pak: national highway network development in balochistan … · 2018-05-02 · 2 engr. zubair ahmed...

62
Environmental Monitoring Report Bi-Annual Environmental Monitoring Report (Up-Gradation, Widening & Improvement of National Highway N-70 from Qila Saifullah to Loralai and to Waigum Rud and National Highway N-50 from Zhob to Mughal Kot) (July ~ December 2017) PAK: National Highway Network Development in Balochistan Project - N-70 from Qila Saifullah to Loralai and to Waigum Rud and N-50 from Zhob to Mughal Kot Prepared by National Highways Authority for the Asian Development Bank.

Upload: others

Post on 26-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Environmental Monitoring Report

Bi-Annual Environmental Monitoring Report (Up-Gradation, Widening & Improvement of National Highway N-70 from Qila Saifullah to Loralai and to Waigum Rud and National Highway N-50 from Zhob to Mughal Kot) (July ~ December 2017)

PAK: National Highway Network Development in

Balochistan Project - N-70 from Qila Saifullah to

Loralai and to Waigum Rud and N-50 from Zhob to

Mughal Kot

Prepared by National Highways Authority for the Asian Development Bank.

Page 2: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

NOTES

(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.

(ii) In this report, "$" refers to US dollars. This Bi-Annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-annual Environmental Monitoring Report

Project Number: (ICB-7A, 7B, 3C, 3D) (July ~ December 2017) Islamic Republic of Pakistan

Up-Gradation, Widening & Improvement of National Highway N-70 from Qila Saifullah to

Loralai and to Waigum Rud and National Highway N-50 from Zhob to Mughal Kot .

Package ICB-7A: Qila Saifullah to Loralai, (67.9 KM)

Package ICB-7B: Loralai to Waigum Rud, (50.375 KM)

Package ICB-3C: Zhob to Killi Khudae Nazar, (49KM)

Package ICB-3D: Killi Khudae Nazar to Mughal Kot, (32.44 KM)

Financed by: Asian Development Bank

For: National Highway Authority This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.

Page 4: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

1

Bi-Annual Environmental Monitoring Report

July – December 2017

N-70 and N-50

NATIONAL HIGHWAY AUTHORITY

Minconsult International / ACE

(Pvt.) Ltd. Associates

(Design Review & Supervision

Consultants)

Page 5: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

2

List of Abbreviations

ADB Asian Development Bank

BMP Best Management Practices

BBS Behavior Based Safety

CAPA Corrective and Preventive actions

CBOs Community Based Organizations

CO Carbon monoxide

dB Decibel

DCP Dry Chemical Powder

DPO District Police Officer

DTR Daily Time Register

EC European Community

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EPA Environmental Protection Agency

EPRM Environmental Progress Review Meeting

HSE Health, Safety and Environment

KM Kilometer

Leq Loudness equivalent

LTI Lost Time Injury

LTV Light Transport Vehicles

ND Not detectable

NEQS National Environmental Quality Standards

NGVS No guideline values

NHA National Highway Authority

NO2 Nitrogen dioxide

PAPs Project Affected Persons

ROW Right of Way

RWI Restricted Work Injury

SC Supervision Consultants

SIMOP Simultaneous Operation

SO2 Sulfur Dioxide

SSEMP Site Specific Environmental Management Plan

SWM Solid Waste Management

TDS Total Dissolved Solids

TRIR Total Recordable Injury Rate

TBT Tool Box Talk

PM Particulate Matter

PAPs Project Affected Persons

PPE Personal Protective Equipment

RD Running Distance

TRA Task Risk Assessment

WHO World Health Organization

Page 6: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

3

Table of Contents

Introduction...............………………………………………...………………………………...........4

Chapter 1 .............................................................................................................................. 6

Summary ............................................................................... Error! Bookmark not defined.

1.1 Construction Activities/ Work Progress: ....................................................................... 6

1.2 Project Organization: ................................................................................................... 6

1.3 Environmental, Health and Safety Management Team: ................................................ 7

1.4 Relationships with Contractors, Owners, Lenders: ....................................................... 7

Chapter 2 .............................................................................................................................. 8

Environmental Monitoring ..................................................................................................... 8

2.1 Noise and Vibrations: ................................................................................................... 8

2.2 Drinking Water Quality: ................................................................................................ 8

2.3 Waste Water Analysis: ................................................................................................. 8

2.4 Air Quality: ................................................................................................................... 8

2.5 Particulate Matter (PM10) ............................................................................................. 8

Chapter 3 .............................................................................................................................. 9

Environmental Management ................................................................................................. 9

3.1 Camp, Plants and Borrow Pits ..................................................................................... 9

3.2 Soil Erosion ............................................................................................................... 10

3.3 Dust /Air Emissions Monitoring .................................................................................. 10

3.4 Waste Management .............................................................................................. 11

3.4.1 Waste Water Management ................................................................................... 11

3.4.2 Solid Waste Management ..................................................................................... 11

3.5 Occupational Health and Safety Management ............................................................ 11

3.5.1 Emergency Preparedness and Response ............................................................ 11

3.5.2 Training of workers .............................................................................................. 12

3.5.3 Personal Protective Equipment’s ......................................................................... 18

3.5.4Site Visits/ Inspections .......................................................................................... 18

3.6 Corrective Action Plan:............................................................................................... 19

3.7 Security Measures ..................................................................................................... 21

3.8 Protected Areas ......................................................................................................... 21

3.9 Social and Cultural issues/ Grievance Redress Mechanism (GRM) ........................... 21

3.10 Record of labor deployed ......................................................................................... 24

3.11 Vehicles and Machinery Maintenance ...................................................................... 27

Annexure I: Photographic Record from July to December 2017 .......................................... 28

Annexure II: Summary of Borrow Pits ................................................................................. 37

Annexure III: Layout Plan of Base Camp ............................................................................. 42

Annexure IV: Environmental Monitoring .............................................................................. 45

Annexure V: Traffic Diversion Plans .................................................................................... 57

Page 7: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

4

1.0 Introduction

1.1 Work Packages

The environmental monitoring for the upgradation, widening and improvement of the National

Highways N-70 (Qila Saifullah – Loralai - Waigum Rud) and N-50 (Zhob - Mughal Kot) started

from the month of August 2016. The various work packages are as follows:

Item Section Package Length

(km) Contractor

1 Qila Saifullah to Loralai (N-70) ICB-7A 67.90 Umar Jan-XGHEC JV

2 Loralai to Waigum Rud (N-70) ICB-7B 50.38 Maqbool-Zarghoon JV

3 Zhob to Killi Khudae Nazar (N-50) ICB-3C 49.00 Limak-ZKB JV

4 Killi Khudae Nazar to Mughal Kot (N-

50) ICB-3D 32.44 Maqbool-Zarghoon JV

1.2 Project Proponent

The proponent of this project is the National Highway Authority (NHA), Ministry of

Communications of the Government of Pakistan. NHA has awarded the construction contracts

for the upgradation, widening and improvement of the N-70 (Package ICB-7A) to Umar Jan-

Xuchang Guangli (JV) and (Package ICB-7B) to Maqbool- Zarghoon (JV) and for N-50

(Package ICB-3C) to LIMAK- ZKB (JV) and (ICB-3D) Maqbool- Zarghoon (JV), herein after

referred to as ‘The Contractors’.

1.3 Design Review & Construction Supervision Consultants

The design review and supervisory consultancy work is awarded to Minconsult international Ltd.

(Malaysia) in association with Associated Consulting Engineers-ACE (Pvt.) Ltd. herein after

referred to as the ‘Consultant’ or the ‘Engineer’.

1.4 Summary of Findings

The construction works are currently in progress and all the Contractors have prepared and

submitted the Site Specific Environmental Management Plan (SSEMP) for each work package,

which has been approved by NHA and ADB.

For N-70 a total of 13 Affected Person Committees (APCs) and for N-50 a total 7 APCs for the

Grievance Redress Committee (GRC) were constituted. The Contractors have provided the

complaints registers in their main base camps. So far only a few major complaints have been

received and all have been addressed accordingly. There are some minor complaints but they

are being investigated and will be resolved amicably.

Page 8: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

5

All the Contractors have employed their Health, Safety and the Environment (HSE) Managers

who are regularly visiting the construction sites, workshops, plants, dumping sites and borrow

areas. The HSE Managers are regularly inspecting fire extinguishers, hand and power tools,

machinery, personal protective equipment (PPE) and the general housekeeping for the main

camps facilities and plants.

The HSE Managers also conducted the safety toolbox talks at camps, plants and active

construction sites. In the second half of the year 2017, the Contractors’ HSE Managers of N-70

delivered 38 sessions of safety toolbox talk whilst for N-50 23 similar training sessions were

conducted. All the contractors have provided a mini clinic/dispensary at their main camps as

well as an ambulance and a Paramedic.

The contractors have constructed temporary road diversions to keep the traffic moving during

construction works. These temporary main road diversions and access roads to borrow pits are

being regularly sprinkled with water using water bowsers. Flagmen at major road crossings and

diversions are provided to control traffic and prevent accidents between construction machinery

and other road users. Safety signboards at the constructions sites, plants, workshops and traffic

signboards at the service roads and diversions have been installed at strategic locations.

Earth materials for embankments are obtained from approved borrow pits at 500 m away from

the ROW, as well as from cutting areas. So far 56 borrow pits have been approved on N-70 and

on N-50 the total number of borrow pits are 23.

All the contractors have established their base camps for the residence of their site staff,

general workers and security personnel. They have also established their concrete batching

plants, stores, workshops, steel yards, diesel stations and materials testing laboratories. All

these base camps have been completed and fully operational.

Fire extinguishers are installed at all base camps. PPE’s are provided to workers working at

plants, workshops and construction sites; including safety helmets, masks, safety gloves and

high visibility vests. Construction workers and site personnel are regularly briefed about the

proper use of the PPE’s and their importance.

At the base camps, proper wastewater treatment and solid waste management is being

maintained as per the SSEMP. Wastewater is collected into septic tanks and disposed off into

soak away pits. Solid wastes are collected primarily in waste drums provided at strategic

locations, and then collected to waste collection points for segregation; the reusable and

recyclable materials are collected and the remaining wastes are disposed in the municipal solid

waste disposal sites.

Provision of treated drinking water is being maintained for all the workers and staff at site camps

and construction sites. Monitoring of the air, water and noise quality are being conducted

regularly as per the SSEMP. The quality values of the air, water and noise remained within the

permissible limits.

The overall occupational health and safety measures, implemented by the Contractors

remained reasonable and satisfactory. The general environmental conditions were found to be

Page 9: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

6

acceptable as per the approved SSEMP, but further improvements are still possible with regular

and serious monitoring.

Chapter 1

1.1 Work Progress

The physical work progress of the four construction contracts, at the end of December 2017, is

as follows:

Item Work Package Planned Progress (%) Actual Progress (%) Ahead (+) / Delay (-)

1 ICB-7A (N-70) 48.80 44.35 -14.45

2 ICB-7B (N-70) 50.41 44.90 -5.51

3 ICB-3C (N-50) 66.72 72.44 +5.72

4 ICB-3D (N-50) 50.31 52.89 +2.58

1.2 Project Organization (Site)

The following personnel head the project teams:

Item Name Position Organization Location

1 Engr. Noor Ul Hassan

GM Construction NHA, Quetta N-70

2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70

3 Major (R) Adnan Farukh Hassan Resident Engineer Minconsult/ACE N-70

4 Engr. Aqeel Ahmed Qazi Project Manager UJ-XGHEC (JV) N-70 (ICB-7A)

5 Engr. Riaz Ahmaed Kalo Project Manager MZ (JV) N-70 (ICB-7B)

6 Engr. Muhammad Shahid Khan GM Construction NHA, Quetta N-50

7 Engr. Zia Uddin Burki Project Director NHA, Quetta N-50

8 Engr. Ijaz Ahmad Resident Engineer Minconsult/ACE N-50

9 Engr. Khalil Jibran Project Manager LIMAK-ZKB (JV) N-50 (ICB-3C)

10 Mr. Naeem Ehsan Project Manager MZ (JV) N-50 (ICB-3D)

11 Engr. Azlan Ahmad Team Leader Minconsult/ACE N-70&N-50

12 Engr. Yunos Abdullah Sr. Highway Engineer Minconsult/ACE N-70&N-50

Page 10: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

7

1.3 Environmental, Health and Safety Management Team

The personnel at site who are involved with the monitoring of the environmental management

plans of the contractors are as follows:

Item Name Position Organization Location

1 Mr. Muhammad Qayyum Environmental Specialist

Minconsult/ACE N-70

2 Mr. Syed Zia Uddin HSE Manager MZ (JV) N-70 (ICB-7B)

3 Mr. Hidayat Ullah HSE Manager UJ-XGHEC (JV) N-70 (ICB-7A)

4 Mr. Zahid Ramzan HSE Manager LIMAK-ZKB (JV) N-50 (ICB-3C)

5 Mr. Fahad Ullah HSE Manager MZ (JV) N-50 (ICB-3D)

1.4 Relationship Between All the Parties

The overall relationship among the Contractors, Employer’s Representatives and the

Supervision Consultant’s staff, as well as the Funding Agency remained harmonious during the

reporting period.

Page 11: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

8

Chapter 2

2.0 Environmental Monitoring

The qualitative environmental monitoring is being carried out during construction activities and

verified that they are undertaken in compliance with the requirements set in the EIA/EMP and

Site Specific Environmental Management Plan (SSEMP).

2.1 Noise and Vibrations

Noise monitoring is conducted on a quarterly basis at different locations. Noise level results so

far show that most of the construction activities are being conducted within the permissible

noise limits. All machines that are producing noise beyond the threshold levels, such as

generator sets, are being isolated in order to reduce the noise level. To minimize the noise from

the construction vehicles, all machineries are periodically checked for their noise level and

notified for repairing and maintenance. The results of noise monitoring are attached as

Annexure IV.

2.2 Drinking Water Quality

At the contractors’ base camps, bottled water and water coolers are provided for drinking

purposes for all personnel. This water supply is also provided to workers at the construction

sites. For all other purposes, clean and treated water is provided through pipes from the local

water supply or pumped from wells.

2.3 Wastewater Treatment

Wastewater from washrooms and kitchens are collected and treated through septic tanks and

soakage pits at all the base camps. No wastewater is released directly into fields and irrigation

water channels from any base camps.

2.4 Air Quality

Ambient air quality monitoring is being carried out once in every four months during the

construction, as per the approved EMP.

2.5 Particulate Matter (PM10)

The particulate matter monitoring was started in the month of August 2017. The particulate

matter (PM10) monitoring done at different locations during the construction activities shows that

the level of PM10 are within the standards specified in the approved contract EMP.

Page 12: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

9

Chapter 3

3.0 Environmental Management

All the contractors have prepared and submitted their Site Specific Environment Management

Plan (SSEMP), which has been reviewed and approved by NHA and ADB. The SSEMP is being

implemented strictly at the construction sites.

3.1 Base Camps, Plants and Borrow Pits

The contractors have established their base camps at the following locations:

Item Work Package Contractor Location Area (m2) Distance to ROW (m)

1 ICB-7A (N-70) UJ – XGHEC (JV) Km 26+100 100,000 100 LHS

2 ICB-7B (N-70) MZ (JV) Km 113+900 81,000 900 LHS

3 ICB-3C (N-50) LIMAK-ZKB (JV) Km 38+000 85,000 200 LHS

4 ICB-3D (N-50) MZ (JV) Km 55+900 80,000 50 RHS

At the base camps the contractors have constructed offices, workers accommodations,

washrooms, workshops, steel yards and areas for materials storage, fuel tanks, mosques, first

aid facilities, recreational space and also facilities for the security personnel (FC). They have

also established a dispensary with paramedic staff on fulltime duty at the base camps.

Adequate and relevant first aid medicines and bandages are provided at these dispensaries.

Ground water is used as water for general purpose as well as for drinking after some basic

treatments.

All types of solid steel scrap metal from the steel yards and workshops are collected in

specifically marked bins and are shifted to scrap the yard. The scrap metal is stored and sold in

market when required. Kitchen and office solid wastes are collected in similar manner and sent

to the solid waste collection points (dustbins placed at various points). These solid wastes are

then collected for final disposal at designated places. As far as the matter of collection of used

oil is concerned it is being collected in fuel spill trays from the motor workshops and shifted to

liquid waste collection point on daily basis where these are stored in drums properly covered

with shed and ultimately sold out to oil dealers on quarterly basis or whenever required.

Wastewater generation and treatment, as per the requirements of IEE and the SSEMP, is

carried out at the base camps. All contractors have constructed septic tanks, soakage pit and

small retention manholes system.

The base camps are fenced and security check-posts are available at the entrance. The

kitchen, dining halls and residential of senior staff and labor staff are properly protected from

flies and mosquitoes and by providing steel gaze on windows.

Page 13: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

10

Emergency contact numbers, fire extinguishers and sand buckets are provided at the camp

offices, fuelling points, workshops and main stores etc. Mosques are also constructed at the

camps for staff and workers. Workshop area for vehicle maintenance is kept paved to avoid oil

contamination. Oil storage area is also paved and covered with shed. Generators are also

provided at the site.

Environmental Education and Awareness about safety measures and good housekeeping at

steel yard, store area, oil/chemical storage area, and kitchen site are done.

Plants & Workshops

Other facilities such as concrete batching plants, crusher plants as well as asphalt plants have

been erected at the sites. These plants have all been located away from populated areas to

reduce the impact on noise and dust pollutants. Mitigation measures like scrubbers and water

sprinklers have also been installed to reduce dust from the operations of these plants.

Borrow pits

The areas from where soil is being taken for the construction of embankment is called borrow

pits. The location and summary of the approved borrow areas is attached as Annexure-II. The

environmental impacts of borrow areas are under observation during soil excavation,

transportation and restoration. Designated routes are being used during soil transportation.

Service roads and adjacent roads used for the transportation of soil are checked regularly, and

if any damage were caused to the public road, it shall be rectified.

3.2 Soil Erosion

This environmental impact is due to the road construction activities. It occurs due to the clearing

and excavation activities at the project site, as these activities are leading to the soil erosion, or

alteration of soil quality resulting from removal of the topsoil at the site, to some extent.

Mitigation measures adopted to minimize soil erosion include:

• The depth of the borrow pits are being maintained so that the sides of the excavation have a

slope not steeper than 1 into 4.

• Soil erosion along the borrow pits is being monitored to prevent / mitigate impacts on

adjacent lands.

• Borrow pits after excavation of soil will be rehabilitated as per the SSEMP.

3.3 Dust /Air Emissions Monitoring

The construction activities generate dust due to excavation and filling works. Diesel and other

petroleum products used for the operation of construction machinery and transportation

equipment also cause air pollution. The impacts generated from such activities are of certain

significance and proper mitigation measures are being practiced. The workforce always wears

personal protective equipment (PPE) including dust masks, to minimize health hazards. Vehicle

maintenance is regularly done to minimize the impacts of air pollution on the surrounding

environment. Dust suppression is being maintained by sprinkling water on the service road,

diversions and access routes / approach roads to the borrow areas.

Page 14: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

11

3.4 Waste Management

3.4.1 Waste Water Management

Wastewater is managed as per the SSEMP; at base camps construction of septic tanks and

soakage pits have been completed in the month of November 2016, respectively therefore

wastewater is managed inside the septic tanks and soakage pits.

3.4.2 Solid Waste Management

All the solid waste generated at the base camps is being collected in waste bins. Solid waste

after collection is being segregated, the recyclable and reusable are collected and the remaining

wastes are disposed of properly at the municipal solid waste dumping sites.

3.5 Occupational Health and Safety Management

The construction activities have certain impacts on the occupational and public health. At the

work site hazards are eliminated/ minimized through engineering controls and administrative

controls, if the controls do not eliminate the hazards appropriate PPEs are being provided to the

workers. Workers and staff are being trained and equipped with the appropriate Personnel

Protective Equipment’s (PPEs) as per their job need.

3.5.1 Emergency Preparedness and Response

Emergency Response preparedness and response plan has been designed as per details given

in the approved SSEMP and being implemented accordingly. The following are the contact

numbers of focal / responsible personnel of the project.

A. Umar Jan – XGHEC (JV) ICB-7A (N-70)

Item Designation / Department Name / Location Contact Details

1 Project Manager Engr. Aqeel Ahmed Qazi 0333-7092420

2 Deputy Project Manager (1) Mr. Muhammad Arshad Shaheen 0333-6687755

3 Deputy Project Manager (2) Mr. Yahiya Khan 0336-1205250

4 HSE Manager Mr. Hidayat Ullah 0313-8235025

5 Paramedic / First Aider Dr. Shahbaz 0345-8309130

6 Administration Manager Mr. Liaqat 0333-4088468

7 Ambulance Driver Mr.Rehmat Ullah 0333-7039342

8 Fire Department Loralai 16

9 Frontier Corps (FC) Loralai 0333- 1391836

10 Police Department Loralai 16

B. MZ (JV) ICB-7B (N-70)

Item Designation / Department Name / Location Contact Details

1 Project Manager Engr. Riaz Ahmed Kalo 0332-7887815

2 Deputy Project Manager Mr. Naeem Khan 0333-5988237

Page 15: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

12

3 HSE Manager Mr. Syed Zia uddin 0333-1564580

4 Paramedic / First Aider Mr. Naseeb Ullah 0340-8382665

5 Administration Manager Mr. Abdul Ali 0333-1419184

6 Ambulance Driver Mr. Sher Muhammad 0333-8321291

C. LIMAK – ZKB (JV) ICB-3C (N-50)

Item Designation / Department Name / Location Contact Details

1 Project Manager Mr. Shafique 0344-39223814

2 Deputy Project Manager Mr. Younis 0343-2515056

3 Camp In Charge Mr.Hikmat Shah 0345-9842142

4 Structure In Charge Mr.Shahbaz Khalid 0300-7024854

5 Base Camp (workshop) Mr.Gulfam 0331-2558575

6 Bridge Engineer Mr.Zeeshan Azeem 0344-2148808

7 Asphalt Laying Foreman Mr. Arshad 0333-6576914

8 Asphalt Plant In charge Mr.Azmat Ullah 0336-325333

9 Concrete Batching Plant in Charge Mr. Azhar 0347-3390006

10 FC Militia Wing 52 Mr. Rab Nawaz 0345-3271948

D. MZ (JV) ICB-3D (N-50)

Item Designation / Department Name / Location Contact Details

1 Project Manager Mr. Rana Naeem Ehsan 0346-2005556

2 HSE Manager Mr. Fahad Ikram 0342-7534493

3 Construction Manager Mr. Muhammad Ilyas 0341-5207217

4 Manager Operation Mr. Ashfaq Ahmad 0344-8105030

5 First Aider Mr. Muhammad Azeem 0343-0798793

6 Administration Manager Mr. Ulusyar Khan 0348-8533378

7 Ambulance Driver Mr. Bismillah 0343-9787556

8 Fire Department Mr. Muhammad Jamshaid 0341-1730580

9 Frontier Corps (FC) Mr. Usman Hawaldar 0346-8125893

10 Police Department Mr. Muhammad Iqbal (SHO) 0346-3218806

3.5.2 Training of Workers

Workers are continuously being trained in order to minimize the risks and impacts of occupational and

environmental hazards. Toolbox talks have been regularly conducted and will be conducted in future. All

Page 16: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

13

the employees are briefed regarding occupational hazards, risks and safety measures. The following are

the details of the safety toolbox talks and training that have been delivered in the second half of the year

2017:

Umar Jan- XGHEC (JV) Lot-1 (N-70)

Sr.

No

Title of the

training

Date

Trainer Site Location Contractor

Day Month Year

1

Work

Safety

Training

14 07

2017

Hidayat

Ullah

Camp Site Camp site

UMARJAN-

XUCHANG

GAUNGLI (JV)

2

Work

Safety

Training

21 07

2017

Hidayat

Ullah

Camp Site Camp Site Sub-contractor

3 Safety 10 08

2017

M.

Qayyum

Camp Site Camp Site UMARJAN-

XUCHANG

GUANGLI (JV)

4 Safety 17 08

2017

Hidayat

Ullah

Camp Site Camp Site Sub-contractor

5 Road

safety 09 09

2017

Hidayat

Ullah

Camp Site Camp Site UMARJAN-

XUCHANG

GUANGLI (JV)

6

Flagman

Training 26 09

2017

Hidayat

Ullah

Construction

site

Construction

site

UMARJAN-

XUCHANG

GUANGLI (JV)

7

Flagman

Training 02 10

2017

Hidayat

Ullah

Construction

site

Construction

site

UMARJAN-

XUCHANG

GUANGLI (JV)

8 Flagman

Training 05 10

2017

Hidayat

Ullah

Construction

site

Construction

site

UMARJAN-

XUCHANG

GUANGLI (JV)

9 Tool Box

Talk 14 10

2017

Hidayat

Ullah

Construction

site

Construction

site

Sub-contractor

10 Tool Box

Talk 26 10

2017

Hidayat

Ullah

Construction

site

Construction

site

UMARJAN-

XGHEC (JV)

Page 17: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

14

Sr.

No

Title of the

training

Date Trainer Site Location Contractor

11

General

Safety

Training

02 11

2017

Hidayat

Ullah

Construction

site

Construction

site

UMARJAN-

XUCHANG

GAUNGLI (JV)

12

Defensive

Driving

Training

11 11

2017

Ahmed

Hassan

Construction

site Construction

site

Sub-contractor-

13 HSE

Training 23 11

2017

Mr.

Qayyum

Camp Site Camp site

Camp Office

UMARJAN-

XUCHANG

GUNGLI (JV)

14 Tool Box

Talk 07 12

2017

Hidayat

Ullah Construction

site

Camp site

Camp Office

Sub-contractor

15

Fire

Fighting

Training

15 12

2017

Hidayat

Ullah

Construction

site

Construction

site

Sub-contractor

Maqbool- Zarghoon (JV) Lot-2 (N-70)

Sr.

No

Title of the

training

Date

Trainer Site Location Contractor

Day Month Year

1 Solid waste 05 07 2017 Syed Zia

Uddin Camp Site

Conference

Hall

MAL-ZEPL

(JV)

2

Environment

Management

System

12 07 2017

Qayyum

Khan Camp Site Conference

Hall

MAL-ZEPL

(JV)

3

Environment

Management

System

20 07 2017 Syed Zia

Uddin

Camp Site

Conference

Hall

MAL-ZEPL

(JV)

4 Work Safety

Training

28

07 2017 Syed Zia

Uddin Site

Working

area

MAL-ZEPL

(JV)

5 Loading

Unloading 07 08 2017

Syed Zia

Uddin Site

Working

area

MAL-ZEPL

(JV)

6 Work Safety

Training 15 08 2017

Syed Zia

Uddin Site

Working

area

MAL-ZEPL

(JV)

Page 18: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

15

Sr.

No

Title of the

training

Date Trainer Site Location Contractor

7 Welding

Safety 17 08 2017

Syed Zia

Uddin Camp Site Workshop

MAL-ZEPL

(JV)

8 Chemicals

Handling 19 08 2017

Qayyum

Khan Camp Site Lab

MAL-ZEPL

(JV)

9 Chemicals

Handling 22 08 2017

Syed Zia

Uddin Camp Site Lab

MAL-ZEPL

(JV)

10 Confined

Space Entry 09 09 2017

Syed Zia

Uddin

Camp Site Camp Site MAL-ZEPL

(JV)

11 Work Safety 14 09 2017 Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

12

Flagman

Training 22 09 2017

Syed Zia

Uddin Camp Site Workshop

MAL-ZEPL

(JV)

13 Chemicals

Handling 28 09 2017

Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

14 Crane Safety 10 10 2017 Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

15 Lifting Safety/

Induction 22 10 2017

Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

16 Housekeeping 05 11 2017

Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

17 Road safety 10 11 2017 Syed Zia

Uddin Camp Site Camp Site

MAL-ZEPL

(JV)

18 Tool Box Talk 12 11 2017 Syed Zia

Uddin Camp Site Camp site

Sub-

contractor

19 Tool Box Talk 13 11 2017 Syed Zia

Uddin Camp Site Camp site

MAL-ZEPL

(JV)

20

General

Safety

Training

18 11 2017 Syed Zia

Uddin Camp Site

HSE

Training Hall

Camp Office

MAL-ZEPL

(JV)

Page 19: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

16

Sr.

No

Title of the

training

Date Trainer Site Location Contractor

21

General

Safety

Training

19 11 2017 Syed Zia

Uddin Camp Site Camp site

MAL-ZEPL

(JV)

22

Scaffolding

Safety

Training

25 11 2017 Syed Zia

Uddin Camp Site

HSE

Training Hall

MAL-ZEPL

(JV)

23 Driving

Training 01 12 2017

Syed Zia

Uddin Camp Site

HSE

Training Hall

MAL-ZEPL

(JV)

Limak – ZKB (JV) Lot-1 (N-50)

Sr. No Date Topics Participants Delivered By

1 04/07/2017 Electrical hazard 18 Environmental

Engineer (EE)

2 6/07/2017 Hot stress 26 EE

3 8/07/2017 Ladder inspection and safety 22 EE

4 11/07/2017 Flammable chemical fire

prevention (asphalt plant) 18 EE

5 15/07/2017 Summer driving 19 EE

6 19/07/2017 A flood of danger 17 EE

7 23/07/2017 Slip, trip and fall 18 EE

8 26/07/2017 Handling flammable liquid 16 EE

9 02/08/2017 Driving, PPEs, speed limit

controls 28

Environmental

Engineer (EE)

10 05/08/2017 Management Of Heavy

Equipment 16 EE

11 10/08/2017 Safety measures 22 EE

Page 20: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

17

12 12/08/2017 Usage of Firefighting techniques 18 EE

13 17/08/2017 Health and Safety 19 EE

14 19/08/2017 First aid Practices 22 EE

15 24/08/2017 Awareness about cleanliness’

and good housekeeping 14 EE

16 28/08/2017 Usage of PPEs, safety measures 26 EE

17 03/09/2017 Heavy Equipment Movement

28

Environmental

Engineer (EE)

18 05/09/2017 Poor Working Condition

17

EE

19 9/09/2017 Emergency Response Plan

21

EE

20 12/09/2017 Water Sprinkling

44

EE

21 15/09/2017 Waste Management

33

EE

22 18/09/2017 Poor Lightening

14

EE

23 21/09/2017

PPEs Implementation

34

EE

24 4/10/2017 Housekeeping 30 Environmental

Engineer (EE)

25 7/10/2017 Implementation of PPEs 56 EE

26 12/10/2017 Snake Bite 22 EE

Page 21: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

18

27 14/10/2017 Hot Work 15 EE

28 17/10/2017 Work at Height 21 EE

29 20/10/2017 Site HSE Rules 21 EE

30 23/10/2017 Implementation of PPEs 27 EE

31 3/11/2017 Work at Height 28 (EE)

32 5/11/2017 Heavy Equipment Movement 17 EE

33 8/11/2017 Poor Working Condition 21 EE

34 11/11/2017 Emergency Response Plan 23 EE

35 16/11/2017 Water Sprinkling 44 EE

36 19/11/2017 Waste Management 33 EE

37 23/11/2017 Poor Lightening 14 EE

38 26/11/2017 Excavation 22 EE

3.5.3 Personal Protective Equipment (PPE)

The workers are forced to wear their PPE for their safety at work. They have been told to wear safety

helmets, safety shoes, hand gloves, dust mask etc. and other necessary protective equipment while

working at site, plants, workshops and other construction areas as per their job requirements.

3.5.4 Site Visits / Inspections

The Consultant Environment Specialist is visiting the active construction sites, camps, plants, workshops,

and borrows pits along with the Contractor HSE Managers. Issues and non-compliances observed are

conveyed to the Contractor in writing and verbally and are also discussed in the fortnightly coordination

meetings with the Contractors. The Contractor HSE Managers are also visiting construction sites, camps,

plants and borrows pits; inspects work sites, welfare facilities, PPEs etc. and also deliver toolbox talks.

Workers have been trained to report near misses and take preventive and corrective actions as

envisaged by HSE Managers.

Page 22: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

19

3.6 Corrective Action Plan

Action Plan Status up to December 2017 (N-70)

Item Non-Compliance Mitigation Measures Status

01

Installation of safety and

traffic sign boards at lot-

1 & 2

Safety and traffic signboards have been installed at

plants, campsite, and workshop. Done

02

Installation of safety and

traffic sign boards at

Lot-1 & Lot-2

Safety and traffic signboards have been installed at

service road. Done

04

First aid facility at

Garang Cutting Area

Lot-1

First aid facility has been provided Done

05 PPEs at Lot1&2 Earplug not worn by operator in plant room. Done

06 First Aid boxes at Lot-

1&2 Items in First Aid box were not complete. Done

07 Workers

accommodation at Lot-1

for sub-contractor

Accommodation with electricity, beds facilities have

been provided to labor Done

08 Air Emission (Lot1&2)

Air emission, noise level, drinking water analysis,

wastewater has assured through self-calibration of the

instrument.

Done

09 PPEs Subcontractor staff working without safety shoes. Done

10 Training Subcontractor staff, need more Training and awareness

is imperative regarding HSE understanding Done

Action Plan Status December 2017 (N-50).

SR.

NO. ISSUES CORRECTIVE ACTION STATUS

1. Safety Issue Sufficient amount of PPEs have been provided at all

construction sites. Compliance

2. Housekeeping Best housekeeping at both camps site, construction sites

have been ensured. Compliance

3. First aid facility First aid center is fully functional at labor campsite. MBBS

Doctor and paramedic is available during day times. Compliance

Page 23: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

20

Moreover first aid box has provided at construction sites.

4. Gardening of Camp

site

Two Gardner has been hired by the Contractor that shall

take care of all the green areas both in labor and main

camp.

Compliance

5. Provision of HSE Staff

HSE Manager, I/C HSE, Environmental officer, HSE officer,

Trainee Engineer, HSE Supervisors, HSE Assistant and

Flagmen are available at site.

Compliance

6. Fire Safety

Fire extinguishers have been provided at all construction

sites, construction sites, office block area and residential

areas.

Compliance

7. Safe Drinking water Safe drinking water is provided to all project personnel’s

working at construction sites and camps area. Compliance

8. Display of safety sign

boards

Safety signboards including warning and informatory have

been erected at camp areas, site facilities and construction

sites. Moreover speed limit signboards are also erected at

diversions and along the road.

Compliance

9. TBTs / Training on

HSE

TBTs and HSE trainings have been conducted by HSE

Supervisors at all construction sites and camp areas. Compliance

10. Water Sprinkling

Water sprinkling is being ensured at all construction sites,

construction sites, site facilities, camp areas and access

routes.

Compliance

11. Washing Facility The Contractor has constructed washing facility in labor

camp. All the employees are facilitating from the services. Compliance

12. Concrete pad Concrete pad has constructed at filling station to avoid any

kind of oil spillage or soil contamination. Compliance

13. Construction of

walkways

Walkways have been constructed in both officer and labor

camp. Walkways are also being maintained in the

supervision of camp boss.

Compliance

14. Provision of Waste

Collection drums

Waste collection drums have been provided at all

construction sites, site facilities area, labor and main camp

to ensure proper housekeeping and waste management.

Compliance

15. Dust Abatement Plan

Three water bowsers are in continuous working at site that

ensured the strict implementation of dust abatement plan

according to the water sprinkling frequency chart.

Compliance

Page 24: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

21

3.7 Security Measures

For the security of employees armed Frontier Corps (FC) and contractors’ armed private security

personnel are deputed. Currently more than 200 security personnel are on duty including 39 private

security guards are deputed on the Contractors’ base camps at Qila Saifullah-Loralai-Waigum Rud (N-70)

and Zhob-Mughal Kot Road (N-50). The FC personnel also escort the Malaysian expatriates consultant

whenever they travel to the construction sites and other locations. Moreover at the main gate of base

camps barriers are placed to prevent unauthorized tress passing. Entry and exit record of all vehicles and

visitors / employees are also maintained at both base camps. Security cameras (CCTV) are also installed

and functional at the base camps.

3.8 Protected Areas

There are no protected areas such as wildlife sanctuaries, game reserves, national parks, and

archaeological, historical or cultural heritage sites in the projects’ neighborhoods. Therefore, no impact is

envisaged.

3.9 Social and Cultural Issues / Grievance Redress Mechanism (GRM)

Grievance Redress Mechanism (GRM) is institutions, instruments, methods and processes by which a

resolution to a grievance is sought and provided. People adversely affected (or about to be affected) by a

development project will raise their grievances and dissatisfactions about actual or perceived impacts in

order to find a satisfactory solution. Some grievances may arise during the project design and planning

stage, while others may come up during project implementation. Not only should affected persons (APs)

be able to raise their grievances and be given an adequate hearing, but also satisfactory solutions should

be found that mutually benefit both the APs and the project.

Currently the Contractor has provided complaint registers in all camps and complaints are duly registered

and redressed. In the reporting period few of the complaint received.

Consultation sessions are being arranged from time to time to improve the environmental conditions of

the project area. The complaints/ grievances received are noted/ recorded in the complaint registers at

camps and are being redressed accordingly. Record of the grievances received and redressed is below.

Page 25: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

22

Qila Saifullah-Loralai-Waigum Rud (N-70)

Sr.

No.

Date Complainant Name

Address/Contacts

Complain Action Taken Remarks

1 29-11-17 Ihsan ullah RD=97+100

TO 97+700

Road according to

drawing was curved to

left side, so said

person said it lies in

our land

Refer to PD office

through formal letter In progress

2 05-10-17 Daulat khan RD=95+600

Vehicles are very

speed in diversion,

which is near to his

house.

In this case, made

two-speed breaker

in the diversion,

which was near to in

house.

Don

03 18-09-17 Malik Aslum

RD=105+000 Dust issue

Resolved by

increasing water

browsing

Resolved

04 12 -08 -17 Abdul Jabbar

RD=88+700

On side while

removing of the trees

of said person, But he

did not allow us due to

No. of trees were

written less than

actual, so did not

receive the cheque.

According to this

case letter was

written to GM and

forwarded

Don

05 10 -07 -17 Muzamill Khan RD=

115+300

Shifted the culvert for

water transferring to

the road other side for

watering of trees.

Application

forwarded to project

director for approval

Don

Page 26: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

23

Zhob-Mughal Kot (N-50)

Sr.

No.

Date Complainant Name

Address/Contacts

Complain Action Taken Remarks

1 05-07-2017

Maiva Khan S/o

Wazir Khan

Manikhawa

RD= 14+200 Km

Due to excavation for

culvert, the excavated

material is dumped

into his grapes garden

Dumping material

has been removed

from grapes garden

Resolved

2 18-07-2017

Umar Khan S/o Hunar

Khan

Khawarena

RD= 46+300

Due to Heavy

machinery dust is

generated near crush

plant

Sprinkling is done to

Suppress the dust.

Water sprinkling is

done twice a day to

suppress the dust or

as per requirement

Resolved

3 2-08- 2017

Noor Ullah S/o Juma

Khan

RD=12+300

Dust generation is

high in cutting area

near grapes gardens

Water sprinkling is

being done twice a

day to Suppress the

dust

Resolved

22-08-2017

Alamgir Khan S/o Noor

Dad Khan

Passenger

Diversion Slope is not

good and heavy

vehicles could slip and

accident can occur

Diversion Slope has

been a changed and

heavy vehicle now

passing easily.

Resolved

Page 27: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

24

3.10 Records of Labor Deployed

A. Employees of UJ-XGHEC at ICB-7A (N-70)

Sr. No.

Position Qty. Sr. No.

Position Qty.

1 Project Manager 1 21 Drivers 17

2 Deputy Project Manager 2 22 Dumper Drivers 34

3 Materials Engineer 1 23 Gardeners 1

4 Administrative Manager 1 24 Inventory Keepers 3

5 Construction Engineer 1 25 Roller Operators 16

6 Field Manager 1 26 Grader Operators 10

7 HSE Manager 1 27 WT Operators 16

8 Surveyors 7 28 Grader Operator Helpers 10

9 Surveyor Helpers 14 29 Dumper Truck Helpers 26

10 Mechanical Engineer 0 30 Transit Mix Operator 5

11 Mechanics 4 31 Assistant Mechanics 7

12 Assistant Accountants 3 32 Welders 2

13 Masons 19 33 Security Guards 50

14 Laborers 92 34 Generator Operator 4

15 Plant Operators 4 35 Electricians 3

16 Foreman 8 36 Sweepers 5

17 Security officers 1 37 Fuel Man 5

18 Auto-Cad Operators 3 38 Cook 5

19 Trainee Site Engineers 4 39 Office Boys 6

20 Laboratory Helpers 8 40 Coordinators 1

Sub-Total 175 Sub-Total 216

Page 28: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

25

B. Employees of Maqbool-Zarghoon (JV) ICB-7B (N-70)

Sr. No.

Position Qty. Sr. No.

Position Qty.

1 Project Manager 1 21 Drivers 22

2 Deputy Project Manager 1 22 Dumper Drivers 25

3 Materials Engineer 1 23 Laboratory Helpers 7

4 Administrative Manager 1 24 Inventory Keepers 5

5 Construction Engineer 3 25 Roller Operators 14

6 Field Manager 2 26 Grader Operators 12

7 HSE Manager 1 27 WT Operators 9

8 Surveyors 7 28 Grader Operator Helpers 4

9 Surveyor Helpers 22 29 Site Engineers 26

10 Mechanical Engineer 1 30 Transit Mix Operator 7

11 Mechanics 8 31 Assistant Mechanics 12

12 Assistant Accountants 2 32 Welders 3

13 Masons 20 33 Security Guards 60

14 Laborers 89 34 Generator Operator 2

15 Plant Operators 4 35 Electricians 2

16 Foreman 7 36 Sweepers 3

17 Security officers 1 37 Fuel Man 5

18 Auto-Cad Operators 3 38 Cook 10

19 Trainee Site Engineers 4 39 Office Boys 6

20 Laboratory Helpers 8 40 HSE 6

Sub-Total 176 Sub-Total 240

Page 29: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

26

C. Employees of LIMAK-ZKB (JV) ICB-3C (N-50)

Sr. No.

Position Qty. Sr. No.

Position Qty.

1 Project Manager 1 12 Laboratory Staff 19

2 Deputy Project Manager 1 13 Mechanical staff 14

3 Structure Engineer 5 14 Machine Operators & Helpers / HTV Drivers & Helpers

228

4 Materials Engineer 1 15 LTV Drivers 50

5 Quantity Surveyor 1 16 Batching Plant Staff 9

6 CAD Operator 1 17 Asphalt Plant Staff 9

7 Site Foreman / Supervisors 18 18 Office Boys 7

8 Accounts Staff 3 19 Crusher Plants Staff 26

9 Surveyor Helpers 39 20 Security Guards 26

10 Environmental / Safety Staff 7 21 Skilled & Unskilled Labors 410

11 Office Staff 8

Sub-Total 85 Sub-Total 798

Page 30: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

27

D. Employees of Maqbool-Zarghoon (JV) ICB-3D (N-50)

Sr. No.

Position Qty. Sr. No.

Position Qty.

1 Project Manager 1 21 Drivers 20

2 Manager Operation 1 22 Dumper Drivers 40

3 Materials Engineer 1 23 Gardeners 1

4 Administrative Manager 1 24 Inventory Keepers 3

5 Construction Manager 1 25 Roller Operators 20

6 Field Manager 1 26 Grader Operators 15

7 HSE Manager 1 27 WT Operators 18

8 Surveyors 7 28 Grader Operator Helpers 15

9 Surveyor Helpers 14 29 Dumper Truck Helpers 30

10 Mechanical Engineer 0 30 Transit Mix Operator 7

11 Mechanics 4 31 Assistant Mechanics 7

12 Assistant Accountants 3 32 Welders 5

13 Masons 19 33 Security Guards 40

14 Laborers 105 34 Generator Operator 4

15 Plant Operators 6 35 Electricians 6

16 Foreman 8 36 Sweepers 5

17 Security officers 1 37 Fuel Man 5

18 Auto-Cad Operators 3 38 Cook 5

19 Trainee Site Engineers 4 39 Office Boys 6

20 Laboratory Helpers 10 40 Coordinators 1

Sub-Total 201 Sub-Total 253

3.11 Vehicles and Machinery Maintenance

Vehicles are periodically checked for their maintenance requirements. For this purpose, noise

and visual observation of vehicle exhaust emission is being done. Moreover record for the change of

Mobile Oil for vehicles is also being maintained. These things will help to assess vehicle efficiency and

need for its repair. Record is being maintained at workshops.

Page 31: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

28

Annexure I: Photographic Record from July to December 2017 (N-50 & N-70)

Laying ACBC Laying of ACBC

Laying of Aggregate Base Course Workers Wearing PPE for Laying of ACBC

Page 32: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

29

Wearing of PPE Being Complied at Site of Both N-50 & N-70

Page 33: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

30

Signboards and Traffic Diversion Signage at N-50 & N-70

Page 34: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

31

Signage and Traffic Diversion Cones at N-50 & N-70

Page 35: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

32

Lot-2

Water Bowsers at Work for Dust Control at N-50 & N-70

Page 36: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

33

Visits of ADB & NHA Officials to N-50 & N-70

Dispensaries at Base Camps and Tool Box Meeting

Photographic Record from July to December 2017 (N-50 & N-70)

Page 37: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

34

Conducting the Tool Box Talk on Site

Page 38: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

35

Compliance with SSEMP at Site and Base Camps of N-50 & N-70

Page 39: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

36

Traffic Signage

Page 40: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

37

Annexure II: Summary of Borrow Pits

Borrow Areas

Borrow materials are being taken from recommended and approved borrow areas. The

recommended pits for borrowing shall be rehabilitated as soon as excavation of material is finished. The

rehabilitation activity and process will take into consideration the aesthetics of the area and safety of

people, animals and community. Until now no agricultural fields, which exist near to the project sites, are

used as borrow pits.

Restoration of Borrow Pits

Before extraction commences, licenses and permits shall be checked and limits of disturbance

and/or clearing will be clearly marked out on the site before any ground disturbing activity takes place.

This usually requires the sides of the pit to be reshaped with gentle safe grades. All disturbed areas

associated with borrow pits are part of the restoration plan.

Approved Borrow Areas

Location Map of Borrow Pits (N-70, Lot-1)

Page 41: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

38

Location Map of Borrow pits (N-70, Lot-2)

Page 42: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

39

List of Approved Borrow Areas at Lot-1 (N-50)

Sr. No. Borrow

No Location Area L/S or R/S Remarks

1 37 RD 37+660 100 R/S

2 38 RD 3+000 70 L/S

3 39 RD 3+940 50 L/S

4 40 RD 4+300 100 R/S

5 41 RD 29+500 80 L/S

6 42 RD 39+900 60 R/S

7 43 RD 46+123 20 L/S

8 44 RD 46+300 40 R/S

Page 43: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

40

Page 44: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

41

Page 45: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

42

Annexure III: Layout Plan of Base Camps

Base Camp Lay-out Plan of UJ- XGHEC (JV) Lot-1 (N-70)

Page 46: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

43

Base Camp Lay-out Plan of Maqbool-Zarghoon (JV) Lot-2 (N-70)

Page 47: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

44

Base Camp Layout Plan of Maqbool-Zarghoon (JV) Lot-2 (N-50)

Page 48: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

45

Annexure IV: Environmental Monitoring Results for July-Dec. 2017

1. Noise Level Measurements (N-70)

S.NO Type Of Vehicle Location Noise Level PPEs Remarks

1 Grader N-70 44 dB safety shoes, jacket

2 Roller N-70 38 dB safety shoes, jacket

3 Excavator Chain N-70 70 dB safety shoes, jacket

4 Excavator Tire N-70 35 dB safety shoes, jacket

5 Dozer N-70 74 dB safety shoes helmet jacket air plug

6 Loader N-70 38 dB safety shoes, jacket

7 Concrete Mixture N-70 33 dB safety shoes, jacket

8 Crain N-70 37 dB safety shoes helmet jacket

9 Paver N-70 35 dB safety shoes helmet jacket Mask

10

Water Pump chef

engine N-70 84 dB safety shoes helmet air plug

11

Concrete

Vibrator N-70 76 dB safety shoes helmet jacket air plug

12 Water Tanker N-70 44 dB safety shoes

13 Trailer N-70 40 dB safety shoes

14 Dumper N-70 42dB safety shoes

15 PTR Roller N-70 36 dB safety shoes, jacket

16 Tandem Roller N-70 33 dB safety shoes, jacket

17 Compressor

N-70 77 dB

safety shoes helmet air plug, jacket

Mask

18 Diesel Tank N-70 35 dB coverall safety shoes helmet jacket

19 Transit Mixture N-70 33 dB safety shoes

20 Tractor N-70 66dB safety shoes, jacket

21 Diesel point N-70 28 dB coverall safety shoes helmet jacket

22 Crush Plant

N-71 84 dB

coverall safety shoes helmet jacket air

muff

23 Asphalt plant N-70 80 dB coverall safety shoes helmet jacket

24 Batching Plant N-70 55 dB

coverall safety shoes helmet jacket air

muff Mask

25 Workshop N-70 NIL coverall safety shoes helmet jacket

26 Site Labor N-70 NIL safety shoes helmet jacket

27 Site staff N-70 NIL safety shoes helmet jacket

28 structure labor N-70 NIL

coverall safety shoes helmet jacket

gloves

Page 49: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

46

Page 50: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

47

2. Water Quality Analysis Samples (N-70)

Page 51: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

48

Page 52: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

49

Page 53: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

50

Page 54: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

51

3. Air Quality Monitoring Report (N-70)

Page 55: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

52

Page 56: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

53

Page 57: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

54

Page 58: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

55

Page 59: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

56

Page 60: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

57

Annexure V: Traffic Diversion Plans (N-70 & N-50)

Page 61: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

58

Page 62: PAK: National Highway Network Development in Balochistan … · 2018-05-02 · 2 Engr. Zubair Ahmed Bajkani Project Director NHA, Quetta N-70 3 Major (R) Adnan Farukh Hassan Resident

Bi-Annual Environmental Monitoring Report July-December 2017

59