Overview of Completions PESA Oil & Gas 101

Ed O’Malley, Engineering Director

23 September 2014

© 2011 Baker Hughes Incorporated. All Rights Reserved.

What is a Well Completion?

• Systems and services deployed in wells after drilling is complete to enable or improve the safe production of hydrocarbons

© 2011 Baker Hughes Incorporated. All Rights Reserved. 2

COMPLETION

Outline

• Background • Drivers affecting selection of completion types • Major completion components • Examples of completion types • Speculation on future completions

Well Life Cycle

© 2011 Baker Hughes Incorporated. All Rights Reserved. 4

InformationManagement,Drilling Engineering,Data Mudlogging,Rig-Site Supervision

Drilling Dynamics

Drilling Fluid Systems

Formation Evaluation MWD

SteerableDrillingSystems

HighPerformance Bits

CompletionFluids

Pumping,Stimulation,Filtration

CompletionHook-ups

Tubing ConveyedPerforating

Packers

Pre-Pack WellScreens

GravelPackingServices

Safety Systems

Flow ControlEquipment

PerformanceChemicals

PackersCementingEquipment

Automated ProductionSystems

Drilling Completion Production

Oil and Gas Reservoirs

© 2011 Baker Hughes Incorporated. All Rights Reserved. 5 Source: Wyoming State University

Completion Functions

• Provide pathway for fluid from the reservoir into the wellbore

• Provide pathway for wellbore fluids to surface

• Control the production rate from the reservoir

• Isolate problematic sections of the well • Allow access for well maintenance

• Enable stimulation

© 2011 Baker Hughes Incorporated. All Rights Reserved. 6

Building a Well: Cross Section

© 2011 Baker Hughes Incorporated. All Rights Reserved. 7

conductor pipe

cement surface casing

intermediate casing # 1

reservoir

intermediate casing # 2

production casing/liner

Outline

• Background • Drivers affecting selection of completion types • Major completion components • Examples of completion types • Speculation on future completions

Completion Classification

• Well Path – Vertical – Deviated – Horizontal – Multlateral

• Mode of production

– Flowing – Artificial lift

• Number of zones

– Single – Multiple

© 2011 Baker Hughes Incorporated. All Rights Reserved. 9

Artificial Lift

© 2011 Baker Hughes Incorporated. All Rights Reserved. 10

Other Drivers

• Reservoir type • Target Resource type • Reservoir extent, depth • Regulatory environment • Financial Objectives • Intervention or re-entry costs in well

environment • Subsurface environment • Expected well performance/life cycle • Monitoring requirements • Cost

Outline

• Background • Drivers affecting selection of completion types • Completion components • Examples of completion types • Speculation on future completions

Progression of Completions Through Time

© 2011 Baker Hughes Incorporated. All Rights Reserved. 14

Subsurface Safety Valve

• Deployed on tubing • Prevents uncontrolled flow from a well

in the case of an emergency • Typically shallowest downhole

equipment • Activated by a change in conditions • Designs vary by application • Most stringently tested product in

completions

© 2011 Baker Hughes Incorporated. All Rights Reserved. 15

Isolation Devices - Packers

• Mechanical device – seal between casing and tubing

• Located above producing zone(s)

• Parts – Sealing element – Slips (anchors) – Setting

mechanism • Well control • Corrosion control

© 2011 Baker Hughes Incorporated. All Rights Reserved. 16

Packers Types

• Permanent • Retrievable

• Mechanical set • Hydraulic set • Cased Hole • Open Hole

• Inflatable • Swelling

Flow Control Devices – Sleeves

© 2011 Baker Hughes Incorporated. All Rights Reserved. 18

• Position-able valves allowing a flow path between the inside and outside of tubing

• Shifted via several means – Mechanical – Hydraulic – Electric

• Multi-cycle and multi-position versions available

Flow Control Devices – Nipples

• Profiles placed in tubing able to receive latching accessories

– Accessories include plugs, chokes, check valves

– Accessories typically retrievable

© 2011 Baker Hughes Incorporated. All Rights Reserved. 19

Structural Devices – Hangers

© 2011 Baker Hughes Incorporated. All Rights Reserved. 20

• Mechanical devices that anchor sections of pipe

• Typically use slips to attach deployed pipe to host pipe

• May be run with packer to provide isolation

Filtration Devices - Screens

© 2011 Baker Hughes Incorporated. All Rights Reserved. 21

• Filters built onto perforated tubing

• Intended to limit the size of particles that can be admitted into the tubing

• Usable in – Open-hole – Perforated casing – In conjunction with

other filters Expandable

Screens

Premium Screens

Wire-wrapped Screens

Conveyance or Deployment Methods

© 2011 Baker Hughes Incorporated. All Rights Reserved. 23

Outline

• Background • Drivers affecting selection of completion types • Major completion components • Examples of completion types • Speculation on future completions

Application Specific Completions

• Sand Control Completions – Aimed at limiting production of solids

• Unconventional Completions – Enable efficient, multi-stage fracturing treatments and

minimize time until production begins

• Intelligent Completions – Allow active control of completion subsystems via electric or

hydraulic control – Limit need to re-enter well

© 2011 Baker Hughes Incorporated. All Rights Reserved. 26

Sand Control Completions

• Tools & services to minimize or prevent sand production in unconsolidated reservoirs

• Drivers: reliability, production

enhancement, efficiency, long term production

© 2011 Baker Hughes Incorporated. All Rights Reserved. 27

Controlling Sand Production Minimizes…

• Equipment damage

• Maintenance costs

• Well plugging

• Disposal costs

© 2011 Baker Hughes Incorporated. All Rights Reserved. 28

© 2011 Baker Hughes Incorporated. All Rights Reserved. 29

Sand Control Completion

Gravel Packing

Formation Sand

Wire Wrapped Screen

Gravel Pack Sand

Cased Hole

Gravel Pack Sand Casing

Perforations

Formation Sand

Screen

Cement

© 2011 Baker Hughes Incorporated. All Rights Reserved. 30

Open Hole

FracPacking

• Similar to gravel packing

• Higher pumping pressures and rates

• Rock strength or fracture pressure of rock exceeded

• Breaking or ‘Fracturing’ the formation

• Packing near wellbore to similar to gravel packing

© 2011 Baker Hughes Incorporated. All Rights Reserved. 31

Sand Control Pumping Services

• Slurry – Combination of proppant/sand and

carrier fluid

• Carrier Fluids – Engineered fluids designed to carry

proppant with one viscosity, and then “break” to a lower viscosity allowing to return to surface

© 2011 Baker Hughes Incorporated. All Rights Reserved. 32

Unconventional Completions

• Completion systems enabling multistage Hydraulic Fracturing

• Drivers: efficiency, reliability, cost

© 2011 Baker Hughes Incorporated. All Rights Reserved. 33

Plug and Perf

© 2010 Baker Hughes Incorporated. All Rights Reserved. 34

Setting Tool

Perf Guns

Composite Plug

• Cemented casing liner or full string • Perforate and produce multiple pay zones with Perf Guns / TCP • Composite Plugs provide isolation • Removed by milling with coil or pipe

© 2011 Baker Hughes Incorporated. All Rights Reserved. 35

Ball Drop Completions

© 2011 Baker Hughes Incorporated. All Rights Reserved. 36

Coiled Tubing Annular Fracturing

Intelligent Well Systems

• Wells able monitor and adjust the condition of downhole devices

• Often in offshore environments, where cost of re-entry is prohibitive

• Enhancements of previously discussed equipment

© 2011 Baker Hughes Incorporated. All Rights Reserved. 37

Well Monitoring

• Discrete Gauges permanently installed on completion assembly to measure real time

– Discrete Pressure – Discrete Temperature – Flow Rate – Water Cut – Density

• Distributed measurements – Fiber Optic Distributed

Temperature – Distributed acoustic

© 2011 Baker Hughes Incorporated. All Rights Reserved. 38

Intelligent Well Components

© 2011 Baker Hughes Incorporated. All Rights Reserved. 39

Outline

• Background • Drivers affecting selection of completion types • Major completion components • Examples of completion types • Speculation on future completions

Future Completions?

• Material enhancements – Reliability and cost

• Drill-in completions • Adaptive Completions

– Interpret – Diagnose – Adjust

© 2011 Baker Hughes Incorporated. All Rights Reserved. 41

Overview of Completions

© 2011 Baker Hughes Incorporated. All Rights Reserved. 42

Thank You