Operation NEXT – The Hyperion Reuse and Resilience Program
Chris Repp, P.E., M.S.C.E.Los Angeles Department of Water and Power
December 19, 2019Santa Monica Basin GSA Briefing
ladwp.com
LADWP Overview
• Largest municipal utility in US• 4 million City residents• 500,000+ AFY Demand • 731,000 service connections• 7,325+ miles of pipeline• City Charter - “supply and
distribute any water owned or controlled by the City”
ladwp.com
LA Water Sources
LA Aqueducts
Colorado River Aqueduct
Conservation & Recycling
Delta
State Water Project
SierraMountains
Local Groundwater & Stormwater
ladwp.com
Groundwater Rights
Primary Groundwater Basins
San Fernando Basin 87,000 AFY
Central Basin 17,236 AFY
Sylmar Basin 3,570 AFY
West Coast Basin 1,503 AFY
LA’s Total Groundwater 109,309 AFYWEST
COAST
CENTRAL
SYLMAR
SAN FERNANDO
EAGLE ROCK
Goal: Bring back use of local basins
ladwp.com
MWD9%
Los Angeles Aqueduct
19%
RW NPR4%
RW GWR32%
Groundwater17%
Stormwater2%
New Conservation
17%
Fiscal Year 2034 - 35 Average HydrologyTotal Supply: 661,800 AFY
MWD59%
Los Angeles Aqueduct
27%
Recycled Water
2%
Groundwater12%
Fiscal Year End 2014 - 18 AverageTotal Production: 523,100 AFY
14% Local
72% Local
Water Supply Future
L.A.’s Green New Deal
ladwp.com
MWD17%
Los Angeles Aqueduct
67%
Recycled Water
2%
Groundwater14%
April 2019 - March 2020Total Supply: 532,400 AFY
MWD9%
Los Angeles Aqueduct
19%
RW NPR4%
RW GWR32%
Groundwater17%
Stormwater2%
New Conservation
17%
Fiscal Year 2034 - 35 Average HydrologyTotal Supply: 661,800 AFY
16% Local
72% Local
Water Supply Future
L.A.’s Green New Deal
ladwp.com
Hyperion Reuse & Water Resilience Program
Program Objective:Recycle 100% of available treated wastewater for
beneficial reuse from the Hyperion Water
Reclamation Plant by 2035.
ladwp.com
Hyperion Water Reclamation Plant
Pacific Ocean
ladwp.com
Hyperion Advanced Treatment
1. Membrane bioreactors 2. Reverse osmosis 3. Advanced oxidation
ladwp.com
Program components
DCT
Hyperion
JWPCP
Terminal Island
Vander Lans
Diemer
ARC
Weymouth
LAG
Los Angeles Aqueduct
Filtration Plant
ladwp.com
Program components
DCT
Hyperion
JWPCP
Terminal Island
Vander Lans
Diemer
ARC
Weymouth
LAG
Los Angeles Aqueduct
Filtration Plant
ladwp.com
Program components
DCT
Hyperion
JWPCP
Terminal Island
Vander Lans
Diemer
ARC
Weymouth
LAG
Distribution System
Los Angeles Aqueduct
Filtration Plant
Possibilities:1. inject, extract, treat, distribute2. DPR3. RWA ahead of treatment
ladwp.com
Program components
DCT
Hyperion
JWPCP
Terminal Island
Vander Lans
Diemer
ARC
Weymouth
LAG
Rio Honda
Santa Fe
Orange County
Distribution System
Los Angeles Aqueduct
Filtration Plant
Possibilities:1. Backbone SF Pump GW2. RWA at Weymouth3. Hyperion Barrier Desalter Distribution
ladwp.com
Program components
Lopez
Hansen
Tujunga
Branford
Pacoima
BalboaPS
DCT
Hyperion
JWPCP
Terminal Island
Vander Lans
Diemer
ARC
Rio Honda
Santa Fe Weymouth
LAG
Orange County
Los Angeles Aqueduct
Filtration Plant
Distribution System
Possibilities:1. Hyperion PS
2. Spreading Grounds2. RWA at LAAFP
ladwp.com15
ladwp.com
Challenges• Focus away from groundwater recharge to DPR
(water recycling criteria for Direct Potable Reuse through Raw Water Augmentation by December 31, 2023)
• In-City Construction• Hyperion Advanced Water Treatment Facility
– Brine Management– Equalization Storage
• Complex groundwater governance structure• Inter-jurisdictional planning• Basin Specific Storage and
Augmentation rules
ladwp.com
Program Partners
How do you collaborate, align goals, and benefit the whole region?
ladwp.com
Ongoing Efforts
• Coordination with partnering agencies (LASAN, WRD, MWD)• Engaging Potential partners – Local Cities, Contract Agencies• DPR Regulations• Financial Plan• Resource Planning• Internal Studies• Pilot Studies• Community Engagement and Outreach Plan
ladwp.com
Recycled Water AvailabilityHyperion Effluent 260 MGDWBMWD 35 MGDWBMWD Future Demand 5 MGDWest Coast Seawater Barrier (Desalter)
10 MGD
In-Plant Consumptive Uses 10 MGDSubtotal 200 MGD
RO brine loss (-15%) 30 MGD
Recycled Water Availability 170 MGD190,400 AFY