part i – the schedule section c – statement of...

32
PART I – THE SCHEDULE SECTION C – STATEMENT OF WORK SECTION C – STATEMENT OF WORK Dated 9/29/14 Page 1 of 32

Upload: dangkhanh

Post on 13-Apr-2018

216 views

Category:

Documents


4 download

TRANSCRIPT

PART I – THE SCHEDULE SECTION C – STATEMENT OF WORK

SECTION C – STATEMENT OF WORK

Dated 9/29/14

Page 1 of 32

PART I – THE SCHEDULE SECTION C – STATEMENT OF WORK

TABLE OF CONTENTS

ARTICLE DESCRIPTION PAGE PREFACE………………………………………………………………………………………… ..3

1.0 DESCRIPTION OF WORK – GENERAL .............................................................................. 4

2.0 SPECIFICATIONS, DRAWINGS, ATTACHMENTS, AND EXHIBITS ................................. 4

3.0 DESCRIPTION OF WORK – SPECIFIC ............................................................................... 7

4.0 MATERIAL, EQUIPMENT, OR SERVICES FURNISHED BY COMPANY ........................ 15

5.0 TEMPORARY FACILITIES AND UTILITIES ...................................................................... 16

6.0 PERFORMANCE SCHEDULE AND SEQUENCE OF WORK ......................................... 234

7.0 REPORTING REQUIREMENTS AND COORDINATION MEETINGS ............................... 26

8.0 CORRESPONDENCE, SUBMITTALS AND COMMUNICATION REQUIREMENTS ........ 27

9.0 CONTRACT MODIFICATIONS........................................................................................... 28

10.0 CLEAN-UP, SAFETY, WORK RULES, AND REGULATIONS .......................................... 28

11.0 WASTE MANAGEMENT…………………………………………………………………..……29

12.0 SECURITY ........................................................................................................................... 30

13.0 QUALITY ASSURANCE ..................................................................................................... 31

14.0 FINAL ACCEPTANCE……………………………………..…………………………………….301

MILESTONE SCHEDULE……………………………………………………..…………………32

ACRONYMS……………………………………………………………………………..…….…..33

PREFACE:

The Portsmouth Gaseous Diffusion Plant is a DOE owned facility located near Piketon, Ohio. The DOE Portsmouth Plant (PORTS) was previously engaged in uranium enrichment for defense purposes but was deactivated in 1981 and is currently undergoing Decontamination and Decommissioning (D&D) and site revitalization. To support air powered equipment and environmental building controls, the X-670 air plant and X-670A cooling tower were constructed to supply compressed air and cooled water to several buildings on the PORTS site. In recent years, the X-670 air plant and the X-670A cooling tower have developed leaks due to oxidation and general buildup of internal sludge and cooling media contamination that must be repaired and revitalized to provide future dependable service.

Page 2 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

The purpose of this project is to repair and upgrade the X-670A cooling tower, the X-670 Air Plant and the X-670 recirculation pipe system to provide compressed air and cooled water for internal equipment and dependent buildings. With the X-670A cooling tower and X-670 air plant returned to service, FBP will continue D&D of existing buildings and begin the demolition of the X-626 cooling tower with associated cooled water pump equipment.

1.0 DESCRIPTION OF WORK – GENERAL

The Contractor shall supply all adequate and competent labor, supervision, tools, equipment, consumable materials, services, testing devices, warehousing and each and every item of expense necessary for the design, engineering, supply, fabrication, field erection, application, handling, hauling, unloading and receiving, installation, construction, demolition, sampling collection assembly, evaluation, and quality assurance for the complete renovation and replacement of the X-670 Dry Air Plant and X-670A Cooling Tower including:

● Remove and replace five (5) cooling tower cells with two (2) coils per cell; ten (10) coils total

● X-670 and X-670A RCW system flushing, cleaning and refilling

● Reconnection of all X-670 Dry Air Plant system components including:

♦ X-670 Recirculating Cooling Water (RCW) system piping

♦ Compressors #1 through #3 (and associated components)

♦ X-670 Chiller

♦ X-670 Equalization tank

• Installation of a new Compressor (compressor #4) and all corresponding piping and components

• Design, furnish and install of a new skid mounted filtration system for the RCW

• Disposal of all liquid and solid waste generated from RCW system flushing and cleaning

● System startup shakedown and validation testing

These structures and facilities outlined above are designated as the X-670 Complex in the remainder of this document.

2.0 SPECIFICATIONS, DRAWINGS, ATTACHMENTS, AND EXHIBITS

All work shall be performed in strict accordance with the following specifications, drawings and accompanying documents. Any proposed modifications requested by the Contractor shall be submitted for approval/concurrence in accordance with Attachments J-6 and J-8.

The Contractor shall notify the Company in writing of any conflict between these specifications and Federal or State guidelines.

Page 3 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

2.1 Specifications

Specification No. Rev. Title

FBP-CSPEC-02200 2 Excavation and backfilling

FBP-CSPEC-03300 2 Reinforced concrete

FBP-SCPEC-05100 2 Structural Steel

FBP-CSPEC-09900 0 Field and Finish Painting

FBP-CSPEC-17100 1 Piping

FBP-CSPEC-17110S106 0 Process Water (RCW)

FBP-CSEPC-17110S128 0 Stainless steel compressor intake

FBP-CSPEC-17110S136 0 Instrumentation piping

FBP-CSPEC-17110S136 0 Plant air

FBP-CSPE-16100 6 Electrical-Basic Materials and Methods

2.2 Drawings

Drawing No. Rev. Title

X-670-6506-E A01 X-670 Dry Air Plant Electrical One-Line Diagram

X-670-6507-E B01 X-670 Dry Air Plant Electrical. Panel Board Schedules

X-670-6508-E A01 X-670 Dry Air Plant Electrical MCC Schedules and Diagrams

X-670-6509-E A01 X-670 Dry Air Plant Electrical. 120 V Power Plan

X-670-6510-E A01 X-670 Dry Air Plant Electrical 2400 & 480 V Power Plan

X-670-6511-E A01 X-670 Dry Air Plant Electrical Cable Tray Plan

X-670-6523-E A X-670 Dry Air Plant Electrical Eaton 2.4 KV MVC and Transformers

Page 4 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

Drawing No. Rev. Title

X-670-6524-E A X-670 Dry Air Plant Air Compressor #4 Electrical Schematic

X-670-6525-E A X-670 Dry Air Plant Air Compressor #4 Electrical Interconnection Diagram

X-670-1-C1 A01 X-670 Dry Air Plant Control System Architecture

X-670-10-C1 A01 X-670 Dry Plant PLC Discrete Input Module 2 Schematic

X-670-11-C1 A01 X-670 Dry Air Plant PLC Communication Panel Instrument Mounting Details & Schedules

X-670-2-M A02 X-670 Dry Air Plant Mechanical – Compressed Air System Process & Instrumentation Diagram

X-670-3-M A02 X-670 Dry Air Plant Mechanical – Coolant Process & Instrumentation Diagram

X-670-5-M A02 X-670 Dry Air Plant Mechanical Lower Floor Plan

X-670-6-M A02 X-670 Dry Air Plant Mechanical – Upper Floor Plan Compressed Air and Nitrogen Piping

X-670-6-M A02 X-670 Dry Air Plant Outdoor Chiller Plan and Section

X-670-14-M A02 X-670 Dry Air Plant Mechanical Details

X-670-15-M A03 X-670 Dry Air Plant Mechanical Valve Schedule Sheet 1 of 2

X-670-16-M A03 X-670 Dry Air Plant Mechanical Valve Schedule Sheet 2 of 2

X-670A-2-M A02 X-670A Outdoor Cooling Tower Piping Plan

X-670A-3-M A03 X-670A Outdoor Cooling Tower Sections

X-670-7-S A02 X-670 Dry Air Plant Pipe Support Sections

SK-E4553-1-M 1 RCW Pipe Plan Partial 1 of 2

SK-E4553-2-M 0 RCW Pipe Plan Partial 2 of 2

X-670-12-M A01 X-670 Dry Air Plant Outdoor Chiller Plan and Section

Page 5 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

2.3 Attachments

For attachments refer to Section J.

2.4 Exhibits

Exhibit No. Title

Exhibit 1 Milestone Schedule

Exhibit 2 Acronyms

Exhibit 3 Security Protocol for the X-670, X-670A, Cooling Tower Coil Replacement Project

Exhibit 4 Independent Assessment of the Premature Failure of the X-670A Cooling Tower Coils (For reference only)

Exhibit 5 Site Prepared Flushing Plan (For reference only)

2.5 References

The attached information is provided for reference in preparing your bid. Your consideration of this information is not intended, nor does it limit, the Contractor’s responsibility to verify and ascertain the conditions in accordance with clause H.69. This information, sketches, exhibits, drawings and the site visits shall be used to quantify and determine the conditions at the project site.

3.0 DESCRIPTION OF WORK – SPECIFIC

The Work for the X-670 Complex described in Articles 1.0 and 2.0 of this Statement of Work shall include, but not be limited to, the following:

3.1 Key Activities:

The Contractor shall remove, size-reduce and load cooling tower coil debris into Company furnished waste containers. The Contractor will shall pre-test and install company furnished replacement coils, supply and return piping, clean and passivate new cooling tower coils and associated pipe components.

The Contractor will shall perform site preparation, flushing and system piping modifications, including temporary bypasses, drain and flush the pipe system, perform mechanical system cleaning, RCW flush media sampling and off-site disposal of all flushing waste. The Contractor shall clean and perform mechanical upgrades to the Equalization Tank. The Contractor shall perform dispersant flush and passivation treatment to the entire X-670 RCW

Page 6 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

pipe system. The Contractor shall perform confirmation sampling to verify that the piping is clean. The Contractor shall then remove temporary bypass piping, restore the original piping configuration and add full strength inhibited propylene glycol to make up 40% glycol/water solution.

With the final glycol solution in place and the X-670 and cooling system verified to be leak free, the Contractor shall reconnect and startup existing compressors #1 through #3, reestablish instrumentation and monitoring systems and demonstrate satisfactory operation of the refurbished X-670 Dry Air Plant facility operation.

The Contractor shall install, connect and startup new Compressor #4; including leveling, anchoring, inlet and outlet pipes, installation of filter assembly, blow off system, furnish and install all valves, supports and perform connections to newly refurbished RCW chilled and cooled water systems, electrical connections and instrumentation

The Contractor shall provide a self-contained filtration skid with the following components/materials:

• 250 gallon per minute (gpm), design flowrate • 0.5 micron cartridge filtration • 304 stainless steel cartridge housing with drain valve(s) and dedicated isolation

valves • Diversion line around cartridge housing with valve • 3” flanged skid connections with isolation valves • Vertical Inline 480 volt/3 phase pump with isolation valves and skid mounted

electrical disconnect • Schedule 80 polyvinyl chloride (PVC) piping/valves/components • Differential pressure gauges across inlet/outlet of filter housing • Maximum skid footprint of 6-ft. x 6-ft.

Note: Filtration skid connection drawings (electrical and mechanical) to the existing system will be provided at a later date. Filtration skid connection to the existing system shall be performed by the Contractor.

The Contractor shall perform complete cooling system start-up, work area restoration, and demobilization from the X-670 Complex

3.2 Flushing Plan

The Contractor shall develop an independent flushing plan, which will recirculate, drain and dispose existing contents, flush the RCW system, mechanically scour the internal components of the system (through ice pigging, mechanical pigging, or any other technically sound method of internal system cleaning), system passivation, drain and cleansing flush of the system, with final sampling confirmation of RCW System acceptance for the X-670 Complex.

Page 7 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

3.3 Facility Descriptions

X-670 Dry Air Plant The X-670 Dry Air Plant is a building constructed on a concrete slab with sheet metal walls on a steel frame. The X-670 Dry Air Plant includes four RCW pumps (#1 through #4), air compressors, Equalization Tank, portable filter skid, chiller and the control room, X-670A Cooling Towers The X-670A Cooling Tower, located east of X-670 building, and consists of five (5) cells, with two (2) coils in each cell (10 total coils), with 12-inch supply and return manifolds on both the east and west sides. Equalization Tank (EQ Tank) The equalization tank is located inside the X-670 building on the North wall of the structure. The tank is a 16,000 gallon fiberglass tank with 20” access man way. X-670 Compressor #1, #2, #3 and #4 The X-670 Dry Air Plant currently has three (3) existing functional compressors. A fourth 4th compressor will be provided by the Company and shall be installed by the Contractor. X-670 Chiller The X-670 Chiller is located outside the X-670 Dry Air Plant near the southwest corner of the X-670 building. X-670 RCW System The piping system that connects the X-670A Cooling Tower to the X-670; EQ tank, pumps, compressors, chiller, and the X-710 building and the X-300 building HVAC chillers; which are cooled by water from the X-670.

3.4 X-670 Complex Condition When Transitioned to the Contractor

The X-670 Complex will be segregated from the Portsmouth Gaseous Diffusion Plant (PORTS) Limited Area (LA) by a temporary security fence. This temporary fence will create a temporary General Access Area (GAA). The temporary GAA will be equipped with access control gates to allow for un-escorted personnel entry. Special Work inside the PORTS Limited Area will require pre-scheduling escorts oversight and controls supplied by the Company Exhibit 4 (Security Protocol for the X-670, X-670A and the X-690 Cooling Tower Coil Replacement Project) provides specific security protocol requirements. (Ref: Security Protocol, Exhibit 4). The X-670A cooling tower is comprised of five (5) cooling cells containing two (2) coils each (total of 10 coils). Each coil is connected to supply and return manifolds running along the east and west side of the cooling tower. The cooling tower coils have developed leaks and must be removed and replaced. The cooling tower is currently filled with glycol/water solution that must be removed before any bypass piping can be installed. The RCW distribution piping system is an above-ground, welded steel pipe system. The system is comprised of approximately 7,800 feet of 6” through 18” diameter pipe on structural supports that transfers recirculated chilled water between the X-670 Dry Air Plant and two remote buildings using recirculated chilled water as a cooling media. The RCW pipe system is known to contain a large quantity of ferric sludge and solid particulates that must be mechanically scoured and flushed to provide satisfactory transmission of recirculated chilled water between the X-670 and remote building chiller units.

Page 8 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

1. An estimation of the pounds of iron sludge (rust) in the X-670 equalization tank and glycol distribution system from the attached waste management analysis of the glycol cooling water system. The calculations were based on:

1. Approximate iron concentration = 300 mg/L as Fe = 828 mg/L as Fe2O3

2. Volume of Equalization tank = 12,000 gallons = 0.012 MG (million gallons)

3. Volume of glycol cooling water distribution system = 60,000 gallons = 0.060 MG (million gallons)

2. Pounds of dry Fe2O3 in the Equalization Tank:

Based on a concentration of 828 mg/L Fe2O3 and EQ tank volume, the Equalization Tank would contain approximately 110 dry pounds of Fe2O3.

3. Pounds of dry Fe2O3 in the remainder of the glycol distribution system:

Based on a concentration of 828 mg/L Fe2O3 and pipe volume, the glycol distribution pipe system would contain approximately 415 dry pounds of Fe2O3.

The X-670 Air Plant has three (#1, #2, #3) recently refurbished compressor’s with associated piping, valves, inlet and outlet piping and components. All three compressors are currently disconnected from the RCW cooling system loop due to internal cooling system ferric sludge contamination. The existing compressors, after coolers and air dryers cannot be reconnected to the RCW system until the system has cleaned/flushed and the RCW cooling loop water quality has been verified. The X-670 Chiller is currently disconnected from the RCW cooling loop due to internal cooling system ferric sludge contamination. Inlet and outlet piping is in place and must be cleaned/flushed before the X-670 Chilled can be reconnected to the RCW system. The X-670 EQ Tank is a 16,000 gallon fiberglass tank that is partially filled with glycol solution. The EQ Tank has an accumulation of solids/sludge in the invert that must be removed before final system cleaning/flushing can begin. The X-670 Building will be fully powered and will require LOTO permits and electrical isolations prior to working on energized systems

3.5 X-670 Complex Final Condition

X-670 Cooling Tower New coils (10) shall be installed, cleaned and internally passivated. The cooling towers shall be tied back into the RCW piping system, leak tested and approved for startup.

Page 9 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

X-670 RCW Pipe Distribution System Piping

The RCW pipe system, including fittings, drains and valves shall be thoroughly cleaned of all internal contaminants and ready to transmit acceptable quality chilled water to meet the needs of dependent facilities. All new fittings, valves, blind flanges will shall be inspected, verified to be leak free. All fittings, flanges hangers and supports shall be painted and secured. All new valves shall be identified per Specification Section 09900. To declare success of the RCW pipe distribution system cleaning, the Contractor shall attain the X-670 RCW water cleanliness level of:

Parameter Concentration (in-situ) Requirement CaCO3 50 PPM <100 PPM pH 8.4 6.0-8.5 LSI 0.0 +0.5 to +1.0 Suspended Solids <2.0 PPM < 1 micron and 50 PPM Fe2O3 < 10,000 PPM during flushing

The Contractor shall recirculate clean water through the RCW pipe system at 3000 GPM (2 pumps) for a minimum of twenty four (24) hours taking independent samples at eight hour increments to demonstrate that the system is acceptably clean throughout and to allow reconnection of critical equipment to the system.

X-670 Dry Air Plant All three existing X-670 compressors and the X-670 chiller shall have the bypass piping removed and tied back into the X-670 RCW System. Compressors #1 through #3 will restarted and be fully operational with all instrumentation, insulation painting/markings and controls. X-670 new compressor #4, including after cooler #4, receiver tank #4, intake filter #4, all associated piping, supports, hangers and accessories shall be installed in its final location, tied into the system, and successfully started up. Compressor #4 is intended as backup and will remain in standby mode following successful startup and commissioning. X-670 Chiller Once the system has been determined clean, by-pass piping shall be removed and the chiller shall be re-connected to the X-670 RCW system.

Equalization Tank The EQ Tank shall be cleaned of all sludge and contaminants. The Contract Technical Representative (CTR) will inspect and approve all modifications to the tank interior, including outlet and overflow screens, new EQ tank filter return valve and fittings and installation of Hexi-Cover floaters (material furnished by the Company). The EQ Tank access hatchway cover shall be reinstalled and leak tested before heated cleaning and passivation flushing.

3.6 Specific Scope of Work

3.6.1 Contractor may mobilize to the Construction Zone once they have received an “A” or “B” status on all required pre-mobilization submittals and Authorization to Mobilization (ATM) has been given.

3.6.2 Prior to the start of work, the Company will coordinate the Alignment/Kickoff Conference and walk-through with the Contractor to conduct a field survey of the

Page 10 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

isolated / air gapped utilities and to verify that all utilities (e.g., electric, water, and/or air services lines, etc., are physically air gapped, capped and/or controlled (as-needed for the scope of the work), per the LOTO.

3.6.3 Contractor shall coordinate all mobilization activities with the CTR listed in section G.3.

3.6.4 Contractor shall install erosion and sediment control measures per the Environmental Protection section of this Statement of Work and Exhibit 5. Contractor shall maintain erosion and sediment control measures throughout the duration of the project.

3.6.5 Contractor shall coordinate with the CTR to establish the field office location, break area, smoke area, restroom facilities, lay down area, staging area, container queuing area, weight scale location and other temporary facilities. Refer to Exhibit-3 for general location for Contractor temporary facilities. Changes to the approved contractor’s temporary facilities area must be approved by the CTR prior to making the change.

3.6.6 Contractor shall establish a waste container staging area as indicated on Exhibit 3. The Contractor shall provide physical boundaries and signage for the waste container staging area(s). The staging area shall be used as a temporary storage area for full debris/waste containers awaiting weighing, testing and labeling.

The Contractor shall strategically place temporary liquid waste storage containers to maximize flushing rates, provide safe access/egress to containers for draining and prevent disruption of plant traffic flow.

3.6.7 Contractor shall establish and erect boundaries around work areas to delineate Construction Zones and prevent unauthorized entry. All temporary boundaries will be approved by the CTR before installation.

Contractor shall provide and install safety / warning signs, such as requirements for personal protective equipment (PPE) and “Danger Construction in Progress”.

3.6.9 Contractor shall install the Company furnished project sign at a location directed by the CTR.

3.6.10 Before beginning any construction work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The Contractor shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or construction work performed under this contract. The Contractor shall be responsible for any engineering or design required for temporary bracing, shoring or modifications to the existing facilities in support of removing/installing coils, new piping equipment and other associated components shall be the responsibility of the Contractor. The Contractor shall submit a written Modification Plan to the Company and shall not proceed with such modifications without the approval of the Company.

Page 11 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

3.6.11 The Contractor shall drain the X-670A cooling tower of existing liquid glycol/water

solution and dispose of off-site.

The Contractor shall install temporary cooling tower manifold bypasses and flange isolations for cooling tower coil supply and return pipes.

The Contractor shall remove all 10 cooling tower coils, size reduce and load coil debris into company furnished containers for subsequent disposal off site

The Contractor shall install 10 new cooling tower coils,

The Contractor shall reconnect cooling tower supply and return pipes, remove temporary cooling tower manifold bypasses, clean and passivate new cooling tower coils after the RCW pipe system cleaning is complete.

3.6.12 The Contractor shall install temporary bypasses at each existing compressor, each existing after cooler, the X-670 chiller, and each existing air dryer.

The Contractor shall perform a systematic program of flushing, scouring, pigging, cleaning and passivation of the RCW distribution pipe system and internal X-670 equipment cooling loop. All waste and flushing discharge shall be collected by the Contractor, tested, characterized and disposed of off-site.

Flushing/cleaning shall be phased as necessary to handle the volumes of liquid sanitary waste. The Company and the Contractor shall perform monitoring to confirm the waste to be sanitary prior to turning over the waste to the Contractor for offsite disposition.

3.6.13 Following the RCW system cleanliness approval, the Contractor shall reconnect the X-670A cooling tower and X-670 Air Plant equipment:

• Remove temporary bypasses and reconnect compressors #1, #2 and #3 and after coolers #1, #2 and #3 to the RCW cooling loop.

• Remove the temporary bypass and reconnect X-670 Chiller to the RCW cooling loop.

• Temporary bypasses to Air Dryers #1 through #3 will remain in place after cleaning completion due to internal leaks in the Compressors #1 through #3 air dryer after coolers.

• Perform startup and system validation of compressors #1, #2 and #3.

3.6.14 After compressors #1, #2 and #3 are fully operational, the Contractor shall install and connect standby compressor #4 to the X-670 Air Plant, perform startup equipment shakedown and validation testing.

3.6.15 Asbestos Abatement: RESERVED: There is no known Asbestos within the scope of work.

Page 12 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

3.6.16 Radiological Contamination

If radiological contamination is discovered, the Contractor shall STOP WORK and notify the CTR before proceeding with any work involving radiological contaminated or suspected radiologically contaminated materials.

3.7 Contractor Work Plan:

3.7.1 The Contractor shall submit a Detailed Work Plan for each task to be performed. The plan can be one work plan with sections on each task or a series of work plans. The Contractor shall follow the format specified in Attachment J-25. The Contractor’s Detailed Work Plan(s) will be reviewed by the FBP High Hazard Work Review Board as part of the submittal review process. The Contractor should be prepared to address their approach to safety management for high hazard work. Required attendees include the Contractor’s HSE representative and field supervisor who shall present the Contractor’s approach managing high hazard work. High hazard work activities include:

• Electrical work – greater than 50 volts • Excavation and penetrations • Elevated work – over 4 feet from the base working surface • Hoisting and rigging • Work in confined space • Radiological and chemical (Radiation work requiring an ALARA review and

chemical for high concentration acids, caustics (>10%))

3.7.2 The Contractor shall submit for approval a detailed Work Plan including but not limited to the following:

A. The Contractors’ Flushing sequence, system draining, refilling, waste water

staging and disposal and piping system modifications. Waste disposal facilities will be vetted by the Company prior to use.

B. Spill prevention methods during flushing activities to prevent the potential spread of contamination

C. Methods to control fugitive dust emissions during construction/ coil removal activities.

D. Provisions to protect adjacent structures, equipment, material, underground and above ground utilities from damage, including protection from projectiles

E. Methods to be used to remove leaking coils from the existing tower and installing new coils.

F. Size reduction methods for removed coil debris G. Methods to install and maintain by-pass piping during flushing activities to

prevent damage to equipment and the environment. H. Methods to be used to mechanically scourer the inside of the piping to be

flushed and cleaned. I. Methods to be used (confined space) to work inside the equalization tank to

clean, install screens and install Hexi-cover floating modules). J. Contractor’s plans for removal of by-pass piping and re-connection of

compressors, chiller and cooling towers to the RCW system once system cleanliness has been accepted.

K. Methods for refilling the system and adding inhibited propylene glycol after final cleanliness acceptance of RVW pipe system

Page 13 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

L. Methods for mechanical and electrical connection of Compressor #4 and

installation of associated piping, supports, receiver tank pad, and components in the X-670 Facility (including Company supplied MCC Bucket and Flexible Containment Berm around compressor #4 concrete base pad) after the X-670 RCW has been started back up and Compressors #1-3 are in full operation

3.8 Pay Item Descriptions

The Pay Item Descriptions as defined in Section B.2 show activities for which the Contractor shall report progress and use for invoicing.

3.8.1 Contractor shall submit a value for each pay item (refer to Section B – Supplies or Services and Prices/Costs for Pay Item Schedule of Values). The value shall correspond to the descriptions of the activities including profit, overhead, insurance, training and submittal documents not specifically listed as a pay item shall be allocated to each pay item proportional to its value. The Company will review each pay item value to ensure that the value is consistent with the work to be performed. Pay item values determined by the Company to be unacceptable shall be revised and resubmitted by the Contractor. Payments shall not be made to the Contractor until the Company approves the pay item values.

4.0 MATERIAL, EQUIPMENT, OR SERVICES FURNISHED BY COMPANY

4.1 Services:

Survey Monuments and Survey Control monuments and/or bench marks for laying out the Work are established on-site.

4.2 Materials and Equipment

Contractor shall provide all necessary resources to receive, stage and store Company supplied materials in accordance with the instructions provided in the contract. The Company will furnish or cause to be furnished to Contractor, without cost to Contractor, the following items for, or in connection with performance of the Work:

1. Hexa-covers for EQ Tank air/glycol separation

Floating 8” diameter floating modules, MODEL R-90

2. Receiver tank and components (pressure gauges, drain valve, pressure relief valve) for compressor #4

MAX FUSION, INC. Model #302450

3. Compressor #4 including base with oil coolers, motor, intake filter, clow off silencer.

CENTAC 2CV35M3 with TURBOLOGX Constant Pressure Control, Surge and Machine Protection.

4. Motor Starter (bucket) for compressor #4

CONTROL, MV MOTOR, EATON AMPGARD, 2500V/1200A/800 HP

Page 14 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

5. After Cooler for compressor #4

ADDAMS SFC IBC Model #SAF-472-NS

6. Cyclone Separator for after cooler #4

R.P. Adams Model 10” CYS-NS

7. 5 sets of 2 replacement cooling coils

Marley HDG COIL MHF07-STD-SERP-12-PASS-72DA

4.3 Permits

Notwithstanding the Article entitled the "Permits, Applications and Licenses" in Section H Special Contract Requirements, Company will furnish the permits listed in Article 5.

4.4 Inspection

Inspection of the Work required by Governmental agencies shall be arranged by Company. Contractor shall request such inspection through Company only after the work is ready for inspection.

4.5 Communication

The Company will provide Plant radios as required

4.6 Respirators

The Company will provide respirators if required.

5.0 TEMPORARY FACILITIES AND UTILITIES

5.1 Furnished by Company

Company will supply or cause to be supplied the following temporary facilities and utilities to Contractor, without cost to Contractor, for or in connection with performance of the Work:

A. Parking areas for the Contractor's Work vehicles will be limited to a location near the Work area as shown on Exhibit 3. Parking along plant site roads and streets shall not be permitted. Unless otherwise permitted by the CTR, parking for the Contractor and subcontractor employees' shall be limited to the parking lot outside the security fence parking facilities.

B. Water, (for work only, non-drinking water) will be provided by the Company. The Company will provide and install a backflow preventer for use by the Contractor to connect water piping or hoses. Connections to and disconnections from backflow preventer shall be by the Contractor. The Company will not provide potable water.

C. Limited roughly graded space adjacent to the construction site for temporary facilities and storage of material and equipment. Refer to Exhibit-3 for location of available areas. (No storage facilities or protective coverings of any kind will be furnished by Company.)

Page 15 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

D. Site perimeter security fencing and access gates.

5.2 Furnished by Contractor

Except as expressly set forth in Article 5.1 of this Statement of Work, the supply, installation, provision, maintenance, repair, and final removal of all temporary facilities and utilities, necessary for full and complete performance of the Work, is the sole responsibility of the Contractor. Such items shall include, but not necessarily be limited to those listed below. Contractor has the sole responsibility to identify and provide all required temporary facilities and utilities to perform the Work. The type of facilities, move-in and move-out dates, and locations on the work Site shall be subject to and in accordance with the review and approval of CTR.

A. Temporary Facilities and Lay-down Area

1. Contractor trailers must be secured or anchored to prevent movement or turnover from high winds. Trailer anchoring shall meet OBBC & DOE-STD-1088-95. Preferred Anchor system is a Minuteman LLBS system with drive pins as determined in length per project condition. Contractor may choose to anchor the trailer by using 10 foot long Jersey Barriers with ½” galvanized wire rope tie downs in accordance with the spacing table 1 in 24 CFR 3285.402. Electrical connections must be made by a qualified electrician. The Company reserves the right to inspect and approve the Contractor’s office installation, through review and approval by the CTR.

2. Power for connection of the Contractor’s Project Trailer shall be provided by the Contractor’s portable generator

3. Maintenance of Contractor's lay down, storage and work areas and roads within such areas are the Contractor’s responsibility (Refer to Exhibits 3).

4. Upon demobilization, the land previously occupied by Contractor's Temporary Facilities and Lay-down area shall be returned to its pre-construction condition or better. This requirement shall also apply to all Temporary Roads, and Parking, Lay-down areas and Temporary Utilities. ODOT #304 gravel shall be used as fill where needed.

5. The Company will provide all waste containers for solid debris as outlined in the Waste Management section of this Statement of Work.

6. Smoking Areas:

Contractor personnel will only be permitted to smoke at designated smoking areas as directed by the CTR.

B. Eating Facilities

It is the Contractor’s sole responsibility to provide break and lunch areas for their employees, vendors and subcontractors (Attachment J-13).

Page 16 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

C. Sanitary and Change Facilities

The Contractor shall supply Sanitary and Change Facilities required for the project. Contractor shall coordinate with the CTR for the location of Sanitary and Change Facilities (Attachment J-13).

D. Storage Compounds

The Contractor shall provide adequate weather-tight storage for storage of materials, tools, and equipment which are subject to damage by weather. The location of storage compounds must be agreed with CTR before storage of materials commences. Such compounds shall be maintained for the storage of the approved materials and for no other purpose.

E. Construction Power/ Temporary Facility Area Power

1. Contractor shall provide temporary power (generator) to provide electric for temporary facilities, temporary lighting, tools and equipment to perform the work. Electrical connections to Contractor trailers, temporary facilities or other electrical systems or equipment must be completed in accordance with the requirements of Attachment J-13. Contractor shall not be permitted to occupy trailers or temporary facilities prior to inspection and approval by the Company. The Contractor shall provide temporary lighting or task lighting to perform the work.

2. Contractor shall be responsible for maintaining and removing any equipment or devices installed.

3. Before the Contractor plugs in any electrical appliance to any plug socket, it shall ensure that the appliance is in good condition and is fitted with a suitable cable, including fully rated and insulated neutral conductor and protective ground conductor.

F. Water

1. The water supply source furnished by the Company shall be used only in connection with work performed under this contract (refer to Article 5.1 of this Statement of Work).

2. The Contractor shall furnish, install, remove and dispose of all necessary piping, fitting, connections, hoses, equipment, systems or storage facilities required to route water from a provided tie-in location to the Work area. Contractor shall distribute and convey water in an efficient and orderly way. Leaks and waste shall be minimized and care shall be exercised to eliminate the buildup and dispersal of mud resulting from leaks, spills, and truck loading operations.

3. Locations of temporary piping shall be subject to review and approval by the CTR. Any permits/permission required will be coordinated by the CTR. If water is not available or not suitable to the Contractor, then the Contractor shall be solely responsible for providing an alternate water source as approved by the CTR. Contractor shall provide all necessary fittings, connections and equipment to provide a complete water system

Page 17 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

G. Water Disposal and De-watering

1. Contractor shall be responsible for the safe and proper disposal of water into either local drainage systems or, where these are either not available or water has become contaminated or not allowable for local discharge, to approved offsite disposal locations approved by CTR.

2. Contractor shall be responsible for dewatering of any excavations or construction areas. It may not be discharged to the sanitary sewer or storm sewer systems.

3. Water used during flushing shall be disposed of at an offsite disposal facility approved and vetted by FBP. The Contractor shall provide the following information for the proposed facility that will be used for treating and/or disposal of waste generated at the Ports site:

1. Name and physical address of the receiving facility.

2. US EPA RCRA Identification #

3. NPDES Permit #

4. CAA Permit #(s)

5. CERCLA Off-site Rule Approval issued by US EPA

6. Documentation of Notices of Violation, Enforcement Action, and/or Compliance Schedules issued by US EPA and/or state agencies. Resolution of the violation/issue if available should also be provided.

7. Reasons for not approving/accepting a treatment and/or disposal facility:

• Regulators determine the facility consistently fails to meet expectations.

• Facility is under enforcement by EPA or state regulatory agency.

• Facility has history of NOVs associated with specific processes that will be utilized for the management of FBP waste/recyclables.

• Facility has received an NOV and has yet to return to compliance for a period longer than 2 months, if even not related to processes that will be utilized for the management of FBP waste/recyclables.

• The facility has a history of significant spills or releases that will require remediation.

• There are significant deviations from regulations, compliance order provisions, or permit conditions that fail to prevent releases of hazardous wastes, materials, or substances into the environment.

Page 18 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

H. Temporary Buildings

Contractor shall provide, operate, maintain, and dispose of all temporary buildings in accordance with the requirements of the Contract.

I. Fuels and Lubricants

1. Oils, greases, and similar materials must be stored in nonflammable bins or buildings or in a fenced compound remote from other combustible materials in accordance with NFPA and as approved by CTR.

2. "No smoking": signs shall be provided by Contractor and prominently displayed in areas where flammable materials are stored. Additionally, Contractor shall provide and maintain suitable fire extinguisher in such areas.

3. Contractor shall provide all fuel for heating and ventilation for their Temporary Facilities.

4. Fossil Fueled Vehicle Limitations in Buildings: This limitation is applicable to, but not limited to, automobiles, trucks, tractors, forklifts, high-lifts, other cylinder handling equipment, and personnel carriers. Fossil fuels include, but are not limited to gasoline, diesel, or ethanol. The size of a fuel tank on each individual fossil fueled vehicle is limited to 50 gallons of fossil fuel. The use of propane for vehicle fuel is prohibited.

5. Stationary fuel powered equipment (e.g. generators, pumps, light plants, etc.) with a fuel holding capacity equal to or greater than 55 gallons of fuel must be equipped with a double walled fuel tank. If a double wall fuel tank is not available then the stationary fuel powered equipment must be placed in an acceptable secondary containment device as approved by HSE and the CTR. If an existing secondary containment area is not available, then it is the Contractor’s sole responsibility to provide an acceptable secondary containment device. The secondary containment device must be sized to hold the equivalent of the largest tank volume within that containment.

6. For equipment requiring secondary containment that will be stored outdoors, the containment area must provide for accumulated precipitation, and as such, be sized to 120% of the largest tank volume within that containment. The secondary containment’s material(s) of construction shall be impervious to and compatible with, the liquid to be contained. Any spills within the dike or outside the dike shall be reported immediately to the CTR. Provisions shall be made for draining off accumulations of water.

7. The Contractor shall ensure that any drain valves remain closed except when draining. The stationary fuel powered equipment and all secondary containment areas must be inspected and maintained daily. The Contractor shall ensure documentation of these inspections is recorded daily, and that the inspection log is available for the Company for inspection upon request. Temporary Electric Generators greater than 25kW will require grounding per OSHA 29 CFR 1926 (F)(3)(i).

Page 19 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

J. Communication

Contractor shall provide and operate all means of communication required for performance of the work, including but not limited to telephones, facsimiles, and computer equipment. Wireless communication systems shall be approved by the CTR prior to bringing the system on-site. Cameras are not permitted on site. FBP will provide site radios, if required.

K. Temporary Roads and Parking

1. Contractor shall be responsible for providing and maintaining all roads and parking areas deemed necessary by Contractor for access, and parking in Temporary Facilities areas, construction areas, and between areas. Contractor provided roads and parking areas shall be constructed so as to provide for adequate safe movement of light and heavy vehicles, and equipment. Contractor's temporary roads shall be constructed in a manner to prevent damage to permanent roads, facilities, and underground utilities and structures.

2. Contractor shall remove and restore areas occupied by temporary roads and parking areas upon completion of the Work.

3. Contractor shall comply with load restrictions in all buildings and all roads and bridges.

4. Maintenance of Traffic: The Contractor shall provide flagmen, safety cones, barricades, signage, etc., as necessary to maintain safe traffic flow on plant streets.

5. The Contractor shall, furnish, erect, and maintain during the progress of construction, substantial barricade, bridging, ramps, sidewalks, cones, barrels, guard rails, and signage; furnish, place and maintain adequate lights and warning signals, provide flagmen and watchmen.

6. No Plant streets or roadways shall be barricaded without coordination with the CTR. Requests for street closures shall be submitted to the CTR for approval at least three (3) days in advance.

7. Contractor area barriers shall have a designated entrance location(s); each location shall have a sign identifying the project name, contract number, Contractor, Contractor contact and phone number and CTR contact and phone number to notify for entry.

8. Barricades, temporary bridging, and other temporary construction installed by the Contractor shall be removed by the Contractor upon completion of work requiring such safeguards.

L. Equipment Inspections

Contractor vehicles, equipment, materials, trailers, tool boxes and tools shall be subject to inspection as described in Attachment J-13.

Page 20 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

M. Material Handling and Rigging

1. Construction activities, material deliveries, and off-loading operations shall be conducted to minimize interruptions to the Company's normal operations. Blockage of Company gates or other access to the work area shall not be permitted without prior coordination and approval of the CTR.

2. Contractor shall provide and operate cranes and other necessary equipment for handling, hauling, unloading, and receiving Contractor-supplied materials, tools, and equipment.

3. Refer to FPR Hoisting and Rigging J-13 1.28 for project lifts.

N. Weather protection of the work and any methods required to allow continuation of the work during periods of inclement weather.

O. Small tools (as described in Attachment J-13 1.47 and 1.48)

1. The Contractor shall perform a daily inspection of all equipment, vehicles, tools, safety devices, electrical cords, equipment guarding, fire extinguishers, etc. to assure the safe working condition and OSHA compliance of all tools and equipment. Documentation must be compiled by date and list all the tools/equipment inspected for that date, daily inspection of tools/equipment shall be noted on the Contractor Daily Report.

2. Documentation of inspections must be made available for the Company’s review. Equipment that does not meet the manufacturer’s requirements for safe use shall be taken out of service. Prior to reinstating tools and equipment previously taken out of service, the tools and equipment must be inspected by the competent person.

P. Electric Power Tools and Equipment (as described in Attachment J-13 1.47 and 1.48)

1. All electric power tools and equipment shall be protected with a Ground Fault Circuit Interceptor (GFCI). The GFCI must be plugged in at the power source and shall be inspected and tested daily or prior to use.

Q. Permits

1. Job Site Work Permits: All permits required for performance of the Work at the jobsite will be arranged by the Company. The Company will provide the following permits as required: Contractor shall request the permit a minimum of five (5) working days in advance of the permit need.

(1) Excavation (2) Penetration (3) Welding / Hot Work (4) Lock Out Tag Out (LOTO) (5) Radiological Work Permit (RWP) (6) Confined Space Work Permit

R. The Contractor shall provide temporary fencing to identify work areas, temporary

facilities areas, materials, and equipment storage areas.

Page 21 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

S. Contractor shall provide project signs for traffic control, and direction, and for

identifying project areas.

T. Only Contractor's company vehicles, as approved by CTR, will be allowed in the construction zone.

5.3 Environmental Protection

A. Vehicles, equipment, or liquid storage containers shall not be stored in areas where spillage or leakage of materials would enter the plant's drainage system without an approved leak mitigation plan. The Contractor shall immediately notify the CTR of any spills, regardless of the quantity, type, or location. Spill response and cleanup will be performed under the direction of the Company. Cost associated with spills resulting from negligence by the Contractor shall be the sole responsibility of the Contractor.

B. The Contractor shall submit erosion and containment control measures including plans for such measures for all contractors’ plans and activities. Erosion and containment control measures and plans are subject to approval by the CTR and Company’s Environmental, Safety and Health and Quality (ESH&Q). Refer to Exhibit 5.

C. All products or hazardous materials brought on-site by the Contractor shall be maintained under the control of the Contractor. No excess products or hazardous materials are to remain onsite after the project is complete. Contractor shall submit Material Safety Data Sheets (MSDS) for review and approval prior to bringing such items on-site in accordance with Attachment J-13.

5.4 Excavation/Penetration

A. A Excavation/ Penetration Permit is required when breaching or penetrating any building surface more than 1-½” (unless excluded), any blacktop or concrete pavement surface more than three (3) inches, or the earth’s surface more than twelve (12) inches. These methods include, but are not limited to, auguring, drilling, driving, and coring, or penetrating. Penetrations include drilling wells and boring for soil samples up to and including 12 inches in diameter in accordance with J-13 Paragraph 1.39.

B. The Company has performed a subsurface investigation to aid the Contractor in locating existing buried/ hidden utilities or other underground structures or interferences that could impact the Work. Prior to excavation, soil penetration, or other soil/surface disturbing activities the Contractor shall review the Company’s subsurface investigation to verify the location of buried/ hidden utilities or other underground structures or interferences that could impact the Work. Contractor shall request and obtain a Penetration Permit from the Company following review of the subsurface investigation and prior to digging.

If during the execution of the Work, the Contractor encounters buried/ hidden utilities or other underground structures or interferences not identified previously, the Contractor shall STOP WORK and immediately advise the Company and confirm findings in writing. Company will evaluate findings and direct Contractor to resume work following investigation in accordance with J-13 Paragraph 1.39. The Contractor shall record location, including elevations of buried/ hidden utilities or other underground structures or interferences.

Page 22 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

C. All excavations require FBP Health Physics to survey the excavation process.

5.5 Existing Utilities/Service Interruption

A. Where work involves breaking into or connecting to existing services or utilities, the Contractor shall schedule work and perform interruptions in coordination with plant utility requirements.

6.0 PERFORMANCE SCHEDULE AND SEQUENCE OF WORK

6.1 Milestone Requirements

Specific Milestones, interfaces, and other schedule related bases of this Contract are as set forth in Exhibit 1.

6.2 General Scheduling Requirements

General scheduling, reporting and coordination requirements shall be described in Section H and C, 6.0, Special Contract Requirements.

A. Contractor shall submit the detailed schedule required by Section H, and C, 6.0, Special Contract Requirements in accordance with Attachments J-6 and J-8.

B. Specific scheduling and coordination requirements may include but not necessarily be limited to the following:

1. Engineering deliverables by discipline 2. Mobilization time for manpower and equipment 3. Material deliveries to jobsite 4. Shop fabrication 5. Incremental completion dates of major components 6. Start and completion of different segments of work (early and late starts) 7. Any qualifying conditions of Company or Client 8. Other as necessary

6.3 Schedule Resource Loading

Contractor Project Schedule shall be a resource loaded Critical Path Method (CPM) Schedule that clearly identifies both, all logical relationships/dependencies between activities related to the project, and the project’s projected critical path schedule from Notice to Proceed (NTP) through project completion. This resource loaded Critical Path Method (CPM) Schedule shall have the following two levels:

1. The first level, the Pay Item level (Pay Item Layout) 2. The second level, the Activity Level (Detailed Layout) 3. Activities will roll up to support the Pay Items

Page 23 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

6.4 Baseline Schedule

The initial Contractor Project Schedule, once approved by the Company will be known as the Contractor Baseline Schedule (may include approved modifications). This Schedule will be used for comparison with subsequent project schedules. The project schedule shall meet the following requirements:

1. Monthly Project Schedule Update which shall include the following:

• Actual or projected start and finish dates • Activity progress and remaining duration • Bar chart schedule comparing the current schedule to the baseline schedule • Revisions to craft resources • Specific to estimated schedules in man hours • Percent complete for each activity (summarized/listed in the Pay Item section of

the Contractor Project Schedule and shall be the basis for the amount invoiced for that Pay Item).

• A copy of the updated Contractor Project Schedule shall be submitted to the Company by the date established in the contract.

6.5 Four Week Rolling Schedule

Contractor shall submit a Four-Week Rolling Schedule (refer to Attachment J-30) which documents/lists four weeks of the Project Detailed Layout, which shall include the following:

• A schedule of the previous week, the present week, and the two future weeks NOTE: The activity may be a pay item when it is of sufficient detail to meet the

definition of the activity. • Activities grouped by Pay Item activities and sorted by Early Start Dates • Activities schedule coded with corresponding Pay Item ID code • Expected/Projected Man-hours by craft (carpenters, laborers, operators, etc.) for

each activity • Pay Item values breakdown of activities

The Four-Week Rolling Schedule shall be presented to the Company at the Weekly Progress Meeting.

6.6 Contractor Scheduling Software

The Contractor shall be required to use the following software, which is compatible with the Company Scheduling Software (Primavera P6) to prepare the required project schedules:

1. Primavera P3 or P6 2. Primavera SureTrack 3. Microsoft Project

Page 24 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

6.7 Schedule Submittals

An electronic file containing the updated project schedule shall be submitted along with the hard copy of the updated schedule.

6.8 Work Hours, Deliveries and Overtime

A. Normal site work hours will be four days per week, 10 hours per day, (Monday through Thursday), between the hours of 7:00 a.m. and 5:30 p.m. Contractor shall be prepared to work the hours required by Contract.

B. Material and equipment deliveries shall be permitted Monday through Thursday, e.g. 7:00 AM-5:30 PM Eastern Time. Deliveries outside of these times must be coordinated with the CTR at least two (2) working days in advance.

C. Requests for scheduled overtime, weekend, or holiday work during normal situations shall be made to the CTR at least two (2) working days before the start of these shifts.

D. Requests for non-scheduled extended work hours in emergency situations shall be made to the CTR at least three hours in advance for overtime during the normal work week and at least by noon of the last regular workday.

E. For work being performed outside the normal work schedule the Contractor shall coordinate with the CTR for any special arrangements for security, safety, escorting, health physics, and other the Company provided resources. Plant entry and exit requirements may change when working outside of the normal work schedule. It is the Contractor’s sole responsibility to coordinate with the CTR to plan accordingly for personnel, deliveries, and all other requirements needed to perform work during non-normal scheduled work times.

7.0 REPORTING REQUIREMENTS AND COORDINATION MEETINGS

Contractor shall promptly submit the schedules and reports set forth in Attachment J-8 (Contractor / Supplier Submittal Register).

7.1 Daily Reports

Contractor shall make written Daily Reports (Attachment “J-5”, Contractor Daily Report) to the CTR by 10:00 am each morning for the preceding day.

7.2 Weekly Progress Meetings

A. The Contractor shall attend weekly progress meetings. Contractor shall be prepared to discuss scheduled progress versus actual progress giving details of Work completed in relation to the approved schedule, together with a Four-Week Rolling Schedule which provides details of how the Work will be completed.

B. The person or persons designated by the Contractor to attend the meetings shall have the required authority to make decisions and commit the Contractor to solutions agreed upon during these meetings.

Page 25 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

7.3 Monthly Reports, Schedules and Schedule updates

Shall be in form and format approved by Company. These reports shall be submitted under cover of a letter in accordance with Attachment J-6.

7.4 Other Meetings

Contractor participation in certain additional activities shall also be required. These activities shall include, but not be limited to:

A. Indoctrination and orientation of all Contractors’ employees (also known as the Alignment/ Kick off meeting) will be held prior to the Contractor commencing work at the jobsite. (This includes the entire labor force and all new hires). The meeting will last approximately 8 hours.

B. Other meetings/ briefings as described in Attachment J-13, as requested by the Company.

8.0 CORRESPONDENCE, SUBMITTALS AND COMMUNICATION REQUIREMENTS

8.1 Contract Transmittals

When required by the Contract, Contractor shall transmit to Company, technical submittals, shop drawings or samples, including supporting catalog cuts, manufacturer’s literature, sketches or drawings, calculations and other pertinent data, in sufficient detail to enable Company to review the information and determine that Contractor clearly understands the requirements of the Contract. Documents shall be transmitted to Company under cover of formal contract correspondence utilizing Attachment J-6 Contractor/Supplier Cover Sheet. Contractor shall provide submittals listed on Attachment J-8 (Contractor / Supplier Submittal Register) as part of the Statement of Work.

8.2 Contract Submittals

Contractor shall submit all engineering data, samples, and shop drawings (herein called "data") listed on “Attachment J- 8 (Contractor / Supplier Submittal Register) for review in accordance with Attachment “J-6”.

1. Refer to the Attachment J-8, (Review Period Column) for the Company required review period of data submitted by Contractor.

2. Each submittal of Contractor's data shall be signed by Contractor and accompanied by a letter of transmittal containing the date of submittal, Contract Number, and all pertinent information required for identifying and checking submittals.

(1) One (1) reproducible and two (2) prints shall be submitted for each drawing and any other documents larger than 11" x 17".

(2) Two (2) prints shall be submitted for documents which are 11" x 17" and smaller, and documents such as procedures and calculations shall be 8 1/2" x 11" size. Although Work may proceed on receipt of data with a Code "B" notation, Contractor must incorporate the changes indicated, resubmit for final approval Code “A” before release of materials or equipment for shipment can be approved by Company. Returned copies of data with

Page 26 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

Code "B" and "C" shall be resubmitted not later than ten days after the date of transmittal by Contractor of such copies of such data.

(3) Contractor shall show the Company Contract Number and identifying item numbers, if applicable, on all data submitted pursuant to this Article 8.0.

8.3 As-Built Drawings and Material Certifications

For Contracts that include new construction or modifications to existing facilities, the Contractor shall furnish to Company reproducible drawings revised by Contractor to show "as-built” information.

A. Contractor's revisions shall show details of those locations where the work performed by Contractor was at variance with the details shown on the drawings (either furnished by Company or furnished by Contractor and reviewed by Company).

B. Contractor's submittal to Company of such "As-Built" drawings shall be made on a continuous basis as the Work proceeds, but in all cases prior to the date of Notice of Acceptance.

C. Company will provide Contractor an electronic version of Company furnished drawings.

D. The Company reserves the right to review certified material test reports for all contractor furnished materials of construction at any time during field erection. Contractor shall maintain these documents readily available for such review and shall submit all documents to Company on the completion of the Work.

8.4 Contract Drawings and Specifications

A. The Contractor shall maintain at the jobsite up-to-date copies of all drawings, specifications, and other documents and supplementary data, complete with latest revisions thereto. In addition, Contractor shall maintain a continuous record of all field changes, and at the conclusion of the Work, shall incorporate all such changes on the "As Built" drawings and other engineering data and shall submit the required number of copies thereof to Company.

8.5 Samples

Where samples are required, they shall be submitted by and at the expense of Contractor. Such submittal shall be made not less than thirty (30) calendar days prior to the time that the materials represented by such samples are needed for incorporation into any Work. Samples shall be subject to review and materials represented by such samples shall not be manufactured, delivered to the site or incorporated into any Work without such review.

9.0 CONTRACT MODIFICATIONS

9.1 The Contract Modification, “Attachment J-11” and the Contract Site Instruction (CSI) are the only documents by which the Contract may be changed or supplemented. Changes may not be invoiced until the appropriate modification has been executed and issued.

9.2 Company will prepare all Contract Modifications.

Page 27 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

9.3 Both Company and Contractor’s authorized representatives shall execute all Contract

Modifications.

9.4 Contract Modifications shall be numbered consecutively.

10.0 CLEAN-UP, SAFETY, WORK RULES, AND REGULATIONS

10.1 General Safety

Contractor shall perform the work in a safe manner and keep the work site in a clean condition in accordance with Attachment J-13, Environmental Health & Safety Requirements for On-site Work and shall comply with all work rules and regulations

10.2 Contractor’s Safety Plan

The Contractor shall submit their Project Safety Plan to the Company for review and approval in accordance with Attachment J-8. The Project Safety Plan shall address project details (general and specific), requirements of J-13, and comply with and meet applicable Federal, State, and local laws, rules, regulations and guidelines governing worker safety and health. The plan shall address all operations and work practices of the Contractor, subcontractors, and suppliers.

10.3 For Fire Protection Requirements refer to Attachment J-29.

11.0 WASTE MANAGEMENT

General

The X-670 Complex construction and demolition debris will include steel, concrete, related structural and building components, cooling tower equipment, tools, and associated utilities (e.g., piping, conduit wire, duct, etc.) and mechanical and electrical components.

The Contractor shall demolish, size reduce and load debris and waste generated from the Work into appropriate containers. Debris and waste generated during this project shall be segregated and containerized as follows:

Waste Type Container type: Debris Industrial Debris/ Industrial Waste Roll-off/dump trucks

The Contractor shall not collect or store debris. When debris piles are necessary for the work, the Contractor shall maintain the piles in a safe orderly condition. This includes minimizing the volume to reduce hazards associated with the material.

Page 28 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

11.2 Debris/Waste Container Supply and Management

A. Sanitary/Industrial Waste Containers

1. The Company will provide roll-off box type containers for use by the Contractor to transport and dispose of sanitary/ industrial debris and waste. The Company will stage the empty containers in the Laydown, Staging area (Refer to Exhibit 3) prior to the start of work.

2. The Contractor shall be responsible for damage to Company provided roll-off boxes caused by loading other than normal wear. The Contractor shall maintain the Company provided roll-off boxes as appropriate to maintain the function of the containers including maintenance and repair of door hardware, rollers and connections for loading the boxes on roll-off trucks.

11.3 Solid Waste Disposal

A. The Contractor shall provide to the Company, in writing, the disposal site selected and the permit/license information for the selected disposal site for industrial/sanitary waste prior to the start of demolition. The selected disposal site shall comply all applicable solid waste requirements listed in Paragraph 5.2.7.D (1-6)

B. The Contractor shall provide copies of weight tickets from the disposal facility for all roll-off boxes delivered to a disposal facility. The weight tickets shall contain truck number, container number, time, and date in addition to the weight as determined by the disposal facility. The weight tickets shall be submitted to the CTR on the business day following the date of disposal.

11.4 Labeling of Waste and Containers

A. The Company will be responsible for labeling and marking sanitary/industrial waste containers for solid demolition waste.

B. The Company will not label the containers from the flushing operation; however, the Contractor shall provide the number and quantity (volume) of containers for each flushing operation to the CTR as part of Contractors’ request for authorization for off-site disposal.

11.5 Contractor Generated Waste

A. No Waste Package Certification will be required for miscellaneous Contractor waste or any waste associated with Contractor break areas. Contractor waste shall not be mixed with any of the X-670 or X-670A rubble/ debris.

11.6 Debris Classification

A. Industrial Debris/Sanitary Waste

Industrial debris/sanitary waste will include the X-670 Complex and RCW flushing and cleaning liquid waste, etc.

B. Low-level Waste

Page 29 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

Low-level waste is not anticipated. In the event LLW is encountered, waste activities will be paused and continued waste processing will be reevaluated.

12.0 SECURITY

12.1 Security Requirements at the ports Site

The Contractor shall comply with all requirements of Attachment J-15, Specification 01546 PORTS FBP Site Security Requirements and Exhibit 4 Security Protocol for the X-670 Cooling Tower Coil Replacement Project while performing work under this contract.

13.0 QUALITY ASSURANCE

13.1 Quality Assurance Program

The Contractor shall be responsible for maintaining an acceptable Quality Assurance Program as specified in Attachment J-16 “Quality Assurance Requirements”. The Contractor shall submit a Quality Assurance Program Plan including Inspection Procedures and documentation for approval prior to Authorization to Mobilize (ATM) in accordance with Attachment J-8. The Company must approve the Contractor‘s Quality Assurance program prior to initiating work.

14.0 FINAL ACCEPTANCE

14.1 Acceptance of Contract:

A. In Conjunction with Contract Clause H.54 the Contractor shall coordinate a final acceptance walk down of the work with the CTR and others as required to verify completion of the work and resolution of any identified discrepancies. Discrepancies will be documented in accordance with J-16 and shall be resolved by the Contractor prior within the Contractor’s project schedule time for work completion and not extend beyond the approved project schedule.

B. A Final Completion of the Punch List will be developed and agreed by the company and Contractor. Any nonconformance shall be just cause for rejection of the service provided and delayed payment until the supplier complies with the SOW.

C. Company shall verify that all deliverables have been received and that all contractual documentation requirements have been satisfied.

Page 30 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

Exhibit 1 – Milestone Schedule

Schedule Summary

Pay Item Pay Item Description Duration

(Calendar Days)

1 Notice to Proceed (NTP) -

2 Pre-Mobilization Submittals 21 Days after NTP

3 Mobilization and Training 35 Days after NTP

4

Construction and Demolition Completion:

a. X-670A Cooling Tower Coil Replacement

b. RCW System Flush and Clean

c. Provide and Install Self-Contained Filtration Skid

d. Compressor #4 Installation

e. Sanitary Waste Off-site Disposal

f. System Start-up and Operational Verification

155 Days after NTP

5 Site Restoration 161 Days after NTP 6 Demobilization 165 Days after NTP 7 Project Close Out 195 Days after NTP

Page 31 of 32

FLUOR B&W PORTSMOUTH LLC SECTION C – STATEMENT OF WORK X-670A Cooling Tower Coil Replacement

Exhibit 2 – Acronyms

ACM Asbestos Containing Material

CPM Critical Path Method

CTR Contract Technical Representative

D & D Decontamination and Decommissioning

DOE Department of Energy

ESH & Q Environmental Safety Health and Quality

FBP Fluor – B&W Portsmouth

FMSCR Federal Motor Carrier Safety Regulations

GFCI Ground Fault Circuit Interrupter

GVWR Gross Vehicle Weight Rating

HEPA High Efficiency Particulate Air

HSE Health Safety Environmental

KW Kilowatt

LLBS Longitudinal and Lateral Bracing System

LLW Low-Level Waste (radiological)

LOTO Lock Out Tag Out (electrical)

NEC National Electric Code

NFPA National Fire Prevention Association

OBBC Ohio Basic Building Code

ODOT Ohio Department of Transportation

OSHA Occupational Safety and Health Administration

PORTS Portsmouth Gaseous Diffusion Plant

PPE Personal Protection Equipment

PUCO Public Utilities Corporation of Ohio

RCW Recirculating Cooling Water

RWP Radiological work permit

SHWP Safety Health Work Permit

SOW Statement of Work

SWPPC Storm Water Pollution Prevention Controls

Page 32 of 32