our journey to a better gauteng · 2014-06-27 · our journey to a better gauteng . ... political...
TRANSCRIPT
SADC - DFRC Presentation on Gautrain
December 2016
OUR JOURNEY TO A BETTER GAUTENG
Contents
1. The Past – Africa’s Largest PPP
2. The Present – Managing Complexity
3. The Future – Creating a Vision
The Past: Africa’s Largest PPP
Key Success Factors
1. Political leadership and will
2. Continuous and strong project leadership and technical team
3. Doing Gautrain as a PPP
4. Treasury involvement in funding
Existing Routes
Pre Gautrain- a challenging future
The Gautrain will promote
Public Transport
SMME & BBBEE Development
Tourism
Business development
The project stimulates
Economic growth
Investment
New development
Job creation
Design to
Restructure urban areas
Reduce travel distances,
time and cost
Improve city sustainability
Gautrain: More than Just Another Transport Project
Public Private Partnership
• Gautrain is a PPP Project
• Leading to a Concession Agreement
• Of the DBFOM type
• PPP Projects on National and Provincial levels are regulated by South African Public Finance Management Act Regulations (TR 16)
PPP Requirements • Feasibility
– Value for money • Public Sector Comparator (PSC)
(What will it cost if Government does the work through normal procurement process; and including completion and integration risk and cost)
– Affordability – Total cost of project, expressed in Net Present Value (NPV) – Yearly cost to the province (contingent liability) – Maintain the 80/20% ratio in social vs.. rest split in budget
– Risk transfer • Identify, cost and allocate various risks to the role
players best equipped to mitigate and manage them
PPP Contracts
• Public-Private-Partnership (PPP) contracts
– Output specification
– Client (authority) only defines the problem (essential minimum requirements)
– Turnkey project
– Contractor (concessionaire) bids to design, build, operate the project for the concession period
PPP Contracts (2) • Concessionaire takes all completion and integration risks
• Concessionaire offers a fixed price, fixed specification and fixed time frame (turnkey) contract
• Concessionaire is fully involved in the operation and maintenance of the system for the full concession period
• Concessionaire must hand over the system to the client at the end of the concession period in a prescribed condition
PPP Contracts (3)
• PPP contract allows for Concessionaire innovation and world-best-practice during design, construction, operations and maintenance
• PPP’s give access to private sector funds (local and international)
• However, potential problems, e.g. value engineering/scope changes, variations, less opportunity to claim, etc.
Major Phases of Project
PHASE PHASE NAME AND PERIOD PROVINCE
SUPPORT
1
PROCUREMENT
Apr 2000 – Sep 2006
Financial Close only in February 2007
Transaction
Advisors
2
CONCESSION DEVELOPMENT
28 Sep 2006 – 7 June 2012
Plus defects/liability/retention period
GMA staff and
Provincial
Support Team
3
OPERATION & MAINTENANCE
7 June 2012 – 27 March 2026
GMA
Procurement Process
• Request for Prequalification (RFQ) – February – May 2002 – Premier Shilowa announced on 2 May 2002 the
Bombela and Gauliwe consortia as pre-qualified bidders
• Request for Proposal (RFP) I – Discussions May – September 2002
• RFP II – Issued 29 November 2002 – Submitted 30 September 2003
Procurement Process (2)
• RFP III (Best and Final Offer/BAFO) – Constructive engagement with bidders – Draft Documents July 2004 – Final Documents Dec 2004 – Submit 26 Jan 2005 – Bidder Presentations 9+10 Feb 2005 – FBAFO March 2005 – Clarification Questions: briefing notes and
meetings – Analysis/Evaluation of proposals
Procurement Process (3)
• Negotiations with preferred bidder
• Sign Concession Agreement and Commence Construction (28 September 2006)
• Financial Close (January 2007)
Project partners
PUBLIC
PRIVATE
33%
25%
17%
17%
8%
Provincial Structure during Procurement Phase
Technical Committee
Legal Team
Financial Team
SED Team
Transaction Advisors
Political Committee
Project Leader
Project Co-ordinator
Project Cost
• Gautrain is a fixed price turn key project – Price had been fixed at the signing of the Concession Agreement
on 28 September 2006
• Provincial contribution R21,9 bn
• Private sector contribution R 3,2 bn
• R25,1 bn is expressed in nominal terms over the next 54 months
• Only the following increases in cost will be allowed: – Extra work through a Variation Order (only 2.1% of Project Value)
– Escalation higher than the escalation prediction of the Reserve Bank
Funding
• The public sector funding of the Gautrain's capital costs over the five year development period will be sourced from three places: – The GPG’s equitable share (i.e. the provincial budget (MTEF));
– provincial borrowing from the National Treasury; and
– a conditional grant from National Treasury via the National Department of Transport
• The conditional grant via the Department of Transport's budget makes up 50% of the public sector's capital costs of the project, with the provincial budget and provincial borrowing sums making up the remaining 50%
Project Financing
MTEF 26.1%
DoRA 44.2%
Equity 1.8%
Private Debt 9.5%
Provincial borrowing
18.4%
Gautrain Socio economic development success (Construction)
Gautrain Socio economic development (Construction)
The Present – Managing Complexity
Key Lessons
1. Keep the customers happy
2. Contract management drives Value for Money
3. Empowered public sector essential
4. Public sector drives change in a PPP
5. External dispute resolution poor value for money
Snap -Shot 1. 99% Availability and 98% Punctuality
2. Less than 0,4% fare evasion
3. Less than 1 security incidents / 1 million trips
4. Strong ridership Growth
5. Operating cost recovery ratio 1,1
6. Overcrowding and capacity constraints currently using entire fleet of trains
7. GMA established and about 82 staff
Gautrain - Ridership
Gautrain – Revenue (Nominal)
R 0
R 100 000 000
R 200 000 000
R 300 000 000
R 400 000 000
R 500 000 000
R 600 000 000
R 700 000 000
R 800 000 000
R 900 000 000
FY 12/13 FY 13/14 FY 14/15 FY 15/16
Gautrain Annual Fare IncomeWith year on year growth rate indicated
GPS
APS
25.3%
15.0%
7.9%
Fare Comparison
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
- 10.0 20.0 30.0 40.0 50.0 60.0 70.0
Trip
Co
st, R
Distance, km
Comparison of Orange Single Train Fares : 2011 to 2016
Minimum - Schedule 20 Maximum - Schedule 20 2015 2016 2014 2013 2012 2011
Managing Capacity As the following slides show, Gautrain
has addressed capacity issues by:
• Introducing 8-car trains
• Structuring the fares to encourage
travel outside of peaks
• Introducing a 10 minute timetable
― August 2011 ― March 2012 ― May 2102 ― September 2012 ― April 2013 ― August 2013 ― April 2014
Additional Rolling Stock
– Province has identified a latent demand and capacity constraint in relation to the Gautrain Rapid Rail Link system
– The actual passenger demand on the Gautrain system has exceeded realistic expectations and predictions
– To manage the provision of capacity, Province will require a total of 48 coaches, expanded depot and upgrade signalling
Being done as a Variation spanning over the end of the concession
DBSA is GMA financing partner
R4,5 billion project
Currently in procurement
Gautrain’s operations Socio-economic development success
Source: GMA SED report 2013/14 financial year
Gautrain’s operations Socio-economic development success
Source: GMA SED report 2013/14 financial year
Gautrain’s operations Socio-economic development success
Source: GMA SED report 2013/14 financial year
The Vision for the Future
Key Success Factors
1. Political leadership and will
2. Build on Gautrain lessons learned – what worked and what didn’t
3. Stick with PPP but tweak the model
4. Partner with the best we can
5. Lead the integration as a Province
6. Follow TR 16 closely
Gauteng Rail Network (Gautrain/ PRASA)
A new modern Gauteng is in the making
• Gauteng premier’s first State of the Province Address on 27 June 2014 in Thokoza, Ekurhuleni – Radically modernise the way Gauteng residents live
and work
– Ten pillars of radical transformation
• Gauteng has a 25 year Integrated Transport Master Plan with Rail as its Public Transport backbone
• Use public transport as an economic growth stimulant
Five key GRRIN outputs
• Integrated safe, affordable and reliable rapid rail public transport
• New transport orientated development nodes promoting higher density living
• Greener transportation solutions for a healthier community
• Enhancing economic integration and development
• Increase in local content, Business Development Job creation/opportunities
Dreaming Of a World-class Rail System To Connect Our People throughout Gauteng
• Integrated public transport
• At its core a rapid rail link system
• Increased infrastructure investment
• Spatial Development Initiatives to stimulate economic growth and job creation
Gauteng future
1. Car/ vehicle growth and
2. Road Congestion
3. Travel time savings if GRRIN implemented
4. Population Growth and land use
5. GRRIN model
6. Connectivity Challenges in Jhb North Western Sector
Car growth and Congestion in Gauteng
• 3,9 million 2014 to 6,6 million 2037
• 300/ 1000 population to 450/1000
• Significant car growth
• Congested road network
“The Cost of Doing Nothing”
• Analysis of the transport situation in 25-years’ time, shows that the consequences or “cost of doing nothing” will be severe, i.e. if current trends continue
• Vehicle population predicted to grow from 3.65 mil. to 6.57mil. • Peak hour person trips to grow from 2.2mil. to 3.9mil. • Weighted average peak hour road network speed will reduce from
48km/h to below 10km/h • Weighted public transport travel speed decline from 38km/h to
below 14km/h • Congestion nightmare, with the transport network, the economy
and the natural environment eventually choking • Major interventions and management of travel choices and
demand will be required to avoid this scenario
7% 9%
30% 53%
Base Year
9%
11%
31%
48%
2025 Demand on Base Year Network
39%
17%
22%
23%
2037 Demand on Base Year Network
0 - 20 km/h
20 - 40 km/h
40 - 60 km/h
> 60 km/h
“The Cost of Doing Nothing”
Gautrain Public transport system
Rapid Rail / Gautrain Speed profile: • 160 km/h Optimal distance • 62 – 75 km Passenger per hour • 7,500 – 20,000 pph
Gautrain Feeder System
GRRIN Integration with BRT in CoT, EMM and CoJ as part of feeder and distribution bus network.
Gautrain
Harambee BRT A RE YENG REA VAYA
Feeder Bus
Feeder Taxi • Marlboro • Rosebank
SANDTON
SUNNINGHILL FOURWAYS
COSMO
LITTLE FALLS
ROODEPOORT
RANDBURG
LANSERIA
SANDTON 2 SOWETO (JABULANI)
MAMELODI
SAMRAND
IRENE TSHWANE
EAST
BOKSBURG
LANSERIA
MIDFIELD
EASTRAND MALL
RHODESFIELD 2
ORTIA
HAZELDEAN
OLIEVENHOUTBOSCH
GRRIN Extensions Phase 1 Western Core Network
SANDTON MARLBORO
MIDRAND
CENTURION
HATFIELD
ROSEBANK
PARK
PRETORIA
RHODESFIELD
O.R. TAMBO
SAMRAND
IRENE
TSHWANE EAST
HAZELDEAN
MAMELODI
OLIEVENHOUTSBOSCH
SUNNINGHILL
FOURWAYS
COSMO
LITTLE FALLS
ROODEPOORT
JABULANI
RANDBURG
LANSERIA
EAST RAND MALL
BOKSBURG
SANDTON 2
LEGEND
North – South Commuter
East – West Commuter
Airport
MODDERFONTEIN
Phase 1
Metrorail
GRRIN Extensions – Phase 2
SANDTON MARLBORO
MIDRAND
CENTURION
HATFIELD
ROSEBANK
PARK
PRETORIA
RHODESFIELD
O.R. TAMBO
SAMRAND
IRENE
TSHWANE EAST
HAZELDEAN
MAMELODI
OLIEVENHOUTSBOSCH
SUNNINGHILL
FOURWAYS
COSMO
LITTLE FALLS
ROODEPOORT
JABULANI
RANDBURG
LANSERIA
EAST RAND MALL
BOKSBURG
SANDTON 2
LEGEND
North – South Commuter
East – West Commuter
Airport
MODDERFONTEIN
Phase 2
Metrorail
GRRIN Extensions: Phase 3-5
SANDTON MARLBORO
MIDRAND
CENTURION
HATFIELD
ROSEBANK
PARK
PRETORIA
RHODESFIELD
O.R. TAMBO
SAMRAND
IRENE
TSHWANE EAST
HAZELDEAN
MAMELODI
OLIEVENHOUTSBOSCH
SUNNINGHILL
FOURWAYS
COSMO
LITTLE FALLS
ROODEPOORT
JABULANI
RANDBURG
LANSERIA
EAST RAND MALL
BOKSBURG
SANDTON 2
LEGEND
North – South Commuter
East – West Commuter
Airport
MODDERFONTEIN
Metrorail
Phase 3- 5
CRADLE
Structure
• GRRIN is an ‘extension’ to the current network and therefore is considered a Brownfield project;
• Expected to be phased over a long construction period in order to consider both ridership demand and funding availability ;
• Expected lower government capital contribution for GRRIN in comparison to Gautrain, – hence the sourcing of non-government (external funding)
is paramount;
• Passenger demand, • Economic impact and • Funding/financing ability for the specific line sections
Contract structure
Thank You
William Dachs
COO Gautrain Management Agency
www.gautrain.co.za