for public hearing on draft permit, if requested by public
• All public comments must be considered before a final permit is developed
• A Technical Support Document (TSD), generally including responses to comments, may also be available with the final permit
Application: Public Involvement
27Permitting Process Simplified
Start
Source not
subject toNSR
Source owner submits permit
application
Reviewing authority reviews:• Application
• Proposed/Required Control Technologies
• Compliance with other applicable requirements
Draft permit
developed
Final permitIssued
End
EPA issued permits may be appealed through EPA’s Environmental Appeals
Board (EAB). After EAB process, permits may be appealed in Federal Court.
APPL
ICAB
ILIT
YAP
PLIC
ATIO
NAP
PEAL
S
Are the source proposed emissions ≥
applicable thresholds or emission rates? (per
pollutant, may include fugitives)
Is the
permit for a new source or a
modification to an existing
source?
Is source in an area
that is attaining or nonattaining the
NAAQS?No
Yes
30 day comment
period
Public hearing
Usually appealed within
30 days of finalpermit decision
After appeal processends, permit is
finally approved orrevoked.
Is thesource
exempted?
28
• Provisions for permit appeals available under the program, same as Tribal Minor NSR program
• Appeals are conducted through the EPA’s Environmental Appeals Board (EAB)
• If all remedies for permit appeal through the EAB are exhausted, person may appeal to Federal Court
Appeals
29
• Program for major sources located in nonattainment areas (generally for emissions at or higher than 100 tpy)
• Pollutants regulated: NAAQS only
• Main requirement: Lowest Achievable Emission Rate (LAER)
• Permits are usually issued no later than 1 year after the date the permit application is deemed complete
Key Points to Remember: NA NSR
Appendix
28 PSD Source Categories
31
28 source categories
1. Coal cleaning plants (with thermal dryers) 15. Coke oven batteries
2. Kraft pulp mills 16. Sulfur recovery plants
3. Portland cement plants 17. Carbon black plants (furnace process)
4. Primary zinc smelters 18. Primary lead smelters
5. Iron and steel mills 19. Fuel conversion plants
6. Primary aluminum ore reduction plants 20. Sintering plants
7. Primary copper smelters 21. Secondary metal production plants
8. Municipal incinerators capable of charging more than 250 tons of refuse per day
22. Chemical process plants
9. Hydrofluoric acid plants 23. Petroleum storage and transfer units with a total storage capacity exceeding 300,000 barrels
10. Sulfuric acid plants 24. Taconite ore processing plants
11. Nitric acid plants 25. Glass fiber processing plants
12. Petroleum refineries 26. Charcoal production plants
13. Lime plants 27. Fossil fuel-fired steam electric plants of more than 250 million British thermal units (BTU)/hour heat input
14. Phosphate rock processing plants 28. Fossil-fuel boilers (or combination thereof) totaling more than 250 million BTU/ hour heat input
NA NSR Major Source Thresholds
32
Nonattainment Areas
Pollutant Nonattainment Classification Major Source Threshold Offset Ratio
Ozone Marginal (≥ 0.085 < 0.092 ppm)
100 tpy of VOC or NOx 1.1 to 1
Moderate (≥ 0.092 < 0.107 ppm) 100 tpy of VOC or NOx 1.15 to 1
Serious (≥ 0.107 < 0.120 ppm) 50 tpy of VOC or NOx 1.2 to 1
Severe (≥ 0.120 < 0.187 ppm) 25 tpy of VOC or NOx 1.3 to 1
Extreme (= 0.187 ppm and up) 10 tpy of VOC or NOx 1.5 to 1
Particulate Matter Moderate 100 tpy -
Serious 70 tpy -
Carbon Monoxide Moderate (9.1 – 16.4 ppm) 100 tpy -
Serious (16.5 ppm and up 50 tpy -
Sulfur Dioxide, Nitrogen Oxides,
and Lead
Only one nonattainment classification
100 tpy -
Significant Emission Rates (SERs)
33
Pollutant SER (tpy) Pollutant SER (tpy)Carbon Monoxide 100 Sulfuric Acid Mist 7
Nitrogen Oxides 40 Hydrogen Sulfide (H2S) 10
Sulfur Dioxide 40 Total Reduced Sulfur (Includes H2S) 10
Particulate Matter (PM10) 15 Reduced Sulfur Compounds (Includes H2S) 10
Particulate Matter (PM2.5) 10; 40 for VOCs, NOx or SO2
Municipal Waste Combustor Organics 3.5*10-6
Ozone 40 VOCs or NOx Municipal Waste Combustor Metals 15
Lead 0.6 Municipal Waste Combustor for Acid Gases
40
Fluorides 3 Municipal Solid Waste Landfills Emissions 50
SER – a rate of emissions that would equal or exceed any of the following rates:
Notwithstanding the above, any emissions rate or any net emissions increase associated with a major stationary source or major modification, which could construct within 10 km of a Class I area, and have an
impact on such area equal to or greater than 1 g/m3 (24-hour average)