pak: mff – power distribution enhancement investment … · 2015-02-03 · 1- bi-annual...

26
Social Monitoring Report Bi-annual Social Monitoring Report January 2015 PAK: MFF – Power Distribution Enhancement Investment Program (Tranche 3) Prepared by Multan Electric Power Company, Punjab for the Asian Development Bank.

Upload: others

Post on 11-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Social Monitoring Report Bi-annual Social Monitoring Report January 2015

PAK: MFF – Power Distribution Enhancement

Investment Program (Tranche 3)

Prepared by Multan Electric Power Company, Punjab for the Asian Development Bank.

Page 2: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

NOTES

(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.

(ii) In this report “$” refer to US dollars. This social monitoring report is a document of the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Re: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014) Ashfaq Khokhar to. Liaqat Ali 29/01/2015 02:33 PM

Cc: Adnan Tareen, Rizwan Haider

Please disclose both reports but ask EA to provide details of all annexes. Annexes are mentioned in the

report but have no details provided.

Thanks

Ashfaq

Ashfaq Ahmed Khokhar

Sr. Social Safeguard Officer

Pakistan Resident Mission

Asian Development Bank

Tel (92) 051-2087300 Ext 230

Fax. +92 51 260 0365-66/208 7397-98

www.adb.org

AD13

Liaqat Ali

Dear Ashfaq: The below reports has not yet bee... 29/01/2015 01:51:24 PM

From: Liaqat Ali/PRM/ADB To: Ashfaq Khokhar/PRM/ADB@ADB, Cc: Adnan Tareen/CWRD/ADB@ADB Date: 29/01/2015 01:51 PM Subject: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)

Dear Ashfaq:

The below reports has not yet been reviewed by you. Please review and provide your comments and approve for disclosure.

Regards,

Liaqat Ali, Project Analyst. Pakistan Resident Mission

Level 8, North, Serena Office Complex, G-5, Islamabad/Pakistan

Tele: (92-51) 2600351-69/2087210 Fax: (92-51) 2600365-66/2087397-98 email: [email protected].

---- Forwarded by Liaqat Ali/PRM/ADB on 29/01/2015 01:49 PM

From: Liaqat Ali/PRM/ADB To: Ashfaq Khokhar/PRM/ADB@ADB, Cc: lmran Ali Memon/PRM/ADB@ADB, Rizwan Haider/Contractors/ADB@ADB Date: 20/01/2015 02:23 PM Subject: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)

Dear Ashfaq:

Please review the Social Monitoring Reports for Loans 2727 and 2972 received from MEPCO..

Page 4: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

ADB Tranche-III Biannual Social July-December, 2014(Excluding Photos).docx

ADB Tranche-II Biannual Social July-December, 2014(Excluding Photos).docx

Regards,

Liaqat Ali, Project Analyst, Pakistan Resident Mission

Level 8, North, Serena Office Complex, G-5, Islamabad/Pakistan

Tele: (92-51) 2600351-69/2087210 Fax: (92-51) 2600365-66/2087397-98

email: [email protected].

---- Forwarded by Liaqat Ali/PRM/ADB on 20/01/2015 02:21 PM

From: Asif Riaz <[email protected]> To: "[email protected]" <[email protected]>, Lali <[email protected]>, Cc: "[email protected]" <[email protected]>, "[email protected]" <[email protected]>,

"[email protected]" <[email protected]>, Jeffrey Bowyer <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>

Date: 20/01/2015 02:11 PM Subject: Re: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)

Respected Madam & Sir

Kindly find attached following Internal Monitoring Reports in respect of MEPCO Multan

1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report of Tranche-II (L-2727-PK)

3- Bi-Annual Social Monitoring Report of Tranche-Ill (L-2972-PK)

Best Room's.

Syed Asif Riaz

On Tuesday. January 20, 2015 12:12 PM, "[email protected]" <[email protected]>

wrote:

Dear Asif,

Thank you for the Tranche 2 report. I have not yet received the Tranche 3 report, which

was to be sent by Monday, January 19. Please send it at the earliest so that the disclosure deadline may be met.

Regards,

Safia Shafiq

Environment Specialist (Consultant)

Pakistan Resident Mission Asian Development Bank

Page 5: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Level 8, North Wing, Serena Office Complex,

Khayaban-e-Suhrawardy G-5, Islamabad. Pakistan.

Tel: +92-51-2087300, Ext: 344

Fax: +92-51-2087397-8 & 2600365-6

Cell: +92-333-2154462

Asif Riaz <[email protected]> wrote:

To: "[email protected]" <[email protected]>

From: Asif Riaz <[email protected]>

Date: 01/16/2015 12:13AM

Cc: "[email protected]" <[email protected]>, "[email protected]"

<[email protected]>, "[email protected]" <[email protected]>, Jeffrey Bowyer

<[email protected]>, "[email protected]"

<[email protected]>, "[email protected]" <[email protected]>,

"[email protected]" <[email protected]>

Subject: Re: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)

Respected Madam

Kindly find attached Bi-annual Environment Monitoring Report of Tranche-II subprojects

(L-2727-PK) in respect of MEPCO Multan.

BAEMR of Tranche-Ill (L-2972-PK) shall be submitted on Monday 19-01-2015

Insha-ALLAH.

Best Regards. Syed Asti Riaz

On Saturday, January 3, 2015 6:39 PM, Asif Riaz <[email protected]> wrote:

Acknowledged Madam

Best Regards.. Syed Asif Riaz

On Friday, January 2, 2015 2:27 PM. "sshafiq.consultant©adb.org" <[email protected]> wrote:

Dear Asif,

The Bi-annual Environmental Monitoring Reports (Jul-Dec 2014) of MEPCO under PDEIP

tranches 2 (L-2727) and 3 (L-2972) are due for submission by January 15, 2015. Please note that two separate reports are required, one for each tranche. Kindly ensure that ADB's comments (if any) on the previous BAEMR Jan-Jun 2014 are taken into consideration while preparing the new reports.

Page 6: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

I look forward to a timely submission.

Regards,

Safia Shafiq

Environment Specialist (Consultant)

Pakistan Resident Mission

Asian Development Bank

Level 8, North Wing, Serena Office Complex,

Khayaban-e-Suhrawardy G-5, Islamabad, Pakistan.

Tel: +92-51-2087300, Ext: 344

Fax: +92-51-2087397-8 & 2600365-6

Cell: +92-333-2154462

[attachment "ADB Tranche-II Biannual Env. report Jul-Dec, 2014 (excluding

Photos)1.docx" removed by Safia Shafiq/Consultants/ADB]

Page 7: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

ADB

Bi-annual Sociai Say guard Monitc:irig Report

ASIAN DEVELOPMENT BANK

Project Number: 2972-PK

PAKISTAN RESIDENT MISSION ISLAMABAD

Islamic Republic of Pakistan: Power Distribution, Enhancement Investment

Program, Multi-Tranche Finance Facility (PDE7!'s:F!*--Tranche-111)

(Financed by the Asian Development Bank (ADB)

(July-December, 2014)

Prepared by: Muhammad Arif, Assistant Manager (Social)

Multan Electric Power Company (MEPCO)

Mu!tan, Pakistan

For Pakistan Electric Power Company (PEPCO)

Multan Electric Power Company (MEPCO)

This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and

the Government cannot be heldtliable for its contents.

Asian Development Bank

Page 8: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

1 Table of Contents

Subject Page

No.

1. Introduction and Background of the Project 2

1.1 Basic Data 2

1.2 Introduction 3

1.3 Scope of Work 3

2. Project wise Summary of the Subprojects 4

2.1 Mubarakpur 132 k

.: kV New Grid ration 4

2.1 Chunnaw01132 kV New Grid Station 4

2.3 Fortabbas 66 kV to 132 kV Conversation 4

2.4 Faqirwali 66 kV to 132 kV Conversation 5

2.5 Dahranwala 66 kV to 132 kV Conversation 5

2.6 Chak 83/12-1 66 kV to 132 kV Conversation --,

6

2.7 Shan Sadardin 66 kV to 1:-,7 kV Conversation 6

2.8 Monitoring of Project sites 7

3. Summary of Physical Works and Implementation Status 8

4. Involuntary Resettlement and Categorization of Project 8

5. Status of LARPs 10

10 5.1 Impact of Land Acquisition and Involuntary Resettlement

5. Social Safeguard Awareness and Training 13

7. Conclusion and Recommendation 14

7.1 Conclusion 14

73. Recommendation 14

Photographs and Annex -. 15

--777-=7,11.21. 31;

Page 9: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

S

2

1. INTRODUCTION AND BACKGROUND OF THE PROJECT

A. BASIC DATA

1. ADB Loan No. 2972-PAK

2. Project Title Power Distribution Enhancement

Isives'ime;-it Project Trancne III

3. Borrower Islamic Republic of Pakistan

4. Executing Agency Pakistan Electric Power Company

(PEPCO)

5. Implementing Agency Mu[tan Electric Power Company Ltd.

(MErco)

6. Total Project Cost US $ 35.18 Million

Total US $ 31.79 Million 7. ADB Loan

Withdrawal US $ 30.93 Million

8. Loan Approval Date

9. Loan Signing Date September 09, 2013

10. Date of Effectiveness December 10, 2013

11. Date of Closing

i) Original

ii) Revised

Juii?, 2013

12. Date of Physical Completion

i) Original

ii) Revised

14. Elapsea Loan Period

i) Original

ii) Revised

11 Months

15. Date of Last ADB Review Mission 27.10.2014

Page 10: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

3

1.2 MEPCO Introduction

Multan Electric Power Company (MEPCO) is a Public Limited Utility Company.

established in 1998 under Companies Ordinance 1984, responsible for distribution of

Electric Power within its territorial jurisdiction in thirteen districts of Punjab Province. To

meet the increased power demand and to improve the grid stations and transmission

lines infrastructure MEPCO decided to approach the loaning agencies through

Government of Pakistan like Asian Development Bank, World Bank and other financing

sources to arrange financing. Negotiations were carried out with the Asian Development

Bank and the Bank has agreed to support the program through Multi Tranche Financing

Facility- i (MFF-1) to be implemented in three phases i.e. Tranche-I, II. III &IV.

1.3 Scope of Work

Asian Development Bank in Tranche - Ill is financing overall 10 Nos. of projects. The

detail of the subproject is as under.

i. Construction of 02 No. of New 132KV Grid Stations and allied

Transmission Lines

ii. Conversion of 05 Nus of Grid Substations fizrn 66kV to 132kV &

allied Transmission Lines

iii. 03 Nos. of Augmentations

Overall the proposed MFF has been designed to address both investment and

institutional aspects in electric power sector. Development Objectives/ Project Purpose

will be fully achieved after completion of he proposed Sub-projects.

• Civil works have started at Fortabbas, Faqirwali, Daharanwal and Chak 83/12-L

grid stations sites and 5% civil works completed. Survey for transmission line

route is being conducted and civil works for transmission lines will be started

after finalization of transmission line route.

• Assistant Manager (Environment) & Assistant Manager (Social) are working in

Environment & Social Cell (ESC) under Chief Engineer (Development) MEPCO

Multan in Project Management Unit (PMU)

3

Page 11: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

4

• PD(GSC), Contractor(s) and other related staff have been provided continuous

orientation on Environmental Management & Implementation of ADB guideline

and rules/regulations of Government of Pakistan.

2. PROJECT WISE SUMV.,".7.Y CF i HE PrIOJErT3 UNDER ADB TRANCHE -

II

2.1 Mubarakpur 132 kV New Grid Station and allied Transmission Line (Social

Monitoring)

MEPCO has purchase 6 acres of land from a landowner on voluntary sale bases

against negotiated price for construction of rew grid station and compensation payment

has been paid to the Affected Persons (see annex III). Therefore no social impacts

associated with the construction of grid station. However, there are some minor social

impacts associated with the construction of 1.5 km transmission line. Boundary wall has

been constructed and site is under the possession of MEPCO. Contractor has not

moved at Mubarakpur subproject site.

2.2 Chunnawala 132; kV New. Grid Station and allied Transmission Line (Social •

Monitoring)

MEPCO has acquired 11 acres of land from 'Provincial government for construction of

new grid station and amount has paid to ft. provincial government. Therefore no social

impacts associated with the construction of grid station. However, there are some minor

social impacts associated with the construction of 26 km transmission line. Boundary

wall has been constructed and site is under the possession of MEPCO. Contractor has

not moved at Chunnawal subproject site

2.3 Fortabbas Conversion of 66kV to 132 kV Grid Station and allied

Transmission Line (Social Moni,+nring)

Contractor has moved and 5% civil works for control room building and yard have been

completed although the conversion works are being carried out totally within the

boundary of the existing grid station without acquiring additional land. The construction

of 25 km transmission line will may cause to affect the crops and trees damages.

Page 12: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

5

• 5% civil works for control room building and switch yard completed.

• Civil works for allied Transmission line will be started after survey completion and

finalization of line route.

• Contrcctor was asked to Make sure he provision of all '-levant documents at

site and all requiten-lei itiaid in cor,tract agrecr.ct ri lust be fully implement.

• Contractor was also asked to make sure the use of all safety gadgets/PPEs.

Onsite orientation/training session was arranged for the use of PPEs. They were

also instructed to take into the account of local norms and values.

2.4 Faciirwali Conversion of 66kV 132 kV Grid Station and allied

Transmission Line (Social Monitoring)

Contractor has moved and 5% civil works for control room building and yard have been

completed although the conversion works are being carried out totally within the

boundary of the existing grid station without acquiring additional land. The construction

of 25 km transmission line will may cause to affect the crops and trees damages

• 5% civil works for control room building and switch yard completed.

• Civil works for allied Transmission line will be started after survey completion and

finalization of line route.

• Contractor was asked to make sure the provision of all relevant documents at

site and all requirement laid in contract agreement must be fully implement.

• Contractor was also asked to make sure the use of all safety gadgets/PPEs.

Onsite orientation/training session was arranged for the use of PPEs. They were

also instructed to take into the account of local norms and values.

2.5 Daharanwala Cwivemion of 36kV to 132 !;',/- Grid Station and allied

Transmission Line (Social Monitoring)

Contractor has moved and 5% civil works for control room building and yard have been

completed although the conversion works are being carried out totally within the

5

Page 13: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

6

boundary of the existing grid station withwit 2cquiring additional land. The construction

of 25 km transmission line will may cause to affect the crops and trees damages

. . . • 5% civil works for control room building and switch yard completed.

• Civil works for allied Tt8tiSthission line will be started after survey completion and

finalization of line route.

• Contractor was asked to make sure the provision of all relevant documents at

site and all requirement laid in contract agreement must be fully implement.

• Contractor was also asked to make , sure the use of all safety gadgets/PPEs.

Onsite orientation/training session ar.anged for the use of PPEs. They were

also instructed to take into the account of local norms and values.

2.6 Chak 83/12-L Conversion of 661,V to 132 kV Grid Station and allied

Transmission Line (Social Monitoring)

Contractor has moved and 5% civil works for control room building and yard have been•

completed although the conversion works are being carried out totally within the •

boundary of he existing grid station without acquiring additional land. The construction

of 25 km transmission line will riay cause to affect i■le ci.:.ps nri freo, damages

• 5% civil works for control room building and switch yard completed.

• Civil works for allied Transmission line will be started after survey completion and

finalization of line route.

• Contractor was asked to make suis tho provision of all relevant documents at

site and all requirement laid in contract agreement must be fully implement.

• Contractor was also asked to make sure the use of all safely gadgets/PPEs.

Onsite orientation/training session was arranged for the use of PPEs. They were

also instructed to take into the account of local norms and values.

2.7 Shah Sadar Din Conversion of 66kV to 132 kV Grid Station and allied

Transmission Line (Social Monitoring)

Contractor not moved yet and civil works not initiated

Page 14: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

7

2.8 Monitoring visits of Project Sites

11- ESC PMU has conducted site monitoring of following site. Detail is as under

i. New 132kV Chunnawala Grid St-3!ion Site

Date: 15-1-15

ii. Conversion of 66KV to 132 KV Alipur Grid Station and allied Transmission

Line

Date: 15-1-15

iii. Conversion of 66KV to 132 KV Fagirwali Grid Station and allied Transmission

Line

Date15-01-15

iv. Conversion of 66KV to 132 KV Daharanwala Grid Station and allied

Transmission Line

Date:15-01-15

v. Conversion of 66KV to 132 KV Chak 83/12-L Grid Station and allied

Transmission Line

Date:12-01-15

vi. Conversion of 66KV to 132 KV Shandadar Din Grid Station and allied

Transmission Line

Date:15-10-14

7

A

Page 15: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

8

3. Summary of Physical Works and Compensation Status

Sr.

No. Name of Subproject Compensatior.

Status Remarks

1 Mubarakpur 132 kV

New Grid Station Paid

Grid Station

• Land has been purchased on willing seller willing buyer basis and after negotiation compensation amounting Rs. 7,200,000/- against land acquired has been paid to the affected person(s).

Transmission Line

• Contractor not moved.

2 Chunnawala 132 kV

New Grid Station Paid

• Land has been acquired from provincial government and amount paid to provincial government _

Transmission Line

• Contractor not moved.

3

Forabbas 132 kV

(conversation from 66

k.v" to 132. kV) grid

station and allied T/L

T/L works no;

initiotP6 +

Grid station

• All works will be carried out within the boundary of existing grid

ry station therefore additional

:-,,, id is not acquired for this subproject.

Transmission Line

• Contractor not moved

4

Faqirwali 132 kV

(conversation from 66

kV to 132 kV) grid

station and allied T/L

T/L works not

initiated

Grid station

• All works will be carried out within the boundary of existing grid station therefore land is not acquired for this subproject.

Transmission Line

• Contractor not moved

5 Daharanwala 132

kV(conversation from

66 kV to 132 kV) grid

T/L works not.

initiated

Grid station

• All works civil works are being carried out within the boundary

Page 16: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Name of Subproject Compen.5:;:ition

Status

Sr.

No. Remarks

of existing grid station therefore land is not acquired for this subproject.

Transmission Line

station and T/L

•, Contractor not moved Grid srat!,-,-,,,

• All works civil works are being carried out within the boundary of existing grid station therefore land is not acquired for this subproject.

Transmission Line

Contractor not moved

Grid station

• Contractor not moved Transmission Line

Contractor not moved

6

Chak 83/12-L, 132

kV(conversation from

66 kV to 132 kV) grid

station and T/L

T/L works not

initiated

7

Shahsadar Din 132

kV(conversation from

66 kV to 132 kV) grid

station and T/L

T/L works not

initiated

9

4. Involuntary Resettlement Identification and Categorization

There are 07 out of 10 Projects which fall in Category-B (02 No. of New Grid Stations

and allied T/Lines and 05 No of T/Lines for conversion of 66 KV to 132 KV grid stations)

requires short LARP preparation, implementation, monitoring and uploading/ posting at

ADB and MEPCO official website. While 03 Nos. of subprojects fall in Category-C,

does not require any LARP as projects are being executed within the boundary of

already existing grid stations.

9

Page 17: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

10

5. Status of LARPs

LARPs for Tranche-Ill have been prepared and approved by MEPCO and uploaded at

MEPCO website (www.mepco.com.pk). Project information booklets in Urdu have been

sent to each project site. LARPs after update will be translated into Urdu and summary

will be sent to the project affected persons.

5.1 Impact of Land Acquisition and Involuntary Resettlement

Name of

Project

Land

Acquisition

Status

Catego,i; of

subproject

Status of

LARPIDDR

Status of

Compensation

Land for grid

station has

been

purchased

willing seller

willing buyer

bases.

As this

subproject

falls in

category B

therefore a

LARP

has been

prepared and

uploaded on

MEPCO

website both

in Urdu and

English

Grid Station

Compensation for

grid station land has

been paid

Transmission Line

Contractor not

moved

Mubarakpi Ir

132 kV New

Grid Station

ri his oroject

fall in

category B

Land for grid

station has

been

purchased

willing seller

willing buyer

bases.

As this

subproject

falls in

category B

therefore a

short LARP

has been

prepared and

uploaded on

MEPCO

website both

in, Urdu and

English

Grid Station

Compensation for

grid station land has

been paid

Transmission Line

Contractor not

moved

Chunnawal

132 kV New

Grid Station

This projeer

fall in

category B

Page 18: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

11

Name of

Project

Land

Acquisition

Status

Category of

subproject

Status of

LARP/DDR

Status of

Compensation

Fortabbas

Conversion of

66 kV to 132

kV grid station

are being

executed on

existing grid

station

therefore no

land is

acquired for

this subproject

As this

subproject

falls in

category B

therefore a

short LARP

has been

prepared and

uploaded on

MEPCO

website both

in Urdu and

English

Grid Station

Compensation for

grid station is not

applicable

Transmission Line

Contractor not

moved.

This project

fall in

category B

Faqirwali

Daharanwala

Conversion of

66 kV to 132

kV grid station

are being

executed on

existing grid

station

therefore no

land is

acquired for

this subproject

Conversion of

66 kV to 132

kV grid station

are being

executed on

existing grid

station

therefore no

land is

This project

fall in

category B

This prcject

fall in

category B

P.s this

subproject

falls in

category B

therefore a

short LARP

has been

prepared and

uploaded on

MEPCO

wc -wI4, 'Loth

in Urdu and

English

As this

subproject

falls in

category B

therefore a

short LARP

has been

prepared and

uploaded on

Grid Station

Compensation for

grid station is not

applicable

Transmission Line

Contractor not

moved.

Grid Station

Compensation for

grid station is not

applicable

Transmission Line

Contractor not

moved.

11

Page 19: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

12

Name of

Project

Category ', of

subproject

Status of

LARP/DDR

Status of

Compensation

Land

Acquisition

Status

acquired for

this subproject

tMEPCO

website both

in Urdu and

English

Conversion of

66 kV to 132

kV grid station

are being

executed on

existing grid

station

therefore no

land is

acquired for

this subproject

This project

fall in

category B

As this

subproject

falls in

category B

therefore s

short LARP

has been

prepared and

uploaded on

MEPCO

website both

in Urdu and

English

Chak 83/12-L

Shahsadar

Din

As this

subproject

falls in

category B

therefore a

short LARP

has been

prepared and

uploaded on

MEPCO

website both

in Urdu and

English

This project

fall in

category B

Conversion of

66 kV to 132

kV grid station

are being

executed on

existing grid

station

therefore no

land is

acquired for

this subproject

Grid Station

Compensation for

grid station is not

applicable

Transmission Line

Contractor not

moved.

Grid Station

Compensation for

grid station is not

applicable

Transmission Line

Contractor not

moved.

Page 20: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

13

6. Social Safeguard Awareness & Trainings

Environmental and Social orientation/awareness training sessions organized at each

subproject site for implementation of Environmental Management Plan. Awareness

sessions with M/S PEL and M/S ICC's subcontractor have conducted for environmental

and social safeguard awareness and ADB's Environmental guidelines which need be

implemented on subproject sites.

13

Page 21: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

14

7. CONCLUSlON AND RECOMMENDATIONS

7.1 Conclusions

Contractor has moved and civil works have started at Fortabbas, Faqirwali, Dahranwala

and chak 83/12-L subproject sites. Surveys are being conducted to get the transmission

lines route finalized. Contractors have been asked to implement the environment and

social management plan. Contractor was akd directed to make sure the provision and

use of all safety gadgets/PPEs. Onsite orientation/training session was arranged for the

use of PPEs. They were also instructed to take into the account of local norms and

values.

7.2 Recommendations

From the findings of the Monitoring Visits„ the following mitigation measures are

proposed to be implemented in order to minimize any potentially significant impacts:

• It is also recommended that the process of communication and consultation with

the community representatives is aggressively maintained.

• Construction work of new T/lines should be planned in accordance with LARPs"

and DDRs to minimize the affect of construction activities.

• Site should restore properly after the completion of construction activities.

• Proper housekeeping can avoid littering.

• To avoid any accident contractor should make the use of PPEs compulsory.

• Timely compensation to the affected persons can avoid any hindrance and may

lead towards in time execution of the project.'

• d 6:so oboorqed thr:t contrac(or(s),does not give to environmental and

social aspects and considered it unnecessary burden over them

• All pertinent bills with reference to EMP management should be vetted by the

Environmental and Social Safeguard section after on site verification.

Page 22: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

15

• Photographs

Figure 1: Civil works in progress at Fortabbas grid site

Figure 2:- littering and lack of waste rtanagernent observed at Fortabbas site

15

Page 23: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

.e. 4,104.

'141,60 4..

• .

Figure 3: Onsite orientation/a session conducted at Faqirwali grid site

• t7V:

Figure 4:- Littering, and workers without PPEs observed at Faqirwali site

I

Page 24: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Figure 5: Civil works' in progress at Dahranwala site

Figure 6: Onsite orientation/awareness session conducted at Dahranwala grid site

17

I

Page 25: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

Figure 7: Chak 83!12L subproject site

Figure 8: Chunnawala 132 1:v New grid station subproject site.

Page 26: PAK: MFF – Power Distribution Enhancement Investment … · 2015-02-03 · 1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report

.. Figure 9: Shahsadlr Din "bproject site

19

19