pak: national highway network development in balochistan … · 2018-05-02 · 2 engr. zubair ahmed...
TRANSCRIPT
Environmental Monitoring Report
Bi-Annual Environmental Monitoring Report (Up-Gradation, Widening & Improvement of National Highway N-70 from Qila Saifullah to Loralai and to Waigum Rud and National Highway N-50 from Zhob to Mughal Kot) (July ~ December 2017)
PAK: National Highway Network Development in
Balochistan Project - N-70 from Qila Saifullah to
Loralai and to Waigum Rud and N-50 from Zhob to
Mughal Kot
Prepared by National Highways Authority for the Asian Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.
(ii) In this report, "$" refers to US dollars. This Bi-Annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Bi-annual Environmental Monitoring Report
Project Number: (ICB-7A, 7B, 3C, 3D) (July ~ December 2017) Islamic Republic of Pakistan
Up-Gradation, Widening & Improvement of National Highway N-70 from Qila Saifullah to
Loralai and to Waigum Rud and National Highway N-50 from Zhob to Mughal Kot .
Package ICB-7A: Qila Saifullah to Loralai, (67.9 KM)
Package ICB-7B: Loralai to Waigum Rud, (50.375 KM)
Package ICB-3C: Zhob to Killi Khudae Nazar, (49KM)
Package ICB-3D: Killi Khudae Nazar to Mughal Kot, (32.44 KM)
Financed by: Asian Development Bank
For: National Highway Authority This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
Bi-Annual Environmental Monitoring Report July-December 2017
1
Bi-Annual Environmental Monitoring Report
July – December 2017
N-70 and N-50
NATIONAL HIGHWAY AUTHORITY
Minconsult International / ACE
(Pvt.) Ltd. Associates
(Design Review & Supervision
Consultants)
Bi-Annual Environmental Monitoring Report July-December 2017
2
List of Abbreviations
ADB Asian Development Bank
BMP Best Management Practices
BBS Behavior Based Safety
CAPA Corrective and Preventive actions
CBOs Community Based Organizations
CO Carbon monoxide
dB Decibel
DCP Dry Chemical Powder
DPO District Police Officer
DTR Daily Time Register
EC European Community
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPA Environmental Protection Agency
EPRM Environmental Progress Review Meeting
HSE Health, Safety and Environment
KM Kilometer
Leq Loudness equivalent
LTI Lost Time Injury
LTV Light Transport Vehicles
ND Not detectable
NEQS National Environmental Quality Standards
NGVS No guideline values
NHA National Highway Authority
NO2 Nitrogen dioxide
PAPs Project Affected Persons
ROW Right of Way
RWI Restricted Work Injury
SC Supervision Consultants
SIMOP Simultaneous Operation
SO2 Sulfur Dioxide
SSEMP Site Specific Environmental Management Plan
SWM Solid Waste Management
TDS Total Dissolved Solids
TRIR Total Recordable Injury Rate
TBT Tool Box Talk
PM Particulate Matter
PAPs Project Affected Persons
PPE Personal Protective Equipment
RD Running Distance
TRA Task Risk Assessment
WHO World Health Organization
Bi-Annual Environmental Monitoring Report July-December 2017
3
Table of Contents
Introduction...............………………………………………...………………………………...........4
Chapter 1 .............................................................................................................................. 6
Summary ............................................................................... Error! Bookmark not defined.
1.1 Construction Activities/ Work Progress: ....................................................................... 6
1.2 Project Organization: ................................................................................................... 6
1.3 Environmental, Health and Safety Management Team: ................................................ 7
1.4 Relationships with Contractors, Owners, Lenders: ....................................................... 7
Chapter 2 .............................................................................................................................. 8
Environmental Monitoring ..................................................................................................... 8
2.1 Noise and Vibrations: ................................................................................................... 8
2.2 Drinking Water Quality: ................................................................................................ 8
2.3 Waste Water Analysis: ................................................................................................. 8
2.4 Air Quality: ................................................................................................................... 8
2.5 Particulate Matter (PM10) ............................................................................................. 8
Chapter 3 .............................................................................................................................. 9
Environmental Management ................................................................................................. 9
3.1 Camp, Plants and Borrow Pits ..................................................................................... 9
3.2 Soil Erosion ............................................................................................................... 10
3.3 Dust /Air Emissions Monitoring .................................................................................. 10
3.4 Waste Management .............................................................................................. 11
3.4.1 Waste Water Management ................................................................................... 11
3.4.2 Solid Waste Management ..................................................................................... 11
3.5 Occupational Health and Safety Management ............................................................ 11
3.5.1 Emergency Preparedness and Response ............................................................ 11
3.5.2 Training of workers .............................................................................................. 12
3.5.3 Personal Protective Equipment’s ......................................................................... 18
3.5.4Site Visits/ Inspections .......................................................................................... 18
3.6 Corrective Action Plan:............................................................................................... 19
3.7 Security Measures ..................................................................................................... 21
3.8 Protected Areas ......................................................................................................... 21
3.9 Social and Cultural issues/ Grievance Redress Mechanism (GRM) ........................... 21
3.10 Record of labor deployed ......................................................................................... 24
3.11 Vehicles and Machinery Maintenance ...................................................................... 27
Annexure I: Photographic Record from July to December 2017 .......................................... 28
Annexure II: Summary of Borrow Pits ................................................................................. 37
Annexure III: Layout Plan of Base Camp ............................................................................. 42
Annexure IV: Environmental Monitoring .............................................................................. 45
Annexure V: Traffic Diversion Plans .................................................................................... 57
Bi-Annual Environmental Monitoring Report July-December 2017
4
1.0 Introduction
1.1 Work Packages
The environmental monitoring for the upgradation, widening and improvement of the National
Highways N-70 (Qila Saifullah – Loralai - Waigum Rud) and N-50 (Zhob - Mughal Kot) started
from the month of August 2016. The various work packages are as follows:
Item Section Package Length
(km) Contractor
1 Qila Saifullah to Loralai (N-70) ICB-7A 67.90 Umar Jan-XGHEC JV
2 Loralai to Waigum Rud (N-70) ICB-7B 50.38 Maqbool-Zarghoon JV
3 Zhob to Killi Khudae Nazar (N-50) ICB-3C 49.00 Limak-ZKB JV
4 Killi Khudae Nazar to Mughal Kot (N-
50) ICB-3D 32.44 Maqbool-Zarghoon JV
1.2 Project Proponent
The proponent of this project is the National Highway Authority (NHA), Ministry of
Communications of the Government of Pakistan. NHA has awarded the construction contracts
for the upgradation, widening and improvement of the N-70 (Package ICB-7A) to Umar Jan-
Xuchang Guangli (JV) and (Package ICB-7B) to Maqbool- Zarghoon (JV) and for N-50
(Package ICB-3C) to LIMAK- ZKB (JV) and (ICB-3D) Maqbool- Zarghoon (JV), herein after
referred to as ‘The Contractors’.
1.3 Design Review & Construction Supervision Consultants
The design review and supervisory consultancy work is awarded to Minconsult international Ltd.
(Malaysia) in association with Associated Consulting Engineers-ACE (Pvt.) Ltd. herein after
referred to as the ‘Consultant’ or the ‘Engineer’.
1.4 Summary of Findings
The construction works are currently in progress and all the Contractors have prepared and
submitted the Site Specific Environmental Management Plan (SSEMP) for each work package,
which has been approved by NHA and ADB.
For N-70 a total of 13 Affected Person Committees (APCs) and for N-50 a total 7 APCs for the
Grievance Redress Committee (GRC) were constituted. The Contractors have provided the
complaints registers in their main base camps. So far only a few major complaints have been
received and all have been addressed accordingly. There are some minor complaints but they
are being investigated and will be resolved amicably.
Bi-Annual Environmental Monitoring Report July-December 2017
5
All the Contractors have employed their Health, Safety and the Environment (HSE) Managers
who are regularly visiting the construction sites, workshops, plants, dumping sites and borrow
areas. The HSE Managers are regularly inspecting fire extinguishers, hand and power tools,
machinery, personal protective equipment (PPE) and the general housekeeping for the main
camps facilities and plants.
The HSE Managers also conducted the safety toolbox talks at camps, plants and active
construction sites. In the second half of the year 2017, the Contractors’ HSE Managers of N-70
delivered 38 sessions of safety toolbox talk whilst for N-50 23 similar training sessions were
conducted. All the contractors have provided a mini clinic/dispensary at their main camps as
well as an ambulance and a Paramedic.
The contractors have constructed temporary road diversions to keep the traffic moving during
construction works. These temporary main road diversions and access roads to borrow pits are
being regularly sprinkled with water using water bowsers. Flagmen at major road crossings and
diversions are provided to control traffic and prevent accidents between construction machinery
and other road users. Safety signboards at the constructions sites, plants, workshops and traffic
signboards at the service roads and diversions have been installed at strategic locations.
Earth materials for embankments are obtained from approved borrow pits at 500 m away from
the ROW, as well as from cutting areas. So far 56 borrow pits have been approved on N-70 and
on N-50 the total number of borrow pits are 23.
All the contractors have established their base camps for the residence of their site staff,
general workers and security personnel. They have also established their concrete batching
plants, stores, workshops, steel yards, diesel stations and materials testing laboratories. All
these base camps have been completed and fully operational.
Fire extinguishers are installed at all base camps. PPE’s are provided to workers working at
plants, workshops and construction sites; including safety helmets, masks, safety gloves and
high visibility vests. Construction workers and site personnel are regularly briefed about the
proper use of the PPE’s and their importance.
At the base camps, proper wastewater treatment and solid waste management is being
maintained as per the SSEMP. Wastewater is collected into septic tanks and disposed off into
soak away pits. Solid wastes are collected primarily in waste drums provided at strategic
locations, and then collected to waste collection points for segregation; the reusable and
recyclable materials are collected and the remaining wastes are disposed in the municipal solid
waste disposal sites.
Provision of treated drinking water is being maintained for all the workers and staff at site camps
and construction sites. Monitoring of the air, water and noise quality are being conducted
regularly as per the SSEMP. The quality values of the air, water and noise remained within the
permissible limits.
The overall occupational health and safety measures, implemented by the Contractors
remained reasonable and satisfactory. The general environmental conditions were found to be
Bi-Annual Environmental Monitoring Report July-December 2017
6
acceptable as per the approved SSEMP, but further improvements are still possible with regular
and serious monitoring.
Chapter 1
1.1 Work Progress
The physical work progress of the four construction contracts, at the end of December 2017, is
as follows:
Item Work Package Planned Progress (%) Actual Progress (%) Ahead (+) / Delay (-)
1 ICB-7A (N-70) 48.80 44.35 -14.45
2 ICB-7B (N-70) 50.41 44.90 -5.51
3 ICB-3C (N-50) 66.72 72.44 +5.72
4 ICB-3D (N-50) 50.31 52.89 +2.58
1.2 Project Organization (Site)
The following personnel head the project teams:
Item Name Position Organization Location
1 Engr. Noor Ul Hassan
GM Construction NHA, Quetta N-70
2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70
3 Major (R) Adnan Farukh Hassan Resident Engineer Minconsult/ACE N-70
4 Engr. Aqeel Ahmed Qazi Project Manager UJ-XGHEC (JV) N-70 (ICB-7A)
5 Engr. Riaz Ahmaed Kalo Project Manager MZ (JV) N-70 (ICB-7B)
6 Engr. Muhammad Shahid Khan GM Construction NHA, Quetta N-50
7 Engr. Zia Uddin Burki Project Director NHA, Quetta N-50
8 Engr. Ijaz Ahmad Resident Engineer Minconsult/ACE N-50
9 Engr. Khalil Jibran Project Manager LIMAK-ZKB (JV) N-50 (ICB-3C)
10 Mr. Naeem Ehsan Project Manager MZ (JV) N-50 (ICB-3D)
11 Engr. Azlan Ahmad Team Leader Minconsult/ACE N-70&N-50
12 Engr. Yunos Abdullah Sr. Highway Engineer Minconsult/ACE N-70&N-50
Bi-Annual Environmental Monitoring Report July-December 2017
7
1.3 Environmental, Health and Safety Management Team
The personnel at site who are involved with the monitoring of the environmental management
plans of the contractors are as follows:
Item Name Position Organization Location
1 Mr. Muhammad Qayyum Environmental Specialist
Minconsult/ACE N-70
2 Mr. Syed Zia Uddin HSE Manager MZ (JV) N-70 (ICB-7B)
3 Mr. Hidayat Ullah HSE Manager UJ-XGHEC (JV) N-70 (ICB-7A)
4 Mr. Zahid Ramzan HSE Manager LIMAK-ZKB (JV) N-50 (ICB-3C)
5 Mr. Fahad Ullah HSE Manager MZ (JV) N-50 (ICB-3D)
1.4 Relationship Between All the Parties
The overall relationship among the Contractors, Employer’s Representatives and the
Supervision Consultant’s staff, as well as the Funding Agency remained harmonious during the
reporting period.
Bi-Annual Environmental Monitoring Report July-December 2017
8
Chapter 2
2.0 Environmental Monitoring
The qualitative environmental monitoring is being carried out during construction activities and
verified that they are undertaken in compliance with the requirements set in the EIA/EMP and
Site Specific Environmental Management Plan (SSEMP).
2.1 Noise and Vibrations
Noise monitoring is conducted on a quarterly basis at different locations. Noise level results so
far show that most of the construction activities are being conducted within the permissible
noise limits. All machines that are producing noise beyond the threshold levels, such as
generator sets, are being isolated in order to reduce the noise level. To minimize the noise from
the construction vehicles, all machineries are periodically checked for their noise level and
notified for repairing and maintenance. The results of noise monitoring are attached as
Annexure IV.
2.2 Drinking Water Quality
At the contractors’ base camps, bottled water and water coolers are provided for drinking
purposes for all personnel. This water supply is also provided to workers at the construction
sites. For all other purposes, clean and treated water is provided through pipes from the local
water supply or pumped from wells.
2.3 Wastewater Treatment
Wastewater from washrooms and kitchens are collected and treated through septic tanks and
soakage pits at all the base camps. No wastewater is released directly into fields and irrigation
water channels from any base camps.
2.4 Air Quality
Ambient air quality monitoring is being carried out once in every four months during the
construction, as per the approved EMP.
2.5 Particulate Matter (PM10)
The particulate matter monitoring was started in the month of August 2017. The particulate
matter (PM10) monitoring done at different locations during the construction activities shows that
the level of PM10 are within the standards specified in the approved contract EMP.
Bi-Annual Environmental Monitoring Report July-December 2017
9
Chapter 3
3.0 Environmental Management
All the contractors have prepared and submitted their Site Specific Environment Management
Plan (SSEMP), which has been reviewed and approved by NHA and ADB. The SSEMP is being
implemented strictly at the construction sites.
3.1 Base Camps, Plants and Borrow Pits
The contractors have established their base camps at the following locations:
Item Work Package Contractor Location Area (m2) Distance to ROW (m)
1 ICB-7A (N-70) UJ – XGHEC (JV) Km 26+100 100,000 100 LHS
2 ICB-7B (N-70) MZ (JV) Km 113+900 81,000 900 LHS
3 ICB-3C (N-50) LIMAK-ZKB (JV) Km 38+000 85,000 200 LHS
4 ICB-3D (N-50) MZ (JV) Km 55+900 80,000 50 RHS
At the base camps the contractors have constructed offices, workers accommodations,
washrooms, workshops, steel yards and areas for materials storage, fuel tanks, mosques, first
aid facilities, recreational space and also facilities for the security personnel (FC). They have
also established a dispensary with paramedic staff on fulltime duty at the base camps.
Adequate and relevant first aid medicines and bandages are provided at these dispensaries.
Ground water is used as water for general purpose as well as for drinking after some basic
treatments.
All types of solid steel scrap metal from the steel yards and workshops are collected in
specifically marked bins and are shifted to scrap the yard. The scrap metal is stored and sold in
market when required. Kitchen and office solid wastes are collected in similar manner and sent
to the solid waste collection points (dustbins placed at various points). These solid wastes are
then collected for final disposal at designated places. As far as the matter of collection of used
oil is concerned it is being collected in fuel spill trays from the motor workshops and shifted to
liquid waste collection point on daily basis where these are stored in drums properly covered
with shed and ultimately sold out to oil dealers on quarterly basis or whenever required.
Wastewater generation and treatment, as per the requirements of IEE and the SSEMP, is
carried out at the base camps. All contractors have constructed septic tanks, soakage pit and
small retention manholes system.
The base camps are fenced and security check-posts are available at the entrance. The
kitchen, dining halls and residential of senior staff and labor staff are properly protected from
flies and mosquitoes and by providing steel gaze on windows.
Bi-Annual Environmental Monitoring Report July-December 2017
10
Emergency contact numbers, fire extinguishers and sand buckets are provided at the camp
offices, fuelling points, workshops and main stores etc. Mosques are also constructed at the
camps for staff and workers. Workshop area for vehicle maintenance is kept paved to avoid oil
contamination. Oil storage area is also paved and covered with shed. Generators are also
provided at the site.
Environmental Education and Awareness about safety measures and good housekeeping at
steel yard, store area, oil/chemical storage area, and kitchen site are done.
Plants & Workshops
Other facilities such as concrete batching plants, crusher plants as well as asphalt plants have
been erected at the sites. These plants have all been located away from populated areas to
reduce the impact on noise and dust pollutants. Mitigation measures like scrubbers and water
sprinklers have also been installed to reduce dust from the operations of these plants.
Borrow pits
The areas from where soil is being taken for the construction of embankment is called borrow
pits. The location and summary of the approved borrow areas is attached as Annexure-II. The
environmental impacts of borrow areas are under observation during soil excavation,
transportation and restoration. Designated routes are being used during soil transportation.
Service roads and adjacent roads used for the transportation of soil are checked regularly, and
if any damage were caused to the public road, it shall be rectified.
3.2 Soil Erosion
This environmental impact is due to the road construction activities. It occurs due to the clearing
and excavation activities at the project site, as these activities are leading to the soil erosion, or
alteration of soil quality resulting from removal of the topsoil at the site, to some extent.
Mitigation measures adopted to minimize soil erosion include:
• The depth of the borrow pits are being maintained so that the sides of the excavation have a
slope not steeper than 1 into 4.
• Soil erosion along the borrow pits is being monitored to prevent / mitigate impacts on
adjacent lands.
• Borrow pits after excavation of soil will be rehabilitated as per the SSEMP.
3.3 Dust /Air Emissions Monitoring
The construction activities generate dust due to excavation and filling works. Diesel and other
petroleum products used for the operation of construction machinery and transportation
equipment also cause air pollution. The impacts generated from such activities are of certain
significance and proper mitigation measures are being practiced. The workforce always wears
personal protective equipment (PPE) including dust masks, to minimize health hazards. Vehicle
maintenance is regularly done to minimize the impacts of air pollution on the surrounding
environment. Dust suppression is being maintained by sprinkling water on the service road,
diversions and access routes / approach roads to the borrow areas.
Bi-Annual Environmental Monitoring Report July-December 2017
11
3.4 Waste Management
3.4.1 Waste Water Management
Wastewater is managed as per the SSEMP; at base camps construction of septic tanks and
soakage pits have been completed in the month of November 2016, respectively therefore
wastewater is managed inside the septic tanks and soakage pits.
3.4.2 Solid Waste Management
All the solid waste generated at the base camps is being collected in waste bins. Solid waste
after collection is being segregated, the recyclable and reusable are collected and the remaining
wastes are disposed of properly at the municipal solid waste dumping sites.
3.5 Occupational Health and Safety Management
The construction activities have certain impacts on the occupational and public health. At the
work site hazards are eliminated/ minimized through engineering controls and administrative
controls, if the controls do not eliminate the hazards appropriate PPEs are being provided to the
workers. Workers and staff are being trained and equipped with the appropriate Personnel
Protective Equipment’s (PPEs) as per their job need.
3.5.1 Emergency Preparedness and Response
Emergency Response preparedness and response plan has been designed as per details given
in the approved SSEMP and being implemented accordingly. The following are the contact
numbers of focal / responsible personnel of the project.
A. Umar Jan – XGHEC (JV) ICB-7A (N-70)
Item Designation / Department Name / Location Contact Details
1 Project Manager Engr. Aqeel Ahmed Qazi 0333-7092420
2 Deputy Project Manager (1) Mr. Muhammad Arshad Shaheen 0333-6687755
3 Deputy Project Manager (2) Mr. Yahiya Khan 0336-1205250
4 HSE Manager Mr. Hidayat Ullah 0313-8235025
5 Paramedic / First Aider Dr. Shahbaz 0345-8309130
6 Administration Manager Mr. Liaqat 0333-4088468
7 Ambulance Driver Mr.Rehmat Ullah 0333-7039342
8 Fire Department Loralai 16
9 Frontier Corps (FC) Loralai 0333- 1391836
10 Police Department Loralai 16
B. MZ (JV) ICB-7B (N-70)
Item Designation / Department Name / Location Contact Details
1 Project Manager Engr. Riaz Ahmed Kalo 0332-7887815
2 Deputy Project Manager Mr. Naeem Khan 0333-5988237
Bi-Annual Environmental Monitoring Report July-December 2017
12
3 HSE Manager Mr. Syed Zia uddin 0333-1564580
4 Paramedic / First Aider Mr. Naseeb Ullah 0340-8382665
5 Administration Manager Mr. Abdul Ali 0333-1419184
6 Ambulance Driver Mr. Sher Muhammad 0333-8321291
C. LIMAK – ZKB (JV) ICB-3C (N-50)
Item Designation / Department Name / Location Contact Details
1 Project Manager Mr. Shafique 0344-39223814
2 Deputy Project Manager Mr. Younis 0343-2515056
3 Camp In Charge Mr.Hikmat Shah 0345-9842142
4 Structure In Charge Mr.Shahbaz Khalid 0300-7024854
5 Base Camp (workshop) Mr.Gulfam 0331-2558575
6 Bridge Engineer Mr.Zeeshan Azeem 0344-2148808
7 Asphalt Laying Foreman Mr. Arshad 0333-6576914
8 Asphalt Plant In charge Mr.Azmat Ullah 0336-325333
9 Concrete Batching Plant in Charge Mr. Azhar 0347-3390006
10 FC Militia Wing 52 Mr. Rab Nawaz 0345-3271948
D. MZ (JV) ICB-3D (N-50)
Item Designation / Department Name / Location Contact Details
1 Project Manager Mr. Rana Naeem Ehsan 0346-2005556
2 HSE Manager Mr. Fahad Ikram 0342-7534493
3 Construction Manager Mr. Muhammad Ilyas 0341-5207217
4 Manager Operation Mr. Ashfaq Ahmad 0344-8105030
5 First Aider Mr. Muhammad Azeem 0343-0798793
6 Administration Manager Mr. Ulusyar Khan 0348-8533378
7 Ambulance Driver Mr. Bismillah 0343-9787556
8 Fire Department Mr. Muhammad Jamshaid 0341-1730580
9 Frontier Corps (FC) Mr. Usman Hawaldar 0346-8125893
10 Police Department Mr. Muhammad Iqbal (SHO) 0346-3218806
3.5.2 Training of Workers
Workers are continuously being trained in order to minimize the risks and impacts of occupational and
environmental hazards. Toolbox talks have been regularly conducted and will be conducted in future. All
Bi-Annual Environmental Monitoring Report July-December 2017
13
the employees are briefed regarding occupational hazards, risks and safety measures. The following are
the details of the safety toolbox talks and training that have been delivered in the second half of the year
2017:
Umar Jan- XGHEC (JV) Lot-1 (N-70)
Sr.
No
Title of the
training
Date
Trainer Site Location Contractor
Day Month Year
1
Work
Safety
Training
14 07
2017
Hidayat
Ullah
Camp Site Camp site
UMARJAN-
XUCHANG
GAUNGLI (JV)
2
Work
Safety
Training
21 07
2017
Hidayat
Ullah
Camp Site Camp Site Sub-contractor
3 Safety 10 08
2017
M.
Qayyum
Camp Site Camp Site UMARJAN-
XUCHANG
GUANGLI (JV)
4 Safety 17 08
2017
Hidayat
Ullah
Camp Site Camp Site Sub-contractor
5 Road
safety 09 09
2017
Hidayat
Ullah
Camp Site Camp Site UMARJAN-
XUCHANG
GUANGLI (JV)
6
Flagman
Training 26 09
2017
Hidayat
Ullah
Construction
site
Construction
site
UMARJAN-
XUCHANG
GUANGLI (JV)
7
Flagman
Training 02 10
2017
Hidayat
Ullah
Construction
site
Construction
site
UMARJAN-
XUCHANG
GUANGLI (JV)
8 Flagman
Training 05 10
2017
Hidayat
Ullah
Construction
site
Construction
site
UMARJAN-
XUCHANG
GUANGLI (JV)
9 Tool Box
Talk 14 10
2017
Hidayat
Ullah
Construction
site
Construction
site
Sub-contractor
10 Tool Box
Talk 26 10
2017
Hidayat
Ullah
Construction
site
Construction
site
UMARJAN-
XGHEC (JV)
Bi-Annual Environmental Monitoring Report July-December 2017
14
Sr.
No
Title of the
training
Date Trainer Site Location Contractor
11
General
Safety
Training
02 11
2017
Hidayat
Ullah
Construction
site
Construction
site
UMARJAN-
XUCHANG
GAUNGLI (JV)
12
Defensive
Driving
Training
11 11
2017
Ahmed
Hassan
Construction
site Construction
site
Sub-contractor-
13 HSE
Training 23 11
2017
Mr.
Qayyum
Camp Site Camp site
Camp Office
UMARJAN-
XUCHANG
GUNGLI (JV)
14 Tool Box
Talk 07 12
2017
Hidayat
Ullah Construction
site
Camp site
Camp Office
Sub-contractor
15
Fire
Fighting
Training
15 12
2017
Hidayat
Ullah
Construction
site
Construction
site
Sub-contractor
Maqbool- Zarghoon (JV) Lot-2 (N-70)
Sr.
No
Title of the
training
Date
Trainer Site Location Contractor
Day Month Year
1 Solid waste 05 07 2017 Syed Zia
Uddin Camp Site
Conference
Hall
MAL-ZEPL
(JV)
2
Environment
Management
System
12 07 2017
Qayyum
Khan Camp Site Conference
Hall
MAL-ZEPL
(JV)
3
Environment
Management
System
20 07 2017 Syed Zia
Uddin
Camp Site
Conference
Hall
MAL-ZEPL
(JV)
4 Work Safety
Training
28
07 2017 Syed Zia
Uddin Site
Working
area
MAL-ZEPL
(JV)
5 Loading
Unloading 07 08 2017
Syed Zia
Uddin Site
Working
area
MAL-ZEPL
(JV)
6 Work Safety
Training 15 08 2017
Syed Zia
Uddin Site
Working
area
MAL-ZEPL
(JV)
Bi-Annual Environmental Monitoring Report July-December 2017
15
Sr.
No
Title of the
training
Date Trainer Site Location Contractor
7 Welding
Safety 17 08 2017
Syed Zia
Uddin Camp Site Workshop
MAL-ZEPL
(JV)
8 Chemicals
Handling 19 08 2017
Qayyum
Khan Camp Site Lab
MAL-ZEPL
(JV)
9 Chemicals
Handling 22 08 2017
Syed Zia
Uddin Camp Site Lab
MAL-ZEPL
(JV)
10 Confined
Space Entry 09 09 2017
Syed Zia
Uddin
Camp Site Camp Site MAL-ZEPL
(JV)
11 Work Safety 14 09 2017 Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
12
Flagman
Training 22 09 2017
Syed Zia
Uddin Camp Site Workshop
MAL-ZEPL
(JV)
13 Chemicals
Handling 28 09 2017
Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
14 Crane Safety 10 10 2017 Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
15 Lifting Safety/
Induction 22 10 2017
Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
16 Housekeeping 05 11 2017
Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
17 Road safety 10 11 2017 Syed Zia
Uddin Camp Site Camp Site
MAL-ZEPL
(JV)
18 Tool Box Talk 12 11 2017 Syed Zia
Uddin Camp Site Camp site
Sub-
contractor
19 Tool Box Talk 13 11 2017 Syed Zia
Uddin Camp Site Camp site
MAL-ZEPL
(JV)
20
General
Safety
Training
18 11 2017 Syed Zia
Uddin Camp Site
HSE
Training Hall
Camp Office
MAL-ZEPL
(JV)
Bi-Annual Environmental Monitoring Report July-December 2017
16
Sr.
No
Title of the
training
Date Trainer Site Location Contractor
21
General
Safety
Training
19 11 2017 Syed Zia
Uddin Camp Site Camp site
MAL-ZEPL
(JV)
22
Scaffolding
Safety
Training
25 11 2017 Syed Zia
Uddin Camp Site
HSE
Training Hall
MAL-ZEPL
(JV)
23 Driving
Training 01 12 2017
Syed Zia
Uddin Camp Site
HSE
Training Hall
MAL-ZEPL
(JV)
Limak – ZKB (JV) Lot-1 (N-50)
Sr. No Date Topics Participants Delivered By
1 04/07/2017 Electrical hazard 18 Environmental
Engineer (EE)
2 6/07/2017 Hot stress 26 EE
3 8/07/2017 Ladder inspection and safety 22 EE
4 11/07/2017 Flammable chemical fire
prevention (asphalt plant) 18 EE
5 15/07/2017 Summer driving 19 EE
6 19/07/2017 A flood of danger 17 EE
7 23/07/2017 Slip, trip and fall 18 EE
8 26/07/2017 Handling flammable liquid 16 EE
9 02/08/2017 Driving, PPEs, speed limit
controls 28
Environmental
Engineer (EE)
10 05/08/2017 Management Of Heavy
Equipment 16 EE
11 10/08/2017 Safety measures 22 EE
Bi-Annual Environmental Monitoring Report July-December 2017
17
12 12/08/2017 Usage of Firefighting techniques 18 EE
13 17/08/2017 Health and Safety 19 EE
14 19/08/2017 First aid Practices 22 EE
15 24/08/2017 Awareness about cleanliness’
and good housekeeping 14 EE
16 28/08/2017 Usage of PPEs, safety measures 26 EE
17 03/09/2017 Heavy Equipment Movement
28
Environmental
Engineer (EE)
18 05/09/2017 Poor Working Condition
17
EE
19 9/09/2017 Emergency Response Plan
21
EE
20 12/09/2017 Water Sprinkling
44
EE
21 15/09/2017 Waste Management
33
EE
22 18/09/2017 Poor Lightening
14
EE
23 21/09/2017
PPEs Implementation
34
EE
24 4/10/2017 Housekeeping 30 Environmental
Engineer (EE)
25 7/10/2017 Implementation of PPEs 56 EE
26 12/10/2017 Snake Bite 22 EE
Bi-Annual Environmental Monitoring Report July-December 2017
18
27 14/10/2017 Hot Work 15 EE
28 17/10/2017 Work at Height 21 EE
29 20/10/2017 Site HSE Rules 21 EE
30 23/10/2017 Implementation of PPEs 27 EE
31 3/11/2017 Work at Height 28 (EE)
32 5/11/2017 Heavy Equipment Movement 17 EE
33 8/11/2017 Poor Working Condition 21 EE
34 11/11/2017 Emergency Response Plan 23 EE
35 16/11/2017 Water Sprinkling 44 EE
36 19/11/2017 Waste Management 33 EE
37 23/11/2017 Poor Lightening 14 EE
38 26/11/2017 Excavation 22 EE
3.5.3 Personal Protective Equipment (PPE)
The workers are forced to wear their PPE for their safety at work. They have been told to wear safety
helmets, safety shoes, hand gloves, dust mask etc. and other necessary protective equipment while
working at site, plants, workshops and other construction areas as per their job requirements.
3.5.4 Site Visits / Inspections
The Consultant Environment Specialist is visiting the active construction sites, camps, plants, workshops,
and borrows pits along with the Contractor HSE Managers. Issues and non-compliances observed are
conveyed to the Contractor in writing and verbally and are also discussed in the fortnightly coordination
meetings with the Contractors. The Contractor HSE Managers are also visiting construction sites, camps,
plants and borrows pits; inspects work sites, welfare facilities, PPEs etc. and also deliver toolbox talks.
Workers have been trained to report near misses and take preventive and corrective actions as
envisaged by HSE Managers.
Bi-Annual Environmental Monitoring Report July-December 2017
19
3.6 Corrective Action Plan
Action Plan Status up to December 2017 (N-70)
Item Non-Compliance Mitigation Measures Status
01
Installation of safety and
traffic sign boards at lot-
1 & 2
Safety and traffic signboards have been installed at
plants, campsite, and workshop. Done
02
Installation of safety and
traffic sign boards at
Lot-1 & Lot-2
Safety and traffic signboards have been installed at
service road. Done
04
First aid facility at
Garang Cutting Area
Lot-1
First aid facility has been provided Done
05 PPEs at Lot1&2 Earplug not worn by operator in plant room. Done
06 First Aid boxes at Lot-
1&2 Items in First Aid box were not complete. Done
07 Workers
accommodation at Lot-1
for sub-contractor
Accommodation with electricity, beds facilities have
been provided to labor Done
08 Air Emission (Lot1&2)
Air emission, noise level, drinking water analysis,
wastewater has assured through self-calibration of the
instrument.
Done
09 PPEs Subcontractor staff working without safety shoes. Done
10 Training Subcontractor staff, need more Training and awareness
is imperative regarding HSE understanding Done
Action Plan Status December 2017 (N-50).
SR.
NO. ISSUES CORRECTIVE ACTION STATUS
1. Safety Issue Sufficient amount of PPEs have been provided at all
construction sites. Compliance
2. Housekeeping Best housekeeping at both camps site, construction sites
have been ensured. Compliance
3. First aid facility First aid center is fully functional at labor campsite. MBBS
Doctor and paramedic is available during day times. Compliance
Bi-Annual Environmental Monitoring Report July-December 2017
20
Moreover first aid box has provided at construction sites.
4. Gardening of Camp
site
Two Gardner has been hired by the Contractor that shall
take care of all the green areas both in labor and main
camp.
Compliance
5. Provision of HSE Staff
HSE Manager, I/C HSE, Environmental officer, HSE officer,
Trainee Engineer, HSE Supervisors, HSE Assistant and
Flagmen are available at site.
Compliance
6. Fire Safety
Fire extinguishers have been provided at all construction
sites, construction sites, office block area and residential
areas.
Compliance
7. Safe Drinking water Safe drinking water is provided to all project personnel’s
working at construction sites and camps area. Compliance
8. Display of safety sign
boards
Safety signboards including warning and informatory have
been erected at camp areas, site facilities and construction
sites. Moreover speed limit signboards are also erected at
diversions and along the road.
Compliance
9. TBTs / Training on
HSE
TBTs and HSE trainings have been conducted by HSE
Supervisors at all construction sites and camp areas. Compliance
10. Water Sprinkling
Water sprinkling is being ensured at all construction sites,
construction sites, site facilities, camp areas and access
routes.
Compliance
11. Washing Facility The Contractor has constructed washing facility in labor
camp. All the employees are facilitating from the services. Compliance
12. Concrete pad Concrete pad has constructed at filling station to avoid any
kind of oil spillage or soil contamination. Compliance
13. Construction of
walkways
Walkways have been constructed in both officer and labor
camp. Walkways are also being maintained in the
supervision of camp boss.
Compliance
14. Provision of Waste
Collection drums
Waste collection drums have been provided at all
construction sites, site facilities area, labor and main camp
to ensure proper housekeeping and waste management.
Compliance
15. Dust Abatement Plan
Three water bowsers are in continuous working at site that
ensured the strict implementation of dust abatement plan
according to the water sprinkling frequency chart.
Compliance
Bi-Annual Environmental Monitoring Report July-December 2017
21
3.7 Security Measures
For the security of employees armed Frontier Corps (FC) and contractors’ armed private security
personnel are deputed. Currently more than 200 security personnel are on duty including 39 private
security guards are deputed on the Contractors’ base camps at Qila Saifullah-Loralai-Waigum Rud (N-70)
and Zhob-Mughal Kot Road (N-50). The FC personnel also escort the Malaysian expatriates consultant
whenever they travel to the construction sites and other locations. Moreover at the main gate of base
camps barriers are placed to prevent unauthorized tress passing. Entry and exit record of all vehicles and
visitors / employees are also maintained at both base camps. Security cameras (CCTV) are also installed
and functional at the base camps.
3.8 Protected Areas
There are no protected areas such as wildlife sanctuaries, game reserves, national parks, and
archaeological, historical or cultural heritage sites in the projects’ neighborhoods. Therefore, no impact is
envisaged.
3.9 Social and Cultural Issues / Grievance Redress Mechanism (GRM)
Grievance Redress Mechanism (GRM) is institutions, instruments, methods and processes by which a
resolution to a grievance is sought and provided. People adversely affected (or about to be affected) by a
development project will raise their grievances and dissatisfactions about actual or perceived impacts in
order to find a satisfactory solution. Some grievances may arise during the project design and planning
stage, while others may come up during project implementation. Not only should affected persons (APs)
be able to raise their grievances and be given an adequate hearing, but also satisfactory solutions should
be found that mutually benefit both the APs and the project.
Currently the Contractor has provided complaint registers in all camps and complaints are duly registered
and redressed. In the reporting period few of the complaint received.
Consultation sessions are being arranged from time to time to improve the environmental conditions of
the project area. The complaints/ grievances received are noted/ recorded in the complaint registers at
camps and are being redressed accordingly. Record of the grievances received and redressed is below.
Bi-Annual Environmental Monitoring Report July-December 2017
22
Qila Saifullah-Loralai-Waigum Rud (N-70)
Sr.
No.
Date Complainant Name
Address/Contacts
Complain Action Taken Remarks
1 29-11-17 Ihsan ullah RD=97+100
TO 97+700
Road according to
drawing was curved to
left side, so said
person said it lies in
our land
Refer to PD office
through formal letter In progress
2 05-10-17 Daulat khan RD=95+600
Vehicles are very
speed in diversion,
which is near to his
house.
In this case, made
two-speed breaker
in the diversion,
which was near to in
house.
Don
03 18-09-17 Malik Aslum
RD=105+000 Dust issue
Resolved by
increasing water
browsing
Resolved
04 12 -08 -17 Abdul Jabbar
RD=88+700
On side while
removing of the trees
of said person, But he
did not allow us due to
No. of trees were
written less than
actual, so did not
receive the cheque.
According to this
case letter was
written to GM and
forwarded
Don
05 10 -07 -17 Muzamill Khan RD=
115+300
Shifted the culvert for
water transferring to
the road other side for
watering of trees.
Application
forwarded to project
director for approval
Don
Bi-Annual Environmental Monitoring Report July-December 2017
23
Zhob-Mughal Kot (N-50)
Sr.
No.
Date Complainant Name
Address/Contacts
Complain Action Taken Remarks
1 05-07-2017
Maiva Khan S/o
Wazir Khan
Manikhawa
RD= 14+200 Km
Due to excavation for
culvert, the excavated
material is dumped
into his grapes garden
Dumping material
has been removed
from grapes garden
Resolved
2 18-07-2017
Umar Khan S/o Hunar
Khan
Khawarena
RD= 46+300
Due to Heavy
machinery dust is
generated near crush
plant
Sprinkling is done to
Suppress the dust.
Water sprinkling is
done twice a day to
suppress the dust or
as per requirement
Resolved
3 2-08- 2017
Noor Ullah S/o Juma
Khan
RD=12+300
Dust generation is
high in cutting area
near grapes gardens
Water sprinkling is
being done twice a
day to Suppress the
dust
Resolved
22-08-2017
Alamgir Khan S/o Noor
Dad Khan
Passenger
Diversion Slope is not
good and heavy
vehicles could slip and
accident can occur
Diversion Slope has
been a changed and
heavy vehicle now
passing easily.
Resolved
Bi-Annual Environmental Monitoring Report July-December 2017
24
3.10 Records of Labor Deployed
A. Employees of UJ-XGHEC at ICB-7A (N-70)
Sr. No.
Position Qty. Sr. No.
Position Qty.
1 Project Manager 1 21 Drivers 17
2 Deputy Project Manager 2 22 Dumper Drivers 34
3 Materials Engineer 1 23 Gardeners 1
4 Administrative Manager 1 24 Inventory Keepers 3
5 Construction Engineer 1 25 Roller Operators 16
6 Field Manager 1 26 Grader Operators 10
7 HSE Manager 1 27 WT Operators 16
8 Surveyors 7 28 Grader Operator Helpers 10
9 Surveyor Helpers 14 29 Dumper Truck Helpers 26
10 Mechanical Engineer 0 30 Transit Mix Operator 5
11 Mechanics 4 31 Assistant Mechanics 7
12 Assistant Accountants 3 32 Welders 2
13 Masons 19 33 Security Guards 50
14 Laborers 92 34 Generator Operator 4
15 Plant Operators 4 35 Electricians 3
16 Foreman 8 36 Sweepers 5
17 Security officers 1 37 Fuel Man 5
18 Auto-Cad Operators 3 38 Cook 5
19 Trainee Site Engineers 4 39 Office Boys 6
20 Laboratory Helpers 8 40 Coordinators 1
Sub-Total 175 Sub-Total 216
Bi-Annual Environmental Monitoring Report July-December 2017
25
B. Employees of Maqbool-Zarghoon (JV) ICB-7B (N-70)
Sr. No.
Position Qty. Sr. No.
Position Qty.
1 Project Manager 1 21 Drivers 22
2 Deputy Project Manager 1 22 Dumper Drivers 25
3 Materials Engineer 1 23 Laboratory Helpers 7
4 Administrative Manager 1 24 Inventory Keepers 5
5 Construction Engineer 3 25 Roller Operators 14
6 Field Manager 2 26 Grader Operators 12
7 HSE Manager 1 27 WT Operators 9
8 Surveyors 7 28 Grader Operator Helpers 4
9 Surveyor Helpers 22 29 Site Engineers 26
10 Mechanical Engineer 1 30 Transit Mix Operator 7
11 Mechanics 8 31 Assistant Mechanics 12
12 Assistant Accountants 2 32 Welders 3
13 Masons 20 33 Security Guards 60
14 Laborers 89 34 Generator Operator 2
15 Plant Operators 4 35 Electricians 2
16 Foreman 7 36 Sweepers 3
17 Security officers 1 37 Fuel Man 5
18 Auto-Cad Operators 3 38 Cook 10
19 Trainee Site Engineers 4 39 Office Boys 6
20 Laboratory Helpers 8 40 HSE 6
Sub-Total 176 Sub-Total 240
Bi-Annual Environmental Monitoring Report July-December 2017
26
C. Employees of LIMAK-ZKB (JV) ICB-3C (N-50)
Sr. No.
Position Qty. Sr. No.
Position Qty.
1 Project Manager 1 12 Laboratory Staff 19
2 Deputy Project Manager 1 13 Mechanical staff 14
3 Structure Engineer 5 14 Machine Operators & Helpers / HTV Drivers & Helpers
228
4 Materials Engineer 1 15 LTV Drivers 50
5 Quantity Surveyor 1 16 Batching Plant Staff 9
6 CAD Operator 1 17 Asphalt Plant Staff 9
7 Site Foreman / Supervisors 18 18 Office Boys 7
8 Accounts Staff 3 19 Crusher Plants Staff 26
9 Surveyor Helpers 39 20 Security Guards 26
10 Environmental / Safety Staff 7 21 Skilled & Unskilled Labors 410
11 Office Staff 8
Sub-Total 85 Sub-Total 798
Bi-Annual Environmental Monitoring Report July-December 2017
27
D. Employees of Maqbool-Zarghoon (JV) ICB-3D (N-50)
Sr. No.
Position Qty. Sr. No.
Position Qty.
1 Project Manager 1 21 Drivers 20
2 Manager Operation 1 22 Dumper Drivers 40
3 Materials Engineer 1 23 Gardeners 1
4 Administrative Manager 1 24 Inventory Keepers 3
5 Construction Manager 1 25 Roller Operators 20
6 Field Manager 1 26 Grader Operators 15
7 HSE Manager 1 27 WT Operators 18
8 Surveyors 7 28 Grader Operator Helpers 15
9 Surveyor Helpers 14 29 Dumper Truck Helpers 30
10 Mechanical Engineer 0 30 Transit Mix Operator 7
11 Mechanics 4 31 Assistant Mechanics 7
12 Assistant Accountants 3 32 Welders 5
13 Masons 19 33 Security Guards 40
14 Laborers 105 34 Generator Operator 4
15 Plant Operators 6 35 Electricians 6
16 Foreman 8 36 Sweepers 5
17 Security officers 1 37 Fuel Man 5
18 Auto-Cad Operators 3 38 Cook 5
19 Trainee Site Engineers 4 39 Office Boys 6
20 Laboratory Helpers 10 40 Coordinators 1
Sub-Total 201 Sub-Total 253
3.11 Vehicles and Machinery Maintenance
Vehicles are periodically checked for their maintenance requirements. For this purpose, noise
and visual observation of vehicle exhaust emission is being done. Moreover record for the change of
Mobile Oil for vehicles is also being maintained. These things will help to assess vehicle efficiency and
need for its repair. Record is being maintained at workshops.
Bi-Annual Environmental Monitoring Report July-December 2017
28
Annexure I: Photographic Record from July to December 2017 (N-50 & N-70)
Laying ACBC Laying of ACBC
Laying of Aggregate Base Course Workers Wearing PPE for Laying of ACBC
Bi-Annual Environmental Monitoring Report July-December 2017
29
Wearing of PPE Being Complied at Site of Both N-50 & N-70
Bi-Annual Environmental Monitoring Report July-December 2017
30
Signboards and Traffic Diversion Signage at N-50 & N-70
Bi-Annual Environmental Monitoring Report July-December 2017
31
Signage and Traffic Diversion Cones at N-50 & N-70
Bi-Annual Environmental Monitoring Report July-December 2017
32
Lot-2
Water Bowsers at Work for Dust Control at N-50 & N-70
Bi-Annual Environmental Monitoring Report July-December 2017
33
Visits of ADB & NHA Officials to N-50 & N-70
Dispensaries at Base Camps and Tool Box Meeting
Photographic Record from July to December 2017 (N-50 & N-70)
Bi-Annual Environmental Monitoring Report July-December 2017
34
Conducting the Tool Box Talk on Site
Bi-Annual Environmental Monitoring Report July-December 2017
35
Compliance with SSEMP at Site and Base Camps of N-50 & N-70
Bi-Annual Environmental Monitoring Report July-December 2017
36
Traffic Signage
Bi-Annual Environmental Monitoring Report July-December 2017
37
Annexure II: Summary of Borrow Pits
Borrow Areas
Borrow materials are being taken from recommended and approved borrow areas. The
recommended pits for borrowing shall be rehabilitated as soon as excavation of material is finished. The
rehabilitation activity and process will take into consideration the aesthetics of the area and safety of
people, animals and community. Until now no agricultural fields, which exist near to the project sites, are
used as borrow pits.
Restoration of Borrow Pits
Before extraction commences, licenses and permits shall be checked and limits of disturbance
and/or clearing will be clearly marked out on the site before any ground disturbing activity takes place.
This usually requires the sides of the pit to be reshaped with gentle safe grades. All disturbed areas
associated with borrow pits are part of the restoration plan.
Approved Borrow Areas
Location Map of Borrow Pits (N-70, Lot-1)
Bi-Annual Environmental Monitoring Report July-December 2017
38
Location Map of Borrow pits (N-70, Lot-2)
Bi-Annual Environmental Monitoring Report July-December 2017
39
List of Approved Borrow Areas at Lot-1 (N-50)
Sr. No. Borrow
No Location Area L/S or R/S Remarks
1 37 RD 37+660 100 R/S
2 38 RD 3+000 70 L/S
3 39 RD 3+940 50 L/S
4 40 RD 4+300 100 R/S
5 41 RD 29+500 80 L/S
6 42 RD 39+900 60 R/S
7 43 RD 46+123 20 L/S
8 44 RD 46+300 40 R/S
Bi-Annual Environmental Monitoring Report July-December 2017
40
Bi-Annual Environmental Monitoring Report July-December 2017
41
Bi-Annual Environmental Monitoring Report July-December 2017
42
Annexure III: Layout Plan of Base Camps
Base Camp Lay-out Plan of UJ- XGHEC (JV) Lot-1 (N-70)
Bi-Annual Environmental Monitoring Report July-December 2017
43
Base Camp Lay-out Plan of Maqbool-Zarghoon (JV) Lot-2 (N-70)
Bi-Annual Environmental Monitoring Report July-December 2017
44
Base Camp Layout Plan of Maqbool-Zarghoon (JV) Lot-2 (N-50)
Bi-Annual Environmental Monitoring Report July-December 2017
45
Annexure IV: Environmental Monitoring Results for July-Dec. 2017
1. Noise Level Measurements (N-70)
S.NO Type Of Vehicle Location Noise Level PPEs Remarks
1 Grader N-70 44 dB safety shoes, jacket
2 Roller N-70 38 dB safety shoes, jacket
3 Excavator Chain N-70 70 dB safety shoes, jacket
4 Excavator Tire N-70 35 dB safety shoes, jacket
5 Dozer N-70 74 dB safety shoes helmet jacket air plug
6 Loader N-70 38 dB safety shoes, jacket
7 Concrete Mixture N-70 33 dB safety shoes, jacket
8 Crain N-70 37 dB safety shoes helmet jacket
9 Paver N-70 35 dB safety shoes helmet jacket Mask
10
Water Pump chef
engine N-70 84 dB safety shoes helmet air plug
11
Concrete
Vibrator N-70 76 dB safety shoes helmet jacket air plug
12 Water Tanker N-70 44 dB safety shoes
13 Trailer N-70 40 dB safety shoes
14 Dumper N-70 42dB safety shoes
15 PTR Roller N-70 36 dB safety shoes, jacket
16 Tandem Roller N-70 33 dB safety shoes, jacket
17 Compressor
N-70 77 dB
safety shoes helmet air plug, jacket
Mask
18 Diesel Tank N-70 35 dB coverall safety shoes helmet jacket
19 Transit Mixture N-70 33 dB safety shoes
20 Tractor N-70 66dB safety shoes, jacket
21 Diesel point N-70 28 dB coverall safety shoes helmet jacket
22 Crush Plant
N-71 84 dB
coverall safety shoes helmet jacket air
muff
23 Asphalt plant N-70 80 dB coverall safety shoes helmet jacket
24 Batching Plant N-70 55 dB
coverall safety shoes helmet jacket air
muff Mask
25 Workshop N-70 NIL coverall safety shoes helmet jacket
26 Site Labor N-70 NIL safety shoes helmet jacket
27 Site staff N-70 NIL safety shoes helmet jacket
28 structure labor N-70 NIL
coverall safety shoes helmet jacket
gloves
Bi-Annual Environmental Monitoring Report July-December 2017
46
Bi-Annual Environmental Monitoring Report July-December 2017
47
2. Water Quality Analysis Samples (N-70)
Bi-Annual Environmental Monitoring Report July-December 2017
48
Bi-Annual Environmental Monitoring Report July-December 2017
49
Bi-Annual Environmental Monitoring Report July-December 2017
50
Bi-Annual Environmental Monitoring Report July-December 2017
51
3. Air Quality Monitoring Report (N-70)
Bi-Annual Environmental Monitoring Report July-December 2017
52
Bi-Annual Environmental Monitoring Report July-December 2017
53
Bi-Annual Environmental Monitoring Report July-December 2017
54
Bi-Annual Environmental Monitoring Report July-December 2017
55
Bi-Annual Environmental Monitoring Report July-December 2017
56
Bi-Annual Environmental Monitoring Report July-December 2017
57
Annexure V: Traffic Diversion Plans (N-70 & N-50)
Bi-Annual Environmental Monitoring Report July-December 2017
58
Bi-Annual Environmental Monitoring Report July-December 2017
59