operating committee report technical operations subcommittee al badella june 10-11, 2010
TRANSCRIPT
Operating Committee Report
Technical Operations SubcommitteeAl Badella
June 10-11, 2010
Document Categorization Project
● 27 Documents Review Status:
12 To be reformatted by the Fall TOS Meeting
5 Reformatted, reviewed by WECC tech writer, being
uploaded to Workgroup Web page.
2 Being reviewed for transfer to PWC.
6 Completed the reformatting process
2 Being retired
2
Work Group Activities
● Telecommunications Work Group
WECC criteria on synchronizing high-speed digital circuits was posted (WECC-0066) for 45 day posting closed on 6/29/2010.
● Control Work Group
Version 2 of the WECC standard on voltage and reactive control (WECC-046) was posted for 30 day review closed 6/7/2010.
Version 2 of a WECC criteria for black start unit testing (WECC-049) was posted for 30 day review and will close on 7/12/2010. Includes expanded scope and draft comments.
3
Work Group Activities
● Relay Work Group
Version 2 of WECC procedure for reporting relay misoperations (WECC -0059) was posted for 30 day comment period and closed on 6/8/2010. Included comments from draft posting.
● Substation Work Group
The annual SWG meeting was held in Scottdale, AZ on May 3-5.
4