on the pre-lay trench tool design - semantic scholar · applying the physics behind the cutting...

14
On The Pre-Lay Trench Tool Design S.K.A. Dirven October 7, 2016 Abstract The significant growth in offshore wind activities in boulder clay areas requires suitable cable protection solutions. It is desirable to create a trench prior installation of the cable in order to guarantee the target depth of burial. Modern equipment of available on the market can be refined in order to create a reduced footprint, both economical and environmental. For this thesis there is looked into an innovative solution to create a pre-trench by utilization of a classic dredging vessel. Several alternatives are investigated. However, eventually two different mechanical cutting methods were selected for detailed investigation as a consequence of a multi criterion analysis. One uses counter rotating shredders and the other concept consists of an inclined screw conveyor. After physical considerations it turns out the screw conveyor has the best potential and is therefore subjected to a detailed design. 1 Introduction Offshore wind power is the use of wind farms located offshore, for harvesting wind energy in or- der to generate electricity. The offshore wind farms are connected to the onshore grid via power cables. The wind turbines are connected to an offshore substation by means of infield cables and consequently the offshore substation is connected to the onshore grid via export cables. Cable protection is required in order to avoid economic losses as much as possible due to damage on the cable. Various techniques can be deployed to bury the cable, such as rock placement, installation of mattresses, mechanical trenching, ploughing and jetting. Among other things depending on soil conditions, one method can be more suitable than another one. Furthermore, the cable can be installed either after trenching (pre-lay), simultaneously (simulta- neous lay and burial) or prior trenching (post-lay). Post-Lay is cost-effective, however, deploying dedicated burial tools, such as trenchers in stiff soils could result in unsatisfactory burial depths due to the cohesive character of the soil. Therefore in these areas is a pre-lay burial method more desirable. Creating a trench can be done by the use of classic dredging. The scope of this thesis includes a pre-lay operation for export power cables, executed by a trail- ing suction hopper dredging vessel exerted in cohesive soils. Utilizing the conventional dredging equipment available on the market results in oversized trenches in terms of volume. In general the trench profiles generated are disproportional compared to the required dimensions for cable installation. Figure 1 depicts a conventional trench profile containing an export power cable. Figure 1: Trench profile created with conven- tional draghead Figure 2: Reduced trench profile Consequently, from both an economical and environmental point of view the operation can be optimized. The aim of the thesis study is to acknowledge the most optimal concept design solution, to create 1

Upload: others

Post on 25-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

On The Pre-Lay Trench Tool Design

S.K.A. Dirven

October 7, 2016

Abstract

The significant growth in offshore wind activities in boulder clay areas requires suitable cableprotection solutions. It is desirable to create a trench prior installation of the cable in orderto guarantee the target depth of burial. Modern equipment of available on the market canbe refined in order to create a reduced footprint, both economical and environmental. Forthis thesis there is looked into an innovative solution to create a pre-trench by utilization of aclassic dredging vessel. Several alternatives are investigated. However, eventually two differentmechanical cutting methods were selected for detailed investigation as a consequence of a multicriterion analysis. One uses counter rotating shredders and the other concept consists of aninclined screw conveyor. After physical considerations it turns out the screw conveyor has thebest potential and is therefore subjected to a detailed design.

1 IntroductionOffshore wind power is the use of wind farms located offshore, for harvesting wind energy in or-der to generate electricity. The offshore wind farms are connected to the onshore grid via powercables. The wind turbines are connected to an offshore substation by means of infield cables andconsequently the offshore substation is connected to the onshore grid via export cables. Cableprotection is required in order to avoid economic losses as much as possible due to damage on thecable.Various techniques can be deployed to bury the cable, such as rock placement, installation ofmattresses, mechanical trenching, ploughing and jetting. Among other things depending on soilconditions, one method can be more suitable than another one.Furthermore, the cable can be installed either after trenching (pre-lay), simultaneously (simulta-neous lay and burial) or prior trenching (post-lay). Post-Lay is cost-effective, however, deployingdedicated burial tools, such as trenchers in stiff soils could result in unsatisfactory burial depthsdue to the cohesive character of the soil. Therefore in these areas is a pre-lay burial method moredesirable. Creating a trench can be done by the use of classic dredging.The scope of this thesis includes a pre-lay operation for export power cables, executed by a trail-ing suction hopper dredging vessel exerted in cohesive soils. Utilizing the conventional dredgingequipment available on the market results in oversized trenches in terms of volume. In generalthe trench profiles generated are disproportional compared to the required dimensions for cableinstallation. Figure 1 depicts a conventional trench profile containing an export power cable.

Figure 1: Trench profile created with conven-tional draghead Figure 2: Reduced trench profile

Consequently, from both an economical and environmental point of view the operation can beoptimized.The aim of the thesis study is to acknowledge the most optimal concept design solution, to create

1

Page 2: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

a reduced trench profile, by utilization of a trailing suction hopper dredger (TSHD), for subseapower cable burial in stiff cohesive soil types with the potential occurrence of boulders. Bouldersare defined as a separate rock mass, having a diameter larger than 200mm. However, on the presentseabed they usually don’t exceed values of 2 m. Problem statement as mentioned, is establishedwith regards to power cable protection for offshore wind activities in the North-Sea areas, werethe seabed consists of boulder clay. Possible geometry of a reduced trench profile can be obtainedfrom Figure 2.

2 ApproachThe strategy of approaching the problem can be obtained from the Kite model depicted in Figure3. Herein the main stages during the project are listed, starting with the literature review.

Detailed Design

Concept Design

MCA

Implementation

Literature review

Figure 3: Project stages

A Literature review on relevant topics like offshore site investigation, subsea cable installation,TSHD and dragheads, soil mechanics and physics on excavation formed the basis for the thesis.Additional there is looked into onshore trenching applications, for instance in the agriculturalindustry. The review includes the current knowledge including substantive findings, as well astheoretical and methodological contributions to the topics in consideration. The gained informationis used directly or indirectly in the following stages.Hereafter a multi criterion analysis (MCA) is carried out including requirements, functional analysisand concept morphology. The two best most conceptual designs out of the MCA are subjected tofurther detail analysis by physical considerations, i.e. cutting forces, power calculations, physicalworking. The one concept which turned out to have the best potential was selected for moredetailed design. And finally there was an implementation stage.

2.1 Multi Criterion AnalysisDesign requirements were drafted including trench geometry, limitations of TSHD, soil properties,area conditions, operability and so on. A distinction is made between fixed requirements andvariable requirements. The latter were assessed to each other in order to assign importance factorsto them. Main function of the tool is obviously Creating the trench. Subsequently, 9 partialfunctions contribute to perform the main function. For each partial function multiple concepts tofulfill the function were considered. A morphological overview containing the above was the result.Hereafter ten solution structures were selected from the overview. Ten potential concept designswere assessed to the requirements including weigh factors. After assessment, the concepts whichhad the highest score were the Shredder Bucket and the Hybrid Auger.

2.2 Shredder BucketThe concept contains a trapezoidal bucket with two counter rotating shredder bodies, located atthe end of the vessel’s suction pipe. The tool will be lowered from the vessel to the seabed by

2

Page 3: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

means of a steel cable connected to the onboard deck winch. A skid plate touches the seabed andconsequently, the tool will be dragged over the seafloor. An actuator, mounted on top enablestransit in of the bucket into the soil . Simultaneously, the counter rotating shredders, mountedinside the bucket are activated. The undisturbed seabed soil will be cut into lumps and as thesoil has passed the shredders, water flow enabled by water jets will contribute to both transportof the lumps into the suction pipe and cleaning of the shredder bodies. The latter is inevitablefor preventing clogging of the bucket. In the initial design, the soil will be sucked into the hopper.The purpose of using two shredder bodies, is that they cross the cutting line in the soil of eachother, which makes it possible to produce lumps. Counter rotating shredders are used to eliminateundesirable lateral forces. Furthermore, the clay sticking to one shredder will come of the shredderbody since the other rotating shredder body will take the lump away.

2.3 Hybrid AugerThe second concept uses an inclined screw conveyor (auger) for both cutting and transport of thesoil out of the trench. The tool is located at the end of the suction pipe as well. A hydraulic systemenables the required cutting depth can be achieved by moving the auger up or down. The housingin were the auger can be retracted, is suspended with a steel wire rope which in turn is connectedto the swell compensator of the operating vessel. The compensated wire force guarantees for aconstant force between tool and seabed. Furthermore, the housing is connected to the suction pipevia a cardan joint. This joint captures the ranges of angles, the pipe can admit as a retinue of thepotential differences in water depth. Once the tool touches the seafloor, the auger will be movedinto the seabed. The concept design supports both suction and sidecast operation, making it anhybrid design.

3 Physical Considerations

3.1 GeneralIn this section, general information is shown which is applicable for both concepts.

3.1.1 Soil parameters

The maximum cohesion value applied is derived out of general survey data within the region. Theadhesion can be expected as a fraction of the cohesion. Figure 4 shows this relation, exposed byTomlinson (1957). On the left vertical an empirical adhesion factor is shown. On the horizontal,the cohesion values of the clay are shown. The chart is generated for foundation piles penetratinginto clay grounds. The pile adhesion is derived from the contact surface area and the shaft resis-tance for penetration.For cohesion values above 150 kPa, the adhesion factor converges to 0.25 according to the chart.However, it is doutbful what physically happens. How stiffer the clay, the less tendency it containsto stick to another material. Considering this effect, the 25 % as shown in the figure will be mostlikely caused by friction and not by adhesion. For this study, however, the true physical meaningis left outside the scope.

Figure 4: Adhesion factor, Tomlinson (1957)Figure 5: Definitions of cutting process, Miedema(2014)

3

Page 4: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

3.2 Cutting forcesApplying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction forces and consequently the energy required for excavation.Cutting forces are determined based on the equilibrium of forces on a layer or chip of soil cut([Miedema, 2014]). The derivation is valid under the assumption that the stresses on the shearplane and the blade are constant and equal to the average stresses acting on the surfaces. Anothercondition is that in this chapter only 2-dimensional situations will be described. Clay cuttingdefinitions on a single blade can be obtained from Figure 5.Where:

A = blade tip hi = layer cut thicknessB = shear plane vc = cutting velocityC = top of blade α = blade angleA-B = shear plane β = shear angleA-C = surface of blade Fh = horizontal forcehb = blade height Fv = vertical force

As per Miedema, the cutting processes in clay are dominated by cohesion and adhesion. Cohesionmeaning the sticky effect between two objects of the same material, in this case the clay particles.Adhesion meaning the sticky effect between two objects of a different material in this case theclay and the material of the tool. Miedema presents 3 different types of failure in his book whencutting clay namely, the flow type, the curling type and the tear type. When cutting under normalconditions, the flow type occurs. The curling type takes place when the adhesion is high comparedto the cohesion. This forces the clay peel to ’curl’ from the blade. The tear type is present whenthere is a relatively small blade angle α and the adhesion is small compared to the cohesion.In this stage as a starting point the calculations derived for the flow type are used. All the forcesare per unit width (w), since a 2-dimensional situation is considered.Both the adhesion force and cohesion force are completely depended on the surface area they areacting on. The expression for the cohesion force reads:

C =λ · c · hi · wsin(β)

Consequently the adhesion force can be calculated by:

A =λ · a · hb · wsin(α)

When cutting clay, the internal and external shear strength increase over the time, also known asstrengthening. Accounting for the strengthening phenomena, a strengthening factor is included inthe calculation, λ. Since λc and λa are nearly identical in magnitude, an average quantity λ isused for the calculations. The equation reads:

λ = 1 +τ0τy

· ln(1 +1.4 · vchi

· sin(α)sin(α+β)

ε0)

With: τ0 /τy = 0.1428 and ε0 = 0.03. The relation between the adhesion and cohesion is knownas the ac ratio r .

r =a · hbc · hi

The standard cutting theories available for clay cutting processes are modified in order to beapplicable for the chosen concept designs.

3.2.1 Torque

From the cutting forces, the required torque to rotate a cutting body can be determined. Torque,also known as the moment of force, is the rotational analog of force. A force is required to changean object’s state of motion in the same way a torque is required to change an object’s state ofrotation.The torque on a shaft can be computed as a force normal to the shaft multiplied with the distance

4

Page 5: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

between the acting point of the force and the rotation point. In general vector form the equationfor torque reads:

~T = ~F · ~r

In where ~T is the torque vector, ~F is the force vector and ~r is the position vector of the pointwhere the force is applied relative to the axis of rotation. The torque direction is perpendicular tothe plane in which it is acting.

3.3 Shredder BucketFor the shredders, the driving forces are dominated by adhesion between the shredder blade andthe clay. Adhesion force is directed in opposite direction of rotation, obtainable in Figure 6.

Ashred

ω

Figure 6: Adhesion on a single shredder

At first sight the strengthening factor is omitted for determining the adhesion force, since it ischallenging to determine some of the relevant parameters, i.e. shear angle and layer cut. Hence,the expression for the adhesive force reads: (Ashred):

Ashred = a · Stot

Stot is the total surface area of one shredder body (top face and bottom face of the plates) andis obtained from a CAD model. Stot is approximately 3 m2. The surface area is not constant inthe direction of z. and can be presented as a function of the height. For simplicity, first the totalsurface area is divided by the total height (h) which turns in the gradient q = Stot

h . Sshred as afunction of the height can be estimated by the following equation.

Sshred(z) = q · z

The adhesion can now be integrated over the height.

Ashred(z) =

∫ h

0

a · Sshred(z) · dz

3.4 TorqueOnce the cutting forces are determined, the torque balance can be derived. Purpose is to definethe required amount of torque for rotation of both shredders. The torque can be estimated bymultiplying the total resistance force with the distance between the rotation point and the actingpoint of the force (rt). For simplicity the top view of one shredder can be seen as a square platewith length of the sides equal to W . Figure 7 shows this top view.With the assumption that the adhesion force is equally distributed over the surface, the magnitudeof the arm rt can be estimated by finding the centroidal line, which basically means that the surfacearea on the left of the line and on the right of the line are equal in magnitude. The position ofthis line is depicted in Figure 7 as well. The derivation for the length of the arm holds:

5

Page 6: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

r

w

w

Y

X

Figure 7: Top view single shredder body

x

z

h

r t,min r t,max

Figure 8: Side view shredder radius

rt =

√W 2

Since the shredders are conical shaped, the width (W ) and therefore, the radius of the shredder isa function of the height. This leads to the following expression:

rt(z) = rt,min +

(rt,max − rt,min

h

)· z

Involved parameters can be seen in Figure 8. The torque equation as a function of the heightreads:

T shred(z) = Ashred(z) · rt(z)The expression requires integration over the total height in order to determine the total amount oftorque. Filling in all the above derived equations and adding the integral boundaries, the torquebalance becomes:

T shred(z) =

∫ h

0

a · q · z · (rt,min +rt,max − rt,min

h)z · dz

3.4.1 Result

Combining the equations turns in the results obtainable in Figure 9 for the required shaft powerto drive the shredders. The chart illustrates the required power in relation to the forward velocityof the tool.

vt [m/s]

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

Pshre

d [kW

]

0

50

100

150

200

250

300

3502 shredders

1 shredder

Figure 9: Shredder power in function of forward velocity

3.5 Hybrid Auger3.5.1 Pitch

According to Kase Custom Conveyors, Bulk Material Handling Equipment and their online ScrewConveyor Engineering Guide, a wide variety of pitch to diameter ratios are present in the industry.

6

Page 7: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

Pitch may vary from p = 12 · Do, for handling extremely fluid materials to p = 1 1

2 · Do, fortransporting fluid materials or for rapid movement of very free-flowing materials.Other specific designs, furthermore, are not surprising e.g. variable pitch, double flights, taperedouter diameter, cut & folded flights and so on.Augers with a pitch equal to the outer diameter are defined as standard. They can be deployed ina broad range of applications and materials including vertical and inclined conveying of material.Therefore, a pitch to diameter ratio of p = Do, will be taken at first sight. Later on the pitch valuewill be optimized.

3.6 Cutting ForcesA schematic side view of the auger approaching the undisturbed seabed is depicted in Figure 10.As per Miedema (2014), cutting processes in clay are dominated by cohesion and adhesion. Firstthe cohesion contribution is exposed followed by the adhesion.As the tool moves forward, only half of the auger’s perimeter is in contact with undisturbed soil(Fig. 11). The other half is facing an empty trench.

Vt

X

Z

hcut αaug

Figure 10: Side view auger in soil

Vt

Y

X

Figure 11: Top view auger in soil

For the cohesion force this contact area is governing. In order to determine the quantity of thissurface area, the parameters involved can be seen in Figure 10. The right hand side of Figure 10is a section view of the contact area.When projecting this area in a 2-dimensional plane, it can be subdivided into a rectangular pieceand a triangular piece. For the total contact area (Scoh) it can be said:

Scoh = Srect + Stria =π

2·Do

(hcut

sin(αaug)− Do

2 · tan(αaug)

)With:

Do = outer diameter auger

hcut = depth of cut

αaug = angle of attack auger

The cohesion force (Caug) can be determined by:

Caug = Scoh · c

As with the shredder calculations, the strengthening factor (λ) will be omitted at first sight, sinceit is a concept design and it is challenging to determine the exact value of the shear angle and thelayer cut of the auger.

3.6.1 Adhesion

The adhesion force (Aaug), is depended on the contact area between the soil and the tool. Thesum of the flight areas is governing the adhesion force. Both the top side and the bottom side ofthe flights are in contact with the soil. During operation, the soil is constantly sliding over theauger. The amount of flights within the given auger length is depended on the pitch (p).Number of flights is given by total length of auger (laug) (including the part inside the housing)divided by the pitch. The total surface area of the flights can be computed by:

7

Page 8: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

Saug =π

2· laug ·Do

To be completely accurate, the shaft diameter (Di) should be subtracted in calculating the surfaceof the flight. However, the total surface area of the inner shaft contributes to the adhesion forceas well. In this stage of the design, it is appropriate to use the simplified Saug. The adhesion force(Aaug) can be computed with:

Aaug = Saug · a

Once the magnitudes of the two dominating forces have been exposed, it is important to determinethe direction in which they act. The cohesion force Caug will act in axial direction of the auger(Fig. 12), since the shear strength of the clay has to failed in that direction. The point of actingis on the edge of the blade. Furthermore, a normal component can be seen (Caug,n) as well asan horizontal component (Caug,h). The latter is important for the torque calculation since it isacting in the same plane as the rotational movement. The horizontal component of the cohesionforce reads:

Caug,h = tan(θaug) · Caug

The pitch angle (θaug) plays a dominant role in the value of this parameter and is depended onthe pitch - diameter ratio. The expression reads:

θaug = tan−1( p

2 ·Do

)Figure 13 shows were the adhesion force (Aaug) is acting. This force contribution is acting overthe complete surface of the auger and is directed in opposite direction of rotation.

θaugCaug,h

Caug,nCaug

Figure 12: Cohesion force

ω

Aaug

Figure 13: Adhesion force

3.7 Lateral Reaction ForcesSince there is 1 auger considered, the reaction forces in the horizontal plane contribute to lateralmovement of the complete tool during operation. Therefore, it is vital to expose the magnitude ofthis force.Accounting for both the angle of attack and the pitch angle, the tangential component (Rftan,tot)in the horizontal plane of the total cohesion force can be calculated by:

Rf tan,tot = cos(αaug − θaug) · Caug,n (2)

The tangential force acting on a point on the cutting edge is depicted in blue in Figure 15.The tangential component, however, will act over the complete auger - soil interaction line (i.e. πin radians). A top view of the situation considered can be seen in Figure 15. The component indirection of Y is governing for the lateral movement of the tool. The magnitude of this force isvarying over the interaction line and is a function of the angle, φ. Hence, the expression reads:

Rfy = sin(φ) ·Rf tan

When taking the integral over the contact area, the total can be exposed as:

Rfy,tot =

∫ π

0

sin(φ) ·Rf tan · dφ

8

Page 9: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

Z

X

ω

Caug,n

Caug

Caug,h

Rftan

αaug - θaug

αaug

Figure 14: Tangential component cohesion force

ω

X

Y

φ

Rftan

φ

Rfy

Figure 15: Y - component cohesion force

The individual components (Rftan) are not known, the total (Rftan,tot), however is. Therefore, thetotal magnitude in Y direction can be calculated by using the following ratio:

Rfy,tot =

∫ π

0

sin(φ) · dφ

π·Rf tan,tot

With this expression, an optimum for the pitch - diameter ratio can be obtained. The adhesionand cohesion components, which are governing for the required shaft power and the lateral forceare plotted in function of the pitch to diameter ratio (p/Do), for an angle of attack equal to 55degrees and a soil cohesion of 200 kPa.

p/Do [-]

0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Fo

rce

[kN

]

0

100

200

300

400

500

600R

y,tot

Aaug

+Caug

h

Figure 16: Forces in function of pitch ratio

For larger ratios, the adhesion and cohesion sum is significant lower. Hence the required shaftpower to drive the auger is lower. The lateral reaction force, however, slightly increases withincreasing pitch ratio. Consequently, as a trade-off a smaller ratio than 1 is not recommended.

3.8 TorqueThe vector form torque equation can be simplified to:

T = F · r

In order to estimate the torque balance, required for the operation, three contributions can bedistinguished, namely:

1. Cohesion

2. Adhesion

3. Inertia of soil inside auger

9

Page 10: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

To encounter the addition of the cohesion, the force normal to the shaft is equal to Caug,h andthe position of the acting point is the outer edge of the auger. Which means the distance betweenrotation point and acting point is equal to half the outer diameter. The torque required is equalto:

T coh = Caug,h · Do2

As can be seen in Figure 13, the adhesion force acts on the complete surface of the flights. To findthe position of the centroidal , the surface on both sides of the line have to be equal. This leadsto the following expression for the torque arm, when encountering the shaft diameter (Di) as well:

radh =

√Do2 +Di2

8

The torque balance to overcome the adhesion is equal to:

T adh = Aaug · radh

Finally there is a contribution from the inertia due to the mass of the soil inside auger. However,not the total amount of soil inside the auger has to be taken. When the auger is rotating, everytime-step a new amount of soil mass is entering the auger. Only this part has to be acceleratedfrom zero to the rotational speed of the auger. The amount of soil what is inside the auger by thattime, already moves with the rotational speed.Experience from calculations in previous projects, learns that this contribution is disproportionalto the cohesion and adhesion. Therefore it will be omitted in the torque calculation.The total torque required to drive the auger during operation is said to be:

T aug = T coh + T adh

3.8.1 Production

The in-situ volume production in function of the forward velocity can be computed by:

Qaug(vt) =Do · dtren

np· vt

With vt the forward velocity of the tool and np the number of passes to complete the trench. Thetarget depth of the trench (dtren) is also in direct relation with the depth of the cut hcut =

dtrennumpas

.

3.8.2 Fill rate

Fill rate (i) of the auger is not constant over the height. At the bottom side the auger is filledhalf (Fig. 10) , meaning i = 0.5. At the top the auger is completely filled and therefore imax = 1.Hence, imin = 0.5.

3.8.3 Angular velocity

The required amount of revolutions is directly proportional with the forward velocity of the tool.The amount of revolutions in radians per second can be expressed as:

ωaug(vt) =4 ·Do · dtren

np · p · π · (Do2 −Di2) · imin· vt

3.8.4 Power

From the torque, subsequently, the required shaft power to drive the auger can be determined byusing following expression:

P aug(vt) = T aug · ωaug(vt)

The results of the calculations can be observed in Figure 17. The contribution of the adhesionand cohesion are shown and the total power consumption as well. All the above in function of theforward velocity of the tool. Two passes are considered.

10

Page 11: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

vt [m/s]

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

Paug [kW

]

0

50

100

150

200

250

Figure 17: Auger shaft power, 2 passes

4 ConclusionUsing the information of the previous sections, a choice is made between the shredder bucketconcept and the auger concept. Accounting for reliability, the amount of moving parts in earthprocessing devices is vital in the comparison. Also other aspects are taken into consideration.

4.1 Shredder bucket• For the shredder bucket design, there are at least two main moving parts, namely the shredder

bodies

• Risk with the shredder bucket is that if one shredder stops functioning, the other one instantlyhits the failed shredder, resulting in damage

• Boulders of sizes larger than the potential cut clay lumps can not be handled and result indamage to the tool

• Significant force required to push bucket into soil, providing stable cutting process. Further-more, significant amount of mass of the tool is vital, required to ensure all the mechanicalenergy can be used for cutting instead of unwanted movements of the tool

4.2 Hybrid Auger• For the auger concept, at first sight there is only one moving part, the auger

• In case of power breakdown the auger can not be retracted easily, this can be solved bysuspend the auger frame hinge able

• Boulders of size equal to the pitch can be handled, larger ones require specific handling whichshould be looked further into

• Auger will pull itself into the soil, owing to downward pointing cutting forces

11

Page 12: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

4.3 Power ConsumptionConsidering, the required power for the two concepts, the auger concepts requires least amount ofmechanical energy at the same forward velocity, as depicted in Figure 18. The shredder bucket,additionally, requires also power to drive the water jets.

vt [m/s]

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

Pto

t [kW

]

0

50

100

150

200

250

300

350Hybrid Auger

Shredder Bucket

Figure 18: Required shaft power in function of forward velocity

References[Ahmad and Amran, 2004] Ahmad, D. and Amran, F. A. (2004). Energy prediction model for

disk plow combined with a rotary blade in wet clay soil. 1(2):102–114.

[Association of Hydraulic Engineers, 2010] Association of Hydraulic Engineers (2010). TrailingSuction Hopper Dredger. VOUB, Gouda.

[Bell, 2002] Bell, F. G. (2002). The geotechnical properties of some till deposits occurring alongthe coastal areas of Eastern England. Engineering Geology, 63(1-2):49–68.

[Berg, 2013] Berg, C. v. d. (2013). IHC Merwede handbook for centrigual pumps and slurrytransportation.

[Boeklagen, 2012] Boeklagen, R. (2012). Inventor Methodisch ontwerpproces. pages 875–896.

[Bosch rexroth, 2012] Bosch rexroth (2012). Hydraulic Formulary.

[Bowles, 1996] Bowles, J. E. (1996). Foundation analysis and design. McGraw-Hill Education -Europe, Peoria, Illinois, 5 edition.

[Budhu, 2015] Budhu, M. (2015). Soil Mechanics Fundamentals, volume 143.

[Carbon Trust, 2015] Carbon Trust (2015). Cable Burial Risk Assessment Methodology. NumberFebruary.

[Caterpilllar, 2000] Caterpilllar (2000). Handbook of Ripping. Caterpillar inc., Peoria, Illinois, 12edition.

[Datas, 2004] Datas, T. (2004). Screw Conveyor System. pages 3–4.

[Degroot and Sc, 2010] Degroot, D. J. and Sc, D. (2010). Recommended site investigation practicefor offshore energy systems Offshore Geotechnical Engineering Emerging Offshore Infrastructurewind farms. pages 1–26.

[Det Norske Veritas, 2014] Det Norske Veritas (2014). Subsea Power Cables in Shallow WaterRenewable Energy Applications. (February):145.

[Durning and Rennie, 1979] Durning, P. J. and Rennie, I. A. (1979). Determining pile capacityand pile driveability in hard, overconsolidated North-Sea clay. Ground engineering.

12

Page 13: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

[Elsayed, 2013] Elsayed, E. (2013). Environmental Balance of Mining from Seafloor. PhD thesis,Technische Universität Bergakademie Freiberg.

[Environment and Climate Change Canada, 2010] Environment and Climate Change Canada(2010). National Marine Weather Guide. pages 45–62.

[Friedrich, 2010] Friedrich, N. K. (2010). Regeneration circuits. Hydraulics & Pneumatics.

[Gourvenec and White, 2010] Gourvenec, S. and White, D. (2010). Frontiers in Offshore Geotech-nics II. Taylor & Amp; Francis Ltd, 2 edition.

[Hall and Elenany, 2010] Hall, N. and Elenany, M. (2010). Experimental study of sand and slurryjets in water. Journal of Hydraulic Engineering, (October):727–738.

[Harwood, 2014] Harwood, P. (2014). Dynamic Amplification Factor for Moment Resisting Framesin Progressive Collapse. PhD thesis, Massachusetts Institute of Technology.

[Helwany, 2007] Helwany, S. (2007). Shear Strength of Soil. Applied Soil Mechanics: with ABAQUSApplications, pages 162–208.

[Hicks, 2001] Hicks, J. (2001). Welded Design. In Rural strucutres in the tropics: design anddevelopment, chapter 7, Structu, pages 115–147.

[IHC holland, 1978] IHC holland (1978). The new generation of dragheads (confidential).

[IHC holland, 2005] IHC holland (2005). Wild dragon.

[Kom, 2005] Kom, T. (2005). Determination of the soil friction coefficient. pages 212–216.

[Liefferink et al., 2014] Liefferink, D., Grima, M. A., Miedema, S., Plat, R., and van Rhee, C.(2014). Failure Mechanism of Cutting Submerged Frozen Clay in an Arctic Trenching Process.Offshore Technology Conference, pages OTC–25337–MS.

[Littleton, 1976] Littleton, I. (1976). An experimental study of the adhesion between clay andsteel. Journal of Terramechanics, 13(3):141–152.

[Malherbe and Pooter, 2008] Malherbe, B. and Pooter, P. D. (2008). New possibilities for ripperdredging of rock. Terra Et Aqua, (110):9–12.

[Mazurek et al., 2001] Mazurek, K. A., N. Rajaratnam, Fellow, A., and D. C. Sego, Member, A.(2001). Scour of cohesive soil by submerged circular turbulent impinging jets. Number July,pages 598–606.

[McKyes, 1989] McKyes, E. (1989). Agricultural Engineering Soil Mechanics. Elsevier Science, 1edition.

[Melorose et al., 2015a] Melorose, J., Perroy, R., and Careas, S. (2015a). Draghead Holland MT.Statewide Agricultural Land Use Baseline 2015, 1:1–2.

[Melorose et al., 2015b] Melorose, J., Perroy, R., and Careas, S. (2015b). Soil Mechanics Funda-mentals, volume 1.

[Menon, 2014] Menon, M. (2014). Utilising a MultiMode Subsea Deployment System for SubseaTrenching and Component Delivery Operations Current state of play. pages 11–13.

[Miedema, 1986] Miedema, S. (1986). The Application of a Cutting Theory on a Dredging Wheel.Wodcon Xi, 1983.

[Miedema, 2014] Miedema, S. (2014). The Delft Sand , Clay & Rock Cutting Model. IOS Press,Amsterdam, 1 edition.

[Miedema, 2015] Miedema, S. (2015). OE4607 Introduction Dredging Engineering. MSc Offshore& Dredging Engineering Delft University of Technology. Delft.

[Miedema, 2016] Miedema, S. (2016). Dredging Processes, Delft University of Technology.

13

Page 14: On The Pre-Lay Trench Tool Design - Semantic Scholar · Applying the physics behind the cutting process during a mechanical trenching operation, is in-evitable to determine the reaction

[Miedema et al., 2007] Miedema, S. A., Lagers, G. H. G., and Kerkvliet, J. (2007). An overviewof drag embedded anchor holding capacity for dredging and offshore applications. WODCON,Orlando, pages 245–274.

[N. Vaartjes Van den Berg, 2012] N. Vaartjes Van den Berg, J. F. (2012). Offshore PipelineTrenching In Arctic Regions : A Unique Concept, The Arctic Subsea Bucket Ladder Trencher.(January).

[Navy, 1986] Navy, U. d. o. t. (1986). Foundations & Earth Structures.

[Neelissen et al., 2010] Neelissen, R. F. J., Tanis, A., and Gool, V. V. A. N. (2010). Dredging rockwith a hopper dredger: the road to the ripper draghead. (118):14–22.

[Nobel, 2013] Nobel, A. J. (2013). On the excavation process of a moving jet in cohesive soil(Doctoral Dissertation). PhD thesis, Delft University of Technology.

[Rambøll, 2009] Rambøll (2009). Offshore pipeline through the Baltic Sea, Environmental ImpactAssessment. Number September. Rambøll Danmark, København V.

[Rambøll, 2011] Rambøll (2011). Geotechnical properties for Glacial deposits. Number May.

[Redclift and Woodgate, 2005] Redclift, M. R. and Woodgate, G. (2005). New Developments inEnvironmental Sociology. pages 19–25.

[Rorres, 2000] Rorres, C. (2000). the Turn of the Screw : Optimal Design of an archimedes screw.Journal of Hydraulic Engineering, 126(January):72–80.

[Sharples, 2011] Sharples, M. (2011). Offshore Electrical Cable Burial for Wind Farms : Stateof the Art , Standards and Guidance & Acceptable Prepared for : November 2011 OffshoreElectrical Cable Burial for Offshore Wind Farms on the OCS. Technology, (November).

[Subramanian, 2010] Subramanian, N. (2010). Properties of Soils. Design of Steel Structures,pages 1396–1400.

[van Rhee, 2014] van Rhee, C. (2014). Jets and Trenching, lecture notes, MSc Offshore & DredgingEngineering Delft University of Technology.

[van Rhee, 2015] van Rhee, C. (2015). Lecture Notes Dredging Processes II, MSc Offshore &Dredging Engineering Delft University of Technology.

[Vandycke, 2002] Vandycke, S. (2002). Dredging stiff to very stiff clay in the Wielingen using theDRACULA system on a hopper dredger. Terra et Aqua, (89):3–8.

[VAV Aandrijvingen, ] VAV Aandrijvingen. Calculatie transportschroeven.

[Verruijt, 2001] Verruijt, A. (2001). Grondmechanica. Delft, 1 edition.

[Verschelde et al., 2010] Verschelde, A., Rhee, C. v., and Broeck, M. v. d. (2010). Erosion be-haviour of a draghead. Terra at Aqua.

[Vlasblom, 2003] Vlasblom, W. (2003). Plain Suction Dredgers. chapter 4, Plain S, pages 1–35.Delft University of Technology.

[Zahalka, 2010] Zahalka, P. (2010). Bollard Pull. Association of Hanseatic Marine Underwriters.

14