    12-1

    CHAPTER 12Other Topics in CapitalBudgeting

    Evaluating projects with unequal

    lives Identifying embedded options

    Valuing real options in projects

  • 8/14/2019 Other Topics in Capital Budgeting

    2/21

    12-2

    Evaluating projects with

    unequal livesProjects S and L are mutually exclusive, andwill be repeated. If k = 10%, which is better?

    Expected Net CFs

    Year Project S Project L

    0 ($100,000) ($100,000)

    1 59,000 33,500

    2 59,000 33,500

    3 - 33,500

    4 - 33,500

  • 8/14/2019 Other Topics in Capital Budgeting

    3/21

  • 8/14/2019 Other Topics in Capital Budgeting

    4/21

  • 8/14/2019 Other Topics in Capital Budgeting

    5/21

  • 8/14/2019 Other Topics in Capital Budgeting

    6/21

    12-6

    of

    real options? Investment timing options

    Abandonment/shutdownoptions

    Growth/expansion options

    Flexibility options

  • 8/14/2019 Other Topics in Capital Budgeting

    7/21

    12-7

    Illustrating an investment

    timing option If we proceed with Project L, its annual cash

    flows are $33,500, and its NPV is $6,190.

    However, if we wait one year, we will find out

    some additional information regarding outputprices and the cash flows from Project L.

    If we wait, the up-front cost will remain at$100,000 and there is a 50% chance thesubsequent CFs will be $43,500 a year, and a

    50% chance the subsequent CFs will be $23,500a year.

  • 8/14/2019 Other Topics in Capital Budgeting

    8/21

    12-8

    Investment timing decision

    tree

    At k = 10%, the NPV at t = 1 is: $37,889, if CFs are $43,500 per year, or

    -$25,508, if CFs are $23,500 per year, inwhich case the firm would not proceed withthe project.

    50% prob.

    50% prob.0 1 2 3 4 5

    Years

    -$100,000 43,500 43,500 43,500 43,500

    -$100,000 23,500 23,500 23,500 23,500

  • 8/14/2019 Other Topics in Capital Budgeting

    9/21

    12-9

    Should we wait or

    proceed? If we proceed today, NPV = $6,190.

    If we wait one year, Expected NPV

    at t = 1 is 0.5($37,889) + 0.5(0) =$18,944.57, which is worth$18,944.57 / (1.10) = $17,222.34 intodays dollars (assuming a 10%

    discount rate).Therefore, it makes sense to wait.

  • 8/14/2019 Other Topics in Capital Budgeting

    10/21

    12-10

    Issues to consider with

    investment timing options Whats the appropriate discount rate?

    Note that increased volatility makes the

    option to delay more attractive. If instead, there was a 50% chance the

    subsequent CFs will be $53,500 a year,and a 50% chance the subsequent CFs

    will be $13,500 a year, expected NPVnext year (if we delay) would be:

    0.5($69,588) + 0.5(0) = $34,794 >$18,944.57

  • 8/14/2019 Other Topics in Capital Budgeting

    11/21

    12-11

    Factors to consider when

    deciding when to invest Delaying the project means that cash

    flows come later rather than sooner.

    It might make sense to proceed todayif there are important advantages tobeing the first competitor to enter amarket.

    Waiting may allow you to takeadvantage of changing conditions.

  • 8/14/2019 Other Topics in Capital Budgeting

    12/21

    12-12

    Abandonment/shutdown

    option Project Y has an initial, up-front cost

    of $200,000, at t = 0. The project isexpected to produce after-tax netcash flows of $80,000 for the nextthree years.

    At a 10% discount rate, what is

    Project Ys NPV?0 1 2 3

    -$200,000 80,000 80,000 80,000

    k = 10%

    NPV = -$1,051.84

  • 8/14/2019 Other Topics in Capital Budgeting

    13/21

    12-13

    Abandonment option Project Ys A-T net cash flows

    depend critically upon customer

    acceptance of the product.There is a 60% probability that

    the product will be wildlysuccessful and produce A-T netCFs of $150,000, and a 40%chance it will produce annual A-Tnet CFs of -$25,000.

  • 8/14/2019 Other Topics in Capital Budgeting

    14/21

    12-14

    Abandonment decision

    tree

    If the customer uses the product,

    NPV is $173,027.80. If the customer does not use the product,

    NPV is -$262,171.30. E(NPV) = 0.6(173,027.8) + 0.4(-262,171.3)

    = -1,051.84

    -$200,000

    60% prob.

    40% prob.

    1 2 3Years

    0

    150,000 150,000 150,000

    -25,000 -25,000 -25,000

  • 8/14/2019 Other Topics in Capital Budgeting

    15/21

    12-15

    Issues with abandonment

    optionsThe company does not have the

    option to delay the project.

    The company may abandon theproject after a year, if the customerhas not adopted the product.

    If the project is abandoned, there will

    be no operating costs incurred norcash inflows received after the firstyear.

  • 8/14/2019 Other Topics in Capital Budgeting

    16/21

  • 8/14/2019 Other Topics in Capital Budgeting

    17/21

    12-17

    Is it reasonable to assume thatthe abandonment option does not

    affect the cost of capital? No, it is not reasonable to

    assume that the abandonment

    option has no effect on thecost of capital.

    The abandonment option

    reduces risk, and thereforereduces the cost of capital.

  • 8/14/2019 Other Topics in Capital Budgeting

    18/21

    12-18

    Growth option

    Project Z has an initial up-front cost of$500,000.

    The project is expected to produce A-T cash

    inflows of $100,000 at the end of each of thenext five years. Since the project carries a 12%cost of capital, it clearly has a negative NPV.

    There is a 10% chance the project will lead tosubsequent opportunities that have an NPV of$3,000,000 at t = 5, and a 90% chance of anNPV of -$1,000,000 at t = 5.

  • 8/14/2019 Other Topics in Capital Budgeting

    19/21

    12-19

    NPV with the growthoption

    100,000 100,000 100,000 100,000 100,000

    -$500,000

    10% prob.

    90% prob.

    1 2 3 4 5Years

    0

    100,000 100,000 100,000 100,000 100,000-$1,000,000

    $3,000,000

    At k = 12%, NPV of top branch (10% prob) =

    $1,562,758.19

    NPV of lower branch (90% prob) = -

    $139,522.38

  • 8/14/2019 Other Topics in Capital Budgeting

    20/21

    12-20

    NPV with the growthoption

    If it turns out that the project has futureopportunities with a negative NPV, thecompany would choose not to pursue them.

    Therefore, the NPV of the bottom branchshould include only the -$500,000 initialoutlay and the $100,000 annual cash flows,which lead to an NPV of -$139,522.38.

    Thus, the expected value of this projectshould be:

    NPV = 0.1($1,562,758) + 0.9(-$139,522)

    = $30,706.

  • 8/14/2019 Other Topics in Capital Budgeting

    21/21

    12-21

    Flexibility options

    Flexibility options exist when itsworth spending money today,

    which enables you to maintainflexibility down the road.