osbl considerations for refinery expansion projects

Upload: readerrrght

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    1/10

    Page 1 of 10

    Title: OSBL Considerations for Refinery Expansion ProjectsAuthors: Mr. Dominic M. Varraveto, Manager, Burns & McDonnellDate: March 18-20, 2007Presented at: National Petrochemical & Refiners Association Annual Meeting

    ABSTRACT

    As demand for transportation fuel has remained strong despite rising prices and as refinery utilization hovers near

    maximum sustainability interest in refinery expansion projects has increased. Refinery expansion projects can bedivided into two major parts distinguished by the industry as ISBL, Inside Battery Limit and OSBL, Outside Battery

    Limit. The ISBL portion of an expansion project typically focuses on the addition of new or additional process unitsto the existing refinery configuration.

    The OSBL portion of that same project generally consists of all the other necessary supporting elements includingutility systems, interconnecting process and utility piping, feed and product handling and storage etc. In some cases

    OSBL may also include an entire unit for production of a key process reactant such as hydrogen and for safe

    handling and disposal of waste streams and byproducts like sour water and sulfur. Many projects include revamp ofexisting process units as part of OSBL.

    This paper will focus on the OSBL portion of three example refinery expansion projects consisting of 1) replacing

    an existing vacuum distillation unit, 2) adding a new vacuum distillation unit and a new delayed coker and 3) adding

    and integrating a new crude distillation unit, a new delayed coker and a new hydrocracker to a typical FCC based

    gasoline refinery. The intent will be to identify and compare the various OSBL requirements for each exampleexpansion project and to discuss guidelines for improving the accuracy of the OSBL definition early in project

    development.

    INTRODUCTION

    A meaningful discourse about OSBL considerations for a refinery project and more specifically, an expansion project

    relies on a clear definition of what is and what is not meant by outside battery limits or OSBL. This term does not

    have a universally accepted definition. For different entities in the same organization the OSBL portion of a project

    often varies, especially during initial project conception and often, even further into project development. The same

    lack of a common definition can be said to be true between organizations, for example, between owner and

    engineering/construction contractor. The first section of this paper discusses how the entire scope of a refinery projectcan be split between ISBL and OSBL and how the OSBL portion can be divided further into subcategories according to

    the nature of the work.

    The second section of this paper discusses recent refinery projects and how the nature of these projects is affected by

    several factors including return on investment in the refining industry, growth in demand for refined products, access to

    crude supplies and impact of environmental compliance. Recently, solid operating margins and continuedprofitability has allowed refinery owners to come out of the latest round of environmental spending for Low Sulfur

    Gasoline, LSG, and Ultra Low Sulfur Diesel, ULSD, with an increased appetite for additional refinery investment

    changing the fundamental nature of the typical refinery expansion project.

    The third part of this paper looks at the OSBL portion of three recent refinery expansion projects: 1) Vacuum Unit,VAC replacement, 2) Addition of a Vacuum Unit coupled with a new Delayed Coker Unit, VAC/DCU, and 3)

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    2/10

    Page 2 of 10

    Addition of new Crude Distillation Unit, new Delayed Coker and new Hydrocracker, CDU/DCU/HDC. Theseexamples will describe increased OSBL scope corresponding to the recent and larger refinery expansion projectscurrently underway in the refining industry.

    The final section of this paper suggests guidelines and practices for improving the accuracy of the OSBL definition

    earlier in the project development effort. An accurate and reliable OSBL definition has become essential since the

    OSBL portion of an expansion project is no longer insignificant relative to ISBL and because the size of todays

    expansion project is now truly deserving of the title Major Project.

    DEFINITIONOFOSBL

    A somewhat overly simplistic definition of OSBL relative to refinery expansion projects is all aspects that are not

    included in the ISBL portion of the project. In other words OSBL is everything else including scope that was

    unexpected and unplanned for during initial project development. By this definition OSBL will be incompletelydefined until it presumably can be defined in latter stages of the development process. A more specific way to define

    OSBL is to initially attempt to identify what everything else includes as early in the project as possible and practical.

    OSBL will include more than interconnecting piping and pipe racks. Also included is infrastructure, secondary process

    units, revamps to existing process units and financial costs like interest and taxes etc. Infrastructure includes not onlyutility system equipment but also roads, rail spurs, docks, loading and unloading equipment, buildings (warehouse,

    power house, control room, office buildings etc).1 Table No. 1 below lists classifications which can be used to

    differentiate OSBL scope and summarizes the items included in each category.

    Table No. 1: OSBL Classifications

    Classification Description

    Interconnecting Systems Pipe/Pipe Rack, Power, Controls

    Infrastructure Utility System Equipment, Roads, Tanks,Truck and/or Rail Feed and Product

    Unloading/Loading, Buildings

    Secondary Process Units WWTP (Waste Water Treatment Plant),

    ARU (Amine Regen Unit), SWS (SourWater Stripper), SRU (Sulfur Recovery

    Unit), TGTU (Tail Gas Treating Unit),

    SMR (Hydrogen), Air Separation

    Revamp of Existing Units Increase Throughput and/or Conversion

    Financial Owners Cost, Start Up, Working Capital,

    Interest, Taxes

    Other Land, Permits, Fees

    Infrastructure is very general and can be further categorized by considering process equipment to supply typical utilitieslike steam, water (boiler feed, cooling) air (instrument and plant), fuel (natural gas, and refinery fuel gas) power

    (electric) etc. Table No. 2 lists the equipment frequently associated with some of the more common OSBL

    infrastructure.

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    3/10

    Page 3 of 10

    Table No. 2: Examples of OSBL Equipment for Utility Infrastructure

    Utility System Equipment

    Steam Boiler Deaerator, Boiler, Circulation Pumps

    Water Boiler Feed Filters, Ion Exchange, Chemical Treatment, RO

    Membrane, Preheat Exchangers, Pumps, Tanks

    Water Cooling Cooling Tower, Circulation Pumps, Chemical

    Treatment

    Air Instrument/Plant Compressor, Intercooler, Drier

    Fuel Fuel Gas Conditioning Mix Drum, Condenser, Liquid KO drum,Filter/Coalescer, Preheater, Strainer(s)

    Power Electric Transformers, power distribution

    Additional utility systems, not shown in Table No. 2 above, which may require equipment for reliable supply mayinclude nitrogen, potable water, utility water, fire water etc.

    Infrastructure also includes systems and associated equipment to handle return streams and wastes. For refinery

    units these systems include steam condensate collection/return flares, sewers etc. Table No. 3 lists equipment

    associated with these systems.

    Table No. 3: Examples of OSBL Equipment for Waste Streams

    Utility System Equipment

    Excess Vapor/Overpressure

    Protection

    Flare Flare Header, KO Drum/Pump, Flare,

    Flare Gas Recovery Compressor

    Sewer Process Sump, CPI (Corrugated Plate

    Interceptor for Oil Removal),Pump(s), Slop Oil Tank

    Sewer Storm Sump Pump(s), Tank or Pond

    Condensate Steam Collection Drum, Pump(s), Tank

    Some utility systems like sewers will require waste water treatment which should be considered in the OSBLclassification of secondary or supporting process units. Essential secondary process units in todays refinery for treating

    waste include a Waste Water Treatment Plant, WWTP and Sulfur Recovery Facilities usually comprised of Sour Water

    Stripper, SWS, Amine Regeneration Unit, ARU, Sulfur Recovery Unit, SRU and Tail Gas Treating Unit, TGTU. TheSWS and ARU process liquid streams, removing hydrogen sulfide, H2S, and ammonia, NH3, so the liquid streams can

    be re-used (i.e. lean amine) or processed further and discharged (i.e. stripped sour water).

    The SRU/TGTU processes the concentrated sour gases from the SWS and ARU producing molten sulfur byproduct

    and dischargeable vent gas. Other process units that might be included in OSBL secondary process units includefacilities to produce a key reactant for a primary process unit. Examples are a Steam/Methane Reformer, SMR,

    producing hydrogen for a Hydrotreater or Hydrocracker and an Air Separation plant producing Oxygen for Sulfur Plant

    Oxygen Enrichment or for petroleum coke gasification.

    Factors Affecting Refinery Expansion Projects Until very recently it has been difficult for refiners to attract investment

    capital both from internal as well as external sources. Some reasons for this have been low return on investment due to

    poor margins, surplus capacity and environmental regulation. In that kind of economic environment, limited capitalwas primarily appropriated for environmental compliance to remain viable. Investment for economic benefit i.e.

    profitability, was limited or non-existent. However, through creative and clever improvement of existing facilities

    some refiners conceived and executed low cost projects that had significant bottom line impact. These projects were

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    4/10

    Page 4 of 10

    usually characterized by step wise debottlenecking over several years that resulted in overall increase in refinerythroughput and/or conversion. These types of projects were typically completed in conjunction with regularlyscheduled maintenance turnarounds and did not involve addition of new process units or improvement to existing

    infrastructure. The OSBL portion of these projects was small or nearly insignificant.

    For a time this approach was adequate to keep pace with growing demand. However, during this same time period

    many refineries, especially smaller less complex facilities were forced to close. Closings have been accelerated by thecost of environmental compliance both to manufacture LSG and ULSD and to reduce air and water pollution

    originating in refineries. Over the same period, growth in demand for transportation fuel increased steadily as the

    number of passenger vehicles as a percent of the US fleet has declined and the number of light trucks and sport utility

    vehicles as percent of the US fleet has increased.

    Eventually the combination of growing demand and loss of capacity from refinery closings has exceeded increased

    output from incremental debottlenecking and created a much more balanced, or, some would say, precarious market forrefined transportation fuel. Margins and profitability have improved dramatically especially for refiners capable of

    processing heavier, higher sulfur crude oil. With the bulk of the large environmental expenditures already made, at least

    for the near to mid term (3 to 5 years), there is an increasing appetite for relatively large expansion projects. These

    larger expansion projects are now characterized by significant capacity increases of 50 to 100%. In some instances this

    involves a second parallel processing train with new infrastructure and secondary process units. The OSBL portion forthese projects is a significant percentage of the overall project cost.

    The three example projects in the next section will illustrate how the OSBL content has increased as refinery expansionprojects have evolved from incremental de-bottlenecking to significant capacity growth.

    EXAMPLES OF RECENT REFINERY EXPANSION PROJECTS

    Example No. 1: Vacuum Unit, VAC, replacement

    This project involved replacing the existing vacuum unit furnace, vacuum fractionation tower, overhead ejector system,

    Heavy Vacuum Gas Oil, HVGO, pumps and Wash Oil pumps, addition of new HVGO vs. Crude heat exchangers as

    well as modifications to the existing Crude preheat system, HVGO heat removal system, vacuum unit charge pumpsand crude and vacuum section heat integration. The project positioned the refinery for greater flexibility in crude feed

    selection allowing heavier crudes with higher percentages of gas oil to be processed. The increased gas oil filled excessFCC capacity. The scope and other details of the project can be found in reference 2.

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    5/10

    Figure No. 1: VAC Replacement

    The OSBL for this project was limited and was not identified separately from the ISBL as described. By definition

    VAC replacement excluded revamp work to existing process units. Spare FCC capacity already existed and the

    design basis defined the heavier crude such that the gas oil content increased but the residual content (i.e. DCU feed)would not increase as a result of the project. Replacement of portions of the HVGO product line to and around the

    Gas Oil Hydrotreater processing FCC feed was the only significant OSBL work. The HVGO piping replacement

    was less than 5% of the overall project and all the OSBL work was less than about 10% of the overall project.

    Example No. 2: New Vacuum Unit and New Delayed Coker, VAC/DCU

    Reconfiguring an existing refinery to process heavier crude and meet Clean Fuel requirements was achieved in this

    project by adding a new Vacuum unit and a new Delayed Coker. Revamp of at least 11 existing process units waspart of the OSBL scope including converting an existing residual oil desulfurizer to a gas oil hydrotreater, a shift in

    FCC conversion to higher gasoline yield, upgrade of the light ends fractionation and treating areas and modification

    of two distillate hydrotreaters for ULSD production. In addition, the OSBL scope included upgrade and expansionof the refinery Amine Circulation and Treating, Sour Water collection and Hydrogen distribution. A new Hydrogen

    plant was also included in the OSBL scope.

    Page 5 of 10

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    6/10

    By far the largest parts of the OSBL scope were 2 miles of pipe rack, the corresponding interconnecting process andutility piping and over 500 tie-ins needed to install and support the pipe. There were many project specificrequirements including extensive application of heat tracing, both steam and electrical, to new and existing

    interconnecting pipe. The introduction of new intermediate process streams from the DCU required a significant

    modification to existing tankage. These modifications vary for each stream but included new gas blanketing, a new

    floating roof, recommissioning of an existing tank heater, new insulation, new heat tracing, and addition of water

    draw collection, piping manifolds and pumps.

    Overall, the OSBL was slightly above 30% of the total project cost. The revamps comprised about one third or 10%

    and the interconnecting piping and tankage modifications were about two thirds or 20% of the total project cost.

    Other than tankage, the OSBL for this example project did not have a very significant infrastructure component.This is somewhat unexpected considering the size and impact on the configuration of the refinery. Some possible

    reasons for this relatively small infrastructure requirement were some of the typical OSBL infrastructure like the

    coke handling facilities was included in the DCU ISBL and the expansion project was based on a shift to lower

    cost crude and increased conversion rather than an increase in throughput.

    Figure No. 2: New VAC/DCU

    Page 6 of 10

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    7/10

    Example No. 3 - New Crude Distillation Unit, New Delayed Coker and New Hydrocracker, CDU/DCU/HDC.

    This example involves the most extensive project of the three presented in that it combines a greater than 50% increase

    in throughput with an increase in conversion for processing a significantly heavier and higher sulfur crude. In fact the

    sulfur recovered from the refinery will increase by nearly an order magnitude as a result of this project.

    Like the previous example this project involves a new VAC unit and a new DCU. In this example the new VAC is partof an entirely new Crude Distillation Unit, CDU. The differences end there since this project also includes a Gas Oil

    Hydrocracker which removes a significant amount of sulfur and converts a significant portion of gas oil producing

    distillate that meets ultra low Clean Fuels requirements and also produces a hydrotreated FCC feed stream. Applying

    the definition of established earlier, the OSBL will include interconnecting pipe, pipe racks, electric power supply anddistribution, infrastructure, secondary process units, and revamps. The flow sketch in Figure No. 3 shows the major

    aspects of the ISBL portion for this example. Not shown in this figure are all the new secondary process units. These

    new facilities are part of the OSBL and include Hydrogen Production, Sour Water Collection and Processing, Amine

    Circulation and Regeneration, Sulfur Recovery, Tail Gas Treating and Waste Water Treatment.

    Figure No. 3

    There are also a significant number of revamps associated with this example that will be part of the OSBL portion of

    the project. They include upgrading the existing crude unit to process heavier crude, modifying the FCC for higher rate

    and shift in yield, expanding the existing DHT for increased throughput and higher feed sulfur, increasing throughput

    Page 7 of 10

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    8/10

    Page 8 of 10

    and adding the capability to process DCU Naphtha in the Naphtha Hydrotreater, NHT, and Reformer and expandingthe light ends treating, fractionation and processing in the Alkylation and Polymerization, ALKY/POLY area. Adetailed listing of the OSBL scope for this project in comparison to the other examples is shown in Table No. 4.

    Table No. 4: OSBL Content Comparison of Example Projects

    OSBL

    Classification

    Example No.1

    VAC

    Example No. 2

    VAC/DCU

    Example No.3

    VAC/DCU/HDC

    Interconnecting

    Systems

    HVGO Piping Process and utility

    Piping/Racks

    Pipe/Pipe Racks, Power,

    Controls

    Infrastructure None Utility System

    Equipment

    (Insignificant)

    Utility System

    Equipment,

    Roads, Tanks, Truck

    and Rail ProductLoading, Buildings

    Secondary Process Units None SMR (Hydrogen)ARU and SWS

    WWTP, ARU/SWS,SRU/TGTU, SMR

    (Hydrogen)

    Revamp of

    Existing Units

    None Resid HDS to Gas Oil

    Feed HDT, 2 DHTs, 2FCCs, LPG treating &

    Fractionation, Amine,

    SWS

    NHDS, DHDS, LPG

    fractionation

    Financial Owners Cost, Start Up,

    Working Capital,

    Interest, Taxes

    Same items as VAC Same items as VAC

    Other Demolition, Permits,

    Fees

    Same items as VAC Same items as VAC

    MEETING OSBL EXPECTATIONS DURING PROJECT DEVELOPMENT

    This section will discuss possible reasons Why the OSBL costs of Refinery Expansion projects consistently exceedexpectations by large margins and provide recommendations for improving OSBL definition quality.

    There are many possible reasons that can cause the OSBL part of a refinery expansion project to exceed expectations.Taken in combination the difference between expectations and actual outcome will be significant. Some of these

    reasons are listed below in Table No. 5. They include factors that affect both definition and pricing of the OSBL scope.

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    9/10

    Page 9 of 10

    Table No. 5: Why Expansion OSBL Does Not Meet Expectations

    No. Reason Impacts

    Definition Pricing

    1. Unfamiliarity with size and complexity of evolving expansion

    projects.

    X

    2. Inadequacy of time and resources allocated for OSBL

    development.

    X X

    3. Overly optimistic about extra capacity in existing infrastructure for

    expansion needs.

    X

    4. Failure to properly account for site specific issues like soil, climate,

    plant layout etc.

    X

    5. Use of factors instead of current pricing to predict costs. X

    6. Unrealistic allowance for escalation, contingency etc. X

    The three examples discussed in the previous section illustrate why many may be unfamiliar with the size and

    complexity of evolving refinery expansion projects. Until recently expansion project scope was limited to revamp of a

    single existing unit with very limited OSBL/Infrastructure content like Example No. 1. The goal for this type of project

    was primarily to reduce raw material cost and improve operating margin with less emphasis on large increases inthroughput and product volume. The more recent, larger projects combine very large increases in through put coupled

    with a significant shift in crude feed gravity and sulfur content. These projects are relatively recent and present a steep

    learning curve to the inexperienced. Assembling an experienced project team and planning and organizing a disciplined

    project development effort are essential first steps for better meeting project expectations.

    Some might say it is somewhat foolhardy to estimate OSBL/Infrastructure cost too early in project development1.

    On the other hand more time is required to successfully define a large, complex project. Much of the early activity will

    not require cost estimating. Early activity should focus on gaining a realistic understanding of the capacity of existinginfrastructure to support additional load and what must be included in the scope to meet site specific needs. If

    necessary, elements of the existing infrastructure should be inspected and tested while in service to prove suitability

    and capacity. Determining availability of open space, the extent of demolition and site clearing and relative location of

    ISBL, OSBL and Infrastructure is crucial.

    OSBL development should be started early even while ISBL is still being developed. Initial site specific OSBL andInfrastructure scope can be developed early using similar or go by ISBL designs. Utilities and infrastructure needs

    can also be determined from the go by designs using scaling factors. The scaling factors can be validated later in the

    development when a firm ISBL definition emerges. Develop site specific OSBL and Infrastructure Scope taking into

    account relative location of

    ISBL and Infrastructure.Conceptual cost estimating for refineries and chemical plants is typically done by applying installation cost factors to

    sized equipment.3 While this technique has proven successful for the ISBL portion of projects, it is less than

    satisfactory for OSBL, especially projects containing a relatively large interconnecting pipe and pipe rack component.For this type of OSBL scope, using technical deliverables like preliminary layouts, pipe/rack routing, electrical onelines etc to produce material take offs is a much more reliable method for costing the non-equipment component of

    OSBL. Where significant equipment based infrastructure is needed installation cost factors can be used.

    The scope definition should be checked by comparison against other similar projects. Adjustments for differences

    related to variation between projects due to site and project specific characteristics should be taken into account when

    making the comparison. In addition, the use of project development checklists specific to each project phase and rating

    tools to quantitatively assess the completeness of the scope definition should be included near the end of each project

    phase in the development process. Finally, given the evolution of refinery expansion projects from small to large and

  • 8/12/2019 OSBl Considerations for Refinery Expansion Projects

    10/10