p planning
DESCRIPTION
TRANSCRIPT
1
Project Planning
24/09/2006 Emad Elbeltagi 2
Project Planning
Planning in General : SWOT analysisS: StrengthsW: WeaknessesO: OpportunitiesT: Threats
Objectives should be: SMARTS: SpecificM: MeasurableA: AchievableR: RealisticT: Timely
2
24/09/2006 Emad Elbeltagi 3
Project Planning
Everybody
Somebody
Nobody
Anybody
TASK
24/09/2006 Emad Elbeltagi 4
Project PlanningCharacteristics of a good plan
Based on clearly definite and practical objectives
Simple
Flexible
Easy to control
Provide proper standards
Exploit existing resources, etc.
3
24/09/2006 Emad Elbeltagi 5
Project PlanningPlanning Inputs and Outputs
Contract informationDrawings
SpecificationsAvailable resources
Bills of quantitiesSite reports
Organizational dataConstruction methods
ActivitiesRelationships among activitiesMethod statementResponsibility Reporting levelsProject network diagramActivities durationActivities cost
INPUTS OUTPUTS
PLANNING
24/09/2006 Emad Elbeltagi 6
Project PlanningPlanning Major steps
Determination of Project Activities (WHAT)
Establishment of Logic; Relationships and overlap (WHEN)
Presentation (Table, Network, Chart, …)
Estimate Activities’ Duration and Cost (HOW)
4
24/09/2006 Emad Elbeltagi 7
Project PlanningWork Breakdown Structure (WBS)
The WBS is a hierarchical structure which is designed to logically sub-divide all the work-elements of the project into smaller elements.
House
Civil Plumping Electrical
Foundations Walls/Roof
Piping
H/C Water
Wiring Finishing
24/09/2006 Emad Elbeltagi 8
Project PlanningWork Breakdown Structure (Why)
Prepare project plan
Identifying Activities
Scheduling
Identifying cost & schedule at various levels of
details
Time & cost control
Identifying individual or departmental responsibilities
5
24/09/2006 Emad Elbeltagi 9
Project PlanningWBS & Organizational Breakdown Structure (OBS)
Project
Area 1 Area 3
Beams Columns Slabs
Formwork Reinforcement Concreting
OBS (Responsibility & reporting)
Area 2 ……
……
……
Project manager
WBS (Work elements)
Subcontractor A
General contractor
Subcontractor B
Civil superinte
ndent
Mechanical
superintendent
Electrical superinte
ndent
Formwork foreman
Rebar foreman
Concrete foreman
Control account
24/09/2006 Emad Elbeltagi 10
Project PlanningWBS Coding
Each work package or activity in a WBS is given a unique code that is used in project planning and control Identifying Activities
6
24/09/2006 Emad Elbeltagi 11
Project PlanningProject Activities
Project is divided into segments of work called activities
Activity: Time-consuming single work element
Guidelines for project breakdown: by: area of
responsibility, structural element, category of work, etc.
Level of details depends on: planning stage, size of the
project, complexity of the work, etc.
24/09/2006 Emad Elbeltagi 12
Project PlanningProject Activities
Types of construction activities:
Production: taken directly from drawings and/or
specifications
Management (Approvals, site establishment, …etc).
Procurement (equipment delivery, material
procurement)
7
24/09/2006 Emad Elbeltagi 13
Project PlanningProject Activities
Example (Double Span Bridge):
24/09/2006 Emad Elbeltagi 14
Project PlanningActivities Relationships
The order in which project activities are to be performed
Which activity(ies) must be completed before an activity
can start
Which activity(ies) can not start until activity completion
Which activity(ies) have no logical relations
Logic constraints: Physical, and Resources
8
180, 190Clear site200
155Bridge railing190
155, 160, 170Road surface 180
150Right road base170
140Left road base160
110, 120Construct deck slab155
90Fill right embankment150
80Fill left embankment140
16, 90, 100Erect right P.C. Beams120
16, 80, 100Erect left P.C. Beams110
70Construct central pier100
60Construct right abutment90
50Construct left abutment 80
14, 40Foundation central pier70
14, 30Foundation right abutment60
14, 20Foundation left abutment 50
10Excavate central pier40
10Excavate right abutment30
10Excavate left abutment 20
---Procure P.C. Beams16
---Procure RFT14
---Set-up site10
PredecessorsDescriptionCode
24/09/2006 Emad Elbeltagi 16
Project PlanningType of Activities Relationships
Four Types:Finish to Start (FS) Finish to Finish (FF)Start to Start (SS) Start to Finish (SF)
FS FF
SS SF
9
24/09/2006 Emad Elbeltagi 17
Project PlanningOverlapshow much a particular activity must be completed
before a succeeding activity may start
Used for activities not using the same type of resources
With a value less than the duration of the preceding activity
+ve overlap (-ve lag) -ve overlap (+ve lag)
24/09/2006 Emad Elbeltagi 18
Project PlanningOverlapsExample
Consider the construction of the following sequential activities of
a bridge consists of 19 bays
Pile manufacturing with duration 2.5 wks/pier
Pile driving with duration 1.5 wks/pier
Pile cap with duration 2.0 wks/pier
Pier shaft with duration 2.5 wks/pier
Determine the appropriate overlap between activities
10
24/09/2006 Emad Elbeltagi 19
Project PlanningRelationships Considering Resource Constraints
-A1B1
A1B1, A2C1, B2
A2B2, A3C2, B3
-A1B1
-A2B2
-A3B3
Excavate unit 1Concreting unit 1Brickwork unit 1
Excavate unit 2Concreting unit 2Brickwork unit 2
Excavate unit 3Concreting unit 3Brickwork unit 3
A1B1C1
A2B2C2
A3B3C3
Predecessors (constrained resources)
Predecessors (unconstrained
resources)descriptionActivity
24/09/2006 Emad Elbeltagi 20
Project PlanningProject networks: AOA
Two Types:Activity-On-Arrow; AOA (Arrow Networks).Activity-On-Node; AON (Precedence Networks):
AOAActivity represented as arrows with start and finish nodes called
Events
i jActivity A
j > i
11
24/09/2006 Emad Elbeltagi 21
Project PlanningProject networks: AOA
5 A 10 15BB depends on A
5 A 10 15C
5
BC depends on A and B
5 A 10 15C
15B B depends on A
C depends on A
5B 10
15D
15C B depends on A and B
D depends on A and B
5 A
24/09/2006 Emad Elbeltagi 22
Project PlanningProject networks: AOA
Dummy activityActivity with zero duration and no resources to adjust the network
Incorrect representation
5A
15 20C
10
B
C depends on A and BD depends on B only
25
D
Correct representation
15
5A
20 25C
10B 30D
Dummy
15A5
B
5 15A
10
BDummy
12
24/09/2006 Emad Elbeltagi 23
Project PlanningProject networks: AON
AOAActivity represented as nodes
10A
Activity number
Activity name
24/09/2006 Emad Elbeltagi 24
Project PlanningProject networks: AON
B depends on A10A
20B
C depends on A and BD depends on C
10A
30C
20B
40D
B depends on AC depends on BD depends on B
10A
20B
40D
30C
13
24/09/2006 Emad Elbeltagi 25
Project PlanningProject networks: Example
--
A, BCCD
D, E
ABCDEFG
PredecessorsActivity
24/09/2006 Emad Elbeltagi 26
Project PlanningProject networks: Example (AOA)
14
24/09/2006 Emad Elbeltagi 27
Project PlanningProject networks: Example (AON)
SS(Start)=12=SS(Start)+12=SS(Start)+13=Highest of [SS(B), SS(A)]4=SS(C)+14=SS(C)+15=SS(D)+15=Highest of [SS(D), SS(E)]6= Highest of [SS(F), SS(G)]
-StartStartA, B
CCD
D, EF, G
StartABCDEFG
Finish
Sequence step (SS)PredecessorsActivity
Calculate the Sequence step
24/09/2006 Emad Elbeltagi 28
Project PlanningProject networks: Example (AON)
Sequence step 1 2 3 4 5 6
15
24/09/2006 Emad Elbeltagi 29
Project PlanningActivity Duration & Direct Cost
Planning time unit (hours, days, weeks, months)
Establish method statement (method of construction)
Specify number of resources, and hence output
Duration = Quantity of work / No. of Res. x Res. Output
24/09/2006 Emad Elbeltagi 30
Project PlanningActivity Duration & Direct Cost
Productivity data
Man-hours/ unitMhrs/unit
Daily productionUnits/day
How long it takes form one labor to finish one unit
Applies to any crew formation
How many units can be done in one time unit
Applies to a given crew
Productivity can be estimated:
From published data ( الموسوعة الهندسية(
Previous records of a company
16
24/09/2006 Emad Elbeltagi 31
Project PlanningActivity Duration & Direct CostExampleWhat is the duration to install 6000 square feet of walls shuttering if:
Crew of 2 carpenters is used, output of 200 square feet/day Productivity is measured as 0.008 man-hour/square feet. Number of carpenters =3, and number of working hours/day = 8 hours
a. Duration = 6000 / 200 = 3 days
b. Total man-hours needed = 6000 x 0.008 = 48 man-hours (if one man used)
Duration = 48 / 8 = 6 days (if one man used)Duration using 3 men = 6 / 3 = 2 days
24/09/2006 Emad Elbeltagi 32
Project PlanningActivity Duration & Direct CostExample (balanced mix of resources)
A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.
- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.
- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
- using one steel-fixer: duration = 50 / 0.5 = 100 days
- using one carpenter: duration = 790 / 16 = 49.4 days
- using one concreting crew: duration = 660 / 16 = 41.25 days.
2 steel-fixer crews, one carpenter crew, and cone concreting crew. duration = 50 / 0.5 x 2 = 50 days
17
24/09/2006 Emad Elbeltagi 33
Project PlanningActivity Duration & Direct Cost
Activity direct cost:
Duration, resources, and cost are interrelated elements
Direct cost comprises: labor, material, equipment, and/or
subcontractors
Unit cost = total cost / quantity