Outsourcing SDWORX Mainframe environment 26/05/2016 Lily Craps - SDWORX

Upload: nrb

Post on 20-Jan-2017

333 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: Outsourcing SDWorx Mainframe environment - Lily Craps

Outsourcing SDWORX Mainframe environment

26/05/2016Lily Craps - SDWORX

Page 2: Outsourcing SDWorx Mainframe environment - Lily Craps

Agenda

2

1. About SDWORX

2. Why Outsourcing?

3. Why NRB?

4. Project goals

5. Project tracks

6. Technical track details

7. Services and procedures

8. Testing

9. Project evaluation

10. Conclusion

Page 3: Outsourcing SDWorx Mainframe environment - Lily Craps

3

1. SD WorxA brief introduction

Antwerp (HQ) - Berlin - Breda

Brussels - Frankfurt - Luxembourg - Paris

Payroll - Tax & Legal - HR Consulting - Learning

Technology services - Outsourcing

2,700HR professionals

60,000Client base

2,350,000Payslips per month

70 yearsof expertise

€ 262 millionTotal turnover 2014

Page 4: Outsourcing SDWorx Mainframe environment - Lily Craps

1. SD Worx

Learning

Targeted and sustainable advice on Payroll,Tax & Legal, Reward,

HR Projects and International Employment

Automation of all payroll and HR processes

Payroll solutions, offering various outsourcing levels from SaaS

(Software as a Service) to full Business Process Outsourcing

PayrollEfficient payroll calculations

and administration

Tax & legalTax and social-legal support

HRSupport for all

of your HR processes

4

Purposive courses allow HR employees to shine

Technology Services

Outsourcing

Consulting

Page 5: Outsourcing SDWorx Mainframe environment - Lily Craps

5

• Moving of our mainframe LPARS to a shared mainframe environment, achieving ‘economies of scale’ on Mainframe infrastructure costs for hardware and software.• Triggers:

• Work on Cost Program• New required investments: DASD subsystem needed to be replaced

• Process • 12/2013 Start study outsourcing Mainframe environment• 01/2014-06/2014 RFI/RFP process• 07/2014 Selection provider • 08/2014-11/2014 Contract negotiations with NRB• 12/2014-05/2015 Migration project

2. Why Outsourcing?

Page 6: Outsourcing SDWorx Mainframe environment - Lily Craps

6

3. Why NRB?Evaluation criteria ( evaluation matrix – objective decision)

• Price • Other criteria:

• Quality RFP proces - contacts• Location ( team on one location or separated, West-Europe … ) • Quality transformation and transition during migration phase• Flexibility concerning ITIL processes ( change requests, problem solving )• Current infrastructure• Flexibility SW versioning• DRP solution• Availability and performance • Security base line assessment• Network: latency• Optional: additional savings

Page 7: Outsourcing SDWorx Mainframe environment - Lily Craps

7

4. Project goals

• Moving of our mainframe LPARS to a shared mainframe environment at NRB, achieving ‘economies of scale’ on Mainframe infrastructure costs for hardware and software

• Ability in a later stage for additional savings related to ISV (Independent Software Vendors) : contract merge, SW replacement.

• Infrastructure As A Service (IaaS cloud model)Only hosting hardware – all system engineering activities remains @ SD Worx

• Integration of change management, incident management and DR processes between SD Worx and NRB for Iaas related activities.

• Ensuring the transparency for business with at least the same performance, availability and with state of the art technology - at a lower cost.

Page 8: Outsourcing SDWorx Mainframe environment - Lily Craps

8

5. Project tracks

• Technical • Transformation tracks• Cut-over actions

Both for:• Distributed servers (latency sensitive applications)• Mainframe• Network

• Services and procedures

• Testing

Page 9: Outsourcing SDWorx Mainframe environment - Lily Craps

9

6. Technical track : transformation5 important technical tracks to be executed before testing & migration :

• Distributed applications: move latency sensitive applications to separated servers

• TCPIP change track : Change IP addresses of all lpars to avoid IP and network changes during cut-over weekend(s) Reduce risk and complexity

• GENERAL ‘MF infrastructure preparation’ track: create a ‘landing platform’ for all the SDWORX lpars Make sure all basic infrastructure is in place and corresponds to the SDWORX needs

DISK migration track : Setting up an asynchronous replication mechanism between the secondary SDWORX MF disk subsystem and the new primary disk infra at NRB allowing smooth testing and ‘fast’ cut-over.

• TAPE Migration track : Convert tape data from CA-VTAPE to hardware VTS solution and allow tape data to be migrated ‘in advance’ to NRB using VTS GRID functionality.

Page 10: Outsourcing SDWorx Mainframe environment - Lily Craps

10

6. Technical track : MF hardwareCPU (existing zEC12-505 CPU – 347 MSU)• Target : zEC12-614 (4 Shared CP’s + 2 ‘Dedicated’ zIIPs)• ‘absolute capping’ to limit peak CPU behavior

DISK (existing DS8830) • Target : DS8870 with flash storage modules and EASY TIER (production environments)

( I/O RT improvement )

TAPE (existing CA VTAPE software virtual tape solution) • Target : IBM TS7720 virtual tape solution - ONLY on disk.

( tape access time improvement)

CONNECTIVITY• LAN (4x 1 GbE ports available - 2 ‘isolated’ for preprod & 2 for other partitions –

active/passive)(to-be equal to as-is situation)

Page 11: Outsourcing SDWorx Mainframe environment - Lily Craps

11

7. Services and procedures

• Integration of change and incident/problem management procedures SD NRB

• Operational Guide

• SLA’s :• Availability• Incidents• Change requests (CPU , Disk , Tape capacity ) – emergency• IT Continuity• Performance

• Netwerk latency• Disk PPRC• CEC capacity (SYSP and SYSG lpars can peak at least 20% above their

defined capacity , the other lpars can peak at least 15% above their defined capacities)

• Dummy applications (I/O, CPU)

Page 12: Outsourcing SDWorx Mainframe environment - Lily Craps

12

8. Testing: formal process

• Testcoördinator• Formal acceptance criteria ( part of contract) • Detailed testscenario’s• Governance:

BusinessBusiness DevelopmentDevelopment Dev support MFDev support MF

Central systems MF &Servers team

Central systems MF &Servers team

Test responsibleTanja Michielsen

Test responsibleTanja Michielsen

Project leaderLily Craps

Project leaderLily Craps

Technical contactTechnical contact

NRBNRB

Test preparation requestGreen light to start execution

Test preparation readyTest execution results

Reported issues

Issue dispatching and follow up

Reporting results & issuesEscalation

Test teams

Page 13: Outsourcing SDWorx Mainframe environment - Lily Craps

8.

Central System + Dev support (MF)

Development (Dev + Test)

Business

SYSPSYSW

+distr.*

Pre-phase

maart-april

Phase 1

9-16/3

Phase 2

25/4

Phase 3b

14/5

Growing team involvement and growing scope per phase ensures the main MF switch activities are repeated multiple times which leads to higher confidence

Focus on quality attributes:• Connectivity• Accessibility• Functionality• Performance (limited)• Migration

NRB (Infrastructure)

Central Systems (MF) SYSA/B SYSI **

SYSD ** + distr.*

* distr. = distributed/decentral system(s) ** including DRP testing at NRB

Server services team

Phase 3a

8/5

SYSG

8. Testing“Phased approach”

Page 14: Outsourcing SDWorx Mainframe environment - Lily Craps

14

9. Project evaluation

+• Cooperation with NRB very professional and positive - both PM and technical staff

• Planning was respected during whole project.

• Staged migration whereby lessons learned were included in subsequent phases with an error free migration of the production Lpars

• All IT departments the same focus/prio to this project: has led to internal smooth cooperation between the various units and teams

-• ISV contracts: some outsourcing fees to be payed

Page 15: Outsourcing SDWorx Mainframe environment - Lily Craps

15

10. Conclusion

Moving of our mainframe LPARS to a shared mainframe environment at NRB, achieving ‘economies of scale’ on Mainframe infrastructure costs for hardware and software

Ability in a later stage for additional savings related to ISV (Independent Software Vendors) : contract merge, SW replacement.

Infrastructure As A Service (IaaS cloud model)Only hosting hardware – all system engineering activities remains @ SD Worx

Integration of change management, incident management and DR processesbetween SD Worx and NRB for Iaas related activities.

Ensuring the transparency for business with at least the same performance, availability and with state of the art technology - at a lower cost.

Project goals

Page 16: Outsourcing SDWorx Mainframe environment - Lily Craps

Thank youAny questions?