or case 8
TRANSCRIPT
![Page 1: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/1.jpg)
INTRODUCTIONThis case is concerned with the topic Simulation. Simulation is one of the most widely used
techniques in OR. It is used in all types of business decision making which covers all the
functional areas. Due to its flexibility, power and intuitive approach its popularity is growing
rapidly, with the increase in availability of computer power. Simulation is performed frequently
for risk analysis, project management, resource planning etc. Simulation is widely used for
systems which involves continuous decision making for a long time.
Facts of the Case1. Carl Schilling is the foreman of a large manufacturing firm which manufactures castings
through planer machines.2. Carl is called by the management to give solution for the problem they are facing. The
planer department is a problem. They cannot match the output with the workload. Work pieces were stuck up for want of free planner. This had disrupted the production schedule of next in line processes which increased the WIP costs and idle time costs which resulted into loss of production.
3. This meeting with the management helped Carl to sort out the major problems which he could see. He wanted a new planner so that bottlenecks could be eased. At one point of time there is a possibility that there would be overload and bottlenecks may occur and on the other hand the machines remain idle. Therefore Carl wanted to have uniform flow of work.
Given Information1. Company has 2 planers for cutting flat smooth surfaces in castings.2. The planers are used for 2 purposes:a. To make top surface of platen for large hydraulic lifts.b. To form mating surface of final drive housing for a large piece of earth moving
equipment.3. For each platen, the time required by a planer has an Erlang distribution with a mean of 25
minutes and shape parameter (k) as 4.4. For each housing the time required has an exponential distribution of minimum time of 10
minutes.5. The castings of both types arrive at one time.6. Casting for platens arrive randomly with mean rate of 2 per hour.7. Casting for housing have a uniform inter arrival time distributed in the time range of 20 to
40 minutes.
![Page 2: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/2.jpg)
8. Estimated costs are:a. Platen casting cost = $200b. Housing casting cost = $100
9. All castings reserved on the FCFS basis.
To evaluate/find/ recommend1. Acquire additional planer whose total incremental cost is $30 per hour.2. Eliminate variability in inter arrival times of platen castings with castings arriving at
uniform manner of one every 30 minutes. Incremental cost = $40 per hour.3. Eliminate variability in inter arrival times of housing castings with castings arriving at
uniform manner of one every 30 minutes. Incremental cost = $20 per hour.4. To evaluate and recommend best solution.
Assumptions Here I have assumed that the manufacturing plant starts its operations at 8.00 AM and ends at 4.00 PM. The complete day schedule is broken in 4 shifts of 2 hours each; and I am considering the first shift from: 8.00 AM to 10.00 AM.
Solution I have found random numbers with the help of Excel function = rand ().
0.036565
0.577524
0.134957
0.196681 0.37766
0.072979
0.738164
0.970452
0.906679
0.031117
0.900105 0.34588
0.063045
0.730949
0.424865
0.968318
0.410758 0.1858
0.603859
0.299077
0.230593
0.439609
0.852662
0.467995
0.924451
0.049473 0.74776
0.384825
0.940334
0.502012
0.104424
0.112969
0.816350.91279
80.72655
60.22311
90.20360
50.42294
60.54554
90.24941
40.65270
50.39447
60.42507
20.86062
50.26698
30.19009
8 0.133440.66186
70.91268
1 0.279310.14292
50.52002
80.71021
90.63644
10.99463
30.28343
80.81187
20.43784
60.68051
60.25378
70.40187
40.85090
10.21385
70.31941
70.31095
10.50243
80.50648
30.91905
30.73772
40.88108
80.13433
10.31945
70.64124
10.49498
2 0.652320.31841
30.53548
30.77471
60.92609
10.13614
30.36575
20.12366
30.85974
20.09045
40.55259
10.28384
20.96668
80.53357
40.63594 0.65369 0.77838 0.97132 0.87239 0.67358 0.06782 0.13165
![Page 3: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/3.jpg)
3 8 3 3 6 10.54986
90.92004
60.86347
80.64185
60.23046
70.72299
10.43344
7 0.443460.05901
10.72311
10.05183
20.93670
10.70796
90.41476
50.80812
50.32869
10.63269
20.71934
10.14647
50.12974
70.64861
80.74395
80.10381
90.71748
40.32241
80.18816
50.98660
60.18883
50.30498
80.50209
8 0.701330.22502
90.27262
60.66372
20.36871
6 0.038930.67763
50.80326
6 0.01190.55858
40.08133
60.30492
70.67033
90.22652
80.53570
70.08345
80.21953
60.23675
80.98777
70.40171
20.64055
90.23682
60.24186
60.64600
50.52060
20.27433
80.78943
90.45746
40.20844
70.78045
4 0.762120.78521
80.33856
30.23835
60.98248
90.99884
60.54989
10.43570
10.94980
60.93097
70.06071
90.73009
80.49748
20.35367
10.75271
40.94246
60.30312
30.80392
10.00430
70.88612
90.67426
30.02882
80.79231
3 0.867490.71864
90.05268
70.51134
80.23335
50.13710
1 0.817890.01639
70.84520
80.85852
10.67681
20.71739
10.65129
40.52088
50.72643
20.30648
90.57974
9 0.511960.31680
90.54301
30.52587
7 Now as there are two machines which do the required job, I have assigned one machine for Platen casting and the other machine for Housing casting. Platen Casting: - Arrivals:- The arrivals for platen casting at the planer machine are random (given) Hence the formula for calculating these random arrivals
t= ln (Rn )− λ
. Where ln = log, Rn = random number.
Here, lambda (λ) = 2 per hour (given); and
All the values are given in minutes, hence I have multiply the equation with 60 as in 1hr = 60
minutes.
Hence, using the above formula I got following values
Serial random Time time Arrival
number number (in minutes) (round off) (clock time)8.00 am
1 0.0366 43.09 43 8.43 am2 0.4108 11.59 12 8.55 am3 0.3110 15.21 15 9.10 am4 0.3658 13.10 13 9.23 am5 0.0590 36.87 37 10.00 am
![Page 4: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/4.jpg)
Platen Casting: - Service:- The service rate for platen casting has Erlang distribution with mean (µ) = 25 and k = 4... (Given) Hence we can say that, µ = 1/25 = 0.04 and k = 4. Now the formula for finding service time for platen castings is –
t = ln∏i=1
k
Rn
−K μ
As the constant parameter k = 4, we shall take 4 random numbers for ln (Rn) value.
Hence, using the above formula I got following values
Housing Casting: - Arrivals:-
π(Rn)service Rounded
random numbers(Rn1*Rn2*Rn3*Rn4) time(min) off(min)0.6327 0.3224 0.2726 0.9878 0.0553 7.85 80.7894 0.9825 0.4975 0.6743 0.2602 3.54 40.5775 0.1858 0.9128 0.3945 0.0394 8.77 90.2793 0.4378 0.5024 0.4950 0.0304 9.48 90.1237 0.6537 0.9200 0.7231 0.0538 7.93 100.7193 0.1882 0.6637 0.3049 0.0274 9.76 100.4017 0.4575 0.9988 0.3537 0.0645 7.44 70.1350 0.9001 0.6039 0.7478 0.0549 7.87 80.7266 0.4251 0.1429 0.6805 0.0300 9.51 100.5065 0.6523 0.8597 0.7784 0.2210 4.09 40.1465 0.9866 0.3687 0.6703 0.0358 9.03 90.6406 0.2084 0.5499 0.7527 0.0552 7.86 80.2231 0.8606 0.5200 0.2538 0.0254 10.32 100.9191 0.3184 0.9713 0.6419 0.1824 4.62 50.2265 0.2368 0.7805 0.4357 0.0124 11.91 12
![Page 5: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/5.jpg)
The inter arrival time is uniformly distributed time between 20 to 40 minutes (given)
Now the formula to find the arrivals of housing castings, we use the following formula –
t = a + (b – a) Rn, where, a = 20 min (least time taken) and b 40 min (max time taken).
Hence, (b-a) = 20.
Random Time Round off TimeNumber (min) (min) (clock)
8.00 am0.0813 21.62 22 8.22 am0.0311 20.62 21 8.43 am0.0495 20.99 21 9.04 am0.0288 20.57 20 9.24 am0.0518 21.03 21 9.45 am
Housing Casting: - Service:-
And the service rate is exponentially distributed with a mean of 10 minutes (given)
The formula for finding the service rate of housing castings is –
t = 10 + ln(Rn)−λ
, where λ = 1/10 = 0.1
Random Time Round offNumber (minutes) (minutes)0.9425 10.25 100.8675 10.61 110.8452 10.73 110.5797 12.37 120.3777 14.23 140.0630 22.00 220.2306 16.37 160.9403 10.27 100.2036 16.91 17
The current situation at the plant where Carl Schilling works is: -
PARTICULARS
ARRIVAL SERVICE ARRIVAL
SERVICE ARRIVAL SERVICE WAITING IDLE IDLE
TIME TIME TIME @ TIME @ TIME @ TIME @ TIME TIME @ TIME @PLANER
1PLANER
1PLANER
2PLANER
2 PLANER 1PLANER
2Housing 8.22 am 10 8.22 am 8.32 am 22Platen 8.43 am 8 8.43 am 8.51 am 43
![Page 6: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/6.jpg)
Housing 8.43 am 11 8.43 am 8.54 am 11Platen 8.55 am 4 8.55 am 8.59 am 4
Housing 9.04 am 11 9.04 am 9.15 am 10Platen 9.10 am 9 9.10 am 9.19 am 11Platen 9.23 am 9 9.23 am 9.32 am 4
Housing 9.24 am 12 9.24 am 9.36 am 9Housing 9.45 am 14 9.45 am 9.59 am 9
Platen10.00
am 1010.00
am10.10
am 28TOTAL 0 61 90
Thus, the present condition of the work done is:-
1. Idle time on Planer Machine 1 is 61 minutes = 1 hour and 1 minute.2. Idle time on Planer Machine 2 is 90 minutes = 1 hour and 30 minutes.
Now for the convenience, I have used the following abbreviations: -
For Proposal No. 1 I have assumed that machine 3 would be used alternatively for housing as well as planer castings. Incremental cost = $ 30 per hour (given)
P AL-TE SE-TE
AL-TE
(M 1)
SE-TE (M 1)
AL-TE (M 2)
SE-TE (M 2)
AL-TE
(M 3)
SE-TE (M 3)
WTG-TE
IDL-TE (M
IDL-TE
(M2
IDL-TE
(M3
P = PARTICULARSP C = PLATEN CASTINGH C = HOUSING CASTING
AL-TE = ARRIVAL TIMESE-TE = SERVICE TIME
AL-TE (M 1) = ARRIVAL TIME AT PLANER MACHINE 1SE-TE (M 1) = SERVICE TIME AT PLANER MACHINE 1AL-TE (M 2) = ARRIVAL TIME AT PLANER MACHINE 2SE-TE (M 2) = SERVICE TIME AT PLANER MACHINE 2AL-TE (M 3) = ARRIVAL TIME AT PLANER MACHINE 3SE-TE (M 3) = SERVICE TIME AT PLANER MACHINE 3
WTG-TE = WATING TIME FOR PLANER MACHINESIDL-TE (M 1) = IDLE TIME FOR PLANER MACHINE 1IDL-TE (M2) = IDLE TIME FOR PLANER MACHINE 2IDL-TE (M3) = IDLE TIME FOR PLANER MACHINE 3
![Page 7: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/7.jpg)
1) ) )HC
8.22 am 10
8.22 am
8.32 am 22
PC
8.43 am 8
8.43 am
8.51 am 43
HC
8.43 am 11
8.43 am
8.54 am 11
PC
8.55 am 4
8.55 am
8.59 am 4
HC
9.04 am 11
9.04 am
9.15 am 10
PC
9.10 am 9
9.10 am
9.19 am 11
PC
9.23 am 9
9.23 am
9.32 am 83
HC
9.24 am 12
9.24 am
9.36 am 9
HC
9.45 am 14
9.45 am
9.59 am 13
PC
10.00 am 10
10.00 am
10.10 am 41
TOTA
L 0 52 99 96 As seen earlier, there was a lot of waiting time on machines 1 and 2, the introduction of additional machine will further increase the idle time as well as additional cost of $ 60 per 1 hour 36 minutes of idle time on machine 3.
For Proposal No. 2 – If platens arrive at uniform rate of one every 30 minutes (given) Then the service rate also should be uniform (assumed) Hence, the service rate would be 1 every 15 minutes (assumed) Incremental cost = $ 40 per hour (given)
PARTICULARS ARRIVAL SERVICE ARRIVAL SERVICE ARRIVAL SERVICE WAITING IDLE IDLE
TIME TIME TIME @ TIME @ TIME @ TIME @ TIME TIME @ TIME @
PLANER 1 PLANER 1PLANER
2PLANER
2PLANER
1PLANER
2PLATEN 8.00 AM 15 8.00 AM 8.15 AM 0
HOUSING 8.22 AM 10 8.22 AM 8.32 AM 22PLATEN 8.30 AM 15 8.30 AM 8.45 AM 15
HOUSING 8.43 AM 11 8.43 AM 8.54 AM 11
![Page 8: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/8.jpg)
PLATEN 9.00 AM 15 9.00 AM 9.15 AM 15HOUSING 9.04 AM 11 9.04 AM 9.15 AM 10HOUSING 9.24 AM 12 9.24 AM 9.36 AM 9PLATEN 9.30 AM 15 9.30 AM 9.45 AM 15
HOUSING 9.45 AM 14 9.45 AM 9.59 AM 9PLATEN 10.00 AM 15 10.00 AM 10.15 AM 15
TOTAL 0 60 61 Hence from the above table we can see that a uniform arrival of platen castings, reduces the idle time by 30 minutes. And the incremental cost remains at $ 40.
For Proposal No. 3 – If housings arrive at a uniform rate of one every 30 minutes (given) Then the service rate also should be uniform (assumed) Hence, the service rate for housing castings would one every 45 minutes (assumed)
PARTICULARSARRIVA
L SERVICE ARRIVAL SERVICE ARRIVAL SERVICE WAITING IDLE IDLETIME TIME TIME @ TIME @ TIME @ TIME @ TIME TIME @ TIME @
PLANER 1
PLANER 1
PLANER 2
PLANER 2
PLANER 1
PLANER 2
Housing 8.00 am 45 8.00 am 8.45 am 0Platen 8.43 am 8 8.43 am 8.51 am 43
Housing 8.30 am 45 8.30 am 9.15 am 15Platen 8.55 am 4 8.55 am 8.59 am 4
Housing 9.00 am 45 9.00 am 9.45 am 15Platen 9.10 am 9 9.10 am 9.19 am 11Platen 9.23 am 9 9.23 am 9.32 am 4
Housing 9.30 am 45 9.30 am10.15
am 15
Platen10. 00
am 1010.00
am10.10
am 28TOTAL 45 0 90
![Page 9: or case 8](https://reader036.vdocuments.us/reader036/viewer/2022082409/577cc9de1a28aba711a4cbd9/html5/thumbnails/9.jpg)
Hence, In this case, the waiting time is 45 minutes for housing castings, which makes the whole process to stretch. The idle time for planer number 2 is 90 minutes which is 1 and ½ hours whose cost comes as $ 40.
Conclusion Hence from the above calculations, I want to conclude that Proposal Number 2 can be accepted.