osha chemical safety initiatives socma washington, dc december 5, 2007

26

Upload: liliana-bryan

Post on 24-Dec-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007
Page 2: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

OSHA Chemical Safety Initiatives

SOCMA

Washington, DC

December 5, 2007

Page 3: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Fatality/Catastrophe PSM Incidents

4

19

24

18

1311

17 1718

12

3

10

75

0

5

10

15

20

25

FA

T-C

AT

S

1992 1994 1996 1998 2000 2002 2004

From DEP Fatality Study

Page 4: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

What’s Up with OSHA

• Refinery National Emphasis Program (NEP)

• Pilot “Chemical Plant” CPL

• “MOTIVA” Interpretation

– Federal Register Notice

• Combustible Dust NEP

• Guidance

• HAZ Comm/GHS ANPR

Page 5: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

‘Motiva” Interpretation

• 2 Business Units– Refinery– Distribution Terminal

• Interconnection of >>> TQ flammable gas

• Fire During Loading– Driver burned

Refinery Complex

7 Propane Bullets >>> TQ

Interconnected to Distribution Terminal

Truck Distribution Rack

Distribution Terminal

Page 6: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Motiva Background

• Issue of interconnection of flammable materials is key to the enforcement of the PSM standard

• Motiva appealed OSHA PSM citations– Motiva only argued scope/application of standard– OSHA won the case at the ALJ level.

• OSHA then lost case at the OSH Review Commission - Motiva Enterprises, 21 BNA OSHC 1696 (OSHRC No. 02-2160, 2006).

• The Review Commission questioned whether the regulatory text was meant to limit the coverage of the PSM standard to a HHC process, that was both “on-site” and “in one location” as per scope/application of 1910.119.

Page 7: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Motiva Background

• Review Commission decided – Could not determine that the cited activities were "on site" and "in one

location”– Absence of an authoritative interpretation – Vacated the citations.

• The Review Commission recognized– OSHA is the agency responsible for policymaking under the OSH Act– Commission left it to OSHA to decide

• "in the first instance . . . the meaning of these terms and offer an 'authoritative interpretation.'"

• "[a]ny such subsequent interpretation" would be reviewed in a future case "under 'standard deference principles.'"

• FR Notice addresses OSHA’s interpretation of the term “on site in one location” in the scope and application section of the PSM standard

• Bottom Line– Interpretation and application of scope provisions of PSM stays the same– NOTHING has changed – FR Notice reiterated OSHA’s current interpretation

Page 8: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Refinery National Emphasis Program

• OSHA national PSM enforcement program– Program (NEP) for inspecting petroleum refineries

– SIC 2911 and NAICS 324110

• Contains policies and procedures to verify employers’

compliance with OSHA’s PSM standard

• Primary Purpose: Tool for OSHA CSHOs to determine

compliance w/PSM

Page 9: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Why Refinery NEP

• Need for OSHA to conduct programmed inspections at high risk facilities

• FAT/CAT data indicates refineries are good place to start– SIC 2911 experienced 36

FAT/CATS since 1992– Top 4 SICs account for 40% of all

PSM FAT/CATS– Refineries account for 20% of Total– Refinery FAT/CATs > other 3 top

SICs combined

• Recent Refinery Incidents– BP TCR

Refinery FAT/CATSby Most Frequent SIC

178 Total PSM FAT/CAT Incidents

36

12

12

11

SIC 2911 SIC 2899

SIC 2869 SIC 2892

Page 10: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Breakdown of 152 U.S. Refineries

Federal vs. State-Plan Refineries

101

51

Feds States

101 "Federal NEP" Refineries

81

20

To Be Inspected VPP Sites

From EPA RMP Submittals

Page 11: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Distribution of U.S. Refineries by Region

06

8 7

16

69

3

1817

7

0

10

20

30

40

50

60

70

Nu

mb

er o

f R

egio

n R

efin

erie

s

R1 R2 R3 R4 R5 R6 R7 R8 R9 R10

Regions

Page 12: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

NEP Focus Areas

• Prioritize on Implementation versus the existence of documentation– Ensure that employers do what they have committed to do

• RAGAGEP– 119(d)(3)(ii) – “…shall comply with RAGAGEP”– Mostly Equipment

• Vessels, Piping, Relief Systems, Blowdown Systems

• PHA– 119(e)(1) - “…shall identify, evaluate, and control hazards of

process” • Equipment Deficiencies

– 119(j)(5) – fix deficient equipment before further use or take necessary means to assure safe operation until deficiency can be fixed at next opportunity

• Others

Page 13: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

New Inspection Strategy

• Evaluate PSM compliance using Inspection Priority Items (IPI)– Gap Analysis (Yes, No, N/A Questions)– Questions developed in-house

• will work in questions provided by anybody

• List Based IPI– Static List

• 95 Questions• Like all OSHA CPLs, posted on public website

– Dynamic List• 8 to 15 questions/list• Changes every 2 to 6 weeks• “Secret List” for inspection integrity

– Not posted on OSHA’s public website

Page 14: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

So Far….

• NEP launched June 7, 2007

• 16 NEP inspections started/on-going– No inspections have been completed– Therefore, no citations issued to-date

• Early inspections finding many deficiencies– CSHOs going “off-script”

• Many deficiencies found that are not related to IPI• Resulting in longer inspections than originally planned

Page 15: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Some Findings…

• Findings are varied• Some specific deficiencies found

– PHA recommendations not resolved– No car seals for isolation valves on relief discharge lines

• Low hanging fruit

– Piping well below retirement thickness– Facility siting – control room– Facility siting – emergency isolation valves– Relief study recommendations as part of PHA not resolved– Factors contributing to the incident not listed in report– Contractors not included in investigation team when required– MOC documentation not complete for vessel rerate– Design basis for relief system does not exist– LOTO failure to verify deenerization– Contractors hot work practices

Page 16: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

“Chemical Plant” ComplianceDirective

• Need for programmed inspections at high risk chemical facilities

• PSM inspection resources fully deployed conducting NEP

• Pilot Program for Chemical Facilities– Regions with few NEP inspections– 1 year in duration

• Decision near end of NEP to fully deploy Chem CPL

Page 17: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Pilot Chem CPL

• Details TBD• Thoughts

– Targeting Sites to be Inspected• Use RMP Program 3 facilities as main target for

selecting sites for inspection• Add SICs typically covered by PSM which are

not covered by RMP

– Inspection Strategy• Many inspections, shorter duration• Use Dynamic List IPI concept

Page 18: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Combustible Dust NEP

• 280 dust fires and explosions in U.S. industrial facilities – past 25 years– 119 fatalities and over 700 injuries– Per CSB

• National Emphasis Program• Policies and procedures for inspecting

workplaces that create or handle combustible dusts.

Page 19: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Combustible Dust CPL

• CPL 03-00-006– http://www.osha.gov/OshDoc/Directive_pdf/

CPL_03-00-006.pdf

• Issued October 18, 2007

Page 20: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Hazard Communication

• Considering adoption of the Globally Harmonized System of Classification and Labeling of Chemicals (GHS)

• Published an advance notice of proposed rulemaking (ANPR) 9/12/2006

• Accepted comments until 11/13/2006

Page 21: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Hazard Communication

• Other OSHA standards may be affected

• Will likely need to change hazard communication provisions in OSHA’s substance-specific standards to be consistent.

• May also need to address parts of other standards that have criteria for hazard definitions, such as flammable liquids.

Page 22: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Completed Guidance Projects

• Motor vehicle safety

• Combustible dust (SHIB)

• Indoor air (mold)

• Pandemic flu preparedness

• Glutaraldehyde

• Perchloroethylene

Page 23: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Completed Guidance Projects

• Guidance for Hazard Determination (HazCom)

• Motor vehicle safety at marine terminals

• Slings

• Marine terminal crane radio communication

Page 24: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Guidance Projects in Development

• Hazard communication/GHS

• PPE for emergency response

• Reactive chemicals

• Combustible dust poster

• Lockout/tagout checklist

Page 25: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007

Questions

Mike Marshall

202-693-2179

[email protected]

Page 26: OSHA Chemical Safety Initiatives SOCMA Washington, DC December 5, 2007