This Development well is the first in Malaysia to utilize the new generation of drilling risk mitigation tools from OMNI OMNI Versatile Drilling Reamer (VDR) was installed at top of BHA replacing the conventional fixed blade stabilizer. Carefully selected drilling parameters and revised drilling practices resulted in drilling this highly deviated well efficiently and with reduced drilling risk. Drill pipe was pulled to surface on elevators and casing was run smoothly according to plan. Best Practice summary: Mechanical Risk Mitigation: OMNI VDR with top PDC cutters Back reaming 1x before every connection while drilling Back reaming 2x before every connection at sections with high torque while drilling OMNI VDR placed at top of BHA in case of mechanical obstruction while pulling out of hole Hole Cleaning: OMNI VDR with TCI on blades and low side utilized 5” Hydroclean drill pipe utilized Circulation maintained at 1000GPM Circulation 5~7 times bottom ups before POOH RPM maintained at 180 Mud System: SBM at 10.2 ppg for the entire section Best Practice Bulletin New Technology for Improved Hole Condition OMNI VDR in Development Wells . OMNI VDR Versatile Drilling Reamer 5” HWDP Accelerator 5” HWDP Jar 5” HWDP Crossover 12” OMNI VDR 8” NMDC MWD Inline Flex Collar Short Hop Receiver Power Drive RSS PD900 12 ¼” RSS PDC Bit Top PDC cutter TCI on Blade & low side www.omnioiltech.com [email protected]

Upload: cory-thibert

Post on 22-Nov-2014

76 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Omni VDR Brief Copy

This Development well is the first in Malaysia to utilize the new generation of drilling risk mitigation tools from OMNI

OMNI Versatile Drilling Reamer (VDR) was installed at top of BHA replacing the conventional fixed blade stabilizer. Carefully selected drilling parameters and revised drilling practices resulted in drilling this highly deviated well efficiently and with reduced drilling risk. Drill pipe was pulled to surface on elevators and casing was run smoothly according to plan. Best Practice summary: Mechanical Risk Mitigation:

• OMNI VDR with top PDC cutters

• Back reaming 1x before every connection while drilling

• Back reaming 2x before every connection at sections with high torque while drilling

• OMNI VDR placed at top of BHA in case of mechanical obstruction while pulling out of hole

Hole Cleaning:

• OMNI VDR with TCI on blades and low side utilized

• 5” Hydroclean drill pipe utilized

• Circulation maintained at 1000GPM

• Circulation 5~7 times bottom ups before POOH

• RPM maintained at 180 Mud System:

• SBM at 10.2 ppg for the entire section

Best Practice Bulletin

New Technology for Improved Hole Condition

OMNI VDR in Development Wells

.

OMNI VDR Versatile Drilling

Reamer

5” HWDP

Accelerator

5” HWDP

Jar

5” HWDP

Crossover

12” OMNI VDR

8” NMDC

MWD

Inline Flex Collar

Short Hop Receiver

Power Drive RSS PD900

12 ¼” RSS PDC Bit

Top PDC cutter

TCI on Blade & low side

www.omnioiltech.com [email protected]

Page 2: Omni VDR Brief Copy

9 5/8" Casing - P/up & Slack off Weight Vs Joint Number

0

50

100

150

200

250

136

130

124

118

112

106

100

94

88

82

76

70

64

58

52

46

40

34

28

22

Joint Number

P/up &

Slack off W

eight (klbs)

P/up S/O

www.omnioiltech.com

Perfect hole condition was achieved with torque and drag within acceptable limits String was pulled out of hole on elevators smoothly Casing was run efficiently according to plan

OMNI VDR equipped with Tungsten Carbide Inserts (TCI) on blade OD has contributed to improved hole condition while drilling and tripping OMNI VDR equipped with PDC cutters and placed near the top of BHA to facilitate back reaming while drilling. This offered a valuable risk mitigation tool for clearing obstructions while pulling out of hole

Dec-07

12 1/4" Off-Bottom Torque

2200

2300

2400

2500

2600

2700

2800

2900

3000

3100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Off-Bottom Torque (k ft/lbs)

Depth (ft)

FF 0.10 FF 0.20 FF 0.30 FF 0.40

FF 0.50 OBT Break-Over Torque

12 1/4" Drilling Hook-Loads

2200

2300

2400

2500

2600

2700

2800

2900

3000

3100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

70 80 90 100 110 120 130 140 150 160 170 180 190 200 210

Hook-Load (k/lbs)

Depth (ft)

S/O 0.10 S/O 0.20 S/O 0.30 S/O 0.40 S/O 0.50

ROB Weight P/U 0.10 P/U 0.20 P/U 0.30 P/U 0.40

P/U 0.50 S/O Wt. P/U Wt. ROT Wt.