on-load tap changer type v - reinhausen081/05 en 5 1 general 1 general 1.1 safety instructions all...
TRANSCRIPT
www.reinhausen.com On-Load Tap Changer Type VOperating Instructions BA 081/05
2 081/05 EN
3081/05 EN
Contents
Contents
1 General
1.1 Safety instructions .................................................................................................................... 51.2 Specified application ................................................................................................................ 5
2 Design ............................................................................................................................................... 6
3 Shipment ........................................................................................................................................... 6
4 Installation of the tap changer for cover mounting4.1 Mounting flange ........................................................................................................................ 84.2 Attachment of the tap changer head to the transformer cover .................................................... 8
5 Installation of the tap changer into a bell-type tank5.1 Installation of the on-load tap changer into the supporting structure ........................................... 95.2 Preparations ............................................................................................................................. 95.3 Removal of the tap changer cover .............................................................................................. 105.4 Removal of the gear mechanism ............................................................................................... 115.5 Separating the tap changer head from the tap changer.............................................................. 125.6 Setting up the bell-type transformer cover ................................................................................. 125.7 Reinstallation of the gear mechanism and attachment of the tap changer cover ........................ 13
6 Connection of tap winding and tap changer take-off leads ......................................................... 13
7 Transformer ratio test ....................................................................................................................... 15
8 Drying procedure and filling with oil8.1 Drying procedure ....................................................................................................................... 15
8.1.1 Vacuum-drying ................................................................................................................ 158.1.1.1 Drying in the vacuum autoclave .......................................................................... 158.1.1.2 Drying in the transformer tank ............................................................................ 15
8.1.2 Vapor-phase drying process ............................................................................................ 168.1.2.1 Vapor-phase drying in the vacuum autoclave ...................................................... 168.1.2.2 Vapor-phase drying in the transformer tank ........................................................ 16
8.1.3 Operating the tap changer ............................................................................................... 16
NOTE
Data contained herein may differ in details from the tap changing equipment delivered.We reserve the right to make alterations without notice.
4 081/05 EN
8.2 Filling with oil ............................................................................................................................ 169 Pipe connections
9.1 Pipe connection R for protective relay RS 2001 ......................................................................... 179.2 Pipe connection S for suction pipe ............................................................................................ 179.3 Pipe connection Q .................................................................................................................... 179.4 Connection flange E2 ................................................................................................................ 17
10 Mounting the motor drive unit, the bevel gear and the drive shaft10.1 Mounting the motor drive unit .................................................................................................... 1810.2 Mounting the bevel gear ............................................................................................................ 1810.3 Mounting the drive shaft (square tube) ....................................................................................... 18
11 Putting the tap changer into service at the transformer manufacturer11.1 Operational test ........................................................................................................................ 2011.2 Final oil filling ............................................................................................................................ 2111.3 Ground connections .................................................................................................................. 2111.4 Electrical transformer tests ....................................................................................................... 21
12 Transport to the operating site ........................................................................................................ 21
13 Putting into service at the operating site ....................................................................................... 22
14 Supervision during service, failures ............................................................................................... 22
15 Inspections ........................................................................................................................................ 23
16 Appendix ........................................................................................................................................... 24
Contents
5081/05 EN
1General
1 General1.1 Safety instructions
All personnel involved in installation, commissioning,operation, maintenance or repair of the equipment must:
- be suitably qualified and- strictly observe these Operating Instructions.
Improper operation or misuse can lead to- a reduction in the efficiency of the equipment- damage to the equipment and property of the
user- serious or fatal injury.
Safety instructions in this manual are presented in threedifferent forms to emphasize important information.
1.2 Specified application
WARNING
This information indicates particular danger to life andhealth. Disregarding such a warning can lead toserious or fatal injury.
CAUTION
This information indicates particular danger to theequipment or other property of the user. Serious orfatal injury cannot be excluded.
NOTE
These notes give important information on a certainsubject.
CAUTION
All relevant fire protection regulations must be strictlyobserved.
CAUTION
Only use the on-load tap changer with the transfor-mer specified in the order. Installation, electricalconnection and commissioning of the on-load tapchanger may only be carried out by qualified, skilledpersonnel and only in accordance with these operat-inginstructions.
It is the responsibility of the user to make sure thatthe tap changer is used for the specified applicationonly.For safety reasons, any unauthorized work, i.e. in-stallation, modification, alteration of the tap changerequipment, electrical connection or commissioning ofthe equipment is forbidden without first consulting MR!
The trouble-free operation of the drive, the on-loadtap changer and the transformer may be put at risk.
6 081/05 EN
2 Design3 Shipment
2 Design 3 Shipment
Tap changer and motor drive are shipped in theadjustment position.
The tap changer equipment is shipped as follows(insulating parts are protected against moisture):
Tap changer type V:
fig. 1 (type V 200, max. weight approx. 140 kg),fig. 2 (type V 350, max. weight approx. 150 kg),fig. 3 (type V 500, max. weight approx. 200 kg),
The tap changer is constructed as a selector switch oftubular design. It combines the functions of a diverterswitch and of a tap selector. The switching oil is sepa-rated from the transformer oil by means of the cylindricalpressure-proof oil compartment. The tap changer isattached to the transformer cover by means of the tapchanger head.If required, the tap changer is equipped with a change-over selector. The design and the designation of themost important parts of the tap changer can be under-stood from the installation drawings (see section 16,drawings 893 945, 893 821 and 894 566).Tap changer models V 200 and V 350 without change-over selector are available up to a maximum of 14 andwith change-over selector up to a maximum of 27operating positions.The tap changer model V 500 is available for up to 12 or23 operating positions, respectively.
These Operating Instructions apply to all tap changervariants specified below (with or without change-overselector):Three-phase tap changers:V III 200 Y, V III 350 Y, V III 500 YV III 200 D, V III 350 D, V III 500 DTap changers in special design:V III 250 Y, V III 250 D, V III 400 Y, V III 400 DSingle-phase tap changers:V I 200, V I 350, V I 700All single-phase tap changers are also available as a tapchanger group 3 x V I ... with a common motor drive.
31 KHW 894-4 KHW 896-42 KHW 895-4
V
0
+-
78
UA
6
78 6
AV
78 6
AW
V
0
+-
7
V68
U8 7 6
7
W68
-
10
10
10
11
11
8
9 8
11 9 8
1V
+
0
9
7081/05 EN
6 KHW 848-4
5 KHW 766-4
4 KHW 915-4
Motor drive unit MA 9 (approx. 60 kg) orMotor drive unit MA 7 (approx. 90 kg),Motor drive unit ED 100/200 S (approx. 80 kg), orMotor drive unit ED 100/200 L (approx. 130 kg), fig 4.
Drive shafts with coupling parts and bevel gear(max. weight approx. 20 kg), fig. 5.
Protective relay RS 2001 (3,5 kg), fig. 6.
The shipment is to be fully checked against consign-ment documents. The parts must be stored in a dryplace until assembly.
All tap changer parts must be left wrapped in theirairtight protective cover and are to be removed onlyshortly before installation.
MR
MR
3Shipment
NOTE
In general, drive shaft parts, bevel gear and protectiverelay are packed with the tap changer.
8 081/05 EN
A mounting flange is necessary in order to mount thetap changer head to the transformer cover. Thismounting flange is to be constructed in accordancewith the sealing surface of the tap changer head (seefig. 8 and section 16, drawing 893 945, 893 821 and894 566).
To position the studs (M12, max. length = 45 mm) werecommend the use of a drilling template (see fig. 9and section 16, dwg. 893 787). If requested, the drillingtemplate will be supplied with the first installation of atap changer type V free of charge.
4.2 Attachment of the tap changer headto the transformer cover
The tap changer is lowered through the cover aperture(= mounting flange) of the transformer and bolted by thetap changer head to the mounting flange.
Proceed as follows:
1. Place the tap changer on a level surface.
2. Clean the sealing surfaces of the mounting flangeand the tap changer head.
3. Put an oil-resistant gasket on the mounting flange.
4. Lift the tap changer by hooking up the tap changerhead and carefully lower it into the opening of themounting flange.
5. Make sure not to damage the terminals.
6. Check installed position of the tap changer.
7. Fix the tap changer head to the mounting flange.
4 Installation of the tap changer forcover mounting (fig. 7)
4.1 Mounting flange
9 int014
8 int013
7 int012
Flat surface
4Installation of the tap changer for cover mounting
9081/05 EN
Drying procedure and transformer ratio test are to beperformed in accordance with sections 7 and 8.
5.2 Preparations
Before setting up the bell-type tank, the tap changerhead must be separated from the tap changer.
For the removal of the tap changer head the gearmechanism has to be removed. Make sure that the tapchanger is in its adjustment position. This position isindicated in the connection diagram which is suppliedwith the tap changer.
5 Installation of the tap changer into abell-type tank
To install the on-load tap changer into a transformer witha bell-type tank the tap changer has to be mounted ontoa supporting structure.Therefore the on-load tap changer is equipped with asupporting flange at the oil compartment (= specialdesign, see dwg. 893 864 in section 16).
First of all, lift the tap changer into the supportingstructure and connect it to the tap winding. For thispurpose the tap changer has to be attached to thesupporting structure in such a way that it cannot bedisplaced.
The supporting flange is provided with bores, so that itcan, without further measures, be provisionally securedto the supporting structure. It is advantageous to putspacer blocks temporarily between supporting structureand supporting flange and to remove them before settingup the bell-type cover.
After mounting the bell-type cover raise the on-load tapchanger by means of the lifting traverse (see drawing893 805 in section 16) and attach both tap changer andtap changer head to the bell-type cover.
To attach the tap changer head to the bell-type cover werecommend the use of a mounting flange as described insection 4.1.
5.1 Installation of the on-load tap changerinto the supporting structure
Lift the tap changer into the supporting structure.Make sure that the tap changer is in its proper mountingposition and fasten it there safely.
Due to the provisionally installed spacer blocks betweensupporting structure and supporting flange, the tapchanger is in its envisaged final position after the bell-type cover is set up. By this measure the leads to beconnected to the tap changer can be correctly dimen-sioned in length.
To connect the tap winding and the tap changer take-offterminal follow the instructions according to section 6.
NOTE
In the supporting structure the tap changer must besuspended in an exactly vertical position.The tap changer must be mounted so that it need notbe lifted by more than 5 to 20 mm to reach its finalposition after the bell-type cover has been set up.
CAUTION
The connected leads must not exert any force onthe tap changer. Moreover, there must be sufficientclearance, so that it is possible to raise the tapchanger to its final installation position after the bell-type tank has been mounted.
5Installation of the tap changer into a bell-type tank
10 081/05 EN
5.3 Removal of the tap changer cover(fig. 10)
• Unscrew the 20 cover screws M10 x 35 / wrenchsize 17, with 20 lock washers.
• Take off the tap changer cover.Take care of the cover gasket (fig. 11).
5Installation of the tap changer into a bell-type tank
11 int016
10 int015
11081/05 EN
The gear plate is attached to the tap changer head by5 screws M8 (fig. 12). Note the positions of the gearmarkings.
Disconnect the suction pipe and the spring energyaccumulator:
• Unscrew the suction pipe elbow R 3/4" (wrench size27 and 39) and take care of the gasket.
• Push the corresponding plug into the tap changerhead.
• Withdraw the fixing bolts for spring energy accumu-lator by means of a screw M5 x 20.
Removal of the gear mechanism:
• Loosen 5 screws M8 x 20, wrench size 13 (fig. 13).Take care of lock washers.
• Remove the gear mechanism in upward direction(fig. 14).
• Take note of the position of the centering support forlater reinstallation (fig. 15).
Keep all removed parts for reinstallation.
5.4 Removal of the gear mechanism
15 int020
14 int019
13 int018
5Installation of the tap changer into a bell-type tank
12 int017
12 081/05 EN
Loosen the fixing screws on the tap changer head(9 six-spline socket screws M8 x 25/w.s.T40, lockwashers, fig. 16). Keep the loose parts for reinstallation.
Lift off the tap changer head from the supporting flange.Take care of the round rubber gasket of the supportingflange (fig. 17).
5.6 Setting up the bell-type transformercover
1. Before setting up the bell-type transformer coverclean the sealing surface of the supporting flange.Withdraw the spacer blocks (see section 5.1).
2. Lift the bell-type cover over the transformer active partand set up the bell-type cover.
3. Before mounting the tap changer head, clean thesealing surfaces (bottom surface of the tap changerhead, mounting flange). Put an oil-resistant gasket onthe mounting flange.
Depending on the final height adjustment leave aclearance of 5 to 15 mm between tap changer headand supporting flange. Check the installation positionof the tap changer head with the help of the twoadjusting bolts (fig. 17) which ensure assembly in thecorrect position in the supporting flange of the oilcompartment. Fasten the tap changer head to themounting flange.
Place the lifting traverse (must be used) on the tapchanger head and screw the 4 bolts M8/w.s. 13 intothe supporting flange (fig. 18).
5.5 Separating the tap changer head fromthe tap changer
CAUTION
Under all circumstances avoid dropping any parts intothe tap changer oil compartment. Otherwise there isthe risk that the tap changer will block and both tapchanger and transformer will be damaged.
Therefore, make sure that the number of small parts iscomplete when disassembling and reinstalling.Count them to be sure.
18 int023
17 int022
16 int021
5Installation of the tap changer into a bell-type tank
CAUTION
It is absolutely necessary to use the lifting traversefor the installation.Otherwise damage may occur.
13081/05 EN
Installation of the tap changer into a bell-type tank 5Connection of tap winding and tap changer take-off leads 6
4. Lift the tap changer slightly by means of the liftingtraverse (see section 16, drawings 893 864 and893 805) so that the oil compartment screws(9 six-spline socket screws M8, wrench size T40,to be secured by lock washers) can be screwed in.Tighten the screws uniformly with a maximumtorque of 14 Nm (fig. 19).
5.7 Reinstallation of the gear mechanismand attachment of the tap changercover
Reinstallation of the gear mechanism is carried out inthe reverse order of its removal.
Set the gear mechanism in the adjustment position(see section 5.4, fig. 12), as installation and couplingcan be done only in this position.
Attachment of the tap changer cover:
Check the gasket before closing the cover. Use 20screws M10 x 35/wrench size 17 with lock washers andfasten them uniformly (max. torque 35 Nm).
The connection of the tap winding and the tap changertake-off leads has to be carried out according to theconnection diagram supplied with the particular tapchanger equipment.
If leads are crossing the surface of the oil compartmentleave a clearance of at least 50 mm between the leadsand the surface of the oil compartment.
The tap changer terminals are designated according tothe connection diagram. They are provided with bores forthe connection of cable shoes to one side of theterminals as follows:
at the change-over selector (fig. 20):11 mm dia. for M10 screws.
CAUTION
Check the adjustment position.
19 int024
6 Connection of tap winding and tapchanger take-off leads
20 KHW 897a-4
- +
v
o
CAUTION
All connections to the tap changer must be carried outcarefully and secured. The connecting leads must beassembled in such a way as to allow all leads to beconnected to the tap changer without tension.
14 081/05 EN
6Connection of tap winding and tap changer take-off leads
23 KHW 897d-4
8 7 6
o
5
at the selector switch V 200 (fig. 21):9 mm dia. for M8 screws.
at selector switches V 350 (fig. 22) or V 500 (fig. 23)11 mm dia. for M10 screws.
at selector switches V 200, V 350 and V 500,for tap changer current take-off lead or neutral point,respectively:11 mm dia. for M10 screws
Neutral connection for tap changers type V III 200 Y,V III 350 Y and V III 500 Y (see fig. 24).
This lead forms the neutral point of the tap changer andmust not be removed. The neutral point terminal is to beconnected at this location.
22
21KHW 897b-4
KHW 897c-4
8 7
o6
8 7 6
5
o6789
6789
8 7 6
8 7 6
8 7 6 5
24 KHW 897e-4
15081/05 EN
We recommend to carry out ratio-testing before drying ofthe transformer.To operate the drive shaft in the tap changer head ashort tube of 25 mm nominal width with a screwed-incoupling bolt of 12 mm dia. together with a hand wheelor a hand crank may be used.In case of motor drive MA 9 one drive shaft revolution isrequired for one tap change operation, in case of motordrive MA 7 33 drive shaft revolutions and in case of motordrive ED 16.5 drive shaft revolutions are required. Theselector switch action can be heard distinctly.When operating the change-over selector (adjustmentposition ±1 step), which can be noticed as it takes moreeffort, the commenced tap change operation mustalways be completed without changing the rotationsense.Keep the number of tap change operations without oil toa minimum.The end positions which can be inferred from theconnection diagram supplied with the tap changerequipment (position designation) must never be overrun.It is therefore necessary to check the attained operatingposition through the inspection window in the tapchanger head (fig. 25).After the transformer ratio test the tap changer has to beset back to the adjustment position (see connectiondiagram delivered with the equipment).
8 Drying procedure and filling with oil
8.1 Drying procedure
As a precondition of MR’s guarantee of the dielectricproperties of the tap changer, a minimum drying treat-ment must be carried out according to the followinginstructions (either 8.1.1 or 8.1.2):
8.1.1 Vacuum-drying
8.1.1.1 Drying in the vacuum autoclave
Heating up:the tap changer in air of atmospheric pressure with atemperature rise of approx. 20 °C/hour to a final tempera-ture of at most 110 °C.
Preparatory drying:in circulating air at 110 °C max. applied to the tapchanger for a duration of 10 hours.
Transformer ratio test 7Drying procedure and filling with oil 8
7 Transformer ratio test
8.1.1.2 Drying in the transformer tank
The tap changer cover is vacuum-proof.
To ensure sufficient drying of the interior of the oilcompartment and the incorporated tap changer insert, ashort by-pass tube of 25 mm nominal width must beconnected between the transformer tank and a connect-ing flange at the tap changer head that leads directly intothe oil compartment.
Connect this by-pass tube either between flanges E2and Q or flanges E2 and R at the tap changer head (forposition of connecting flanges see fig. 26 and section 9).
Procedure, temperature, pressure and duration of thedrying process are described in section 8.1.1.1.
25
9 b
KHW 764-4
26 int025
Vacuum-drying:with a temperature of 110 °C max. applied to the tapchanger and the same drying time as for the transformer.
NOTE
When drying the transformer in the autoclave removethe tap changer cover and store it outside the vacuumautoclave.
NOTE
If the transformer is to be dried in its own tank, the in-terior of the tap changer must be connected tovacuum by a connecting pipe, as the tap changercover remains closed during the entire drying process.
16 081/05 EN
8Drying procedure and filling with oil
Before starting the drying procedure, the kerosene drainplug in the oil compartment bottom must be opened todrain the condensate from the oil compartment.The kerosene drain plug has a hexagon socket (w.s. 24)and can be unscrewed from outside (fig. 27) or inside.The kerosene drain plug is loss-proof and must beclosed again after the drying procedure (max. torque39 Nm).
8.1.2.1 Vapor-phase drying in the vacuumautoclave
Heating up:by admitting the kerosene vapor at a temperature ofabout 90 °C. Keep this temperature constant for about3 to 4 hours.
Drying:by increasing the kerosene vapor temperature by about10 °C per hour to the desired final temperature, but atmost to 125 °C applied to the tap changer.The duration of the drying procedure is normally thesame as that of the transformer.Make sure that the kerosene drain plug has been closedafter the drying process.
8.1.2 Vapor-phase drying process
CAUTION
The kerosene drain plug must be closed safely afterthe drying process to ensure that no oil from the tapchanger oil compartment can flow into the transformertank.
CAUTION
The tap changer oil compartment and the associatedoil conservator must be filled only with new mineralinsulating oil for transformers according to IEC 296.The use of other oil puts at risk the trouble-freeoperation of tap changer and transformer.
8.1.2.2 Vapor-phase drying in the transformer tank
For vapor-phase drying in the transformer tank the tapchanger insert has to be withdrawn to enable opening ofthe kerosene drain plug from inside. Please contact usfor further instructions on removal and reinstallation.
8.1.3 Operating the tap changer
The tap changer must not be operated before the oilcompartment has been filled with oil.
8.2 Filling with oil
Close the tap changer head by lowering the cover.Tighten all 20 cover bolts M10 equally (wrench size 17,max. torque 34 Nm).
Tap changer and transformer are simultaneously filledwith new oil under vacuum. When filling the tap changerwith oil, pipe connection S or R on the tap changer headis to be used. To apply vacuum to the tap changer a by-pass tube between connections E2 and Q is to beinstalled in order to evacuate both transformer and oilcompartment simultaneously.
27 int026
CAUTION
Do not operate the tap changer after drying withoutoil wetting, otherwise bearings and gaskets will bedamaged.
NOTE
When drying the transformer in the autoclave removethe tap changer cover and store it outside the vacuumautoclave.
17081/05 EN
The tap changer head is provided with 3 pipe connec-tions for different purposes. After loosening the thrustcollar (4 bolts M10/w.s.17) these pipe connections canbe freely swivelled (see fig. 28 and section 16, drawing893 779).
9.1 Pipe connection R for protective relayRS 2001
The mounting of the protective relay RS 2001 (seesection 16, dimension drawing 892 608) is pursuant toour Operating Instructions No. 59.
9.2 Pipe connection S for suction pipe
This is the connection for the feeding pipe of a stationaryoil filter unit. If no filter is used, a pipe must beconnected which ends with a drain cock at the side ofthe transformer tank at operating height.
9.3 Pipe connection Q(special design, required only with oilfilter unit)
This pipe connection serves as the connection of the oilreturn pipe of a stationary oil filter unit. If no oil filter isconnected, a dummy plug is mounted instead of the pipeconnection.
9.4 Connection flange E2This connection is closed by a dummy plug. It leads intothe oil chamber of the transformer tank directly beneaththe tap changer head and can, in case of need, beconnected to an accumulating tube for the Buchholzrelay.
9 Pipe connections
9Pipe connections
28 int027
NOTE
The stamped-on serial number must be the same asthat of the tap changer.
The relay must be mounted as near to the tapchanger head as possible and in horizontal position.
The directional arrow on the relay must point towardsthe oil conservator in the mounted state.
The pipe extending to the oil conservator must have aninclination of at least 2 %.
18 081/05 EN
The drive shaft must be mounted according to ourOperating Instructions No. 42. The drive shaft is themechanical connection between the motor drive and thetap changer head. The diverting from the vertical to thehorizontal direction takes place through the bevel gear.
Accordingly, when mounting, the vertical drive shaft is tobe mounted between motor drive unit and bevel gear,whereas the horizontal drive shaft is to be mountedbetween bevel gear and tap changer head.
The drive shaft itself consists of a square tube and is tobe connected at both ends to the respective implementby two coupling brackets and one coupling bolt.
Square tubes, coupling brackets, coupling bolts, screws,nuts and lock tabs are corrosion-resistant. We recom-mend, however, to apply the same outside coating tothese parts as to the transformer tank.
The square tubes and the guard plate, which serves asfoot step protection for the horizontal drive shaft at thetransformer cover, are supplied in oversize (variousstandard lengths). These parts must be cut to therequired size before mounting.
10Mounting the motor drive unit, the bevel gear and the drive shaft
NOTE
When mounting the drive shaft make sure that theshaft ends to be connected are aligned exactly.
NOTE
The stamped-on serial number of bevel gear and tapchanger must be identical.
The horizontal drive shaft must be in proper alignmentwith the shaft end of the tap changer head.After loosening the thrust collar (6 screws M8/w.s.13) the upper gear unit can be freely swivelled (fig.29). When having adjusted the upper gear unit, tightenthe thrust collar (max. torque 15 Nm).The bolts are to be secured.
In case of bevel gears and diverting gears in specialdesign and intermediate bearings of the vertical orhorizontal drive shaft, the above instructions applyanalogously.
10.2 Mounting the bevel gear
The bevel gear is to be attached to a support on thetransformer cover with 2 bolts (through-bores of18 mm dia., see section 16, dwg. 892 916).
10.3 Mounting the drive shaft (square tube)
10 Mounting the motor drive unit,the bevel gear and the drive shaft
NOTE
The serial number of motor drive unit and tap changermust be identical (rating plate).
Motor drive unit and tap changer must be in the sameoperating position. The adjustment position is indi-cated in the tap changer connection diagram suppliedwith the equipment.
The motor drive unit must be mounted at the pro-videdplace on the transformer tank in a vertical position andprotected against excessive transformer vibrations.
You may find comprehensive mounting instructions inour Operating Instructions No. 40 for motor drive unit MA7 or No. 80 for motor drive unit MA 9 and No. 138 formotor drive unit ED.
10.1 Mounting the motor drive unit (see sec-tion 16, dwgs. 895 660, 893 381, 898 420 resp.)
29 int028
19081/05 EN
32 int031
31 int030
30 int029
10Mounting the motor drive unit, the bevel gear and the drive shaft
Before coupling of the upper gear unit of the tapchanger head, adjust the correct adjustment position(inclusive idling) as follows:
a) in case of motor drive unit MA 9(1 revolution per tap change operation):
Turn the drive shaft of the upper gear unit manually inboth directions until you feel that the spring energyaccumulator winds up (fig. 30, 31).
The centre of the rotation angle (approx. 180°) is theexact adjustment position (fig. 32). Couple the driveshaft in this position. When producing the coupling, thesquare tube and the upper gear unit should be alignedwith the smallest possible rotation angle (max. 45°).
b) In case of motor drive unit MA 7 respectively ED(33 revolutions per tap change operation respectively16.5 revolutions per tap change operation)
Loosen the screws of the tap changer cover(20 screws M10/w.s. 17, lock washers) and lift the tapchanger cover by at least 15 mm until the gear unitdisengages. Support the tap changer cover in thisposition by suitable pieces of wood or the like.
Turn the upper gear unit in the desired direction, so thatthe drive shaft can be properly coupled.
Check the position of the driven shaft on the output sideof the gear unit below the tap changer cover and turn thedrive shaft manually until the driven shaft engages intothe coupling of the gear unit.
Remove the wooden supports and fasten the tap changercover again by 20 screws M10/w.s. 17,max. torque 34 Nm and secure with spring washers.
Finally, checking the symmetrical coupling of the motordrive to the selector switch according to OperatingInstructions No. 40 for MA 7 or No. 80 for MA 9 andNo. 138 for ED.
20 081/05 EN
11Putting the tap changer into service at the transformer manufacturer
35 int034
34 int033
33 int032
11 Putting the tap changer into serviceat the transformer manufacturer
11.1 Operational test
Before applying voltage to the transformer some testoperations must be carried out to check the mechanicalfunctions of tap changer and motor drive.
For these test operations the tap changer has to be runthrough the entire operating cycle.
Make sure that in each operating position the indica-tions of motor drive and tap changer (inspection windowin the tap changer head) read the same position.
Check, in both end positions, the automatic switching offand the function of the electrical and mechanical endposition limitation (see Operating Instructions No. 40 formotor drive unit MA 7 or No. 80 for motor drive unitMA 9 and No. 138 for motor drive unit ED).
CAUTION
A coupling fault between tap changer and motor driveunit exists, if tap changer and motor drive unit showdifferent operating positions.Misalignment of coupling between tap changer andmotor drive unit leads to severe damage of tap changerand transformer, if operation is continued.The transformer must not be put into service.
21081/05 EN
Putting the tap changer into service at the transformer manufacturer 11Transport to the operating site 12
If the motor drive unit is to be demounted for transport ofthe transformer to the installation site, move the motordrive into the adjustment position and then uncouple.
To remount the motor drive unit follow the instructionsaccording to sections 10.1 and 10.3.
Install this by-pass tube at the tap changer between pipeconnections E2 and Q of the tap changer head.
For short stand-by periods of 2 to 4 weeks without oilconservator, it is also sufficient to lower the oil level byapprox. 5 litres.
If the transformer is to be completely emptied, drain alsothe switching oil of the tap changer completely.
The interior of the tap changer oil compartment shouldbe conserved and protected in the same way as thetransformer (e.g. by filling with nitrogen).
If a longer stand-by period is expected, the heater of themotor drive unit must be connected and put intooperation.
12 Transport to the operating site
CAUTION
Do not operate the motor drive while the tap changer isuncoupled.
NOTE
If the transformer is filled with oil but stored or trans-ported without oil conservator, a by-pass tube must beinstalled between the interior of the tap changer oilcompartment and the transformer tank to equalize thepressure caused by the expansion of the oil.
Fill up the tap changer completely with transformer oil viathe oil conservator and bleed as follows:
• The tap changer head via the bleeder valce in thetap changer cover (E1):
Open the screw cap M30/w.s.36 (fig. 33),lift the valve tappet by means of a screwdriver.
• The suction pipe (S) via the bleeder screw at theconnecting elbow: cap nut M16/w.s. 22, max.torque 9 Nm, slotted bleeder screw M6 (max.torque 2 Nm, fig. 34).
11.3 Ground connections
Connect the ground screws of the tap changer head(2 screws M12 mit nuts, w.s. 19, max torque 60 Nm,fig. 35) to the transformer cover.Connect the ground screw M12/w.s. 19, max. torque60 Nm, of the motor drive protective housing to thetransformer tank.
11.4 Electrical transformer tests
After the afore-mentioned steps the electrical testsnecessary for acceptance of the transformer can now beperformed.
CAUTION
Make sure that the suction pipe has been bled com-pletely. The insulation capability of the tap changer toground is otherwise significally impaired.
11.2 Final oil filling
22 081/05 EN
Supervision of tap changer and motor drive unit is limitedto occasional visual checks of tap changer head,protective relay and motor drive.
Pay special attention to:
• oil tightness at the sealing locations of the tapchanger head, the protective relay and the pipeconnection,
• sealings at the protective housing of the motor drive,
• proper function of the incorporated electrical heaterinside the motor drive housing,
• the condition of the control devices in the motor drive unit.
In case of major faults with tap changer or motor drivewhich cannot be easily overcome on the spot and incase of a response of the protective relay, please con-tact the authorized MR representative, the transformermanufacturer or directly
Maschinenfabrik Reinhausen GmbHTechnical Service
Postfach 12 03 60D-93025 Regensburg
Phone: +49-941-4090-0Telefax: +49-941-4090-501Telex: 6 5 881
14 Supervision during service, failures
13 Putting into service at the operating site14 Supervision during service, failures
Before putting the transformer into service operationaltests of tap changer and motor drive have to be per-formed according to section 11.1. At the same timecheck the function of the protective relay.Loop in signaling contact for undershooting theminimum oil level in the on-load tap-changer oilconservator in the on-load tap-changer tripping circuit.
Make sure that the circuit breakers switching off thetransformer operate when test button »OFF« of theprotective relay is pressed. Be sure that they energizethe transformer only after test button »IN SERVICE« ofthe protective relay has been pressed.
When having energized the transformer, tap changeoperations under load can be performed. The then arisingswitching gas accumulating under the cover of the tapchanger head will cause minor oil displacement orescape via the oil conservator.
13 Putting into service at the operatingsite
NOTE
The protective relay has to be inserted into the trippingcircuit of the circuit breakers so that on response ofthe protective relay the transformer is immediatelyswitched off (see Operating Instructions No. 59 forprotective relay RS 2001).
CAUTION
Check that all stop valves between oil conservator andtap changer are open.
NOTE
Damage to the on-load tap-changer due to not enoughoil in the oil conservator of the on-load tap-changer!Actuation of the on-load tap-changer with too little oilin the on-load tap-changer’s oil conservator maycause damage to the on-load tap-changer!Make sure that the contact for signaling the fallingbelow the minimum oil level in the on-load tap-changer’s oil conservator was looped through to thetripping circuit of the circuit-breaker and that thecircuit-breaker will immediately de-energize thetransformer when the oil has fallen below thisminimum oil level in the oil conservator.
WARNING
After a response of the protective relay, do not resetuntil the tap changer and the transformer have beenchecked. For this purpose withdraw the tap changerinsert and check it according to our InspectionInstructions. Proceed in detail according to OperatingInstructions No. 59 for the protective relay RS 2001.Before returning to operation, make sure that thecause of the trouble has been corrected and that tapchanger and transfromer are free of damage.Reconnection of the transformer without prior check-ing is prohibited and can lead to severe damage of tapchanger and transformer.
23081/05 EN
15Inspections
The inspection can be carried out by qualified andMR-trained personnel usually within one day,provided it is well prepared and organized.
We strongly recommend to have the inspectionscarried out by our Technical Service. This guarantees aprofessional performance of the inspection and ensuresthe updating of specific components to the latestoperational state.
If the inspection is not to be carried out by MR person-nel, we recommend that you ask for a quotation of thespare parts required for the inspection (please quotethe tap changer serial number and the number ofswitching operations).
The numbers of tap change operations determining theinspection intervals indicated in table II are figuresbased on experience with use of usual oil qualities.
After reaching 800 000 operations the OLTC insert andthe complete gear must be replaced.
If the number of tap change operations per year ex-ceeds 15,000 we recommend the use of our stationaryoil filter unit type 51 (see Operating Instructions No. 18).
15 Inspections
NOTE
The tap changing equipment must be inspected atregular intervals to maintain a high level of operatingreliability.
When the tap changer V III 200 D, V III 350 D andV III 500 D is in operation in countries with a tropical orsubtropical climate where the relative humidity is ex-tremely high and the temperature in the oil conservatorusually falls below the dew point every day, the use of anoil filter unit with a combined filter insert is recommendedto maintain the dielectric properties of the switching oil.
If, under such circumstances, the highest operating vol-tage between the phases of the tap changer is > 55 kV,the use of an MR oil filter unit with combined filter isalways required (see Operating Instructions No. 18).
Filtering of the switching oil allows the inspectionintervals to be extended.
The insulating oils in the transformer are to be monitoredby the operator according to the appropriate directions.
If inspections are not carried out by MR personnel, werequest a report to supplement our inspection data.
CAUTION
Disregard of the inspection intervals puts at risk thetrouble-free operation of the tap changer andtransformer.
The following standard values for oil testing according to CIGRE report 12-13 (1982) apply to transformer oil at servicetemperature:
*) measured according to Karl-Fischer method based on IEC-Publication 814**) measured according to DIN VDE 0370 Teil 1
On-load tap changer Water content*) Dielectric strength**)
V III 200 Y, V III 350 Y, V III 500 Y < 40 ppm > 30 kV/2.5 mm
V III 200 D, V III 350 D, V III 500 D < 30 ppm > 40 kV/2.5 mm
V I 200, V I 350, V I 700 < 30 ppm > 40 kV/2.5 mm
Table I Guide values for monitoring the tap changer oil
24 081/05 EN
15 Inspections16 Appendix
16 Appendix
On-load tap changer type V 200, installation drawing_________________________________________ 893 945On-load tap changer type V 350, installation drawing_________________________________________ 893 821On-load tap changer type V 500, installation drawing_________________________________________ 894 566Drilling template for tap changer head ____________________________________________________ 893 787Tap changer head, dimension drawing ____________________________________________________ 893 779Supporting flange for installation into a bell-type transformer tank _______________________________ 893 864Lifting traverse, dimension drawing _____________________________________________________ 893 805Protective relay RS 2001, dimension drawing ______________________________________________ 892 608Motor drive unit MA 7, dimension drawing _________________________________________________ 895 660Motor drive unit MA 9, dimension drawing _________________________________________________ 893 381Motor drive unit ED-S, protective housing__________________________________________________ 898 420Bevel gear CD 6400, dimension drawing __________________________________________________ 892 916
On-load tap changer Transformer- Number of tap changer operationsrated current without MR oil filter unit with MR oil filer unit
V III 200 Y, V III 200 D, V I 200 up to 100 A 100 000 150 000V III 250 Y, V III 250 D up to 250 A 70 000 140 000
V III 350 Y, V III 350 D, V I 350 up to 200 A 100 000 150 000V III 400 Y, V III 400 D up to 400 A 70 000 140 000
V III 500 Y, V III 500 D up to 350 A 100 000 150 000up to 500 A 70 000 140 000
V I 700 up to 350 A 100 000 150 000up to 700 A 70 000 140 000
If the number of operations indicated in table II has not been reached an inspection is to be carried out after the followingnumber of years:
On-load tap changer type: V III 200 Y, V III 350 Y, V III 500 YFirst inspection: 6 - 7 yearsFurther inspections: 6 - 7 years with or without MR oil filter unit
On-load tap changer type: V III 200 D, V III 250 D, V III 350 D, V III 400 D, V III 500 D, V I 200, V I 350, V I 700Arrangement of the on-load tap changer at the line end of the delta winding or inautotransformers
First inspection: 2 yearsFurther inspections: 4 years without MR oil filter unit / 6 - 7 years with MR oil filter unit
Arrangement of the on-load tap changer in the middle of the delta windingFirst inspection: 2 yearsFurther inspections: 6 - 7 years with or without MR oil filter unit
Table IIInspection intervals
25081/05 EN
16Appendix
On-load tap changer type V 200893 945:4E
Installation drawing
Flat surface
Provide sufficientclearance!
Transformer tank bottom
appr
ox.
Tap changer terminals also availablewith through-bore in vertical position!
Transformer tank bottom
Provide sufficientclearance!
11 – Mounting flange on transformer cover12 – Fixing bolt M1213 – Tap changer head gasket14 – Inspection window for position indication15 – Through-bore 16 mm
21 – Tap changer head22 – Cover of tap changer head23 – Pipe connection R for protective relay24 – Pipe connection Q for oil return pipe (with oil filter unit only)25 – Pipe connection S for suction pipe
26a – Bleeder screw of tap changer cover26b – Bleeder screw for transformer oil26c – Bleeder screw for suction pipe27 – Upper gear unit with drive shaft 27a
31 – Selector switch contact cylinder32 – Bottom of oil compartment with kerosene drain screw 32a33 – Selector switch terminal34 – Output terminal or neutral terminal35 – Change-over selector terminal ’’+’’ and ’’–’’36 – Change-over selector terminal ’’0’’
thick
26 081/05 EN
On-load tap changer type V 350893 821:7E
Installation drawing
16Appendix
Provide sufficientclearance!
7.6 thick
Transformer tank bottom
Tap changer terminals also available with through-bore in vertical position!
Transformer tank bottom
Provide sufficientclearance!
11 – Mounting flange on transformer cover12 – Fixing bolt M1213 – Tap changer head gasket14 – Inspection window for position indication15 – Through-bore 16 mm diameter
21 – Tap changer head22 – Cover of tap changer head23 – Pipe connection R for protective relay24 – Pipe connection Q for oil return pipe (with oil filter unit only)25 – Pipe connection S for suction pipe
26a – Bleeder valve for tap changer cover26b – Bleeding facility for transformer oil chamber26c – Bleeder screw for suction pipe27 – Upper gear unit with drive shaft 27a
31 – Selector switch oil compartment32 – Bottom of oil compartment with kerosene drain screw 32a33 – Selector switch terminal34 – Output terminal34a – Output terminal or neutral terminal34b – Star-point connection35 – Change-over selector terminal ’’+’’ and ’’–’’36 – Change-over selector terminal ‘’0’’37 – Change-over selector terminal V I 700 ’’+’’ and ’’–’’38 – Change-over selector terminal V I 700 ‘’0’’
Flatsurface
5 thick
27081/05 EN
On-load tap changer type V 500894 566:4E
Installation drawing
16Appendix
Flatsurface
Provide sufficientclearance!
Transformer tank bottom
Tap changer terminals also available with through-bore in vertical position!
11 – Mounting flange on transformer cover12 – Fixing bolt M1213 – Tap changer head gasket14 – Inspection window for position indication15 – Through-bore 16 mm diameter
21 – Tap changer head22 – Cover of tap changer head23 – Pipe connection R for protective relay24 – Pipe connection Q for oil return pipe (with oil filter unit only)25 – Pipe connection S for suction pipe
26a – Bleeder screw of tap changer head cover26b – Bleeder screw for transformer oil26c – Bleeder screw for suction pipe27 – Upper gear unit with drive shaft 27a
31 – Selector switch contact cylinder32 – Bottom of oil compartment with kerosene drain screw 32a33 – Selector switch terminal34 – Output terminal or neutral terminal35 – Change-over selector terminal ’’+’’ and ’’–’’36 – Change-over selector terminal ‘’0’’
thick
28 081/05 EN
On-load tap changer type V893 787:0E
Drilling template for tap changer head
16Appendix
3 thickness
Marks to be pounded
29081/05 EN
16Appendix
On-load tap changer type V893 779:7E
Tap changer head, dimension drawing
Detail ''X''
E1
= Bleeding facility for tap changer head
E2
= Bleeding facility for space under the headoutside the tap changer oil compartment
R = Connection for protective relay (exchangeable with connection Q)
Q = Connection for oil return pipe (only for oil filter)
S = Connection for suction pipe
= Earth connection M12
Width of gasket
Connecting flangefor R, Q, S
O-ring 44.2 - 5.7
Thickness 16
Connections can be swivelled by 360°
30 081/05 EN
On-load tap changer type VSupporting flange for installation 893 864:4E
into a bell-type transformer tank (special design)
16Appendix
Lifting device
Lifting traverse (illustrated in turned position)
Transformercover
Gasket
Washer 8
Supporting flange
Lifting traverse
Z - Centering boltFurther dimensions of tap changerhead see dwg. 893 779
Lifting traverse see dwg. 893 805
O-ring 44.2 - 5.7
31081/05 EN
On-load tap changer type V893 805:3E
Lifting traverse
16Appendix
(Part no. for subassembly: 086 402) Sheet steel U St- 37-1KDIN 1652
32 081/05 EN
Protective relay RS 2001892 608:7E
Dimension drawing
16Appendix
Inspectionwindow
Gasket
Designin service o f f
Reedcontact
Designation of relay1)Variant
Plan view of test push buttons(cover removed)
Arrangement of terminalsContact positions
Key of variants
Sta
ndar
d de
sign
Spe
cial
des
ign
agai
nst s
urch
arge
The arrowhead must always point towardsthe oilpipe leading to the oil conservator
of the transformer
1)NO - normally open, NC - normally closed, CO - change-over contact
The protective relay is to be connected in such a way that if it is energized, the power transformer is switched-offimmediately by its circuit breakers
Cable glandPG 16
Identification plate
Blind screw PG 16
Gasket
Test push buttons
Off(trip)
In service(reset)
33081/05 EN
Motor drive unit MA 7895 660:AE
Attachment and dimensions (lock with clamp lever)
16Appendix
Design for guard plate(special design)
Earthing screwM12
3 blind gland plates
Hinge
The cover can be opened to the leftor to the right according to thearrangement of the hinge pins.
opened by 90°
opened by 180°
Section A-B
Shi
m
Wal
l of
trans
form
er ta
nk
Protective housing(fixing hole)
Aperture in protective housing for cable entry(viewed from below)
Location of fixing holesat protective housing
Hand crankcentre line
34 081/05 EN
Motor drive unit MA 9893 381:AE
Attachment and dimensions
16Appendix
opened by 135°
Wall oftransformer tank
Fixation ofprotective housing
Aperture in protective housing for cable entry(view from below)
opened by90°
Washer
opened by 180°
Blind glandplate
Hinge pin
Design for guard plate(special design) Earthing screw M12
35081/05 EN
16Appendix
Motor drive unit ED-S898 420:3E
Protective housing
Vertical guard platewith spacing ring
Hand crank
Wall of transformer tank
3 dummy plates forpacking glands
Shim
Attachment of protective housing
approx. 685 if opened 130°
approx. 858 if opened 180°
The cover can be openedto the left or to the rightdepending on the arrangementof the hinge pins.
Location of fixing holes on protective housing(rear view) Aperture in protective housing for cables
(underside view)
36 081/05 EN
Bevel gear CD 6400892 916:6E
Dimension drawing
e 1 =
205
for
sta
ndar
d de
sign
e 2 =
215
for
des
ign
with
bal
l joi
nt
16Appendix
37081/05 EN
www.reinhausen.com
© Maschinenfabrik Reinhausen GmbHPostfach 12 03 60
D-93025 Regensburg
BA 081/05 EN • 06/10 • F0001804 • Printed in Germany
Telefon: (+49) 9 41 / 40 90-0Telefax: (+49) 9 41 / 40 90-111Telex: 65881