ownership of materials briefing note on site

Upload: khairul-hazwan

Post on 17-Oct-2015

28 views

Category:

Documents


0 download

DESCRIPTION

dispute against unfixed material between both parties

TRANSCRIPT

  • 1

    PART III:

    OWNERSHIP OF MATERIALS

    Briefing note Author: Roberta Vella Date: June 2009

    Contents

    Introduction Materials on site Materials off site Conclusion

    1 INTRODUCTION

    1.1 On the insolvency of the contractor the question arises as to who can claim

    ownership in materials that are intended for incorporation into the works.

    This paper considers the question of ownership of materials in the context of

    those on site and those off site: with reference to the common law, JCT

    Standard Design & Build Contract 2005, Revision 1 (2007) and NEC3 (June

    2005).

    2 MATERIALS ON SITE

    2.1 As discussed by Andrew Keeley in his paper, it is important that on the

    contractor's insolvency the site is secured so that materials on site are not

    removed by unpaid subcontractors or other possible creditors. This, of

    course, must be the starting point for an employer keen to complete the

    project and avoid as much delay as possible. However, as will be seen an

    employer does not have an automatic right to ownership of anything and

    everything on site. It is suggested that to begin with a distinction has to be

    made between materials affixed to the property and those merely placed on

    or adjacent to the works.

    2.2 In the absence of any express terms, the common law position is that where

    materials are affixed to a building ownership will pass to the freeholder1. In

    the context of a building contract, the materials will become the property of

    the employer: note that where the employer is not the freeholder the

    materials will become his property for the duration of his estate or interest in

    the property. The contractor is not permitted to reclaim or remove the

    materials even where the employer or a third party has subsequently

    severed them from the property2.

    2.3 Where materials are not affixed but on site then under common law

    ownership of the materials will pass as intended by the parties. This

    principle is contained in s.17 of the Sale of Goods Act 1979 (SGA). In

    determining the intention of the parties s.17(2) provides that regard should

  • 2

    be had to the terms of the contract, the conduct of the parties and the circumstances of the case.

    2.4 Common law has evolved a number of presumptions as to ascertaining

    intention where the parties had no intention or did not express an intention.

    These presumptions can now be found in s.18 of the SGA, Rules 1 to 5,

    which can be summarised as3:

    Rule 1: where the goods are specified and there are no conditions,

    property will pass when the contract is made, regardless of time of

    payment or delivery or both;

    Rule 2: where the goods are specified and the seller is bound to put

    the goods in a deliverable state, property will pass when the goods

    are put in a deliverable state and the buyer has been informed;

    Rule 3: where the goods are specified and the seller is bound to

    weigh, measure, test or do some act to ascertain the price, property

    will pass when that act is done and the buyer has been put on notice;

    Rule 4: where the goods are specified and the buyer is to give his

    approval of the goods, property will pass when the buyer signifies his

    approval or the buyer retains the goods without giving notice of

    rejection within a specified time or a reasonable time has lapsed;

    Rule 5: where the goods are unascertained or future goods sold by

    description, are in a deliverable state and unconditionally

    appropriated to the contract (where goods are delivered by the seller

    to a carrier or bailee for the purpose of transmission to the buyer and

    does not reserve the right of disposal), property will pass when either

    the buyer or the seller gives their assent.

    2.5 Where ownership has passed to the buyer then he may claim the goods if

    the seller becomes insolvent. In the case of the buyer becoming insolvent

    then the seller can claim the goods only if ownership has not passed.

    However, where the goods have been delivered to the buyer then the seller

    is only entitled to claim as a creditor for the price.

    2.6 A contract may contain a Romalpa 4 or retention of title clause. As a

    minimum these clauses state that a seller is to retain ownership of the goods

    until he receives payment5. Such clauses may simply retain ownership until

  • 3

    the goods have been paid for in full6, or go as far as to reserve the right of

    the seller to retake possession of the goods agreed to be sold in the event

    that payment is not made or in the event that a petition is presented to wind

    up the buyer (in such circumstances the seller is entitled to re-sell the

    goods)7. Under s.19 of the SGA the seller may reserve the right of disposal

    of the goods until the conditions imposed by the seller have been fulfilled.

    2.7 However, such a clause will not be effective where goods have been affixed

    to the property and a sub-contractor will not be able to assert such a

    provision as against an employer8.

    2.8 Clause 2.21 of the JCT Design & Build Contract 2005 deals with the

    question of the passing of property where materials are on site. Under this

    clause, materials do not need to be affixed to the property before ownership

    transfers to the employer, they merely have to be delivered to, placed on or adjacent to the Works, with the important element that they are

    intended for the works unless consent to remove them is given by the employer in writing.

    2.9 It is noted in Benjamin's Sale of Goods, 7th Edition, paragraph 5-157,

    footnote 69 that:

    Certain standard forms of building contract provide that unfixed materials delivered to the site are not to be removed without the

    consent of the architect of supervising officer, but such provision in the main contract would not be binding on a sub-contractor who was

    not a party to the main contract: Dawber Williamson Roofing Ltd v Humberside CC (1979) 14 Build. L.R. 70.

    2.10 This clause also makes provision for where materials have been paid for:

    providing that ownership passes to the employer but that the contractor shall

    remain responsible for loss or damage to them (depending on insurance

    options B or C having been elected).

    2.11 But would this clause be effective against a sub-contractor who supplies

    goods and materials to a main contractor under a contract of sale which is

    subject to a Romalpa clause - the goods are delivered to site but not affixed

    and the main contractor then becomes insolvent?

    2.12 The sub-contractor may not be able to recover the materials and goods from

    the employer if it is successfully argued that the main contractor had good

  • 4

    title9. Such an argument may be defeated where the sub-contractor

    successfully argues that:

    2.12.1 his contract with the main contractor was not one of sale of goods but

    a contract for work and materials, in which case s.25(1) of the SGA

    would not apply; or

    2.12.2 the facts may be such that there was no sale, pledge or other

    disposition of the goods by the main contractor to the employer

    sufficient for the employer to assert that he has acquired good title in

    the goods pursuant to s.25(1) of the SGA; or

    2.12.3 the employer may be on notice of the terms of the sub-contract as

    required under s.25(1) of the SGA (the sub-contractor may have

    been nominated by the employer).

    2.13 Note that under clause 8.5 of the JCT contract, on the insolvency of the

    contractor the employer is entitled to take all reasonable measures to ensure

    that the Site Materials (defined as all unfixed materials and goods

    delivered to and placed on or adjacent to the Works which are intended for incorporation) are retained on site and that the contractor shall not

    hinder or delay the employer taking these measures.

    2.14 NEC3 provides limited guidance compared to the JCT contract. Pursuant to

    clause 70.2 the employer will be able to assert whatever title the contractor

    has to the materials once brought within the Working Areas. It is suggested

    that the same rules as above apply: so that, if the goods have been fixed

    property passes to the freeholder. Where goods are not affixed, the

    intention of the parties will have to be ascertained; this will involve

    considering the terms of the contract (does it contain a Romalpa style

    clause?), the conduct of the parties and the circumstances of the case.

    2.15 Clause 70.2 is similar to the JCT contract, if slightly more prescriptive, in

    stating that title will pass back to the contractor if materials are removed from

    the Working Area with the consent of the Project Manager. Note that as

    mentioned in paragraph 2.11 above such a clause may be ineffective as

    against a sub-contractor.

  • 5

    3 MATERIALS OFF SITE

    3.1 An employer is in a weaker position where goods are held off site because

    he has no control over them and because they may not necessarily have

    been ascertained or identified as being required for incorporation into the

    works.

    3.2 The common law position is that ownership of materials held off site will pass

    as intended between the parties (see s.17 of the SGA). As mentioned

    above, the presumptions contained in s.18 of the SGA - Rules 1 to 5 - will

    assist in determining when ownership of materials has passed between the

    parties.

    3.3 Clause 2.22 of the JCT Design & Build Contract 2005 deals with the

    question of the passing of property where materials are off-site. Pursuant to

    this clause where items are Listed Items defined as materials, goods

    and/or items prefabricated for inclusion in the Works which are listed as such items by the Employer in a list supplied to the Contractor and annexed to the Employers requirements then such items shall be the property of the employer where in accordance with clause 4.15 the items

    have been included in any Interim Payment. The contractor, however, will

    bear the risk until such materials are delivered to, placed on or adjacent to

    the Works.

    3.4 Note also clause 4.15 which sets out the provisions to be fulfilled for Listed

    Items to be included in an Application for Interim Payment: such as, the

    contractor provides reasonable proof to the employer of his title to the goods

    and that he has maintained insurance for them, as well as showing that the

    items have been clearly identified for the works.

    3.5 Under clause 70.2 of the NEC3 contract, where materials are off site but

    marked by the supervisor then the employer will be able to assert whatever

    title the contractor has to the materials. Marking the items means that they have been separately identified10 under the contract for payment or the

    contractor has prepared them for marking as identified in the Works

    Information (see clause 71.1 of NEC3).

    3.6 It appears that the employer must pay for the materials in order to claim

    ownership of them but it is not clear where the identification for payment

    should be made11.

  • 6

    3.7 The best way in which an employer can protect his position is to obtain an off

    site materials bond as a pre-condition to payment. This would entitle the

    employer to make a demand up to the value of the off site materials.

    4 Conclusion

    4.1 In essence, the employer is in a stronger position to claim ownership in

    materials where they have been delivered to site (particularly, where they

    have been affixed to the property). The employer, contractor and sub-

    contractor should all ensure that they are adequately protected by the

    express terms of the contract or by obtaining a bond.

    1 Elwes v. Maw (1802) 3 East 38 2 Lyde v. Russell (1830) 1 B & Ad 394 3 Note this is a summary only and does not include Rule 5(3) and (4) relating to goods forming part of a bulk as amended by the Sale of goods (Amendment) Act c. 28 s1(2) (September 19, 1995) 4 Aluminium Industrie Vaassen BV v. Romalpa Aluminium Ltd [1976] 1 W.L.R. 676 5 Benjamin's Sale of Goods, 7th Edition, paragraph 5-141 6 Ibid, paragraph 5-146 7 Ibid, paragraph 5-145 8 Aircool Installations v. British Telecommunications [1995] C.L.Y. 821 (Cty. Ct.) 9 Section 25(1) Sale of Goods Act 1979 10 See Guidance Notes to NEC3, Chapter 7 Title, page 82 11 The NEC3 Engineering and Construction contract, a commentary by Brian Eggleston, 2nd Edition, pages 284 and 285 More information Roberta Vella +44 (0)1483 252545 [email protected]

    This information has been prepared by Charles Russell LLP as a general guide only and does not constitute advice on any specific matter. We recommend that you seek professional advice before taking action. No liability can be accepted by us for any action taken or not taken as a result of this information. Charles Russell LLP is not authorised under the Financial Services and Markets Act 2000 but we are able in certain circumstances to offer a limited range of investment services to clients because we are members of the Law Society. We can provide these investment services if they are an incidental part of the professional services we have been engaged to provide.