Organics Waste Processing Facility Construction Progress Update May 12, 2011. Organics Waste Processing Facility Construction Progress Update May 12, 2011. Cast in place of process pipes in tunnel . Organics Waste Processing Facility Construction Progress Update May 12, 2011. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Page 2: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Cast in place of process pipes in tunnel

Page 3: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

156ft high Biofilter Exhaust delivery

Page 4: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Installed Biofilter Exhaust stack

Page 5: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Catch basin installation west of Maturation Building

Page 6: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Drywall installation in Ground Floor offices of Administration Building

Page 7: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Site Overview looking South

Page 8: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Inside of Blower Room

Page 9: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

Inside of Blower Room (view from west side)

Page 10: Organics Waste Processing Facility Construction Progress Update May 12, 2011

Organics Waste Processing Facility Construction Progress Update

May 12, 2011

View of tip floor, transfer area and tunnels