Social Monitoring Report Bi-annual Social Monitoring Report January 2015
PAK: MFF – Power Distribution Enhancement
Investment Program (Tranche 3)
Prepared by Multan Electric Power Company, Punjab for the Asian Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.
(ii) In this report “$” refer to US dollars. This social monitoring report is a document of the Borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Re: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014) Ashfaq Khokhar to. Liaqat Ali 29/01/2015 02:33 PM
Cc: Adnan Tareen, Rizwan Haider
Please disclose both reports but ask EA to provide details of all annexes. Annexes are mentioned in the
report but have no details provided.
Thanks
Ashfaq
Ashfaq Ahmed Khokhar
Sr. Social Safeguard Officer
Pakistan Resident Mission
Asian Development Bank
Tel (92) 051-2087300 Ext 230
Fax. +92 51 260 0365-66/208 7397-98
www.adb.org
AD13
Liaqat Ali
Dear Ashfaq: The below reports has not yet bee... 29/01/2015 01:51:24 PM
From: Liaqat Ali/PRM/ADB To: Ashfaq Khokhar/PRM/ADB@ADB, Cc: Adnan Tareen/CWRD/ADB@ADB Date: 29/01/2015 01:51 PM Subject: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)
Dear Ashfaq:
The below reports has not yet been reviewed by you. Please review and provide your comments and approve for disclosure.
Regards,
Liaqat Ali, Project Analyst. Pakistan Resident Mission
Level 8, North, Serena Office Complex, G-5, Islamabad/Pakistan
Tele: (92-51) 2600351-69/2087210 Fax: (92-51) 2600365-66/2087397-98 email: [email protected].
---- Forwarded by Liaqat Ali/PRM/ADB on 29/01/2015 01:49 PM
From: Liaqat Ali/PRM/ADB To: Ashfaq Khokhar/PRM/ADB@ADB, Cc: lmran Ali Memon/PRM/ADB@ADB, Rizwan Haider/Contractors/ADB@ADB Date: 20/01/2015 02:23 PM Subject: Fw: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)
Dear Ashfaq:
Please review the Social Monitoring Reports for Loans 2727 and 2972 received from MEPCO..
ADB Tranche-III Biannual Social July-December, 2014(Excluding Photos).docx
ADB Tranche-II Biannual Social July-December, 2014(Excluding Photos).docx
Regards,
Liaqat Ali, Project Analyst, Pakistan Resident Mission
Level 8, North, Serena Office Complex, G-5, Islamabad/Pakistan
Tele: (92-51) 2600351-69/2087210 Fax: (92-51) 2600365-66/2087397-98
email: [email protected].
---- Forwarded by Liaqat Ali/PRM/ADB on 20/01/2015 02:21 PM
From: Asif Riaz <[email protected]> To: "[email protected]" <[email protected]>, Lali <[email protected]>, Cc: "[email protected]" <[email protected]>, "[email protected]" <[email protected]>,
"[email protected]" <[email protected]>, Jeffrey Bowyer <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>, "[email protected]" <[email protected]>
Date: 20/01/2015 02:11 PM Subject: Re: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)
Respected Madam & Sir
Kindly find attached following Internal Monitoring Reports in respect of MEPCO Multan
1- Bi-Annual Environment Monitoring Report of Tranche-Ill (L-2972-PK) 2- Bi-Annual Social Monitoring Report of Tranche-II (L-2727-PK)
3- Bi-Annual Social Monitoring Report of Tranche-Ill (L-2972-PK)
Best Room's.
Syed Asif Riaz
On Tuesday. January 20, 2015 12:12 PM, "[email protected]" <[email protected]>
wrote:
Dear Asif,
Thank you for the Tranche 2 report. I have not yet received the Tranche 3 report, which
was to be sent by Monday, January 19. Please send it at the earliest so that the disclosure deadline may be met.
Regards,
Safia Shafiq
Environment Specialist (Consultant)
Pakistan Resident Mission Asian Development Bank
Level 8, North Wing, Serena Office Complex,
Khayaban-e-Suhrawardy G-5, Islamabad. Pakistan.
Tel: +92-51-2087300, Ext: 344
Fax: +92-51-2087397-8 & 2600365-6
Cell: +92-333-2154462
Asif Riaz <[email protected]> wrote:
To: "[email protected]" <[email protected]>
From: Asif Riaz <[email protected]>
Date: 01/16/2015 12:13AM
Cc: "[email protected]" <[email protected]>, "[email protected]"
<[email protected]>, "[email protected]" <[email protected]>, Jeffrey Bowyer
<[email protected]>, "[email protected]"
<[email protected]>, "[email protected]" <[email protected]>,
"[email protected]" <[email protected]>
Subject: Re: L-2727, L-2972 PDEIP: Submission of BAEMRs (Jul-Dec 2014)
Respected Madam
Kindly find attached Bi-annual Environment Monitoring Report of Tranche-II subprojects
(L-2727-PK) in respect of MEPCO Multan.
BAEMR of Tranche-Ill (L-2972-PK) shall be submitted on Monday 19-01-2015
Insha-ALLAH.
Best Regards. Syed Asti Riaz
On Saturday, January 3, 2015 6:39 PM, Asif Riaz <[email protected]> wrote:
Acknowledged Madam
Best Regards.. Syed Asif Riaz
On Friday, January 2, 2015 2:27 PM. "sshafiq.consultant©adb.org" <[email protected]> wrote:
Dear Asif,
The Bi-annual Environmental Monitoring Reports (Jul-Dec 2014) of MEPCO under PDEIP
tranches 2 (L-2727) and 3 (L-2972) are due for submission by January 15, 2015. Please note that two separate reports are required, one for each tranche. Kindly ensure that ADB's comments (if any) on the previous BAEMR Jan-Jun 2014 are taken into consideration while preparing the new reports.
I look forward to a timely submission.
Regards,
Safia Shafiq
Environment Specialist (Consultant)
Pakistan Resident Mission
Asian Development Bank
Level 8, North Wing, Serena Office Complex,
Khayaban-e-Suhrawardy G-5, Islamabad, Pakistan.
Tel: +92-51-2087300, Ext: 344
Fax: +92-51-2087397-8 & 2600365-6
Cell: +92-333-2154462
[attachment "ADB Tranche-II Biannual Env. report Jul-Dec, 2014 (excluding
Photos)1.docx" removed by Safia Shafiq/Consultants/ADB]
ADB
Bi-annual Sociai Say guard Monitc:irig Report
ASIAN DEVELOPMENT BANK
Project Number: 2972-PK
PAKISTAN RESIDENT MISSION ISLAMABAD
Islamic Republic of Pakistan: Power Distribution, Enhancement Investment
Program, Multi-Tranche Finance Facility (PDE7!'s:F!*--Tranche-111)
(Financed by the Asian Development Bank (ADB)
(July-December, 2014)
Prepared by: Muhammad Arif, Assistant Manager (Social)
Multan Electric Power Company (MEPCO)
Mu!tan, Pakistan
For Pakistan Electric Power Company (PEPCO)
Multan Electric Power Company (MEPCO)
This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and
the Government cannot be heldtliable for its contents.
Asian Development Bank
1 Table of Contents
Subject Page
No.
1. Introduction and Background of the Project 2
1.1 Basic Data 2
1.2 Introduction 3
1.3 Scope of Work 3
2. Project wise Summary of the Subprojects 4
2.1 Mubarakpur 132 k
.: kV New Grid ration 4
2.1 Chunnaw01132 kV New Grid Station 4
2.3 Fortabbas 66 kV to 132 kV Conversation 4
2.4 Faqirwali 66 kV to 132 kV Conversation 5
2.5 Dahranwala 66 kV to 132 kV Conversation 5
2.6 Chak 83/12-1 66 kV to 132 kV Conversation --,
6
2.7 Shan Sadardin 66 kV to 1:-,7 kV Conversation 6
2.8 Monitoring of Project sites 7
3. Summary of Physical Works and Implementation Status 8
4. Involuntary Resettlement and Categorization of Project 8
5. Status of LARPs 10
10 5.1 Impact of Land Acquisition and Involuntary Resettlement
5. Social Safeguard Awareness and Training 13
7. Conclusion and Recommendation 14
7.1 Conclusion 14
73. Recommendation 14
Photographs and Annex -. 15
--777-=7,11.21. 31;
S
2
1. INTRODUCTION AND BACKGROUND OF THE PROJECT
A. BASIC DATA
1. ADB Loan No. 2972-PAK
2. Project Title Power Distribution Enhancement
Isives'ime;-it Project Trancne III
3. Borrower Islamic Republic of Pakistan
4. Executing Agency Pakistan Electric Power Company
(PEPCO)
5. Implementing Agency Mu[tan Electric Power Company Ltd.
(MErco)
6. Total Project Cost US $ 35.18 Million
Total US $ 31.79 Million 7. ADB Loan
Withdrawal US $ 30.93 Million
8. Loan Approval Date
9. Loan Signing Date September 09, 2013
10. Date of Effectiveness December 10, 2013
11. Date of Closing
i) Original
ii) Revised
Juii?, 2013
12. Date of Physical Completion
i) Original
ii) Revised
14. Elapsea Loan Period
i) Original
ii) Revised
11 Months
15. Date of Last ADB Review Mission 27.10.2014
3
1.2 MEPCO Introduction
Multan Electric Power Company (MEPCO) is a Public Limited Utility Company.
established in 1998 under Companies Ordinance 1984, responsible for distribution of
Electric Power within its territorial jurisdiction in thirteen districts of Punjab Province. To
meet the increased power demand and to improve the grid stations and transmission
lines infrastructure MEPCO decided to approach the loaning agencies through
Government of Pakistan like Asian Development Bank, World Bank and other financing
sources to arrange financing. Negotiations were carried out with the Asian Development
Bank and the Bank has agreed to support the program through Multi Tranche Financing
Facility- i (MFF-1) to be implemented in three phases i.e. Tranche-I, II. III &IV.
1.3 Scope of Work
Asian Development Bank in Tranche - Ill is financing overall 10 Nos. of projects. The
detail of the subproject is as under.
i. Construction of 02 No. of New 132KV Grid Stations and allied
Transmission Lines
ii. Conversion of 05 Nus of Grid Substations fizrn 66kV to 132kV &
allied Transmission Lines
iii. 03 Nos. of Augmentations
Overall the proposed MFF has been designed to address both investment and
institutional aspects in electric power sector. Development Objectives/ Project Purpose
will be fully achieved after completion of he proposed Sub-projects.
• Civil works have started at Fortabbas, Faqirwali, Daharanwal and Chak 83/12-L
grid stations sites and 5% civil works completed. Survey for transmission line
route is being conducted and civil works for transmission lines will be started
after finalization of transmission line route.
• Assistant Manager (Environment) & Assistant Manager (Social) are working in
Environment & Social Cell (ESC) under Chief Engineer (Development) MEPCO
Multan in Project Management Unit (PMU)
3
4
• PD(GSC), Contractor(s) and other related staff have been provided continuous
orientation on Environmental Management & Implementation of ADB guideline
and rules/regulations of Government of Pakistan.
2. PROJECT WISE SUMV.,".7.Y CF i HE PrIOJErT3 UNDER ADB TRANCHE -
II
2.1 Mubarakpur 132 kV New Grid Station and allied Transmission Line (Social
Monitoring)
MEPCO has purchase 6 acres of land from a landowner on voluntary sale bases
against negotiated price for construction of rew grid station and compensation payment
has been paid to the Affected Persons (see annex III). Therefore no social impacts
associated with the construction of grid station. However, there are some minor social
impacts associated with the construction of 1.5 km transmission line. Boundary wall has
been constructed and site is under the possession of MEPCO. Contractor has not
moved at Mubarakpur subproject site.
2.2 Chunnawala 132; kV New. Grid Station and allied Transmission Line (Social •
Monitoring)
MEPCO has acquired 11 acres of land from 'Provincial government for construction of
new grid station and amount has paid to ft. provincial government. Therefore no social
impacts associated with the construction of grid station. However, there are some minor
social impacts associated with the construction of 26 km transmission line. Boundary
wall has been constructed and site is under the possession of MEPCO. Contractor has
not moved at Chunnawal subproject site
2.3 Fortabbas Conversion of 66kV to 132 kV Grid Station and allied
Transmission Line (Social Moni,+nring)
Contractor has moved and 5% civil works for control room building and yard have been
completed although the conversion works are being carried out totally within the
boundary of the existing grid station without acquiring additional land. The construction
of 25 km transmission line will may cause to affect the crops and trees damages.
5
• 5% civil works for control room building and switch yard completed.
• Civil works for allied Transmission line will be started after survey completion and
finalization of line route.
• Contrcctor was asked to Make sure he provision of all '-levant documents at
site and all requiten-lei itiaid in cor,tract agrecr.ct ri lust be fully implement.
• Contractor was also asked to make sure the use of all safety gadgets/PPEs.
Onsite orientation/training session was arranged for the use of PPEs. They were
also instructed to take into the account of local norms and values.
2.4 Faciirwali Conversion of 66kV 132 kV Grid Station and allied
Transmission Line (Social Monitoring)
Contractor has moved and 5% civil works for control room building and yard have been
completed although the conversion works are being carried out totally within the
boundary of the existing grid station without acquiring additional land. The construction
of 25 km transmission line will may cause to affect the crops and trees damages
• 5% civil works for control room building and switch yard completed.
• Civil works for allied Transmission line will be started after survey completion and
finalization of line route.
• Contractor was asked to make sure the provision of all relevant documents at
site and all requirement laid in contract agreement must be fully implement.
• Contractor was also asked to make sure the use of all safety gadgets/PPEs.
Onsite orientation/training session was arranged for the use of PPEs. They were
also instructed to take into the account of local norms and values.
2.5 Daharanwala Cwivemion of 36kV to 132 !;',/- Grid Station and allied
Transmission Line (Social Monitoring)
Contractor has moved and 5% civil works for control room building and yard have been
completed although the conversion works are being carried out totally within the
5
6
boundary of the existing grid station withwit 2cquiring additional land. The construction
of 25 km transmission line will may cause to affect the crops and trees damages
. . . • 5% civil works for control room building and switch yard completed.
• Civil works for allied Tt8tiSthission line will be started after survey completion and
finalization of line route.
• Contractor was asked to make sure the provision of all relevant documents at
site and all requirement laid in contract agreement must be fully implement.
• Contractor was also asked to make , sure the use of all safety gadgets/PPEs.
Onsite orientation/training session ar.anged for the use of PPEs. They were
also instructed to take into the account of local norms and values.
2.6 Chak 83/12-L Conversion of 661,V to 132 kV Grid Station and allied
Transmission Line (Social Monitoring)
Contractor has moved and 5% civil works for control room building and yard have been•
completed although the conversion works are being carried out totally within the •
boundary of he existing grid station without acquiring additional land. The construction
of 25 km transmission line will riay cause to affect i■le ci.:.ps nri freo, damages
• 5% civil works for control room building and switch yard completed.
• Civil works for allied Transmission line will be started after survey completion and
finalization of line route.
• Contractor was asked to make suis tho provision of all relevant documents at
site and all requirement laid in contract agreement must be fully implement.
• Contractor was also asked to make sure the use of all safely gadgets/PPEs.
Onsite orientation/training session was arranged for the use of PPEs. They were
also instructed to take into the account of local norms and values.
2.7 Shah Sadar Din Conversion of 66kV to 132 kV Grid Station and allied
Transmission Line (Social Monitoring)
Contractor not moved yet and civil works not initiated
7
2.8 Monitoring visits of Project Sites
11- ESC PMU has conducted site monitoring of following site. Detail is as under
i. New 132kV Chunnawala Grid St-3!ion Site
Date: 15-1-15
ii. Conversion of 66KV to 132 KV Alipur Grid Station and allied Transmission
Line
Date: 15-1-15
iii. Conversion of 66KV to 132 KV Fagirwali Grid Station and allied Transmission
Line
Date15-01-15
iv. Conversion of 66KV to 132 KV Daharanwala Grid Station and allied
Transmission Line
Date:15-01-15
v. Conversion of 66KV to 132 KV Chak 83/12-L Grid Station and allied
Transmission Line
Date:12-01-15
vi. Conversion of 66KV to 132 KV Shandadar Din Grid Station and allied
Transmission Line
Date:15-10-14
7
A
8
3. Summary of Physical Works and Compensation Status
Sr.
No. Name of Subproject Compensatior.
Status Remarks
1 Mubarakpur 132 kV
New Grid Station Paid
Grid Station
• Land has been purchased on willing seller willing buyer basis and after negotiation compensation amounting Rs. 7,200,000/- against land acquired has been paid to the affected person(s).
Transmission Line
• Contractor not moved.
2 Chunnawala 132 kV
New Grid Station Paid
• Land has been acquired from provincial government and amount paid to provincial government _
Transmission Line
• Contractor not moved.
3
Forabbas 132 kV
(conversation from 66
k.v" to 132. kV) grid
station and allied T/L
T/L works no;
initiotP6 +
Grid station
• All works will be carried out within the boundary of existing grid
ry station therefore additional
:-,,, id is not acquired for this subproject.
Transmission Line
• Contractor not moved
4
Faqirwali 132 kV
(conversation from 66
kV to 132 kV) grid
station and allied T/L
T/L works not
initiated
Grid station
• All works will be carried out within the boundary of existing grid station therefore land is not acquired for this subproject.
Transmission Line
• Contractor not moved
5 Daharanwala 132
kV(conversation from
66 kV to 132 kV) grid
T/L works not.
initiated
Grid station
• All works civil works are being carried out within the boundary
•
Name of Subproject Compen.5:;:ition
Status
Sr.
No. Remarks
of existing grid station therefore land is not acquired for this subproject.
Transmission Line
station and T/L
•, Contractor not moved Grid srat!,-,-,,,
• All works civil works are being carried out within the boundary of existing grid station therefore land is not acquired for this subproject.
Transmission Line
Contractor not moved
Grid station
• Contractor not moved Transmission Line
Contractor not moved
6
Chak 83/12-L, 132
kV(conversation from
66 kV to 132 kV) grid
station and T/L
T/L works not
initiated
7
Shahsadar Din 132
kV(conversation from
66 kV to 132 kV) grid
station and T/L
T/L works not
initiated
9
4. Involuntary Resettlement Identification and Categorization
There are 07 out of 10 Projects which fall in Category-B (02 No. of New Grid Stations
and allied T/Lines and 05 No of T/Lines for conversion of 66 KV to 132 KV grid stations)
requires short LARP preparation, implementation, monitoring and uploading/ posting at
ADB and MEPCO official website. While 03 Nos. of subprojects fall in Category-C,
does not require any LARP as projects are being executed within the boundary of
already existing grid stations.
9
10
5. Status of LARPs
LARPs for Tranche-Ill have been prepared and approved by MEPCO and uploaded at
MEPCO website (www.mepco.com.pk). Project information booklets in Urdu have been
sent to each project site. LARPs after update will be translated into Urdu and summary
will be sent to the project affected persons.
5.1 Impact of Land Acquisition and Involuntary Resettlement
Name of
Project
Land
Acquisition
Status
Catego,i; of
subproject
Status of
LARPIDDR
Status of
Compensation
Land for grid
station has
been
purchased
willing seller
willing buyer
bases.
As this
subproject
falls in
category B
therefore a
LARP
has been
prepared and
uploaded on
MEPCO
website both
in Urdu and
English
Grid Station
Compensation for
grid station land has
been paid
Transmission Line
Contractor not
moved
Mubarakpi Ir
132 kV New
Grid Station
ri his oroject
fall in
category B
Land for grid
station has
been
purchased
willing seller
willing buyer
bases.
As this
subproject
falls in
category B
therefore a
short LARP
has been
prepared and
uploaded on
MEPCO
website both
in, Urdu and
English
Grid Station
Compensation for
grid station land has
been paid
Transmission Line
Contractor not
moved
Chunnawal
132 kV New
Grid Station
This projeer
fall in
category B
11
Name of
Project
Land
Acquisition
Status
Category of
subproject
Status of
LARP/DDR
Status of
Compensation
Fortabbas
Conversion of
66 kV to 132
kV grid station
are being
executed on
existing grid
station
therefore no
land is
acquired for
this subproject
As this
subproject
falls in
category B
therefore a
short LARP
has been
prepared and
uploaded on
MEPCO
website both
in Urdu and
English
Grid Station
Compensation for
grid station is not
applicable
Transmission Line
Contractor not
moved.
This project
fall in
category B
Faqirwali
Daharanwala
Conversion of
66 kV to 132
kV grid station
are being
executed on
existing grid
station
therefore no
land is
acquired for
this subproject
Conversion of
66 kV to 132
kV grid station
are being
executed on
existing grid
station
therefore no
land is
This project
fall in
category B
This prcject
fall in
category B
P.s this
subproject
falls in
category B
therefore a
short LARP
has been
prepared and
uploaded on
MEPCO
wc -wI4, 'Loth
in Urdu and
English
As this
subproject
falls in
category B
therefore a
short LARP
has been
prepared and
uploaded on
Grid Station
Compensation for
grid station is not
applicable
Transmission Line
Contractor not
moved.
Grid Station
Compensation for
grid station is not
applicable
Transmission Line
Contractor not
moved.
11
12
Name of
Project
Category ', of
subproject
Status of
LARP/DDR
Status of
Compensation
Land
Acquisition
Status
acquired for
this subproject
tMEPCO
website both
in Urdu and
English
Conversion of
66 kV to 132
kV grid station
are being
executed on
existing grid
station
therefore no
land is
acquired for
this subproject
This project
fall in
category B
As this
subproject
falls in
category B
therefore s
short LARP
has been
prepared and
uploaded on
MEPCO
website both
in Urdu and
English
Chak 83/12-L
Shahsadar
Din
As this
subproject
falls in
category B
therefore a
short LARP
has been
prepared and
uploaded on
MEPCO
website both
in Urdu and
English
This project
fall in
category B
Conversion of
66 kV to 132
kV grid station
are being
executed on
existing grid
station
therefore no
land is
acquired for
this subproject
Grid Station
Compensation for
grid station is not
applicable
Transmission Line
Contractor not
moved.
Grid Station
Compensation for
grid station is not
applicable
Transmission Line
Contractor not
moved.
13
6. Social Safeguard Awareness & Trainings
Environmental and Social orientation/awareness training sessions organized at each
subproject site for implementation of Environmental Management Plan. Awareness
sessions with M/S PEL and M/S ICC's subcontractor have conducted for environmental
and social safeguard awareness and ADB's Environmental guidelines which need be
implemented on subproject sites.
13
14
7. CONCLUSlON AND RECOMMENDATIONS
7.1 Conclusions
Contractor has moved and civil works have started at Fortabbas, Faqirwali, Dahranwala
and chak 83/12-L subproject sites. Surveys are being conducted to get the transmission
lines route finalized. Contractors have been asked to implement the environment and
social management plan. Contractor was akd directed to make sure the provision and
use of all safety gadgets/PPEs. Onsite orientation/training session was arranged for the
use of PPEs. They were also instructed to take into the account of local norms and
values.
7.2 Recommendations
From the findings of the Monitoring Visits„ the following mitigation measures are
proposed to be implemented in order to minimize any potentially significant impacts:
• It is also recommended that the process of communication and consultation with
the community representatives is aggressively maintained.
• Construction work of new T/lines should be planned in accordance with LARPs"
and DDRs to minimize the affect of construction activities.
• Site should restore properly after the completion of construction activities.
• Proper housekeeping can avoid littering.
• To avoid any accident contractor should make the use of PPEs compulsory.
• Timely compensation to the affected persons can avoid any hindrance and may
lead towards in time execution of the project.'
• d 6:so oboorqed thr:t contrac(or(s),does not give to environmental and
social aspects and considered it unnecessary burden over them
• All pertinent bills with reference to EMP management should be vetted by the
Environmental and Social Safeguard section after on site verification.
15
• Photographs
Figure 1: Civil works in progress at Fortabbas grid site
Figure 2:- littering and lack of waste rtanagernent observed at Fortabbas site
15
.e. 4,104.
'141,60 4..
• .
Figure 3: Onsite orientation/a session conducted at Faqirwali grid site
• t7V:
•
Figure 4:- Littering, and workers without PPEs observed at Faqirwali site
I
Figure 5: Civil works' in progress at Dahranwala site
Figure 6: Onsite orientation/awareness session conducted at Dahranwala grid site
17
I
Figure 7: Chak 83!12L subproject site
Figure 8: Chunnawala 132 1:v New grid station subproject site.
•
.. Figure 9: Shahsadlr Din "bproject site
19
19