onscreen cover – alternative 5 nuclear law and contracting nuclear new build made easy vanessa...
TRANSCRIPT
Nuclear Law and ContractingNuclear new build made easy
Vanessa Jakovich, Counsel, London
UKELA, 8 June 2015
Nuclear new build in the UK
Sizewell
Utilities and Sites
Bradford
Hinkley Point
Oldbury
Heysham
HartlepoolMoorsid
e
Wylfa
Decommissioning
Consortium creation and site selection
Project design, licensing and
consenting
Construction Commissioning and operation
Key project phases: Current UK Status
Develop the operating entity
Incorporation and
consortium agreements
Develop human resources
Operational governanceDevelop governance, financing and contract
management procedures
Select site
Early site works (preliminary planning
permissions)
Land optio
n
Site work
s
Siting Exercise lease
Sele
ct
tech
nolo
gy
Fuel contractsTechnology, contracting and procurement
Contract placement
Long lead
items
Further componen
ts
Procurement
Waste contracts
Decommissioning contractsOfftake contracts (and CfDs)
NDF
Construction and operation
Grid connection agreements
Operation and maintenance Decommissioning
Construction
Hinkley Point
Wylfa
Moorside
Site design, EIA and consultation
Decommissioning EIA and
de-licensing
DCO Site
LicensingGDA
Consents
Licensing hold point and DCO condition clearance
Maintain compliance
4
O P E R A T O R
Legal anatomy of a nuclear project
Offtake Arrangements
Lease
I N V E S T O R
I N V E S T O R
I N V E S T O R
L A N D L O R D
OFFTAKER/GRID
CfD COUNTERPARTY
Contract for Difference
Shareholders Agreement
REACTOR SUPPLIER/
EPC CONSORTIUM
SUPPLY CHAIN
DIRECT SUPPLIERS
EPCContract
Direct supply contracts
Supply chain contracts
FUEL SUPPLY CHAIN
Fuel contracts
WASTE TRANSFER
COUNTERPARTIES
Waster transfer contracts
INDEPENDENT NUCLEAR
DECOMMISSIONING FUND
Funded decommissioning
arrangements
NUCLEAR NEIGHBOUR
Cooperation arrangements
CONSTRUCTION AND SUPPLY ARRANGEMENTS
CONSORTIUM ARRANGEMENTS
LANDARRANGEMENTS
5
Land arrangements: background
Land ownership• New build sites identified through Strategic Siting Assessment, embedded
in the Nuclear NPS (EN-6)• EdF developing former British Energy sites: bespoke regime applies to
legacy liabilities• Other sites (Horizon and NuGen) are leased from the NDA
Issues• Government landlord NDA sites not designated under Energy Act 2004
• use/development is unrestricted• NDA has no statutory liability for legacy remediation
DECC Policy - requirement to progress development of sites• Nuclear neighbours All sites neighbour legacy plants which are operational or undergoing
decommissioning Reasons for original siting decisions endure: eg, cooling water, seismic
stability, visual impacts, transport. existing grid. workforce and skills, community acceptance
Presents new and interesting challenges:• Risk of legacy contamination on new build site• Impacts on each other's safety cases (generating v
generating/decommissioning)• Competition for local resources: transport and access; workforce; grid
capacity• Cumulative radiological dose impacts?
6
Land arrangements: contracting considerations
• Leases: Timing Obligation to progress development: milestones and conditionality Aligning land access and payment obligations with investment and permitting
milestones, eg:• Identification of core site: access for EIA and technical site assessment; defining the
boundary• Hand-back obligations for laydown land?• Need a long-term leasehold interest before site licence grant (but investor funding
more difficult pre-license grant)• Grant of new licence can immediately channel the legacy liability to the new
operator: need to ensure licence not granted until project definitely proceeding• Environmental liability allocation for legacy contamination
Channelling regime for third party liability: implications of licensing a site contaminated by its licensed nuclear neighbour
Nature of remediation costs• Clean-up obligations arising through DCO and licensing conditions• Radioactive Contaminated Land Regime
• Site Licensee Cooperation Agreements Safety case
• Agree cooperative processes up-front to avoid later irresolvable impasse during licensing
• Sharing of information to facilitate radiological assessments Local resource management
7
Consortium arrangements: backgroundCurrent generation of nuclear consortia• Private, and not just utility driven: cross-disciplinary• Reactor vendors driving consortia creation• Competing requirements: Flexibility to attract investment –v- stability to secure nuclear site licence Attracting early investment to fund siting and consenting -v- deferring funding
commitment until regulatory milestones are met• “Licensable entities” being grown organically, in a competitive market for skills and
resources
AP1000Justified
Phase 4 of GDA
UK ABWRJustified
Phase 2 of GDA
EPRJustified
GDA finalised
Sizewell
Utilities and Sites
Bradford
Hinkley Point
Oldbury
Heysham
HartlepoolMoorsid
e
Wylfa
Reactor Technology
8
Consortium arrangements: contracting considerations
Stage Consortium agreement considerations
Securing a site and characterising its suitability
• Land option (and government strategic siting commitments)• Land purchase costs / Lease premiums and obligations• Site characterisation (including risk from works; grid connection;
workforce; exit planning; legacy liability from site characterisation works?)
• Making the site suitable (eg, legacy nuclear neighbour) contamination
Building a “licensable entity”
• Committing stable, consistent expertise (the right mix of investor expertise; exit restrictions; investor secondment obligations)
• Ensuring corporate governance meets regulator’s standards (independence; stability; expertise – intelligent customer status)
Selecting and certifying a reactor design
• Technology competition processes• Justification• Design certification – costs; timing
Securing a reliable supply chain
• Ensuring supply chain is capable of meeting regulator expectations
• Ensuring delivery (eg, early long-lead items) is committed to be made at the right time
• Securing a main contractor, or means to coordinate project delivery
Developing relationships with stakeholders
• Ensuring enough stability, early design and planning for meaningful community engagement
• Strategy for engagement with regulators• Making and supporting licence and permit applications (and
defending legal challenges)
Consortium arrangements: contracting considerations
Planning the project timeline• Interdependencies between licensing and investment milestones require
strategic planning • Consortium agreements need to align with key licensing stages Certainty: To harness the increased certainty from the grant of key
approvals, as pre-conditions to major investment decisions/commitments Resources: To ensure parties commit to provide the necessary resources to
facilitate the completion of licensing phases – both expertise and finance Risk: To ensure that liabilities and duties are not triggered until the
consortium is adequately resourced and committed – and to create an exit plan
Exit Participant interest changes over the life of a project Consortium agreement exit become important Managing “licensable entity” status an important consideration
9
UK Nuclear new build: generic consortium timeline
Justification
NuclearSiteLicence
Planning
OtherConsents
Generic Design Assessment Nuclear site licence application
Funded Decommissioning Plan
Strategic Siting
Assessment
Environmental Impact
Assessment
Consultation with community
Grid Connection
Generation Licence
Nuclear Insurance
Justification of Reactor Design
Materials handlingPreliminary site work
permission
Development Consent Order (DCO) Application
Preparatory Phase Construction Phase
Environmental Permit
Satisfy ongoing licence condition hold-points
Satisfy pre-operation DCO conditions
allows early site access
Initial Investment
Decision
Preliminary funding and
consortia creation
Final Investment
Decision
11
Construction and supply contracts: Regulatory risks
Risks associated with grant of licence approvals• High level licensing risks: pre-licence early works and long lead items• Risk of new/changes to requirements arising out of the licensing process
Requirements for design change Additional justification (eg, demonstration of the quality of components, materials
and as-built works) Requirements for particular working methods (manufacture, construction and/or
commissioning)
Risk of delayContinual ONR oversight, supervision and intervention into supply chain operationsExtensive use of “hold points” where work cannot proceed without ONR approval: significant scope for schedule overruns
Practical consequences of constructing in a nuclear environment• Nuclear safety has priority: quality supervised closely by regulator and non-
negotiable• Requirement for operator to retain control – “intelligent customer” status:
limited ability for Suppliers to work ‘at risk’ • Operator and ONR control limits supplier ability to manage internal
processes • Limited ability for parties to agree substitutes and compromises• Normal management techniques to control time and cost are not available:
risk of significant cost and schedule overruns
Footer12
Construction and supply contracts: Nuclear liability
Strict Liability - Operator liable for any damage caused by radiation release- Victims do not need to prove fault or negligence
Exclusive Liability - All liability channelled exclusively to the operator- Statutory bar on victim claims against any other party- Very limited scope for operator recourse to third parties
Cap on liability - Operator liability limited to a specified amount- Government/s meet claims above the cap- Usually no recourse by governments against operators - Some exceptions (e.g. Germany, Switzerland, Japan)
Time limit - Claims barred a certain period after incident - eg, 30/10 years from accident; 2-3 years from discovery
Mandatory insurance - Operators bound to maintain financial security up to cap- Can be private insurance, operator pool (eg, US and Germany), self-insurance; state/bank/corporate guarantee or a combination
Exclusive jurisdiction - Courts of the installation country have exlusive jurisdiction over victim claims
Nuclear liability: statutory framework
NIA 65 implements the Paris/Brussels convention in a unique way:• Duties: Licensee bears section 7 duties to prevent release of radioactive substances at
from a licensed nuclear site • Scope of licensee liability: personal injury or property damage arising from any breach
of Section 7 duties English common law jurisprudence on conventional property damage means wider
scope Includes come economic loss arising from property damage, and damage to the owned
environment • Cap: £140million per incident (and licensee must carry government-approved insurance)• Licensee recourse: Ability to for suppliers to accept licensee liability by contract much
more limited than other countries: Only applies to damage to property within the site boundary
Implementation of the 2004 Amending Protocol• DECC Consultation process finalised in December 2012• The Nuclear Installations (Liability for Damage) Order 2015 not yet laid before
Parliament Adopts wider scope and higher caps of the 2004 Protocol Does not directly adopt 2004 Protocol – as UK common law already channelled some of
wider scope Resolves some uncertainties under UK case law (eg, meaning of “occurrence” after
Magnohard)• Political support for implementation• Unlikely to be implemented until insurance is available (for all EU signatories, given EC
requirement for simultaneous ratification)
Dealing with exceptions to channelling in contractsOnly third party claims are covered• Suppliers can still be exposed to nuclear damage to the nuclear installation
itself, or property within the site licence boundaryInternational claimants• Claims by nationals of a non-Convention country can be brought against
anyone under normal principles of law in that other country• Supply across Convention boundaries exposes suppliers to home country
litigation risk• Who is your counterparty?Operators have rights of recourse• Against an individual acting or omitting to act with intent to cause nuclear
damage• Where such recourse is expressly provided for by contract
Beware risk of implication from a general contractual indemnity or warranty
Unchannelled scope
• Claims for economic loss, environmental damage and the costs of preventative measures currently unchannelled
• Construct change of law clauses carefully
ThismaterialisprovidedbytheinternationallawfirmFreshfieldsBruckhausDeringerLLP(alimitedliabilitypartnershiporganisedunderthelawofEnglandandWales)(theUKLLP)andtheofficesandassociatedentitiesoftheUKLLPpractisingundertheFreshfieldsBruckhausDeringernameinanumberofjurisdictions,andFreshfieldsBruckhausDeringerUSLLP,togetherreferredtointhematerialas‘Freshfields’.Forregulatoryinformationpleaserefertowww.freshfields.com/support/legalnotice.
TheUKLLPhasoffices orassociatedentitiesinAustria,Bahrain,Belgium,China,England,France,Germany,HongKong,Italy,Japan,theNetherlands,Russia,Singapore,Spain,theUnitedArabEmiratesandVietnam.FreshfieldsBruckhausDeringerUSLLPhasofficesinNewYorkCityandWashingtonDC.
Thismaterialisforgeneralinformationonlyandisnotintendedtoprovidelegaladvice.
©FreshfieldsBruckhausDeringerLLP2014
Thank you