panduan pondasi
TRANSCRIPT
-
8/13/2019 panduan pondasi
1/37
FOUNDATION ENGINEERINGFOUNDATION ENGINEERING
,,
Budapest3 November 2011
-
8/13/2019 panduan pondasi
2/37
Foundation Engineering
1. Excavations
,
excavation.
Determinants of the value of the excavation:
Geometry of the building;
Transportation requirments;
Dewatering requirments
Determinants of the t e of the retainin structures:
Size of the site;
Type of the soil;
Groundwater;
me;
Neighbour structures;
Size of the building;
Available facilities technolo .
-
8/13/2019 panduan pondasi
3/37
Foundation Engineering
sloped (soil, torkret concrete);
1.1. Types of retainings
braced (wood, reinforced concrete, steel, plastic);
sheet piling (wood, steel, reinforced concrete);
diaphragma walls;
ore p e wa s;
freezing or chemical methods;
-
8/13/2019 panduan pondasi
4/37
Foundation Engineering
2. Sloped open cut method
building
stairs
If c=0, b
Most simple way to make excavation, but it needs bigfree lace and it re uires rather bi volume earthworks.
ditch
Under 6 m it requires slope stability calculations.
Excavated soil deponation must be out of slipsurface.
Under groundwater only in cohesive soils or dewatering is alsoneccesary.Dewatering of rainfalls is required.
Dynamic effects reduces slopestability.
-
8/13/2019 panduan pondasi
5/37
-
8/13/2019 panduan pondasi
6/37
Foundation Engineering
If the vertical eartwall is stable to excavation level.
3. 1. Braced with standing walls
Procedure:1.Excavate the soil to foundation level.2.Install walls into the excavation. (not continous)3.Install wales.4.Install struts.
-
8/13/2019 panduan pondasi
7/37
Foundation Engineering
If the excavation is deeper than>
3. 2. Braced excavation with repressing
Procedure:1. Excavate the soil to first stage (mo).2. Install walls, wales and struts temporary.3. Excavate the soil to the next stage.4. Relase struts and push walls down and install wales and struts.5. Repeat 3 and 4 till the designed depth.
-
8/13/2019 panduan pondasi
8/37
Foundation Engineering
3. 3. Braced excavation with lateral walls
The stable earthwall is very small,
in case of non-cohesive soils.
Procedure. o,
2. Install the walls, wales and struts temporary.3. Excavate the soil to the next stage.4. Rebuild wales and struts.5. Repeat procedure 3 and 4 till the designed depth.
-
8/13/2019 panduan pondasi
9/37
Foundation Engineering
3. 4. Table braced system
-
8/13/2019 panduan pondasi
10/37
Foundation Engineering
3. 5. Braced system
-
8/13/2019 panduan pondasi
11/37
Foundation Engineering
3. 5. Braced system
Chang-Yu Ou:Deep excavation
-
8/13/2019 panduan pondasi
12/37
Foundation Engineering
3. 6. Design braced excavation
compressed or bended.
Input:
Depth of excavation (H)
Space between wales (t);
Space between struts (y).
Output:
Thickness of walls (v);
Cross-section of wales ( ba );
Cross-section of struts (A).
-
8/13/2019 panduan pondasi
13/37
Foundation Engineering
4. Soldier pile method
Mostly 6 m deeper or 3-4 m wider excavations.
-
8/13/2019 panduan pondasi
14/37
Foundation Engineering
4. Soldier pile method
Chang-Yu Ou:Deep excavation
-
8/13/2019 panduan pondasi
15/37
Foundation Engineering
4. Design soldier pile method
Design:
- Cross-section of Soldier pile
- Depth of embedment
Loads Moment Shear
- Thickness of lagging
- Parameters of anchors
(if it is necessary)
-
8/13/2019 panduan pondasi
16/37
Foundation Engineering
Sturctural types of sheet-pile walls:
5. Sheet-pile walls
- em e e
- anchored in one level, without embeding- anchored and embeded- struted (braced)
- Death of embeding
- Mmaxcross-section of sheet
- Load of anchorsparameteres of anchors
-
8/13/2019 panduan pondasi
17/37
Foundation Engineering
5. Sheet-pile walls
Chang-Yu Ou:Deep excavation
-
8/13/2019 panduan pondasi
18/37
Foundation Engineering
5.1. Design sheet-pile walls
Embeded Anchored in one level,
without embeding
-
8/13/2019 panduan pondasi
19/37
Foundation Engineering
5.1. Design sheet-pile walls
Anchored and embeded
-
8/13/2019 panduan pondasi
20/37
Foundation Engineering
5.1. Design sheet-pile walls
Struted (braced)
-
8/13/2019 panduan pondasi
21/37
Foundation Engineering
5.2. Types of sheet-pile walls
Strate sheets
Half wave sheets
Total wave sheets
-
8/13/2019 panduan pondasi
22/37
Foundation Engineering
-
8/13/2019 panduan pondasi
23/37
Foundation Engineering
-
8/13/2019 panduan pondasi
24/37
Foundation Engineering
6. Diaphragma walls
Chang-Yu Ou:Deep excavation
-
8/13/2019 panduan pondasi
25/37
Foundation Engineering
6. Diaphragma walls
-
8/13/2019 panduan pondasi
26/37
Foundation Engineering
7. Freezing and injection
-
8/13/2019 panduan pondasi
27/37
Foundation Engineering
7. Freezing and injection
Gravely soils under groundwater and waterproof layer ismissing or in very deep.
Advantages:- Absolute waterproof- Other retaining structures are not neccesary- In any kind of soil (except injection clay)
Disadvanteges:- Difficult technical facilities- Expensive- Long time defrost in case of freezing
-
8/13/2019 panduan pondasi
28/37
Foundation Engineering
8. Shotcrete method
Excavation Nailing
ExcavationReinforcement, shotcreteApplication field:
Temporary or permanent retaining structure
Retaininig wall
Stabilization of slopes
Repair retaining structures
-
8/13/2019 panduan pondasi
29/37
Foundation Engineering
Thickness of shotcrete (12-25 cm),
8. Shotcrete method
Reinforcment:
oNetting,oReinforcing steel (1-2 layers),oHajbeton (steel, PE),
oSteel tube,oSteel bar,
oSteel nail, Instalation of nails:
oHit,oScrewed-injected,oJetedoScrewed
-
8/13/2019 panduan pondasi
30/37
Foundation Engineering
Application field:
8. Shotcrete method
Cohesive soils,Gravely soils,
Can not used:
Soft cohesive soilsOrganic soils, turf,Loose gravely soilsFilling (rocks, ash)
Advanteges
CheapSim le facilitiesVariable formElastic structure
Disadvanteges:
. .Can not install in case of groundwater
flowingDemages of public utilities
-
8/13/2019 panduan pondasi
31/37
Foundation Engineering
Procedure of designig:
8. Design shotcrete excavation
. e v s
2. Geometry of excavation3. Stability analysis
Sloping
bearingcapacity
-
8/13/2019 panduan pondasi
32/37
Foundation Engineering
8. Design shotcrete excavation
Compound
failure
Deep failure
Outpulling
Nail breakage
Shotcrete
breakage
-
8/13/2019 panduan pondasi
33/37
Foundation Engineering
8. Shotcrete method
-
8/13/2019 panduan pondasi
34/37
Foundation Engineering
Order of nailing
8. Shotcrete qualification
Outpull test
Measure movmentsInclinometer Install points
ShortcreteThicknessStrenght
-
8/13/2019 panduan pondasi
35/37
Foundation Engineering
Inclination of the wall: 1:8-1:10
8. Geometry of Shotcrete excavation
Tpus L/H
DL/S
d
2/SScrewed-injected nailsin gravely soils
0,5-0,8
0,5-0,6 (4-8)10-4
Hit nail in gravely soil 0,5--
(13-0,6
, ,19)10-
Mantle rock, marl0,5-1
0,15-0,2
(1-2,5)10-4
L: length of nails, H: depth of excavation, D: dimeter of, ,
-
8/13/2019 panduan pondasi
36/37
-
8/13/2019 panduan pondasi
37/37
Foundation Engineering
Thank You
for your attention!