overhead conductor condition monitoring astp/api quarterly ... · overhead conductor condition...
TRANSCRIPT
1
Overhead Conductor Condition Monitoring
ASTP/API Quarterly Progress Report (No.1 2019)
Prepared by:
Dr Lakshitha Naranpanawe, Dr Hui Ma and Professor Tapan Saha
Power & Energy Systems Research Group
School of Information Technology & Electrical Engineering
The University of Queensland
Brisbane, Queensland, May 2019
2
Overhead Conductor Condition Monitoring
Quarterly Progress Report (No. 1 2019)
Produced by
Dr Lakshitha Naranpanawe, Dr Hui Ma and Professor Tapan Saha
This report was prepared as part of the “Overhead Conductor Condition Monitoring” project being funded by
the Energy Networks Association Limited.
To be cited as “Overhead Conductor Condition Monitoring (Quarterly Progress Report No 1 of 2019)”, The
University of Queensland, St. Lucia, 2018.
Power & Energy Systems Research Group
Axon building (#47), Staff House Road, St. Lucia Campus
The University of Queensland
Brisbane, QLD 4072 Australia
May 6 2019
Checked by Project Industry Partners:
Issue Changes Date
1 New document May 6, 2019
Signature Date
Ayan Ghosal (Western Power)
Matthew Cupples (AusGrid)
Peter Livingston (CitiPower/Powercor/United Energy)
Tony Stevens (SA Power)
3
Executive Summary
Energy Networks Association (ENA) member utilities have almost 800,000 kilometres of
overhead conductor in service, valued at several billion dollars. Many of this critical
infrastructure is ageing with some already reaching 70 years. This project investigates the
effective ways of condition monitoring of overhead conductor in Australian distribution
networks. The objectives are:
Review of conductor failure modes, degradation mechanisms and ageing parameters and
current Australian industry practices to asset manage overhead conductors.
Define the criteria for quantifying conductor condition and its end-of-life, and determine
the probability of conductor failure and estimate its remaining useful life.
Identify the core areas of research and development for improving condition assessment of
conductors in Australian Distribution Network Service Providers (DNSPs) networks.
Survey state-of-the-art conductor condition monitoring techniques that could be used to
monitor distribution conductor condition and assess the practicality and economics of
applying these techniques in Australian networks.
This project was started on June 20, 2018. Having been working closely with project industry
partners, the UQ team has successfully completed Milestone 1 tasks, including:
A comprehensive review on the types, failures modes and geographical locales of
conductors in Australian DNSPs’ networks. The review was based on an extensive
literature study on ENA 2015-2016 conductor survey and individual utility surveys, open
source databases, IEEE, IEC and CIGRE standards and recommendations and other
literature as well as discussions with industry experts.
A comprehensive study to understand the conductor degradation mechanism and
parameters that affect each type of degradation mechanism in Australian DNSPs’ networks.
After a survey of the current Australian DNSPs’ practice on conductor asset management
and their requirements for a proactive yet cost-effective conductor condition monitoring,
the UQ team identified core areas of research and development for an improved condition
assessment of conductors in Australian DNSPs’ circuits.
The Milestone 1 report was submitted to ENA on December 20, 2018. Since the completion of
Milestone 1, the UQ team has conducted a feasibility study on the implementation of conductor
4
health index methodology in Australian DNSP’s networks. In the past four months (from
January 1 to April 30 2019), the UQ team made the following progress:
Conducted a feasibility study on the application of health index method to improve the
condition assessment of bare overhead conductors in Australian distribution networks.
After carefully reviewing two representative health index methods i.e. Canadian method
and EA technology method, the UQ team found that the Canadian method may not be
suitable for Australian distribution networks while the parameters and their weightages
used in the EA technology method need to be further investigated.
Developed a model using corrosion induced conductor failure data. The model can provide
an estimation on the critical age, at which ACSR conductors in different geographical zones
may fail due to corrosion.
Developed a tool to estimate the remaining life of overhead conductors. The tool used a set
of indices to determine the conductor age de-rating factors, including operating conditions,
geographical locations, frequencies of fault occurrences, the number of mid-span joints and
the repair history.
Several Australian DNSPs have been using commercial software tools for condition-based
asset remaining life estimation. However, several issues are still not clear which impair the
applicability of these tools, especially (1) what parameters are the most suitable as the inputs
to the tools; (2) how to determine the weights to these parameters; and (3) how to obtain these
parameters from in-service circuits. Within the period of Millstone 2, the UQ team will focus
on the above three issues. In addition, the UQ team is planning to start the feasibility study of
using drone to take high-resolution photos of conductors and then evaluate the conductor
condition from these photos. This is the first task in Milestone 3 of the project proposal.
5
Table of Contents
1. Introduction 6
1.1 Background 6
1.2 Highlight of Project Progress 6
2. Industry and University Partners – Current 8
2.1 University team: 8
2.2 Industry: 8
3. Project Progress / Methodology 9
3.1 A Brief Review of Canadian Methodology of Conductor Health Index Calculation 10
3.2 A Brief Review of EA Technology’s CBRM Methodology of Conductor Health Index Calculation 11
3.3 A Brief Introduction of the UQ Team’s Methodology of Estimating Remaining Life of Conductors 13
3.4 Further Discussions on the Canadian and EA Technology Methods of Calculating Conductor Health Index 14
3.5 Input Parameters Proposed as Inputs for Calculating Conductor Health Index 15
3.6 Conductor Failure Data of Australian Distribution Networks 16
3.7 Weibull Analysis for Extracting Conductor Life Information Data 18
4. Future Works 20
5. Conclusions and Recommendations 20
6. References 21
7. Appendix 22
7.1 Risk Matrix 22
7.2 Gantt Chart/ Project Plan 23
7.3 Financial statement 24
6
1. Introduction
1.1 Background
ENA members have almost 800,000 circuit kilometres of overhead conductor in service. This
represents an asset, which is conservatively valued over several billion dollars. Overhead
conductor asset can be of different metal types, different sizes and capacities, and is employed
in all climatic zones including tropical, temperate, arid, and highlands. Many conductor assets
are ageing with some already reaching 70 years. Though many advancements in technology
have been achieved throughout these years, approaches to cost-effectively monitor condition
of bulk of conductors have not substantially changed. Existing conductor condition monitoring
practices are still visual inspections and conductor replacement is usually driven by the
frequency of conductor failures [1]. Reliable and cost-effective methods to assess the likelihood
of a conductor failure have not yet been developed for the Australian distribution network
service providers (DNSP) networks.
On June 20th 2018, ENA approved a research project proposal submitted by the University of
Queensland team. The project is aimed at investigating how to effectively monitor and assess
the condition of overhead conductor for an improved asset management of conductors in
Australian distribution networks. The research works conducted in this project are:
1. An establishment of a knowledge base of overhead conductors in Australian distribution
networks and subsequently the identification of the current core areas of research and
development for an improved conductor condition assessment;
2. A methodology for quantifying conductor condition and estimating the remaining useful
life of conductor; and
3. Identification of state-of-the-art commercially available conductor monitoring system and
emerging smart sensor-based system and possibly evaluating a smart sensor with data
collection methods.
The June 20th 2018, the project was formally started on June 20, 2018. Milestone 1 tasks were
completed in December 2018 and Milestone 1 report was submitted to ENA on December 20,
2018. After that, the UQ team is working on the tasks of Milestone 2. This report is the project
report for the period from January 1 to April 30, 2019.
1.2 Highlight of Project Progress
Having been working closely with project industry partners and two industry experts Colin Lee
and Keith Callaghan, the UQ team made significant progress.
7
During the period of Milestone 1, the UQ team reviewed conductor population in Australian
Distribution Network Service Providers (DNSPs) circuits including the types, failure modes
and geographical locales of conductors [2]. The UQ team performed a comprehensive study to
understand the conductor degradation mechanism and parameters that affect each type of
degradation mechanism. Moreover, the UQ team reviewed the current Australian DNSP’s
practice on conductor asset management and their requirements for a proactive yet cost-
effective conductor condition monitoring. The UQ team identified core areas of research and
development for an improved condition assessment of conductors in Australian DNSPs’
circuits.
During the period from January 1 to April 30 2019, the UQ team has conducted a feasibility
study on the application of health index method to improve the condition assessment of bare
overhead conductors in Australian distribution networks. The UQ team did a comprehensive
review on two representative health index methods, i.e. Canadian method and EA technology
method. Moreover, the UQ team developed a model, which was based on the dataset of
conductor failure due to corrosion. The model can estimate the critical age, at which ACSR
conductors in different geographical zones can fail due to corrosion. Furthermore, the UQ team
developed a tool to estimate the remaining life of overhead conductors. The tool used a set of
indices to determine the conductors’ age de-rating factors, which includes conductor operating
conditions, geographical locations, frequencies of fault occurrence, the number of mid span
joints and the repair history.
Though some Australian DNSPs have been using commercial software tools for condition
based asset remaining life estimation, several issues still exist impairing the applicability of
these tools. These issues are: (1) what parameters are the most suitable inputs to the tools; (2)
how to determine the weights assigned to these parameters; and (3) how to obtain these
parameters from in-service circuits. The UQ is currently working on these issues and findings
will be included in Milestone 2 report.
8
2. Industry and University Partners – Current
2.1 University team:
Tapan Saha
Hui Ma
Lakshitha Naranpanawe
University Lead: Tapan Saha
2.2 Industry:
Srinivansan Chinnargan (Energy Queensland),
Matthew Cupples (AusGrid),
Ayan Ghosal (Western Power),
Peter Livingston (CitiPower, Powercor, United Energy),
Tony Stevens (SA Power)
Industry Lead: Ayan Ghosal
9
3. Project Progress / Methodology
In the past four months (from January 1, 2019 to April 30, 2019), the UQ team has been
working on Milestone 2, which objective is to investigate a methodology for quantifying
conductor condition and estimating the remaining useful life of conductor. The key research
and developed activities are:
1) Feasibility of developing condition assessment of conductor using health index
methodology. Investigation of globally documented conductor ‘health index’ methods
including the Canadian method (the health index is a weighted sum of conductor condition
parameters, field inspection data, and service records, used to estimate the remaining useful
life of conductor). Compare alternative Health index methods, assess suitability for
Australian conditions and select the best to be trialled in the project.
2) A demonstration of health index method for condition assessment of a representative type
conductor in Australia DNSPs’ lines. Demonstration of the selected ‘health index’ method
on a representative type of distribution conductor for the participating ENA members, and
benchmark the results against past investigation of conductor samples and metallurgical
studies (such as those undertaken by Western Power and other ENA members). Trialling
the Health index could be only possible provided the ENA member utility provides in-kind
contribution for testing, validation, and access of previous measurements on selective
conductor types.
This chapter of the report presents the methodologies, approaches, outcomes and discussions
of the above research and developed activities. The UQ team has conducted a comprehensive
review on two representative health index methods (Canadian method and EA technology
method), which is detailed in Sections 3.1 and 3.2. With the help from industry experts Colin
Lee and Keith Callaghan, the UQ team developed a method to estimate the remaining life of
overhead conductors. This method is presented in Section 3.3. Further discussions on the
advantages and limitations of the above three methods are provided in Section 3.4. To calculate
conductor health index and estimate conductor remaining life, the input parameters and their
weightages need to be properly defined. This can be achieved through statistical analysis of
conductor failure data and condition monitoring, which are presented in Section 3.5. The UQ
team has analysed conductor failure datasets from a number of Australian DNSPs. A summary
of these datasets is presented in Section 3.6. By analysing the datasets of conductor failure due
to corrosion, the UQ team has developed a methodology to extract conductor life information
and estimate the critical age, at which conductors in different geographical zones can fail due
to corrosion. The methodology is presented in Section 3.7.
10
3.1 A Brief Review of Canadian Methodology of Conductor Health Index Calculation
The conductor health index (HI) methodology presented in this section was developed by a
team of Canadian researchers [3]. The health index was calculated using a set of condition
parameters, which are related to the long-term degradation factors leading to the conductor’s
end of life. Firstly, a set of condition parameter scores (CPS) are calculated as
1
.max
1
( )
( )
n
n n n
n
n
n n n
n
SCPS WSPC
CPS
SCPS WSPC
(1.1)
Where,
SCPS - Sub-Condition Parameter Score
WSCP - Weight of Sub-Condition Parameter
SCPSmax - Maximum Score for Sub-Condition Parameter
βn - Data availability coefficient
DRF - De-Rating Factor
Then, the above CPSs are used to calculate the health index as
1
.max
1
( )
( )
m
m m m
m
m
m m m
m
CPS WPC
HI DRF
CPS WPC
(1.2)
Where,
CPS - Condition Parameter Score
WCP - Weight of Condition Parameter
CPSmax - Maximum Score for Condition Parameter
αm - Data availability coefficient
In the Canadian method, the conductor’s mechanical strength (torsional ductility and tension)
was adopted as a critical parameter. Visual observations, service records, number of
11
repairs/splices and the remaining tensile strength of the conductor samples were all used in
health index calculation.
3.2 A Brief Review of EA Technology’s CBRM Methodology of Conductor Health
Index Calculation
EA Technology’s Condition based risk management (CBRM 2.0) platform can calculate
assets’ health indexes and the probability of failure [4-6]. The main reasons for investigating
the EA technology’s CBRM method are: (1) the publically availability of the detailed
information of the EA Technology’s CBRM methodology, procedures and implementations;
and (2) Australian utility companies’ experience in using the EA technology’s CBRM tools
The EA Technology’s CBRM software is designed for the assessment, forecasting and
reporting of Asset Risk. Its main objectives are:
Comparative analysis of network asset performance between Distribution Service
Providers over time.
Assessment of the licensee's performance against the Network Asset Secondary
Deliverables.
Communication of information affecting the Network Asset Secondary Deliverables
between the licensee, the Authority and, as appropriate, other interested parties in a
transparent manner.
The key outputs of the EA Technology’s CBRM methodology is
An evaluation of Probability of Failure (PoF), which is the likelihood of condition-
based failure per annum for individual assets.
An evaluation of the Cost of Failure (CoF) associated with condition-based failures for
individual assets.
To calculate the PoF and CoF and eventually to obtain the risk matrix, the following input
parameters are used (refer to Figure 1):
Location Factors - factors relating to aspects of the environment, in which the asset is
installed and may have impact on the asset’s expected life.
Duty Factors – factors relating to the usage of the asset at its specific location that may
have impact on the asset’s expected life.
12
Observed Condition Inputs - factors relating to the observed condition of the asset.
Measured Condition Inputs – factors relating to the condition/health of the asset
determined by measurements, tests or functional checks.
Reliability Modifier - a factor relating to generic reliability issues associated with the
individual make and type of an asset.
Figure 1 Methodology for calculating the probability of failure [2]
The factors such as Location Factor, Duty Factor, Health Score Modifier and Reliability
modifier in Figure 1 are calculated using the methodologies as summarized in Table 1.
Limitation of this method is described in section 3.4.
13
Table 1 Parameters used to calculate PoF and CoF modifiers
Modifier Required Parameters
Location Factor Distance from the coast
Altitude
Corrosion category
Indoor/Outdoor
Duty Factor Asset category
Factors that introduce additional ageing due to the way the
asset is being used
Health Score Modifier Observed condition modifier (defined as follows)
Measured condition modifier (defined as follows)
Observed Condition Modifier Condition inputs from observations
Measured Condition Modifier Condition inputs from measurement
Reliability Modifier Based on the industry experience and available conductor
condition data
3.3 A Brief Introduction of the UQ Team’s Methodology of Estimating Remaining
Life of Conductors
The UQ teams’ conductor remaining life estimation methodology uses a set of input parameters
including
1. Conductor data (Type, Age, Climate zone and Conductor operating conditions)
2. Conductor operating conditions are
a. Whether the conductor is a distribution conductor
b. Whether the conductor is operating in a costal location
c. Does the conductor has high fault history
d. Level of tension in the conductor (high or low)
e. Whether the conductor span is above 300 m or not
f. Whether the conductor already has multiple repairs and mid span joints
14
Each of the above parameters is assigned a de-rating factor. The de-rating factors are used to
compute the remaining life of the conductors. The UQ team’s software tool is implemented in
Microsoft Excel. Several screen shots of the current version of the UQ team’s software are
shown below.
Figure 2 The GUI of the UQ team developed software: Typical conductor life
Figure 3 The calculated results of the UQ team developed software: Conductor data input and estimated
data
It should be noted that UQ team is currently working with industry experts towards refining
the de-rating factors correspond to each conductor operating condition for improving the
performance of the above software tool.
3.4 Further Discussions on the Canadian and EA Technology Methods of Calculating
Conductor Health Index
According the existing literature, the Canadian health index methodology has shown promising
results [3]. However, after a feasibility study the UQ team found that,
15
The Canadian method was developed mainly for transmission networks, on which
various sensors can be installed.
Canadian climate conditions are significantly different from that of Australia.
The detailed information of the input parameters used in the Canadian method is not
disclosed.
Based on the above facts, the UQ team has concluded that the Canadian method may not be
suitable to the Australian distribution network.
The EA Technology’s CBRM method provides a well-defined platform that can be used to
calculate the health indices of various power system assets. However, the standard CBRM
method is not tuned to produce an accurate health index of distribution overhead conductors.
For example, the standard CBRM method only uses visual condition and Mid-span joints as
the input parameter to derive the observed condition modifier of conductors (please refer to
Figure 1). However, according to the existing literature and experts’ knowledge, only visual
condition and Mid-span joints alone do not reflect the true condition of the conductor.
Therefore, one can suggest that the CBRM method needs to be refined by incorporating more
observed conditions and test data for accurately calculating the health indices of distribution
conductors. A number of Australian DNSPs have already used the EA Technology’s CBRM
methodology to determine health indices of their conductors. Hence, there is a timely
requirement of focusing our research on selecting the most suitable input parameters and
determining their weightages, which can be used as inputs of the EA Technology’s CBRM
method.
3.5 Input Parameters Proposed as Inputs for Calculating Conductor Health Index
To accurately calculate the health index for conductors in Australian distribution networks, it
is necessary to select a set of parameters that can accurately reflect the true condition of the
conductors under investigation. However, according to the UQ teams findings, the information
on how to select these parameters are still insufficient. The UQ team has started working on
identifying: (1) what parameters are the most suitable as the inputs to the tools; (2) how to
determine the weights to these parameters; and (3) how to obtain these parameters from in-
service circuits.
The input parameters the UQ team has identified so far are:
1. Maximum conductor operating temperature
2. Loss of cross section from lightning and fault current
16
3. Loss of cross section due to conductor clashing (phase to phase faults and high winds)
4. Conductor location (i.e. the distance to the coast)
5. Loss of cross section from corrosion
6. Loss of galvanizing layer (ACSR and SC/GZ conductors)
7. Loss of cross section from galvanic corrosion (ACSR conductors)
8. Line has long spans in open area (greater than 200 m)
9. Loss of cross section from fatigue (at clamps and damper positions)
10. Loss of cross section due to vegetation impact
11. Number of repair sleeves
12. Condition of repair sleeves and adjacent conductor
13. Visual inspections records
Among the above input parameters, only items 11, 12 and 13 are considered in the EA
Technology’s CBRM methodology. The UQ team is currently working on refining the above
list and identifying the weighting factors for each of these parameters.
As the first step of the parameter identification process, the UQ team has started analysing the
conductor failure data collected from a number of Australian DNSPs.
3.6 Conductor Failure Data of Australian Distribution Networks
The conductor failure data received from Australian DNSPs are listed in Table 2. From the
table, it can be seen that all the data consist of conductor population, cause of failure and
voltage level. Except for the data provided by SA Power Networks, all data comprise sufficient
information for linking the cause of failure to the type of the conductor.
One vital information required for the statistical analysis of conductor failure data is the
conductor age when fail. Such information are available only in the data provided by Western
Power and Citipower/Powercor. The UQ team is conducting a Weibull analysis on conductor
failure data provided by Western Power.
17
Table 2 Information of conductor failure data received form Australian DNSPs
Data source Content of the failure data received
Energy Queensland Conductor type
Cause of failure
Voltage level
Maintenance crews’ notes
Citipower/Powercor Conductor population/ Year Installed/ Climate Zone
Conductor failure data
o Conductor type
o Cause of failure
o Voltage level
o Conductor age when fail
Western Power Conductor age profile
Conductor failure data
o Conductor type
o Cause of failure
o Voltage level
o Conductor age when fail
o Climate Zone
SA Power
Networks
Conductor population
Cause of failure/ Voltage level – Conductor type unknown
Ausgrid Conductor Age Profile
Failure cause, Number of failures per year (2014 – 2018)
TasNetworks Conductor population
Distance from coastline
Conductor age profile
Length of conductors installed per year (1952 - 2014)
Age based conductor replacement cost
Conductor failure data (# of failures per year 2006 – 2017)
Conductor failure data
o Conductor type
o Cause of failure
o Voltage level
Maintenance crews’ notes
18
3.7 Weibull Analysis for Extracting Conductor Life Information Data
Weibull analysis (also called "life data analysis") is a statistical method used to make
predictions on the life of assets in the population [7, 8]. This is achieved by fitting a statistical
distribution to data samples. The UQ team has conducting Weibull analysis on a data set
provided by Western power. The data set comprises of conductor type, climate zone, cause of
failure and conductor age at the time of failure.
Figure 4 and 5 illustrate the Weibull plots and conductor age distribution Steel, ACSR and
Aluminium conductors in various climate zones of Western Power distribution network
respectively.
Figure 4 Weibull plots correspond to Steel, Aluminium and ACSR conductors failed due to corrosion in
Western Power DN
Figure 5 Conductor age distribution in Western Power DN
y = 7.3406x - 27.947
y = 7.9065x - 30.387
y = 2.3307x - 8.1675
y = 5.8923x - 23.823
-5
-4
-3
-2
-1
0
1
2
2 2.5 3 3.5 4 4.5
ln(l
n(1
/(1
-Pf)
))
ln(age)
Steel-Arid Steel-costal Aluminium ACSR
0
200
400
600
800
1000
1200
1400
1600
1800
1 4 8 12 15 19 22 25 28 30 34 37 41 44 47 50 53 57 60 63 66 70 76
length
(km
)
Age( Years)
ACSR coastal Steel Arid Steel coastal Aluminium coastal
19
The Weibull plots in Figures 4 used to calculate two statistical parameters, namely β and η. β
corresponds to the shape of the Weibull plot while η is a scale parameter representing the
characteristic life of the conductor. Values of these two parameters corresponding to Western
Power data are calculated and listed in Table 3.
Table 3 Statistical parameters calculated using Weibull modelling
β Characteristic life
η (years)
Mean time to
failure (MTTF)
(years)
Steel - Arid 7.3406 45 42
Steel - Costal 7.9065 45 43
Aluminium 2.3307 33 29
ACSR 5.8923 57 52
From Figure 4, Figure 5 and the values of β and η, it can be concluded that:
Steel-Arid: The length of steel conductors in Arid is 17,897 km. According to the data,
the average conductor age is 31.3 years. However, according to the Weibull modelling,
the characteristic life1 of the steel conductors in arid is 45 years. Further, β is 7.341
hence the failure data represent a wear-out failure of steel conductor due to corrosion.
As β = 7.341, the mean time to failure2 is 42 years.
Steel-Coastal: The length of steel conductors in coastal is 15,076 km. According to the
data, average conductor age is 44 years. However, according to the Weibull modelling,
the characteristic life of steel conductors in coastal areas is 45 years. Further, the β is
7.9, which implies failure data represent wear-out failure of steel conductors in coastal
areas. However, the mean time to failure is 43 years.
Aluminium: The length of aluminium conductors in coastal is 16,113 km. According
to the data, the average conductor age is 38.48 years. According to Weibull analysis, β
is 2.3307 and characteristic life is 33 years. This implies that the failure data represent
a wear-out failure of aluminium conductor due to corrosion. The mean time to failure
is 29 years.
1 Characteristic life (η)- the time at which 63.2% of the units will fail
2– Mean time to failure describes the expected time to failure for a non-repairable system
20
ACSR: The length of ACSR conductors is 3,156 km. According to the data, the average
conductor age is 40 years. The β is 5.8923 and the characteristic life is 57 years. This
implies that the failure data represent a wear-out failure of steel conductors. The mean
time to failure is 52 years.
Based on above results, it can be seen that there is a difference between the conductor end-of-
life estimated using simple statistical parameters (i.e. mean value) and that obtained from the
Weibull analysis. Further, the Weibull analysis results are in a good agreement with the
conductor end of life figures typically use by Australian DNSPs. Therefore, the Weibull
analysis can be used to analyse conductor failure data. However, it should be noted that,
conductor failure data collected from DNSPs may not always contain the information required
to conduct a Weibull analysis.
4. Future Works
To conduct a detailed investigation of the parameters that Australian DNSPs should use
as the input parameters to their in-house condition-based asset management tools.
To investigate the methods of obtaining, calculating and estimating the above input
parameters.
To identify the weighting factors for each of the input parameters.
To incorporate the refined input parameters with suitable weighting coefficients and
provide to one of project partners to use in their in-house condition-based asset
management tool on a selected type of conductors (given that the UQ team is granted
the access to the tool by the project partner).
A feasibility study of using drone to take high-resolution photos of conductors and then
evaluate the conductor condition from these photos. This is the part of the first task in
Milestone 3 of the project proposal.
5. Conclusions and Recommendations
The following conclusions and recommendations are made:
The Canadian method was developed for transmission networks, on which various
sensors can be installed. However, Canadian climate conditions are significantly
different from that of Australia. Moreover, the detailed information of the input
parameters used in the Canadian method are not disclosed. As a result, the Canadian
method may not be suitable to the Australian distribution network.
21
Some of Australian DNSPs in-house asset management software tools can provide
health index calculation and predict the probability of failure of overhead conductors
in distribution networks. However, there is still lack of understanding of input
parameter selection. Hence, the accuracy of these software tool cannot be guaranteed.
To deal with such difficulties, the UQ team has been investigating the input parameters,
which can reflect the condition of the conductors more accurately.
The UQ team found that the conductor failure data collected from Australian DNSPs
do not always contain sufficient information, which may impair the accuracy of
calculating conductors’ health index and estimating conductors’ remaining useful life.
The UQ team is currently working towards improving the accuracy of existing
conductor health index calculation techniques.
6. References
[1] R. K. Aggarwal, A. T. Johns, J. A. S. B. Jayasinghe, and W. Su, "An overview of the
condition monitoring of overhead lines," Electric Power Systems Research, vol. 53, no.
1, pp. 15-22, 2000/01/05/ 2000.
[2] H. M. Lakshitha Naranpanawe, Tapan Saha, "Overhead Conductor Condition
Monitoring : Milestone REport 1," December 2018.
[3] Y. Tsimberg, K. Lotho, C. Dimnik, N. Wrathall, and A. Mogilevsky, "Determining
transmission line conductor condition and remaining life," in 2014 IEEE PES T&D
Conference and Exposition, 2014, pp. 1-5.
[4] DNO COMMON NETWORK ASSET INDICES METHODOLOGY. Available:
https://www.ofgem.gov.uk/system/files/docs/2017/05/dno_common_network_asset_i
ndices_methodology_v1.1.pdf
[5] E. Technology. Condition Based Risk Management (CBRM). Available:
https://www.eatechnology.com/wp-content/uploads/2017/03/CBRM-brochure.pdf
[6] E. Technology. CBRM 2.0. Available: http://www.eatechnology.com.cn/wp-
content/uploads/pdfs/10348_EA_CBRM_2_Brochure_LR_V4.pdf
[7] R. B. Abernethy, J. Breneman, C. Medlin, and G. L. Reinman, "Weibull analysis
handbook," Pratt and Whitney West Palm beach fl Government Products DIV1983.
[8] W. Nelson, "Weibull analysis of reliability data with few or no failures," Journal of
Quality Technology, vol. 17, no. 3, pp. 140-146, 1985.
22
7. Appendix
7.1 Risks
Insufficient information contained in the conductor failure data provided by the industry
partners.
Inaccuracy of some type of data provided by the industry partners.
The UQ team is not given the access to the industry partners in –house asset management
tools.
23
7.2 Gantt Chart/ Project Plan
Task
Time (months)
1-6 7-10 11-12 13-14 15-18
Milestone 1
Review, literature study, analysis and
writing report
Milestone 2
Collecting conductor failure data
modelling and analysing
Determining feasibility of developing
condition assessment of conductor
using health index methodology
Study of DNSPs in-house assert
management software tools
Identifying input parameters
Identifying weighting factors for
the input parameters
A demonstration of health index
method for condition assessment of a
representative type conductor in
Australia DNSPs’ lines
Milestone 3
Survey state-of-the-art conductor
condition monitoring techniques
Evaluating prospective emerging smart
sensor-based conductor monitoring
systems and provide some
recommendations
- Completed tasks
- In-Progress Tasks
24
7.3 Financial statement
2018
Consolidated Carry
Fwd
Aug - Dec Adjustments YTD
Actuals
Carry
Forward
Jan
Feb Mar Apr Adjustments YTD
Actuals
Revenue
External Revenue
Research Income 0.00 0.00 0.00 0.00 0.00 90,000.00 0.00 0.00 0.00 0.00 90,000.00
Total External Revenue 0.00 0.00 0.00 0.00 0.00 90,000.00 0.00 0.00 0.00 0.00 90,000.00
Internal Transfers
UQ Wide Transfers
Expense
0.00 0.00 0.00 0.00 0.00 (13,163.56) 0.00 0.00 0.00 0.00 (13,163.56)
Total Internal Transfers 0.00 0.00 0.00 0.00 0.00 (13,163.56) 0.00 0.00 0.00 0.00 (13,163.56)
TOTAL REVENUE 0.00 0.00 0.00 0.00 0.00 76,836.44 0.00 0.00 0.00 0.00 76,836.44
Expenditure
Academic Salaries
Salaries - Academic Non
Casual
0.00 47,026.59 0.00 47,026.59 0.00 9,299.73 8,780.37 9,223.64 9,053.24 0.00 36,356.98
Total Academic Salaries 0.00 47,026.59 0.00 47,026.59 0.00 9,299.73 8,780.37 9,223.64 9,053.24 0.00 36,356.98
General Salaries
Salaries - General Casual 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total General Salaries 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Other Expenditure
General Operating
Expenses
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Consultant Professional &
Oth
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Travel 0.00 0.00 0.00 0.00 0.00 32.28 0.00 0.00 0.00 0.00 32.28
Total Other Expenditure 0.00 0.00 0.00 0.00 0.00 32.28 0.00 0.00 0.00 0.00 32.28
TOTAL EXPENDITURE 0.00 47,026.59 0.00 47,026.59 0.00 9,332.01 8,780.37 9,223.64 9,053.24 0.00 36,389.26
Operating
Surplus/(Deficit)
0.00 (47,026.59) 0.00 (47,026.59) 0.00 67,504.43 (8,780.37) (9,223.64) (9,053.24) 0.00 40,447.18
Carry Forward 0.00 0.00 0.00 (47,026.59) 0.00 0.00 0.00 0.00 0.00 (47,026.59)
Accumulated Position (47,026.59) (6,579.41)
* Currently the project is in deficit by $6,579.41.