ontario superior court of justice hydro one … · its stated purpose is to represent the...
TRANSCRIPT
Court File No.
ONTARIO SUPERIOR COURT OF JUSTICE
B E T W E E N:
HYDRO ONE NETWORKS INC. Plaintiff
- and -
THE HAUDENOSAUNEE CONFEDERACY CHIEFS COUNCIL, HAUDENOSAUNEE DEVELOPMENT INSTITUTE, TODD WILLIAMS
COLIN MARTIN, RHONDA MARTIN, HAYLEY DOXTATOR, JILL STYRES, JOHN STYRES, MATT MYKE, JAQUELINE HOUSE, JOLEEN
BOMBERRY, RYAN BURNHAM, TOM KEEFER, COLLEEN DAVIS, KYLE HARRIS, BOBBY JO JOHNSON, JOLEEN JOHNSON, GARY
JOHNSON, JOHN DOE, JANE DOE, and persons unknown Defendants
STATEMENT OF CLAIM
TO THE DEFENDANTS
A LEGAL PROCEEDING HAS BEEN COMMENCED AGAINST YOU by the Plaintiff. The claim made against you is set out in the following pages.
IF YOU WISH TO DEFEND THIS PROCEEDING, you or an Ontario lawyer acting for you must prepare a statement of defence in Form 18A prescribed by the Rules of Civil Procedure, serve it on the Plaintiff’s lawyer and file it, with proof of service, in this court office, WITHIN TWENTY DAYS after this statement of claim is served on you, if you are served in Ontario.
If you are served in another province or territory of Canada or in the United States of America, the period for serving and filing your statement of defence is forty days. If you are served outside Canada and the United States of America, the period is sixty days.
Electronically issued Délivré par voie électronique
: 05-Jul-2019
Brantford
Court File No./N° du dossier du greffe: CV-19-00000152-0000
Instead of serving and filing a statement of defence, you may serve and file a notice of intent to defend in Form 18B prescribed by the Rules of Civil Procedure. This will entitle you to ten more days within which to serve and file your statement of defence.
IF YOU FAIL TO DEFEND THIS PROCEEDING, JUDGMENT MAY BE GIVEN AGAINST YOU IN YOUR ABSENCE AND WITHOUT FURTHER NOTICE TO YOU. IF YOU WISH TO DEFEND THIS PROCEEDING BUT ARE UNABLE TO PAY LEGAL FEES, LEGAL AID MAY BE AVAILABLE TO YOU BY CONTACTING A LOCAL LEGAL AID OFFICE.
Date: July 5, 2019 Local Registrar
Address of Court Office: 70 Wellington St, Brantford, ON N3T 2L9
TO: THE HAUDENOSAUNEE CONFEDERACY CHIEFS COUNCIL and HAUDENOSAUNEE DEVELOPMENT INSTITUTE c/o R. Aaron Detlor 16 Sunrise Court P.O. Box 714 Ohsweken, Ontario N0A 1M0 [email protected]
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 3 -
AND TO: TODD WILLIAMS, COLIN MARTIN, RHONDA MARTIN, HAYLEY DOXTATOR, JILL STYRES, JOHN STYRES, MATT MYKE, JAQUELINE HOUSE, JOLEEN BOMBERRY, RYAN BURNHAM, TOM KEEFER, COLLEEN DAVIS, KYLE HARRIS, BOBBY JO JOHNSON, JOLEEN JOHNSON, GARY JOHNSON, JOHN DOE, JANE DOE, and persons unknown
c/o R. Aaron Detlor 16 Sunrise Court P.O. Box 714 Ohsweken, Ontario N0A 1M0 [email protected]
Colin Martin1789 First Line Hagersville, ON N0A 1H0
Gary Johnson3120 5th Line Rd. Ohsweken, ON R2 N0A 1M0
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 4 -
C L A I M
1. The Plaintiff claims against the Defendants for:
(a) an interim, interlocutory and permanent injunction restraining and enjoining the
Defendants from directly or indirectly, by any means whatsoever:
(i) Trespassing on (i) lands owned by Hydro One and/or lands over which
Hydro One has a statutory or common law easement (“Hydro One
lands”); and (ii) specifically, the 76 kilometer double circuit 230 kilovolt
transmission line between the Allanburg Transformer Station in Niagara
and the Middleport Transformer Station, in Hamilton as depicted in the
map attached as Schedule “A” (the “NRP Line”); and (iii) specifically,
the Hydro One lands on which the transmission corridor between Tower
248 (east of the Caledonia Transformer Station near Grand River) to
Tower 285 (northwest of the Caledonia Transformer Station) are located,
as depicted in the map attached as Schedule “B” (the “NRP Work
Sites”); and (iv) more specifically, the parcel legally described as PT LT
1-2 RANGE WEST OF PLANK RD ONEIDA AS IN HC266364
(SCHEDULE S, S-1, S-3) E OF CNR & SW OF HWY 6 (NEW); S/T
HC117452E, HC270591; HALDIMAND COUNTY being PIN:
381660035 (LT) as depicted in the map attached as Schedule “C” (the
“NRP Site”);
(ii) physically preventing, impeding, restricting or in any way physically
interfering with, or counselling others to impede, restrict or in any way
physically interfere with, the Plaintiff’s carrying on of its business, alone,
and in conjunction with the Niagara Reinforcement Limited Partnership
(“NRP LP”), AECON Group Inc. (“AECON”), Six Nations of the Grand
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 5 -
River Development Corp. (“Six Nations Dev. Corp.”), A6N (a joint
venture between AECON Group Inc. and Six Nations Dev. Corp.), Thirau
Inc. (“Thirau”) and any other agents thereof, and in particular its right to
the Hydro One lands, the NRP Line, the NRP Work Sites and the NRP
Site;
(iii) physically preventing, impeding, restricting or in any way physically
interfering with, or counselling others to prevent, impede, restrict or in any
way physically interfere with the transport or removal of any objects to or
from the Hydro One lands, the NRP Line, the NRP Work Sites and the
NRP Site or the maintenance, reconstruction, construction, or alteration of
the Hydro One lands, the NRP Line, the NRP Work Sites and the NRP
Site;
(iv) threatening or intimidating the employees, servants, agents or other
persons having business with the Plaintiff, its contractors, subcontractors,
and its consultants and in particular, NRP LP, AECON, Six Nations Dev.
Corp., A6N and/or Thirau;
(v) physically interfering with or counselling others to physically interfere
with the performance by the Plaintiff’s contractors, subcontractors and
consultants, and in particular, NRP LP, AECON, Six Nations Dev. Corp.,
A6N and/or Thirau, of their contractual relations with the Plaintiff, its
related companies, employees, servants, agents or other persons having
business with the Plaintiff;
(vi) creating a nuisance by physically obstructing the Plaintiffs, its contractors,
subcontractors and consultants and any of their employees, servants,
agents or other persons having business with them from carrying on their
operations and activities.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 6 -
(b) damages, including special damages and punitive damages, for:
(i) trespass;
(ii) intimidation;
(iii) interference with contractual relations;
(iv) interference with economic relations;
(v) nuisance;
(c) prejudgment and post-judgment interest pursuant to the Courts of Justice Act,
R.S.O. 1990, c. C. 43, as amended;
(d) costs on a full indemnity basis; and
(e) such further and other relief as this Honourable Court deems just.
The Parties
2. The plaintiff, Hydro One, is a corporation incorporated pursuant to the Business
Corporations Act, R.S.O. 1990, c. B.16, as amended. Hydro One is Ontario’s largest electricity
transmission and distribution service provider.
3. Hydro One has been working with a partnership of the Six Nations of the Grand River
(“Six Nations”) and Mississaugas of the Credit First Nation (“Mississaugas”) referred to as Six
Nations Dev. Corp. on the NRP Site, as defined in more detail below.
4. The defendant, The Haudenosaunee Confederacy Chiefs Council (the “HCCC”), is a
traditional confederacy, made up of the Mohawks, Oneidas, Onondagas, Cayugas, and Senecas.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 7 -
Its stated purpose is to represent the hereditary governance of the Haudenosaunee Confederacy
or Six Nations “Iroquois” Confederacy (the “Confederacy”).
5. The defendant, Haudenosaunee Development Institute (“HDI”), is a branch or
department of the HCCC charged with the development of lands within the HCCC’s jurisdiction.
6. The personal defendants, Todd Williams, Colin Martin, Rhonda Martin, Hayley
Doxtator, Joleen Bomberry, John Styres, Matt Myke, Jaqueline House, Tom Keefer, Colleen
Davis, Kyle Harris, Bobby Jo Johnson, Ryan Burnham, Joleen Johnson and Gary Johnson
(collectively, the “Personal Defendants”) are individuals who are either members of the
Confederacy or who are employees, representatives or agents of the HCCC or HDI. The true
identities and proper names of each of “John Doe” and “Jane Doe” are currently unknown to
Hydro One, but the proper names will be inserted by way of amendment once the true identities
and the proper names of those individuals become known to Hydro One.
7. The defendants, acting both individually and in concert, have a long history of organizing
blockades, causing public disruption, breaching court orders and interfering with both the
development of land and with the maintenance, repair, construction and operation of utilities as a
tactic to negotiate compensation and other benefits to members of the Confederacy.
The Niagara Reinforcement Project
8. As set out in more detail below, in relation to the NRP, the defendants have a history of
trespassing on the NRP Site and preventing work on the NRP from taking place.
9. In October of 2004, Hydro One applied to the Ontario Energy Board (the “OEB”) to
build and operate transmission facilities in the Niagara Region required to alleviate transmission
constraints at the Queenstown Flow West transmission interface. At an estimated cost of $116
million, the project, known as the Niagara Reinforcement Project (the “NRP” or the “Project”),
includes the construction of a 76 kilometre double circuit 230 kilovolt transmission line between
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 8 -
the Allanburg Transformer Station in Niagara and the Middleport Transformer Station in
Hamilton.
10. The original planned in-service date for the NRP was the summer of 2007. In the summer
of 2006, an unforeseen land claim dispute between First Nations and the Province of Ontario
resulted in the project being put on hold Ontario (the “Caledonia Dispute”). While the majority
of the line had been completed by this time, the disruption did not allow a section of the line near
Caledonia to be completed and the line could not be put in-service.
11. As a result of the Caledonia Dispute, the completion of the Project was stalled for
approximately ten years. During that time, Hydro One worked with the two neighbouring First
Nations who were closest in proximity to the NRP in an attempt to resolve outstanding issues
and disputes so that Hydro One contractors could recommence and complete construction of the
NRP. As part of those efforts, Hydro One and its agents continued to engage with two First
Nations, the Six Nations and Mississaugas, as well as HCCC.
12. With respect to the HCCC, Hydro One continued to meet and exchange correspondence
with them regarding a path forward for the NRP as well as other Hydro One projects. A number
of meetings and discussions took place between HCCC and Hydro One (particularly in 2007,
2012 and 2013) in an attempt to address any and all concerns that the HCCC had.
13. As discussed in further detail below, the NRP was restarted in summer 2018 with planned
completion in summer 2019. The Project was ahead of schedule and completion was forecast for
around March 1, 2019. However, work was stopped in January 2019 as a result of interference
with the project by the HCCC.
14. Consultations in 2018 led to the negotiation and execution of an Implementation
Agreement (the “Partnership Agreement”) in August 2018 with the Six Nations Dev. Corp., a
wholly owned subsidiary of the Six Nations, Mississaugas, and Hydro One. Pursuant to the
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 9 -
Partnership Agreement, Hydro One established the NRLP, between Six Nations Dev. Corp. as
limited partner and a new Hydro One entity as general partner.
15. The Partnership Agreement contemplated that the long-delayed NRP would proceed by
way of a mutually beneficial venture that would result in significant local employment, training
and investments in community infrastructure. Accordingly, it was agreed that:
(a) each of Six Nations Dev. Corp. and Mississaugas would participate as investors
and partners in the Project through a limited partnership structure with a
substantial equity interest therein; and
(b) that the parties target September 1, 2019 for completion of the project.
16. The community consultations underlying the Partnership Agreement and related
agreements took place over the course of ten weeks in 2018, and were led by representatives of
the Six Nations in conjunction with Hydro One. The HCCC was invited on a number of
occasions to participate in negotiations with the other signatories to the Partnership Agreement
during that period, however, they declined to participate.
17. In addition to the Partnership Agreement, in May 2018, Six Nations and Six Nations Dev.
Corp. entered into a contract with the Ontario Ministry of Energy with respect to the NRP (the
“Ministry Agreement”). The Ministry had agreed that they would set aside up to 300 megawatts
of renewable energy capacity for Six Nations Dev. Corp. for new projects on Six Nations lands,
provided that the NRP was “in-service” by September 1, 2019.
18. In the summer of 2018, in order to complete the Project, Hydro One contracted with
A6N, a joint venture between AECON Group Inc. and Six Nations Dev. Corp. (“A6N”) to
complete the outstanding work on the NRP (the “Outstanding Work”):
(c) to “string” 8.5 kilometres of a 230 kV transmission line from Tower #248 (east of
the Caledonia Transformer Station near Grand River) to Tower #285 (northwest
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 10 -
of the Caledonia Transformer Station), which represented approximately ten
percent of the entire Project;
(d) to install twenty-one structures from the Caledonia Transformer Station Towers
266 A and B to Tower #282 to remedy extensive vandalism that had occurred
over the previous years;
(e) to erect two (2) 3-pole structures and an air brake switch and to connect it to the
existing 115 kV transmission line at Caledonia Junction, which would act as an
emergency supply to the Dunnville Transformer Station;
(f) to repair and reinforce various access roads to certain towers and transformer
stations within the Project;
(g) to increase the height of a transmission tower as a consequence of an intervening
change in the applicable clearance standards; and
(h) to remove and “re-string” conductors and shield wires in the incomplete section
from Tower #248 to Tower #253.
19. At the time the Hydro One/A6N contract was entered into, Hydro One expected that the
Project would be substantially completed by February 28, 2019. HONI selected A6N to complete
the work in part because it hoped that A6N would be in the best position from an Indigenous
relations perspective to ensure that the Outstanding Work was finally completed.
NRP Work Resumes in 2019
20. Work resumed on the NRP in the summer of 2018 by A6N and its subcontractor, Thirau.
21. On January 17, 2019, representatives of the HCCC, including two men who identified
themselves as the Defendants, Todd Williams and Colin Martin, trespassed on Hydro One
property at the NRP Site while Rob Fournier, at that time Thirau Foreman, and his crew were
there completing NRP work. The HCCC representatives blocked the access roads and
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 11 -
construction site where Outstanding Work was being undertaken and demanded to meet with
Hydro One leadership. At that time, HCCC’s representatives advised that if their demands were
not met over that weekend, they would cause the Outstanding Work to be stopped immediately.
22. Between January 17 and January 21, 2019, discussions between Hydro One, A6N and
HCCC took place with respect to completing the Outstanding Work without interference by
HCCC.
23. During that time, HCCC advised that work on the NRP could only continue if the
“Engagement Agreement” was executed between HCCC and Hydro One. HCCC stated that if
the NRP work were to move forward without their consent the HCCC would seek support from
other Haudenosaunee allies, namely members from Oneida, Mohawks of the Bay of Quinte, and
Akwesasne communities. Moreover, they suggested that if allies do show up at the work site,
HCCC may not be able to control their behavior and there is a risk of towers coming down.
24. On January 21, 2019, at approximately 9:30 am, numerous HCCC representatives,
including Mr. Martin, arrived at the NRP Site in three vehicles and again trespassed on Hydro
One property. The HCCC representatives spoke with Mr. Fournier and provided him with an
alleged “cease and desist order” purportedly approved and issued by the HCCC on January 19,
2019.
25. Following this January 21, 2019 encounter with the HCCC, fearing for their safety, A6N
and Thirau’s personnel ceased construction on the Outstanding Work and departed from the NRP
Site, leaving electrical lines at Tower 285 of the NRP in an unsafe condition (the “Suspended
Work”).
26. Between January 25, 2019 and January 31, 2019 discussions ensued between Hydro One
and HCCC regarding the Suspended Work.
27. On January 25, 2019, Six Nations Dev. Corp. sent a letter to the HCCC, requesting that
the HCCC lift the stop work order on the NRP. In their letter, Six Nations Dev. Corp. set out the
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 12 -
economic consequences for the Six Nations Community if the project was not completed as
planned.
28. On January 31, 2019, a meeting was held between Hydro One and members of HDI.
Hydro One expected the meeting to focus on terms referenced in the Engagement Agreement.
Instead, HDI presented Hydro One with a draft “memorandum of understanding” (“MOU”)
which contemplated the HCCC acquiring a partnership interest in the NRP and other existing
Hydro One transmission assets adjacent to the NRP, to the exclusion of Six Nations Dev. Corp.
and the Mississaugas First Nation. This was presented by HCCC as the sole path forward for
Hydro One to complete construction of the NRP.
29. On or about February 8, 2019, Hydro One’s legal counsel sent a letter to Aaron Detlor,
counsel for HCCC which (among other things):
(a) requested that he confirm that there would be no interference with contractors
attending at site to carry out the Suspended Work the following Monday;
(b) provided an engineering report from SNC-Lavalin which outlined the condition of
the NRP and the several safety measures that had to take place on Monday,
February 11, 2019; and
(c) advised that any persons who interfered with remedial work would be held fully
accountable for any and all damages that may ensue.
30. On February 11, 2019, the Suspended Work was completed as scheduled.
31. On February 16, 2019, Six Nations Dev. Corp. wrote to HCCC advising that the recent
events surrounding the NRP were threatening the community’s financial development. In the
letter, the Six Nations Dev. Corp. and EDT outlined the repercussions to the community’s
financial development if interference continued with the Project. The Six Nations Dev. Corp.
also advised that a community information session regarding the NRP would take place on
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 13 -
February 19 at the Six Nations Community Hall, at which they would be publically requesting
that the HCCC lift their cease and desist.
32. Throughout this time, Hydro One continued to consider its position with respect to
HCCC’s proposed agreement. Ultimately, however, Hydro One was not prepared to agree to the
unreasonable and bad faith negotiations orchestrated by the HCCC and the HCCC continued to
threaten the disruption and interference with the Outstanding Work. On April 1, 2019, Hydro
One delivered a letter to HCCC formally rejecting their offer to partner on the NRP to the
exclusion of the Six Nations Dev. Corp. and Mississaugas.
April Attempt to go Back to Work
33. On Wednesday April 3, 2019 Six Nations Dev. Corp. placed a full page advertisement in
two local newspapers, Two Row Times and Turtle Island News, to highlight the benefits of NRP
to Six Nations and the impacts of the work stoppage.
34. Between April 4 and 26, 2019, various discussions took place about A6N’s intention to
move forward with finishing the NRP.
35. On April 26, 2019, A6N provided notice to the community of its intention to
recommence construction of the Outstanding Work and that on April 29, 2019, members of Six
Nations would hold a community barbecue at the site to show support for the Project and to
dissuade persons, including the HCCC and the other defendants, from interfering with the
completion of the Outstanding Work.
36. On April 29, 2019, members of Six Nations and some individuals from the surrounding
community attended the NRP Site at approximately 11:00 am, with the intention of having a
barbecue to show support for the Project and to dissuade persons, including the HCCC and the
other defendants, from interfering with the completion of the Outstanding Work.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 14 -
37. Mr. Martin appeared to be in control of the group of protestors. When Matt Jamieson, Six
Nations Dev. Corp. President and CEO, approached the protestors, Mr. Martin stated that there
wasn’t “going to be any work today”, and that the HCCC were there to enforce the cease and
desist order. Mr. Martin also indicated that Mr. Jamieson needed to speak to the Chiefs about
going back to work, and advised that Mr. Jamieson could schedule that meeting through the
council secretary, Mr. Hill. The protestors then proceeded to vocally challenge Mr. Jamieson and
other nearby Six Nations community members as to the authenticity of their lineage and
authority.
38. The following Defendants were in attendance on April 29 at the NRP Site on behalf of
HCCC: Colin Martin, Rhonda Martin, Hayley Doxtator, Jill Styres, John Styres, Matt Myke,
Jaqueline House, Joleen Bomberry, Ryan Burnham, Tom Keefer, Colleen Davis, Kyle Harris and
Bobby Jo Johnson. Others were also involved but could not be identified.
39. A video recording of the event depicts the protestors and a conversation that SGRNDC
employees had with them. Excerpts of the conversation are below:
(a) Man’s voice – “The bottom line is you guys are not allowing us to come to work
today, is that right?” Man’s voice – “Nope, not until something’s done”
(b) Man’s voice – “We’ll be here every goddamn day we have to be…”
(c) Man’s voice – “We’re here because you’re publicly going out there saying you’s
(sic) are going back to work.”
40. Fearing for the safety of Hydro One’s employees, agents and contractors in light of the
HCCC’s intimidation, threats and interference, construction and completion of the Outstanding
Work was suspended to enable Hydro One to seek court assistance to enforce its legal rights to
complete the Outstanding Work and the Project.
41. Since April 29, 2019, there have been a number of discussions between HCCC, A6N and
Six Nations Dev. Corp. to discuss potential resolutions to HCCC’s concerns about the NRP.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 15 -
42. In particular, there was a meeting on June 19, 2019 between representatives from HCCC
and Six Nations Dev. Group to discuss the possibility of HCCC lifting the cease and desist Order
that it has maintained since January 21, 2019.
43. There was also a meeting on June 27, 2019 between representatives from HCCC and
Hydro One to discuss reasonable solutions to HCCC’s concerns about the NRP.
44. The HCCC has maintained their position that they require an equity stake in not only the
NRP, but also broader Hydro One assets. This is not an agreeable solution to Six Nations Dev.
Corp. and/or Hydro One and therefore, the discussions have not led to a resolution of the issues
surrounding the Outstanding Work and/or the Project.
July Attempt to Return to Work
45. On July 4, 2019 at approximately 9:00 a.m. Hydro One employees and A6N employees
attended at the NRP Site to attempt to conduct a site assessment. OPP had been advised in
advance of the intention to resume work and sent two indigenous liaison officers to observe. A
large Mohawk flag had been affixed to a Hydro One transmission tower.
46. The Defendant, Mr. Todd Williams was in and around the location of the NRP Site by the
access road near the smoke shop. Mr. Jamieson observed two safety cones and wire blocking the
access road entrance to the NRP Site. He removed this material from the access road entrance.
47. Once Mr. Jamieson removed the material, and the Hydro One and A6N crews were ready
to move into the NRP Site to conduct the site assessment, Mr. Williams and the Defendant Mr.
Colin Martin approached them.
48. A6N and Hydro One proceeded to have a conversation with Mr. Williams and Mr.
Martin, who:
(a) Demanded to know why A6N and Hydro One were there;
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 16 -
(b) Advised that there is a “cease and desist” which “prevents A6N and Hydro One
from being there”;
(c) Advised that they would prevent any work from being completed on the site;
(d) Stated that “things are going to get ugly” if A6N and Hydro One attempted to
conduct the site assessment.
49. Fearing for their safety if they were to complete the site assessment, they instructed their
Hydro One and A6N crews to leave the NRP Site at that time.
50. As Hydro One and A6N employees were leaving the NRP Site, they observed the
Defendants, Gary Johnson and Joleen Johnson, entering the access road.
51. The current schedule contemplated that a site assessment would commence on July 4,
with work on the NRP scheduled to restart on July 8. If this schedule proceeds with no further
delays, it is estimated that substantial completion of the project could be completed by August
23, which would allow Hydro One to have the NRP in service on September 1, 2019. These
timelines are predicated on there having been no damages, sabotage, or loss of equipment since
the work on the NRP was suspended on January 21, 2019, which could significantly impact the
timeline to bring the Project to completion.
52. As a result of the protest, as described above, the general contractor and subcontractor for
the Project has deemed the threat of further HDI/HCCC actions to be a safety threat. The general
contractor has refused to continue work on the Project until it is satisfied that this threat has been
addressed.
53. The Defendants prevented and obstructed workers on the NRP Site from carrying out on-
going construction work and other lawful operations of its business.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 17 -
54. The Defendants interfered with the economic and contractual relations of Hydro One
with its contractors, subcontractors, consultants, employees, agents, customers or other persons
having business with Hydro One.
55. The Defendants trespassed by unlawfully entering on the NRP Site, to which Hydro One
has a right of ownership, a right of possession, or an easement.
56. The Defendants engaged in intimidation.
57. The Defendants unreasonably and substantially interfered with Hydro One’s right to
lawful use and enjoyment of the NRP Site, causing a nuisance.
Damages
58. Hydro One is suffering and will continue to suffer irreparable harm and other damages
from the actions of the Defendants, as set out below. The scale and extent of the losses that
Hydro One will suffer as a result of the protest and resulting construction delay is extremely
difficult, if not impossible, to quantify in monetary terms. Further, the Defendants likely have
limited financial resources and lack the ability to pay the significant damages and costs which
have been and will continue to be incurred as a result of the protest.
59. Hydro One will provide full particulars of damages prior to trial.
60. Hydro One states that it is entitled to an award of prejudgment and post-judgment interest
pursuant to the Courts of Justice Act, R.S.O. 1990, c. C. 43, as amended.
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
- 18 -
61. The Plaintiff proposes that this action be tried at Brantford, Ontario.
July 5, 2019 BORDEN LADNER GERVAIS LLP Barristers and Solicitors Bay Adelaide Centre, East Tower 22 Adelaide Street West Toronto, Ontario M5H 4E3
Christopher D. Bredt (LSO #23627Q) Tel: (416) 367-6165 Email: [email protected]
Maureen Doherty (LSO #63621W) Tel: (416) 367-6183 Fax: (416) 367-6749 Email: [email protected]
Lawyers for the Plaintiffs
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
SCHEDULE “A” – NRP LINE
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
HA
LDIM
AN
DH
ALD
IMA
ND
HA
MIL
TO
NH
AM
ILT
ON
LIN
CO
LNLI
NC
OLN
WE
ST
LIN
CO
LNW
ES
T L
INC
OLN
WA
INF
LEE
TW
AIN
FLE
ET
GR
IMS
BY
GR
IMS
BY
PE
LHA
MP
ELH
AMST
. CA
TH
AR
INE
SS
T. C
AT
HA
RIN
ES
NIA
GA
RA
FA
LLS
NIA
GA
RA
FA
LLS
BU
RLI
NG
TO
NB
UR
LIN
GT
ON
PO
RT
CO
LBO
RN
EP
OR
T C
OLB
OR
NE
NIA
GA
RA
-ON
-TH
E-L
AK
EN
IAG
AR
A-O
N-T
HE
-LA
KE
TH
OR
OLD
TH
OR
OLD
FO
RT
ER
IEF
OR
T E
RIE
WE
LLA
ND
WE
LLA
ND
BR
AN
TB
RA
NT
Lake
Ont
ario
Lake
Ont
ario
Lake
Erie
Lake
Erie
Nia
gara
Riv
erN
iaga
ra R
iver
QU
EE
N E
LIZ
AB
ET
H W
AY
QU
EE
N E
LIZ
AB
ET
H W
AY
KIN
G S
TK
ING
ST
YO
RK
RD
YO
RK
RD
RIV
ER
RD
RIV
ER
RD
4 A
VE
4 A
VE
FL
Y R
DF
LY
RD
30 RD 30 RD
IND
IAN
LIN
E R
D
IND
IAN
LIN
E R
D
RE
GIO
NA
L R
D 2
0R
EG
ION
AL
RD
20
1 ST1 ST
7 ST7 ST FO
RK
S R
DF
OR
KS
RD
BROCK RDBROCK RD
RE
GIO
NA
L R
D 1
7R
EG
ION
AL
RD
17
RID
GE
RD
RID
GE
RD
LAK
ES
HO
RE
RD
LAK
ES
HO
RE
RD
NIAGARA PKY
NIAGARA PKY
16 R
D16
RD
HIGHWAY 56
HIGHWAY 56
SIL
VE
R S
TS
ILV
ER
ST
CA
NB
OR
OU
GH
RD
CA
NB
OR
OU
GH
RD
SODOM RDSODOM RD
NE
TH
ER
BY
RD
NE
TH
ER
BY
RD
REGIONAL RD 9
REGIONAL RD 9
HIGHWAY 406
HIGHWAY 406
BA
RT
ON
ST
E
BA
RT
ON
ST
E
SANDUSK RD
SANDUSK RD
HIG
HW
AY
54
HIG
HW
AY
54
MONTROSE RDMONTROSE RD
KIN
G S
T E
KIN
G S
T E
ROBINSON RD
ROBINSON RD
BA
RT
ON
ST
BA
RT
ON
ST
CA
NB
OR
O R
DC
AN
BO
RO
RD
CR
EE
K R
D
CR
EE
K R
D
REGIONAL RD 56
REGIONAL RD 56
NEBO RDNEBO RD
KOHLER RD
KOHLER RD
VINELAND TOWNLINE RDVINELAND TOWNLINE RD
KALAR RDKALAR RD
ELM STELM ST
BIN
BR
OO
K R
D
BIN
BR
OO
K R
D
20 R
D20
RD
NIAGARA S
TONE RD
NIAGARA S
TONE RD
VICTORIA AVEVICTORIA AVE
WE
BB
ER
RD
WE
BB
ER
RD
HIG
HW
AY
40
5
HIG
HW
AY
40
5
LIN
E 6
RD
LIN
E 6
RD
FIS
HE
RV
ILLE
RD
FIS
HE
RV
ILLE
RD
RICE RDRICE RD
HIGHWAY 403
HIGHWAY 403
BRANT ST
BRANT ST
GO
VE
RN
OR
S R
D
GO
VE
RN
OR
S R
D
FLETCHER RD
FLETCHER RD
MILLER RDMILLER RD
4 LI
NE
4 LI
NE
WIL
SO
N S
T W
WIL
SO
N S
T W
FOUR MILE CREEK RD
FOUR MILE CREEK RD
POINT ABINO RD NPOINT ABINO RD N
MU
D S
T E
MU
D S
T E
MA
IN S
T W
MA
IN S
T W
BIS
MA
RC
K R
D
BIS
MA
RC
K R
D
50 RD 50 RD
RID
GE
RD
WR
IDG
E R
D W
RY
MA
L R
D E
RY
MA
L R
D E
BIG
GA
R R
DB
IGG
AR
RD
WH
ITE
CH
UR
CH
RD
WH
ITE
CH
UR
CH
RD
BUNTING RDBUNTING RD
RE
GIO
NA
L R
D 5
21
RE
GIO
NA
L R
D 5
21
NEW ST
NEW ST
MERRITTVILLE HWYMERRITTVILLE HWYPELHAM RD PELHAM RD
LUN
DY
S L
AN
ELU
ND
YS
LA
NE
RE
GIO
NA
L R
D 6
3
RE
GIO
NA
L R
D 6
3
RE
GIO
NA
L R
D 3
RE
GIO
NA
L R
D 3
WILHELM RDWILHELM RD
CAR
LTO
N S
T
CAR
LTO
N S
T
SA
FA
RI R
DS
AF
AR
I RD
HIGHWAY 6 & 403HIGHWAY 6 & 403
MOYER RDMOYER RD
RA
INH
AM
RD
RA
INH
AM
RD
GENEVA STGENEVA ST
LIN
E 3
RD
LIN
E 3
RD
RE
GIO
NA
L R
D 8
RE
GIO
NA
L R
D 8
MARSHAGAN RD
MARSHAGAN RD
PROGRESSIVE AVEPROGRESSIVE AVE
PARK RD SPARK RD S
TRINITY RD
TRINITY RD
STEWART RDSTEWART RD
CAISTORVILLE RDCAISTORVILLE RD
TW
EN
TY
MIL
E C
RE
EK
RD
TW
EN
TY
MIL
E C
RE
EK
RD
DORCHESTER RDDORCHESTER RD
8 A
VE
8 A
VE
LAK
E S
HO
RE
RD
LAK
E S
HO
RE
RD
QU
EE
NS
TO
N R
DQ
UE
EN
ST
ON
RD
DE
CE
W R
DD
EC
EW
RD
REGIONAL RD 53
REGIONAL RD 53
FIDDLERS GREEN RD
FIDDLERS GREEN RD
CENTRE RD
CENTRE RD
JORDAN RDJORDAN RD
ONTARIO ST
ONTARIO ST
SC
HIS
LE
R R
DS
CH
ISL
ER
RD
RE
GIO
NA
L R
D 2
9
RE
GIO
NA
L R
D 2
9
REGIONAL RD 52
REGIONAL RD 52
WELLANDPORT RDWELLANDPORT RD
THOROLD TOWNLINE RDTHOROLD TOWNLINE RD
21 ST21 ST
RID
GE
RD
E
RID
GE
RD
EJE
RS
EY
VIL
LE R
D W
JER
SE
YV
ILLE
RD
W
SCO
TT S
T
SCO
TT S
T
HUTCHINSON R
D
HUTCHINSON R
D
CAMPDEN RDCAMPDEN RD
ER
IE R
DE
RIE
RD
RY
MA
L R
DR
YM
AL
RD
PARKSIDE D
R
PARKSIDE D
R
MIC
HE
NE
R R
DM
ICH
EN
ER
RD
LON
G B
EA
CH
RD
LON
G B
EA
CH
RD
BEA
VE
RD
AM
S R
D
BEA
VE
RD
AM
S R
D
WILSON ST E
WILSON ST E
STEVENSVILLE RDSTEVENSVILLE RD
EASTPORT DR
EASTPORT DR
GLE
ND
ALE
AV
E
GLE
ND
ALE
AV
E
GA
RN
ER
RD
E
GA
RN
ER
RD
E
MU
D S
T W
MU
D S
T W
TYNESIDE RD
TYNESIDE RD
MC
LEO
D R
DM
CLE
OD
RD
AIR
PO
RT
RD
AIR
PO
RT
RD
HIG
HW
AY
58
HIG
HW
AY
58
DIC
KE
NS
ON
RD
DIC
KE
NS
ON
RD
LOUTH STLOUTH ST
MOUNTAIN RD
MOUNTAIN RD
PORTAGE RDPORTAGE RD
TAPLEYTOWN RD
TAPLEYTOWN RD
WE
LLA
ND
AV
E
WE
LLA
ND
AV
E
PLAINS R
D W
PLAINS R
D W
GOVERNMENT RD
GOVERNMENT RDM
OH
AW
K R
D W
MO
HA
WK
RD
W
MILES RDMILES RD
CONCESSION RD 7CONCESSION RD 7
OLD
FIS
HE
RV
ILLE
RD
OLD
FIS
HE
RV
ILLE
RD
GLENRIDGE AVEGLENRIDGE AVE
NIAGARA STNIAGARA ST
GRASSIE RDGRASSIE RD
GRIMSBY RDGRIMSBY RD
GA
RN
ER
RD
W
GA
RN
ER
RD
W
PLAINS R
D E
PLAINS R
D E
MARTINDALE RD
MARTINDALE RDSOUTH PELHAM RDSOUTH PELHAM RD
RE
GIO
NA
L R
D 6
9R
EG
ION
AL
RD
69
KIR
K R
DK
IRK
RD
DUNDAS ST E
DUNDAS ST E
DUNDAS ST
DUNDAS ST
RY
MA
L R
D W
RY
MA
L R
D W
MILLGROVE SIDE RD
MILLGROVE SIDE RD
AIKENS RDAIKENS RD
STATION RDSTATION RD
PORT DAVIDSON RDPORT DAVIDSON RD
SMITHVILLE RD
SMITHVILLE RD
DOANS RIDGE RDDOANS RIDGE RD
ON
TA
RIO
RD
ON
TA
RIO
RD
MU
D S
TM
UD
ST
UPPER CENTENNIAL PKY
UPPER CENTENNIAL PKY
6 AVE
6 AVE
REGIONAL RD 27REGIONAL RD 27
RY
ME
R R
DR
YM
ER
RD
WEST S
T
WEST S
T
MERRITT STMERRITT ST
MA
IN S
T E
MA
IN S
T E
DOVER R
D
DOVER R
D
BEECHWOOD RD
BEECHWOOD RD
RIV
ERSI
DE
RD
RIV
ERSI
DE
RD
IND
US
TR
IAL
DR
IND
US
TR
IAL
DR
SCHIHIL RDSCHIHIL RD
MAIN
ST
MAIN
ST
11 RD E11 RD E
BOULTON DITCH RD
BOULTON DITCH RD
EMPIRE RDEMPIRE RD
CA
ITH
NE
SS
ST
E
CA
ITH
NE
SS
ST
E
QUEEN ST SQUEEN ST S
COOTES DR
COOTES DR
KIN
G S
T W
KIN
G S
T W
SA
WM
ILL
RD
SA
WM
ILL
RD
RE
GIO
NA
L R
D 6
6
RE
GIO
NA
L R
D 6
6
REGIONAL RD 33
REGIONAL RD 33
REGIONAL RD 6
REGIONAL RD 6
GOLF COURSE RDGOLF COURSE RD
MA
RY
ST
MA
RY
ST
FAR
R A
VE
FAR
R A
VE
SYDENHAM RD
SYDENHAM RD
STONEY CREEK RD
STONEY CREEK RD
HARTZELL RDHARTZELL RD
BLACKHEATH RD
BLACKHEATH RD
MOUNTAIN STMOUNTAIN ST
JAMES ST SJAMES ST S
GRAY RDGRAY RD
VAUGHAN RDVAUGHAN RD
CA
NB
Y S
TC
AN
BY
ST
RE
GIO
NA
L R
D 5
25
RE
GIO
NA
L R
D 5
25
OLYMPIC DROLYMPIC DR
CENTENNIAL PKY S
CENTENNIAL PKY S
MUNSEE ST N
MUNSEE ST N
QU
EE
N S
T
QU
EE
N S
T
VICTORIA AVE SVICTORIA AVE S
ME
TL
ER
RD
ME
TL
ER
RD
TO
WN
LIN
E R
DT
OW
NL
INE
RD
PELHAM STPELHAM ST
KIN
G S
T E
KIN
G S
T E
11 RD E11 RD E
MU
D S
T E
MU
D S
T E
MOUNTAIN RDMOUNTAIN RD
MA
IN S
T E
MA
IN S
T E
YORK RD
YORK RD
RIVER RDRIVER RD
GRAY RDGRAY RD
HIGHWAY 403
HIGHWAY 403
SIL
VE
R S
TS
ILV
ER
ST
MA
IN S
T W
MA
IN S
T W
RE
GIO
NA
L R
D 8
RE
GIO
NA
L R
D 8
MU
D S
T W
MU
D S
T W
RE
GIO
NA
L R
D 2
0
RE
GIO
NA
L R
D 2
0
HIGHW
AY 54
HIGHW
AY 54
LAK
ES
HO
RE
RD
LAK
ES
HO
RE
RD
FISHERVILLE RD
FISHERVILLE RD
20 R
D20
RD
KIN
G S
T W
KIN
G S
T W
QU
EE
N E
LIZ
AB
ET
H W
AY
QU
EE
N E
LIZ
AB
ET
H W
AY
CAISTORVILLE RDCAISTORVILLE RD
REGIONAL R
D 27
REGIONAL R
D 27
VICTORIA AVEVICTORIA AVE
NIAGARA PKYNIAGARA PKY
HIG
HW
AY
40
5
HIG
HW
AY
40
5
RE
GIO
NA
L R
D 6
6
RE
GIO
NA
L R
D 6
6
TRINITY RDTRINITY RD
MO
UN
TA
IN R
DM
OU
NT
AIN
RD
YO
RK
RD
YO
RK
RD
HIGHWAY 54
HIGHWAY 54
Q5G
Q5G
Q23
BM
/ Q
24H
M
Q23
BM
/ Q
24H
M
A8G
A8G
M34H M34H
C9
/ C12
C9
/ C12
Q30
MQ
30M
N6M
/ N
5M
N6M
/ N
5M
N1M
/ N
2M
N1M
/ N
2M
Q2AHQ2AH
B18H / B20H
B18H / B20H
D3AD3AQ
24H
M /
Q29
HM
Q24
HM
/ Q
29H
M
Q25
BM
/ Q
29H
M
Q25
BM
/ Q
29H
M
Q23BM / Q25BMQ23BM / Q25BM
M27
B / M
28B
M27
B / M
28B
D1AD1A
Q2A Q2A
Q5G
Q5G
A8G
A8G
Q30
MQ
30M
Q5G
Q5G
Q2A
HQ
2AH
Q30
MQ
30M
Q25
BM
/ Q
29H
M
Q25
BM
/ Q
29H
M
A8G A8G
M34HM34H
Q2A
HQ
2AH
Q5GQ5GA
8GA
8G
Q2A
HQ
2AH
Q2A
HQ
2AH
Q2A
HQ
2AH
Q25
BM /
Q29
HM
Q25
BM /
Q29
HM
Q26
AM
/ Q
32A
MQ
26A
M /
Q32
AM
Q23BM / Q25BMQ23BM / Q25BM
CH
ER
RY
JC
TC
HE
RR
Y J
CT
RA
ILW
AY
JC
TR
AIL
WA
Y J
CT
DU
NN
VIL
LE T
SD
UN
NV
ILLE
TS
CA
LED
ON
IA T
SC
ALE
DO
NIA
TS
BE
CK
GS
BE
CK
GS
CA
IST
OR
JC
TC
AIS
TO
R J
CT
05
1015
2.5
Kilo
me
ters
Kilo
me
ters
Leg
end
Ch
ang
ed T
ran
smis
sio
n L
ines
Exi
stin
g cc
t, sa
g te
mp
to b
e ra
ised
New
2 c
ct 2
30 k
V L
ine
Tra
nsm
issi
on
Lin
es11
5 kV
230
kV
500
kV
Mun
icip
al B
ound
arie
s
Maj
or R
oads
WIL
CO
XC
OR
NE
RS
WIL
CO
XC
OR
NE
RS
ST
. AN
N'S
JC
TS
T. A
NN
'S J
CT
RO
SE
DE
NE
JC
TR
OS
ED
EN
E J
CT
ALL
AN
BU
RG
WE
ST
JC
TA
LLA
NB
UR
GW
ES
T J
CT
ALL
AN
BU
RG
TS
ALL
AN
BU
RG
TS
HO
LL
AN
D R
OA
D J
CT
HO
LL
AN
D R
OA
D J
CT
BE
AV
ER
DA
MS
JC
TB
EA
VE
R D
AM
S J
CT
ST
. JO
HN
'SV
AL
LEY
JC
TS
T. J
OH
N'S
VA
LLE
Y J
CT
LOU
TH
JC
TLO
UT
H J
CT
BE
AC
H T
SB
EA
CH
TS
HA
NN
ON
JC
TH
AN
NO
N J
CT
NE
AL
E J
CT
NE
AL
E J
CT
SO
UT
HC
OT
E J
CT
SO
UT
HC
OT
E J
CT
CA
RLU
KE
JC
TC
AR
LUK
E J
CT
MID
DLE
PO
RT
TS
MID
DLE
PO
RT
TS
BU
RLI
NG
TO
N T
SB
UR
LIN
GT
ON
TS
N58
0M /
N58
1M
N58
0M /
N58
1M
M27
B /
M28
B
M27
B /
M28
B
M27B / M28B
M27B / M28B
Q23
BM
/ Q
25B
M
Q23
BM
/ Q
25B
M
Q23
BM
/ Q
24H
M
Q23
BM
/ Q
24H
M
Q24HM / Q29HM
Q24HM / Q29HM
Q5G
Q5G
Q2A
HQ
2AH
Q23
BM
/ Q
24H
M
Q23
BM
/ Q
24H
MQ
26A
/ Q
28A
Q26
A /
Q28
A
Q2AHQ2AH
D3A
D3A
Q3
0M
/ Q
32A
Q3
0M
/ Q
32A
Q2
6A
/ Q
28
AQ
26
A /
Q2
8A
Q2
6A
M/ Q
32A
MQ
26
AM
/ Q32
AM
N580M / N581M
N580M / N581M
(C)
Cop
yrig
ht H
ydro
One
Inc.
All
right
s re
serv
ed.
No
part
of
this
dra
win
g m
ay b
e re
dist
ribut
ed o
r re
prod
uced
in a
ny fo
rmby
any
pho
togr
aphi
c, e
lect
roni
c, m
echa
nica
l or
any
othe
rm
eans
, or
used
in a
ny in
form
atio
n st
orag
e or
ret
rieva
l sys
tem
.N
eith
er H
ydro
One
Inc.
nor
any
of i
ts s
ubsi
diar
ies
assu
mes
liabi
lity
for
any
erro
rs o
r om
issi
ons.
A8G
A8G
Q30
M /
Q32
A
Q30
M /
Q32
A
Q26
AM
/ Q
32A
M
Q26
AM
/ Q
32A
M
Pro
pose
d F
acili
ties
- N
iaga
ra R
einf
orce
men
t Pro
ject
Exh
ibit
B -
2 -
2Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
SCHEDULE “B” – NRP WORK SITES
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
SCHEDULE “C” – NRP SITE
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000
Cou
rt F
ile
No.
HY
DR
O O
NE
NE
TW
OR
KS
IN
C.
Pla
inti
ff
- an
d -
HA
UD
EN
OS
AU
NE
E C
ON
FE
DE
RA
CY
CH
IEF
S
CO
UN
CIL
ET
AL
.D
efen
dan
ts
ON
TA
RIO
S
UP
ER
IOR
CO
UR
T O
F J
US
TIC
E
PR
OC
EE
DIN
GS
CO
MM
EN
CE
D A
T
BR
AN
TF
OR
D
ST
AT
EM
EN
T O
F C
LA
IM
BO
RD
EN
LA
DN
ER
GE
RV
AIS
LL
P
Bar
rist
ers
and
Sol
icit
ors
Bay
Ad
elai
de
Cen
tre,
Eas
t T
ower
22
Ade
laid
e S
tree
t W
est
Tor
onto
, Ont
ario
M5
H 4
E3
Ch
rist
oph
er D
. Bre
dt
(LS
O #
2362
7Q)
Tel
: (
416)
367
-616
5
Em
ail:
CB
redt
@bl
g.co
m
Mau
reen
Doh
erty
(L
SO
#63
621W
) T
el:
(416
) 36
7-61
83
Fax
: (4
16)
367-
6749
E
mai
l: M
Doh
erty
@bl
g.co
m
Law
yers
for
the
Pla
inti
ffs
Electronically issued / Délivré par voie électronique : 05-Jul-2019 Court File No./N° du dossier du greffe: CV-19-00000152-0000