Paltinu Dam is located in Prahova County, Doftana River valley, downstream from its confluence with the valley Păltinoasa the keys named "heels." Because of the geomorphological conditions of the site difficult, was adopted version of a concrete dam with double curvature arch perimeter point. This solution involved the creation of a foundation base extended with a wing on the left side dish. This base allows a symmetrization section where the concrete dam itself and allows a better reception modules of elasticity of ROCE differences on the two slopes. It also allowed a better adaptation to base the local geological conditions by stopping altered rock zones. The plot of the foundation was reinforced by a veil of realities by sealing grout injections. Parabolic barrier between May and run to the left side and a concrete abutment, which contributes to a better cooperation with the slope of the dam. The dam has a height of 108 m above the foundation, the rate of dam crest is at elevation 654 ASL, total length of the dam crest is 455 m. For stabilization works have been executed by both sides to strengthen the anchoring tensioned cables. With all this work during the first filling of the lake, they found large infiltration under the cap, exceeding 150 l / s and displacement of the structure at the contact between the central and wing parabolic arc. As a result, various works were executed including adding additional sealing veil, enhancing the drainage system and cover the downstream part of the slope with concrete blocks left in increments of 6 -8 m, tensioned cables anchored in depth. With these measures, and the reaction stopped dam seepage and slope remained within acceptable limits.

Upload: diana-dia

Post on 06-Nov-2015

218 views

Category:

Documents


1 download

DESCRIPTION

Geography

TRANSCRIPT

Paltinu Dam is located in Prahova County, Doftana River valley, downstream from its confluence with the valley Pltinoasa the keys named "heels."Because of the geomorphological conditions of the site difficult, was adopted version of a concrete dam with double curvature arch perimeter point. This solution involved the creation of a foundation base extended with a wing on the left side dish. This base allows a symmetrization section where the concrete dam itself and allows a better reception modules of elasticity of ROCE differences on the two slopes. It also allowed a better adaptation to base the local geological conditions by stopping altered rock zones. The plot of the foundation was reinforced by a veil of realities by sealing grout injections. Parabolic barrier between May and run to the left side and a concrete abutment, which contributes to a better cooperation with the slope of the dam.

The dam has a height of 108 m above the foundation, the rate of dam crest is at elevation 654 ASL, total length of the dam crest is 455 m.For stabilization works have been executed by both sides to strengthen the anchoring tensioned cables.

With all this work during the first filling of the lake, they found large infiltration under the cap, exceeding 150 l / s and displacement of the structure at the contact between the central and wing parabolic arc. As a result, various works were executed including adding additional sealing veil, enhancing the drainage system and cover the downstream part of the slope with concrete blocks left in increments of 6 -8 m, tensioned cables anchored in depth.With these measures, and the reaction stopped dam seepage and slope remained within acceptable limits.Paltinu implementation works of the dam began in 1966, the dam was commissioned in 1971. A second phase of consolidation was carried out between 1976 to 1982.

Paltinu dam serves mainly to supply drinking water to municipalities and industrial plant in Campina and Ploiesti. Alternatively, the dam also provides water for irrigation of 9,000 ha in the meadow river area Bicoi-Prahova Ploiesti Ploiesti mound for river cleaningPaltinu dam is located on theDoftana River (Prahova)downstream of the confluence with thePltinoasa Riverin the gorges known as "La Tocile". The cross-section of the valley is assymetric. On the left bank, there is a terrace of around 100 m width. The base rock issandstonewithmarlstoneintercallations. The foundation rock has several faults and also has complex fractures.The DamEditThe height of the dam over foundation is 108.00 m, the crest elevation being 654 m above sea level. The total length of the dam crest is 455 m.Due to the difficult geological conditions of the site, the solution of an arch dam with double curvature set on a peripheric joint. This solution implied the creation of a foundation base extended with a parabolic wing on the west bank. This base allows a simetrisation of the cross-section in which the arch is located. The base also allowed the filling the areas with weak bedrock. The foundation was consolidated with cement injections. In order to increase stability, both abutments of the dam were consolidated with pre-stressed steel cables.Plan of Paltinu DamAdded byAfilCross section of Paltinu DamAdded byAfilDespite all the precautions taken, during the first filling of the reservoir, important water leaks, exceeding 150 l/s, could be assessed under the base as well as a shifting in the contact area between the central arch and the parabolic wing on the left bank. The structure was further consolidated by an additional range of cement injections and a cover of the downstream part of the left abutment by concrete blocks anchored by pre-stressed steel cables. Following these works the water leaks ceased and the shifts of the structure were kept within the acceptable limits.The construction of the dam started in 1966 and was completed in 1971. The additional consolidation was carried out between 1976 and 1982.