Page 1ERCOT Project Status
1
ERCOT Dynamic Ratings
METF
March 29, 2012
![Page 2: Page 1 ERCOT Project Status 1 ERCOT Dynamic Ratings METF March 29, 2012](https://reader036.vdocuments.us/reader036/viewer/2022082805/5519b8c055034667578b48cc/html5/thumbnails/2.jpg)
Page 2ERCOT Project Status
Conceptual Model
ProcessedRatings
ICCP
WeatherForecast
Data
Dynamic RatingsApplication
SCADA
Portal
StaticTable
RawRatings
Weather Bank
Real TimeNetwork
Applications
Real Time MarketClearance Engine
Day AheadStudies
![Page 3: Page 1 ERCOT Project Status 1 ERCOT Dynamic Ratings METF March 29, 2012](https://reader036.vdocuments.us/reader036/viewer/2022082805/5519b8c055034667578b48cc/html5/thumbnails/3.jpg)
Page 3ERCOT Project Status
Dynamic Ratings – Weather Stations and Zones
![Page 4: Page 1 ERCOT Project Status 1 ERCOT Dynamic Ratings METF March 29, 2012](https://reader036.vdocuments.us/reader036/viewer/2022082805/5519b8c055034667578b48cc/html5/thumbnails/4.jpg)
Page 4ERCOT Project Status
Dynamic Ratings Weather Stations to Zone Mapping
Weather Zone Station 1 Station 2 Station 3
North Central 50% -- Dallas 25% -- Waco 25% -- Mineral Wells
East 50% -- Tyler 50% -- Lufkin
North 50% -- Witchita Falls 50% -- Paris
Far West 50% -- Wink 50% -- Midland
West 40% -- Abeline 40% -- San Angelo 20% -- Junction
South Central 50% -- Austin 50% -- San Antonio
Coast 50% -- Houston 30% -- Galveston 20% -- Victoria
Southern 40% -- Corpus Christi 40% -- Brownsville 20% -- Lardeo
![Page 5: Page 1 ERCOT Project Status 1 ERCOT Dynamic Ratings METF March 29, 2012](https://reader036.vdocuments.us/reader036/viewer/2022082805/5519b8c055034667578b48cc/html5/thumbnails/5.jpg)
Page 5ERCOT Project Status
Dynamic Ratings – Real Time Process
• Ratings may be supplied via ICCP. Three ratings (normal, emergency, and 15 minute) must be submitted for each line.
• If ICCP data is not supplied or if ICCP is currently unavailable, ratings from a standard table mapped to temperatures are used.
• Updates are made in near real-time and applied to SCED
• For jointly-owned lines, the most conservative value will be used.
![Page 6: Page 1 ERCOT Project Status 1 ERCOT Dynamic Ratings METF March 29, 2012](https://reader036.vdocuments.us/reader036/viewer/2022082805/5519b8c055034667578b48cc/html5/thumbnails/6.jpg)
Page 6ERCOT Project Status
Dynamic Ratings Project – Look Ahead Process
• All lines have static temperature versus ratings tables defined by the owning TSP.
• All lines use the forecasted temperature of a nearby weather station (or weather zone temperature), as assigned by the TSP.
• ERCOT uses its 168hr weather station forecast data updated hourly by the weather vendor for both load forecasting and dynamic ratings.
• The resulting temperature-adjusted ratings are used for all RUC and manual future studies performed on the power system network.
• For jointly-owned lines or for lines that cross multiple weather stations, the most conservative value will be used.