1 Name: Ayenigba Sogo Emmanuel Department: Civil Engineering Matric Number: 08/30GB096 Course: CVE657 (Operational research techniques) Assignment 1.0 What is Operations research? Operations research (OR), or operational research in British usage, is a discipline that deals with the application of advanced analytical methods to help make better decisions. It employs techniques from other mathematical sciences, such as mathematical modelling, statistical analysis and mathematical optimization. It arrives at optimal or near-optimal solutions to complex decision- making problems. Operations research attempts to provide those who manage organized systems with an objective and quantitative basis for decision; it is normally carried out by teams of scientists and engineers drawn from a variety of disciplines. Thus, operations research is not a science itself but rather the application of science to the solution of managerial and administrative problems, and it focuses on the performance of organized systems taken as a whole rather than on their parts taken separately. 1.1 Terminologies Operations The activities carried out in an organization related to attaining its goals and objectives. Research The process of observation and testing characterized by the scientific method. The steps of the process include observing the situation and formulating a problem statement, constructing a mathematical model, hypothesizing that the model represents the important aspects of the situation, and validating the model through experimentation. Organization The society in which the problem arises or for which the solution is important. The organization may be a corporation, a branch of government, a department within a firm, a group of employees, or perhaps even a household or individual. Decision maker An individual or group in the organization capable of proposing and implementing necessary actions. Analyst An individual called upon to aid the decision maker in the problem solving process. The analyst typically has special skills in modeling, mathematics, data gathering, and computer implementation. Team A group of individuals bringing various skills and viewpoints to a problem. Historically, operations research has used the team approach in order that the solution not be limited by past experience or too narrow a focus. A team also provides the collection of specialized skills that are rarely found in a single individual. Model An abstract representation of reality. As used here, a representation of a decision problem related to the operations of the organization. The model is usually presented in mathematical terms and includes a statement of the assumptions used in the functional relationships. Models can also be physical, narrative, or a set of rules embodied in a computer program. Systems approach An approach to analysis that attempts to ascertain and include the broad implications of decisions for the organization. Both quantitative and qualitative factors are included in the analysis.

Upload: ayenigba-sogo-emmanuel

Post on 27-Sep-2015

220 views

Category:

Documents


1 download

DESCRIPTION

Operations research assignment

TRANSCRIPT

  • 1

    Name: Ayenigba Sogo Emmanuel

    Department: Civil Engineering

    Matric Number: 08/30GB096

    Course: CVE657 (Operational research techniques) Assignment

    1.0 What is Operations research?

    Operations research (OR), or operational research in British usage, is a discipline that deals with the

    application of advanced analytical methods to help make better decisions. It employs techniques

    from other mathematical sciences, such as mathematical modelling, statistical analysis and

    mathematical optimization. It arrives at optimal or near-optimal solutions to complex decision-

    making problems. Operations research attempts to provide those who manage organized systems

    with an objective and quantitative basis for decision; it is normally carried out by teams of scientists

    and engineers drawn from a variety of disciplines. Thus, operations research is not a science itself

    but rather the application of science to the solution of managerial and administrative problems, and

    it focuses on the performance of organized systems taken as a whole rather than on their parts taken

    separately.

    1.1 Terminologies

    Operations The activities carried out in an organization related to attaining its goals and

    objectives.

    Research The process of observation and testing characterized by the scientific method.

    The steps of the process include observing the situation and formulating a

    problem statement, constructing a mathematical model, hypothesizing that the

    model represents the important aspects of the situation, and validating the

    model through experimentation.

    Organization The society in which the problem arises or for which the solution is important.

    The organization may be a corporation, a branch of government, a department

    within a firm, a group of employees, or perhaps even a household or individual.

    Decision maker An individual or group in the organization capable of proposing and

    implementing necessary actions.

    Analyst An individual called upon to aid the decision maker in the problem solving

    process. The analyst typically has special skills in modeling, mathematics, data

    gathering, and computer implementation.

    Team A group of individuals bringing various skills and viewpoints to a problem.

    Historically, operations research has used the team approach in order that the

    solution not be limited by past experience or too narrow a focus. A team also

    provides the collection of specialized skills that are rarely found in a single

    individual.

    Model An abstract representation of reality. As used here, a representation of a

    decision problem related to the operations of the organization. The model is

    usually presented in mathematical terms and includes a statement of the

    assumptions used in the functional relationships. Models can also be physical,

    narrative, or a set of rules embodied in a computer program.

    Systems

    approach

    An approach to analysis that attempts to ascertain and include the broad

    implications of decisions for the organization. Both quantitative and qualitative

    factors are included in the analysis.

    http://en.wikipedia.org/wiki/Mathematical_modelhttp://en.wikipedia.org/wiki/Statisticshttp://en.wikipedia.org/wiki/Mathematical_optimizationhttp://www.britannica.com/EBchecked/topic/528756/science
  • 2

    Optimal solution A solution to the model that optimizes (maximizes or minimizes) some

    objective measure of merit over all feasible solutions -- the best solution

    amongst all alternatives given the organizational, physical and technological

    constraints.

    Operations

    research

    techniques

    A collection of general mathematical models, analytical procedures, and

    optimization algorithms that have been found useful in quantitative studies.

    These include linear programming, integer programming, network

    programming, nonlinear programming, dynamic programming, statistical

    analysis, probability theory, queuing theory, stochastic processes, simulation,

    inventory theory, reliability, decision analysis, and others. Operations research

    professionals have created some of these fields while others derive from allied

    disciplines.

    1.2 The Operations research process

    The goal of operations research is to provide a framework for constructing models of decision-

    making problems, finding the best solutions with respect to a given measure of merit, and

    implementing the solutions in an attempt to solve the problems. The problem is a situation arising in

    an organization that requires some solution. The decision maker is the individual or group

    responsible for making decisions regarding the solution. The individual or group called upon to aid

    the decision maker in the problem solving process is the analyst. The steps taken in the OR

    processes are as follows:

    1.2.1 Recognize the problem

    Decision making begins with a situation in which a problem is recognized. The problem may be

    actual or abstract, it may involve current operations or proposed expansions or contractions due to

    expected market shifts, it may become apparent through consumer complaints or through employee

    suggestions, it may be a conscious effort to improve efficiency or a response to an unexpected

    crisis. It is impossible to circumscribe the breadth of circumstances that might be appropriate for

    this discussion, for indeed problem situations that are amenable to objective analysis arise in every

    area of human activity.

    1.2.2 Formulate the problem

    The first analytical step of the solution process is to formulate the problem in more precise terms.

    At the formulation stage, statements of objectives, constraints on solutions, appropriate

    assumptions, descriptions of processes, data requirements, alternatives for action and metrics for

    measuring progress are introduced. Because of the ambiguity of the perceived situation, the process

    of formulating the problem is extremely important. The analyst is usually not the decision maker

    and may not be part of the organization, so care must be taken to get agreement on the exact

    character of the problem to be solved from those who perceive it. There is little value to either a

    poor solution to a correctly formulated problem or a good solution to one that has been incorrectly

    formulated.

  • 3

    1.2.3 Construct a model

    A mathematical model is a collection of functional relationships by which allowable actions are

    delimited and evaluated. Although the analyst would hope to study the broad implications of the

    problem using a systems approach, a model cannot include every aspect of a situation. A model is

    always an abstraction that is, by necessity, simpler than the reality. Elements that are irrelevant or

    unimportant to the problem are to be ignored; hopefully leaving sufficient detail so that the solution

    obtained with the model has value with regard to the original problem. The statements of the

    abstractions introduced in the construction of the model are called the assumptions. It is important

    to observe that assumptions are not necessarily statements of belief, but are descriptions of the

    abstractions used to arrive at a model. The appropriateness of the assumptions can be determined

    only by subsequent testing of the models validity. Models must be both tractable -- capable of

    being solved, and valid -- representative of the true situation. These dual goals are often

    contradictory and are not always attainable.

    1.2.4 Find a solution

    Here tools available to the analyst are used to obtain a solution to the mathematical model. Some

    methods can prescribe optimal solutions while other only evaluate candidates, thus requiring a trial

    and error approach to finding an acceptable course of action. To carry out this task the analyst must

    have a broad knowledge of available solution methodologies. It may be necessary to develop new

    techniques specifically tailored to the problem at hand. A model that is impossible to solve may

    have been formulated incorrectly or burdened with too much detail. Such a case signals the return to

    the previous step for simplification or perhaps the postponement of the study if no acceptable,

    tractable model can be found. Of course, the solution provided by the computer is only a proposal.

    An analysis does not promise a solution but only guidance to the decision maker. Choosing a

    solution to implement is the responsibility of the decision maker and not the analyst. The decision

    maker may modify the solution to incorporate practical or intangible considerations not reflected in

    the model.

    1.2.5 Establish the procedure

    Once a solution is accepted a procedure must be designed to retain control of the implementation

    effort. Problems are usually on-going rather than unique. Solutions are implemented as procedures

    to be used repeatedly in an almost automatic fashion under perhaps changing conditions. Control

    may be achieved with a set of operating rules, a job description, laws or regulations promulgated by

    a government body, or computer programs that accept current data and prescribe actions. Once a

    procedure is established (and implemented), the analyst and perhaps the decision maker are ready to

    tackle new problems, leaving the procedure to handle the required tasks. But what if the situation

    changes? An unfortunate result of many analyses is a remnant procedure designed to solve a

    problem that no longer exists or which places restrictions on an organization that are limiting and no

    longer appropriate. Therefore, it is important to establish controls that recognize a changing

    situation and signal the need to modify or update the solution.

  • 4

    1.2.6 Implement the solution

    A solution to a problem usually implies changes for some individuals in the organization. Because

    resistance to change is common, the implementation of solutions is perhaps the most difficult part

    of a problem solving exercise. Some say it is the most important part. Although not strictly the

    responsibility of the analyst, the solution process itself can be designed to smooth the way for

    implementation. The persons who are likely to be affected by the changes brought about by a

    solution should take part, or at least be consulted, during the various stages involving problem

    formulation, solution testing, and the establishment of the procedure.

    1.2.7 The OR process

    Combining the steps we obtain the complete OR process. In practice, the process may not be well

    defined and the steps may not be executed in a strict order. Rather there are many loops in the

    process, with experimentation and observation at each step suggesting modifications to decisions

    made earlier. The process rarely terminates with all the loose ends tied up. Work continues after a

    solution is proposed and implemented. Parameters and conditions change over time requiring a

    constant review of the solution and a continuing repetition of portions of the process. It is

    particularly important to test the validity of the model and the solution obtained. Are the

    computations being performed correctly? Does the model have relevance to the original problem?

    Do the assumptions used to obtain a tractable model render the solution useless? These questions

    must be answered before the solution is implemented in the field. There are a number of ways to to

    test a solution. The simplest determines whether the solution makes sense to the decision maker.

    Solutions obtained by quantitative studies may not be predictable but they are often not too

    surprising. Other testing procedures include sensitivity analysis, the use of the model under a

    variety of conjectured conditions including a range of parameter values, and the use of the model

    with historical data.

    Fig. 1.1 The OR process

  • 5

    2.0 Operations research models

    Most operations research studies involve the construction of a mathematical model. The model is a

    collection of logical and mathematical relationships that represents aspects of the situation under

    study. Models describe important relationships between variables; include an objective function

    with which alternative solutions are evaluated, and constraints that restrict solutions to feasible

    values. OR models include: Linear Programming, Network Flow Programming, Integer

    Programming, Nonlinear Programming, Dynamic Programming, Stochastic Programming,

    Combinatorial Optimization, Stochastic Processes, Discrete Time Markov Chains, Continuous

    Time Markov Chains, Queuing, and Simulation.

    2.1 Linear programming

    Linear programming (LP) is a widely used model type that can solve decision problems with many

    thousands of variables. Generally, the feasible values of the decisions are delimited by a set of

    constraints that are described by mathematical functions of the decision variables. The feasible

    decisions are compared using an objective function that depends on the decision variables. For a

    linear program the objective function and constraints are required to be linearly related to the

    variables of the problem.

    2.1.1 Terminologies

    Decision

    Variables

    Decision variables describe the quantities that the decision makers would like to

    determine. They are the unknowns of a mathematical programming model.

    Typically we will determine their optimum values with an optimization method. In

    a general model, decision variables are given algebraic designations such

    as . The number of decision variables is n, and is the name of

    the jth variable. In a specific situation, it is often convenient to use other names

    such as or or . In computer models we use names such as FLOW1 or

    AB_5 to represent specific problem-related quantities. An assignment of values to

    all variables in a problem is called a solution.

    Objective

    function

    The objective function evaluates some quantitative criterion of immediate

    importance such as cost, profit, utility, or yield. The general linear objective

    function can be written as

    Here is the coefficient of the jth decision variable. The criterion selected can be

    either maximized or minimized.

    Constraints A constraint is an inequality or equality defining limitations on decisions.

    Constraints arise from a variety of sources such as limited resources, contractual

    obligations, or physical laws. In general, an LP is said to have m linear constraints

    that can be stated as

  • 6

    One of the three relations shown in the large brackets must be chosen for each

    constraint. The number is called a "technological coefficient," and the

    number is called the "right-hand side" value of the ith constraint. Strict

    inequalities (< and >) are not permitted. When formulating a model, it is good

    practice to give a name to each constraint that reflects its purpose.

    Simple upper

    bound Associated with each variable, , may be a specified quantity, , that limits its

    value from above;

    When a simple upper is not specified for a variable, the variable is said to be

    unbounded from above.

    Nonnegativity

    restrictions

    In most practical problems the variables are required to be nonnegative;

    This special kind of constraint is called a nonnegativity restriction. Sometimes

    variables are required to be nonpositive or, in fact, may be unrestricted (allowing

    any real value).

    Complete

    linear

    programming

    model

    Combining the aforementioned components into a single statement gives:

    The constraints, including nonnegativity and simple upper bounds, define the

    feasible region of a problem.

    Parameters The collection of coefficients for all values of the indices i and j are

    called the parameters of the model. For the model to be completely determined all

    parameter values must be known.

    2.1.2 Properties of a linear programming model

    Any linear programming model (problem) must have the following properties:

    (a) The relationship between variables and constraints must be linear.

    (b) The model must have an objective function.

    (c) The model must have structural constraints.

    (d) The model must have non-negativity constraint.

  • 7

    Let us consider a product mix problem and see the applicability of the above properties.

    A company manufactures two products X and Y, which require the following resources. The

    resources are the capacities machine M1, M2, and M3. The available capacities are 50, 25, and 15

    hours respectively in the planning period. Product X requires 1 hour of machine M2 and 1 hour of

    machine M3. Product Y requires 2 hours of machine M1, 2 hours of machine M2 and 1 hour of

    machine M3. The profit contribution of products X and Y are Rs.5/- and Rs.4/- respectively.

    In the above problem, Products X and Y are competing candidates or variables. Machine capacities

    are available resources. Profit contribution of products X and Y are given. Now let us formulate the

    model. Let the company manufactures x units of X and y units of Y. As the profit contributions of X

    and Y are Rs.5/- and Rs. 4/- respectively. The objective of the problem is to maximize the profit Z,

    hence objective function is:

    Maximize Z = 5x + 4y ----------------------------- Objective function

    This should be done so that the utilization of machine hours by products x and y should not

    exceed the available capacity. This can be shown as follows:

    For Machine M1 0x + 2y 50

    For Machine M2 1x + 2y 25 and ----------- Linear structural constraints

    For machine M3 1x + 1y 15

    But the company can stop production of x and y or can manufacture any amount of x and y. It

    cannot manufacture negative quantities of x and y. Hence,

    Both x and y are 0 ---------------- non-negativity constraint

    As the problem has got objective function, structural constraints, and non-negativity constraints

    and there exist a linear relationship between the variables and the constraints in the form of

    inequalities,

    the problem satisfies the properties of the Linear Programming Problem.

    2.1.3 Basic assumptions

    The following are some important assumptions made in formulating a linear programming model:

    1. It is assumed that the decision maker here is completely certain (i.e., deterministic conditions)

    regarding all aspects of the situation, i.e., availability of resources, profit contribution of the

    products, technology, courses of action and their consequences etc.

    2. It is assumed that the relationship between variables in the problem and the resources available

    i.e., constraints of the problem exhibits linearity. Here the term linearity implies proportionality and

    additivity. This assumption is very useful as it simplifies modelling of the problem.

    3. We assume here fixed technology. Fixed technology refers to the fact that the production

    requirements are fixed during the planning period and will not change in the period.

  • 8

    4. It is assumed that the profit contribution of a product remains constant, irrespective of level of

    production and sales.

    5. It is assumed that the decision variables are continuous. It means that the companies manufacture

    products in fractional units. For example, company manufacture 2.5 vehicles, 3.2 barrels of oil etc.

    This is referred to as the assumption of divisibility.

    6. It is assumed that only one decision is required for the planning period. This condition shows that

    the linear programming model is a static model, which implies that the linear programming problem

    is a single stage decision problem. (Note: Dynamic Programming problem is a multistage decision

    problem).

    7. All variables are restricted to nonnegative values (i.e., their numerical value will be 0).

    2.1.4 Steps in formulating linear programming

    The steps for formulating the linear programming are:

    1. Identify the unknown decision variables to be determined and assign symbols to them.

    2. Identify all the restrictions or constraints in the problem and express them as linear equations or

    inequalities of decision variables.

    3. Identify the objective or aim and represent it also as a linear function of decision variables.

    2.1.5 Methods for the solution of a linear programming problem

    Linear Programming, is a method of solving the type of problem in which two or more candidates

    or activities are competing to utilize the available limited resources, with a view to optimize the

    objective function of the problem. The objective may be to maximize the returns or to minimize the

    costs. The various methods available to solve the problem are:

    1. The Graphical Method: when we have two decision variables in the problem. (To deal with

    more decision variables by graphical method will become complicated, because we have to deal

    with planes instead of straight lines. Hence in graphical method, it is better to work within the limits

    of two variable problems.

    2. The Systematic Trial and Error method: where we go on giving various values to variables

    until we get optimal solution. This method takes too much of time and laborious.

    3. The Vector method: In this method each decision variable is considered as a vector and

    principles of vector algebra is used to get the optimal solution. This method is also time consuming.

    4. The Simplex method: When the problem is having more than two decision variables, simplex

    method is the most powerful method to solve the problem. It has a systematic programme

    which can be used to solve the problem.

  • 9

    Fig 2.1 Network flow

    2.2 Network flow programming

    The term network flow program describes a type of model that is a

    special case of the more general linear program. The class of network

    flow programs includes such problems as the transportation problem,

    the assignment problem, the shortest path problem, the maximum flow

    problem, the pure minimum cost flow problem, and the generalized

    minimum cost flow problem. It is an important class because many

    aspects of actual situations are readily recognized as networks and the

    representation of the model is much more compact than the general linear program. When a

    situation can be entirely modelled as a network, very efficient algorithms exist for the solution of

    the optimization problem, many times more efficient than linear programming in the utilization of

    computer time and space resources.

    2.2.1 Terminologies

    Nodes and arcs The network flow model consists of nodes and arcs. In the context of

    modeling a problem, each node, shown as a circle, represents some aspect of

    the problem such as a physical location, an individual worker, or a point in

    time. For modeling purposes it is often convenient to assign names to the

    nodes. Arcs are directed line segments. The nodes at its ends identify an arc.

    The arc passes from its origin node to its terminal node. We use m as the

    number of nodes and n as the number of arcs.

    Arc flow Flow is associated with the network, entering and leaving at the nodes and

    passing through the arcs. The flow in arc k is . Flow is conserved at the

    nodes, implying that the total flow entering a node must equal the total flow

    leaving the node. The arc flows are the decision variables for the network flow

    programming model.

    Upper and lower

    bounds on flow

    Flow is limited in an arc by the lower and upper bounds on flow. Sometimes

    the term capacity refers to the upper bound on flow. We use and for the

    lower and upper bounds of arc k.

    Cost The criterion for optimality is cost. Associated with each arc k, is the cost per

    unit of flow, . Negative values of model revenues

    Gain The arc gain, , multiplies the flow at the beginning of the arc to obtain the

    flow at the end of the arc. When a flow is assigned to an arc, this flow

    leaves the origin node of the arc. The flow entering the terminal node of the

    arc is

    .

    The arc lower bound, upper bound, and cost all refer to the flow at the

    beginning of the arc. Gains less than 1 model losses such as evaporation or

    spoilage. Gains greater than 1 model growth in flow.

    A network in which all arcs have unit gains is called a pure network. The

    optimum solution for a pure network with integer parameters always has

    integer flows. If some gains have values other than 1 the network is a

    generalized network, and the solution is not usually all integer.

    Arc parameters The set of arc parameters are shown adjacent to arcs enclosed in parenthesis:

  • 10

    (lower bound, upper bound, cost, gain).

    When a parameter is not shown, it assumes its default value. Default values

    are: 0 for lower bound, infinity for upper bound, 0 for cost and 1 for gain.

    External flows The external flow at node i, , is the flow that must enter or leave node i. A

    positive external flow enters the node, and a negative external flow leaves the

    node. We show the external flow adjacent to the node with square brackets.

    Feasible flow A feasible flow is an assignment of flow to the arcs that satisfies conservation

    of flow for each node and the bounds on flow for each arc.

    Side constraints Side constraints are constraints on arc flows that cannot be modeled using the

    network structure, arc parameters or external flows.

    Optimal flow The feasible flow that minimizes total arc cost is the optimal flow.

    The linear

    programming

    model

    Every network flow programming model has an equivalent linear

    programming model.

    2.2.2 Special cases

    When learning to use network models, it is helpful to recognize several special cases of network

    flow programming. These are the transportation, assignment, shortest path, and maximum flow

    models. The problems differ primarily in the set of arc parameters that are relevant or the

    arrangement of nodes and arcs. For example, for the transportation model only the arc costs are

    relevant and all arcs originate at one set of nodes and terminate at another. We describe in this

    section the classes in terms of the network model defined above and note that for each only a subset

    of the parameters is relevant. All irrelevant parameters will take on the default values. For the

    special network models of this section we set the parameter default values as: 0 for the lower bound,

    M (a large number) for the upper bound, 0 for the cost, and 1 for the gain.

    Using the default values for parameters, all of the classes can be solved using algorithms defined for

    the more general case. There are, however, a number of algorithms for solving each class that do

    not use the irrelevant parameters at all. In this way the special case algorithms can be more efficient

    than the more general ones. Fig. 2.2 shows the relationships between the various network flow

    programming models and linear programming. The models on the left are the least general. As we

    move to the right, the problems become more general. Thus all the problems to the left of the

    generalized minimum cost flow problem can be solved with an algorithm designed for the

    generalized problem. The generalized problem is itself a special case of the linear program.

  • 11

    2.2.3 Transportation problem

    A typical transportation problem is shown in Fig. 2.3 It deals with sources where a supply of some

    commodity is available and destinations where the commodity is demanded. The classic statement

    of the transportation problem uses a matrix with the rows representing sources and columns

    representing destinations. The algorithms for solving the problem are based on this matrix

    representation. The costs of shipping from sources to destinations are indicated by the entries in the

    matrix. If shipment is impossible between a given source and destination, a large cost of M is

    entered. This discourages the solution from using such cells. Supplies and demands are shown

    along the margins of the matrix. As in the example, the classic transportation problem has total

    supply equal to total demand.

    The network model of the transportation problem is shown in Fig. 2.4. Sources are identified as the

    nodes on the left and destinations on the right. Allowable shipping links are shown as arcs, while

    disallowed links are not included.

    Fig. 2.2 Relationship between network models

    Fig. 2.3 Matrix model of a transportation problem.

  • 12

    Only arc costs are shown in the network model, as these are the only relevant parameters. All other

    parameters are set to the default values. The network has a special form important in graph theory;

    it is called a bipartite network since the nodes can be divided into two parts with all arcs going from

    one part to the other.

    On each supply node the positive external flow indicates supply flow entering the network. On each

    destination node a demand is a negative fixed external flow indicating that this amount must leave

    the network. The optimum solution for the example is shown in Fig. 2.5.

    Variations of the classical transportation problem are easily handled by modifications of the

    network model. If links have finite capacity, the arc upper bounds can be made finite. If supplies

    represent raw materials that are transformed into products at the sources and the demands are in

    units of product, the gain factors can be used to represent transformation efficiency at each source.

    If some minimal flow is required in certain links, arc lower bounds can be set to nonzero values.

    2.3 Integer programming (IP)

    Integer programming is concerned with optimization problems in which some of the variables are

    required to take on discrete values. Rather than allow a variable to assume all real values in a given

    range, only predetermined discrete values within the range are permitted. In most cases, these

    values are the integers giving rise to the name of this class of models.

    The integrality requirement underlies a wide variety of applications. There are many situations,

    such as distributing goods from warehouses to factories or finding the shortest path through a

    network, where the flow variables are logically required to be integer valued. In manufacturing,

    Fig. 2.4 Network flow model of the transportation problem.

    Fig. 2.5 Optimum solution, z = 46.

  • 13

    products are often indivisible so a production plan that calls for fractional output is not acceptable.

    There are also many situations that require logical decisions of the form yes/no, go/no go,

    assign/dont assign. Clearly these are discrete decisions that when quantified allow only two values.

    They can be modelled with binary variables that assume values of zero or one. Designers faced with

    selecting from a finite set of alternatives, schedulers seeking the optimal sequence of activities, or

    transportation planners searching for the minimum cost routing of vehicles all face discrete decision

    problems.

    When optimization models contain both integer and continuous variables they are referred to as

    mixed-integer programs. The power and usefulness of these models to represent real-world

    situations cannot be overstated, but along with modelling convenience comes substantial

    computational difficulty. Only relatively small problems containing integer variables can be solved

    to optimality in most cases. At first glance this might seem counterintuitive given our ability to

    solve huge linear programs. However, the discrete nature of the variables gives rise to a

    combinatorial explosion of possible solutions. In the worst case, a majority of these solutions must

    be enumerated before optimality can be confirmed. Consequently, when the number of integer

    variables in a problem gets large, solving a model to optimality becomes very difficult, if not

    impossible. Rather, heuristic methods that do not guarantee optimality must be used to find

    solutions.

    2.3.1 Terminologies

    Integer programming

    model (IP)

    Mixed interger

    programming model

    (MIP)

    IP Model with p strictly less than n.

    Pure integer

    programming model (PIP)

    IP with all variables required to be integer (p = n).

    Binary programming

    model (BP)

    IP with all integer variables restricted to 0 or 1. The model can be

    classified as a pure-binary programming model or mixed-binary

    programming model.

    Logical constraint A linear constraint involving integer variables that models some

    logical condition on the decision variables.

    Concave function of a

    single variable

    A function of a single variable with a decreasing derivative. The

    figure below shows a concave function of a decision variable. A

    piecewise linear approximation is shown by the dotted lines.

  • 14

    A concave function in the objective function of a maximization

    problem can be represented by the sum of several linear expressions

    with a piecewise linear approximation (3 for the figure). No binary

    variables are required.

    For a minimization problem, a piecewise linear approximation

    requires binary variables to force the pieces to enter the solution in

    the proper order. The number of binary variables is one fewer than

    the number of pieces.

    Convex function of a

    single variable

    A function of a single variable with a increasing derivative. The

    figure below shows a convex function of a decision variable. A

    piecewise linear approximation is shown by the dotted lines.

    A convex function in the objective function of a minimization

    problem can be represented by the sum of several linear expressions

    with a piecewise linear approximation (3 for the figure). No binary

    variables are required.

    For a maximization problem, a piecewise linear approximation

    requires binary variables to force the pieces to enter the solution in

    the proper order. The number of binary variables is one fewer than

    the number of pieces.

    Fixed charge function A nonlinear function that represents the cost of a decision. The cost

    is 0 if the variable is 0. The cost is a fixed value plus a cost which is

  • 15

    linear with the amount of the variable.

    The fixed charge is modeled with a binary variable.

    The fixed charge multiplies the binary variable and the unit cost

    multiplies the decision variable.

    The model must include an implication constraint that forces the

    decision variable to 0 when the binary variable is zero. When the

    binary variable is 1, the constraint limits the decision variable to its

    upper bound. The model also includes nonnegativity restrictions and

    the upper bound on the binary variable.

    2.3.2 Site selection problem

    A builder is planning to construct new buildings at four local sites designated 1, 2, 3 and 4. At each

    site there are three possible building designs labelled A, B and C. There is also the option of not

    using a site. The problem is to select the building locations and accompanying designs. Preliminary

    studies have determined the required investment and net annual income for each of the 12 options.

    These are shown in the table below, with A1, for example, denoting design A at site 1. The

    company has an investment budget of $100M. The goal is to maximize total annual income without

    exceeding the investment budget. As the OR analyst, you are given the job of finding the optimum

    plan.

  • 16

    This example introduces one of the major differences between linear and integer programming; the

    indivisibility of decisions. It is an obvious requirement here that only whole buildings may be built

    and only whole designs may be selected.

    Linear/Integer programming model:

    To begin creating a model, variables must be defined to represent each decision. In many cases

    models can be more succinctly stated using algebraic expressions with subscripted variables. In this

    section, we use variable names like A1, A2, C3, and C4 to represent the decisions. This makes it

    easier to present the model in a browser readable format. The notation is also similar to that used for

    the computer model. We will write several models in this section, but the simplest is:

    Objective: Max. z = 6*A1 + 7*A2 + 9*A3 ... + 19*C3 + 20*C4

    subject to:

    Budget: 13*A1 + 20*A2 + 24*A3 ... + 48*C3 + 55*C4 100

    Simple Bounds and Integrality

    0 A1 1, 0 A2 1, ... , 0 C4 1 and integer

    We use * to indicate multiplication and ... to indicate a continuation in a similar fashion.

    Note that since the variables are restricted between 0 and 1 and required to be integer, there are

    actually only two feasible values, 0 and 1 for each variable. A design/location combination either

    adds its contributions to the net income and budget (=1) or does not (=0). The simple phrase "and

    integer" specifies that all the variables must be integer Thus the model describes the problem of

    selecting the set of design/location combinations that maximize net income, while not exceeding the

    budget constraint.

    The model has the linear form required for linear programming, but it is not a linear programming

    model because the variables are not allowed to assume all values within a continuum. Often the

    phrase Integer Programming is used for the linear model with some or all the variables required to

    be integer, leaving out the term linear. Although, one can express models that are integer and

    nonlinear, these are generally much more difficult to solve. For a nonlinear-integer model we use

    the phrase nonlinear-integer program.

    2.4 Nonlinear programming

    The principal abstraction of the linear programming model is that all functions are linear. This leads

    to a number of powerful results that greatly facilitate our ability to find solutions. The first is that all

    local optima are global optima; the second is that if the optimal value of the objective function is

    finite, at least one of the extreme points in the set of feasible solutions will be an

    optimum. Furthermore, starting at any extreme point in the feasible region, it is possible to reach an

    optimal extreme point in a finite number of steps by moving only to an adjacent extreme point in an

    improving direction. The simplex method embodies these ideas and has proven to be extremely

    efficient.

  • 17

    Nevertheless, much of the world is nonlinear so it is natural to ask if it is possible to achieve the

    same efficiency with nonlinear models. In many contexts, the elements of a linear model are really

    approximations of more complex relationships. Economies of scale in manufacturing, for example,

    lead to decreasing costs, while biological systems commonly exhibit exponential growth. In the

    design of a simple hatch cover, the shearing stress, bending stress and degree of defection are each

    polynomial functions of flange thickness and beam height. Similar relationships abound in

    engineering design, economics, and distribution systems, to name a few.

    The appeal of nonlinear programming (NLP) is strong because of the modelling richness it affords.

    Unfortunately, NLP solvers have not yet achieved the same level of performance and reliability

    associated with LP solvers. For all but the most structured problems, the solution obtained from an

    NLP solver may not be globally optimal. This argues for caution. Before taking any action, the

    decision maker should have a full understanding of the nonlinearities governing the system under

    study.

    2.4.1 Terminologies

    Model

    components

    The objective and constraint functions are scalar quantities that vary with

    the decision vector. The functions may be nonlinear. General

    model

    Every mathematical programming model can be put in this form. General

    discussions assume this standard format. Global

    minimum A solution that has an objective value less than or equal to all other

    solutions.

    Unique global

    minimum A solution that has an objective value less than all other solutions. Not all

    problems have a strict global minimum.

    Weak local

    minimum A solution that has an objective value less than or equal to all other

    solutions in a small neighbourhood of the solution.

    Strong local

    minimum A solution that has an objective value less than all other solutions in a

  • 18

    small neighbourhood of the solution.

    Global and

    local

    maximum

    Definitions are the same as the definitions of global and local minimum

    with greater than replacing less than.

    Convex

    function When a straight line is drawn between any two points on a convex

    function, the line lies on or above the function. The figure shows a one

    dimensional convex function.

    In multiple dimensions a convex function has the following property.

    Concave

    function When a straight line is drawn between any two points on a concave

    function, the line lies on or below the function. The figure shows a one

    dimensional concave function.

    In multiple dimensions a concave function has the following property.

    Feasible

    region The feasible region is the set of all solutions that satisfy all of the

  • 19

    constraints.

    Convex set A set S is convex if any point on the line segment connecting any two

    points in the set is also in S. The figure shows examples of convex sets in

    two dimensions. An important issue in nonlinear programming is

    whether the feasible region is convex.

    When the all the constraints of a problem are linear or convex, the

    feasible region is a convex set.

    If the objective function is a convex and the feasible region defines a

    convex set, every local minimum is a global minimum.

    If the objective function is not a convex function, a local minima may or

    may not be global minimum. A nonlinear programming algorithm may

    terminate at a solution that is not a global minimum. Nonconvex

    set f a set does not satisfy the requirements of convex set, it is a nonconvex

    set. The figure shows examples of nonconvex sets in two dimensions.

    If the feasible region of a problem is a nonconvex set, a local minimum

    may or may not be global minimum. A nonlinear programming algorithm

    may terminate at a solution that is not a global minimum.

    2.4.2 Manufacturing example: Linear objective

    Problem

    We consider a manufacturing problem with three products, P, Q and R, being manufactured on four

    machines, A through D. The products require four raw materials, M1 through M4. Tables 1, 2 and 3

    provide revenue and cost data, as well as information relating production to machine capacity and

  • 20

    raw material usage. In this section we show a linear programming model of the problem. After

    examining its solution, we introduce several nonlinearities and discuss their implications.

    Linear Programming Model

    For the linear programming model, we select the goal of maximizing net operating income, revenue

    minus raw material cost.

    Decision Variables:

    : number of units of product P to produce during the week

    : number of units of Q to produce during the week

    : number of units of R to produce during the week

    : number of units of raw material j to purchase, j = 1...4.

    Objective: Maximize operating income = Revenue - Raw Material Cost

    Subject to:

    Machine Time Limit Constraints

  • 21

    Raw Material Constraints

    Nonegativity and Upper Bounds

    Solution:

    The figure below shows the linear model created and solved in Excel.

    The solution to the LP model is a basic solution. We note that machines A and B are bottlenecks,

    with their available capacity entirely used. Production of R is limited by the market.

    2.5 Dynamic programming

    Many planning and control problems involve a sequence of decisions that are made over time. The

    initial decision is followed by a second, the second by a third, and so on. The process continues

    perhaps infinitely. Because the word dynamic describes situations that occur over time and

    programming is a synonym for planning, the original definition of dynamic programming was

    "planning over time." In a limited sense, our concern is with decisions that relate to and affect

    phenomena that are functions of time. This is in contrast to other forms of mathematical

  • 22

    programming that often, but not always, describe static decision problems. As is true in many fields,

    the original definition has been broadened somewhat over the years to connote an analytic approach

    to problems involving decisions that are not necessarily sequential but can be viewed as such. In

    this expanded sense, dynamic programming (DP) has come to embrace a solution methodology in

    addition to a class of planning problems. It is put to the best advantage when the decision set is

    bounded and discrete, and the objective function is nonlinear.

    To model with dynamic programming, an abstraction or reduction of complexity from the real

    world problem is necessary. There are two reasons for this, one practical and the other

    computational. From a practical point of view, it is rarely possible to identify and evaluate all the

    factors that are relevant to a realistic decision problem. Thus the analyst will inevitably leave out

    some more or less important descriptors of the situation. From a computational point of view, only

    problems with relatively simple state descriptions will be solvable by dynamic programming

    algorithms. Thus abstraction is necessary in order to arrive at a formulation that is computationally

    tractable. Often a particular problem may have several alternative representations in terms of state

    and decision variables. It is important that the analyst realize that some formulations require more

    computation than others do, and hence choose the most manageable representation.

    Dynamic programming has been described as the most general of the optimization approaches

    because conceivably it can solve the broadest class of problems. In many instances, this promise is

    unfulfilled because of the attending computational requirements. Certain problems, however, are

    particularly adaptable to the model structure and lend themselves to efficient computational

    procedures; in cases involving discontinuous functions or discrete variables, dynamic programming

    may be the only practical solution methodology.

    2.5.1 Terminologies

    State

    where si is the value of state variable i and m is the number of state

    variables.

    Initial state set I = {s : states where the decision process begins}

    Final state set F = {s : states where the decision process ends}

    State space S = {s : s is feasible}

    Decision

    where dj is the value of the jth decision variable and p is the number of

    decision variables.

    Feasible decision D(s) = {d : d leads to a feasible state from state s}

    Transition function s' = T(s, d), a function that determines the next state, s', reached when

    decision d is taken from state s

    Decision objective z(s, d), the measure of effectiveness associated with decision d taken in

    state s

    Path objective z(P), the measure of effectiveness defined for path P. This function

    describes how the objective terms for each state on the path and the final

    value function are combined to obtain a measure for the entire path

    Final function

    value

    f(s) value that is specified for all final states

  • 23

    2.5.2 Investment problem

    Problem statement:

    A portfolio manager with a fixed budget of $100 million is considering the eight investment

    opportunities shown in Table 1. The manager must choose an investment level for each alternative

    ranging from $0 to $40 million. Although an acceptable investment may assume any value within

    the range, we discretize the permissible allocations to intervals of $10 million to facilitate the

    modelling. This restriction is important to what follows. For convenience we define a unit of

    investment to be $10 million. In these terms, the budget is 10 and the amounts to invest are the

    integers in the range from 0 to 4.

    Table 1 provides the net annual returns from the investment opportunities expressed in millions of

    dollars. A ninth opportunity, not shown in the table, is available for funds left over from the first

    eight investments. The return is 5% per year for the amount invested, or equivalently, $0.5 million

    for each $10 million invested. The manager's goal is to maximize the total annual return without

    exceeding the budget.

    The investment problem has a general mathematical programming formulation.

    The notation is the general model is defined below.

  • 24

    2.6 Stochastic programming

    There is no question that decision making in the face of uncertainty is an important topic. It is one

    of the prime activities of man, arising in every field of purposeful work and in most of the games

    that we invent for our amusement.

    The mathematical programming models, such as linear programming, network flow programming

    and integer programming generally neglect the effects of uncertainty and assume that the results of

    decisions are predictable and deterministic. This abstraction of reality allows large and complex

    decision problems to be modelled and solved using powerful computational methods.

    Stochastic programming explicitly recognizes uncertainty by using random variables for some

    aspects of the problem. With probability distributions assigned to the random variables, an

    expression can be written for the expected value of the objective to be optimized. Then a variety of

    computational methods can be used to maximize or minimize the expected value. This page

    provides a brief introduction to the modelling process.

    When we recognize the possibility of uncertainty or risk within the context of mathematical

    programming, the decision problem might be written as below. The model is shown in the typical

    matrix format for an LP except tildes appear over all the parameter matrices. This implies that all

    may be affected by a vector of random variables. In practical instances the model could be

    complicated by nonlinear terms and integrality restrictions. In any event, the model as stated is not

    well defined because: (1) the timing of the decisions and observations of the randomness are

    ambiguous and (2) the concepts of optimal solutions and feasible solutions are unclear.

    Stochastic programming addresses the first issue by explicitly defining the sequence of decisions in

    relation to the realization of the random variables. Given the sequence, an objective function is

    defined that reflects a rational criterion for evaluating the decisions at the time they must be made.

    Feasibility conditions must be adapted to the fact that decisions made before the realization of

    randomness may have feasibility consequences after the realization. How the issues are resolved

    leads to the several different problems listed below. No single problem formulation is sufficient.

    For stochastic programming the probability distribution of must be known. More properly we

    should say that stochastic programming is decision making under risk, reserving the phrase decision

    making under uncertainty for those situations for which probability distributions are unavailable.

    For stochastic programming, some variables are to be set by a decision maker, these are the decision

    variables, while some model parameters are determined by chance, and these are the random

    variables. There are a variety of situations one might consider in this context. One differentiation is

  • 25

    based on when the decision maker must make decisions relative to the time when the random

    variables are realized. There are several possibilities.

    - Wait and See: The decision maker makes no decisions until all random variables are

    realized.

    - No Recourse: The decision maker must choose values for the decision variables before any

    of the random variables are realized. There is a risk of violating the constraints.

    - Chance Constraints: This is the no-recourse situation when only the RHS vector is random.

    Solutions are found with specified risks of constraint infeasibility.

    - Simple Recourse: This topic considers the problem with a random RHS vector. The decision

    maker must choose values for the decision variables before the RHS values are known, but

    variables adjusting to the RHS variation are set after the realization. Penalties for constraint

    violation are specified.

    - Recourse: Some of the decision variables must be set before the random variables are

    realized, while others may wait until after they are realized. Models explicitly represent the

    initial decisions and all recourse decisions. Although the models can be very large, optimum

    solutions solve for all possible circumstances.

    - Multistage Recourse: Decisions and random variables are determined in stages. The first set

    of decision variables must be fixed before all realizations. Then the first set of random

    variables are realized and the second set of decision variables are fixed. The process

    continues through a series of decisions and realizations. Typically the stages represent

    intervals of time. We do not consider this situation.

    2.6.1 Stochastic programming example Wait and see

    To illustrate stochastic programming, consider the linear programming model below. The solution

    algorithm is the Jensen LP/IP add-in. The problem was generated randomly using the Math

    Programming add-in. The solution shown is the optimum solution when all parameters of the model

    are deterministic.

    We assume that all parameters are deterministic except the right-hand-side vector, shown in the

    range F15:F19. The numbers given are the expected values but we add a random variation for each

    value that is distributed as a Normal variant with mean 0 and a standard deviation of 10. We

    http://www.me.utexas.edu/~jensen/ORMM/computation/unit/mp_add/subunits/stochastic/wait.htmlhttp://www.me.utexas.edu/~jensen/ORMM/computation/unit/mp_add/subunits/stochastic/no_recourse.htmlhttp://www.me.utexas.edu/~jensen/ORMM/computation/unit/mp_add/subunits/stochastic/chance.htmlhttp://www.me.utexas.edu/~jensen/ORMM/computation/unit/mp_add/subunits/stochastic/simple.htmlhttp://www.me.utexas.edu/~jensen/ORMM/computation/unit/mp_add/subunits/stochastic/recourse.html
  • 26

    investigate the wait-and-see policy in that the random variables are realized before the decision

    maker sets the solution vector x. The solution x is determined by the solution of the LP. This is not

    really a stochastic programming problem because there is no uncertainty when the decisions must

    be made. We might be interested, however, in the stochastic features of the optimum solution value

    and on the feasibility of the model when viewed before the random variables are realized. We will

    use the Monte Carlo simulation features of the Random Variables add-in to perform the analysis.

    The stochastic model:

    To create a stochastic model that describes the random features of the situation, we

    choose Function from the Random Variables menu and fill in the Add Function dialog as below.

    We have specified LP/IP as the algorithm in the field at the bottom of the dialog. This means that

    the LP will be solved for each point of the sample space that is generated by the enumeration or

    simulation procedure. For the example we use the Simulate method.

    The form is placed below the LP model as shown below. The information in rows 22 and 23 give

    the function name, F_9, the type of analysis, Simulate, the number of simulation iterations, 100, and

    the algorithm to be used with each iteration, LP/IP.

    The random variable definitions are in rows 25 through 27. All have been specified as Normal

    distributions with mean values of 0 and standard deviations of 10. The parameters can be changed

    on the form. The math programming model is linked to the random variables via the RHS entries

    shown in column F of the LP model. They have been replaced by the equations in column G (the

    equations are placed in column F, but illustrated in G). Each RHS is the sum of the original value

    stored in column C and a Normal random variable defined on the function form. As the simulation

    is performed the RHS values will change randomly.

    http://www.me.utexas.edu/~jensen/ORMM/computation/unit/rvadd/functions.htmlhttp://www.me.utexas.edu/~jensen/ORMM/computation/unit/rvadd/index.html
  • 27

    Rows 28 through 30 generate the simulated values. The numbers in row 29 (now 0.5) will be

    replaced by uniformly distributed random numbers. The numbers in row 30 compute the simulated

    values based on the Monte Carlo method.

    Rows 31, 32 and 33 describe the functions to be observed during the simulation. Cell G31 is the

    name. The function value in G32 is an equation that links to the LP objective in F4. The feasibility

    value in G33 is a logical statement that points to cell O4 (shown with the LP model above). That

    cell, filled by the LP/IP add-in, holds the word "Optimal" only when the model has a feasible

    solution. For each simulation these cells will hold the optimum LP value and an indication of

    feasibility. The particular solution shown has all random variables set to 0, their expected values.

    The solution for this sample point is the same as the deterministic solution.

    The green cells in the range G34 through G38 hold the results of the simulation. These are filled in

    by the add-in. Cell 34 returns the proportion of the observations that are feasible. Cells G36 and

    G37 hold the mean and variance of the simulated function, the LP optimum value in this case. Only

    the results for feasible solutions are reported. Cell G38 holds the number of feasible solutions or the

    sample size of the mean and variance statistics immediately above. G39 holds a confidence level

    entered by the user, cell G40 holds a confidence interval computed from the statistics.

  • 28

    To simulate the model choose Moments from the Random Variables menu and set the number of

    simulation observations to 100. Larger values give more accurate results, but take more time. Each

    simulation iteration draws a random sample from each distribution. The values are reflected in the

    RHS vector, and the LP/IP algorithm solves the problem. The results of 100 observations are

    combined and placed on the form. The results begin in row 34 of the figure below. The numbers

    shown in rows 29 through 33 are for the final simulated observation of the random variables.

    We have simulated 100 observations of the wait-and-see option. Even though the solution is

    optimum for each simulated RHS, the mean objective function (estimated at 122.7 in cell G36) is

    lower than the value when the RHS values were set to the expected values (125.6). This is a

    consequence of "Jensen's Inequality" (named after a different person than the author). The expected

    value solution will always have a higher objective function (when maximizing) than a solution that

    explicitly represents uncertainty.

    All the observations in the sample of 100 were feasible for the example and the 90% confidence

    interval for the LP objective value is almost 2. The values of the solution variables, X1 through X10

    are not reported on this form.

    It is interesting to increase the standard deviation of the random variables to 30, thus increasing the

    variability of the RHS values. The simulated results are below. For this model, the solution is

    infeasible only if one of the RHS values is negative. With the data provided, the proportion of

    feasible solutions is 0.73. The mean objective value is decreased with significantly greater variance

    over the case when the standard deviation values were 10. The 90% confidence interval is now

    about 8.5. There is a price to pay for variability, even with the wait and see policy.

  • 29

    2.7 Combinatorial optimization

    The most general type of optimization problem and one that is applicable to most spreadsheet

    models is the combinatorial optimization problem. Many spreadsheet models contain variables and

    compute measures of effectiveness. The spreadsheet user often changes the variables in an

    unstructured way to look for the solution that obtains the greatest or least of the measure. In the

    words of OR, the analyst is searching for the solution that optimizes an objective function, the

    measure of effectiveness. Combinatorial optimization provides tools for automating the search for

    good solutions and can be of great value for spreadsheet applications.

    Combinatorics is the branch of mathematics studying the enumeration, combination, and

    permutation of sets of elements and the mathematical relations that characterize their properties.

    Combinatorial optimization does not only enumerate sets, but has the goal of finding the member of

    the set that optimizes an objective function. For OR, combinatorial optimization has come to mean

    methods for finding or searching for the optimum of problems with discrete solution spaces. This is

    in contrast to problems with continuous solution spaces, such as nonlinear programs. Continuous

    solution spaces allow the use of differentiation to aid in finding optimum solutions. For

    combinatorial optimization differentiation is not commonly used. The Combinatorial optimization

    problem is the most general of the optimization problems considered by OR and has been the

    subject of a great deal of research.

    2.7.1 Combinatorial optimization problem (COP)

    We use the general model given below for the combinatorial optimization problem.

  • 30

    This model places very few limitations on the model components. Since the principal methods of

    solution involve enumeration there is no need to restrict the functions involved. Special cases of the

    model will add restrictions, and the solution methods for the special cases depend on these

    restrictions.

    A solution x is a vector of integers. For a spreadsheet application, the individual solution

    components may be cells anywhere on the worksheet, usually arranged for convenience related to

    the application. A solution is a member of the solution space X. The discrete solution space X is

    defined using mathematical relations that members of the set must satisfy. The number of solutions

    in the solution space is finite. An example is below where the solution vectors are restricted to

    integers between lower and upper limits. This is the restriction for IP.

    The definition of X is very important for our models, because it will be different for different

    classes of problems. For a permutation problem, X is the set of all permutations of n integers. For

    the traveling salesman problem it is the set of all tours through n cities. The definition of X might

    also include combinatorial constraints that limit individual components of x or combinations of

    components. The delineation of the set X determines the number of solutions that must be

    enumerated or partially enumerated in the search for the optimum.

    The objective function, f(x), is a single real number and the measure by which alternative solutions

    are compared.

    This function will be evaluated in a single worksheet cell, but it may be the result of computations

    performed in many cells and even on several worksheets in a workbook. For the general model, no

    specific form is specified for f(x), but it is important that its value be unique for a given x. The

    function must also be computable for all x in the solution space. By computable we mean that it

    contains no errors such as dividing by zero, taking the square root of a negative number, or using

    circular cell references. These errors are easy to make on a spreadsheet.

    For the IP, the objective function is a linear function.

  • 31

    G is the set of solutions that are feasible. Many applications have several separate logical relations

    that must all be satisfied (logically TRUE) if the solution is feasible. Logical relations are easy to

    express on a spreadsheet. The expressions involved in G must be computable for all solutions in X.

    Considering again an IP, the components of G come from linear constraints. The following shows

    the development for "less than or equal to" constraints. A similar development follows for

    "equality" and "greater than or equal to" constraints.

    The optimum solution is the feasible solution that minimizes (or maximizes) the objective over all

    feasible solutions in the solution space.

    Although X and G both limit the set over which the optimum is to be found, in our solution

    methods X is the most important. We will search the solutions delimited by X, but only consider for

    optimality those solutions that are feasible, members of G. The process of generating solutions from

    the set X is embodied in the solution algorithm for each special type of problem, so only members

    of X are generated.

    Problem types:

    We identify a problem type by its decisions and the space from which the decisions are to be drawn.

    For each case a solution is given by a vector of integer variables.

  • 32

    We consider four problem types identified by their solution spaces. More detail and examples are

    on the following pages.

    Range

    Permutation

    TSP

    Tree

    Finding solutions:

    In general our goal is to find the feasible solution in X that maximizes or minimizes the objective

    function. Much OR research and practice and many commercial products related to OR have been

    dedicated to this task for special classes of problems.

    Some problems such as minimal spanning tree, shortest path tree and others have very efficient

    algorithms for finding optimum solutions. There are many papers describing faster and faster

    algorithms for solving these problems. We call these the easy problems. Other problems such as the

    traveling salesman and most sequencing problems are very difficult in that there are problems of

    moderate size that cannot be solved on today's high-speed computers and probably never will be

    solved. We call these the hard problems.

    Hard problems are usually solved by enumeration of the solution space. In the most general case,

    exhaustive enumeration of all solutions is necessary to find the optimum. Although practical for

    small problems, this method becomes impossible for problems of only moderate size. For some

    kinds of problems, implicit enumeration methods may provide optimum solutions for larger

    problems. These include the branch and bound methods of integer programming and discrete

    dynamic programming. Implicit enumeration considers all solutions, but large subsets are

    eliminated by numerical tests that assure that the optimum cannot lie in the eliminated subsets.

    2.8 Stochastic process

    In many practical situations the attributes of a system randomly change over time. Examples

    include the number of customers in a checkout line, congestion on a highway, the number of items

    in a warehouse, and the price of a financial security, to name a few. In certain instances, it is

    possible to describe an underlying process that explains how the variability occurs. When aspects

    of the process are governed by probability theory, we have a stochastic process.

  • 33

    The first step in modelling a dynamic process is to define the set of states over which it can range

    and to characterize the mechanisms that govern its transitions. The state is like a snapshot of the

    system at a point in time. It is an abstraction of reality that describes the attributes of the system of

    interest. Time is the linear measure through which the system moves, and can be thought of as a

    parameter. Because of time there is a past, present, and future. We usually know the trajectory a

    system has followed to arrive at its present state. Using this information, our goal is to predict the

    future behaviour of the system in terms of a basic a set of attributes. As we shall see, a variety of

    analytic techniques are available for this purpose.

    From a modelling point of view, state and time can be treated as either continuous or discrete. Both

    theoretical and computational considerations, however, argue in favour of the discrete state case so

    this will be our focus. We consider both discrete time and continuous time models. To obtain

    computational tractibility we assume that the stochastic process satisfies the Markov condition. That

    is, the path the process takes in the future depends only on the current state, and not the sequence of

    states visited prior to the current state. For the discrete time system this leads to the Markov Chain

    model. For the continuous time system the model is called a Markov Process.

    The model of a stochastic process describes activities that culminate in events. The events cause a

    transition from one state to another. Because activity durations are assumed to be continuous

    random variables, events occur in the continuum of time.

    2.8.1 Terminologies

    Stochastic

    process

    A random variable, {X(t)}, where t is a time index that takes values from a

    given set T. T may be discrete or continuous. X(t) is a scalar that may take

    discrete or continuous values. We consider here only finite-discrete stochastic

    processes.

    Time The parameter of a stochastic process.

    State A vector that describes attributes of a system at any point in time. The state

    vector has m components.

    X(t) describes some feature of the state.

    State space Collection of all possible states.

    Activity An activity begins at some point in time, has a duration and culminates in an

    event. Generally the duration of the activity is a random variable with a known

    probability distribution.

    Event The culmination of an activity. The event has the potential to change the state

    of the process.

    Calendar The set of events that can occur in a specified state, Y(s).

    Next event While in some state when one or more events can occur, the one that occurs

    next is called the next event. Measured from the current time, the time of the

    next event is:

    The next event is the value of x that obtains the minimum. When the durations

    of events are random variables both the next event and the time of the next

    event are random variables.

    Transition A function that determines the next state, s', based on the current state, s, and

    the event, x. The number of elements of the transition function is the same as

    the number of elements in the state vector.

  • 34

    s' = T(s,x).

    State-transition

    network

    A graphical representation of the states, represented by nodes, and events,

    represented by arcs. A transition is shown as a directed arc going from one

    node to another.

    Markovian

    property

    Given that the current state is known, the conditional probability of the next

    state is independent of the states prior to the current state.

    Discrete-time

    markov chain

    A stochastic process that satisfies the Markovian property and has a discrete

    time parameter. Sometimes such a process is called simply Markov Chain.

    Continuous-time

    markov chain

    A stochastic process that satisfies the Markovian property and has a continuous

    time parameter. Sometimes such a process is called a Markov Process.

    2.9 Discrete Time Markov Chains

    We now investigate a finite-state stochastic process in which the defining random variables are

    observed at discrete points in time. When the future probabilistic behaviour of the process depends

    only on the present state regardless of when the present state is measured, the resultant model is

    called a Markov chain. When time is measured in discrete intervals the model is called the Discrete

    Time Markov Chain (DTMC). The term Markov Chain is more general that DTMC because it also

    includes continuous time processes called Continuous Time Markov Chains (CTMC).We consider

    CTMC in a later section. We use the term Markov chain when a comment refers to both CTMC and

    DTMC.

    Unlike most stochastic processes, Markov chains have very agreeable properties allowing for easy

    study. Often they are used to approximate quite complex physical systems, even when it is clear that

    the actual behavior of the system being analyzed may depend on more than just the present state, or

    when the number of states is not really finite.

    To develop a model of a DTMC we need to define the system states S and specify the one-step

    transition matrix P. Given this information, computational procedures are available to answer

    questions related to the steady-state behavior of the DTMC. In particular we can compute: the t-step

    transition matrix, transient and steady-state probability vectors, absorbing state probabilities,

    and first passage probability distributions. Integrating these results with economic data leads

    directly to a framework for systems design and optimal decision making under uncertainty.

    2.9.1 Example problem Computer repair

    A real estate office that relies on two aging computers for word processing is experiencing high

    costs and great inconvenience due to chronic machine failures. It has been observed that when both

    computers are working in the morning, there is a 30% chance that one will fail by evening and a

    10% chance that both will fail. If it happens that only one computer is working at the beginning of

    the day, there is a 20% chance that it will fail by the close of business. If neither is working in the

    morning, the office sends all work to a typing service. In this case, of course, no machines will fail

    during the day. Service orders are placed with a local repair shop. The computers are picked up

    during the day and returned the next morning in operating condition. The one-day delay is

    experienced when either one or both machines are under repair.

    Time:

  • 35

    For a DTMC, the system is observed at discrete points in time that are indexed with the nonnegative

    integers. Time t = 0 is the initial point of observation. It is important to identify carefully the exact

    moment when the system is to be observed in relation to the events described by the problem

    statement. For the example, the system is to be observed in the morning after any repaired

    computers are returned and before any failures have occurred during the current day.

    State:

    The state describes the situation at a point in time. Because the states are required to be discrete

    they can be identified with nonnegative integers 0, 1, 2, 3... and so on. There may be a finite or an

    infinite number of states. For this introductory discussion, it is easier to concentrate on the finite

    case and use m - 1 as the maximum state index. The sequence of random variables

    is the stochastic process that describes the state at time t. Each can take one of m values.

    Depending on the situation, the state may be very complex or very simple. We use a v-dimensional

    vector of state variables to define the state.

    In constructing a model, it must be made clear what the one-to-one relationships are between the

    possible state vectors and the nonnegative integers used to identify a state in a DTMC. We call the

    state associated with index i, . Depending on the context, i typically ranges from 0 to m - 1 or from

    1 to m. The state definition must encompass all possible states; however, the system can reside in

    only one state at any given time.

    The computer repair example allows a simple state definition with only one component, s =

    (n), where n is the number of computers that have failed when the system is observed in the

    morning. Note that the system is observed after the repaired units are delivered but before any

    failures occur. The value of m is 3. In this case, the state index is conveniently identical to the

    variable defining the state; however, this relationship will not always be true. We assign a cost of

    operating the system for one day that depends on how many computers are failed. The cost is $50

    per computer failed. This cost is a function of the state.

    Index s State definitions Cost

    0

    No computers have failed. The office starts the day with

    both computers functioning properly. 0

    1

    One computer has failed. The office starts the day with one

    working computer and the other in the shop until the next

    morning.

    50

    2

    Both computers have failed. All work must be sent out for

    the day. 100

  • 36

    Events:

    To understand the behaviour of a DTMC, it is necessary to identify the events that might occur

    during a single time period and to describe their probabilities of occurrence. Generally, the set of

    possible events and their probabilities depend on the state s.

    Given some current state at the beginning of a period and one or more events occurring during the

    period, the system will be in some new (next) state at the beginning of the next period. This

    occurrence is called a transition. One or more events may occur within the period, and by observing

    them, we must identify the resulting new state at the beginning of the next period.

    For the computer example we list the current states together with the set of possible events that

    might occur during the day. Given the current state and the problem description, one must be able to

    determine the probability of every possible transition for the upcoming period. We use coloured

    bands to distinguish the states. Note that each state has one or more associated events and that the

    sum of the probabilities for each state must equal 1. The cost column represents the repair cost of

    the computers assumed to be $40 per computer repaired.

    Index s Events Probability Next

    state Cost

    0

    Neither computer fails. 0.6 (0) 0

    One computer fails. 0.3 (1) 40

    Both computers fail. 0.1 (2) 80

    1

    The remaining computer does not fail

    and the other is returned. 0.8 (0) 0

    The remaining computer fails and the

    other is returned. 0.2 (1) 40

    2

    Both computers have failed. No failures

    can occur. 1.0 (0) 0

    State-transition matrix:

    The major properties of a DTMC model can be described with the m x m state-transition

    matrix P whose rows and columns are labelled 0 through m-1. An element of the matrix, is the

    probability that given the system is in state i at some time t, the system will be in state j at time t+1.

    A requirement of a DTMC is that the transition probability depends only on the current state i and

    not on the particular path that the process takes to reach state i.

  • 37

    The state indices are shown to the right and above the matrix.

    Some general characteristics of the transition matrix are as follows.

    - The elements of a row must sum to 1. This follows from the logical requirement that the

    states define every possible condition for the system.

    - All elements are between 0 and 1. This follows from the definition of probability.

    State-transition network:

    The information in the transition matrix can also be displayed in a directed network which has a

    node for each state and an arc passing from state i to state j if is nonzero. The figure depicts the

    network for the computer repair example. Transition probabilities are adjacent to the arcs. A

    requirement is that the sum of all probabilities leaving a node must be 1.

    Complete model:

    A DTMC model requires the specification of the following:

    - The times when the system is to be observed.

    - The discrete states in which the system may be found. The list of states must be exhaustive.

    In addition, a one-to-one correspondence must be prescribed between the states and the

    nonnegative integers.

    - The state-transition matrix showing the transition probabilities in one time interval.

    Transition probabilities must satisfy the Markovian property, and every row must sum to

    one.

    Although the model structure is easily stated it is not always easy to realize. For example, one might

    propose time and state definitions (parts (1) and (2) above) for which the Markovian property is not

    satisfied. This may sometimes be remedied by a more complex state definition.

    Because a DTMC model is very general it can be used to describe many interesting stochastic

    systems. In many cases, however, the number of states required to adequately define the model is

  • 38

    very large. As with dynamic programming, this "curse of dimensionality" frequently arises when

    we try to identify all possible states of the system.

    2.10 Continuous Time Markov Chains

    A natural extension of a DTMC occurs when time is treated as a continuous parameter. In this

    section, we consider continuous-time, discrete-state stochastic processes but limit our attention to

    the case where the Markovian property holds; that is, the future realization of a system depends

    only on the current state and the random events that proceed from it. This is called a Continuous

    Time Markov Chain (CTMC). Sometimes we use the term Markov Process for this kind of system.

    It happens that the Markov property is only satisfied in a continuous-time stochastic process if all

    activity durations are exponentially distributed. Although this may sound somewhat restrictive,

    many practical situations can be modelled as CTMC and many powerful analytical results can be

    obtained. A primary example is an M/M/s queuing system in which customer arrivals and service

    times follow an exponential distribution. Because it is possible to compute the steady-state

    probabilities for such systems, it is also possible to compute many performance-related statistics

    such as the average wait and the average number of customers in the queue. In addition, many

    critical design and operational questions can be answered with little computational effort.

    2.10.1 Example problem ATM machine

    To illustrate the elements of the stochastic process model, we use the example of a single

    Automated Teller Machine (ATM) located in foyer of a bank. The ATM performs banking

    operations for people arriving for service. The machine is used by only one person at a time, and

    that person said to be in service. Others arriving when the machine is busy must wait in a single

    queue, and these people are said to be in the queue. Following the rule of first-come-first-served, a

    person in the queue will eventually enter service and will ultimately leave the system. The number

    in the system is the total of the number in service plus the number in the queue. The foyer is limited

    in size so that it can hold only five people. Since the weather is generally bad in this part of the

    country, when the foyer is full, arriving people do not enter. We have gathered statistics on ATM

    usage that show the time between arrivals averages 30 seconds (or 0.5 minutes). The time for

    service averages 24 seconds (or 0.4 minutes). Although the ATM has sufficient capacity to meet all

    demand, we frequently observe queues at the machine and occasionally customers are lost.

    We want to perform an analysis to determine statistical measures that describe the number of people

    in the system, the waiting time for customers, the efficiency of the ATM machine, and the number

    of customers not served because there is no room in the foyer. We intend to use these statistics to

    guide managers in design questions such as whether another ATM should be installed, or whether

    the size of the foyer should be expanded.

    One way to describe the process associated with this situation is in the state-transition network. The

    state is the number of customers in the foyer. A change in state occurs when we have an arrival (a)

    or a departure (d). When the foyer opens in the morning, the system is empty -- in state 0. As

    customers arrive the state increases. Since there is only one machine, customers must wait in a

    queue when the state is greater than one. The state index increase