operation and maintenance manual - microsoft...5 the riprap has shifted, maintenance may be required...

22
June, 2009 MONUMENT ACADEMY Operation and Maintenance Manual for Extended Detention Basins (EDBs)

Upload: others

Post on 13-Mar-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

June, 2009

MONUMENT ACADEMY

Operation and Maintenance Manual for

Extended Detention Basins(EDBs)

Page 2: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

2

TABLE OF CONTENTS

EDB-1 BACKGROUND...........................................................................................3EDB-2 INSPECTING EXTENDED DETENTION BASINS (EDBS) .........................3

EDB-2.1 ACCESS AND EASEMENTS............................................................................3EDB-2.2 STORMWATER BEST MANAGEMENT PRACTICE (BMP) LOCATIONS ..................3EDB-2.3 EXTENDED DETENTION BASIN (EDB) FEATURES ...........................................3

EDB-2.3.1 Inflow Points ....................................................................................4EDB-2.3.2 Forebay ...........................................................................................5EDB-2.3.3 Trickle Channel (Low-Flow) .............................................................6EDB-2.3.4 Bottom Stage ...................................................................................7EDB-2.3.5 Micropool .........................................................................................8EDB-2.3.6 Outlet Works ....................................................................................9EDB-2.3.7 Emergency Spillway ......................................................................10EDB-2.3.8 Upper Stage (Dry Storage) ............................................................11EDB-2.3.9 Miscellaneous ................................................................................12

EDB-2.4 INSPECTION FORMS ..................................................................................13EDB-3 MAINTAINING EXTENDED DETENTION BASINS (EDBS).......................13

EDB-3.1 MAINTENANCE PERSONNEL .......................................................................13EDB-3.2 EQUIPMENT ..............................................................................................13EDB-3.3 SAFETY....................................................................................................14EDB-3.4 MAINTENANCE FORMS...............................................................................14EDB-3.5 MAINTENANCE CATEGORIES AND ACTIVITIES...............................................14EDB-3.6 ROUTINE MAINTENANCE ACTIVITIES ...........................................................15

EDB-3.6.1 Mowing ..........................................................................................15EDB-3.6.2 Trash/Debris Removal ...................................................................16EDB-3.6.3 Outlet Works Cleaning...................................................................16EDB-3.6.4 Weed Control.................................................................................16EDB-3.6.5 Mosquito/Algae Treatment.............................................................16

EDB- 3.7 RESTORATION MAINTENANCE ACTIVITIES ...................................................17EDB-3.7.1 Sediment Removal ........................................................................17EDB-3.7.2 Erosion Repair ...............................................................................18EDB-3.7.3 Vegetation Removal/Tree Thinning ...............................................18EDB-3.7.4 Clearing Drains/Jet-Vac.................................................................18

EDB-3.8 REHABILITATION MAINTENANCE ACTIVITIES................................................19EDB-3.8.1 Major Sediment Removal ..............................................................19EDB-3.8.2 Major Erosion Repair .....................................................................20EDB-3.8.3 Structural Repair............................................................................20

Page 3: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

3

EDB-1 BACKGROUND

Extended Detention Basins (EDBs) are one of the most common types ofStormwater BMPs utilized within the Front Range of Colorado. An EDB is asedimentation basin designed to “extend” the runoff detention time, but to draincompletely dry sometime after stormwater runoff ends. The EDB’s drain time for thewater quality portion of the facility is typically 40 hours. The basins are consideredto be “dry” because the majority of the basin is designed not to have a significantpermanent pool of water remaining between runoff events.

EDBs are an adaptation of a detention basin used for flood control, with the primarydifference is the addition of forebays, micropools and a slow release outlet design.Forebays are shallow concrete “pans” located at the inflow point to the basin and areprovided to facilitate sediment removal within a contained area prior to releasing intothe pond. These forebays collect and briefly hold stormwater runoff resulting in aprocess called sedimentation, dropping sediment out of the stormwater. Thestormwater is then routed from the forebay into the concrete trickle channel andupper basin, the large grassy portion of the basin. The EDB uses a much smalleroutlet that extends the emptying time of the more frequently occurring runoff eventsto facilitate pollutant removal. An EDB should have a small micropool just upstreamof the outlet. This micropool is designed to hold a small amount of water to keepsediment and floatables from blocking the outlet orifices.

EDB-2 INSPECTING EXTENDED DETENTION BASINS (EDBs)

EDB-2.1 Access and Easements

Inspection or maintenance personnel may utilize the figures located in theapproved Final Drainage Report for the project and recorded subdivision platcontaining the location(s) of the access points and potential maintenanceeasements of the EDB(s) within this development.

EDB-2.2 Stormwater Best Management Practice (BMP) Locations

Inspection or maintenance personnel may utilize the figures located in theapproved Final Drainage Report for the project and recorded subdivision platcontaining the location(s) of the EDB(s) within this development.

EDB-2.3 Extended Detention Basin (EDB) Features

EDBs have a number of features that are designed to serve a particular function.Many times the proper function of one feature depends on another. Forexample, if a forebay is not properly maintained, it could negatively affect theperformance of a feature downstream (trickle channel, micropool, etc.).

Page 4: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

4

Therefore, it is critical that each feature of the EDB is properly inspected andmaintained to ensure that the overall facility functions as it was intended. Belowis a list and description of the most common features within an EDB and thecorresponding maintenance inspection items that can be anticipated:

Table EDB-1Typical Inspection & Maintenance Requirements Matrix

EDB Features SedimentRemoval

Mowing/Weed

control

Trash &Debris

Removal

Erosion OvergrownVegetationRemoval

StandingWater

(mosquito/algae

control)

StructureRepair

Inflow Points(outfalls)

X X X

Forebay X X XLow-flow

channelX X X X X

Bottom Stage X X X X X XMicropool X X X X XOutlet Works X X XEmergencySpillway

X X X X

Upper Stage X XEmbankment X X X

EDB-2.3.1 Inflow Points

Inflow Points or Outfalls into EDBs are the point source of thestormwater discharge into the facility. An inflow point is commonly astorm sewer pipe with a flared end section that discharges into theEDB. In some instances, an inflow point could be a drainage channelor ditch that flows into the facility.

An energy dissipater (riprap or hard armor protection) is typicallyimmediately downstream of the discharge point into the EDB to protectfrom erosion. In some cases, the storm sewer outfall can have a toe-wall or cut-off wall immediately below the structure to preventundercutting of the outfall from erosion.

The typical maintenance items that are found with inflow points are asfollows:

a. Riprap Displaced – Many times, because the repeated impact/forceof water, the riprap can shift and settle. If any portion of the riprapapron appears to have settled, soil is present between the riprap, or

Page 5: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

5

the riprap has shifted, maintenance may be required to ensure futureerosion is prevented.

b. Erosion Present/Outfall Undercut – In some situations, the energydissipater may not have been sized, constructed, or maintainedappropriately and erosion has occurred. Any erosion within the vicinityof the inflow point will require maintenance to prevent damage to thestructure(s) and sediment transport within the facility.

c. Sediment Accumulation – Because of the turbulence in the watercreated by the energy dissipater, sediment often deposits immediatelydownstream of the inflow point. To prevent a loss in hydraulicperformance of the upstream infrastructure, sediment that accumulatesin this area must be removed in a timely manner.

d. Structural Damage – Structural damage can occur at anytime duringthe life of the facility. Typically, for an inflow, the structural damageoccurs to the pipe flared end section (concrete or steel). Structuraldamage can lead to additional operating problems with the facility,including loss of hydraulic performance.

e. Woody Growth/Weeds Present – Undesirable vegetation can growin and around the inflow area to an EDB that can significantly affect theperformance of the drainage facilities discharging into the facility. Thistype of vegetation includes trees (typically cottonwoods) and denseareas of shrubs (willows). If woody vegetation is not routinelymowed/removed, the growth can cause debris/sediment toaccumulate, resulting in blockage of the discharge. Also, tree rootscan cause damage to the structural components of the inflow. Routinemaintenance is essential for trees (removing a small tree/sapling ismuch cheaper and “quieter” than a mature tree). In addition, noxiousweeds growing in the facility can result in the loss of desirable nativevegetation and impact adjacent open spaces/land.

EDB-2.3.2 Forebay

A forebay is a solid surface (pad), typically constructed of concrete,immediately downstream of the inflow point. The forebay is designedto capture larger particles and trash to prevent them from entering themain portion of the EDB. The solid surface is designed to facilitatemechanical sediment removal (skid steer). The forebay typicallyincludes a small diameter discharge pipe or v-notch weir on thedownstream end and designed to drain the forebay in a specifiedperiod of time to promote sedimentation. The forebays vary in sizeand depth depending on the design and site constraints.

Page 6: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

6

The typical maintenance items that are found with forebays are asfollows:

a. Sediment/Debris Accumulation – Because this feature of the EDB isdesigned to provide the initial sedimentation, debris and sedimentfrequently accumulate in this area. If the sediment and debris is notremoved from the forebay on a regular basis, it can significantly affectthe function of other features within the EDB. Routine sedimentremoval from the forebay can significantly reduce the need fordredging of the main portion of the EDB using specialized equipment(long reach excavators). Routine removal of sediment from theforebay can substantially decrease the long-term sediment removalcosts of an EDB.

b. Concrete Cracking/Failing – The forebay is primarily constructed ofconcrete, which cracks, spalls, and settles. Damage to the forebaycan result in deceased performance and impact maintenance efforts.

c. Drain Pipe/Weir Clogged – Many times the drainpipe or weir can beclogged with debris, and prevent the forebay from draining properly. Ifstanding water is present in the forebay (and there is not a base flow),the forebay is most likely not draining properly. This can result in adecrease in performance and create potential nuisances with stagnantwater (mosquitoes).

d. Weir/Drain Pipe Damaged – Routine maintenance activities,vandalism, or age may cause the weir or drain pipe in the forebay tobecome damaged. Weirs are typically constructed of concrete, whichcracks and spalls. The drainpipe is typically smaller in diameter andconstructed with plastic, which can fracture.

EDB-2.3.3 Trickle Channel (Low-Flow)

The trickle channel conveys stormwater from the forebay to the micro-pool of the EDB. The trickle channel is typically made of concrete.However, grass lined (riprap sides protected) is also common and canprovide for an additional means of water quality within the EDB. Thetrickle channel is typically 6-9 inches in depth and can vary in width.

The typical maintenance items that are found with trickle channels areas follows:

a. Sediment/Debris Accumulation – Trickle channels are typicallydesigned with a relatively flat slope that can promote sedimentationand the collection of debris. Also, if a trickle channel is grass lined itcan accumulate sediment and debris at a much quicker rate. Routine

Page 7: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

7

removal of accumulated sediment and debris is essential in preventingflows from circumventing the trickle channel and affecting the drystorage portion of the pond.

b. Concrete/Riprap Damage – Concrete can crack, spall, and settleand must be repaired to ensure proper function of the trickle channel.Riprap can also shift over time and must be replaced/repaired asnecessary.

c. Woody Growth/Weeds Present – Because of the constant moisturein the area surrounding the trickle channel, woody growth(cottonwoods/willows) can become a problem. Trees and dense shrubtype vegetation can affect the capacity of the trickle channel and canallow flows to circumvent the feature.

d. Erosion Outside of Channel – In larger precipitation events, thetrickle channel capacity will likely be exceeded. This can result inerosion immediately adjacent to the trickle channel and must berepaired to prevent further damage to the structural components of theEDB.

EDB-2.3.4 Bottom Stage

The bottom stage is at least 1.0 to 2.0 feet deeper than the upperstage and is located in front of the outlet works structure. The bottomstage is designed to store the smaller runoff events, assists in keepingthe majority of the basin bottom dry resulting in easier maintenanceoperations, and enhances the facilities pollutant removal capabilities.This area of the EDB may develop wetland vegetation.

The typical maintenance items that are found with the bottom stage areas follows:

a. Sediment/Debris Accumulation – The micro-pool can frequentlyaccumulate sediment and debris. This material must be removed tomaintain pond volume and proper function of the outlet structure.

b. Woody Growth/Weeds Present - Because of the constant moisturein the soil surrounding the micro-pool, woody growth(cottonwoods/willows) can create operational problems for the EDB. Ifwoody vegetation is not routinely mowed/removed, the growth cancause debris/sediment to accumulate outside of the micro-pool, whichcan cause problems with other EDB features. Also, tree roots cancause damage to the structural components of the outlet works.Routine management is essential for trees (removing a smalltree/sapling is much cheaper and “quieter” than a mature tree).

Page 8: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

8

c. Bank Erosion – The micro-pool is usually a couple feet deeper thanthe other areas of the ponds. Erosion can be caused by waterdropping into the micro-pool if adequate protection/armor is notpresent. Erosion in this area must be mitigated to prevent sedimenttransport and other EDB feature damage.

d. Mosquitoes/Algae Treatment – Nuisance created by stagnant watercan result from improper maintenance/treatment of the micro-pool.Mosquito larvae can be laid by adult mosquitoes within the permanentpool. Also, aquatic vegetation that grows in shallow pools of water candecompose causing foul odors. Chemical/mechanical treatment of themicro-pool may be necessary to reduce these impacts to adjacenthomeowners.

e. Petroleum/Chemical Sheen – Many indicators of illicit dischargesinto the storm sewer systems will be present in the micro-pool area ofthe EDB. These indicators can include sheens, odors, discolored soil,and dead vegetation. If it is suspected that an illicit discharge hasoccurred, contact the supervisor immediately. Properremoval/mitigation of contaminated soils and water in the EDB isnecessary to minimize any environmental impacts downstream.

EDB-2.3.5 Micro-pool

The micro-pool is a concrete or grouted boulder walled structuredirectly in front of the outlet works. At a minimum, the micropool is 2.5feet deep and is designed to hold water. The micro-pool is critical inthe proper function of the EDB; it allows suspended sediment to bedeposited at the bottom of the micro-pool and prevents thesesediments from being deposited in front of the outlet works causingclogging of the outlet structure, which results in marshy areas withinthe top and bottom stages.

The typical maintenance items that are found with micro-pools are asfollows:

a. Sediment/Debris Accumulation – The micro-pool can frequentlyaccumulate sediment and debris. This material must be removed tomaintain pond volume and proper function of the outlet structure.

b. Woody Growth/Weeds Present - Because of the constant moisturein the soil surrounding the micro-pool, woody growth(cottonwoods/willows) can create operational problems for the EDB. Ifwoody vegetation is not routinely mowed/removed, the growth cancause debris/sediment to accumulate outside of the micro-pool, which

Page 9: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

9

can cause problems with other EDB features. Also, tree roots cancause damage to the structural components of the outlet works.Routine management is essential for trees (removing a smalltree/sapling is much cheaper and “quieter” than a mature tree).

c. Mosquitoes/Algae Treatment – Nuisance created by stagnant watercan result from improper maintenance/treatment of the micro-pool.Mosquito larvae can be laid by adult mosquitoes within the permanentpool. Also, aquatic vegetation that grows in shallow pools of water candecompose causing foul odors. Chemical/mechanical treatment of themicro-pool may be necessary to reduce these impacts to adjacenthomeowners.

d. Petroleum/Chemical Sheen – Many indicators of illicit dischargesinto the storm sewer systems will be present in the micro-pool area ofthe EDB. These indicators can include sheens, odors, discolored soil,and dead vegetation. If it is suspected that an illicit discharge hasoccurred, contact the supervisor immediately. Properremoval/mitigation of contaminated soils and water in the EDB isnecessary to minimize any environmental impacts downstream.

EDB-2.3.6 Outlet Works

The outlet works is the feature that drains the EDB in specifiedquantities and periods of time. The outlet works is typicallyconstructed of reinforced concrete into the embankment of the EDB.The concrete structure typically has steel orifice platesanchored/embedded into it to control stormwater release rates. Thelarger openings (flood control) on the outlet structure typically havetrash racks over them to prevent clogging. The water quality orificeplate (smaller diameter holes) will typically have a well screen coveringit to prevent smaller materials from clogging it. The outlet structure isthe single most important feature in the EDB operation. Properinspection and maintenance of the outlet works is essential in ensuringthe long-term operation of the EDB.

The typical maintenance items that are found with the outlet works areas follows:

a. Trash Rack/Well Screen Clogged – Floatable material that entersthe EDB will most likely make its way to the outlet structure. Thismaterial is trapped against the trash racks and well screens on theoutlet structure (which is why they are there). This material must beremoved on a routine basis to ensure the outlet structure drains in thespecified design period.

Page 10: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

10

b. Structural Damage - The outlet structure is primarily constructed ofconcrete, which can crack, spall, and settle. The steel trash racks andwell screens are also susceptible to damage.

c. Orifice Plate Missing/Not Secure – Many times residents, propertyowners, or maintenance personnel will remove or loosen orifice platesif they believe the pond is not draining properly. Any modification tothe orifice plate(s) will significantly affect the designed discharge ratesfor water quality and/or flood control. Modification of the orifice platesis not allowed without approval from the County.

d. Manhole Access – Access to the outlet structure is necessary toproperly inspect and maintain the facility. If access is difficult or notavailable to inspect the structure, chances are it will be difficult tomaintain as well.

e. Woody Growth/Weeds Present - Because of the constant moisturein the soil surrounding the outlet works, woody growth(cottonwoods/willows) can create operational problems for the EDB. Ifwoody vegetation is not routinely mowed/removed, the growth cancause debris/sediment to accumulate around the outlet works, whichcan cause problems with other EDB features. Also, tree roots cancause damage to the structural components of the outlet works.Routine management is essential for trees (removing a smalltree/sapling is much cheaper and “quieter” than a mature tree).

EDB-2.3.7 Emergency Spillway

An emergency spillway is typical of all EDBs and designed to serve asthe overflow in the event the volume of the pond is exceeded. Theemergency spillway is typically armored with riprap (or other hardarmor) and is sometimes buried with soil. The emergency spillway istypically a weir (notch) in the pond embankment. Proper function ofthe emergency spillway is essential to ensure flooding does not affectadjacent properties.

The typical maintenance items that are found with emergencyspillways are as follows:

a. Riprap Displaced – As mentioned before, the emergency spillway istypically armored with riprap to provide erosion protection. Over thelife of an EDB, the riprap may shift or dislodge due to flow.

b. Erosion Present – Although the spillway is typically armored,stormwater flowing through the spillway can cause erosion damage.

Page 11: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

11

Erosion must be repaired to ensure the integrity of the basinembankment, and proper function of the spillway.

c. Woody Growth/Weeds Present – Management of woody vegetationis essential in the proper long-term function of the spillway. Largertrees or dense shrubs can capture larger debris entering the EDB andreduce the capacity of the spillway.

d. Obstruction Debris – The spillway must be cleared of anyobstruction (man made or natural) to ensure the proper designcapacity.

EDB-2.3.8 Upper Stage (Dry Storage)

The upper stage of the EDB provides the majority of the water qualityflood detention volume. This area of the EDB is higher than the micro-pool and typically stays dry, except during storm events. The upperstage is the largest feature/area of the basin. Sometimes, the upperstage can be utilized for park space and other uses in larger EDBs.With proper maintenance of the micro-pool and forebay(s), the upperstage should not experience much sedimentation; however, bottomelevations should be monitored to ensure adequate volume.

The typical maintenance items that are found with upper stages are asfollows:

a. Vegetation Sparse – The upper basin is the most visible part of theEDB, and therefore aesthetics is important. Adequate and properlymaintained vegetation can greatly increase the overall appearance andacceptance of the EDB by the public. In addition, vegetation canreduce the potential for erosion and subsequent sediment transport tothe other areas of the pond.

b. Woody Growth/Undesirable Vegetation – Although some trees andwoody vegetation may be acceptable in the upper basin, some thinningof cottonwoods and willows may be necessary. Remember, the basinwill have to be dredged to ensure volume, and large trees and shrubswill be difficult to protect during that operation.

c. Standing Water/Boggy Areas – Standing water or boggy areas in theupper stage is typically a sign that some other feature in the pond isnot functioning properly. Routine maintenance (mowing, trashremoval, etc) can be extremely difficult for the upper stage if theground is saturated. If this inspection item is checked, make sure youhave identified the root cause of the problem.

Page 12: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

12

d. Sediment Accumulation – Although other features within the EDBare designed to capture sediment, the upper storage area will collectsediment over time. Excessive amounts of sedimentation will result ina loss of storage volume. It may be more difficult to determine if thisarea has accumulated sediment without conducting a field survey.

Below is a list of indicators:1. Ground adjacent to the trickle channel appears to be several

inches higher than concrete/riprap2. Standing water or boggy areas in upper stage3. Uneven grades or mounds4. Micro-pool or Forebay has excessive amounts of sediment

e. Erosion (banks and bottom) – The bottom grades of the dry storageare typically flat enough that erosion should not occur. However,inadequate vegetative cover may result in erosion of the upper stage.Erosion that occurs in the upper stage can result in increaseddredging/maintenance of the micro-pool.

f. Trash/Debris – Trash and debris can accumulate in the upper areaafter large events, or from illegal dumping. Over time, this material canaccumulate and clog the EDB outlet works.

g. Maintenance Access – Most EDBs typically have a gravel/concretemaintenance access path to either the upper stage or forebay. Thisaccess path should be inspected to ensure the surface is still drivable.Some of the smaller EDBs may not have maintenance access paths;however, the inspector should verify that access is available fromadjacent properties.

EDB-2.3.9 Miscellaneous

There are a variety of inspection/maintenance issues that may not beattributed to a single feature within the EDB. This category on theinspection form is for maintenance items that are commonly found inthe EDB, but may not be attributed to an individual feature.

a. Access – Access needs to be maintained.

b. Graffiti/Vandalism – Damage to the EDB infrastructure can becaused by vandals. If criminal mischief is evident, the inspector shouldforward this information to the local enforcement agency.

c. Public Hazards – Public hazards include items such as verticaldrops of greater than 4-feet, containers of unknown/suspicious

Page 13: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

13

substances, exposed metal/jagged concrete on structures. If anyhazard is found within the facility area that poses an immediatethreat to public safety, contact the local emergency services at911 immediately!

d. Burrowing Animals/Pests – Prairie dogs and other burrowing rodentsmay cause damage to the EDB features and negatively affect thevegetation within the EDB.

e. Other – Any miscellaneous inspection/maintenance items notcontained on the form should be entered here.

EDB-2.4 Inspection Forms

Inspection forms shall be completed by the person(s) conducting the inspectionactivities. These inspection forms shall be kept a minimum of 5 years and madeavailable to the County upon request.

EDB-3 MAINTAINING EXTENDED DETENTION BASINS (EDBS)

EDB-3.1 Maintenance Personnel

Maintenance personnel must be qualified to properly maintain EDBs.Inadequately trained personnel can cause additional problems resulting inadditional maintenance costs.

EDB-3.2 Equipment

It is imperative that the appropriate equipment and tools are taken to the fieldwith the operations crew. The types of equipment/tools will vary depending onthe task at hand. Below is a list of tools, equipment, and material(s) that may benecessary to perform maintenance on an EDB:

1.) Loppers/Tree Trimming Tools2.) Mowing Tractors3.) Trimmers (extra string)4.) Shovels5.) Rakes6.) All Surface Vehicle (ASVs)7.) Skid Steer8.) Back Hoe9.) Track Hoe/Long Reach Excavator10.) Dump Truck

Page 14: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

14

11.) Jet-Vac Machine12.) Engineers Level (laser)13.) Riprap (Minimum - Type M)14.) Filter Fabric15.) Erosion Control Blanket(s)16.) Seed Mix (Native Mix)17.) Illicit Discharge Cleanup Kits18.) Trash Bags19.) Tools (wrenches, screw drivers, hammers, etc)20.) Chain Saw21.) Confined Space Entry Equipment22.) Approved Inspection and Maintenance Plan

Some of the items identified above may not be needed for every maintenanceoperation. However, this equipment should be available to the maintenanceoperations crews should the need arise.

EDB-3.3 Safety

Vertical drops may be encountered in areas located within and around thefacility. Avoid walking on top of retaining walls or other structures that have asignificant vertical drop. If a vertical drop is identified within the EDB that isgreater than 48” in height, make the appropriate note/comment on themaintenance inspection form.

EDB-3.4 Maintenance Forms

An EDB Maintenance Form provides a record of each maintenance operationperformed by maintenance contractors. An EBD Maintenance Form shall befilled out in the field after the completion of the maintenance operation.

EDB-3.5 Maintenance Categories and Activities

A typical EDB Maintenance Program will consist of three broad categories ofwork: Routine, Restoration (minor), and Rehabilitation (major). Within eachcategory of work, a variety of maintenance activities can be performed on anEDB. A maintenance activity can be specific to each feature within the EDB, orgeneral to the overall facility. This section of the SOP explains each of thecategories and briefly describes the typical maintenance activities for an EDB.

A variety of maintenance activities are typical of EDBs. The maintenanceactivities range in magnitude from routine trash pickup to the reconstruction of

Page 15: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

15

drainage infrastructure. Below is a description of each maintenance activity, theobjectives, and frequency of actions:

EDB-3.6 Routine Maintenance Activities

The majority of this work consists of regularly scheduled mowing and trash anddebris pickups for stormwater management facilities during the growing season.This includes items such as the removal of debris/material that may be cloggingthe outlet structure well screens and trash racks. It also includes activities suchas includes weed control, mosquito treatment, and algae treatment. Theseactivities normally will be performed numerous times during the year. Theseitems can be completed without any prior correspondence with the County;however, completed inspection and maintenance forms shall be kept on file.

The Maintenance Activities are summarized below, and further described in thefollowing sections.

TABLE – EDB-2Summary of Routine Maintenance Activities

MAINTENANCEACTIVITY

MINIMUMFREQUENCY

LOOK FOR: MAINTENANCE ACTION

Mowing Twice annually Excessive grassheight/aesthetics

Mow grass to a height of 4” to6”

Trash/Debris Removal Twice annually Trash & debris inEDB

Remove and dispose of trashand debris

Outlet Works Cleaning As needed -after significantrain events –twice annuallymin.

Clogged outletstructure; pondingwater

Remove and dispose ofdebris/trash/sediment to allowoutlet to function properly

Weed control Minimum twiceannually

Noxious weeds;Unwantedvegetation

Treat w/ herbicide or hand pull;Consult the local weedspecialist

Mosquito Treatment As needed Standingwater/mosquitohabitat

Treat w/ EPA approvedchemicals

Algae Treatment As needed Standing water/Algal growth/greencolor

Treat w/ EPA approvedchemicals

EDB-3.6.1 Mowing

Occasional mowing is necessary to limit unwanted vegetation and toimprove the overall appearance of the EDB. Native vegetation should

Page 16: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

16

be mowed to a height of 4-to-6 inches tall. Grass clippings should becollected and disposed of properly.

Frequency – Routine - Minimum of twice annually or depending onaesthetics.

EDB-3.6.2 Trash/Debris Removal

Trash and debris must be removed from the entire EDB area tominimize outlet clogging and to improve aesthetics. This activity mustbe performed prior to mowing operations.

Frequency – Routine – Prior to mowing operations and minimum oftwice annually.

EDB-3.6.3 Outlet Works Cleaning

Debris and other materials can clog the outlet work’s well screen,orifice plate(s) and trash rack. This activity must be performed anytimeother maintenance activities are conducted to ensure proper operation.

Frequency - Routine – After significant rainfall event or concurrentlywith other maintenance activities.

EDB-3.6.4 Weed Control

Noxious weeds and other unwanted vegetation must be treated asneeded throughout the EDB. This activity can be performed eitherthrough mechanical means (mowing/pulling) or with herbicide.Consultation with the local Weed Inspector is highly recommendedprior to the use of herbicide.

Frequency – Routine – As needed based on inspections.

EDB-3.6.5 Mosquito/Algae Treatment

Treatment of permanent pools is necessary to control mosquitoes andundesirable aquatic vegetation that can create nuisances. Only EPAapproved chemicals/materials can be used in areas that are warranted.

Frequency – As needed.

Page 17: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

17

EDB- 3.7 Restoration Maintenance Activities

This work consists of a variety of isolated or small-scale maintenance oroperational problems. Most of this work can be completed by a small crew, tools,and small equipment. These items do not require prior correspondence with theCounty require completed inspection and maintenance forms to be kept on file.

Table – EDB-3Summary of Restoration Maintenance Activities

MAINTENANCEACTIVITY

MINIMUMFREQUENCY

LOOK FOR: MAINTENANCEACTION

Sediment Removal As needed;typically every 1–2 years

Sediment build-up;decrease in pondvolume

Remove and disposeof sediment

Erosion Repair As needed,based uponinspection

Rills/gullies formingon side slopes,trickle channel,other areas

Repair eroded areasRevegetate; addresssource of erosion

Vegetation Removal/TreeThinning

As needed,based uponinspection

Large trees/woodvegetation in lowerchamber of pond

Remove vegetation;restore grade andsurface

Drain Cleaning/Jet Vac As needed,based uponinspection

Sediment build-up/non drainingsystem

Clean drains; Jet Vacif needed

EDB-3.7.1 Sediment Removal

Sediment removal is necessary to maintain the original design volumeof the EDB and to ensure proper function of the infrastructure. Regularsediment removal (minor) from the forebay, inflow(s), and tricklechannel can significantly reduce the frequency of major sedimentremoval activities (dredging) in the upper and lower stages. The minorsediment removal activities can typically be addressed with shovelsand smaller equipment. Major sediment removal activities will requirelarger and more specialized equipment. The major sediment activitiesmay also require surveying with an engineer’s level, and consultationwith the Consulting Engineer or County staff to ensure designvolumes/grades are achieved.

Stormwater sediments removed from EDBs do not meet the criteria of“hazardous waste”. However, these sediments are contaminated witha wide array of organic and inorganic pollutants and handling must bedone with care. Sediments from permanent pools must be carefullyremoved to minimize turbidity, further sedimentation, or other adverse

Page 18: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

18

water quality impacts. Sediments should be transported by motorvehicle only after they are dewatered. All sediments must be taken toa landfill for proper disposal. Prompt and thorough cleanup isimportant should a spill occur during transportation.

Frequency – Nonroutine – As necessary based upon inspections.Sediment removal in the forebay and trickle channel may be necessaryas frequently as every 1-2 years.

EDB-3.7.2 Erosion Repair

The repair of eroded areas is necessary to ensure the proper functionof the EDB, minimize sediment transport, and to reduce potentialimpacts to other features. Erosion can vary in magnitude from minorrepairs to trickle channels, energy dissipaters, and rilling to majorgullies in the embankments and spillways. The repair of eroded areasmay require the use of excavators, earthmoving equipment, riprap,concrete, erosion control blankets, and turf reinforcement mats. Majorerosion repair to the pond embankments, spillways, and adjacent tostructures will require consultation with the Consulting Engineer orCounty Engineering staff.

Frequency – Nonroutine – As necessary based upon inspections.

EDB-3.7.3 Vegetation Removal/Tree Thinning

Dense stands of woody vegetation (willows, shrubs, etc) or trees cancreate maintenance problems for the infrastructure within an EDB.Tree roots can damage structures and invade pipes/channels therebyblocking flows. Also, trees growing in the upper and lower stages ofthe EDB will most likely have to be removed when sediment/dredgingoperations occur. A small tree is easier to remove than a large tree,therefore, regular removal/thinning is imperative. All trees and woodyvegetation that is growing in the bottom of the EDB or near structures(inflows, trickle channels, outlet works, emergency spillways, etc)should be removed. Any trees or woody vegetation in the EDB shouldbe limited to the upper portions of the pond banks.

Frequency – Nonroutine – As necessary based upon inspections.

EDB-3.7.4 Clearing Drains/Jet-Vac

An EDB contains many structures, openings, and pipes that can befrequently clogged with debris. These blockages can result in adecrease of hydraulic capacity and create standing water in areasoutside of the micro-pool. Many times the blockage to this

Page 19: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

19

infrastructure can be difficult to access and/or clean. Specializedequipment (jet-vac machines) may be necessary to clear debris fromthese difficult areas.

Frequency – Nonroutine – As necessary based upon inspections.

EDB-3.8 Rehabilitation Maintenance Activities

This work consists of larger maintenance/operational problems and failureswithin the stormwater management facilities. All of this work requiresconsultation with the Consulting Engineer or County Engineering staff to ensurethe proper maintenance is performed. This work requires that the engineeringstaff review the original design and construction drawings to access the situationand assign the necessary maintenance. This work may also require morespecialized maintenance equipment, design/details, surveying, or assistancethrough private contractors and consultants. Any proper permits required for thisactivity must be obtained.

Table – EDB-4Summary of Rehabilitation Maintenance Activities

MAINTENANCEACTIVITY

MINIMUMFREQUENCY

LOOK FOR: MAINTENANCEACTION

Major Sediment Removal As needed –based uponscheduledinspections

Large quantities ofsediment; reducedpond capacity

Remove and disposeof sediment. Repairvegetation as needed

Major Erosion Repair As needed –based uponscheduledinspections

Severe erosionincluding gullies,excessive soildisplacement, areasof settlement, holes

Repair erosion – findcause of problem andaddress to avoid futureerosion

Structural Repair As needed –based uponscheduledinspections

Deterioration and/ordamage tostructuralcomponents –broken concrete,damaged pipes,outlet works

Structural repair torestore the structure toits original design

EDB-3.8.1 Major Sediment Removal

Major sediment removal consists of removal of large quantities ofsediment or removal of sediment from vegetated areas. Care shall begiven when removing large quantities of sediment and sedimentdeposited in vegetated areas. Large quantities of sediment need to becarefully removed, transported and disposed of. Vegetated areas

Page 20: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

20

need special care to ensure design volumes and grades arepreserved.

Frequency – Nonroutine – Repair as needed based upon inspections.

EDB-3.8.2 Major Erosion Repair

Major erosion repair consist of filling and revegetating areas of severeerosion. Determining the cause of the erosion as well as correcting thecondition that caused the erosion should also be part of the erosionrepair. Care should be given to ensure design grades and volumes arepreserved.

Frequency – Nonroutine – Repair as needed based upon inspections.

EDB-3.8.3 Structural Repair

An EDB includes a variety of structures that can deteriorate or bedamaged during the course of routine maintenance. These structuresare constructed of steel and concrete that can degrade or be damagedand may need to be repaired or re-constructed from time to time.These structures include items like outlet works, trickle channels,forebays, inflows and other features. In-house operations staff canperform some of the minor structural repairs. Major repairs tostructures may require input from a structural engineer and specializedcontractors. Consultation with the Consulting Engineer or CountyEngineering staff should take place prior to all structural repairs.

Frequency – Nonroutine – Repair as needed based upon inspections.

Reference:This Manual is adapted from City of Colorado Springs O&M Procedures, which are adapted fromSEMSWA (2007) and from the Town of Parker, Colorado (2004), STORMWATER PERMANENTBEST MANAGEMENT PRACTICES (PBMP) LONG-TERM OPERATION AND MAINTENANCE

MANUAL

Page 21: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

U3.1

DATE:

DRAWN BY:

CHECKED BY:

REVISED:

OWNERSHIP OF INSTRUMENTS OF SERVICE:

ALL REPORTS, PLANS, SPECIFICATIONS, COMPUTER FILES, FIELDDATA, NOTES AND OTHER DOCUMENTS AND INSTRUMENTSPREPARED BY DESIGN PROFESSIONAL AS INSTRUMENTS OF

SERVICE SHALL REMAIN THE PROPERTY OF THE DESIGNPROFESSIONAL. THE DESIGN PROFESSIONAL SHALL RETAIN ALL

COMMON LAW STATUTORY AND OTHER RESERVED RIGHTSINCLUDING THE COPYRIGHT THERETO.

UTILITY NOTES & DETAILS

BJJ

JPS

1/25/19

4/29/19

MONUMENT

ACADEMY

HIGH SCHOOL

FOR CONSTRUCTION

PROFILE

OFFSET BEND

TYPICAL OFFSET = 6",12",18",24"

CONC. THRUST

BLOCK (TYPICAL)

CONC. THRUST

BLOCK (TYPICAL)

PLACED AGAINST

UNDISTRUDED

SOIL

HYDRANT LATERAL

SHOWING TYPICAL VERTICAL

Tracer wire and test box to be installed with each fire hydrant.1.)

Mechanical joint restraints 1.)

NOTE:

GROUND LEVEL

TEST BOX

MECHANICAL JOINT

RESTRAINTS (TYP.)

CROSS INSTALLATION

RESTRAINTS (TYP.)

MECHANICAL JOINT

MECHANICAL

RESTRAINTS (TYP.)

TEE INSTALLATION

MECHANICAL JOINT

LENGTH OF M-J

SPACER PIPE (TYP.)

MJ VALVE

(TYP.)

RESTRAINT (TYP.)

PIPE *

RESTRAINED

STANDARD PIPE

JOINT BEND

MECHANICAL

JOINT

JOINT

STANDARD PIPE

RESTRAINED PIPE *

LENGTH OF

JOINT

BLOCK REQUIRED

CONCRETE THRUST REACTION

MJ VALVE (TYP.)

SPACER PIPE (TYP.)

VALVE TO BE THE SAME SIZE

AS THE FITTING DIA. (TYP.)

(EXCL. HYDRANT TEE)

VALVE TO BE THE SAME SIZE

AS THE FITTING DIA. (TYP.)

(EXCL. HYDRANT TEE)

Z:\040201.w

ald

en

\d

wg

\civil\W

ALD

EN

P

RESER

VE 2\M

ON

UM

EN

T A

CA

DEM

Y\U

3.1.d

wg

, 4/30/2019 11:51:45 A

M, D

WG

To

P

DF.p

c3

AutoCAD SHX Text
%%UGENERAL UTILITY NOTES:
AutoCAD SHX Text
1. ALL WATER AND SEWER INSTALLATIONS SHALL CONFORM TO WALDEN CORPORATION SPECIFICATIONS, IN THE ABSENCE OF PUBLISHED GUIDANCE, ALL UTILITY WORK SHALL FOLLOW COLORADO SPRINGS UTILITIES STANDARD SPECIFICATIONS. 2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE NOTIFICATION AND FIELD LOCATION OF ALL EXISTING UTILITIES, WHETHER SHOWN ON THE PLANS OR NOT, BEFORE BEGINNING CONSTRUCTION. LOCATION OF EXISTING UTILITIES SHALL BE VERIFIED BY THE CONTRACTOR PRIOR TO ACTUAL CONSTRUCTION. 3. REVEGETATION OF ALL DISTURBED SLOPES SHALL BE DONE WITH DRY LAND GRASS SEED WITHIN 30 DAYS AFTER FINE GRADING IS COMPLETE. 4. STORM DRAIN PIPE SHALL BE RCP (CLASS III) UNLESS OTHERWISE NOTED. 5. STORM DRAIN PIPE BEDDING SHALL BE CLASS C. 6. SANITARY SEWER PIPE SHALL BE PVC ASTM D3034-SDR35 UNLESS OTHERWISE NOTED. 7. STATIONING IS AT CENTERLINE UNLESS OTHERWISE NOTED. 8. ALL ELEVATIONS ARE AT FLOWLINE UNLESS OTHERWISE NOTED. ALL DIMENSIONS ARE FROM FACE OF CURB UNLESS OTHERWISE NOTED. 9. WATER PIPES AND FITTINGS SHALL BE INSTALLED PER WALDEN CORPORATION SPECIFICATIONS. ALL TRENCH BEDDING, THRUST BLOCKS AND REVERSE ANCHORS SHALL BE INSTALLED PER WALDEN STANDARDS. ALL WATER PIPE SHALL BE PVC AWWA C900 (DR14). DISINFECTION AND TESTING SHALL BE COMPLETED PER WALDEN SPECIFICATIONS. 10. LENGTHS SHOWN FOR STORM SEWER PIPES ARE TO CENTER OF MANHOLE. 11. CONTRACTOR SHALL MAKE WATER CONNECTIONS WITHOUT SHUTDOWN OR NOTIFY WALDEN CORPORATION AND AFFECTED RESIDENTS OF ANY SERVICE SHUTDOWNS NECESSARY TO CONNECT TO EXISTING LINES. 12. BENDS, DEFLECTION & CUT PIPE LENGTHS SHALL BE USED TO HOLD HORIZONTAL ALIGNMENT OF SEWER AND WATER LINES TO 10 FEET SEPARATION AT ALL POINTS REQUIRED. ALIGNMENT CONSTRUCTION STAKES SHALL BE PLACED AT 25' INTERVALS ALONG CURVES FOR PLACEMENT OF SEWER AND WATER LINES. 13. FIRE HYDRANT ASSEMBLIES SHALL BE INSTALLED PER WALDEN CORPORATION STANDARDS AND SHALL INCLUDE LATERAL, VALVE, ELBOW, HYDRANT, AND THRUST BLOCKS. 14. WHEREVER DUCTILE IRON PIPE IS USED, THE PIPE, FITTINGS AND HYDRANTS SHALL BE WRAPPED IN POLYETHYLENE. 15. SERVICE LINES SHALL BE INSTALLED PER WALDEN CORPORATION STANDARDS. 16. CONTRACTOR SHALL COORDINATE WITH GAS, ELECTRIC, TELEPHONE AND CABLE T.V. UTILITY SUPPLIERS FOR INSTALLATION OF ALL UTILITIES. MINIMUM COVER FOR ALL UTILITIES SHALL BE 36". 17. UTILITY BEDDING SHALL BE PLACED PER WALDEN CORPORATION REQUIREMENTS. 18. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL EXISTING STRUCTURES, DEBRIS, WASTE AND OTHER UNSUITABLE FILL MATERIAL FOUND WITHIN THE LIMITS OF EXCAVATION. 19. ELECTRONIC FILE OF SITE DRAWING IS AVAILABLE FROM ENGINEER FOR CONSTRUCTION STAKING PURPOSES. 20. REFER TO WALDEN CORPORATION SPECIFICATIONS FOR BACKFILL AND COMPACTION SPECIFICATIONS, ALSO MEET ALL WALDEN CORPORATION BACKFILL SPECIFICATIONS IN THE ROADWAY R.O.W.'S. 21. CONTRACTOR SHALL OBTAIN ALL REQUIRED PERMITS. 22. CONTRACTOR SHALL SUBMIT SHOP DRAWINGS FOR ALL MATERIALS TO WALDEN CORPORATION FOR APPROVAL PRIOR TO BEGINNING WORK. 23. WATER MAIN FITTINGS 5' OR LESS APART REQUIRE ALL-THREAD (2 EA. "). 34"). 24. INSTALLATION OF CURVILINEAR WATER & SANITARY SEWER MAINS SHALL FOLLOW MANUFACTURER'S RECOMMENDATIONS. 25. INSTALL POLY-WRAP AS BOND BREAKER AT ALL THRUST BLOCKS. 26. ANY WATER LINE LOWERINGS UNDER STORM DRAIN SHALL MEET WALDEN CORPORATION SPECIFICATIONS. ANY STEEL SLEEVES IN ROADWAY R.O.W. NEED TO MEET 50-YEAR DESIGN LIFE MINIMUM. 27. SEWER MAINS SHALL BE TV INSPECTED AFTER INSTALLATION FOR APPROVAL BY WALDEN CORPORATION.
AutoCAD SHX Text
19 E. Willamette Ave.
AutoCAD SHX Text
Colorado Springs, CO
AutoCAD SHX Text
80903
AutoCAD SHX Text
PH: 719-477-9429
AutoCAD SHX Text
FAX: 719-471-0766
AutoCAD SHX Text
www.jpsengr.com
AutoCAD SHX Text
100 E. St. Vrain, Suite 300
AutoCAD SHX Text
Colorado Springs, Colorado 80903
AutoCAD SHX Text
ARCHITECTS AIA
AutoCAD SHX Text
NO.
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
DATE
AutoCAD SHX Text
BY
AutoCAD SHX Text
A
AutoCAD SHX Text
B
AutoCAD SHX Text
FOR PERMIT
AutoCAD SHX Text
JPS
AutoCAD SHX Text
4/01/19
AutoCAD SHX Text
TYPICAL WATER MAIN TEE DETAIL 5
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
TYPICAL FIRE HYDRANT DETAIL 1
AutoCAD SHX Text
TYPICAL TRENCH SECTION 2
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
TYPICAL SEWER MANHOLE 3
AutoCAD SHX Text
MECHANICAL JOINT RESTRAINTS 4
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
TYPICAL STORM SEWER TRENCH SECTION 6
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
3. MINIMUM COVER TO BE BELOW OFFICIAL STREET GRADE.
AutoCAD SHX Text
2. TRENCH WALLS TO BE SUPPORTED AS REQUIRED BY O.S.H.A.
AutoCAD SHX Text
MATERIAL
AutoCAD SHX Text
6"
AutoCAD SHX Text
6"
AutoCAD SHX Text
12"
AutoCAD SHX Text
NOTES: 1. PAVING SHALL COMPLY WITH LOCAL AUTHORITY JURISDICTION.
AutoCAD SHX Text
3'-4"
AutoCAD SHX Text
2'-4"
AutoCAD SHX Text
3'-0"
AutoCAD SHX Text
2'-0"
AutoCAD SHX Text
2'-8"
AutoCAD SHX Text
1'-8"
AutoCAD SHX Text
2'-6"
AutoCAD SHX Text
1'-6"
AutoCAD SHX Text
2'-4"
AutoCAD SHX Text
1'-4"
AutoCAD SHX Text
16"
AutoCAD SHX Text
12"
AutoCAD SHX Text
8"
AutoCAD SHX Text
6"
AutoCAD SHX Text
4"
AutoCAD SHX Text
6' COVER MIN.
AutoCAD SHX Text
.
AutoCAD SHX Text
SEE TABLE
AutoCAD SHX Text
WIDTH
AutoCAD SHX Text
BEDDING
AutoCAD SHX Text
LIMITS OF
AutoCAD SHX Text
GRANULAR BEDDING
AutoCAD SHX Text
BACKFILL
AutoCAD SHX Text
COMPACTED
AutoCAD SHX Text
NEW BASE COURSE.
AutoCAD SHX Text
EXISTING BASE COURSE.
AutoCAD SHX Text
EXISTING STREET SURFACE.
AutoCAD SHX Text
ASPHALT/CONCRETE
AutoCAD SHX Text
UNIFORM CUT LINE
AutoCAD SHX Text
SURFACE
AutoCAD SHX Text
NEW STREET
AutoCAD SHX Text
IN STREET
AutoCAD SHX Text
IN OPEN FIELD
AutoCAD SHX Text
WIDTH
AutoCAD SHX Text
MAXIMUM
AutoCAD SHX Text
WIDTH
AutoCAD SHX Text
MINIMUM
AutoCAD SHX Text
DIAMETER
AutoCAD SHX Text
PIPE
AutoCAD SHX Text
(TYP.)
AutoCAD SHX Text
(MIN. 6" CLASS 6)
AutoCAD SHX Text
16"
AutoCAD SHX Text
B
AutoCAD SHX Text
OVER 14'
AutoCAD SHX Text
A
AutoCAD SHX Text
12"
AutoCAD SHX Text
12"
AutoCAD SHX Text
0' TO 14'
AutoCAD SHX Text
DEPTH
AutoCAD SHX Text
MANHOLE
AutoCAD SHX Text
DIMENSION
AutoCAD SHX Text
6"
AutoCAD SHX Text
A
AutoCAD SHX Text
8"
AutoCAD SHX Text
B
AutoCAD SHX Text
A
AutoCAD SHX Text
A
AutoCAD SHX Text
(A)
AutoCAD SHX Text
4"
AutoCAD SHX Text
GRADE ADJUSTMENT RINGS SHALL
AutoCAD SHX Text
NOT EXCEED 8".
AutoCAD SHX Text
1' ADJUSTMENT RING REQUIRED
AutoCAD SHX Text
FOR ALL PRECAST MANHOLES.
AutoCAD SHX Text
NOT LESS THAN TOP
AutoCAD SHX Text
OF PIPE.
AutoCAD SHX Text
FLOOR OF MANHOLE SLOPE
AutoCAD SHX Text
NOT LESS THAN 1/2" PER
AutoCAD SHX Text
FOOT.
AutoCAD SHX Text
STEP TREAD TO BE
AutoCAD SHX Text
PARALLEL WITH INVERT
AutoCAD SHX Text
FLOW DIRECTION.
AutoCAD SHX Text
RAM NECK OR EQUAL
AutoCAD SHX Text
FOR ATTACHING ALL
AutoCAD SHX Text
SECTIONS.
AutoCAD SHX Text
#4 REBARS, 12" O.C. EACH
AutoCAD SHX Text
WAY (8"O.C. IF OVER 20'
AutoCAD SHX Text
DEEP).
AutoCAD SHX Text
NOTE:
AutoCAD SHX Text
4' MH - 24" CAP
AutoCAD SHX Text
5' MH - 30" CAP
AutoCAD SHX Text
6' MH - 30" CAP
AutoCAD SHX Text
DOUBLE WIRE MESH TO BE
AutoCAD SHX Text
PLACED IN WALL OF MANHOLE
AutoCAD SHX Text
SECTIONS GREATER THAN 20'
AutoCAD SHX Text
LENGTH, A RESTRAINING COUPLING IS REQUIRED
AutoCAD SHX Text
WHEN LATERAL IS GREATER THAN ONE PIPE
AutoCAD SHX Text
MECHANICAL JOINT
AutoCAD SHX Text
ON UNDISTURBED EARTH
AutoCAD SHX Text
SOLID PRECAST BASE BLOCK
AutoCAD SHX Text
AS REQUIRED
AutoCAD SHX Text
FINISHED GRADE
AutoCAD SHX Text
DEPTH OF BURY
AutoCAD SHX Text
AT JOINT.
AutoCAD SHX Text
4"
AutoCAD SHX Text
RESTRAINTS
AutoCAD SHX Text
%%UNOTE:
AutoCAD SHX Text
NO OBSTRUCTIONS TO BE CONSTRUCTED
AutoCAD SHX Text
IN FRONT OF THE FIRE HYDRANT.
AutoCAD SHX Text
TRACER WIRE
AutoCAD SHX Text
CONNECTED TO
AutoCAD SHX Text
TEST BOX
AutoCAD SHX Text
(2) 4" CONCRETE FILLED
AutoCAD SHX Text
METAL POST BOLLARDS
AutoCAD SHX Text
8" PVC UTILITY LINE
AutoCAD SHX Text
8" MJ GATE VALVE
AutoCAD SHX Text
8"x8" TEE W/ MJ RSTNTS.
AutoCAD SHX Text
8" MJ GATE VALVE
AutoCAD SHX Text
8" MJ GATE VALVE
AutoCAD SHX Text
30" MJ PUP
AutoCAD SHX Text
30" MJ PUP
AutoCAD SHX Text
30" MJ PUP
AutoCAD SHX Text
THRUST BLOCK
AutoCAD SHX Text
STORM DRAIN
AutoCAD SHX Text
PROPOSED
AutoCAD SHX Text
OTHER UTILITIES.
AutoCAD SHX Text
AND THE PROTECTION OF
AutoCAD SHX Text
THE SAFETY OF THE WORKMEN
AutoCAD SHX Text
SHEETED AS NECESSARY FOR
AutoCAD SHX Text
TRENCH TO BE BRACED OR
AutoCAD SHX Text
MATERIAL TO 95%
AutoCAD SHX Text
STANDARD PROCTOR
AutoCAD SHX Text
DENSITY
AutoCAD SHX Text
PIPE DIA.
AutoCAD SHX Text
10"-18"
AutoCAD SHX Text
6"
AutoCAD SHX Text
12" MIN.
AutoCAD SHX Text
COVER
AutoCAD SHX Text
COMPACT BACKFILL
AutoCAD SHX Text
10"-18"
AutoCAD SHX Text
LIMITS OF BEDDING
AutoCAD SHX Text
IN OPEN FIELD IN STREET
AutoCAD SHX Text
BASE COURSE
AutoCAD SHX Text
STREET SURFACE - PATCH ALL
AutoCAD SHX Text
DISTURBED ROADWAY AREAS
AutoCAD SHX Text
TO EL PASO COUNTY STANDARDS
AutoCAD SHX Text
(4" MIN. FULL-DEPTH ASPHALT)
AutoCAD SHX Text
CLASS I OR II GRANULAR BEDDING MATERIAL PER ASTM D-2321, COMPACTED IN 6" LIFTS TO 95% STANDARD PROCTOR DENSITY
AutoCAD SHX Text
COUNTY COMMENTS
AutoCAD SHX Text
JPS
AutoCAD SHX Text
4/29/19
AutoCAD SHX Text
PCD PROJECT NO. PPR-19-009
Page 22: Operation and Maintenance Manual - Microsoft...5 the riprap has shifted, maintenance may be required to ensure future erosion is prevented. b. Erosion Present/Outfall Undercut –

C3.2

SCALE : AS SHOWN

DATE:

DRAWN BY:

CHECKED BY:

REVISED:

OWNERSHIP OF INSTRUMENTS OF SERVICE:

ALL REPORTS, PLANS, SPECIFICATIONS, COMPUTER FILES, FIELDDATA, NOTES AND OTHER DOCUMENTS AND INSTRUMENTSPREPARED BY DESIGN PROFESSIONAL AS INSTRUMENTS OF

SERVICE SHALL REMAIN THE PROPERTY OF THE DESIGNPROFESSIONAL. THE DESIGN PROFESSIONAL SHALL RETAIN ALL

COMMON LAW STATUTORY AND OTHER RESERVED RIGHTSINCLUDING THE COPYRIGHT THERETO.

DETENTION POND C14

PLAN & DETAILS

BJJ

JPS

12/20/18

4/29/19

6" CONCRETE SLAB

W/#4 BARS @ 12" O.C.E.W.

6'10.5'

2.5

'5

'2

.5

'

SLOT

3"

18

"

A A

10

'

1'-6

"

5.5"

TOP OF

BASE

SLAB

PLAN

SECTION A

SLOT DETAIL

6" CURB

0.5%

CONCRETE

TRICKLE

CHANNEL

CONCRETE

TRICKLE

CHANNEL

36

"

24"

SD

6'

24" SD

MONUMENT

ACADEMY

HIGH SCHOOL

FOR CONSTRUCTION

16.5'

Z:\040201.w

ald

en

\d

wg

\civil\W

ALD

EN

P

RESER

VE 2\M

ON

UM

EN

T A

CA

DEM

Y\C

3.1.d

wg

, 4/25/2019 3:43:35 P

M, D

WG

To

P

DF.p

c3

AutoCAD SHX Text
M?
AutoCAD SHX Text
M?
AutoCAD SHX Text
7370
AutoCAD SHX Text
7366
AutoCAD SHX Text
7362
AutoCAD SHX Text
7378
AutoCAD SHX Text
7370
AutoCAD SHX Text
7374
AutoCAD SHX Text
7362
AutoCAD SHX Text
7364
AutoCAD SHX Text
7370
AutoCAD SHX Text
7368
AutoCAD SHX Text
7370
AutoCAD SHX Text
7382
AutoCAD SHX Text
DETENTION POND OUTLET STRUCTURE C
AutoCAD SHX Text
SCALE: NTS
AutoCAD SHX Text
D
AutoCAD SHX Text
-
AutoCAD SHX Text
2.5'
AutoCAD SHX Text
2.5'
AutoCAD SHX Text
6"
AutoCAD SHX Text
6"
AutoCAD SHX Text
6"
AutoCAD SHX Text
4.0'
AutoCAD SHX Text
6.5'
AutoCAD SHX Text
5.0'
AutoCAD SHX Text
OUTLET PIPE (18" HDPE)
AutoCAD SHX Text
PLAN VIEW
AutoCAD SHX Text
NTS
AutoCAD SHX Text
SECTION
AutoCAD SHX Text
CONCRETE OPENING WIDTH=12"
AutoCAD SHX Text
EL.=7370.0
AutoCAD SHX Text
GRATE EL.=7366.0
AutoCAD SHX Text
FINISHED GRADE
AutoCAD SHX Text
EMERGENCY SPILLWAY
AutoCAD SHX Text
BURIED RIPRAP OVERTOPPING PROTECTION (24" THICK LAYER OF TYPE M RIPRAP; d50=12") 50=12") =12")
AutoCAD SHX Text
OPEN MESH GRATE
AutoCAD SHX Text
TUBULAR TRASH RACK ON 6" CENTERS, KLEMP CORPORATION (OR EQUAL) WITH 1-1/4" x 3/16" BEARING BARS SPACED 1-3/16" ON CENTER, CROSS RODS SPACED 2" ON CENTER
AutoCAD SHX Text
WQCV ORIFICE PLATE
AutoCAD SHX Text
CONCRETE CATCH BASIN (DOUBLE CDOT TYPE C-MODIFIED OR EQUAL)
AutoCAD SHX Text
TOP OF BERM
AutoCAD SHX Text
EL.=7367.5
AutoCAD SHX Text
POND BOTTOM=7362.0
AutoCAD SHX Text
BOTTOM EL=7358.5
AutoCAD SHX Text
NO. 93 JOHNSON VEE WIRE STAINLESS STEEL WELL SCREEN (OR EQUIVALENT PER TABLES OS-2A AND OS-2B)
AutoCAD SHX Text
C8X18.75 AMERICAN STANDARD STRUCTURAL STEEL CHANNEL FORMED INTO CONCRETE BOTTOM AND SIDES OF WOPENING TRASH RACK OPENING TRASH RACK TRASH RACK ATTACHED BY INTERMITTENT WELDS
AutoCAD SHX Text
TYPICAL WQCV ORIFICE PLATE DETAIL D
AutoCAD SHX Text
INTEGRAL MICROPOOL
AutoCAD SHX Text
1/4" STEEL RESTRICTOR PLATE BOLTED TO INSIDE FACE OF BOX BOT. PLATE EL=7361.92
AutoCAD SHX Text
MAX WSL=7367.5
AutoCAD SHX Text
INTEGRAL MICROPOOL
AutoCAD SHX Text
1.
AutoCAD SHX Text
2.
AutoCAD SHX Text
OVERFLOW TRASH RACKS:
AutoCAD SHX Text
3.
AutoCAD SHX Text
ALL TRASH RACKS SHALL BE MOUNTED USING STAINLESS STEEL HARDWARE AND PROVIDED WITH
AutoCAD SHX Text
HINGED AND LOCKABLE OR BOLTABLE ACCESS PANELS.
AutoCAD SHX Text
TRASH RACKS SHALL BE STAINLESS STEEL, ALUMINUM, OR STEEL. STEEL TRASH RACKS SHALL BE HOT
AutoCAD SHX Text
DIP GALVANIZED AND MAY BE HOT POWDER COATED AFTER GALVANIZING.
AutoCAD SHX Text
TRASH RACKS SHALL BE DESIGNED SUCH THAT THE DIAGONAL DIMENSION OF EACH OPENING IS
AutoCAD SHX Text
STRUCTURAL DESIGN OF TRASH RACKS SHALL BE BASED ON FULL HYDROSTATIC HEAD WITH ZERO
AutoCAD SHX Text
HEAD DOWNSTREAM OF THE RACK.
AutoCAD SHX Text
4.
AutoCAD SHX Text
SMALLER THAN THE DIAMETER OF THE OUTLET PIPE.
AutoCAD SHX Text
ATTACHED BY INTERMITTENT WELDS ALONG THE EDGE OF THE MOUNTING FRAME.
AutoCAD SHX Text
HEAD DOWNSTREAM OF THE RACK.
AutoCAD SHX Text
STRUCTURAL DESIGN OF TRASH RACKS SHALL BE BASED ON FULL HYDROSTATIC HEAD WITH ZERO
AutoCAD SHX Text
2.
AutoCAD SHX Text
WELL-SCREEN TRASH RACKS (FOR CIRCULAR ORIFICES) SHALL BE STAINLESS STEEL AND SHALL BE
AutoCAD SHX Text
EURV AND WQCV TRASH RACKS:
AutoCAD SHX Text
1.
AutoCAD SHX Text
%%UELEVATION
AutoCAD SHX Text
%%UORIFICE PATTERN
AutoCAD SHX Text
4" O.C. (TYP.)
AutoCAD SHX Text
ORIFICE PLATE NOTES: 1. MINIMIZE THE NUMBER OF COLUMNS. MINIMIZE THE NUMBER OF COLUMNS. 2. PROVIDE GASKET MATERIAL BETWEEN THE ORIFICE PLATE AND CONCRETE. PROVIDE GASKET MATERIAL BETWEEN THE ORIFICE PLATE AND CONCRETE. 3. BOLT PLATE TO CONCRETE 12" MAX. ON CENTER.BOLT PLATE TO CONCRETE 12" MAX. ON CENTER.
AutoCAD SHX Text
2'-6"
AutoCAD SHX Text
12" PLATE WIDTH
AutoCAD SHX Text
1/4" THICK STEEL ORIFICE PLATE
AutoCAD SHX Text
D
AutoCAD SHX Text
-
AutoCAD SHX Text
INV IN=7361.5
AutoCAD SHX Text
18" HDPE OUTLET PIPE INV=7361.0
AutoCAD SHX Text
SCALE: NTS
AutoCAD SHX Text
19 E. Willamette Ave.
AutoCAD SHX Text
Colorado Springs, CO
AutoCAD SHX Text
80903
AutoCAD SHX Text
PH: 719-477-9429
AutoCAD SHX Text
FAX: 719-471-0766
AutoCAD SHX Text
www.jpsengr.com
AutoCAD SHX Text
NORTH
AutoCAD SHX Text
MICROPOOL WSE=7361.0
AutoCAD SHX Text
PROPOSED DETENTION POND C14 BOT EL=7362.0 SPILLWAY=7367.5 TOP EL=7370.0 REQ'D FSD VOL=1.1 AF DSN VOL=1.3 AF
AutoCAD SHX Text
C -
AutoCAD SHX Text
PROPOSED BERM
AutoCAD SHX Text
%%UENLARGED DETENTION POND C14 PLAN
AutoCAD SHX Text
WALKER ROAD
AutoCAD SHX Text
STRUCTURAL STEEL CHANNEL
AutoCAD SHX Text
FORMED INTO CONCRETE
AutoCAD SHX Text
4'-0"
AutoCAD SHX Text
2'-6" MIN.
AutoCAD SHX Text
1/4" THICK STEEL ORIFICE PLATE
AutoCAD SHX Text
STAINLESS STEEL BOLTS OR INTERMITTANT WELDS, SEE UDFCD FIGURE OS-5 AND OS-6, SECTION B
AutoCAD SHX Text
7366.0
AutoCAD SHX Text
7358.5
AutoCAD SHX Text
MICROPOOL WSE=7361.0 (1-7/16" DIA. ORIFICE)
AutoCAD SHX Text
EL=7363.55 (1-7/16" DIA. ORIFICE)
AutoCAD SHX Text
EL=7362.27 (1-7/16" DIA. ORIFICE)
AutoCAD SHX Text
6"
AutoCAD SHX Text
PROPOSED 15'L x 6'W RIPRAP INFILTRATION ZONE (2' DEPTH; d50=12" RR)50=12" RR)=12" RR)
AutoCAD SHX Text
PROPOSED INTEGRAL FOREBAY INV IN=7362.0
AutoCAD SHX Text
PROPOSED OUTLET STRUCTURE 18" INV OUT=7360.3
AutoCAD SHX Text
PROPOSED 110.7 LF 18" HDPE DISCHARGE PIPE @ 0.5% SLOPE
AutoCAD SHX Text
PROPOSED 18" FES W/RIPRAP APRON INV=7359.7
AutoCAD SHX Text
PROPOSED 77 LF TRICKLE CHANNEL @ 0.5% SLOPE
AutoCAD SHX Text
A
AutoCAD SHX Text
-
AutoCAD SHX Text
12'Wx15% ACCESS RAMP
AutoCAD SHX Text
EXISTING DRIVEWAY
AutoCAD SHX Text
10'W BERM
AutoCAD SHX Text
PROPOSED DRAINAGE EASEMENT
AutoCAD SHX Text
PROPOSED BURIED RIPRAP SPILLWAY CHANNEL (6' WIDE x 2'D; d50=12" RR)50=12" RR)=12" RR)
AutoCAD SHX Text
EXISTING DRIVEWAY CULVERT
AutoCAD SHX Text
N
AutoCAD SHX Text
30'
AutoCAD SHX Text
30'
AutoCAD SHX Text
60'
AutoCAD SHX Text
15'
AutoCAD SHX Text
(30"x42" Sheet)
AutoCAD SHX Text
0
AutoCAD SHX Text
Contour Interval = 2 ft.
AutoCAD SHX Text
Original Scale: 1"=30'
AutoCAD SHX Text
INTEGRAL FOREBAY DETAIL A
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
N
AutoCAD SHX Text
NOT TO SCALE
AutoCAD SHX Text
TRICKLE CHANNEL
AutoCAD SHX Text
TYPICAL CONCRETE
AutoCAD SHX Text
B
AutoCAD SHX Text
4'
AutoCAD SHX Text
2"
AutoCAD SHX Text
FLOWLINE
AutoCAD SHX Text
6" CONCRETE W/4x4 WWF
AutoCAD SHX Text
100 E. St. Vrain, Suite 300
AutoCAD SHX Text
Colorado Springs, Colorado 80903
AutoCAD SHX Text
ARCHITECTS AIA
AutoCAD SHX Text
PROPOSED DRAINAGE EASEMENT
AutoCAD SHX Text
MATCH INTO EXISTING GRAVEL DRIVEWAY
AutoCAD SHX Text
NO.
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
DATE
AutoCAD SHX Text
BY
AutoCAD SHX Text
A
AutoCAD SHX Text
B
AutoCAD SHX Text
FOR PERMIT
AutoCAD SHX Text
JPS
AutoCAD SHX Text
4/17/19
AutoCAD SHX Text
PROPOSED 12'W MAINTENANCE ACCESS ROAD (MIN. 6" CLASS 6 ABC)
AutoCAD SHX Text
COUNTY COMMENTS
AutoCAD SHX Text
JPS
AutoCAD SHX Text
4/29/19
AutoCAD SHX Text
PROPOSED SPILLWAY (L=2'; 4:1 END SLOPES) EL=7367.5
AutoCAD SHX Text
PCD PROJECT NO. PPR-19-009