outline of presentation ppp’s in irelandold.pppa.lv/faili/konf2007_prez/pppa07_14_minnock.pdf ·...
TRANSCRIPT
1
Donal Minnock
National Roads Authority
PPP’s in Ireland
The Fermoy Bypass
PPP Scheme
Outline of Presentation• Delivery of Fermoy Bypass
– Statutory Procedures
– Tender Competition
– Project scope
• Payment Mechanism
• Risk Allocation
• Project Consortium structure
• Contract Management & Monitoring
• NRA PPP Programme Activity overview & recap
Fermoy Bypass
Statutory Procedures
Delivery of Fermoy Bypass:
Statutory Procedures - Planning
• Planning application submitted by Cork County Council 12th July 2001
• Oral Hearing held November 2001
• Supplementary material requested by the board and submitted 27th May 2002
• Oral Hearing re-opened 24th September 2002
• Approval received 30th December 2002
Statutory Procedures - tolling
• Draft Toll Scheme published 14th May 2001
• 8 objections received
• Oral Hearing into toll scheme 3rd April 2002
• Adoption of toll scheme by NRA Board
27th March 2003
• Publication of Draft Bye-Laws 12th May 2006
• Adoption of Bye-Laws 20th July 2006
Tender Competition
2
Tender Competiton
• Pre-qualification in OJEU commenced July 2001
• Shortlisting successful tenders in Nov 2001 :� Direct Route
Halliburton Brown & Root Ltd, Strabag AG, John Sisk & Son (Holdings) Ltd, Lagan Holdings Ltd, Roadbridge Ltd (Mulcair).
� Erin RouteCarillion Private Finance Ltd, Balfour Beatty Capital Projects, EgisProjects SA, WS Atkins Investments Ltd.
� Togher TollMota-Engil SGPS SA, Mota & Companhia SA, Engil Sociedadede Construcao Civil SA, Acciona SA, Banco Espirito Santo SA, Coffey Construction Ltd, Priority Construction Ltd.
� Vinci-HegartyVinci, PJ Hegarty & Sons.
PPP Procurement ProcessPrequalification
Invitation to Negotiate
Shortlisting
Preferred
BidderPrequalEvaluation
Tender
Evaluation
ClarificationMeetings Due diligence
& BAFO
Negotiations
Close
Provisional Preferred Tenderer (“PPT”)
Tender Programme
• Issue of tender documentation 19th April 2002
• Tender return date 18th November 2002
• Shortlisting of tenderers to BAFO 25th March
2003 – Togher Toll & DirectRoute
• Best and Final Offers in 16th December 2003
• Announced Preferred tender 17th February 2004
• Contract Close 11th June 2004
Statutory
Procedures
Project Scope
N8 Rathcormac
/Fermoy Bypass
Scheme
Layout Plan
Galway
Belfast
Waterford
Cork
Dublin
Limerick
3
N8 Rathcormac/Fermoy Bypass
Technical Scope
• 17.5 km 2 Lane motorway
• 450m Motorway Viaduct
• 2 Major River Bridges
• 3 Interchanges (1 was removed by ABP)
• 9 County Road Crossings
• 1 Motorway Toll Plaza
• 2 Ramp Toll Plazas
N8 Rathcormac/Fermoy Bypass
Typical Standard
Motorway Cross-Section
Toll Plazas
� Mainline Plaza between Watergrasshill and
Rathcormac South Interchanges
� 6 lanes in each direction
� Ramp Plazas to be located at North facing Ramps
at the Corrin Interchange
� 2 lanes per Ramp
� Includes Administration Building, Canopy, Toll
Booths, access, etc.
Toll Plazas Toll Plazas –– Standard Layout Drawings Standard Layout Drawings
Front Elevation
Side Elevation
N8 Rathcormac/Fermoy BypassSignificant Construction Issues
• Blackwater Crossing Viaduct
– 450m Long Motorway Viaduct in SAC
• Corrin Interchange
– Construction on Soft Ground
• Condonstown Toll Plaza
– Construction of Motorway Tolling Facility
Payment Mechanism
4
Payment Mechanism Elements
Primarily:
1. Hard Toll Revenue
2. Construction Payments
3. Operational Payments
Secondarily
� Revenue Share
� Non Availability Payment
� Traffic Guarantee
� Lane Occupation Charges
Payment Mechanism1. Hard toll revenue – from Permit to Use Date
- Tenderer bids on his own traffic forecasts
- Maximum toll charges as per Toll Scheme
- Base toll as per Toll Scheme + Indexation + VAT, rounded to nearest 10c
2. Construction Payments (if required)
- Maximum overall amount set in nominal terms
- Maximum annual amount specified
- Not greater than 50% of certified value of work completed at any point
- Linked to Milestone Events
3. Operational Payments
- Maximum annual amount set
- Maximum average annual amount set
- Cannot commence before Target Completion Date
- Now subject to Non Availability deductions
• Fermoy Bypass - NRA payments to Direct Route:
– Approx €80m (2003 prices) over the period of
construction
– Approx €40m (2003 prices) during the period of
operation. (subject to CPI)
Payment Mechanism (Cont’d)Toll Charge Regime
• NRA set maximum tolls annually
• Same charge regime on M1, N6,
N7, M7/M8, M8, N25 PPP
Schemes
• Motor car = €1.70, Bus = €3.10
• PPP Co’s can propose lower
charges to stimulate demand
• Agreed with PPP Co & published
annually in national papers
• Visit www.nra.ie
Risk Allocation
Risk Allocation
• Statutory Approvals / Planning risks rest entirely with the public sector.
• Construction related risks rest with PPP Co.
• Traffic risk mainly with PPP Co
• NRA establish a Data Room providing significant information to tenderers ie,.
• Site investigation results
• Survey results etc.
5
LAW
FINANCING
RESIDUAL LIFE
DEMAND
OPERATING
CONSTRUCTION
DESIGN
PLANNING
PPPTRADITIONALRISK N8 Rathcormac/Fermoy BypassSite Investigation
• Limited existing SI available - geophysical investigation carried out in areas of Karst Limestone
• Advance Ground Investigation Contract tendered by Local Authority - 12 week site works; 4 weeks testing and reporting
• Detailed investigation to comprise boreholes, trial pits and testing
• Overview report along length of project road provided during tender period
N8 Rathcormac/Fermoy BypassArchaeology
• EIS identified 13 sites of archaeological interest
• Archaeological Investigation Contracts were tendered by
Cork County Council to excavate a 2m wide trench, at
12.5m centers, alternated along the centreline out to the
CPO line
• Reports identifying all known sites within the site and
progress of resolution of such sites fed in to the tender
programme
• Approximately 93% of site was tested in this fashion prior
to signing of PPP Contract
Archaeological risk management
• Intensive advance testing
– Pioneered on N4/N6 PPP
contract
M4 - Johnstown
On site excavation• Sites are excavated in
timescales that sit within a
considered timeframe
Advance testing• non-invasive techniques –
geophysics, aerial, topographic,
terrain modelling
• invasive techniques – testing of
sites & trenching of geophysical
areas
Roestown on the M3 Clonee-Kells Motorway
Existing N3
Aerial view of testing on the M3 Clonee-Kells
6
Project Consortium
Structures
Typical PPP Contract Structure
ConstructionContractor
OperatingContractor
Contracting
Authority
Funders
Operating Contract
Shareholders
Project Agreement
Shareholders
AgreementPPP Co
Direct
Agreements
Loan Agreement
Direct Agreement
Security
Package
Construction
Contract
Direct Route (Fermoy) Ltd.:
Consortium Members
• Kellog Brown & Root
• Strabag
• John Sisk & Son
• Lagan Holdings
• Roadbridge
• First Irish Infrastructure Fund
– Joint AIB/EIB investment fund
• Subsequent inclusion of Bank of Scotland
Lenders
• KBC/IIB, AIB, ING
– Subsequent inclusion of Bank of Scotland
• European Investment Bank (EIB)
Construction Joint Venture:
Direct Route (Fermoy) Construction Ltd.
• All equity members except FIIF and Bank
of Scotland
Cash Flow Overview
Direct Route (Fermoy) Limited
Project Lenders
KBC/IIB, ING Bank NV,AIB & EIB + BoS
Project Investors
HalliburtonStrabag
SiskLagan
RoadbridgeFIIF
+BoS
Loans
Principle &
Interest
Loan Stock
National Roads
Authority
Revenue Share
Public
Sector
Finance
Providers
Road Users
Tolls
Other Public Sector
TaxVAT
Rates
Third PartiesConstruction Joint
Venture Co.
Construction Costs Operating Costs
Construction & operation payments
DirectRoute
(Fermoy) Holdings Limited
Equity
Dividends
Equity Dividends
Principle& Interest
Designers
• Kellog Brown & Root
• Toll Link
Lender’s Technical Adviser
• RPS MCoS
Functions of the Lender’s Technical adviser• Technical Due Diligence (pre-Financial Close review and report on organisation structure, technical proposals -
feasibility, risks and costs, contract documents etc.)
• Syndication Support (report update and presentation to Syndication Banks, post Finacial Close - if appropriate)
• Progress Monitoring (both for D&C progress and preparation work for O&M phase)
• Payment Certification (in accordance with the terms of the Credit Facility and LTA Agreements)
• Approvals (in accordance with the terms of the Credit Facility and LTA Agreements)
7
NRA Contract
Management
NRA PPP Contract• Based on Highways Agency DBFO contract
• Amended to suit Irish PPP programme
• No compensation on PPP Co Default
• High level of risk transfer
• Strong incentive on PPP Co to identify, avoid, mitigate and manage risks effectively
• Toll Road (with free alternative route)
– Traffic and revenue risks
• Programme flexibility
• Long stop date
– 12 months past the Target Completion Date
• NRA provide access to site
– Co-operation Agreement with Local Authorities
• Little opportunity for claims or cost overruns
• Essential to avoid / minimise Authority changes
PPP Contract: Key Sections
• Part 1: Definitions
• Part 4: Property
• Part 5: Design and Construction
• Part 6: O&M
• Part 7: Representatives
• Part 8: Change
• Part 9: Payment and Monitoring.
• Expiry Date
• Completion Date
• Substantial Completion
• Permit to Use / Taking Over Certificates
Key Dates
Key Contract Schedules for D&C
Management
• Schedule 2: Land Issues, Roads and Orders
• Schedule 3: Third Parties
• Schedule 4: Design and Construction
• Schedule 5: Certification Procedure
• Schedule 9: Liaison Procedures
• Schedule 10: Quality and Environmental Management
• Schedule 15: Payments
• Schedule 16: Performance Points
• Schedule 28: Tender Proposals
Clause 20.1 The Authority’s Representative
• The Authority has appointed or will appoint the Authority’s
Representative to act as its agent in relation to the Project and as
otherwise set out in this Agreement. The Authority’s Representative
shall exercise the functions set out in Schedule 8 (Representatives),
such other functions as are set out in this Agreement, and those other
functions in respect of this Agreement which the Authority may notify
to the PPP Co from time to time.
Main Duties of Authority’s Representative• Monitor (and review) the Design
• Monitor Construction
• Assess the need for Variations to the Contract
• Contract Administration and Financial Control
• Perform delegated functions
Fermoy Bypass NRA Site TeamAuthority’s Representative
G. Murphy /D Minnock
Authority’s RepresentativeG. Murphy /D Minnock
Project Director(Consultant)
Project Director(Consultant)
Commission Manager(Consultant)
Commission Manager(Consultant)
Consultant’s Technical
Review Team
Consultant’s Technical
Review Team
ProjectArchaeologist
Ken Hanley
Cork Co. Co.Liaison Officer (1)
Authority’s SiteRepresentative
(Consultant)
Authority’s SiteRepresentative
(Consultant)
Consultant’s Landscape
Subconsultant
Consultant’s Landscape
Subconsultant
Consultant’s Tolling
Specialist
Consultant’s Tolling
Specialist
Assistant ContractManager(Roads)
Assistant ContractManager(Roads)
Section Manager(Roads)
Section Manager(Roads)
Assistant ResidentEngineer or Clerk of
Works
Assistant ResidentEngineer or Clerk of
Works
Assistant ContractManager
(Bridges/Structures)
Assistant ContractManager
(Bridges/Structures)
Section Manager(Bridges/Structures)
Section Manager(Bridges/Structures)
Assistant ResidentEngineer
Assistant ResidentEngineer
Assistant ContractManager(Quality)
Assistant ContractManager(Quality)
ClericalOfficer
ClericalOfficer
SecretarySecretary
Cork Co. Co.Project ManagerKieran McKeone
NRA SPM/ InspectorTim Ahern/Paschal
Griffin
8
PPP Co’s Certificates
• The PPP Co’s Certification Procedure shall apply to those
Certificates that are to be supplied to the Authority’s
Representative by the PPP Co
• “Acknowledged”, following which the PPP Co may proceed on the basis of there being no objection; or
• “Acknowledged with Comments”, and full details of the Authority’s Representative’s comments shall be supplied to the PPP Co. The PPP Co shall amend its proposals and resubmit amended Certificates. The resubmitted Certificates shall be deemed to be Acknowledged if not objected to within two Working Days after resubmission; or
• “Rejected”, and full details of the reasons for the rejection shall be supplied to the PPP Co. Grounds for such rejection are as set out in Schedule 5 Part 3.
PPP Co’s Certificates: Responses
PPP Co’s Certificates :
Constraints on Starting Work
1. The PPP Co shall not be permitted to proceed with the Works which are the subject matter of a Certificate until such time as the Certificate has been Acknowledged
2. Quality and Environmental Documentation shall includea list of the written procedures, inspection and test plans and method statements which shall be followed to ensure the effective management of the activities to be undertaken by the Contractor. This shall indicate a programme for submission of any written procedure or method statement which allows for its submission to the Authority’s Representative in accordance with the Certification Procedure prior to the commencement of the relevant activity .
• The PPP Co. shall procure that all aspects of the Project are the
subject of Quality and Environmental Management Systems
which comply with Clause 23 and Schedule 10 of the
Agreement.
Clause 23. Quality and Environmental Management
Non Conformance Reports (NCR’s)
• Aid for control of site procedures & construction quality
• ‘No blame’ culture
• Majority should be coming from PPP Co’s quality check &
from Contractor & Designer.
• Follow up - closure
Authority’s Key Objectives for Construction
Monitoring
• Receipt of design and its certification
• Monitor construction and progress
• Monitor management of environmental issues
• Monitor supervision by PPP Co
• Appropriate traffic management
• Report and advise on variations
• Monitoring of third party issues
Donal Minnock
National Roads Authority
NRA PPP
Programme Activity
Review of NRA Progress
• Approx €2.088 billion of private finance
committed to road schemes
• Almost 70 km of national roads
completed and 113 km operated and
maintained under PPP Contracts
• Almost 180 km of national roads under
construction
9
Recently opened toll roads• 3 PPP roads open, 10 months, 8 months, and 5 months
early and with no cost over-runs
• M1 Drogheda Bypass – June 2003
• M4/M6 Kilcock-Kinngead – Dec. 2005
• M8 Rathcormac/Fermoy – Oct. 2006
• Dublin Port Tunnel – Dec. 2006
• Next openings– N25 Waterford City Bypass - 2010
– N7 Limerick Tunnel - 2010
– N6 Galway Ballinasloe - 2010
– M7/M8 Portlaoise - 2010
– M3 Clonee Kells - 2010
– M50 Upgrade incorporating free flow tolling - 2010
Or earlier – watch this space!Donal Minnock - National Roads Authority
PPP’s in Ireland – Fermoy Bypass PPP Scheme
Thank you for listening