ontario superior court of justice hydro one … · its stated purpose is to represent the...

25
Court File No. ONTARIO SUPERIOR COURT OF JUSTICE B E T W E E N: HYDRO ONE NETWORKS INC. Plaintiff - and - THE HAUDENOSAUNEE CONFEDERACY CHIEFS COUNCIL, HAUDENOSAUNEE DEVELOPMENT INSTITUTE, TODD WILLIAMS COLIN MARTIN, RHONDA MARTIN, HAYLEY DOXTATOR, JILL STYRES, JOHN STYRES, MATT MYKE, JAQUELINE HOUSE, JOLEEN BOMBERRY, RYAN BURNHAM, TOM KEEFER, COLLEEN DAVIS, KYLE HARRIS, BOBBY JO JOHNSON, JOLEEN JOHNSON, GARY JOHNSON, JOHN DOE, JANE DOE, and persons unknown Defendants STATEMENT OF CLAIM TO THE DEFENDANTS A LEGAL PROCEEDING HAS BEEN COMMENCED AGAINST YOU by the Plaintiff. The claim made against you is set out in the following pages. IF YOU WISH TO DEFEND THIS PROCEEDING, you or an Ontario lawyer acting for you must prepare a statement of defence in Form 18A prescribed by the Rules of Civil Procedure, serve it on the Plaintiff’s lawyer and file it, with proof of service, in this court office, WITHIN TWENTY DAYS after this statement of claim is served on you, if you are served in Ontario. If you are served in another province or territory of Canada or in the United States of America, the period for serving and filing your statement of defence is forty days. If you are served outside Canada and the United States of America, the period is sixty days. Electronically issued Délivré par voie électronique : 05-Jul-2019 Brantford Court File No./N° du dossier du greffe: CV-19-00000152-0000

Upload: others

Post on 06-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

Court File No.

ONTARIO SUPERIOR COURT OF JUSTICE

B E T W E E N:

HYDRO ONE NETWORKS INC. Plaintiff

- and -

THE HAUDENOSAUNEE CONFEDERACY CHIEFS COUNCIL, HAUDENOSAUNEE DEVELOPMENT INSTITUTE, TODD WILLIAMS

COLIN MARTIN, RHONDA MARTIN, HAYLEY DOXTATOR, JILL STYRES, JOHN STYRES, MATT MYKE, JAQUELINE HOUSE, JOLEEN

BOMBERRY, RYAN BURNHAM, TOM KEEFER, COLLEEN DAVIS, KYLE HARRIS, BOBBY JO JOHNSON, JOLEEN JOHNSON, GARY

JOHNSON, JOHN DOE, JANE DOE, and persons unknown Defendants

STATEMENT OF CLAIM

TO THE DEFENDANTS

A LEGAL PROCEEDING HAS BEEN COMMENCED AGAINST YOU by the Plaintiff. The claim made against you is set out in the following pages.

IF YOU WISH TO DEFEND THIS PROCEEDING, you or an Ontario lawyer acting for you must prepare a statement of defence in Form 18A prescribed by the Rules of Civil Procedure, serve it on the Plaintiff’s lawyer and file it, with proof of service, in this court office, WITHIN TWENTY DAYS after this statement of claim is served on you, if you are served in Ontario.

If you are served in another province or territory of Canada or in the United States of America, the period for serving and filing your statement of defence is forty days. If you are served outside Canada and the United States of America, the period is sixty days.

Electronically issued Délivré par voie électronique

: 05-Jul-2019

Brantford

Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 2: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

Instead of serving and filing a statement of defence, you may serve and file a notice of intent to defend in Form 18B prescribed by the Rules of Civil Procedure. This will entitle you to ten more days within which to serve and file your statement of defence.

IF YOU FAIL TO DEFEND THIS PROCEEDING, JUDGMENT MAY BE GIVEN AGAINST YOU IN YOUR ABSENCE AND WITHOUT FURTHER NOTICE TO YOU. IF YOU WISH TO DEFEND THIS PROCEEDING BUT ARE UNABLE TO PAY LEGAL FEES, LEGAL AID MAY BE AVAILABLE TO YOU BY CONTACTING A LOCAL LEGAL AID OFFICE.

Date: July 5, 2019 Local Registrar

Address of Court Office: 70 Wellington St, Brantford, ON N3T 2L9

TO: THE HAUDENOSAUNEE CONFEDERACY CHIEFS COUNCIL and HAUDENOSAUNEE DEVELOPMENT INSTITUTE c/o R. Aaron Detlor 16 Sunrise Court P.O. Box 714 Ohsweken, Ontario N0A 1M0 [email protected]

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 3: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 3 -

AND TO: TODD WILLIAMS, COLIN MARTIN, RHONDA MARTIN, HAYLEY DOXTATOR, JILL STYRES, JOHN STYRES, MATT MYKE, JAQUELINE HOUSE, JOLEEN BOMBERRY, RYAN BURNHAM, TOM KEEFER, COLLEEN DAVIS, KYLE HARRIS, BOBBY JO JOHNSON, JOLEEN JOHNSON, GARY JOHNSON, JOHN DOE, JANE DOE, and persons unknown

c/o R. Aaron Detlor 16 Sunrise Court P.O. Box 714 Ohsweken, Ontario N0A 1M0 [email protected]

Colin Martin1789 First Line Hagersville, ON N0A 1H0

Gary Johnson3120 5th Line Rd. Ohsweken, ON R2 N0A 1M0

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 4: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 4 -

C L A I M

1. The Plaintiff claims against the Defendants for:

(a) an interim, interlocutory and permanent injunction restraining and enjoining the

Defendants from directly or indirectly, by any means whatsoever:

(i) Trespassing on (i) lands owned by Hydro One and/or lands over which

Hydro One has a statutory or common law easement (“Hydro One

lands”); and (ii) specifically, the 76 kilometer double circuit 230 kilovolt

transmission line between the Allanburg Transformer Station in Niagara

and the Middleport Transformer Station, in Hamilton as depicted in the

map attached as Schedule “A” (the “NRP Line”); and (iii) specifically,

the Hydro One lands on which the transmission corridor between Tower

248 (east of the Caledonia Transformer Station near Grand River) to

Tower 285 (northwest of the Caledonia Transformer Station) are located,

as depicted in the map attached as Schedule “B” (the “NRP Work

Sites”); and (iv) more specifically, the parcel legally described as PT LT

1-2 RANGE WEST OF PLANK RD ONEIDA AS IN HC266364

(SCHEDULE S, S-1, S-3) E OF CNR & SW OF HWY 6 (NEW); S/T

HC117452E, HC270591; HALDIMAND COUNTY being PIN:

381660035 (LT) as depicted in the map attached as Schedule “C” (the

“NRP Site”);

(ii) physically preventing, impeding, restricting or in any way physically

interfering with, or counselling others to impede, restrict or in any way

physically interfere with, the Plaintiff’s carrying on of its business, alone,

and in conjunction with the Niagara Reinforcement Limited Partnership

(“NRP LP”), AECON Group Inc. (“AECON”), Six Nations of the Grand

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 5: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 5 -

River Development Corp. (“Six Nations Dev. Corp.”), A6N (a joint

venture between AECON Group Inc. and Six Nations Dev. Corp.), Thirau

Inc. (“Thirau”) and any other agents thereof, and in particular its right to

the Hydro One lands, the NRP Line, the NRP Work Sites and the NRP

Site;

(iii) physically preventing, impeding, restricting or in any way physically

interfering with, or counselling others to prevent, impede, restrict or in any

way physically interfere with the transport or removal of any objects to or

from the Hydro One lands, the NRP Line, the NRP Work Sites and the

NRP Site or the maintenance, reconstruction, construction, or alteration of

the Hydro One lands, the NRP Line, the NRP Work Sites and the NRP

Site;

(iv) threatening or intimidating the employees, servants, agents or other

persons having business with the Plaintiff, its contractors, subcontractors,

and its consultants and in particular, NRP LP, AECON, Six Nations Dev.

Corp., A6N and/or Thirau;

(v) physically interfering with or counselling others to physically interfere

with the performance by the Plaintiff’s contractors, subcontractors and

consultants, and in particular, NRP LP, AECON, Six Nations Dev. Corp.,

A6N and/or Thirau, of their contractual relations with the Plaintiff, its

related companies, employees, servants, agents or other persons having

business with the Plaintiff;

(vi) creating a nuisance by physically obstructing the Plaintiffs, its contractors,

subcontractors and consultants and any of their employees, servants,

agents or other persons having business with them from carrying on their

operations and activities.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 6: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 6 -

(b) damages, including special damages and punitive damages, for:

(i) trespass;

(ii) intimidation;

(iii) interference with contractual relations;

(iv) interference with economic relations;

(v) nuisance;

(c) prejudgment and post-judgment interest pursuant to the Courts of Justice Act,

R.S.O. 1990, c. C. 43, as amended;

(d) costs on a full indemnity basis; and

(e) such further and other relief as this Honourable Court deems just.

The Parties

2. The plaintiff, Hydro One, is a corporation incorporated pursuant to the Business

Corporations Act, R.S.O. 1990, c. B.16, as amended. Hydro One is Ontario’s largest electricity

transmission and distribution service provider.

3. Hydro One has been working with a partnership of the Six Nations of the Grand River

(“Six Nations”) and Mississaugas of the Credit First Nation (“Mississaugas”) referred to as Six

Nations Dev. Corp. on the NRP Site, as defined in more detail below.

4. The defendant, The Haudenosaunee Confederacy Chiefs Council (the “HCCC”), is a

traditional confederacy, made up of the Mohawks, Oneidas, Onondagas, Cayugas, and Senecas.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 7: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 7 -

Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy

or Six Nations “Iroquois” Confederacy (the “Confederacy”).

5. The defendant, Haudenosaunee Development Institute (“HDI”), is a branch or

department of the HCCC charged with the development of lands within the HCCC’s jurisdiction.

6. The personal defendants, Todd Williams, Colin Martin, Rhonda Martin, Hayley

Doxtator, Joleen Bomberry, John Styres, Matt Myke, Jaqueline House, Tom Keefer, Colleen

Davis, Kyle Harris, Bobby Jo Johnson, Ryan Burnham, Joleen Johnson and Gary Johnson

(collectively, the “Personal Defendants”) are individuals who are either members of the

Confederacy or who are employees, representatives or agents of the HCCC or HDI. The true

identities and proper names of each of “John Doe” and “Jane Doe” are currently unknown to

Hydro One, but the proper names will be inserted by way of amendment once the true identities

and the proper names of those individuals become known to Hydro One.

7. The defendants, acting both individually and in concert, have a long history of organizing

blockades, causing public disruption, breaching court orders and interfering with both the

development of land and with the maintenance, repair, construction and operation of utilities as a

tactic to negotiate compensation and other benefits to members of the Confederacy.

The Niagara Reinforcement Project

8. As set out in more detail below, in relation to the NRP, the defendants have a history of

trespassing on the NRP Site and preventing work on the NRP from taking place.

9. In October of 2004, Hydro One applied to the Ontario Energy Board (the “OEB”) to

build and operate transmission facilities in the Niagara Region required to alleviate transmission

constraints at the Queenstown Flow West transmission interface. At an estimated cost of $116

million, the project, known as the Niagara Reinforcement Project (the “NRP” or the “Project”),

includes the construction of a 76 kilometre double circuit 230 kilovolt transmission line between

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 8: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 8 -

the Allanburg Transformer Station in Niagara and the Middleport Transformer Station in

Hamilton.

10. The original planned in-service date for the NRP was the summer of 2007. In the summer

of 2006, an unforeseen land claim dispute between First Nations and the Province of Ontario

resulted in the project being put on hold Ontario (the “Caledonia Dispute”). While the majority

of the line had been completed by this time, the disruption did not allow a section of the line near

Caledonia to be completed and the line could not be put in-service.

11. As a result of the Caledonia Dispute, the completion of the Project was stalled for

approximately ten years. During that time, Hydro One worked with the two neighbouring First

Nations who were closest in proximity to the NRP in an attempt to resolve outstanding issues

and disputes so that Hydro One contractors could recommence and complete construction of the

NRP. As part of those efforts, Hydro One and its agents continued to engage with two First

Nations, the Six Nations and Mississaugas, as well as HCCC.

12. With respect to the HCCC, Hydro One continued to meet and exchange correspondence

with them regarding a path forward for the NRP as well as other Hydro One projects. A number

of meetings and discussions took place between HCCC and Hydro One (particularly in 2007,

2012 and 2013) in an attempt to address any and all concerns that the HCCC had.

13. As discussed in further detail below, the NRP was restarted in summer 2018 with planned

completion in summer 2019. The Project was ahead of schedule and completion was forecast for

around March 1, 2019. However, work was stopped in January 2019 as a result of interference

with the project by the HCCC.

14. Consultations in 2018 led to the negotiation and execution of an Implementation

Agreement (the “Partnership Agreement”) in August 2018 with the Six Nations Dev. Corp., a

wholly owned subsidiary of the Six Nations, Mississaugas, and Hydro One. Pursuant to the

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 9: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 9 -

Partnership Agreement, Hydro One established the NRLP, between Six Nations Dev. Corp. as

limited partner and a new Hydro One entity as general partner.

15. The Partnership Agreement contemplated that the long-delayed NRP would proceed by

way of a mutually beneficial venture that would result in significant local employment, training

and investments in community infrastructure. Accordingly, it was agreed that:

(a) each of Six Nations Dev. Corp. and Mississaugas would participate as investors

and partners in the Project through a limited partnership structure with a

substantial equity interest therein; and

(b) that the parties target September 1, 2019 for completion of the project.

16. The community consultations underlying the Partnership Agreement and related

agreements took place over the course of ten weeks in 2018, and were led by representatives of

the Six Nations in conjunction with Hydro One. The HCCC was invited on a number of

occasions to participate in negotiations with the other signatories to the Partnership Agreement

during that period, however, they declined to participate.

17. In addition to the Partnership Agreement, in May 2018, Six Nations and Six Nations Dev.

Corp. entered into a contract with the Ontario Ministry of Energy with respect to the NRP (the

“Ministry Agreement”). The Ministry had agreed that they would set aside up to 300 megawatts

of renewable energy capacity for Six Nations Dev. Corp. for new projects on Six Nations lands,

provided that the NRP was “in-service” by September 1, 2019.

18. In the summer of 2018, in order to complete the Project, Hydro One contracted with

A6N, a joint venture between AECON Group Inc. and Six Nations Dev. Corp. (“A6N”) to

complete the outstanding work on the NRP (the “Outstanding Work”):

(c) to “string” 8.5 kilometres of a 230 kV transmission line from Tower #248 (east of

the Caledonia Transformer Station near Grand River) to Tower #285 (northwest

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 10: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 10 -

of the Caledonia Transformer Station), which represented approximately ten

percent of the entire Project;

(d) to install twenty-one structures from the Caledonia Transformer Station Towers

266 A and B to Tower #282 to remedy extensive vandalism that had occurred

over the previous years;

(e) to erect two (2) 3-pole structures and an air brake switch and to connect it to the

existing 115 kV transmission line at Caledonia Junction, which would act as an

emergency supply to the Dunnville Transformer Station;

(f) to repair and reinforce various access roads to certain towers and transformer

stations within the Project;

(g) to increase the height of a transmission tower as a consequence of an intervening

change in the applicable clearance standards; and

(h) to remove and “re-string” conductors and shield wires in the incomplete section

from Tower #248 to Tower #253.

19. At the time the Hydro One/A6N contract was entered into, Hydro One expected that the

Project would be substantially completed by February 28, 2019. HONI selected A6N to complete

the work in part because it hoped that A6N would be in the best position from an Indigenous

relations perspective to ensure that the Outstanding Work was finally completed.

NRP Work Resumes in 2019

20. Work resumed on the NRP in the summer of 2018 by A6N and its subcontractor, Thirau.

21. On January 17, 2019, representatives of the HCCC, including two men who identified

themselves as the Defendants, Todd Williams and Colin Martin, trespassed on Hydro One

property at the NRP Site while Rob Fournier, at that time Thirau Foreman, and his crew were

there completing NRP work. The HCCC representatives blocked the access roads and

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 11: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 11 -

construction site where Outstanding Work was being undertaken and demanded to meet with

Hydro One leadership. At that time, HCCC’s representatives advised that if their demands were

not met over that weekend, they would cause the Outstanding Work to be stopped immediately.

22. Between January 17 and January 21, 2019, discussions between Hydro One, A6N and

HCCC took place with respect to completing the Outstanding Work without interference by

HCCC.

23. During that time, HCCC advised that work on the NRP could only continue if the

“Engagement Agreement” was executed between HCCC and Hydro One. HCCC stated that if

the NRP work were to move forward without their consent the HCCC would seek support from

other Haudenosaunee allies, namely members from Oneida, Mohawks of the Bay of Quinte, and

Akwesasne communities. Moreover, they suggested that if allies do show up at the work site,

HCCC may not be able to control their behavior and there is a risk of towers coming down.

24. On January 21, 2019, at approximately 9:30 am, numerous HCCC representatives,

including Mr. Martin, arrived at the NRP Site in three vehicles and again trespassed on Hydro

One property. The HCCC representatives spoke with Mr. Fournier and provided him with an

alleged “cease and desist order” purportedly approved and issued by the HCCC on January 19,

2019.

25. Following this January 21, 2019 encounter with the HCCC, fearing for their safety, A6N

and Thirau’s personnel ceased construction on the Outstanding Work and departed from the NRP

Site, leaving electrical lines at Tower 285 of the NRP in an unsafe condition (the “Suspended

Work”).

26. Between January 25, 2019 and January 31, 2019 discussions ensued between Hydro One

and HCCC regarding the Suspended Work.

27. On January 25, 2019, Six Nations Dev. Corp. sent a letter to the HCCC, requesting that

the HCCC lift the stop work order on the NRP. In their letter, Six Nations Dev. Corp. set out the

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 12: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 12 -

economic consequences for the Six Nations Community if the project was not completed as

planned.

28. On January 31, 2019, a meeting was held between Hydro One and members of HDI.

Hydro One expected the meeting to focus on terms referenced in the Engagement Agreement.

Instead, HDI presented Hydro One with a draft “memorandum of understanding” (“MOU”)

which contemplated the HCCC acquiring a partnership interest in the NRP and other existing

Hydro One transmission assets adjacent to the NRP, to the exclusion of Six Nations Dev. Corp.

and the Mississaugas First Nation. This was presented by HCCC as the sole path forward for

Hydro One to complete construction of the NRP.

29. On or about February 8, 2019, Hydro One’s legal counsel sent a letter to Aaron Detlor,

counsel for HCCC which (among other things):

(a) requested that he confirm that there would be no interference with contractors

attending at site to carry out the Suspended Work the following Monday;

(b) provided an engineering report from SNC-Lavalin which outlined the condition of

the NRP and the several safety measures that had to take place on Monday,

February 11, 2019; and

(c) advised that any persons who interfered with remedial work would be held fully

accountable for any and all damages that may ensue.

30. On February 11, 2019, the Suspended Work was completed as scheduled.

31. On February 16, 2019, Six Nations Dev. Corp. wrote to HCCC advising that the recent

events surrounding the NRP were threatening the community’s financial development. In the

letter, the Six Nations Dev. Corp. and EDT outlined the repercussions to the community’s

financial development if interference continued with the Project. The Six Nations Dev. Corp.

also advised that a community information session regarding the NRP would take place on

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 13: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 13 -

February 19 at the Six Nations Community Hall, at which they would be publically requesting

that the HCCC lift their cease and desist.

32. Throughout this time, Hydro One continued to consider its position with respect to

HCCC’s proposed agreement. Ultimately, however, Hydro One was not prepared to agree to the

unreasonable and bad faith negotiations orchestrated by the HCCC and the HCCC continued to

threaten the disruption and interference with the Outstanding Work. On April 1, 2019, Hydro

One delivered a letter to HCCC formally rejecting their offer to partner on the NRP to the

exclusion of the Six Nations Dev. Corp. and Mississaugas.

April Attempt to go Back to Work

33. On Wednesday April 3, 2019 Six Nations Dev. Corp. placed a full page advertisement in

two local newspapers, Two Row Times and Turtle Island News, to highlight the benefits of NRP

to Six Nations and the impacts of the work stoppage.

34. Between April 4 and 26, 2019, various discussions took place about A6N’s intention to

move forward with finishing the NRP.

35. On April 26, 2019, A6N provided notice to the community of its intention to

recommence construction of the Outstanding Work and that on April 29, 2019, members of Six

Nations would hold a community barbecue at the site to show support for the Project and to

dissuade persons, including the HCCC and the other defendants, from interfering with the

completion of the Outstanding Work.

36. On April 29, 2019, members of Six Nations and some individuals from the surrounding

community attended the NRP Site at approximately 11:00 am, with the intention of having a

barbecue to show support for the Project and to dissuade persons, including the HCCC and the

other defendants, from interfering with the completion of the Outstanding Work.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 14: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 14 -

37. Mr. Martin appeared to be in control of the group of protestors. When Matt Jamieson, Six

Nations Dev. Corp. President and CEO, approached the protestors, Mr. Martin stated that there

wasn’t “going to be any work today”, and that the HCCC were there to enforce the cease and

desist order. Mr. Martin also indicated that Mr. Jamieson needed to speak to the Chiefs about

going back to work, and advised that Mr. Jamieson could schedule that meeting through the

council secretary, Mr. Hill. The protestors then proceeded to vocally challenge Mr. Jamieson and

other nearby Six Nations community members as to the authenticity of their lineage and

authority.

38. The following Defendants were in attendance on April 29 at the NRP Site on behalf of

HCCC: Colin Martin, Rhonda Martin, Hayley Doxtator, Jill Styres, John Styres, Matt Myke,

Jaqueline House, Joleen Bomberry, Ryan Burnham, Tom Keefer, Colleen Davis, Kyle Harris and

Bobby Jo Johnson. Others were also involved but could not be identified.

39. A video recording of the event depicts the protestors and a conversation that SGRNDC

employees had with them. Excerpts of the conversation are below:

(a) Man’s voice – “The bottom line is you guys are not allowing us to come to work

today, is that right?” Man’s voice – “Nope, not until something’s done”

(b) Man’s voice – “We’ll be here every goddamn day we have to be…”

(c) Man’s voice – “We’re here because you’re publicly going out there saying you’s

(sic) are going back to work.”

40. Fearing for the safety of Hydro One’s employees, agents and contractors in light of the

HCCC’s intimidation, threats and interference, construction and completion of the Outstanding

Work was suspended to enable Hydro One to seek court assistance to enforce its legal rights to

complete the Outstanding Work and the Project.

41. Since April 29, 2019, there have been a number of discussions between HCCC, A6N and

Six Nations Dev. Corp. to discuss potential resolutions to HCCC’s concerns about the NRP.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 15: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 15 -

42. In particular, there was a meeting on June 19, 2019 between representatives from HCCC

and Six Nations Dev. Group to discuss the possibility of HCCC lifting the cease and desist Order

that it has maintained since January 21, 2019.

43. There was also a meeting on June 27, 2019 between representatives from HCCC and

Hydro One to discuss reasonable solutions to HCCC’s concerns about the NRP.

44. The HCCC has maintained their position that they require an equity stake in not only the

NRP, but also broader Hydro One assets. This is not an agreeable solution to Six Nations Dev.

Corp. and/or Hydro One and therefore, the discussions have not led to a resolution of the issues

surrounding the Outstanding Work and/or the Project.

July Attempt to Return to Work

45. On July 4, 2019 at approximately 9:00 a.m. Hydro One employees and A6N employees

attended at the NRP Site to attempt to conduct a site assessment. OPP had been advised in

advance of the intention to resume work and sent two indigenous liaison officers to observe. A

large Mohawk flag had been affixed to a Hydro One transmission tower.

46. The Defendant, Mr. Todd Williams was in and around the location of the NRP Site by the

access road near the smoke shop. Mr. Jamieson observed two safety cones and wire blocking the

access road entrance to the NRP Site. He removed this material from the access road entrance.

47. Once Mr. Jamieson removed the material, and the Hydro One and A6N crews were ready

to move into the NRP Site to conduct the site assessment, Mr. Williams and the Defendant Mr.

Colin Martin approached them.

48. A6N and Hydro One proceeded to have a conversation with Mr. Williams and Mr.

Martin, who:

(a) Demanded to know why A6N and Hydro One were there;

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 16: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 16 -

(b) Advised that there is a “cease and desist” which “prevents A6N and Hydro One

from being there”;

(c) Advised that they would prevent any work from being completed on the site;

(d) Stated that “things are going to get ugly” if A6N and Hydro One attempted to

conduct the site assessment.

49. Fearing for their safety if they were to complete the site assessment, they instructed their

Hydro One and A6N crews to leave the NRP Site at that time.

50. As Hydro One and A6N employees were leaving the NRP Site, they observed the

Defendants, Gary Johnson and Joleen Johnson, entering the access road.

51. The current schedule contemplated that a site assessment would commence on July 4,

with work on the NRP scheduled to restart on July 8. If this schedule proceeds with no further

delays, it is estimated that substantial completion of the project could be completed by August

23, which would allow Hydro One to have the NRP in service on September 1, 2019. These

timelines are predicated on there having been no damages, sabotage, or loss of equipment since

the work on the NRP was suspended on January 21, 2019, which could significantly impact the

timeline to bring the Project to completion.

52. As a result of the protest, as described above, the general contractor and subcontractor for

the Project has deemed the threat of further HDI/HCCC actions to be a safety threat. The general

contractor has refused to continue work on the Project until it is satisfied that this threat has been

addressed.

53. The Defendants prevented and obstructed workers on the NRP Site from carrying out on-

going construction work and other lawful operations of its business.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 17: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 17 -

54. The Defendants interfered with the economic and contractual relations of Hydro One

with its contractors, subcontractors, consultants, employees, agents, customers or other persons

having business with Hydro One.

55. The Defendants trespassed by unlawfully entering on the NRP Site, to which Hydro One

has a right of ownership, a right of possession, or an easement.

56. The Defendants engaged in intimidation.

57. The Defendants unreasonably and substantially interfered with Hydro One’s right to

lawful use and enjoyment of the NRP Site, causing a nuisance.

Damages

58. Hydro One is suffering and will continue to suffer irreparable harm and other damages

from the actions of the Defendants, as set out below. The scale and extent of the losses that

Hydro One will suffer as a result of the protest and resulting construction delay is extremely

difficult, if not impossible, to quantify in monetary terms. Further, the Defendants likely have

limited financial resources and lack the ability to pay the significant damages and costs which

have been and will continue to be incurred as a result of the protest.

59. Hydro One will provide full particulars of damages prior to trial.

60. Hydro One states that it is entitled to an award of prejudgment and post-judgment interest

pursuant to the Courts of Justice Act, R.S.O. 1990, c. C. 43, as amended.

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 18: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

- 18 -

61. The Plaintiff proposes that this action be tried at Brantford, Ontario.

July 5, 2019 BORDEN LADNER GERVAIS LLP Barristers and Solicitors Bay Adelaide Centre, East Tower 22 Adelaide Street West Toronto, Ontario M5H 4E3

Christopher D. Bredt (LSO #23627Q) Tel: (416) 367-6165 Email: [email protected]

Maureen Doherty (LSO #63621W) Tel: (416) 367-6183 Fax: (416) 367-6749 Email: [email protected]

Lawyers for the Plaintiffs

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 19: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

SCHEDULE “A” – NRP LINE

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 20: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

HA

LDIM

AN

DH

ALD

IMA

ND

HA

MIL

TO

NH

AM

ILT

ON

LIN

CO

LNLI

NC

OLN

WE

ST

LIN

CO

LNW

ES

T L

INC

OLN

WA

INF

LEE

TW

AIN

FLE

ET

GR

IMS

BY

GR

IMS

BY

PE

LHA

MP

ELH

AMST

. CA

TH

AR

INE

SS

T. C

AT

HA

RIN

ES

NIA

GA

RA

FA

LLS

NIA

GA

RA

FA

LLS

BU

RLI

NG

TO

NB

UR

LIN

GT

ON

PO

RT

CO

LBO

RN

EP

OR

T C

OLB

OR

NE

NIA

GA

RA

-ON

-TH

E-L

AK

EN

IAG

AR

A-O

N-T

HE

-LA

KE

TH

OR

OLD

TH

OR

OLD

FO

RT

ER

IEF

OR

T E

RIE

WE

LLA

ND

WE

LLA

ND

BR

AN

TB

RA

NT

Lake

Ont

ario

Lake

Ont

ario

Lake

Erie

Lake

Erie

Nia

gara

Riv

erN

iaga

ra R

iver

QU

EE

N E

LIZ

AB

ET

H W

AY

QU

EE

N E

LIZ

AB

ET

H W

AY

KIN

G S

TK

ING

ST

YO

RK

RD

YO

RK

RD

RIV

ER

RD

RIV

ER

RD

4 A

VE

4 A

VE

FL

Y R

DF

LY

RD

30 RD 30 RD

IND

IAN

LIN

E R

D

IND

IAN

LIN

E R

D

RE

GIO

NA

L R

D 2

0R

EG

ION

AL

RD

20

1 ST1 ST

7 ST7 ST FO

RK

S R

DF

OR

KS

RD

BROCK RDBROCK RD

RE

GIO

NA

L R

D 1

7R

EG

ION

AL

RD

17

RID

GE

RD

RID

GE

RD

LAK

ES

HO

RE

RD

LAK

ES

HO

RE

RD

NIAGARA PKY

NIAGARA PKY

16 R

D16

RD

HIGHWAY 56

HIGHWAY 56

SIL

VE

R S

TS

ILV

ER

ST

CA

NB

OR

OU

GH

RD

CA

NB

OR

OU

GH

RD

SODOM RDSODOM RD

NE

TH

ER

BY

RD

NE

TH

ER

BY

RD

REGIONAL RD 9

REGIONAL RD 9

HIGHWAY 406

HIGHWAY 406

BA

RT

ON

ST

E

BA

RT

ON

ST

E

SANDUSK RD

SANDUSK RD

HIG

HW

AY

54

HIG

HW

AY

54

MONTROSE RDMONTROSE RD

KIN

G S

T E

KIN

G S

T E

ROBINSON RD

ROBINSON RD

BA

RT

ON

ST

BA

RT

ON

ST

CA

NB

OR

O R

DC

AN

BO

RO

RD

CR

EE

K R

D

CR

EE

K R

D

REGIONAL RD 56

REGIONAL RD 56

NEBO RDNEBO RD

KOHLER RD

KOHLER RD

VINELAND TOWNLINE RDVINELAND TOWNLINE RD

KALAR RDKALAR RD

ELM STELM ST

BIN

BR

OO

K R

D

BIN

BR

OO

K R

D

20 R

D20

RD

NIAGARA S

TONE RD

NIAGARA S

TONE RD

VICTORIA AVEVICTORIA AVE

WE

BB

ER

RD

WE

BB

ER

RD

HIG

HW

AY

40

5

HIG

HW

AY

40

5

LIN

E 6

RD

LIN

E 6

RD

FIS

HE

RV

ILLE

RD

FIS

HE

RV

ILLE

RD

RICE RDRICE RD

HIGHWAY 403

HIGHWAY 403

BRANT ST

BRANT ST

GO

VE

RN

OR

S R

D

GO

VE

RN

OR

S R

D

FLETCHER RD

FLETCHER RD

MILLER RDMILLER RD

4 LI

NE

4 LI

NE

WIL

SO

N S

T W

WIL

SO

N S

T W

FOUR MILE CREEK RD

FOUR MILE CREEK RD

POINT ABINO RD NPOINT ABINO RD N

MU

D S

T E

MU

D S

T E

MA

IN S

T W

MA

IN S

T W

BIS

MA

RC

K R

D

BIS

MA

RC

K R

D

50 RD 50 RD

RID

GE

RD

WR

IDG

E R

D W

RY

MA

L R

D E

RY

MA

L R

D E

BIG

GA

R R

DB

IGG

AR

RD

WH

ITE

CH

UR

CH

RD

WH

ITE

CH

UR

CH

RD

BUNTING RDBUNTING RD

RE

GIO

NA

L R

D 5

21

RE

GIO

NA

L R

D 5

21

NEW ST

NEW ST

MERRITTVILLE HWYMERRITTVILLE HWYPELHAM RD PELHAM RD

LUN

DY

S L

AN

ELU

ND

YS

LA

NE

RE

GIO

NA

L R

D 6

3

RE

GIO

NA

L R

D 6

3

RE

GIO

NA

L R

D 3

RE

GIO

NA

L R

D 3

WILHELM RDWILHELM RD

CAR

LTO

N S

T

CAR

LTO

N S

T

SA

FA

RI R

DS

AF

AR

I RD

HIGHWAY 6 & 403HIGHWAY 6 & 403

MOYER RDMOYER RD

RA

INH

AM

RD

RA

INH

AM

RD

GENEVA STGENEVA ST

LIN

E 3

RD

LIN

E 3

RD

RE

GIO

NA

L R

D 8

RE

GIO

NA

L R

D 8

MARSHAGAN RD

MARSHAGAN RD

PROGRESSIVE AVEPROGRESSIVE AVE

PARK RD SPARK RD S

TRINITY RD

TRINITY RD

STEWART RDSTEWART RD

CAISTORVILLE RDCAISTORVILLE RD

TW

EN

TY

MIL

E C

RE

EK

RD

TW

EN

TY

MIL

E C

RE

EK

RD

DORCHESTER RDDORCHESTER RD

8 A

VE

8 A

VE

LAK

E S

HO

RE

RD

LAK

E S

HO

RE

RD

QU

EE

NS

TO

N R

DQ

UE

EN

ST

ON

RD

DE

CE

W R

DD

EC

EW

RD

REGIONAL RD 53

REGIONAL RD 53

FIDDLERS GREEN RD

FIDDLERS GREEN RD

CENTRE RD

CENTRE RD

JORDAN RDJORDAN RD

ONTARIO ST

ONTARIO ST

SC

HIS

LE

R R

DS

CH

ISL

ER

RD

RE

GIO

NA

L R

D 2

9

RE

GIO

NA

L R

D 2

9

REGIONAL RD 52

REGIONAL RD 52

WELLANDPORT RDWELLANDPORT RD

THOROLD TOWNLINE RDTHOROLD TOWNLINE RD

21 ST21 ST

RID

GE

RD

E

RID

GE

RD

EJE

RS

EY

VIL

LE R

D W

JER

SE

YV

ILLE

RD

W

SCO

TT S

T

SCO

TT S

T

HUTCHINSON R

D

HUTCHINSON R

D

CAMPDEN RDCAMPDEN RD

ER

IE R

DE

RIE

RD

RY

MA

L R

DR

YM

AL

RD

PARKSIDE D

R

PARKSIDE D

R

MIC

HE

NE

R R

DM

ICH

EN

ER

RD

LON

G B

EA

CH

RD

LON

G B

EA

CH

RD

BEA

VE

RD

AM

S R

D

BEA

VE

RD

AM

S R

D

WILSON ST E

WILSON ST E

STEVENSVILLE RDSTEVENSVILLE RD

EASTPORT DR

EASTPORT DR

GLE

ND

ALE

AV

E

GLE

ND

ALE

AV

E

GA

RN

ER

RD

E

GA

RN

ER

RD

E

MU

D S

T W

MU

D S

T W

TYNESIDE RD

TYNESIDE RD

MC

LEO

D R

DM

CLE

OD

RD

AIR

PO

RT

RD

AIR

PO

RT

RD

HIG

HW

AY

58

HIG

HW

AY

58

DIC

KE

NS

ON

RD

DIC

KE

NS

ON

RD

LOUTH STLOUTH ST

MOUNTAIN RD

MOUNTAIN RD

PORTAGE RDPORTAGE RD

TAPLEYTOWN RD

TAPLEYTOWN RD

WE

LLA

ND

AV

E

WE

LLA

ND

AV

E

PLAINS R

D W

PLAINS R

D W

GOVERNMENT RD

GOVERNMENT RDM

OH

AW

K R

D W

MO

HA

WK

RD

W

MILES RDMILES RD

CONCESSION RD 7CONCESSION RD 7

OLD

FIS

HE

RV

ILLE

RD

OLD

FIS

HE

RV

ILLE

RD

GLENRIDGE AVEGLENRIDGE AVE

NIAGARA STNIAGARA ST

GRASSIE RDGRASSIE RD

GRIMSBY RDGRIMSBY RD

GA

RN

ER

RD

W

GA

RN

ER

RD

W

PLAINS R

D E

PLAINS R

D E

MARTINDALE RD

MARTINDALE RDSOUTH PELHAM RDSOUTH PELHAM RD

RE

GIO

NA

L R

D 6

9R

EG

ION

AL

RD

69

KIR

K R

DK

IRK

RD

DUNDAS ST E

DUNDAS ST E

DUNDAS ST

DUNDAS ST

RY

MA

L R

D W

RY

MA

L R

D W

MILLGROVE SIDE RD

MILLGROVE SIDE RD

AIKENS RDAIKENS RD

STATION RDSTATION RD

PORT DAVIDSON RDPORT DAVIDSON RD

SMITHVILLE RD

SMITHVILLE RD

DOANS RIDGE RDDOANS RIDGE RD

ON

TA

RIO

RD

ON

TA

RIO

RD

MU

D S

TM

UD

ST

UPPER CENTENNIAL PKY

UPPER CENTENNIAL PKY

6 AVE

6 AVE

REGIONAL RD 27REGIONAL RD 27

RY

ME

R R

DR

YM

ER

RD

WEST S

T

WEST S

T

MERRITT STMERRITT ST

MA

IN S

T E

MA

IN S

T E

DOVER R

D

DOVER R

D

BEECHWOOD RD

BEECHWOOD RD

RIV

ERSI

DE

RD

RIV

ERSI

DE

RD

IND

US

TR

IAL

DR

IND

US

TR

IAL

DR

SCHIHIL RDSCHIHIL RD

MAIN

ST

MAIN

ST

11 RD E11 RD E

BOULTON DITCH RD

BOULTON DITCH RD

EMPIRE RDEMPIRE RD

CA

ITH

NE

SS

ST

E

CA

ITH

NE

SS

ST

E

QUEEN ST SQUEEN ST S

COOTES DR

COOTES DR

KIN

G S

T W

KIN

G S

T W

SA

WM

ILL

RD

SA

WM

ILL

RD

RE

GIO

NA

L R

D 6

6

RE

GIO

NA

L R

D 6

6

REGIONAL RD 33

REGIONAL RD 33

REGIONAL RD 6

REGIONAL RD 6

GOLF COURSE RDGOLF COURSE RD

MA

RY

ST

MA

RY

ST

FAR

R A

VE

FAR

R A

VE

SYDENHAM RD

SYDENHAM RD

STONEY CREEK RD

STONEY CREEK RD

HARTZELL RDHARTZELL RD

BLACKHEATH RD

BLACKHEATH RD

MOUNTAIN STMOUNTAIN ST

JAMES ST SJAMES ST S

GRAY RDGRAY RD

VAUGHAN RDVAUGHAN RD

CA

NB

Y S

TC

AN

BY

ST

RE

GIO

NA

L R

D 5

25

RE

GIO

NA

L R

D 5

25

OLYMPIC DROLYMPIC DR

CENTENNIAL PKY S

CENTENNIAL PKY S

MUNSEE ST N

MUNSEE ST N

QU

EE

N S

T

QU

EE

N S

T

VICTORIA AVE SVICTORIA AVE S

ME

TL

ER

RD

ME

TL

ER

RD

TO

WN

LIN

E R

DT

OW

NL

INE

RD

PELHAM STPELHAM ST

KIN

G S

T E

KIN

G S

T E

11 RD E11 RD E

MU

D S

T E

MU

D S

T E

MOUNTAIN RDMOUNTAIN RD

MA

IN S

T E

MA

IN S

T E

YORK RD

YORK RD

RIVER RDRIVER RD

GRAY RDGRAY RD

HIGHWAY 403

HIGHWAY 403

SIL

VE

R S

TS

ILV

ER

ST

MA

IN S

T W

MA

IN S

T W

RE

GIO

NA

L R

D 8

RE

GIO

NA

L R

D 8

MU

D S

T W

MU

D S

T W

RE

GIO

NA

L R

D 2

0

RE

GIO

NA

L R

D 2

0

HIGHW

AY 54

HIGHW

AY 54

LAK

ES

HO

RE

RD

LAK

ES

HO

RE

RD

FISHERVILLE RD

FISHERVILLE RD

20 R

D20

RD

KIN

G S

T W

KIN

G S

T W

QU

EE

N E

LIZ

AB

ET

H W

AY

QU

EE

N E

LIZ

AB

ET

H W

AY

CAISTORVILLE RDCAISTORVILLE RD

REGIONAL R

D 27

REGIONAL R

D 27

VICTORIA AVEVICTORIA AVE

NIAGARA PKYNIAGARA PKY

HIG

HW

AY

40

5

HIG

HW

AY

40

5

RE

GIO

NA

L R

D 6

6

RE

GIO

NA

L R

D 6

6

TRINITY RDTRINITY RD

MO

UN

TA

IN R

DM

OU

NT

AIN

RD

YO

RK

RD

YO

RK

RD

HIGHWAY 54

HIGHWAY 54

Q5G

Q5G

Q23

BM

/ Q

24H

M

Q23

BM

/ Q

24H

M

A8G

A8G

M34H M34H

C9

/ C12

C9

/ C12

Q30

MQ

30M

N6M

/ N

5M

N6M

/ N

5M

N1M

/ N

2M

N1M

/ N

2M

Q2AHQ2AH

B18H / B20H

B18H / B20H

D3AD3AQ

24H

M /

Q29

HM

Q24

HM

/ Q

29H

M

Q25

BM

/ Q

29H

M

Q25

BM

/ Q

29H

M

Q23BM / Q25BMQ23BM / Q25BM

M27

B / M

28B

M27

B / M

28B

D1AD1A

Q2A Q2A

Q5G

Q5G

A8G

A8G

Q30

MQ

30M

Q5G

Q5G

Q2A

HQ

2AH

Q30

MQ

30M

Q25

BM

/ Q

29H

M

Q25

BM

/ Q

29H

M

A8G A8G

M34HM34H

Q2A

HQ

2AH

Q5GQ5GA

8GA

8G

Q2A

HQ

2AH

Q2A

HQ

2AH

Q2A

HQ

2AH

Q25

BM /

Q29

HM

Q25

BM /

Q29

HM

Q26

AM

/ Q

32A

MQ

26A

M /

Q32

AM

Q23BM / Q25BMQ23BM / Q25BM

CH

ER

RY

JC

TC

HE

RR

Y J

CT

RA

ILW

AY

JC

TR

AIL

WA

Y J

CT

DU

NN

VIL

LE T

SD

UN

NV

ILLE

TS

CA

LED

ON

IA T

SC

ALE

DO

NIA

TS

BE

CK

GS

BE

CK

GS

CA

IST

OR

JC

TC

AIS

TO

R J

CT

05

1015

2.5

Kilo

me

ters

Kilo

me

ters

Leg

end

Ch

ang

ed T

ran

smis

sio

n L

ines

Exi

stin

g cc

t, sa

g te

mp

to b

e ra

ised

New

2 c

ct 2

30 k

V L

ine

Tra

nsm

issi

on

Lin

es11

5 kV

230

kV

500

kV

Mun

icip

al B

ound

arie

s

Maj

or R

oads

WIL

CO

XC

OR

NE

RS

WIL

CO

XC

OR

NE

RS

ST

. AN

N'S

JC

TS

T. A

NN

'S J

CT

RO

SE

DE

NE

JC

TR

OS

ED

EN

E J

CT

ALL

AN

BU

RG

WE

ST

JC

TA

LLA

NB

UR

GW

ES

T J

CT

ALL

AN

BU

RG

TS

ALL

AN

BU

RG

TS

HO

LL

AN

D R

OA

D J

CT

HO

LL

AN

D R

OA

D J

CT

BE

AV

ER

DA

MS

JC

TB

EA

VE

R D

AM

S J

CT

ST

. JO

HN

'SV

AL

LEY

JC

TS

T. J

OH

N'S

VA

LLE

Y J

CT

LOU

TH

JC

TLO

UT

H J

CT

BE

AC

H T

SB

EA

CH

TS

HA

NN

ON

JC

TH

AN

NO

N J

CT

NE

AL

E J

CT

NE

AL

E J

CT

SO

UT

HC

OT

E J

CT

SO

UT

HC

OT

E J

CT

CA

RLU

KE

JC

TC

AR

LUK

E J

CT

MID

DLE

PO

RT

TS

MID

DLE

PO

RT

TS

BU

RLI

NG

TO

N T

SB

UR

LIN

GT

ON

TS

N58

0M /

N58

1M

N58

0M /

N58

1M

M27

B /

M28

B

M27

B /

M28

B

M27B / M28B

M27B / M28B

Q23

BM

/ Q

25B

M

Q23

BM

/ Q

25B

M

Q23

BM

/ Q

24H

M

Q23

BM

/ Q

24H

M

Q24HM / Q29HM

Q24HM / Q29HM

Q5G

Q5G

Q2A

HQ

2AH

Q23

BM

/ Q

24H

M

Q23

BM

/ Q

24H

MQ

26A

/ Q

28A

Q26

A /

Q28

A

Q2AHQ2AH

D3A

D3A

Q3

0M

/ Q

32A

Q3

0M

/ Q

32A

Q2

6A

/ Q

28

AQ

26

A /

Q2

8A

Q2

6A

M/ Q

32A

MQ

26

AM

/ Q32

AM

N580M / N581M

N580M / N581M

(C)

Cop

yrig

ht H

ydro

One

Inc.

All

right

s re

serv

ed.

No

part

of

this

dra

win

g m

ay b

e re

dist

ribut

ed o

r re

prod

uced

in a

ny fo

rmby

any

pho

togr

aphi

c, e

lect

roni

c, m

echa

nica

l or

any

othe

rm

eans

, or

used

in a

ny in

form

atio

n st

orag

e or

ret

rieva

l sys

tem

.N

eith

er H

ydro

One

Inc.

nor

any

of i

ts s

ubsi

diar

ies

assu

mes

liabi

lity

for

any

erro

rs o

r om

issi

ons.

A8G

A8G

Q30

M /

Q32

A

Q30

M /

Q32

A

Q26

AM

/ Q

32A

M

Q26

AM

/ Q

32A

M

Pro

pose

d F

acili

ties

- N

iaga

ra R

einf

orce

men

t Pro

ject

Exh

ibit

B -

2 -

2Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 21: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

SCHEDULE “B” – NRP WORK SITES

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 22: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 23: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

SCHEDULE “C” – NRP SITE

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 24: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000

Page 25: ONTARIO SUPERIOR COURT OF JUSTICE HYDRO ONE … · Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy or Six Nations “Iroquois” Confederacy

Cou

rt F

ile

No.

HY

DR

O O

NE

NE

TW

OR

KS

IN

C.

Pla

inti

ff

- an

d -

HA

UD

EN

OS

AU

NE

E C

ON

FE

DE

RA

CY

CH

IEF

S

CO

UN

CIL

ET

AL

.D

efen

dan

ts

ON

TA

RIO

S

UP

ER

IOR

CO

UR

T O

F J

US

TIC

E

PR

OC

EE

DIN

GS

CO

MM

EN

CE

D A

T

BR

AN

TF

OR

D

ST

AT

EM

EN

T O

F C

LA

IM

BO

RD

EN

LA

DN

ER

GE

RV

AIS

LL

P

Bar

rist

ers

and

Sol

icit

ors

Bay

Ad

elai

de

Cen

tre,

Eas

t T

ower

22

Ade

laid

e S

tree

t W

est

Tor

onto

, Ont

ario

M5

H 4

E3

Ch

rist

oph

er D

. Bre

dt

(LS

O #

2362

7Q)

Tel

: (

416)

367

-616

5

Em

ail:

CB

redt

@bl

g.co

m

Mau

reen

Doh

erty

(L

SO

#63

621W

) T

el:

(416

) 36

7-61

83

Fax

: (4

16)

367-

6749

E

mai

l: M

Doh

erty

@bl

g.co

m

Law

yers

for

the

Pla

inti

ffs

Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000