parapet precast
TRANSCRIPT
African Union Peace & Security Building
Project: African Union Peace and Security Building
Location: Addis Ababa
Implementing Agency: giz
Flintstone engineering
Ethio China Road Ave.
Addis Ababa, Sub City Cherkos, Kebele 03
PO Box 559/1110, Ethiopia
9 / 2 0 / 2 0 1 1
Date:21th February 2012
Work Methodology for prefabricated parapet construction
African union Peace & security building
Contents1. Scope of Methodology............................................................................................................................2
2. Column Reinforcement bar...................................................................................................................2
3. Column shuttering...................................................................................................................................3
4. Concrete Placing.......................................................................................................................................4
Labor Arrangement.........................................................................................................................................5
5. Schedule......................................................................................................................................................5
A U - P S B P a g e | 1
African union Peace & security building
1. Scope of Methodologyo This method statement relates to the construction of precast concrete parapet
construction and assembly work. o It shall mainly cover the processes related to the mass production and
assembly of standard diagonal parapet sections of a standard angle of inclination 780 and 800
o
2. Prefabrication
2.1 formwork productiono The AU-PSB Building has a sloped façade parapet on the west and south sides
of the building. This sloped façade is one of the major architectural significant features of the building.
o The sloped façade shall start from the slab above the first floor o The 50ml is the 810 slope (South Direction ) and the 44ml is the 780 slopes
(West direction)
o Concrete column heights to be cast at once may rich from 4.60m to 10.40m up to the bottom of ground floor beams. o 14.2 tons of reinforcement bars shall be fixed to ground floor circular columns.o The Ground floor wall rebar quantity is around 92 tons. o The rebar Overlap length shall not be less than 96cm for the main bars.o The rebar work shall continue to be done is 2 shifts.
A U - P S B P a g e | 2
African union Peace & security building
3. Column shuttering
There are around 39 circular columns in ground floor with a diamter as shown below,
o In order to finish the casting in one month, with the limited circular formwork available on site, it is a must to cast 5 columns of dia. 50cm columns in one week of time.
o Since the formwork on site are a maximum of 4m height we are forced to cut some of the column formworks which has a diameter less than 50cm and monolithically fix on the formworks of 4m height of the same diameter to get a full height of 6ml.
o Joints between two Half circle shall be sealed with silicon to avoid the outflow of cement paste during concrete casting.
o
o Bottom frame shall be prepared as shown above from a piece of plywood and fixed to the concrete floor slab so that later on the circular column formwork shall be precisely guided with it.
o After the inspection of the column reinforcement, the shuttering shall be closed.
o A bottom and top push and pull prop will be attached in a horizontal 900 angle and adjusted to get the vertical plumb.
o The circular formwork panel is painted with a release agent to avoid the bonding effect between the shuttering and concrete element. Sika Decoffre Mineral is the material that shall be used as a formwork releasing agent.
4. Concrete Placingo The ground floor wall concrete volume is about 47m3
o Casting shall start at the third week of February 2012o Concrete columns which have a diameter equal of less than 50cm shall be cast
in one layer while columns greater than 50cm shall be cast twice per floor height.
o The columns located in the plenary room shall be casted with C-40 concrete compressive strength.
A U - P S B P a g e | 3
African union Peace & security building
o Cement paste or cement rich concrete mix shall first be placed to a height of 1m where the reinforcement and starter bars are congested in order to avoid the honey comb due to outflow of concrete, or due to segregation effect.
o PVC casting pipes of diameter 160mm shall be used to place the concrete to the bottom of column sections.
o Pocket Vibrator hose of length greater than 6m shall be used for casting columns.
o Viberator hose shall be inserted in the columns and shall be removed out very slowly.
o A gauging rod shall be prepared from reinforcement bar so that to assist the mason not to fill in excess of the required height.
o A copy of Concrete Delivery ticket (concrete book) shall be delivered to giz office for each mix of concrete.
o Site arrangement shall be made for slump tests and concrete cube tests for quality assurance purposes according to the DIN Standard.
Labor Arrangement
1. Surveying Teamo 1 Surveyoro 1 Assistant Surveyoro 2 Daily Laborers
2. Cleaning Teamo 1 Labor with the Compressor machineo 3 Cleaners
3. Welding Teamo 2 Welderso 2 Daily Laborerso
4. Tower Crane Operatoro 3 Operatoro 1 Assistant Operatoro 1 Mechanic
5. Shuttering fixing crewo 6 carpenters
A U - P S B P a g e | 4
African union Peace & security building
o 8 Daily Laborerso General Foremano Foremano Group Leader
6. Concrete casting groupo 3 mason in concrete placingo 6 carpenters to check the shuttering in placeo 13 Daily Laborers
5. Schedule
o In order to finish the 39 columns within 15 days, we have to cast 3 columns in a day.
o For the 50cm diameter column, we shall cast 3 columns in two days gap.
A U - P S B P a g e | 5