overview of heat recovery projects related to the chemical … · 2018. 4. 11. · preem lysekil...
TRANSCRIPT
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
Overview of Heat Recovery projects related to the Chemical
Cluster in Stenungsund
Professor Simon Harvey
Chalmers University of Technology
Appendix 3: Presentations from the workshops
Page 153 of 367
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
105 kton
390 kton
1230 kton
590 kton
11 kton
115 kton
110 kton
531 kton
43,6 GWh
206 kton
113 kton
84 kton (??)
636 kton
111 kton
47,4 GWh
Chemical Cluster Stenungsund: Production and emissions 2011 CO2 41 kton
CO2 54 kton
CO2 56 kton
CO2 101 kton
CO2 650 kton
TOTAL Emissions of CO2 approx. 900 kton/yr
Appendix 3: Presentations from the workshops
Page 154 of 367
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
The potential of inter-process heat integration: Opportunities for
improving energy efficiency in Stenungsund – Sweden’s largest
chemical cluster
Key figures for total site:
• Total CO2 emissions: ~900 kton/yr
• Total heating demand: 442 MW 320 MW
are covered by internal heat recovery
• Current utility usage fr fired boilers: 122 MW
• Can theoretically be reduced to 0 MW
through inter-process heat integration!
How this can be accomplished:
• New circulating hot water systems 50-100°C
• Harmonization of utility pressure levels to
enable heat exchange between process
plant utility systems
• Rebuild steam heaters for 2 bar(g) operation
• Fire process off-gases in different boilers
Substantial opportunities for energy efficiency through Inter-process heat recovery
Appendix 3: Presentations from the workshops
Page 155 of 367
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
0
100
200
300
400
500
600
700
800
2
3
4
5
6
7
8
0 10 20 30 40 50 60
To
tal fixe
d c
ap
ita
l [M
SE
K]
Estim
ate
d P
BP
[yr
]
Amount of heat recovery [MW]
By-product fuelredistribution fromPerstorp to Cracker
Steam demandat Pertorp is met
Steam demandat Pertorp andINEOS is met
System 20
System 30System 40 System 50
System 54
Consequences of increased heat recovery with the HW systems on the
overall PBP; red squares: Total fixed capital, blue diamonds: PBP.
Detailed design of specific heat recovery systems has
been accomplished in a recent study at Chalmers
Appendix 3: Presentations from the workshops
Page 156 of 367
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
Perstorp Borealis PE
Borealis Cracker
Heat sources
Heat sinks
E-443357
Hot water pipe
Steam pipe
Hot water pump
E-443201
E-1608 E-1845
HW1(79/55 °C)
E-442161
20.7 MW
22.8 MW
20.7 MW
Losses:
2.1 MW
Current LP steam demand: 25.7 MW
System 20
Total investment:
199 MSEK
Total hot utility savings:
20.7 MW
Payback period:
App. 3.2 years
New HXs: 5
System 20 can be pre-fitted for
extension to System 50 (extra cost 19
MSEK)
Appendix 3: Presentations from the workshops
Page 157 of 367
-
Heat and Power Technology Dept of Energy and Environment
IEA IETS Excess Heat Workshop, Lisbon, 26-27 May 2014
Total investment:
598 MSEK (199)
Total hot utility savings:
50,8 MW (20.7)
Pay back period:
App. 3.9 years (3.2)
New HX: 32 (5)
Current LP steam demand: 25.7 MW Borealis PE
Borealis CrackerINEOS
Heat sources
Heat sinks
Potential heat sink
for excess utility
E-443357
E-1701
81,77,57,15,
72,50,31,2,13
Reboiler HTC, Air to spray dryer,
Air to two dryers
Perstorp
Potential
demand:
40.3 MW
Current LP steam demand: 2.5 MW
Hot water pipe
Steam pipe
Fuel pipe
Hot water pump
Potential
demand:
10.5 MW
E-443201
E-1608 E-1845
E-1890
56
Condensor
49
Condensor
47 flash steam
Condensor
65 Rx1
Cooler16
Cooler
24
Reb
E-1606Y
E-1802CT1701
cond
Preheat
demin
E-1609
E-442161
Rx2
Cooler
10.5 MW
40.3 MW
24 MW
5.5 MW
26.8 MW
Losses:
2.7 MW
27.7 MW
23 MW
2.2 MWLosses:
2.5 MWFuel:
21 MW
System 50HW1
(79/55 °C)
HW2(97/75 °C)
9x
4x
Appendix 3: Presentations from the workshops
Page 158 of 367
-
Studying competition between internal heat recovery
and excess heat export
Lina Eriksson
SP – Energiteknik
Examinator and main supervisor: Simon Harvey
Co-supervisor: Matteo Morandin
Timeframe: September 2013 – December 2015
Appendix 3: Presentations from the workshops
Page 159 of 367
-
Part of collaborative project package investigating
different aspects of regional district heating
• Other sub-projects:
– “How district heating market models influence industrial excess
heat usage” – SP, Magnus Brolin
– “Assessment of Sustainability of industrial waste heat - the
Stenungsund case” – Chalmers and IVL, Erik Ahlgren and Thomas
Ekervall
– “Analysis of need and demand for sustainable district heating from
the large customers”– Business Region Gothenburg, Lars Bern
• Scientific co-ordination of the projects lead by Thore Berntsson
– Exchange results
– Use common assumptions
Appendix 3: Presentations from the workshops
Page 160 of 367
-
Aim: Promote rational use of industrial excess heat, and
provide conditions for creating a sustainable energy system.
The primary goal is to understand:
• Technical feasibility, profitability and environmental impact of
the use of excess heat for district heating
• The competition between the production of district heating
and opportunities within industry for heat recovery
Aim and goal Appendix 3: Presentations from the workshops
Page 161 of 367
-
Two case studies:
PREEM Lysekil
Chemical cluster in Stenungsund
1. Identify some different levels of use of excess heat internally for:
a. Heat recovery within each industry / sub-process
b. Exchange between industries / / sub-processes
c. Investigate the possibilities for using heat pumps
2. Identify for each level and area of use above:
a. Quantity and temperature of the remaining excess heat for district heating delivery
b. Opportunities to increase the delivery of district heat by using heat pumps
3. Evaluate costs and CO2 emissions for the different cases based on some different scenarios
for:
a. Marginal production for district heating (what is replaced)
b. Marginal production of electricity (what is replaced)
c. Policy instruments (such as future costs of emitting CO2)
Project outline
District Heating
Heat recovery
Marginal production
Appendix 3: Presentations from the workshops
Page 162 of 367
-
Project outline
District
heating
Heat recovery
1. S
2. S
3. h
4. Identify and include some other technologies:
a. Biorefinery concepts
b. Electricity generation with ORC
c. Drying of biomass
d. CCS, etc.
Evaluate these in the manner described in step 2 and 3, in terms of economy, CO2
emissions and impact on the possibilities to produce district heating.
5. Find some optimal solutions for utilisation of excess heat with regards to costs and climate
impact (CO2) for the different scenarios that were created in step 3.
Marginal production
Biorefinery
ORC
CCS
Appendix 3: Presentations from the workshops
Page 163 of 367
-
Potentials estimated using ACLC - Actual Cooling
Load Curves
Appendix 3: Presentations from the workshops
Page 164 of 367
-
Industrial Excess Heat for District Heating
Comparison of potentials from top-down and bottom-up
studies for energy-intensive process industries
Based on the MSc Thesis project conducted
by Moa Swing Gustafsson
2013
Professor Simon Harvey
Heat and Power Technology Group
Department of Energy and Environment
Chalmers University of Technology
Appendix 3: Presentations from the workshops
Page 165 of 367
-
Background
• In response to EU’s Energy Efficiency Directive: Ongoing
legislation changes in Sweden aim to facilitate third party
access to DH networks (in particular industrial processes)
• 4.1 TWh/yr of industrial excess heat was delivered to DH
networks in Sweden in 2012 (total DH heat delivered
2012: 50 TWh)
• A number of studies indicate that there is a potential for
increasing excess process heat recovery for DH delivery
Appendix 3: Presentations from the workshops
Page 166 of 367
-
Major study commissioned by the Swedish
DH Association (SDHA) in 2009
Statistical data was compiled for excess heat deliveries from industrial plants.
This data was related to the corresponding fuel usage for these plants.
Sector Excess heat delivered per unit of fuel
usage [%]
Pulp industry 2.8
Paper industry 3.2
Chemicals and chemical products 24.3
Ferrous and non-ferrous metals 2.5
Based on this data it was estimated that the potential for excess recovery
for DH purposes is 6.3 TWh/yr compared to 4.1 TWh/yr currently delivered
Appendix 3: Presentations from the workshops
Page 167 of 367
-
Objective of the MSc thesis project
Compare the potentials estimated in the SDHA report with
results generated using pinch analysis for case studies in key
industrial sectors
5 industrial plant case studies were studied
• Chemical pulp and paperboard mill
• Chemical pulp mill
• Mechanical pulp and paper mill
• Steel mill
• PVC plant
Appendix 3: Presentations from the workshops
Page 168 of 367
-
Brief presentation of Pinch analysis
• Well established tool for analysing heat flows in industrial
processes with liquid and gas flows.
• Allows heat recovery targets to be established: Determines
minimum cooling and heating demand of a process for a
given value of minimum temperature difference allowed in
the heat exchangers (∆Tmin)
• Requires the following data for process streams that must
be heated or cooled
• Start temperature
• Target temperature
• Mass Flowrate
• Specific heat capacity
Appendix 3: Presentations from the workshops
Page 169 of 367
-
Process streams Energy analysis
Basics of Pinch Analysis
P
r
o
c
e
s
s
Cooling
Heat
Feedstock Products
El
Heat
Kylning
T
Heat
balances
0
20
40
60
80
100
120
140
160
0 10000 20000 30000 40000 50000 Q
T (
°C)
Hot streams
Cold streams
Theoretical minimum heating demand
Teoretical cooling demand
Graphically
Process
Pinch Depends on choice of ΔTmin
Maximal internal
Heat recovery
Appendix 3: Presentations from the workshops
Page 170 of 367
-
Grand composite curves
The grand composite curve (GCC) illustrates the net energy flow in each temperature interval
Appendix 3: Presentations from the workshops
Page 171 of 367
-
Estimating the potential for export of excess process
heat to a DH network using the GCC
QC
Excess heat is discharged to
CW if no other options are
available
DH
Tshift QH
Appendix 3: Presentations from the workshops
Page 172 of 367
-
Quantification of maximal excess heat recovery
DH
Temperature profile
for DH water
TDH,Supply
(Target
Temperature)
Tshift
Slope of line is
related to flowrate
QH,Min
Process GCC
)( Return,,, DHSupplyDHWpWDH TTCFQ
TDH,Return
(Start
Temperature)
Case 1: DH supply Ttarget can be reached.
All process excess heat can be
used for WW production.
Appendix 3: Presentations from the workshops
Page 173 of 367
-
DH
Tshift QH,Min Case 2: All process excess heat
cannot be delivered to DH network.
(DH supply Ttarget too high)
Utility pinch activated.
DH flow is limited
by DTmin
Cold utility for
remaining cooling load
TDH,Supply
TDH,Return
Appendix 3: Presentations from the workshops
Page 174 of 367
-
• DH export potentials estimated from GCCs for 4 different values of
∆Tmin
0 K 5 K 10 K 15 K
• In practice, few processes achieve the energy target. It is also of
interest to estimate potentials based on the composite curve of
process streams that are cooled in process coolers (ACLC Actual
Cooling Load Curve)
• These numbers are compared with the estimates obtained using the
SDHA procedure
Results presented in the thesis
theoretical maximum for
reference
Appendix 3: Presentations from the workshops
Page 175 of 367
-
Limitations and assumptions
• All work based on case studies (pinch analysis studies
conducted within our group)
• District heating water temperatures
- Return temperature: 55°C
- Supply temperature: 85-105°C
• Required minimum ∆T between the district heating water
and process streams
- 7 K
Appendix 3: Presentations from the workshops
Page 176 of 367
-
Chemical pulp and paperboard mill
Appendix 3: Presentations from the workshops
Page 177 of 367
-
0
50
100
150
200
250
0 50000 100000 150000 200000 250000
Tsh
ift
(°C
)
Q (kW)
Grand Composite Curve ΔT=10
GCC DH at 85°C DH at 95°C DH at 100°C DH at 105°C
Appendix 3: Presentations from the workshops
Page 178 of 367
-
0
50
100
150
200
250
0 50000 100000 150000 200000 250000
T (
°C)
Q (kW)
Grand Composite Curve ΔT=15
GCC
Appendix 3: Presentations from the workshops
Page 179 of 367
-
Results
∆Tmin
DH export potentials [MW] for
varying DH water supply
temperature levels [°C] Pinch
temperature
[°C] 85 95 100 105
0 K 28.0 25.6 24.9 - 111.0
5 K 24.2 22.6 21.9 - 108.5
10 K 12.6 12.1 12.0 11,9 110.4
15 K - - - - (60)
ACLC Estimate 14.3 12.5 12.0 11.5
SDHA estimate
Pulp: 10.0 MW
Paper: 11.4 MW
Appendix 3: Presentations from the workshops
Page 180 of 367
-
PVC plant
Appendix 3: Presentations from the workshops
Page 181 of 367
-
-50
0
50
100
150
200
250
0 5000 10000 15000 20000 25000 30000 35000
Tsh
ift (°
C)
Q (kW)
Grand Composite Curve
GCC DH at 85°C DH at 95°C DH at 100°C DH at 105°C
Appendix 3: Presentations from the workshops
Page 182 of 367
-
Estimated potentials for DH delivery
from PVC plant
∆Tmin
DH water supply temperature [°C]
85 95 100 105
0 K 17.6 MW 5.0 MW 4.0 MW -
5 K 21.5 MW 6.5 MW 5.3 MW 4.6 MW
10 K 22.2 MW 7.8 MW 6.3 MW 5.4 MW
15 K 23.0 MW 10.1 MW 8.2 MW 7.1 MW
ACLC 25.6 MW 20.4 MW 18.3 MW 16.9 MW
SDHA Estimate
13.1 MW
Appendix 3: Presentations from the workshops
Page 183 of 367
-
Appendix 3: Presentations from the workshops
Page 184 of 367
-
Case study 1
Chem. P&P
mill
Case study 2
Chem. Pulp
mill
Case study 3
Mech. P&P
mill
Case study 4
Steel works
Coking plant
Case study 4
Steel works
rest of plant
Case study 5
PVC Plant
DH [°C] 85 105 85 105 85 105 85 105 85 105 85 105
ΔTmin=0 28.0 - 38.2 - - - 4.4 1.5 14.6 14.6 17.6 -
ΔTmin=5 24.2 - 42.2 - 2.3 - 4.4 1.6 15.0 15.0 21.5 4.6
ΔTmin=10 12.6 11.9 45.5 - - - 4.5 1.7 15.4 15.4 22.2 5.4
ΔTmin=15 - - 48,9 - - - 4.5 1.8 16.2 16.2 23.0 7.1
ACLC 14.3 11.5 - - - - 11.0 7.2 17.2 17.2 25.6 16.9
SDHA
estimate
10.0-11.4 9.8 1.6-1.8 6.6 6.7 (13.1)
Estimated potentials for DH export [MW]
Appendix 3: Presentations from the workshops
Page 185 of 367
-
Conclusions • The SDHA approach usually underestimates the
potential for DH export compared to estimates using
pinch analysis
• The potentials based the actual cooling (ACLC) are usually higher since they (often) reflect inefficient use of
heat within the process
• ”Beauty is in the eye of the beholder”. There is no clearcut definition of excess heat
• Even if the ”excess heat” at the plant isn’t at a high enough temperature to produce DH it may be beneficial
to recover the excess heat available and provide final
heating to the required delivery temperature with steam
(or other hot utility)
Appendix 3: Presentations from the workshops
Page 186 of 367
-
Regional Energy System
Appendix 3: Presentations from the workshops
Page 187 of 367
-
2 2
Idea: Benefits from an integrated system Appendix 3: Presentations from the workshops
Page 188 of 367
-
3 3
RESO, Studied region
Distance approx 50 km Heating demand approx 7 TWh/year
Sandviken Gävle
Skutskär
StoraEnso
KorsnäsSandvik
40 km
Sweden
Sandviken Gävle
Skutskär
StoraEnso
KorsnäsSandvik
40 km
Sweden
Appendix 3: Presentations from the workshops
Page 189 of 367
-
4 4
When the systems are integrated
§ The profit for integrating the system is up to 240 MSEK* per year compared to the present system § Average: 140 MSEK/year* § Payback time: 2-11 years*
§ District heating market: 150 – 620 GWh/year* § Average: 430 GWh/year*
§ Electricity production: 850 – 1360 GWh/year* § Average: 1080 GWh/year*
*based on 30 scenarios with different investment possibilities
Appendix 3: Presentations from the workshops
Page 190 of 367
-
5 5
Lowest cost solution, [GWh]
352 7 53 40 28 0
0 515
Sandviken Energy
Gävle Energy
Älvkarleby Fjärrvärme
Korsnäs Sandvik
168 0
StoraEnso Skutskär
0 39
Heat market
Karskär Energy
Appendix 3: Presentations from the workshops
Page 191 of 367
-
6 6
Reasons for the profits when integrating the systems to one system
§ The boilers are used in a better way § It is possible to produce more electricity § Investments
Appendix 3: Presentations from the workshops
Page 192 of 367
-
7 7
Influence on each operator, compared to separate systems*
-150
-100
-50
0
50
100
150
200
GEAB SEAB Sandvik KEAB Skutskär
MSEK/year
Scenario 5Scenario 10Scenario 14Scenario 18Scenario 21Scenario 24Scenario 25Scenario 26Scenario 28
*9 scenarios are analyzed in-depth
Appendix 3: Presentations from the workshops
Page 193 of 367
-
8 8
The boundaries for CO2-emission accounting
§ Swedish average electricity mix § European average electricity
mix § Present marginal production
Appendix 3: Presentations from the workshops
Page 194 of 367
-
9 9
Reduction of CO2 emissions, compared to reference scenario
0100200300400500600700800
Marginal Coal Marginal NGCC Average Swedish
Scenario
kton
CO
2/år Scenario 5
Scenario 21Scenario 25Scenario 28
Appendix 3: Presentations from the workshops
Page 195 of 367
-
10 10
Idea: Benefits from an integrated system Appendix 3: Presentations from the workshops
Page 196 of 367
-
11 11
Development of a sustainable, competitive society with high security of supply
§ Develop a common infrastructure for energy and other resources § Regional cooperation on infrastructure - Skutskär, Gävle, Sandviken och
Hofors, Falun and Borlänge!
Appendix 3: Presentations from the workshops
Page 197 of 367
-
Projects at Linköping university
Excess heat
Mats Söderström, Energy Systems, Linköping university
Appendix 3: Presentations from the workshops
Page 198 of 367
-
Contents
§ Harvesting
§ Quantification
§ Systems analysis § Realization
Appendix 3: Presentations from the workshops
Page 199 of 367
-
IR images from cooling bed 1 (CB1) and cooling bed 2 (CB2). The tubes move over the bed in the direction of the arrow. The diagrams to the right of the images show the temperature profile of the cooling bed along the arrow. Source: Johansson MT, Wren J, Söderström M. Submitted to Applied Energy
0
200
400
600
800
1000
Tempe
rature (°C)
Length profile of cooling bed 1
CB 1
0
200
400
600
800
1000
Tempe
rature (°C)
Length profile of cooling bed 2
CB 2
In this case: • Measurements using IR
camera and thermocouples
• Possible to transfer 0,3 GWh annually to water and air
Cooling beds in the steel industry Appendix 3: Presentations from the workshops
Page 200 of 367
-
Electricity generation from low-temperature industrial excess heat
Excess heat with a temperature below 230 C Technology alternatives
Thermo Electric Generator – F2F200W TEG Power Organic Rankine Cycle – 750 kWel Opcon Powerbox PCM-motor – 100-200 kWel Exencotech
Excess heat
Cooling water from EAF – ORC Cooling water from ingot casting – PCM electricity generation 3,5 GWh
Economy TEG – not suitable ORC for temperatures over 80 C PCM for temperatures below 80 C
Källa: Johansson MT, Söderström M, Electricity generation from low-temperature industrial excess heat – an opportunity for the steel industry. Energy Efficiency 6 (2013) 1-13.
Appendix 3: Presentations from the workshops
Page 201 of 367
-
Excess heat today = ca 35 GWh Potential excess heat = ca 90 GWh !!
DH to Ovako 45 GWh Electricity and Fuels
700 GWh
DH
50 GWh
Wood
chips
100 GWh
El /oil
15 GWh
Excess heat
35 GWh
Supply to HEAB
El production
4 GWh
HEAB
Steam to Ovako 33 GWh
Ovako
Appendix 3: Presentations from the workshops
Page 202 of 367
-
Survey of industry in Örebro och Östergötland counties
0
20
40
60
80
100
120
0
100
200
300
400
500
600
700
800
900
25 30 35 45 55 70 90 160
200
350
Not specified
GWh/year (A
ir/Flue
gases)
GWh/year (W
ater)
Temperature (°C)
Water
Flue gases
Air
• Cooperation with county boards • Energy intensive industries • Responses from industries representing 10,5 of 12,5 TWh • Today 107 GWh of excess heat is used in district heating • Fig shows unused excess heat 1480 GWh • 146 GWh in flue gases over 160C • Uppscaling to national level - 2TWh
Källa: Broberg S, Backlund S, Karlsson M, Thollander P, Industrial excess heat deliveries to Swedish district heating networks: drop it like it´s hot. Energy Policy 51 (2012) 332-339
Appendix 3: Presentations from the workshops
Page 203 of 367
-
Survey of industry in Gävleborg county
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0
20
40
60
80
100
120
140
160
180
200
GWh/year (H
eat in material)
GWh/year (W
ater/Flue gases/Air)
Temperature (°C)
Water
Fluegases
Air
• Cooperation with the county board • Survey to the energy manager in 58 industries • Responses from industries representing 9,5 of 11,2 TWh • Today 220 GWh is used in district heating • Fig shows unused excess heat 800 GWh • Over 100 C: ca 300 GWh (water and gases)
Källa: Broberg Viklund S, Johansson MT, Technologies for utilization of industrial excess heat: Potentials för energy recovery and CO2 emission reduction. Energy Conversion and Management 77 (2014) 369-379
Appendix 3: Presentations from the workshops
Page 204 of 367
-
Technologies for utilization of excess heat based on the survey of Gävleborg county
Case 1: to district heating water over 95 C Gases over 100 C Hot material ca 90 GWh to district heating
Case 2: to electricity generation
Hot material 1000 C TPV Gases and water over 80 C ORC Water under 80 C PCM –motor ca 25 GWh electricity
Källa: Broberg Viklund S, Johansson MT, Technologies for utilization of industrial excess heat: Potentials för energy recovery and CO2 emission reduction. Energy Conversion and Management 77 (2014) 369-379.
Appendix 3: Presentations from the workshops
Page 205 of 367
-
Systems analysis
• Based on input data from the Gävleborg survey
• System optimization reMIND
• Energimarket scenarios ENPAC
Results: • All available excess heat is
used
• ORC is not used
• CO2-emissions decrease in all scenarios, decrease depends on what is replaced by the excess heat
Broberg S, Karlsson M, Systems analysis and CO2 reductions using industrial excess heat. Int Conf on Applied Energy 2013, Pretoria
Appendix 3: Presentations from the workshops
Page 206 of 367
-
Idea: Benefits from an integrated system Gävleborg county
Appendix 3: Presentations from the workshops
Page 207 of 367
-
Thanks!
Appendix 3: Presentations from the workshops
Page 208 of 367
-
We also do:
• Biogas applications in industry – excess heat • Excess heat and policies
Appendix 3: Presentations from the workshops
Page 209 of 367