overall assessment of the quality of the ppp · pdf fileromania overall assessment of the...
TRANSCRIPT
WS0101.3730241.1WS1801.141312.1
ROMANIA
OVERALL ASSESSMENT OF THE QUALITY OF THE PPP LEGISLATION AND OF THE EFFECTIVENESS OF ITS IMPLEMENTATION
2011
I- PPP Legislative Framework
Assessment (LFA)
Compliance of the PPP legal framework with PFI Guide
recommendations1 and Best Practice
Core Area Rating Assessment
1- PPP Legal Framework
Existence of specific PPP law or a comprehensive set of laws regulating
concessions and other forms of PPP and allowing a workable PPP legal
framework
14/18
2-Definitions and
Scope of the Law
Existence of a clear definition of the boundaries and scope of application
of the concession legal framework (e.g. definition of "PPP", sectors
concerned, competent authorities, eligible Private party) limiting the risk
of a challenge to the validity of PPP contracts, irrespective of whether
the act is specifically targeted at PPP
16/24
3-Selection of the Private
Party
Mandatory application of a fair and transparent tender selection process.
Limited exceptions allowing direct negotiations, competitive rules for
unsolicited proposals and the possibility to challenge illegal awards.
35/45
4-Project Agreement Flexibility with respect to the content of the provisions of the Project
agreements which should allow a proper allocation of risks without
unnecessary or unrealistic/not bankable/compulsory
requirements/interferences from the Contracting Authority (obligations,
tariff, termination, compensation).
16/30
5-Security and Support Issues Availability of reliable security instruments to contractually secure the
assets and cash-flow of the Private Party in favour of lenders, including
"step in" rights and the possibility of government financial support, or
guarantee of, the Contracting Authority’s proper fulfilment of its
obligations.
4/18
1 UNCITRAL Legislative Guide on Privately Financed Infrastructure Projects, 2001 (hereinafter the "PFI Guide")
Checklist ROMANIA
2.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
6-Settlement of Disputes and
Applicable Laws
Possibility to obtain proper remedy for breach under the applicable law
through international arbitration and enforcement of arbitral awards.
13/15
General LFA Rating 64,2% Medium Compliance
II-Legal Indicators Survey
(LIS)
Effectiveness Assessment : How the PPP law works in practice
Core Area Rating Legal Indicator Survey
7- Policy Framework Existence of a policy framework for public private partnerships 7/24
8 Institutional Framework Existence of an institutional framework for public private partnerships 9/27
9- PPP Law Enforcement Award and implementation of PPP projects in compliance with the Law 20/27
General LIS Rating 45,3% Low Compliance/ Effectiveness
OVERALL RATING 54,8% Medium Compliance/ Effectiveness
Local Expert2: Gide Loyrette Nouel (Bucharest)
2 The Local Experts in charge of each country have been consulted for the elaboration of the responses to the Checklist in their capacity of well recognized established law
firm in the country but the Local Experts as well as EBRD are in no way responsible for the responses given to any question in this Checlist as the Consultant was free to
use any other sources of information for its final determination.
3.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
RATING: Key for assessment of Each Question
Yes 3 points Yes, with reservations 2 points No, with Limited compliance / redeeming
features
1 point
No 0 point
N/A Not applicable 0 point/ Not included in total
Key for Assessment of Each Core Area and for Overall Assessment
> 90% Very High Compliance/Effectiveness
≥ 70%-89% High Compliance/ Effectiveness
50%-69% Medium Compliance/ Effectiveness
30%-49% Low Compliance/ Effectiveness
< 30% Very low Compliance/ Effectiveness
TERMINOLOGY
So as to keep answers consistent and avoid ambiguity, we set out below some brief definitions of the terminology used in this questionnaire. Any
definition is provided solely to clarify some of the terminology used below. The reader should note that any such definition does not correspond
with any given definition under best international practice (which does not provide for any standardised PPP legal definitions recognised
worldwide) neither should it be interpreted that we recommend the adoption of such definitions under actual documentation, but they are
included in the interests of clarity for the completion of this questionnaire, and we should be grateful if you could adopt such definitions for the
purposes of completing the questionnaire.
4.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
"Public Private Partnership" -"PPP" or "PPP project" includes all types of long-term arrangements between public authorities
and private institutions , including but not limited to; Concessions , BOT and derived forms, PFI and Institutional PPP. For the
purposes of this questionnaire, PPP excludes the sale of public assets or of public company shares which are part of a privatisation
process and also excludes public works, services or supply contracts which are subject to public procurement rules.
The following types of Public - Private Partnership Agreements may be adopted by a Contracting Authority for undertaking infrastructure
projects. These are solely indicative in nature and the Contracting Authority may seek to adopt a combination of the different contractual
arrangements, which incorporate some of their elements or combine elements.
"BOT" - (Build-Operate-and-Transfer)- and derived forms : a contractual arrangement whereby the Private Party undertakes to
finance, design, construct under a turnkey risk basis, operate and maintain an Infrastructure project for a specified period after
which period the project facilities are transferred to the Granting Authority usually without payment of any compensation.
The Private Party has the right to collect contract or market based tariffs or fees from the users of the infrastructure project, as
specified in the PPP agreement, to recover its investment and operating and maintenance expenses for the project. A BOT type of
PPP arrangement may provide for all the implementation and operational efficiencies of the private sector, together with new
sources of infrastructure capital. Derived forms of BOT contractual arrangements exist such as Build-Own-Operate-and-Transfer
(BOOT) similar to the BOT agreement, except that the Private Party owns the Infrastructure project during the specified term before
its transfer to the Contracting Authority or its designee, or such as Build-Own-and-Operate (BOO) which is a contractual
arrangement similar to the BOT agreement, except that the Private Party owns the Infrastructure project and no transfer of the
project to the Contracting Authority or its designee at the end of the fixed period is envisaged. Derived forms incorporating Lease
right rather than Ownership or dealing with rehabilitation or extension rather than construction which extent the possible
combination which for the purpose of this questionnaire will all be hereafter refferred to as BOT for simplification purpose exept
where legal specificcity requires specific treatment.
"Concession": is an act attributable to the State whereby a Contracting Authority entrusts to a third party the total or partial
management of public services for which that authority would normally be responsible and for which the third party assumes all or
part of the risk.
"PFI" (Private Finance Initiative) : a form of cooperation and partnership between public authorities and Private Parties which aim
to ensure the funding, construction, renovation, management or maintenance of an infrastructure or the provision of service to the
infrastructure without the delegation of the public service itself. It is a contractual arrangement whereby the Private Party
5.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
undertakes the financing and the construction of an infrastructure project and after its completion transfer it to the Contracting
Authority or its designee. This arrangement may be employed in the construction of a public service facility for which the public
service must be operated directly by the contracting authority for whatever reason but the operation and maintenance of the facility
remain the responsibility of the Private Party for the entire duration of the PPP agreement. The contracting authority will reimburse
the total project investment on the basis of a rent based of an agreed schedule with the payment starting from the date of
commencement of operation and pay for the services rendered to the facility on a performance basis.
"IPPP"(Institutional PPP): a structural or corporate form of PPP which provide for the cooperation between public authorities and
a Private Party through a joint venture or mix (publid- private shareholding) company in which case all reference to the slection
process refers to the selection of the Private Party.
Other definitions:
The "Law" or "PPP Law": a law regulating any form of PPP including but not limited to Concession, BOT, PFI, IPPP and
including, for the purpose of this questionnair, the set of rules applicable to any PPP in the absence of a specific PPP law. The Law
for the purpose of this questionnaire also includes any implementing regulation and any form of governemental act regulating PPP.
"BOT Law" : a law regulating a BOT type of PPP in their multiple forms.
"Concession Law": a law regulating a Concession form of PPP.
"Contracting Authority": a public authority empowered to award a PPP and enter into Project Agreements
"PFI Law": a law regulating a PFI form of PPP.
"PPP unit" : specialized institution/agency/ministerial department established to promote and take care of PPP.
"Private Party" : Private Party or other entity in the form of a special purpose company to which a Project Agreement in general
has been awarded. [The word Private party will be used for the sake of this study even in case the PPP regulation allows PPP
business partner to be a mix company or even a public entity.]
"Project Agreement": an agreement(s) between the Contracting Authority and the Private Party regulating their respective rights
and obligations with respect to the PPP project.
6.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
REFERENCE TO BEST PRACTICE
•UNCITRAL Legislative Guide on Privately Financed Infrastructure Projects, 2001 (hereinafter the "PFI Guide") and UNCITRAL
Model Legislative Provisions on Privately Financed Infrastructure Projects, 2003 (UNCITRAL Model Legislative Provisions).
•EC - Commission Interpretative Communication on Concessions Under Community Law dated 12 April 2000; together with additional
EU major documents/decision /recommendation on concessions including Directives 2004/18/EC and 2004/17 EC of 31 March 2004;
Green Paper on Public Private Partnerships and Community Law on Public Contracts and Concessions dated 30 April 2004; Report on
the public consultation on the Green Paper (SEC(2005) 629- Communication from the Commission to the European Parliament, the
Council, the European Economic and Social Committee and the Committee of the Regions on Public-Private Partnerships and
Community Law on Public Procurement and Concessions (Brussels, 15.11.2005.COM(2005) 569) European Parliament resolution on
public-private partnerships and Community law on public procurement and concessions (2006/2043(INI)); European Commission
Guidelines for Successful Public-Private Partnerships (2003).Commission Interpretative Communication Brussels, 05.02.2008
C (2007)6661on the application of Community law on Public Procurement, and Concessions to Institutionalised Public-Private
Partnerships (IPPP);
•EBRD Core Principles for a Modern Concessions Law – selection and justification of principles Prepared by the EBRD Legal
Transition Team.2005;
•UNIDO Guidelines for Infrastructure Development through Build Operate Transfer (BOT) Projects, 1996 (UNIDO BOT Guidelines);
and
•OECD Basic Elements of a Law on Concession Agreements, 1999-2000.
7.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2011 OVERALL ASSESMENT ROMANIA
Romanian Law has undergone important changes at the end of 2010 further to the enactment of a new legal framework dedicated to PPPs, comprising the PPP
Act No. 178/2010 (the "PPP Act 178/2010") and the Government Decision No. 1239/2010 approving the Norms for the implementation of the PPP Act No.
178/2010, as well as certain measures for the reorganisation of the Central Unit for the Coordination of Public-Private Partnership within the Ministry of
Public Finances (the "PPP Norms").Please note that important amendments have been brought to the PPP Act 178/2010 as of 17 October 2011, further to the
enactment of Government Emergency Ordinance No. 86/2011, and to the PPP Norms as of 20 October 2011, further to the enactment of Government Decision
No. 1000/2011.
The amendments brought to the PPP legal framework in October 2011 purport at rendering the procedures for the award of a PPP contract
compliant with the European Union Directives on public procurement.
Among the important amendments to the PPP regulations, the following should be noted:
- contracts awarded for the purposes of carrying out relevant activities in public utility sectors: gas, heat and electricity, water, transport, postal
services, exploration and extraction of oil, gas, coal and other solid fuels, ports and airports are expressly included among the PPP contracts;
- detailed provisions on the qualification and selection criteria;
- provisions on subcontracting: right for Contracting Authorities to ask potential investors, without prejudice to the question of the private
investor's liability, to indicate in the offer any share of the contract they intend to subcontract to third parties, as well as any proposed
subcontractors; contracts entered into with the subcontractors indicated in the offer must be submitted to the Contracting Authority upon
execution of the PPP contract and attached thereto; the replacement of subcontractors throughout the performance of the PPP contract is
allowed only subject to the approval of the Contracting Authority and to such replacement not resulting in any modification of the initial
technical or financial offer;
- possibility of submitting variants (alternative offers) if expressly allowed in the contract notice;
- detailed provisions on technical specifications including: definitions of certain technical specifications, rules to be complied with by
Contracting Authorities when establishing technical specifications;
- the price of the PPP contract may be modified throughout the performance of the contract only in limitative circumstances expressly
provided by the PPP Norms;
- detailed rules on the publishing and content of notices of award of PPP agreements;
8.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
- the possibility for the public partner to resort to a negotiated procedure without having published a contract notice only in exceptional
circumstances;
- enhancement of the role of the Central Unit for the Coordination of Public Private Partnership."
-
Romania had benefited from a PPP Act which was repealed in 2006 by Government Emergency Ordinance No. 34/2006 implementing the
European acquis (i.e. Directives 2004/17/EC, 2004/18/EC, 89/665/EEC and 92/13/EEC). Concessions, regulated as contractual PPPs, thus
became the only form of partnership between public authorities and private operators that benefited from a dedicated legal framework.
This approach did not have the results expected, as a limited number of Concessions of works and services have been granted under GEO
34/2006.
In this context, the enactment of a new legal framework dedicated exclusively to institutionalised PPPs was deemed necessary in 2010 as a
possible solution for attracting private funding in the public sector.
The new PPP Act did not repeal or amend the pieces of legislation regulating Concessions enacted in 2006. As a result, Romanian Law currently
includes the following main sets of rules:
- Public-Private Partnerships implemented as IPPPs governed by the PPP Act 178/2010 and the PPP Norms; and
- Concessions of works and services governed by GEO 34/2006 and the relevant Norms for the implementation thereof. Concessions of assets that are
public property are governed by GEO 54/2006 and the Norms of implementation thereof.
It is worth mentioning that the legal texts currently in force are the result of several amendments.
Thus, the initial version of the PPP Act 178/2010 raised serious doubts as to its compliance with the European Union rules and principles, triggering the risk
of infringement procedures being started by the European Commission against Romania. Major amendments have therefore been brought to the PPP
legislation in order to render it compliant with the EU legal framework and to enable its implementation.
Although these amendments have better defined the scope of the regulation and have considerably detailed the award procedures, the current Romanian legal
framework still lacks a certain degree of clarity, in particular as regards the line between PPPs and Concessions, which makes it difficult to determine whether
a particular project will be governed by one or the other set of rules.
9.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Further difficulties might result from the fact that recent amendments to the PPP Act 178/2010 have included within its scope of application relevant activities
that also benefit from sector-specific regulations, among which gas, energy, water, post. The Law is not very clear as to when the general regulation on PPPs
and when the sector-specific regulations are applicable.
In any case, the current legal framework on PPPs is broad enough to allow the implementation of different types of Public-Private Partnerships,
such as Concessions, PFIs, BOTs and its respective forms, in both merchant sectors of the economy and in sectors related to the provision of
Government service.
The PPP Law provides criteria for identifying the entities having the capacity to act as Contracting Authorities, while both Romanian and foreign
investors may have the capacity to act as Private Parties under the PPP legal framework, without discrimination.
Selection procedures, governed by basic principles among which transparency, non-discrimination, equal treatment, proportionality are detailed
by the relevant regulations, providing for obligations of Contracting Authorities among which: publishing notices in respect of the award
procedure, applying the same criteria made public through the contract notice and the relevant documents to all the candidates/bidders, keeping a
record of the key stages and information regarding the award procedure.
PPP agreements may be awarded without a competitive procedure only in limited circumstances.
There is no standard Project Agreement to be complied with; the Law sets forth lists of clauses to be included in the Project Agreement but the
content thereof is to be determined in each case based on the requirements of the Contracting Authority and the offer submitted by the Private
Party.
The Law also provides for the right of the Private Party or the IPPP to collect tariffs or fees for the use of facilities or provision of services. Availability
payments are also allowed under the Romanian legislation.
Review procedures are provided by the Law granting private investors the possibility to challenge a decision or a failure to act by a Contracting Authority, as
well as to obtain appropriate compensation for the damages incurred. The Norms on Concessions expressly refer to the possibility of resorting to arbitration
for settling a dispute related to a Concession Agreement.
The Law includes very few indications as far as financial and security issues are concerned, it does not provide for step-in rights in favour of lenders or for
Government financial support or guarantee for PPP projects.
As regards the implementation of the legal framework, official statements of members of the Romanian Government have repeatedly emphasised the
importance of PPPs.
10.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Strategies involving the partnership between the public sector and the private sector have been enacted in several sectors among which energy, infrastructure
and municipal services. Furthermore, in April 2011, the Romanian Government has announced a list of 17 projects to be carried out on a PPP basis under the
PPP Act 178/2010 in sectors among which: infrastructure, energy, health, housing, prisons.
Entities acting as Central PPP Units have been set up with key functions of promoting PPPs and providing counsel and guidance to both Contracting
Authorities and private investors, especially the newly reorganized Central Unit for Coordinating Public Private Partnership.
However, as a general remark, the Romanian experience in implementing successful PPPs is very limited.
Thus, to this day, the Electronic Public Procurement System (SEAP) has published a number of 194 notices for the award of Concessions of
works and services, the vast majority thereof being awarded by local and county authorities in the field of municipal services. Nevertheless, in
absence of official statistics, it is difficult to assess how many of them have been implemented successfully.
No award procedure has been started yet under the PPP Act 178/2010.
Among possible obstacles, we could note: insufficient training of civil servants, insufficient awareness as regards the PPPs, lack of clarity of the legal
framework, no clear lenders' rights.
11.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
ASSESSMENT & LEGAL INDICATOR SURVEY
1. LEGAL FRAMEWORK
1.1 Existence of different forms of PPP legal framework
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the country have a single act dealing
specifically with Concessions or a generalised
act incorporating the legal framework for PPP,
including Concessions?
Romanian legal framework includes several pieces of
legislation regulating different types of long-term
arrangements between public authorities and private
entities.
Thus, Public-Private Partnerships established as IPPPs are
regulated by recently enacted pieces of legislation: the PPP
Act No. 178/2010 (the "PPP Act 178/2010") and the Norms
for the implementation thereof approved by Government
Decision No. 1239/2010 (the "PPP Norms").
The concept of Concessions under Romanian law is
regulated under two Government Emergency Ordinances
enacted in 2006 with the purpose of implementing the
relevant EU regulations, as follows:
12.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
- concessions of works and services are governed by
Chapter VII of Government Emergency Ordinance No. 34/2006 on the
award of public procurement contracts, of public works concession
contracts and services concession contracts (the "GEO 34/2006") and the
Norms for the implementation thereof approved by Government Decision
no. 71/2007 (the "Concession Norms");
- concessions of assets that are public property are
governed by Government Emergency Ordinance No. 54/2006 on the legal
regime of concession contracts for assets that are public property (the
"GEO 54/2006") and the Norms for the implementation thereof approved
by Government Decision No. 168/2007.
Furthermore, the Local Public Administration Act No.
215/2001 provides for the possibility for county/local
public authorities to associate with private partners, under
the terms and conditions provided by the law, for the
purposes of financing and carrying out activities, works,
services and projects of county/local interest. No further
details are provided regarding the procedure to be complied
with for selecting the Private Party.
As a general remark on the Romanian legal framework,
although recent amendments to the PPP Act 178/2010 and
the PPP Norms have provided further details as regards the
scope of these regulations and have clarified to a certain
extent the procedures to be complied with for the award of
a PPP contract, the line between the scope of the different
regulations is not very clearly drawn in all cases. A specific
project may qualify either as a PPP or as a Concession and
there are no clear guidelines on the choice among the set of
rules that should be complied with.
13.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2. Does the country have an act that allows BOT or
derived forms such as BOOT, BOO or other
forms either as part of a specific act or as part of
a general PPP Law?
Despite the absence of express references thereto in the
relevant pieces of legislation, BOTs and derived forms
thereof may be implemented within the framework of
Public-Private Partnerships.
3. Does the country have an act that allows PFI,
either as part of a specific act or as part of a
general PPP Law?
Despite the absence of express references thereto in the
relevant pieces of legislation, PFIs may be implemented
within the framework of Public-Private Partnerships.
4. If the answer is No to any of the three first
questions concerning a specific form of PPP
does the Constitution or other general act (ex:
the Civil Code, sectoral law) recognise the basic
principles of the concerned PPP and regulate its
granting?
N/A
For our general information: Is a new PPP Law or an amendment to the existing Law being prepared, or considered, in the country?
If so, at what stage of the legislative process is such new PPP Law or amendment to the existing Law?
14.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
We are not aware of any amendment to existing regulations being prepared or of any new regulation being proposed as regards PPPs in
Romania. Please note that important amendments have been brought to the PPP Act 178/2010 as of 17 October 2011, further to the
enactment of Government Emergency Ordinance No. 86/2011, and to the PPP Norms as of 20 October 2011, further to the enactment of
Government Decision No. 1000/2011.
1.2 Specificity and integration of PPP the legal framework
5. If the country has a Public Procurement Law, is
it clear to what extent does the Public
Procurement Law apply or not to the granting of
a PPP?
The Romanian Public Procurement Law is represented
by the chapters dedicated to the procurement of
goods/works/services included in GEO 34/2006
(implementing the European Directives 2004/17/EC
and 2004/18/EC) and the relevant norms for the
implementation thereof.
The Romanian Public Procurement Law includes
provisions indicating which texts of the Public
Procurement Law also apply to the granting of
Concessions.
6. If the country has sectoral laws regulating PPP
in specific sectors, is it clear which law is
applicable to the granting of PPP for each
particular sector?
In addition to the above-mentioned general texts, the
Romanian legal framework also includes numerous
sector-specific texts providing for the option of using
PPPs for carrying out a public service; some of these
regulations also provide for specific rules for the award
of the PPP.
Romanian law allows special norms derogating from
general norms. However, general principles should be
15.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
complied with and both the general and the specific
regulation should be clear enough as regards their
respective scopes in order to avoid the risk of
overlapping and confusion.
Among the sectors where specific pieces of legislation
provide for PPPs, we note the following:
oil: Oil Act No. 238/2004 and the Norms on the
implementation thereof approved by Government
Decision No. 2075/2004;
mining: Mining Act No. 85/2003 and the Norms on
the implementation thereof approved by
Government Decision No. 1208/2003;
electricity: Electricity Act No. 13/2007;
natural gas: Gas Act No. 351/2004;
municipal services: a framework regulation: the
Municipal Services Act No. 51/2006 and relevant
regulations for each category of municipal services
governed thereby:
- Act No. 325/2006 on the organisation and
functioning of the public services of thermal energy
supply;
- Act No. 101/2006 on sanitation services;
- Act No. 241/2006 on the organisation and
functioning of the public services of water supply
and sewage;
- Act No. 230/2006 on public lighting services;
- Act No. 92/2007 on local public transportation
services;
- Government Ordinance No. 71/2002 regarding the
16.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
organisation and operation of public services of
management of the local public and private domain.
The Law is not clear as to when the general regulation
and when the sector-specific regulations are applicable.
7. Does the country have a Law allowing the
Institutional form of PPP (IPPP) which
regulates IPPP participation to PPP?
PPP Norms
Art.1 (2)
Concession
Norms
Art 16
Under the PPP Act 178/2010 Public-Private
Partnerships may be implemented only by setting-up an
IPPP whose purpose is to carry out the Public-Private
Partnership Project.
The Contracting Authority and the Private Party may
set up an IPPP in view of carrying out a Concession.
17.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2. DEFINITIONS AND SCOPE OF THE PPP LAW(S)
2.1 PPP definition 3
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the Law define one or several term(s) (i.e.
"PPP", "Concession", "BOT", "Partnership"
etc. and/or respective agreements) for the
arrangements to be regulated by the Law which
specify the limits of application of the Law?
For our general information: please provide the given
definition(s), if any.
PPP Act
178/2010
Art. 4, d),
g), t), ţ), u)
Various types of arrangements are defined by the Law.
However, the limits of application of the Law cannot be
clearly determined.
A. Public Private- Partnership
A public-private project is the project that is fully or
partially completed with the financial resources of an
investor or with financial resources obtained by the
investor (i.e. the Private Party), based on a public-
private partnership model, from which a public asset or
service results;
A Public-Private Partnership agreement or project
3 PFI Guide, Consolidated Legislative Recommendations, Recommendation 3and Commission Interpretative Communication on Concessions Under Community Law dated
12 April 2000; together with additional EU major documents/decision /recommendation on concessions including Directives 2004/18/EC and 2004/17 EC of 31 March
2004; Green Paper on Public Private Partnerships and Community Law on Public Contracts and Concessions dated 30 April 2004; Report on the public consultation on the
Green Paper (SEC(2005) 629- Communication from the Commission to the European Parliament, the Council, the European Economic and Social Committee and the
Committee of the Regions on Public-Private Partnerships and Community Law on Public Procurement and Concessions (Brussels, 15.11.2005. COM(2005) 569)
European Parliament resolution on public-private partnerships and Community law on public procurement and concessions (2006/2043(INI))
18.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
agreement is the legal document that stipulates the
rights and obligations of the public partner (i.e. the
Contracting Authority) and of the private partner (i.e.
the Private Party), throughout the entire duration of the
Public-Private Partnership, covering one or several
stages of the Public-Private Partnership project, for a
definite term;
PPP Act 178/2010 also defines each type of Public-
Private Partnership agreement, as follows:
- PPP works agreements are partnership agreements
concerning either: (i) only the performance or the design and the
performance of works related to one of the activities listed in
Appendix 1 of GEO 34/2006 or (ii) the carrying out, through any
means, of works meeting the requirements indicated by the
Contracting Authority in the contract notice or in the accompanying
document thereof. "Works" are defined as the result of construction
works or public works, meant to fulfil itself an economic or technical
function.
- PPP goods agreements are partnership agreements,
other than PPP works agreements (as defined above) concerning the
supply of goods corresponding to the necessities specified by the
Contracting Authority in the contract notice and in the accompanying
document thereof. A PPP agreement concerning the supply of goods
and that, in addition, covers the installation works, is considered to be
a PPP goods agreement.
- PPP services agreements are partnership
agreements, other than PPP works agreements and PPP goods
agreements (as defined above) concerning the provision of services
listed in Appendix 2 of GEO 34/2006. A PPP agreement concerning
19.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
34/2006
Art. 3, g), h)
Concession
Norms
Art. 3
both goods and services listed in Appendix 2 of GEO 34/2006 will
qualify as a PPP services agreement inasmuch as the value of the
services concerned exceeds the value of the goods. A PPP agreement
concerning services listed in Appendix 2 of GEO 34/2006 and, only
incidentally, activities listed in Appendix 1 to GEO 34/2006 will be
qualified as a PPP services agreement depending of the main object
thereof.
B. Concessions
The Law does not include a definition of Concession, as
such, but it defines concession agreements.
Agreements for concession of public works and services
are defined by reference to public works or services
agreements. Thus, Concession agreements have the
same characteristics as the corresponding public
procurement agreements, the difference consisting in
the fact that, as regards concession agreements, the
consideration for works performed or services rendered
by the concessionaire consists either solely of the right
to operate the construction/services (thus the Private
Party undertaking the most important part of the risks
related to the performance and operation thereof), or in
that right together with payment of a predetermined
amount by the Contracting Authority.
Under GEO 54/2006, a Concession agreement is the
agreement concluded in written form whereby a
Contracting Authority, acting as conceding authority,
transfers, for a limited period of time, to a Private Party,
20.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
54/2006
Art 1 (2)
acting as concessionaire, acting on its own risk and
responsibility, the right and obligation to operate a
public property asset in return for the payment of a
royalty.
2. Does the Law apply to all contracts entered into
that fall under the definition(s) given above,
irrespective of the name given to such contract
(concession, license, usufruct right, lease, etc.)?
PPP Act
178/2010
Art. 10-12
GEO
34/2006
Art. 220
Yes, subject to the exceptions explicitly provided in the
relevant regulations, where they are not applicable.
3. Does the Law make a clear distinction between
a PPP agreement (such as a Concession) and a
license (i.e. an authorisation to operate by a
public authority)?
The Law does not include express provisions in this
respect. Nevertheless, a distinction between the
authorisation to operate granted by a relevant regulatory
authority by issuing a licence and the authorisation to
perform a public service granted by a Contracting
Authority by entering into a PPP agreement can be
inferred further to the analysis of the legal provisions in
force. In any case, both are required for a Private Party
to duly perform a public service within the framework
of a PPP in a regulated sector.
21.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2.2 Contracting Authority
QUESTION
ANSWER
ARTICLE
COMMENTARY
4. Does the Law identify (or allow clear
identification by reference to other laws or
regulations) the public authorities ("Contracting
Authorities") that are empowered to select
projects, prepare for, and award PPPs and enter
into Project Agreements ?
PPP Act
178/2010
Art. 4, j),
Art. 7, Art.
8
GEO
34/2006
Art. 8
The following entities may act as Contracting
Authorities to implement Public- Private Partnerships,
either as PPPs under PPP Act 178/2010 or as
Concessions:
any State body, public authority or institution,
acting at a central, regional or local level;
any body, other than those indicated above,
having legal personality, which was set-up in
view of satisfying general interest needs without
a commercial or industrial nature and that is
financed mostly by a public entity (i.e.: a State
body, public authority or institution, acting at a
central, regional or local level) or by a body
governed by the public law;
any body, other than those indicated above,
having legal personality, which was set-up in
view of satisfying general interest needs without
a commercial or industrial nature and that is
either subordinated to or subject to the control
(for Concessions) or subject to supervision or
management (for PPPs) of a public entity (i.e.: a
State body, public authority or institution, acting
at a central, regional or local level) or another
22.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
body governed by public law;
any body, other than those indicated above,
having legal personality, which was set-up in
view of satisfying general interest needs without
a commercial or industrial nature and whose
board of directors/management or supervisory
body comprises more than half of its members,
appointed by a public entity (i.e.: a State body,
public authority or institution, acting at a
central, regional or local level) or by another
body governed by public law;
any association formed of entities falling under
the scope of the above mentioned categories.
In addition to the above, the following entities may
equally act as Contracting Authorities under the PPP
Act 178/2010:
- any association formed of one or more entities
qualifying as Contracting Authorities as defined
above, on the one hand, and authorities, public
institutions and public companies of Member
States of the European Union, irrespective of
their activity, on the other hand;
- any public company operating one of the
activities mentioned under Art. 52-5
6 of PPP
Act 178/2010 (i.e.: relevant activities), on
which an entity qualifying as Contracting
Authority as defined above has, either directly
23.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
or indirectly, a dominant influence, as a result
of a property right, a financial participation or
of norms governing it. The dominant influence
is presumed when the entity qualifying as a
Contracting Authority as defined above, either
directly or indirectly:
- owns the majority of the company's
subscribed share capital; or
- controls the majority of the votes
associated to shares issued by the
company; or
- can nominate more than half of the
members of the
administrative/management/supervisory
body.
- any legal entities that do not qualify as
Contracting Authorities as defined above, as
defined above, but carry out, as one of their
activities, one or several activity(s) defined under
Art. 52-5
6 of PPP Act 178/2010 (i.e.: relevant
activities) or any combination thereof and benefit
from special or exclusive rights granted by a
relevant authority; special or exclusive rights are
defined as rights granted by a relevant authority
of a Member State by means of a
legal/regulatory/administrative provision having
as effect the limitation of the carrying out of
activities defined under Art. 52-5
6 of PPP Act
178/2010 (i.e.: relevant activities) to one or
several entities and which affect in a substantial
manner the capacity of other entities to perform
24.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
54/2006
Art. 5
such activity.
Under GEO 54/2006, the following entities may act as
Contracting Authority, on behalf of the State, the
county or the municipality: (i) Ministries or other
specialised bodies of the central public administration
for assets that are public property of the State; and (ii)
county councils, local councils, public institutions of
local interest for assets that are public property of the
county or the municipality.
For our general information: If yes, which of the following authorities are identified:
National authorities (e.g.: the government, ministries, and independent agencies);
Regional/state-level authorities;
Local or municipal authorities; or State owned companies?
Public authorities at all levels (State level, county level, municipality level) may act as Contracting Authorities under Romanian law. Further,
State owned companies may equally qualify as Contracting Authorities, inasmuch as they fall under one of the categories indicated above.
25.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2.3 Private Party and Project Company
QUESTION
ANSWER
ARTICLE
COMMENTARY
5. Is it possible for a PPP be awarded to a foreign
company, a Private Party or to a domestic
company with foreign participation in the share
capital and/or management (without
discrimination)?
PPP Law
178/2011
Art. 31, 3² 4,
e)
Concession
Norms
Art. 6(2)
GEO
54/2006
Art. 6
PPPs may be awarded to foreign companies, or to
domestic companies with foreign participation in the
share capital and/or management thereof.
The Law does not include restrictions in this respect.
On the contrary, non-discrimination of private
investors, regardless of their nationality or citizenship,
is one of the basic principles of the award of PPPs and
the Law expressly provides that both Romanian and
foreign legal persons or associations may act as a
Private Party.
For our general information: can a PPP be awarded to public entities or to entities jointly owned by private and public entities (IPPP)?
Are there restrictions imposed on such contracts?
According to the Law, in principle, PPPs may be awarded to both public entities and IPPPs formed of a private partner and a public partner.
26.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
2.4 Concerned sectors4
QUESTION
ANSWER
ARTICLE
COMMENTARY
6. Does the Law identify (or allow identification
by reference to other laws or regulations) the
sectors and/or types of infrastructure and/or
services in respect of which a PPP may or may
not be granted?
PPP Act
178/2010
Art. 2, 41
5²
-56
GEO
34/2006
Appendix 1,
2A and 2B
Under Romanian law PPPs may be granted in a large
number of sectors.
The sectors where PPPs may be granted are defined by
reference to the lists of works and services included in
Appendix 1, 2A and 2B to GEO 34/2006 implementing
the EU Directives on public procurement.
7. Do the list of sectors eligible for PPP
correspond to an open-ended one (as opposed to
being exhaustive) allowing (or at least not
preventing) PPP to be granted in numerous
sectors”?
It can be argued that a wide variety of sectors may be
eligible for PPPs.
4 For further information on the concerned sectors please refer to:PFI Guide, Consolidated Legislative Recommendations, Recommendation 3 and 4.
27.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
8. Do the sectors eligible for PPP includes non
commercial activities such as the provision of
government services (such as schools, hospitals,
prisons, defence and housing) in addition to the
merchant sectors of the economy (energy,
transport, water, oil and gas).
The sectors where PPPs may be carried out includes
both non commercial sectors and merchant sectors of
the economy.
Moreover, education, health and social services are
expressly listed in Appendix 2B of GEO 34/2006.
For our general information: Please indicate the restrictions if any imposed by the Law on the sectors eligible for PPP:
The Law does not impose specific restrictions, but provides that it does not apply to the following:
- agreements concerning the acquisition or lease of land, buildings, other immovable assets or rights thereon;
- agreements concerning the acquisition, development, production or coproduction of programs to be broadcasted by
radio or television;
- agreements concerning arbitration and conciliation services;
- agreements concerning financial services related to the issuance, the acquisition, the selling, the transfer of securities
or other financial instruments or to the provision by the National Bank of Romania of services specific to a central
bank;
- employment agreements;
- agreements concerning the provision of research-development services, other than those exclusively for the benefit of
a Contracting Authority, provided that the service rendered is fully paid by the Contracting Authority;
- agreements in the fields of defence and security governed by Directive 2009/81/EC;
- agreements further to the execution of which the Contracting Authority may make available or operate public
telecommunication networks or may provide the public with one or several telecommunication services;
- agreements that have been declared secret by the relevant authorities;
- where the protection of essential State interests requires it;
- where the performance of the agreement requires imposing special safety and national security measures;
- agreements executed further to an international convention concerning the stationing of troops and only if a specific
procedure was mentioned in such international convention;
- agreements executed further to an international convention entered into according to the provisions of the EU Treaty
with one or several States that are not members of the EU concerning the provision of goods or performance of works
28.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
in view of implementing or operating a joint project and only if a specific procedure was mentioned in such
international convention;
- agreements awarded further to a specific procedure of an international organisation.
29.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3. SELECTION OF THE PRIVATE PARTY5
3.1 General Considerations
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the Law require, in principle, the
Contracting Authority to select Private Parties
through a competitive tender process?
PPP Act
178/2010
Art. 4
letters r)
and s)
Art. 14 (1)
letter b)
Art. 18(1)
GEO
34/2006
Art. 2181
Concession
Norms
Art.26
The Law provides for competitive tender procedures for
the award of PPPs.
Under the PPP Act 178/2010, in principle, a
Contracting Authority is entitled to use either an open
procedure or a competitive dialogue procedure for the
purposes of selecting the Private Party.
Concessions of public works and services may be
awarded by a Contracting Authority by using one of the
following award procedures: open tender, restricted
tender or competitive dialogue.
As a general rule, Concession over an asset that is
public property is to be granted further to a tender
procedure.
5 For further information on the selection of the Private Party, please refer to:PFI Guide, Consolidated Legislative Recommendations, Recommendations 14 to 39 included.
30.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
54/2006
Art. 14
2. Is there reference in the Law to the principles of
transparency, equal treatment and
proportionality?
PPP Act
178/2010
Art. 3
GEO
34/2006
Art. 217,
Art. 2 (2)
GEO
54/2006
Art. 13
Yes, non-discrimination, equal treatment, transparency
and proportionality are expressly indicated in the Law
as the basic principles that must be complied with for
the award of PPPs.
3. Is there a provision in the Law concerning the
publication of information related to the
competitive procedures in the country media
and in the international media (for large
projects)?
In view of ensuring the transparency of the award
procedures, the Law provides for the obligation of
Contracting Authorities to publish notices regarding the
competitive procedures for the award of PPP, and
indicates the information to be included in such notices.
Such notices must be published in the Electronic
System of Public Procurement (SEAP), which is a
public utility electronic system available online and,
where certain thresholds are met, in the Official Journal
of the European Union, as well.
For PPPs governed by the PPP Act 178/2010, SEAP
31.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
34/2006
Art. 21, Art.
222, 223
Concession
Norms Art.
19-25
PPP Act
178/2010
Art. 24
PPP Norms
Art. 40, 41
should provide Contracting Authorities with a new
specialized information flow. Such new specialized
information flow has not yet been implemented and we
are not aware of the progress of such implementation.
If the value of the PPP project exceeds the thresholds
below, the contract notice should be published in the
Official Journal of the European Union, as well.
Contract notices regarding Concessions of works of a
Type of
contract
Thresholds6
(VAT excluded)
Publication
Goods
and
services
≤ 125.000 Euro SEAP
> 125.000 Euro SEAP and
OJEU
Works ≤ 4.845.000 Euro SEAP
> 4.845.000 Euro SEAP and
OJEU
6 Equivalent in RON;
32.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
GEO
54/2006
Art. 21
value exceeding the equivalent in RON of EUR
4,845,000 must also be published in the Official Journal
of the European Union.
Finally, GEO 54/2006 provides that contract notices
must be published in the Official Gazette, in a national
newspaper and in a local newspaper.
4. Are there provisions within the Law or any
special manual or recommendations governing
in detail the selection of the Private Party (i.e.:
the pre-selection of bidders, the procedure for
requesting proposals or other procedure such
as competitive dialogue/two stage procedure)?
The Law regulates in detail the selection of the Private
Party.
5. Does the Law provide that if the Contracting
Authority rejects an applicant at the time of pre-
selection or disqualifies a bidder, it must make
public the reasons for the decision (or inform
the rejected bidder thereof explaining the
reasons for rejection)?
PPP Act
178/2010
Art. 18 (2)
letter k), (7)
letter r)
GEO
34/2006
Art. 207 (2),
(a), (b)
Concession
Norms
Art. 46
GEO
54/2006
Art. 41
The Contracting Authority is under a legal obligation to
send a letter indicating the reasons of its decision to
disqualified bidders / rejected applicants.
33.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3.2 Award of PPP
QUESTION
ANSWER
ARTICLE
COMMENTARY
6. Does the Law provide that all proposals are
ranked solely on the basis of a predefined
evaluation criteria set forth in the pre-selection
documents/ request for proposals?
PPP Act
178/2010
Art. 3 letter
(b), 4 letter
(m)
GD
71/2007,
Art. 17, 18
GEO
54/2006
Art. 37
Proposals submitted by all the candidates/bidders must
be assessed by using the same criteria set out in the pre-
selection documents/request for proposals.
7. Does the Law provide for the publication of a
notice of the award of the project, identifying
the Private Party and including a summary of
the essential terms of the project agreement?
PPP Act
178/2010
Art. 18(2)
(k1), 18(7)
(r1), 24(2),
(3)
PPP Norms
Art. 54 28
(8)
The Law provides for the obligation of Contracting
Authorities to publish notices of award of a PPP project
and indicates the information to be included in such
notices.
Such notices must include information on the selected
Private Party and basic information on the PPP
agreement, including the value thereof and a brief
description of the works/services/products subject of
34.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Concession
Norms
Art. 56
the agreement, and where applicable, the royalty to be
received by the Contracting Authority or the financial
contribution to be paid by the Contracting Authority.
8. Does the Law provide that the Contracting
Authority or any other public authority maintain
records of key information pertaining to the
selection and award proceedings?
PPP Act
178/2010
Art. 204
GEO
34/2006
Art. 213,
214
GEO
54/2006
Art. 60
The PPP Act 178/2010 provides for the obligation of
Contracting Authorities to prepare, for each PPP
agreement awarded, a Minutes including the following
information: name and address of the Contracting
Authority, object and value of the PPP contract; names
of the private investors selected and the reasons for the
decision; names of the private investors rejected and
reasons for the decision, reasons for the rejection of
offers considered abnormally low; name of the winning
party and reasons for the selection of its offer, as well
as (if applicable) the part of the contract to be
subcontracted to third parties; for competitive dialogue
procedures, circumstances justifying the choice of the
procedure in question; and, if applicable, the reasons
for which the Contracting Authority has decided not to
award the PPP.
As regards the award of Concessions, Contracting
Authorities are under an obligation to prepare, for each
award procedure, the file of the award procedure
including information and documents among which: the
contract notice, the request for proposals, the requests
for clarifications and clarifications issued by the
Contracting Authority, the report of the award
procedure (including essential terms such as: name and
35.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
address of the Contracting Authority, object of the
Project Agreement, name of the candidate(s)/bidder(s)-
selected and rejected, as well as reasons for the
decision, name(s) of the winning bidders, the part of the
contract to be subcontracted, as well as the name(s) of
the subcontractor(s)), the signed version of the Project
Agreement etc.
GEO 54/2006 also provides for the obligation of a
Contracting Authority to set up a file of the award
procedure including: the notices published, the
decisions approving the concession, the request for
proposals, information on the concessionaire, the
signed version of the Project Agreement.
9. If the answer to the previous question is Yes,
does the Law provide that such record is
accessible to the public, or at least to interested
parties?
GEO
34/2006
Art.215
GEO
54/2006
Art. 63
The Public Procurement Law and GEO 54/2006
expressly provide that the procurement file is a public
document and it should be accessible to the public
under the conditions provided for under the specific
regulations on the free access to public interest
information.
GEO 34/2006 does not include express provisions as
regards Concessions.
The PPP Act 178/2010 does not include provisions on
public access to the Minutes to be prepared by the
Contracting Authority.
36.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3.3 Final negotiations
QUESTION
ANSWER
ARTICLE
COMMENTARY
10. Does the Law contain provisions regulating
final negotiations (i.e. post contract award) so
that transparency, equal treatment and
competition are preserved?
11. Does the Law provide that the Contracting
Authority has the authority to terminate
negotiations with the invited bidder if it
becomes apparent that the bid will not result in
an agreement and start negotiations with the
second ranked candidate?
PPP Act
178/2010
Art. 18 (17)
Such authority of the Contracting Authority is provided
by the PPP Act 178/2010 only for the cases where the
Private Party is selected through a competitive dialogue
procedure.
In such cases, if negotiations with the bidder who
ranked first cannot lead to the execution of the Project
Agreement, the Contracting Authority will start
negotiating with the private investors ranked on the
following positions until a favourable result is obtained.
37.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3.4 PPP Award without competitive procedure
QUESTION
ANSWER
ARTICLE
COMMENTARY
12. Does the Law provide that the Contracting
Authority has the authority to award a PPP
without a competitive process? Is this only in
limited/ exceptional circumstances?
PPP Act
178/2010
Art. 18 (24)
GEO 34/2006
Art. 2181
Concession
Norms
Art. 27
GEO 54/2006
Art. 26-31, 59
The Law provides for limited circumstances where a
Contracting Authority is entitled to award a PPP
without a competitive process.
Under the PPP Act 178/2010, a Contracting Authority
is entitled to resort to a negotiation procedure without
prior publication of a notice in exceptional
circumstances where the conditions below are met:
- additional works or services not indicated in
the initially estimated project or in the initial
PPP agreement have become necessary for the
carrying out of works or services further to
unforeseen circumstances;
- the agreement is awarded to the Private Party
that has been awarded the initial agreement;
- the additional works/services cannot be
separated from a technical or economic point
of view from the initial agreement without
causing a major inconvenient for the
Contracting Authority or, even if they could
be separated, the additional works/services are
strictly necessary for the completion of the
PPP project;
- the aggregate value of agreements awarded
38.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
for additional works/services must not exceed
50% of the value of the initial agreement.
As regards Concessions, a Contracting Authority is
entitled to use the award procedure of negotiation
with prior publication of a notice in one of the
following circumstances:
- if, further to using either open or restricted
tender or competitive dialogue, no offers are
submitted or all the offers submitted are
noncompliant;
- in exceptional circumstances, well-grounded,
where the nature of the works or services or
the risks involved in the performance thereof
do not allow an initial estimation of the
aggregate price of the agreement to be entered
into;
- if the services (such as financial services or
design of works) are such as not to allow the
terms of reference to be drafted with the
accuracy required for the award of a contract
by tender;
- if the works to be carried out are necessary
exclusively for purposes of scientific research,
experiments or technological development
and only if they are not carried out in view of
obtaining a profit and do not purport to cover
related costs.
GEO 54/2006 provides that a Concession may be
awarded further to direct negotiations in the following
39.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
circumstances: if three valid offers have not been
submitted, the Contracting Authority must launch a
new tender. If the minimum number of valid offers
has not been submitted at the second call for tender,
the Contracting Authority can proceed with direct
negotiations, which means that the Contracting
Authority negotiates the clauses of the agreement,
including the royalty payment, with one or more of
the participants in the procedure for the award of the
concession agreement.
Another specific exception is provided under GEO
54/2006: assets that are public property may be
granted in Concession directly, to national companies
or companies subordinated to, under the authority or
the coordination, of a Contracting Authority under
GEO 54/2006, that have been set-up further to
reorganisation of public companies (regii autonome)
having as main purpose of business the management,
maintenance, repair and development of such assets,
until the completion of privatisation of such
companies.
13. Does the Law provide for a procedure, set of
rules or principles to be respected when
awarding a PPP without a competitive process?
GEO 34/2006
Art. 111-121
PPP Act 178/2010 does not provide for any set of
rules or principles to be complied with by a
Contracting Authority, when resorting to negotiation
without prior publication of notice.
Regulations on Concessions provide for rules to be
complied with, among which: obligation to publish a
40.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
For our general information, please specify the conditions which would allow such direct negotiations?
The circumstances allowing such direct negotiations are indicated in our answer to Question 12 above.
3.5 Special case of unsolicited proposals
QUESTION
ANSWER
ARTICLE
COMMENTARY
14. Does the Law provide for an adequate
framework for the Contracting Authority to
manage unsolicited proposals/private initiatives
(i.e. a proposal relating to the implementation of
a PPP that is not submitted in response to a
request or solicitation by the Contracting
Authority) that ensures transparency and equal
treatment and does not distort competition?
GEO
54/2006
Art. 9
Certain rules are provided only in GEO 54/2006.
GEO 54/2006 provides that the award procedure in
view of granting a Concession may be started further to
the Contracting Authority accepting a proposal of an
interested party regarding the concession of an asset
that is public property. Such proposal must be well-
grounded from an economic, financial, social and
environmental standpoint must include the coordinates
of the interested investor, the firm and serious
indication of the intention of concession, the object of
concession, the business plan. GEO 54/2006 provides
that, within 30 days as of accepting an unsolicited
proposal, the Contracting Authority must prepare the
opportunity study in view of launching the award
procedure.
notice, obligation to assess offers based on the
evaluation criteria established by the Contracting
Authority.
41.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3.6 Review procedures
QUESTION
ANSWER
ARTICLE
COMMENTARY
15. Does the Law allow the bidders who claim to
have suffered, or that may suffer loss or injury,
to seek review of the Contracting Authority’s
actions or failure to act?
PPP Act
178/2010
Art. 28(1)
GEO
34/2006
Art.255(1)
GEO
54/2006
Art. 66
The Law provides for review procedures in respect of the
Contracting Authority’s actions or failure to act.
4. PROJECT AGREEMENT7
4.1 Model or list of provisions
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the Law give flexibility to the negotiation
of most terms of the Project agreement and if it
Romanian Law on PPPs provides for lists of mandatory
material provisions which must be included in the PPP
7 For further information on the project agreement definition, please refer to:PFI Guide, Consolidated Legislative Recommendations, Recommendations 12 and 40 to 68
included.
42.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
contain (or refer to): (i) a model PPP agreement
it is an optional template agreement for
guidance only or (ii) a list of mandatory
material provisions which must be included in
the agreement, the content of such provisions is
left for negotiation)?
agreement; the content of such provisions is left for
negotiation.
The implementation Norms of GEO 54/2006 include a
template agreement for Concession of assets that are
public property, which is a model agreement, for
guidance only.
4.2 Duration and extension of the Project Agreement
QUESTION
ANSWER
ARTICLE
COMMENTARY
2. Does the Law provide that the duration of the
Project Agreement should depend on the length
of time taken for the amortisation of the Private
Party's investment and an appropriate return on
the capital?
PPP Act
Art.4 letter
(q)
Concession
Norms
Art. 7
GEO
54/2006
Art. 7
The PPP Act defines the fixed term of a Public Private
Partnership agreement as a negotiated timeframe
ensuring the recovery of the financing by the Private
Party, without indicating the return on capital as a
criterion for determining such duration.
The Concession Norms provide detailed information
regarding the criteria to be used for determining the
duration of a Concession Agreement. Such duration
must be determined so as to: avoid the artificial
restriction of access to competition, ensure a minimum
profit further to operation within a given timeframe;
ensure a reasonable level of prices for the services to be
43.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
provided throughout the duration of the agreement.
For concessions of assets that are public property, the
duration of the agreement is of maximum 49 years.
3. Does the Law provide that the renewal or
extension of the Project Agreement should be
limited and depend on exceptional
circumstances (such as Contracting Authority
default or an event of force majeure)?
GEO
54/2006
Art. 7
Romanian Law does not include provisions regarding
the renewal or extension of the duration of the Project
Agreement, except for concessions of assets that are
public property. In such cases, the duration of the
concession agreement may be extended by agreement
of the parties for a duration that may not exceed half of
the initial term of the agreement.
For our general information, please provide the given minimum and maximum duration (if any)
Romanian Law provides for a maximum duration of 49 years in case of concessions of assets that are public property.
4.3 Termination of the Project Agreement
QUESTION
ANSWER
ARTICLE
COMMENTARY
4. Does the Law leave open to the Project
Agreement negotiations the list of possible
ground for termination and the content of the
termination provision?
PPP Act
178/2010
Art. 25
letter (c)
Concession
Norms
Art.54
GEO
54/2006
It results from the PPP Act 178/2010 that, for PPPs
governed by this legal text, the parties thereto are free
to negotiate the list of possible grounds for termination
and the content of the termination provisions. Thus, the
PPP Act 178/2010 provides that, besides the expiry of
its term, a PPP agreement may be terminated by mutual
agreement of the parties and in other cases provided by
law or the PPP agreement.
44.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Art. 57(1) Romanian Law on Concessions provides for restrictive
lists of termination grounds. Besides the expiry of the
term of the agreement, such grounds of termination
include:
- termination by the Contracting Authority in case
of serious failure of the concessionaire in
fulfilling its contractual obligations,
- termination by the concessionaire for serious
failure of the Contracting Authority in carrying
out its contractual obligations;
- termination by the Contracting Authority for
reasons of national or local interest;
- termination by either party for reasons of force
majeure or act of God.
5. If the answer to the previous question is No does
the Law provide for a list of grounds of
termination which does not affect the balance
between the parties rights and obligations (one
sided provisions) or the stability of the
contractual relation under the Project
Agreement (e.g.: too large or non exhaustive
list)?
As indicated above, the Law provides for exhaustive
lists of grounds of termination as regards Concessions;
the grounds of termination included in such lists are not
such as to lead to the conclusion that they would affect
the balance between the parties rights and obligations.
6. Does the Law provide for (or at least does not
prevent) compensation of the Private Party for
losses incurred as a result for termination on the
grounds of public interest for losses incurred as
a result of public authority acts?
Concession
Norms
Art. 54
GEO
54/2006
Romanian Law on Concessions expressly provides that
the Private Party is entitled to compensation for losses
incurred as a result of termination on the grounds of
public interest.
45.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Art. 57
7. Does the Law provide for (or at least does not
prevent) compensation of the Private Party for
all cases of early termination (including in case
of serious breach or failure by the Private
Party), for fair value after depreciation of the
assets financed by the Private Party?
The Law does not provide for compensation of the
Private Party for fair value after depreciation of the
assets financed by the Private Party regardless of the
grounds for termination.
Furthermore, where the agreement is terminated for
failure by the Private Party, the Law prevents the
Private Party from recovering the value of assets
financed
4.4 Tariff setting, service standards
QUESTION
ANSWER
ARTICLE
COMMENTARY
8. Does the Law provide clear guidance on all
aspects of interaction between the bodies that
have the power to award PPP and the bodies
that regulate tariffs and service standards?
The Law does not provide clear guidance on the
interaction between the bodies awarding PPPs and the
bodies regulating tariffs and service standards
46.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
4.5 Financial responsibilities of the Private Party and Contracting Authority
QUESTION
ANSWER
ARTICLE
COMMENTARY
9. Does the Law provide that the Private Party can
collect tariffs or fees for the use of the facility or
its services?
PPP Norms
Art.93(3)
Concession
Norms
Art. 48
The PPP Norms explicitly provide that the IPPP is
allowed, through the Project Agreement, to collect
tariffs for the use by third parties of the public asset for
a defined period of time, the Private Party being thus
able to recover the investment, to finance the
maintenance and obtain profit.
The Concession Norms also include express provisions
to the effect that a Private Party is entitled to use and to
collect the fruits of the asset subject to Concession
according to the nature of the asset and the purpose
indicated by the parties in the Concession agreement; a
concessionaire is thus entitled to collect tariffs or fees
for the use by third parties of the asset or services.
10. Does the Law provide for the possibility of
fixed and/or consumption-based payments to the
Private Party by the Granting Authority or other
public authorities (in the case of Power
Purchase Agreement , shadow tool or PFI for
instance) ?
Concession
Norms
Art. 49
As regards Concessions of public works and services,
such possibility results from the provisions of Article
49 of the Concession Norms.
Neither PPP Act 178/2010, nor the PPP Norms include
provisions in this respect.
47.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
5. SECURITY AND SUPPORT ISSUES8
5.1 Security Interests
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the Law provide for (or does not
specifically prevent) a Private Party to create
security interests over the project assets, rights
and proceeds or other valuable guarantees
related to the project?
PPP Act
178/2010
Art.30(2)
The PPP Act 178/2010 specifically provides that, with
the exception of assets and land used for the project that
are public property, the assets resulting from the
implementation of the PPP project and the land may be
subject to mortgage or pledge in favour of the parties
having provided financing for the project.
Romanian Laws on Concessions do not prevent the
concessionaire to create such security interests,
provided however that such security interests may not
be created on assets that are public property.
2. If the answer to the previous question is Yes,
does the Law clearly state which types of
security can be provided and include some of
the most common type of guarantees in project
financing (such as those listed in the request for
general information below)?
Please see above.
8 For further information on support and financial securities, please refer to:PFI Guide, Consolidated Legislative Recommendations, Recommendations 13, 49, 57 and 60.
48.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
For our general information, please can you confirm whether a Private Party may pledge or assign by way of security:
the proceeds and receivables arising out of the PPP;
Yes.
the assets for which it has rights of use under a project agreement;
Yes, except for assets that are public property
its property;
Yes.
shares of the Project Company;
Yes.
the project agreement; or
No.
obtain other valuable guarantees (please specify)?
5.2 Government support
QUESTION
ANSWER
ARTICLE
COMMENTARY
3. Does the Law provide for (or does not
specifically prevent) the public authority to
provide support to the Contracting Authority
and a guarantee for the proper implementation
49.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
of the PPP by the Contracting Authority?
4. Does the Law provide for (or does not
specifically prevent) the Public Authority to
provide financial or economic support for the
implementation of PPP?
5. If the answer to the previous question is Yes,
does the Law clearly state which public
authorities may provide such support and which
types of support can be provided? (i.e. tax and
customs benefits; foreign exchange protection
(convertibility and transfer guarantees;
subsidies; equity or loan participation)?
N/A
5.3 Lenders’ rights
QUESTION
ANSWER
ARTICLE
COMMENTARY
6. Does the Law provide for the Parties to arrange
the financing with reasonable flexibility under
the Project Agreement without strict time
constraints or other constraints (except with
respect to security package and government
support)?
Romanian Law does not include specific provisions in
this respect.
50.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
7. Does the Law provide, in the event of the
default of the Private Party for the lenders to
“step-in” or substitute the Private Party with a
qualified new Private Party without initiating a
new tender process?
6. SETTLEMENT OF DISPUTES AND APPLICABLE LAWS9
6.1 Settlement of disputes
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Does the Law permit the Contracting Authority
to enter into a Project Agreement that is subject
to international arbitration?
Concession
Norms
Art. 55
2. Has the government of the country ratified the
Washington Convention on the Settlement of
Investment Disputes (ICSID) (1965)?
Yes, Romania has ratified the Washington Convention
on the Settlement of Investment Disputes through
Decree No. 62/1975.
9 For further information on the settlement of disputes, please refer to: PFI Guide, Consolidated legislative Recommendations, Recommendations 57, 69 and 71.
51.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3. Has the government of the country ratified the
New York Convention on recognition and
enforcement of foreign arbitral awards (1958)?
Yes, Romania has ratified the New York Convention on
recognition and enforcement of foreign arbitral awards
through Decree No. 186/1961.
6.2 Applicable laws
QUESTION
ANSWER
ARTICLE
COMMENTARY
4. Does the Law permit (or does not prevent) the
Contracting Authority) to enter into side
agreements to the Project Agreement (such as a
direct agreement with the lenders to the project
or a support and guarantee agreement in
respect of the Project Agreement) that is
governed by foreign law.
There is no provision under the Law expressly
preventing the Contracting Authority from entering into
side agreements to the Project Agreement governed by
foreign law.
5. Has the country ratified any international
convention for the protection of foreign
investments?
Yes, Romania has ratified numerous conventions for
the mutual development and protection of investments.
52.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
II- EFECTIVENESS ASSESSMENT: HOW THE LAW WORKS IN PRACTICE:
(Please comment based on the previous 2006 effectiveness general assessment)
7. POLICY FRAMEWORK
7.1 Existence of PPP Policy Framework
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Is there a general/national policy framework
(explicit or implicit) for PPPs for infrastructure
or public services?
Romanian Constitution states that public assets may be
operated by the private sector under Concessions.
Although there is no official document setting forth a
national policy framework or strategy on PPPs in
general, we note the existence of such strategies for
several sectors, among which, infrastructure, municipal
services and energy.
2. Is there any administrative guidance or printed
information edited by the government or the
PPP Unit concerning the legal framework for
PPP projects in the country?
No such guidance or information has been yet
published as regards PPPs under the PPP Act 178/2010.
However, a Guide for the implementation of works and
services concessions in Romania, approved by Order of
the Ministry of Public Finance and the relevant
regulatory authority (ANRMAP) in 2009 provides
guidance on the award of Concessions.
53.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
3. Is there a municipal/regional policy framework
(explicit or implicit) for PPPs in infrastructure
or public services?
There are various projects related to the development of
certain regions. We note the existence of infrastructure
development programs for small and medium size cities
in Romania, as well as road refurbishment and water
supply programs, integrated waste management at a
county level.
7.2 PPP Awareness and Sustainability
4. Is there a national and/or municipal /regional
long term programme for PPP promotion and
awareness?
No national/municipal/regional long term program to
promote or present PPPs has been developed so far.
Awareness/promotion of PPPs is limited, being carried
out only through the media informing the public of the
enactment or amendments of PPP laws and of PPP
projects or within the framework of debates organized
in specialized business environment.
5. Are there PPP training programmes on a
national and/or municipal/regional level for
public servants and other PPP concerned
people?
To our knowledge, no action has been taken so far in
organizing any special training programs on PPPs under
PPP Act 178/2010 and a limited number of training
courses and conferences have been organised on
Concessions.
6. Are there PPP courses as part of university
curriculum or specialist departments and
faculties in universities teaching PPP?
To our knowledge, PPPs are not the subject-matter of
specialized courses or specialist departments and
faculties in universities. Administrative law courses
taught at the Faculty of Law include very few
references to Concessions.
54.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
7.3 Obstacle to implementation of PPP Policy
7. Are you of the opinion that there are no
social/political obstacles to implementing PPP
in the country (e.g. grass roots opposition,
policy measures against private sector
participation in public infrastructure/services,
etc.)?
8. Are you of the opinion that there are no legal
obstacles to implementing PPP in the country
(e.g. non-publication of a decree provided under
the Law and necessary for such law to become
effective, etc.)?
For our general information, please describe the existing impediment and obstacles if any with respect to the two previous questions
Insufficient training of public servants in the relevant entities that might qualify as Contracting Authorities and insufficient awareness of the
public regarding the PPPs may be possible obstacles from a social and political standpoint.
In our opinion, despite recent amendments to the PPP Act 178/2010 and the PPP Norms, the implementation of PPPs may encounter obstacles
deriving from the fact that the current legal framework is not clear enough as regards the scope of application thereof and, in particular, the
delimitation between PPPs and Concessions.
55.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
8. INSTITUTIONAL FRAMEWORK
8.1 Existence and role of PPP Central Units/Agency
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Is there a specialised
institution/agency/ministerial department
established to promote PPP and to serve as
Central PPP Unit?
The entities that may be considered as having the role
of Central PPP Units are as follows:
- for Public Private Partnerships: the Central Unit for
Coordinating Public-Private Partnership (UCCPPP);
and
- for Concessions: the National Authority for
Regulating and Monitoring Public Procurement
(ANRMAP).
2. Is such Central PPP Unit composed mainly of
specialists recruited from the business
community and not exclusively composed of
civil servants coming from different public
ministries?
The above mentioned entities are composed mainly of
civil servants.
ANRMAP is entitled to employ personnel including
specialists from the business environment.
3. Is the role of such Central PPP Unit comparable
to a "task force" assisting in the development of
projects in general and not limited to promotion
of PPP?
56.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
4. Is the consent or recommendation of such
Central PPP Unit necessary for the development
and granting of most PPP projects (except small
or local PPP)?
Both ANRMAP and UCCPPP verify before publication
the relevant notices and requests for proposals and must
give their consent as regards the content thereof.
5. Is one of the roles of the Central PPP Unit to
assist in building capacity namely of the public
sector with respect to PPP?
Both UCCPPP and ANRMAP have a role of providing
counsel and guidance to both Contracting Authorities
and Private Parties in respect of the implementation of
PPPs.
For our general information, please name such establishment and specify its place in public hierarchy, format and key functions
(regulatory, operational, know how collecting, etc. or a combination thereof).
Further to the enactment of the new legal framework on PPPs, the UCCPPP has been recently reorganised and has received more powers and
functions. Currently, UCCPPP is organised as a department subordinated to the General Secretary of the Government and has, among its key
functions, the following:
- verifying contract notices and accompanying documents thereof;
- preparing the national strategy for the promotion and the implementation of PPP projects;
- monitoring the implementation of such strategy, establishing and promoting procedures in view of identifying and carrying out PPP
projects and providing support to Contracting Authorities in the process of preparing and implementing PPP projects;
- ensuring the promotion of the PPP concept and projects;
- preparing documents on the implementation of PPP projects;
- taking part, further to the invitation of Contracting Authorities, at the evaluation and negotiation commissions set up in view of selecting
a Private Party for the execution of a PPP agreement;
- identifying and ensuring the national wide dissemination of the best practices in the field of PPPs;
- establishing contacts with and keeping informed both governmental and nongovernmental bodies and Romanian and foreign investors as
regards investments through PPP projects;
- ensuring the contact between Romanian and foreign investors and Contracting Authorities in view of carrying out PPP projects;
57.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
- issuing recommendations on structuring PPP projects considering the impact of credit on the public sector as well as credit limitations at
a national and local level;
- monitoring the implementation of PPP projects and coordinating the actions required in view of the proper implementation thereof;
- providing specialised counsel to both Contracting Authorities and private investors on all stages of implementation of a PPP project;
- providing specialised assistance to Contracting Authorities on the setting-up the specialised department coordinating PPPs.
ANRMAP is a public institution under the subordination of the Romanian Government whose fundamental role consists in defining the concept,
promoting and implementing policies in the field of public procurement. The attributions of ANRMAP also refer to Concessions and, among the
key functions of this institution we note
- preparing action plans in view of implementing the strategy and development policy in the public procurement field;
- preparing and submitting for Government approval legal texts in the field, including amendments to existent texts;
- evaluating the requirements of improving the relevant legal framework and proposing measures in view of remedying the deficiencies
noted;
- approving draft pieces of legislation in other fields with an impact on the activities and public procurement;
- developing monitoring mechanisms and monitoring the award of agreements;
- setting-up a data base and preparing statistics and reports, analysis, studies and evaluations of the public procurement system;
- verifying and assessing the notices and requests for proposals before publication thereof;
- monitoring the functioning of the public procurement system;
- providing counsel and guidance to Contracting Authorities and bidders;
- organising training programs and public debates.
58.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
8.2 Other institutions concerned by PPP
6. Is there any PPP unit/agency or department of
the Central PPP unit either at the municipal or
regional level?
7. Is there any specific PPP unit department in any
ministry (other than the central PPP unit) or at
sectoral level?
Such entities should have specialised departments on
public procurement and concessions, furthermore,
entities having the capacity of Contracting Authorities
carrying out more than 2 Public-Private Partnerships
are entitled to set up a department dedicated to PPP.
8. Is there either a specific "one stop shop" for PPP
authorisations and formalities or a "one stop shop"
which services are available to the sponsors of PPP
project as well as other investors?
9. Is the division of power between different public
authorities involved in the PPP granting process
simple and coordinated?
59.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
9. PPP LAW ENFORCEMENT
9.1 Effectiveness of PPP enforcement and compliance with the Law
QUESTION
ANSWER
ARTICLE
COMMENTARY
1. Have any PPP projects in any form ever been
awarded in the country on the basis of the Law
discussed above? (with or without specific
reference to the Law)
No PPP project has been awarded so far under PPP Act
178/2010.
A limited number of Concessions have been awarded
under GEO 34/2006. Thus, to this day, SEAP has
published a number of 194 notices for the award of
Concessions of works and services, the vast majority
thereof being awarded by local and county authorities in
the field of municipal services.
2. Have such PPP projects, if any, been awarded
generally following a transparent competitive
selection procedure (and only through direct
negotiation under exceptional legal
circumstances as may be provided by the Law)?
To our knowledge, the Concessions awarded under
GEO 34/2006 have generally been awarded according
to competitive selection procedures.
3. Have any PPP projects or similar long term
agreements (falling under the definition of PPP
under this questionnaire) been awarded on any
legal basis different from the Law since the Law
has been in force?
For our general information, please give example of legal instruments, or reasons used, to bypass the Law and establish a PPP.
60.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
To our knowledge, county and local authorities set-up associations with Private Parties in view of carrying out projects of county/local
interest by resorting to the provisions of the Local Public Administration Act No. 215/2001, without organising competitive tender
procedures.
9.2 Statistics on PPP implementation under the Law
4. Have most of the awarded PPP projects been
successfully implemented and put into operation
in compliance with the Law?
There are no official statistics on PPPs implemented and
put into operation allowing us to give an assessment in
this respect. In absence of publicly available
information to the contrary, it can be argued that most
of them have been implemented and put into operation
in compliance with the Law.
5. Has a PPP project ever been awarded and
implemented in the country at the local /regional
/municipal level in compliance with the Law?
Yes. We are aware of such PPP carried out by
Bucharest Municipality in the water sector.
6. Have PPP project ever been awarded in the
country in the non merchant sector (such as
Hospital, School, prisons) and not exclusively
in the merchant sector (energy, water,
transport)?
To our knowledge, there has been a very limited
application of PPPs in the medical sector regarding
dialysis centres.
For our general information:
61.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
Approximately how many PPP projects are presently in operation (figure or order of magnitude)in the country and in what sectors have PPP
projects been awarded (energy, water, education, health for example)?
There is no updated official statistics of PPP projects implemented and presently in operation. In any case, as a general remark, Romanian
experience in implementing successful PPPs is very limited. Thus, the absence of an important number of successful Concessions
implemented under GEO 34/2006 has been indicated by the Romanian authorities as one of the reasons for the enactment of the PPP Act
178/2010.
As indicated above, no PPP has been awarded so far under the PPP Act 178/2010. As regards Concessions, in absence of statistics on the
actual implementation thereof, we cannot assess how many Concessions out of the194 agreements awarded under GEO 34/2006 (according
to the award notices published by SEAP) have actually been implemented.
Furthermore, it should also be noted that PPP projects have also been implemented and put into operation before the entry into force of GEO
34/2006.
As regards sectors, most of such PPPs appear to have been awarded in municipal services sectors: water and waste.
Please give some examples of the most significant project awarded:
under which legal form have such PPP projects been awarded (Concession, BOT, PFI, other):
In terms of legal form, PPPs awarded under Romanian Law have been mostly in the form of Concessions in the municipal services sectors.
have such PPP project been granted by (i) central, (ii) sub-sovereign/regional (if applicable) or (iii) municipal government as Contracting
Authority;
PPPs have been granted mostly by local/county authorities acting as Contracting Authority.
when did PPP begin to be awarded in the country: (i) in the last 10 years or before; (ii) in the last 5 years; or (iii) within the past few years
only; and
62.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
(i) PPPs began to be awarded in Romania in the last 10 years. Before the enactment of GEO 34/2006, PPPs have been awarded
based on the previous legal framework regarding Concessions of works and services and Public-Private Partnership.
please give examples of any PPP projects awarded but not implemented (or not implemented under a PPP form)
We note an example of a PPP project awarded but not implemented in the infrastructure sector: the Concession agreement for the design,
financing, construction, operation and maintenance of the Comarnic-Brasov Sector of the Bucharest-Brasov Motorway.
.are there any PPP/Project Agreements in discussion?
Yes, in April 2011, the Romanian Government has announced a list of 17 projects to be carried out on a PPP basis under the PPP Act 178/2010
in sectors among which: infrastructure, energy, health, housing, prisons.
9.3 Challenge of PPP
7. Are you of the opinion that there is a reasonable
chance for an unsuccessful bidder to
successfully challenge in the country a PPP
awarded under conditions contrary to the Law?
Yes, the Law provides for relevant mechanisms in this
respect.
8. If the answer to the previous question is Yes, are
you of the opinion that there is a reasonable
chance for the plaintiff to get some
compensation or for such action to result in the
cancellation of the award?
Yes, the Law provides for relevant mechanisms in this
respect.
9. Have PPP project been implemented by the
parties most generally without serious
Yes, according to publicly available information we are
aware of.
63.
Checklist ROMANIA
WS0101.3730241.1WS1801.141312.1
claims/arbitration by either Party concerning the
performance of the Project Agreements under
the Law?
10. If any Project Agreement has been terminated
prior to the end of the contractual period by the
Contracting Authority, has fair compensation
been paid to the Private Party in compliance
with the Law?
N/A
We are not aware of any such cases.
For our general information, can you provide any examples of a successful legal challenge in the courts or otherwise of a PPP award in
the country based on the PPP Law? Please describe the matter and, if known, the outcome of such matter.
We are not aware of any such challenges.