panduan pondasi

Upload: toyobt

Post on 04-Jun-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 panduan pondasi

    1/37

    FOUNDATION ENGINEERINGFOUNDATION ENGINEERING

    ,,

    Budapest3 November 2011

  • 8/13/2019 panduan pondasi

    2/37

    Foundation Engineering

    1. Excavations

    ,

    excavation.

    Determinants of the value of the excavation:

    Geometry of the building;

    Transportation requirments;

    Dewatering requirments

    Determinants of the t e of the retainin structures:

    Size of the site;

    Type of the soil;

    Groundwater;

    me;

    Neighbour structures;

    Size of the building;

    Available facilities technolo .

  • 8/13/2019 panduan pondasi

    3/37

    Foundation Engineering

    sloped (soil, torkret concrete);

    1.1. Types of retainings

    braced (wood, reinforced concrete, steel, plastic);

    sheet piling (wood, steel, reinforced concrete);

    diaphragma walls;

    ore p e wa s;

    freezing or chemical methods;

  • 8/13/2019 panduan pondasi

    4/37

    Foundation Engineering

    2. Sloped open cut method

    building

    stairs

    If c=0, b

    Most simple way to make excavation, but it needs bigfree lace and it re uires rather bi volume earthworks.

    ditch

    Under 6 m it requires slope stability calculations.

    Excavated soil deponation must be out of slipsurface.

    Under groundwater only in cohesive soils or dewatering is alsoneccesary.Dewatering of rainfalls is required.

    Dynamic effects reduces slopestability.

  • 8/13/2019 panduan pondasi

    5/37

  • 8/13/2019 panduan pondasi

    6/37

    Foundation Engineering

    If the vertical eartwall is stable to excavation level.

    3. 1. Braced with standing walls

    Procedure:1.Excavate the soil to foundation level.2.Install walls into the excavation. (not continous)3.Install wales.4.Install struts.

  • 8/13/2019 panduan pondasi

    7/37

    Foundation Engineering

    If the excavation is deeper than>

    3. 2. Braced excavation with repressing

    Procedure:1. Excavate the soil to first stage (mo).2. Install walls, wales and struts temporary.3. Excavate the soil to the next stage.4. Relase struts and push walls down and install wales and struts.5. Repeat 3 and 4 till the designed depth.

  • 8/13/2019 panduan pondasi

    8/37

    Foundation Engineering

    3. 3. Braced excavation with lateral walls

    The stable earthwall is very small,

    in case of non-cohesive soils.

    Procedure. o,

    2. Install the walls, wales and struts temporary.3. Excavate the soil to the next stage.4. Rebuild wales and struts.5. Repeat procedure 3 and 4 till the designed depth.

  • 8/13/2019 panduan pondasi

    9/37

    Foundation Engineering

    3. 4. Table braced system

  • 8/13/2019 panduan pondasi

    10/37

    Foundation Engineering

    3. 5. Braced system

  • 8/13/2019 panduan pondasi

    11/37

    Foundation Engineering

    3. 5. Braced system

    Chang-Yu Ou:Deep excavation

  • 8/13/2019 panduan pondasi

    12/37

    Foundation Engineering

    3. 6. Design braced excavation

    compressed or bended.

    Input:

    Depth of excavation (H)

    Space between wales (t);

    Space between struts (y).

    Output:

    Thickness of walls (v);

    Cross-section of wales ( ba );

    Cross-section of struts (A).

  • 8/13/2019 panduan pondasi

    13/37

    Foundation Engineering

    4. Soldier pile method

    Mostly 6 m deeper or 3-4 m wider excavations.

  • 8/13/2019 panduan pondasi

    14/37

    Foundation Engineering

    4. Soldier pile method

    Chang-Yu Ou:Deep excavation

  • 8/13/2019 panduan pondasi

    15/37

    Foundation Engineering

    4. Design soldier pile method

    Design:

    - Cross-section of Soldier pile

    - Depth of embedment

    Loads Moment Shear

    - Thickness of lagging

    - Parameters of anchors

    (if it is necessary)

  • 8/13/2019 panduan pondasi

    16/37

    Foundation Engineering

    Sturctural types of sheet-pile walls:

    5. Sheet-pile walls

    - em e e

    - anchored in one level, without embeding- anchored and embeded- struted (braced)

    - Death of embeding

    - Mmaxcross-section of sheet

    - Load of anchorsparameteres of anchors

  • 8/13/2019 panduan pondasi

    17/37

    Foundation Engineering

    5. Sheet-pile walls

    Chang-Yu Ou:Deep excavation

  • 8/13/2019 panduan pondasi

    18/37

    Foundation Engineering

    5.1. Design sheet-pile walls

    Embeded Anchored in one level,

    without embeding

  • 8/13/2019 panduan pondasi

    19/37

    Foundation Engineering

    5.1. Design sheet-pile walls

    Anchored and embeded

  • 8/13/2019 panduan pondasi

    20/37

    Foundation Engineering

    5.1. Design sheet-pile walls

    Struted (braced)

  • 8/13/2019 panduan pondasi

    21/37

    Foundation Engineering

    5.2. Types of sheet-pile walls

    Strate sheets

    Half wave sheets

    Total wave sheets

  • 8/13/2019 panduan pondasi

    22/37

    Foundation Engineering

  • 8/13/2019 panduan pondasi

    23/37

    Foundation Engineering

  • 8/13/2019 panduan pondasi

    24/37

    Foundation Engineering

    6. Diaphragma walls

    Chang-Yu Ou:Deep excavation

  • 8/13/2019 panduan pondasi

    25/37

    Foundation Engineering

    6. Diaphragma walls

  • 8/13/2019 panduan pondasi

    26/37

    Foundation Engineering

    7. Freezing and injection

  • 8/13/2019 panduan pondasi

    27/37

    Foundation Engineering

    7. Freezing and injection

    Gravely soils under groundwater and waterproof layer ismissing or in very deep.

    Advantages:- Absolute waterproof- Other retaining structures are not neccesary- In any kind of soil (except injection clay)

    Disadvanteges:- Difficult technical facilities- Expensive- Long time defrost in case of freezing

  • 8/13/2019 panduan pondasi

    28/37

    Foundation Engineering

    8. Shotcrete method

    Excavation Nailing

    ExcavationReinforcement, shotcreteApplication field:

    Temporary or permanent retaining structure

    Retaininig wall

    Stabilization of slopes

    Repair retaining structures

  • 8/13/2019 panduan pondasi

    29/37

    Foundation Engineering

    Thickness of shotcrete (12-25 cm),

    8. Shotcrete method

    Reinforcment:

    oNetting,oReinforcing steel (1-2 layers),oHajbeton (steel, PE),

    oSteel tube,oSteel bar,

    oSteel nail, Instalation of nails:

    oHit,oScrewed-injected,oJetedoScrewed

  • 8/13/2019 panduan pondasi

    30/37

    Foundation Engineering

    Application field:

    8. Shotcrete method

    Cohesive soils,Gravely soils,

    Can not used:

    Soft cohesive soilsOrganic soils, turf,Loose gravely soilsFilling (rocks, ash)

    Advanteges

    CheapSim le facilitiesVariable formElastic structure

    Disadvanteges:

    . .Can not install in case of groundwater

    flowingDemages of public utilities

  • 8/13/2019 panduan pondasi

    31/37

    Foundation Engineering

    Procedure of designig:

    8. Design shotcrete excavation

    . e v s

    2. Geometry of excavation3. Stability analysis

    Sloping

    bearingcapacity

  • 8/13/2019 panduan pondasi

    32/37

    Foundation Engineering

    8. Design shotcrete excavation

    Compound

    failure

    Deep failure

    Outpulling

    Nail breakage

    Shotcrete

    breakage

  • 8/13/2019 panduan pondasi

    33/37

    Foundation Engineering

    8. Shotcrete method

  • 8/13/2019 panduan pondasi

    34/37

    Foundation Engineering

    Order of nailing

    8. Shotcrete qualification

    Outpull test

    Measure movmentsInclinometer Install points

    ShortcreteThicknessStrenght

  • 8/13/2019 panduan pondasi

    35/37

    Foundation Engineering

    Inclination of the wall: 1:8-1:10

    8. Geometry of Shotcrete excavation

    Tpus L/H

    DL/S

    d

    2/SScrewed-injected nailsin gravely soils

    0,5-0,8

    0,5-0,6 (4-8)10-4

    Hit nail in gravely soil 0,5--

    (13-0,6

    , ,19)10-

    Mantle rock, marl0,5-1

    0,15-0,2

    (1-2,5)10-4

    L: length of nails, H: depth of excavation, D: dimeter of, ,

  • 8/13/2019 panduan pondasi

    36/37

  • 8/13/2019 panduan pondasi

    37/37

    Foundation Engineering

    Thank You

    for your attention!