on the benefits of planning and grouping software maintenance requests

30
On the Bene ts of Planning and Grouping Software Maintenance Requests CSMR – Oldenburg, Germany, March 2011 Gladston Aparecido Junio (PUC Minas, Brazil) Marcelo Malta (PUC Minas, Brazil) Humberto Mossri (PUC Minas, Brazil) Humberto Marques-Neto (PUC Minas, Brazil) Marco Tulio Valente (UFMG, Brazil)

Upload: arlene

Post on 13-Jan-2016

45 views

Category:

Documents


0 download

DESCRIPTION

On the Benefits of Planning and Grouping Software Maintenance Requests. Gladston Aparecido Junio (PUC Minas , Brazil ) Marcelo Malta (PUC Minas , Brazil ) Humberto Mossri (PUC Minas , Brazil ) Humberto Marques-Neto (PUC Minas , Brazil ) Marco Tulio Valente (UFMG , Brazil ). - PowerPoint PPT Presentation

TRANSCRIPT

On the Benefits of Planning and Grouping Software Maintenance Requests

CSMR – Oldenburg, Germany, March 2011

Gladston Aparecido Junio (PUC Minas, Brazil)

Marcelo Malta (PUC Minas, Brazil) Humberto Mossri (PUC Minas, Brazil)

Humberto Marques-Neto (PUC Minas, Brazil)Marco Tulio Valente (UFMG, Brazil)

Motivation

Policies for scheduling maintenance requests: Continuous: requests implemented as quick as possible Periodic: requests packaged in larger projects

In theory, the benefits of periodic policies are widely known Several statistical models have been proposed Example: Banker et. al (+30% of cost reduction)

Do such gains happen in real organizations? Theoretical models have not been validated by field

studies

2

In this Talk

Define a simple process – called PASM – for handling maintenance requests as projects PASM: Process for Grouping Maintenance Requests

Propose a methodology to evaluate maintenance policies

Evaluate the gains achieved by the PASM process in a real software development organization

3

PASM

Three phases: Registration Grouping Processing

4

1st Phase: Registration

5

Pre-defined time frame for registration

Typical requests are buffered

Users can specify that a request is urgent If ratified by the process manager:

Request goes directly to implementation No waiting-costs

2nd Phase: Grouping

6

No rigid guidelines for grouping Two forces: size and cohesion Size:

Compatible with the production capacity Should not imply in waiting costs that users will

not tolerate Cohesion:

Requests of a project should be functionally coherent

3rd Phase: Processing

7

PASM does not fix a development method

Characterization Methodoly

Characterization Methodology

How to evaluate the gains achieved by PASM in a real setting?

Adapted a methodology proposed to understand the behavior of web users

Central idea: Software Maintenance Request Model Graph Nodes: states of each request Edges: transition between such states

9

Software Maintenance Request Model Graph

10

Metrics

QueueTime = WaitTime + ServiceTime

Service Time =

PlanningTime + AnalysisTime +

ImplementationTime + ValidationTime +

DeploymentTime

11

Methodology

1. Classify the requests in the following groups: Before PASM, Urgent Before PASM, Project After PASM, Urgent After PASM, Project

2. For each request in each of the previous groups Generate the SMRMG Generate a vector with the previous metrics

3. For the vectors in each group Apply a clustering algorithm (k-means)

12

Goal with Clustering

1. Discover the characteristics of the typical projects Before PASM After PASM

2. Evaluate the positive and negative effects of the PASM adoption on such projects

3. Discover the characteristics of typical urgent requests Before PASM After PASM

4. Evaluate the positive and negative effects of the PASM adoption on such requests

13

Evaluation

We have evaluated the PASM process at DATAPUC

DATAPUC: IT Department of PUC Minas 34 developers 40 systems, 4 MLOC

Until October 2008: (most) maintenance requests handled on demand, in a

continuous way.

Starting on November 2008: DATAPUC has moved to the PASM process

14

PASM @ DATAPUC

Registering Phase: first 10 days of each month

Grouping: next 20 days Requests are evaluated and grouped in projects

Cycle is repeated in the next month

15

Data Source

Same sequence of months: Before PASM: February-October 2008 After PASM: February-October 2009

16

Requests Before PASM (2008)

After PASM (2009)

Urgents 1051 953

Projects 22 62

Results: Maintenance Projects

Maintenance Projects: Clusters

18

Metrics2008 2009

Cluster 1(19 proj.)

Cluster 2(3 proj.)

Cluster 1(52 proj.)

Cluster 2(10 proj.)

QueueTime 185,00 771,87 245,04 694,91

WaitTime 12,16 17,50 26,85 11,95

ServiceTime 172,84 754,37 218,19 682,97

AnalysisTime 31,51 7,48 48,71 141,61

PlanningTime 6,34 5,02 3,66 64,61

ImplementationTime 74,63 348,27 50,39 122,56

StandByTime 0,00 0,00 0,20 0,00

ValidationTime 39,34 377,46 94,19 249,70

DeploymentTime 21,01 16,14 21,04 104,49

QueueTime: + 32%

Maintenance Projects: SMRMG + Probabilities

19

Maintenance Projects: Summary

More projects: Before PASM: 22 projects After PASM: 62 projects

Dominant development task: Before PASM: implementation (43%) After PASM: validation (43%)

20

Results: Urgent Requests

Urgent Requests: SMRMG

22

Typical Urgent Requests

23

Metrics Cluster 2 - 2008(651 req)

Cluster 5 - 2009(383 req)

QueueTime 16,79 12,82

WaitTime 2,80 3,22

ServiceTime 13,98 9,60

AnalysisTime 4,46 2,45

ImplementationTime 7,02 3,94

StandByTime 2,50 3,21

ValidationTime 0,00 0,00

DeploymentTime 0,00 0,00

Complex, Error-Prone, Urgent Request

24

MetricsCluster 5 -

2008(222 req.)

Cluster 2 - 2009

(212 req.)

QueueTime 25,82 26,51

WaitTime 3,56 3,05

ServiceTime 22,26 23,46

AnalysisTime 8,33 3,23

ImplementationTime 2,28 4,27

StandByTime 1,02 2,07

ValidationTime 10,63 13,89

DeploymentTime 0,00 0,00

Urgent Requests: Summary

QueueTime, after PASM: Typical requests: - 4 hours Complex requests: + 1 hour (more time to validation)

25

Conclusions

Contributions

1. PASM: Process for grouping maintenance requests Lightweighted process Three phases: registration, grouping, processing

2. Methodology to evaluate maintenance policies, based on: Software Maintenance Request Model Graph Clustering techniques Classical queue model metrics

3. Field study to evaluate the benefits achieved by PASM

27

Benefits

More requests handled as projects Side-effects:

More time dedicated to analysis and validation Less time dedicated to implementation

Urgent maintenance requests: Handled in less time

28

Further Work

Promote and evaluate the PASM’s adoption by other organizations

Assess the internal and external quality of the software released under PASM guidelines

29

Thank you!