overview of road construction and maintenance
TRANSCRIPT
-
8/3/2019 Overview of Road Construction and Maintenance
1/14
1
Introduction
Road construction is one of the oldest arts known to man. The earliestroads developed from trails made by man or animals which became
footpaths. They naturally followed the lines of least resistance, avoiding
steep grades, marshland, and circumventing natural obstacles. If a river had
to be crossed, the trail either detoured to affordable location or fallen trees
used as bridges across the river.
The invention of the wheel at about 3500 BC constituted a significanttechnical advancement and greatly accelerated the development of road
construction. The possibility of carrying greater loads on wheel called for
corresponding improvement in carriageway development
The period after the world War of 1914-1918 was marked by quick growthof automobile transportation and an increase in the speed and carrying
capacity of automobiles. It was then that parallel with construction of
highways for mixed traffic (automobile traffic and horse traffic), highways
were constructed which were intended exclusively for high-speed
automobile traffic on large scale. This period might well be called the
automobile age for during this period highway transportation assumed a
dominant role in most part of the worlds.
-
8/3/2019 Overview of Road Construction and Maintenance
2/14
2
ROAD DEVELOPMENT IN NIGERIA
Road transportation has played a vital role in every aspect of Nigerias
development. Before the advent of British rule, movement of people and goods
naturally took place between the various communities. Social requirements such
as traditional festivals, where people had to travel from one village to another
gave rise to communal footpaths. These paths eventually developed into
commercial routes for trading, and from these roads the genesis of highway
development in Nigeria started.
Highway construction however started in the real sense at the beginning ofthe twentieth century.
The first efforts were made with: Roads from Calabar to Obubra and from Oron to Onitsha in the East; Ibadan to Oyo, Oshogbo to Ilesha and Ogbomosho in the West, and Zungeru-Zaria cart road in the North.
Progress was slow because of the First World War, but the tempo increasedsomewhat after the war as Lagos was linked to Ibadan, Benin to Sapele,
Ijebu-Ode to Ibadan and Abeokuta, Enugu to Port Harcourt, Sokoto to Zaria
and Kano to Katsina.
These roads were first developed as feeders to the railway, but by themiddle of the twentieth century, road development had overtaken the railin importance.
The total length of road (federal, state and local governments) has grown asfollows:
45,128km (with 1,648km bituminous surfaced and 43,480km oflaterite/gravel surface) in 1950
66,086km (with 8,745km bituminous surfaced) in 1960, 116,421km (with 30,285km bituminous surfaced) in 1980. According to the Federal Ministry of Works and Housing Road Vision
2000 report, the total length of roads in Nigeria as at Year 2000 was
about 191,250km as shown in Table 1.
-
8/3/2019 Overview of Road Construction and Maintenance
3/14
3
Components of a road
A road is composed of the following elements: Pavement Shoulders Kerbs Sidewalks Drainage channels and side slopes Medians Right of way
The Pavement A road pavement is a structure consisting of superimposed layers of
processed materials above the natural soil sub-grade,
Its primary function is to distribute the applied vehicle loads to thesub-grade.
The pavement structure should be able to provide: a surface of acceptable riding quality, adequate skid resistance, favorable light reflecting characteristics, and low noise pollution.
The ultimate aim is to ensure that the transmitted stresses due to wheelload are sufficiently reduced, so that they will not exceed bearing capacity
of the sub-grade.
Two types of pavements are generally used as serving this purpose, namely: flexible pavements and rigid pavements.
This section will present an overview of pavement of the two pavementtypes, layers, and their functions, and pavement failures.
Improper design of pavements leads to early failure of pavements affectingthe riding quality.
-
8/3/2019 Overview of Road Construction and Maintenance
4/14
4
Requirements of a Pavement
An ideal pavement should meet the following requirements: Sufficient thickness to distribute the wheel load stresses to a safe
value on the sub-grade soil,
Structurally strong to withstand all types of stresses imposed upon it, Adequate coefficient of friction to prevent skidding of vehicles, Smooth surface to provide comfort to road users even at high speed, Produce least noise from moving vehicles, Dust proof surface so that traffic safety is not impaired by reducing
visibility,
Impervious surface, so that sub-grade soil is well protected, and Long design life with low maintenance cost.
Flexible and Rigid Pavements
Classification of pavements into flexible and rigid is based on the structuralperformance, that is the behavior of the pavement under traffic loads:
In flexible pavements, wheel loads are transferred by grain-to-grain contactof the aggregate through the granular structure. The flexible pavement,
having less flexural strength, acts like a flexible sheet (e.g. bituminous
road). On the contrary, in rigid pavements, wheel loads are transferred to sub-
grade soil by flexural strength of the pavement and the pavement acts like
a rigid plate (e.g. cement concrete roads).
In addition to these, composite pavements are also available. A thin layer of
flexible pavement over rigid pavement is an ideal pavement with most
desirable characteristics. However, such pavements are rarely used in new
construction because of high cost and complex analysis required.
Flexible Pavements
Flexible pavements will transmit wheel load stresses to the lower layers by
grain-to-grain transfer through the points of contact in the granular structure
(see Figure 1).
-
8/3/2019 Overview of Road Construction and Maintenance
5/14
5
Figure 1: Load transfer in granular structure
The wheel load acting on the pavement will be distributed to a wider area,and the stress decreases with the depth. Taking advantage of this stress
distribution characteristic, flexible pavements normally has many layers.
Hence, the design of flexible pavement uses the concept of layered system. Based on this, flexible pavement is constructed in a number of layers and
the top layer has to be of best quality to sustain maximum compressive
stress, in addition to wear and tear.
The lower layers will experience lesser magnitude of stress and low qualitymaterial can be used.
Flexible pavements are constructed using bituminous materials. These canbe either in the form of surface treatments (such as bituminous surface
treatments generally found on low volume roads) or, asphalt concrete
surface courses (generally used on high volume roads such as national
highways).
Flexible pavement layers reflect the deformation of the lower layers on tothe surface layer (e.g., if there is any undulation in sub-grade then it will be
transferred to the surface layer).
In the case of flexible pavement, the design is based on overallperformance of flexible pavement, and the stresses produced should be
kept well below the allowable stresses of each pavement layer.
-
8/3/2019 Overview of Road Construction and Maintenance
6/14
6
Components of Flexible Pavements
Flexible pavements: Are layered systems with high quality expensive materials placed in
the top where stresses are high, and low quality cheap materials are
placed in lower layers.
Flexible pavements has the following components: Wearing course of bituminous treatment or asphalt concrete Binder course of asphalt concrete Base course of crushed stone (stone base) or good laterite Sub-base course of good laterite or stabilized poor materials Service life is about 10 to 15 years Service life refers to period of use with routine maintenance
and no periodic maintenance.
Typical layers of a flexible pavement
Figure 2: Typical cross section of a flexible pavement
Wearing Course
Wearing course is the layer directly in contact with traffic loads andgenerally contains superior quality materials. They are usually constructed
with dense graded asphalt concrete(AC).
The functions and requirements of this layer are: It provides characteristics such as friction, smoothness, drainage, etc. Also it will prevent the entrance of excessive quantities of surface
water into the underlying base, sub-base and sub-grade,
-
8/3/2019 Overview of Road Construction and Maintenance
7/14
7
It must be tough to resist the distortion under traffic and provide asmooth and skid- resistant riding surface,
It must be water proof to protect the entire base and sub-grade fromthe weakening effect of water.
Binder Course
This layer provides the bulk of the asphalt concrete structure. It's chief purpose is to distribute load to the base course The binder course generally consists of aggregates having less asphalt and
doesn't require quality as high as the surface course, so replacing a part of
the surface course by the binder course results in more economical design.
Base Course
The base course is the layer of material immediately beneath the surface ofbinder course and it provides additional load distribution and contributes to
the sub-surface drainage
It may be composed of crushed stone, good laterite, and other untreated orstabilized materials.
Sub-Base Course The sub-base course is the layer of material beneath the base course and
the primary functions are:
To provide structural support, improve drainage, and reduce the intrusion of fines from the sub-grade in the pavement structure A sub-base course is not always needed or used. For example, a pavement
constructed over a high quality, stiff sub-grade may not need the additional
features offered by a sub-base course. In such situations, sub-base coursemay not be provided.
Sub-grade
The top soil or sub-grade is a layer of natural soil prepared to receive thestresses from the layers above.
-
8/3/2019 Overview of Road Construction and Maintenance
8/14
8
It is essential that at no time soil sub-grade is overstressed. It should becompacted to the desirable density, near the optimum moisture content.
Kerbs
Use of kerbs is generally confined to urban and sub-urban areas. Notusually used for rural roads.
Functions of Kerbs
To control surface drainage To act as deterrents to vehicles leaving the pavement at haphazard
locations
To delineate the edge of the pavement To present a more finished appearance To assist in orderly development of the road side
Shoulders
Shoulders are strips provided on both sides of the carriageway. Theirprimary function is to serve as parking place for vehicles which have
developed some defects and need parking. If shoulders are not provided,
vehicles going out of order shall have to be parked on the carriageway andthus efficiency of the road is affected and may even become the source of
serious accidents.
Functions of Shoulders
They provide space for emergency and occasional stopping of vehicles dueto motor troubles, such as breakdown, flat tyres, etc.
They provide space for escaping potential accidents or reducing theirseverity
They improve sight distance especially in hilly and cut sections and bendsthus reducing hazards
They provide space for road maintenance operations They make the discharge of storm water farther away from the pavement They provide lateral support to the pavement structure
-
8/3/2019 Overview of Road Construction and Maintenance
9/14
9
Types of Road Maintenance
Road Maintenance Proper road maintenance contributes to reliable transport at
reduced cost, as there is a direct link between road condition and
vehicle operating costs (VOC). An improperly maintained road can
also represent an increased safety hazard to the user, leading to
more accidents, with their associated human and property costs.
Routine maintenance works.
These are works that are undertaken continuously in order topreserve the road. Activities can be grouped into cyclic and reactive
works types. Cyclic works are those undertaken where the
maintenance standard indicates the frequency at which activities
should be undertaken. Examples are verge cutting and culvert
cleaning, both of which are dependent on environmental effects
rather than on traffic levels. Reactive works are those where
intervention levels, defined in the maintenance standard, are used to
determine when maintenance is needed. An example is patching,
which is carried out in response to the appearance of cracks or pot-
holes.
Periodic maintenance works. These include activities undertaken at intervals of several years to
preserve the structural integrity of the road, or to enable the road to
carry increased axle loadings. The category normally excludes those
works that change the geometry of a road by widening or
realignment. Works can be grouped into the works types of
preventive, resurfacing, overlay and pavement reconstruction.Examples are resealing and overlay works, which are carried out in
response to measured deterioration in road conditions. Periodic
works are expected at regular, but relatively long, intervals.
-
8/3/2019 Overview of Road Construction and Maintenance
10/14
10
Special maintenance works. These are activities whose need cannot be estimated with any
certainty in advance. The activities include emergency works to
repair landslides and washouts that result in the road being cut or
made impassable. These works are also referred to as emergency
maintenance
Road and Highway Maintenance
Definition: Preserving and keeping each type of roadway, roadside, structures as
nearly as possible in its original condition as constructed or as
subsequently improved and the operation of highway facilities and
services to provide satisfactory and safe transportation, is called
maintenance of Highways.
The various maintenance function includes; Surface maintenance Roadside and drainage maintenance Shoulder and approaches maintenance Snow and ice control Bridges maintenance Traffic service Highway maintenance is closely related to the quality of constructionof original road.
Insufficient pavement or base thickness or improper construction ofthese elements soon results in expensive patching or surface repair.
Shoulder care becomes a serious problem where narrow lanes forceheavy vehicle to travel with one set of wheels off the pavement.
Improperly designed drainage facilities, mean erosion or depositionof material and costly cleaning operation or other corrective
measures.
Sharp ditches and steep slopes require manual maintenance ascompare to cheap maintenance of flatter ditch and soil by machine.
-
8/3/2019 Overview of Road Construction and Maintenance
11/14
11
In snowy country, improper location extremely low fills and narrow
cuts leave no room for snow storage, creating extremely difficult
snow removal problems.
Surface maintenance of Roads Pavement maintenance and rehabilitation programs, restore riding
quality and maintain the structural integrity of the pavement over its
full design life.
Asphalt concrete pavements are subjected to various types ofpavement distress or Failure these include.
Alligator Cracking: A series of interconnecting or interlaced cracks caused by fatigue of
the asphalt concrete surface under repeated traffic leading. [Cracking
is due to foundation movement at subgrade
Block Cracking: Cracks forming large interconnected polygon usually with sharp
corners or angles. These cracks are generated by hardening or
shrinking e.g. asphalt or reflection cracking for underlying layers suchas cement treated base.
Transverse Cracking: Cracks approximately at right angle to the pavement center line.
These may be caused by hardness and shrinkage of asphalt or
differential thermal stresses of asphalt concrete or may be reflection
cracking.
Longitudinal Cracking: Cracks approximately parallel to the pavement centerline. These are
caused by poorly constructed construction joints and shrinkage of
the asphalt concrete surface. They may also be reflection cracks.
-
8/3/2019 Overview of Road Construction and Maintenance
12/14
12
Raveling: Wearing away the pavement surface caused by dislodging of
aggregate particles and binders. This is usually a result of insufficient
asphalt binder in the mix or stripping of asphalt from particles of
aggregate.
Drip Track Raveling: Progressive disintegration of the surface between wheel paths
caused by dripping of gasoline oil from vehicle.
Longitudinal Cracking: Cracks approximately parallel to the pavement centerline. These are
caused by poorly constructed construction joints and shrinkage of
the asphalt concrete surface. They may also be reflection cracks.
Raveling: Wearing away the pavement surface caused by dislodging of
aggregate particles and binders. This is usually a result of insufficient
asphalt binder in the mix or stripping of asphalt from particles of
aggregate.
Drip Track Raveling: Progressive disintegration of the surface between wheel paths
caused by dripping of gasoline oil from vehicle.
Bleeding or Flushing (Fatting Up): The exuding of bitumen on to the pavement surface causing
reduction in skid resistance. Bleeding is generally caused by excessiveamount of asphalt in the mix or low air void content. It occurs in the
mix in hot weather.
-
8/3/2019 Overview of Road Construction and Maintenance
13/14
13
Corrugations: Due to instability of base or poor original riding surface (plastic
movement of pavement)
Pot Holes: When cracks become deep.
Ruts: Depressions formed under the wheel due to heavy load, this causes
consolidation, deformation or plastic flow.
General surface maintenance: For maintenance of gravel roads blading and occasional resurfacing is
required.
For surface treatments of low type bituminous surface inmaintenance of roads; Patching, seal coating or possible loosening
oiling, re mixing and relaying are involved.
For high type bituminous concrete and Portland cement concrete,the Removal and replacement of failure areas and resurfacing are
approximate treatment methods for highway maintenance.
Use same material and methods for road surface maintenance as fasas possible. Highway Maintenance must be planned for rapid performance and to
cause least possible disruption or hazard to traffic.
Roadside and Highway Drainage maintenance
Depends on the characters of road side where the roadside is grassy it mustbe mowed; cutting, ploughing or spraying with weed killer must be done.
If there is dry grass fire hazard burning, plowing must be done. When back slope is covered with bush, trimming must be done to
increase the sight distance and clearance of road.
Control of side slope erosion by mulching, seeding etc. Picking up litter, thrown or blown along roadside or wayside area a
Routine work.
-
8/3/2019 Overview of Road Construction and Maintenance
14/14
14
Drainage of Highway Maintenance: Keeping ditch, culvert and otherdrainage structure, clean and ready to carry next flow water.
Sediments deposited during period of heavy flow must be removed
badly eroded channel and dikes properly protected to prevent
recurrence.
Shoulders
Depend on the surface character of these areas SOD shoulders must be moved and occasionally bladed down to the
level of the roadway so that water is not trapped in the traveled way.
Gross must be kept in good condition.
Shoulders protected by bituminous blankets or surface treatmentssame as for roadway surface.
Gravel and earth shoulders that leaves a drop off at the pavementedges creates a serious accident hazard, hence, should be corrected
by reconstruction, resurfacing or other appropriate means.
Due to continuous wetting and drying of shoulder, edge joints resultbetween lane and shoulder which may cause settlement of
pavement due to entrance of water in sub grade soil. It can Repaired
by filling the joint with sand and asphalt concrete
CONCLUSION
This paper has discussed an overview of road construction on maintenanceas well as the importance of road infrastructure.
I believe you have stick one or two things from the paper Thank you for listening.