2011-2012 and

What’s Next

• Introduction ….Eddie Hueston• Cheri Stanley• Parking Lot A & B Renovation• Bonham Elevator Project• Decommissioning of Verde• Continuation of Landscape Lighting Project• Wichita Restrooms Renovation• Completion of Phase II Storefront

Replacement• Austin Longacre• Spillway Renovation Project• El Paso Walkway Improvement• Phase III Carpet Replacement• Landscape Conversion Plan• Removal & Relocation of Thunderduck

Planters• New Fleet Decals• Ron Foster• Utility Bridge Project

• Jerry Owens• New Custodial Cleaning Schedule• New Seasonal Temperature Settings• New Cooling Towers• Oncor Rebate Incentive Program• Light Harvesting on Campus• Parking Lot Lighting Project• Electric Cart Charging Dock• Waste Reduction on Campus• Conclusion… Eddie Hueston• Q & A’s

Page 3: Pardon Our Thunderdust 2011-2012

Parking Lot A & B Renovation

Page 4: Pardon Our Thunderdust 2011-2012

Parking Lot A & B Renovation• Purpose: To repair

Parking Lots A & B, from the sub-base to the lot surface

• To be done in one phase to expedite completion

• Temp. ADA parking to be provided in Parking Lots C & D

• Projected time of project: Oct. 10 – Nov. 17th

Page 5: Pardon Our Thunderdust 2011-2012

• Bonham has an elevator that measures 44” deep x 80” wide

• The minimum requirement is 54” deep x 80” wide

Bonham Elevator Project

5

Page 6: Pardon Our Thunderdust 2011-2012

Bonham Elevator Project• Purpose: To meet

ADA standards for existing elevator in Bonham building

• In addition, ADA accessible corridor will be constructed on 1st floor

• Status: In the design and planning stage

Page 7: Pardon Our Thunderdust 2011-2012

7DEMOLITION PLAN-FIRST FLOOR

Existing elevator cab and exterior front wall to be removed

Corridor wall to be removed

Existing doorsTo be removed

Classroom walls, doors, ceilings, lighting to be removed

Page 8: Pardon Our Thunderdust 2011-2012

Decommissioning of Verde

Page 9: Pardon Our Thunderdust 2011-2012

Decommissioning of Verde

• Purpose: Verde building was found structurally unsound for classroom use; decision was made to decommission the building for safety reasons

• In the process of contracting an outside vendor to demolish and remove the building; Material suitable for recycling will be saved and dealt with appropriately

Page 10: Pardon Our Thunderdust 2011-2012

Continuation of Landscape Lighting Project

Page 11: Pardon Our Thunderdust 2011-2012

Continuation of Landscape Lighting Project

• Currently in Phase IV of the project• Purpose: To provide safety on campus

through better lighting, as well as reduced energy consumption

• Will add (4) additional fixtures at Westside Medina (lakeside) for better illumination

• This phase should be the final phase for the foreseeable future

Page 12: Pardon Our Thunderdust 2011-2012

Wichita Restrooms Renovation

Page 13: Pardon Our Thunderdust 2011-2012

Wichita Restroom Renovation• Purpose: To improve the

overall aesthetic condition of (4) Wichita restrooms

• Restroom fixtures to be removed and replaced, as well as tile

• Will match the new campus standard, as seen in the Peco Expansion

Page 14: Pardon Our Thunderdust 2011-2012

Completion of Phase II Storefront Replacement

Page 15: Pardon Our Thunderdust 2011-2012

Completion of Phase II Storefront Replacement

• Replaced 79 door openings; Approx. 30 doors remain to be replaced

• New doors more energy efficient; Allow less UV penetration than previous doors, and seals contain inside air better

Page 16: Pardon Our Thunderdust 2011-2012

Spillway Renovation Project

Page 17: Pardon Our Thunderdust 2011-2012

Spillway Renovation Project

• Purpose: To fix separation in several joints in the spillway culverts, causing the formation of sinkholes after heavy rains

• Will utilize high-pressure grout injection to realign the sections of concrete pipes

• Pipe sections will be sealed from the inside after realignment

• Minimal impact on surrounding area expected; Draining of lake not necessary

Page 18: Pardon Our Thunderdust 2011-2012

El Paso Walkway Renovation

Page 19: Pardon Our Thunderdust 2011-2012

El Paso Walkway Renovation

• Purpose: To eliminate suspected exterior leak origins above El Paso

• Joint sealant removed from Crockett/Alamito breezeway to Fannin/Lavaca breezeway; Replaced with high-impact, flexible, traffic-grade joint sealant

• Patchwork made on any areas where aggregate spalling was more than 1” deep

Page 20: Pardon Our Thunderdust 2011-2012

Phase III Carpet Replacement

Page 21: Pardon Our Thunderdust 2011-2012

Phase III Carpet Replacement

• Purpose: To replace dated and damaged carpet in Medina & Bonham buildings

• Will be completed through the help of a District SAR

Page 22: Pardon Our Thunderdust 2011-2012

Landscape Conversion Plan

Page 23: Pardon Our Thunderdust 2011-2012

Landscape Conversion Plan• Purpose: To increase

sustainable landscape by 20% over the next two years

• Will reduce water consumption, fertilizer application, labor, and carbon footprint

• Will include various wildflower mixes and native turfgrasses

Page 24: Pardon Our Thunderdust 2011-2012

Removal and Relocation of Thunderduck Planters

Page 25: Pardon Our Thunderdust 2011-2012

Removal and Relocation of Thunderduck Planters

• Purpose: To increase flow during high-traffic periods in Thunderduck Hall

• Repurposed planters to (4) different locations on campus

• Planters now contain native, low-maintenance plant material

Page 26: Pardon Our Thunderdust 2011-2012

New Fleet Decals

• Purpose: To update vehicle fleet decals

• Mono-chromatic graphics to be used to prevent sun damage / fading

• Similar to graphic to the left, but either all black, or all white, die-cut vinyl

Page 27: Pardon Our Thunderdust 2011-2012

Utility Bridge Project• REPLACE LEAKING HVAC

(HEATING VENTILATION & AIR CONDITIONING) PIPING THAT TRAVELS UNDER THE LAKE NEAR PECOS

• TEMPORARY SOLUTION WAS TO INSTALL 165 FEET OF EIGHT (8) INCH PIPING ACROSS THE NORTH BRIDGE TO PROVIDE HEATING TO THE EASTSIDE

• INSTALL NEW BRIDGE NORTH OF EXISTING PEDESTRIAN BRIDGE

• RE-OPEN EXISTING BRIDGE FOR FOOT AND UTILITY VEHICLE TRAFFIC

Page 28: Pardon Our Thunderdust 2011-2012

New Custodial Cleaning Schedule

• T-DUCKS IN ROW #101 – CUSTODIAL SERVICES SCHEDULE ADJUSTMENTS TO ACTIVE BUDGET SAVINGS

• MONDAY – THURSDAY. TRASH AND RECYCLING CONTAINERS SHOULD BE PLACED OUTSIDE OF OFFICE DOORS WHEN THE LAST OCCUPANTS LEAVE. THE DEEP-NIGHT CUSTODIAL CREW WILL EMPTY THE CONTAINERS AND PLACE THEM BACK OUTSIDE OF OFFICES

• FRIDAY- CONTAINERS SHOULD BE LEFT INSIDE OFFICES FOR TRASH AND RECYCLING TO BE REMOVED BY WEEKEND CLEANING CREW

• THE WEEKEND CUSTODIAL CREW WILL CLEAN OFFICES AND EMPTY CONTAINERS

• ANNUAL COST SAVINGS OF $102,000

Page 29: Pardon Our Thunderdust 2011-2012

New Seasonal Temperature Settings for Summer & Winter

• WINTER SETTING OF 72°F WILL COMMENCE ON DECEMBER 1 AND END ON APRIL 1

• SUMMER SETTING of 76°F WILL COMMENCE ON APRIL 2 AND END ON NOVEMBER 30

• ESTIMATED COST SAVINGS OF 20% TO 30% OF UTILITY BUDGET

Page 30: Pardon Our Thunderdust 2011-2012

New Cooling Towers

Page 31: Pardon Our Thunderdust 2011-2012

Energy Savings

Page 32: Pardon Our Thunderdust 2011-2012

Oncor Incentive Rebate Program

• ONCOR PRESENTED DCCCD WITH REBATE CHECK OF $75,480 FOR THE INSTALLATION OF A HIGH EFFICIENCY (.541 KW/TON) CHILLER AT RICHLAND

• VICE CHANCELLOR OF BUSINESS AFFAIRS, ED DES PLAS, PRESENTED THE REBATE CHECK TO RICHLAND TO BE USED IN ENERGY REDUCTION PROJECTS

• RICHLAND WILL UTILIZE THE FUNDS TO ACCOMPLISH THE FOLLOWING:

– Upgrade the main energy management system (EMS)– Install control system for exhaust fans, water coolers and electric hot water heaters– Replace old outdated equipment on air handling units– Purchase and install electrical and water monitoring devices– Install lighting and HVAC systems control points on EMS for Kiowa, Uvalde and Yegua

Halls– Upgrade HVAC controls for Bonham, Del Rio and Neches Halls

Page 33: Pardon Our Thunderdust 2011-2012

Light Harvesting on Campus• Through the use of photo sensors, light levels are automatically

adjusted to take into account ambient natural sunlight entering the building. Appropriate light levels are maintained and artificial lighting is dimmed when necessary.

• BUILDINGS SELECTED IN PHASE I:– EL PASO HALL– STUDENT LOUNGE– DEL RIO 2ND FLOOR– GYM LOBBY– MEDINA 1ST FLOOR WEST HALLWAY– CROCKETT HALL OUTSIDE C-140

Page 34: Pardon Our Thunderdust 2011-2012

Parking Lot Lighting Project• RE-COMMISSIONING OF 120’

PARKING LOT LIGHT FIXTURES• INSTALL THIRTY-EIGHT (38)

SOLAR NEW LIGHT EMITTING DIODE (LED) LIGHT FIXTURES ON BOTH (EAST & WEST) PERIMETER ROADWAYS

• REPLACE FORTY-ONE (41) METAL HALIDE FIXTURES WITH LED IN PARKING LOTS U, V & W

• INSTALL FOUR (4) NEW LED LANDSCAPE LIGHTS BETWEEN MEDINA & DEL RIO

• REDUCE OUR ANNUAL CARBON FOOT PRINT BY 93.3 METRIC TONS OF CO²

Page 35: Pardon Our Thunderdust 2011-2012

Parking Lot Lighting Project

East Side West Side

Page 36: Pardon Our Thunderdust 2011-2012

Waste Reduction on Campus

Page 37: Pardon Our Thunderdust 2011-2012

Waste Reduction on Campus

• BASE YEAR – TOTAL TRASH SENT TO LANDFILL WAS 1,300,000 LBS. OR 650 TONS

• LAST YEAR- TOTAL TRASH SENT TO LANDFILL WAS 780,000 LBS. OR 390 TONS– 60 % OF OUR TRASH WAS DIVERTED FROM THE LANDFILL– REDUCTION IN DUMPSTER PICK-UP– REDUCTION IN DUMPSTERS– ANNUAL COST SAVINGS OF $5800

Page 38: Pardon Our Thunderdust 2011-2012

Electric Cart Charging Dock

Page 39: Pardon Our Thunderdust 2011-2012

Thank You for Your Time and PatienceRichland College Facilities Services

Page 40: Pardon Our Thunderdust 2011-2012
Page 41: Pardon Our Thunderdust 2011-2012
Page 42: Pardon Our Thunderdust 2011-2012