Tips Tricks with Version Six (Client)Don Louser PMP, PMA Consultants LLC
![Page 2: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/2.jpg)
2
Give Us Your Card
• There are more items in this presentation than we will have time to demonstrate
• Give us your business card and we will send you the entire presentation complete with notes
• Or, contact me @ [email protected]
![Page 3: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/3.jpg)
3
• What’s New in Client v. 6.0 (Slides 1-20)• Use of Indicators (Slide 21)• Global Changes – De-status the Schedule (Slides 22-26)• Global Changes – Change WBS from Filters (Slide 27)• Export and Importing Projects (Slides 28-39)• Project details that are often forgotten (Slides 40-42)• Renumbering Activities (Slides 43-45)• Building your Schedule – Making a List (Slides 46-47)• Building your Schedule - Linking Shortcuts (Slide 48)• The Schedule Report (Slides 49-52)• Lag Calendars (Slides 53-54)
What we have for you today...
![Page 4: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/4.jpg)
4
• Fragnets (Slides 55-58)• Coding and WBS Shortcuts (Slides 59-63)• Finding and Filtering Activities (Slides 64-65)• Roles and Resource Loading (Slides 66)• Schedule Crashing Basics (Slides 67-68)• Advanced Layouts For Communication (Slides 69-71)• Advanced Gantt Chart Formatting (Slides 72-76)• Exporting and Importing Layouts/Reports (Slide 77)• Add Bar-charts & Graphics to Reports (Slides 78-83)• Working with Baselines (Slides 84-91)
What we have for you today (cont.)...
![Page 5: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/5.jpg)
5
What’s New – Reflection Projects
• Power with Simplicity !!!
• A Reflection is a Copy of a Project that enhances Your Ability to “What If” or Update Your Project
• Same Name – What If – Internal Link to Source – Baseline –Timesheet Data – Activity Owner
• “Activity Owner” make changes via .xer or Web
• Review & Change or Merge As Is (Check Boxes)
• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection
DEMO
![Page 6: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/6.jpg)
6
What’s New - Create Reflection Project
![Page 7: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/7.jpg)
7
Making Changes to Reflection Projects
• Use to test Scenarios or Update Project
• Send w/Project Specific Layout to Others to Update
• Import/Export just like any other Project file
• Activity Owner – designate Owner w/Required Web License & Privileges to Update/Change
• Admin or Project Superuser gets last shot to Review/Correct before merging back into Source Project
• Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection
![Page 8: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/8.jpg)
8
Merging Reflection into Source Project
• Close all Projects
• Go to Projects Table – Select Reflection Project
• Right Click – Merge Reflection into Source Project
![Page 9: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/9.jpg)
9
Merging Reflection into Source Project
![Page 10: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/10.jpg)
10
Merging Reflection into Source Project
![Page 11: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/11.jpg)
11
Merging Reflection into Source Project
![Page 12: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/12.jpg)
12
What’s New – Future Bucket Planning
• Redistribute Even Distribution of Budgeted Units
• Editable Security Privilege
• Duration Type Must be Fixed Duration & Units, or Fixed Duration & Units/Time
• Use Resource Spreadsheet or Resource Assignment
• In Future Bucket Period type or change Values as Needed
![Page 13: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/13.jpg)
13
What’s New – Future Bucket Planning
4010R10R4A8A8AFuture Bucket
4088888Even Spread
TOTALDay 5Day 4Day 3Day 2Day 1
•Assuming Daily TS – P5 spread evenly
•Actual levels of work may vary
•Example shows 20 A units in 3 days
•Remaining needs to be adjusted
•Two remaining buckets reflect adjustment
•Activity Adjusted must have Fixed Duration & Units, orFixedDuration & Units/Time
•Use Resource Spreadsheet to adjust future bucket period
![Page 14: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/14.jpg)
14
Edit Future Bucket Security
![Page 15: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/15.jpg)
15
What’s New – Group & Sort Dialog
• New Checkbox for Show Group Totals, Shrink Vertical Bands
SHOW PIX & EXPLAIN
![Page 16: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/16.jpg)
16
What’s New - Search in Pop-Up Dialog and Type Ahead in Drop Down
SHOW PIX & EXPLAIN
![Page 17: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/17.jpg)
17
What’s New - Copy Baselines• Checkbox in Copy Project Options
• Copy Baselines Dialog
# Copies Controlled by New Setting in Admin Preferences
![Page 18: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/18.jpg)
18
Admin preferences Setting for Copying Baselines
![Page 19: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/19.jpg)
19
What’s New - Role Limits
• Similar to Limits for Resources
• Effective Date and Max Units/Time
![Page 20: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/20.jpg)
20
What’s new – Project Specific Layouts (Yeah!)
• Layout with Filter when Project Exported
• Reduces Need for Global Layouts
• Only Global and Layout Filters will Restrict Use
• Expanded & Collapsed Bars & Row Height Setting when switching between layouts and Windows (Yeah!)
![Page 21: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/21.jpg)
21
Use of Indicators
![Page 22: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/22.jpg)
22
Re-create a Baseline, Copy an Existing Schedule that has Been Progressed
Project Detail Calculations Tab =
Any Actual Units that Exist Must be set to 0• See Actual Units Slide
Run 2 Global Changes to Reset Activities to Not Started
• See De-Progress GCs
Make any Needed Changes and Reschedule
Useful Global Changes –De-Status the Schedule
Skip
![Page 23: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/23.jpg)
23
Actual Work Units
Useful Global Changes –De-Status the Schedule (cont.)
Go Back
![Page 24: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/24.jpg)
24
De-Statusthe GC’s
Useful Global Changes –De-Status the Schedule (cont.)
Go Back
![Page 25: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/25.jpg)
25
Sometimes...
An Activity may have a Unit without a Resource Assigned...
Errors?
![Page 26: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/26.jpg)
26
Useful Global Changes –De-Status the Schedule (cont.)
Delete Manually, or Use the Fill-Down Feature
Set Cols for All Units
![Page 27: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/27.jpg)
27
Useful Global Changes –Change WBS Based on Filters
![Page 28: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/28.jpg)
28
Primavera PM/MM (.xer)
MS Project
Project Planner (P3)
Spreadsheet (.xls)
Primavera Contractor 4.1 (.xer)
Exporting and Importing Projects
![Page 29: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/29.jpg)
29
1. Select Items for Export
2. Separate Sheet for Each Item
Exporting and Importing Projects – Spreadsheet (.XLS)
![Page 30: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/30.jpg)
30
3. Select a Project (it must be open)
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 31: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/31.jpg)
31
4. Establish Templates for each Item
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 32: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/32.jpg)
32
5. Certain items are mandatory, and you can filter & sort
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 33: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/33.jpg)
33
6. Select any or all templates
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 34: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/34.jpg)
34
7. Select the file path and name
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 35: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/35.jpg)
35
8. Confirm before you finish
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
![Page 36: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/36.jpg)
36
One Worksheet Per Subject
Exporting and Importing Projects (cont.)
![Page 37: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/37.jpg)
37
Caution! – Don’t Edit this Sheet
Exporting and Importing Projects (cont.)
![Page 38: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/38.jpg)
38
Importing is a Snap!
Importing Projects
![Page 39: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/39.jpg)
39
Importing Projects (cont.)
![Page 40: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/40.jpg)
40
Project details that are often forgotten
![Page 41: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/41.jpg)
41
Project details that are often forgotten
![Page 42: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/42.jpg)
42
Project details that are often forgotten
![Page 43: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/43.jpg)
43
Many GCs like Intelligent IDs
CSI Code – Bldg – Floor
Establish UDF (Activity) or Activity Code
Put in Column in Layout
Type Codes in Column
Use Global Change
Codes Become Activity IDs
Renumbering Activities
![Page 44: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/44.jpg)
44
Leave Blank
Renumbering Activities (cont.)
![Page 45: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/45.jpg)
45
For those a bit more familiar with (GC’s)
Create Activity Code
Add Activity Code column in Layout
Fill Column
Create GC’s that add suffix for Bldg & Floor
Renumbering Activities (cont.)
![Page 46: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/46.jpg)
46
Building your schedule – Making a list
![Page 47: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/47.jpg)
47
Building your schedule – Making a list
![Page 48: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/48.jpg)
48
<Ctrl-Click> the order to link the activities, then <right-click> your mouse and choose “Link Activities.”
They are now linked in the order you clicked on them.
Building your schedule – Linking shortcuts
![Page 49: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/49.jpg)
49
When you schedule your project, don’t forget to choose “Log to file” and click on the ellipsis to specify the location of the “schedule.txt” file.
Always view the log to spot errors.
Building your schedule – The Schedule Report
![Page 50: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/50.jpg)
50
Building your schedule – The Schedule Report
![Page 51: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/51.jpg)
51
Building your schedule – The Schedule Report
![Page 52: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/52.jpg)
52
Building your schedule – The Schedule Report
![Page 53: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/53.jpg)
53
Lag Calendars and Schedule Result - Version 5.0
+ =
![Page 54: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/54.jpg)
54
Lag Calendars Reschedule
+ =
?
This has been changed in v 6.0 to default to the predecessor
![Page 55: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/55.jpg)
55
• Time Saving – why recreate the wheel?– Building a Single Schedule– Modifying Many Schedules
• Create New or Modify Existing– New = As You Would New Project– Modify = Delete from Existing
• WBS is the Key to Integration
Fragnets
![Page 56: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/56.jpg)
56
Modify a template with a Fragnet
Fragnets (cont.) 2 Projects
Move to 2 WBS elements
To Here
From Here
![Page 57: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/57.jpg)
57
Objective – Add 22 new Activities in Template to 2 WBS Nodes
• Copy the Template as Fragnet, Delete All Activities Except those to Remain in Planning & Design WBS Nodes
• Add the 22 New Activities & All Links to Fragnet
• Open Template & Fragnet
• Delete All Activities in Planning & Design TemplateWBS Nodes
• Select & Copy All Fragnet Activities
Fragnets (cont.)
![Page 58: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/58.jpg)
58
• Paste into one of the empty Template Nodes (Preserves all Links)
• Control-Click all Activities to be moved to other Node
• <Ctrl-X> (Cut)
• <Ctrl-V> (Paste) into other Node
• Re-establish any Links from 2 Nodes to others
• Use Template to create new Schedules
Fragnets (cont.)
![Page 59: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/59.jpg)
59
Here is one person’s Layout
Coding and WBS Shortcuts
![Page 60: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/60.jpg)
60
Coding and WBS Shortcuts (cont.)
![Page 61: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/61.jpg)
61
Coding and WBS Shortcuts (cont.)
![Page 62: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/62.jpg)
62
Here. the work is organized by WBS1 and Level
Coding and WBS Shortcuts (cont.)
![Page 63: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/63.jpg)
63
Here, the work is organized only by Level
Coding and WBS Shortcuts (cont.)
![Page 64: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/64.jpg)
64
Unleash the power of Find with <Ctrl-F>
Finding and Filtering Activities
![Page 65: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/65.jpg)
65
Finding and Filtering Activities (cont.)
![Page 66: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/66.jpg)
66
• Roles are placeholders for Resources that are not yet assigned. • Roles allow teams to be assigned quickly to project activities, once the resource team is identified.• Only resources for roles that are unfilled are shown in the assign resources for roles dialogue box.• <Shift-Click> and <Ctrl-Click> can be used to select the activities being assigned resources by roles.• A project team could be assigned to all of the project’s activities at once.
Roles and Resource Loading
![Page 67: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/67.jpg)
67
28 DaysTotal Duration
Schedule Crashing Basics
![Page 68: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/68.jpg)
68
28 Days Total Duration
Assume We Need to Reduce Duration by 5 Days
Schedule Crashing Basics (cont.)
![Page 69: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/69.jpg)
69
• User Defined Fields
• Bring in Related Data from Other Sources
• Tabular + Graphic Presentation
Advanced Layouts to Enhance Communication
![Page 70: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/70.jpg)
70
Schedule DataUser Defined Random Data
Advanced Layouts to Enhance Communication (cont.)
![Page 71: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/71.jpg)
71
Advanced Layouts to Enhance Communication (cont.)
![Page 72: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/72.jpg)
72
Advanced Gantt Chart Formatting
![Page 73: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/73.jpg)
73
Advanced Gantt Chart Formatting
![Page 74: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/74.jpg)
74
Advanced Gantt Chart Formatting
![Page 75: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/75.jpg)
75
Advanced Gantt Chart Formatting
![Page 76: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/76.jpg)
76
Advanced Gantt Chart Formatting
![Page 77: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/77.jpg)
77
.plf filename extension
Exporting and Importing Layouts and Reports
![Page 78: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/78.jpg)
78
Adding Barchart Graphics to Reports
1. Create a layout that you want to print in your report
2. From the tool menu or print preview, choose Publish
3. Choose the directory for the report
4. Open a notebook topic and insert the graphic
5. Include that notebook topic in your tabular report
6. Run the report
BC1
![Page 79: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/79.jpg)
Slide 78
BC1 Please doublecheck first bullet. Thanks, BCBill Camarda, 10/17/2006
![Page 80: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/80.jpg)
79
Publish to HTML
From the Tool menu or Print Preview, choose Publish
Adding Barchart Graphics to Reports (cont.)
![Page 81: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/81.jpg)
80
Adding Graphics to Reports
![Page 82: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/82.jpg)
81
Click on the Picture Icon, and browse for a graphic file to insert into the Notebook topic
Adding Graphics to Reports (cont.)
![Page 83: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/83.jpg)
82
Adding Graphics to Reports (cont.)
![Page 84: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/84.jpg)
83
![Page 85: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/85.jpg)
84
Baselines are an established method of tracking progress and measuring results
When you first begin using Baselines, you may see some strange results that are difficult to diagnose
Baselines can refer to either the Current Project or another Project
How can you know which, without opening?
Working with Baselines
![Page 86: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/86.jpg)
85
Baseline CodeProject
DateResp
Sort
Why Alpha Prefix??
Add aBaselineColumn
Working with Baselines (cont.)
Sort by BLName
![Page 87: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/87.jpg)
86
Are we a year ahead?
Is the Current Schedule Ahead or Behind the Original Plan?
Working with Baselines (cont.)
![Page 88: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/88.jpg)
87
Summarized Dates
Something is Wrong?
Working with Baselines (cont.)
MAGIC!
![Page 89: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/89.jpg)
88
Perform a Global Change on a Baseline
Working with Baselines (cont.)
![Page 90: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/90.jpg)
89
1
2 PL Strt = Start (Milestone): If = SM, Then, PS = Start
3
Here are the details...
Working with Baselines (cont.)
![Page 91: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/91.jpg)
90
Here are the changes
Working with Baselines (cont.)
![Page 92: P6 tips tricks-client](https://reader033.vdocuments.us/reader033/viewer/2022051323/5492633fac7959ff2d8b45df/html5/thumbnails/92.jpg)
91
Questions?