omega - nasa · evaluate the omega return on investment for both energy, economics, and perform a...
TRANSCRIPT
![Page 1: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/1.jpg)
OMEGA
Offshore Membrane Enclosures for Growing Algae
1
![Page 2: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/2.jpg)
2
![Page 3: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/3.jpg)
Current State of the Art
Open circulating ponds
(raceways)
Limitations:
Water
Energy demand for pumping
Weed species
Closed bioreactors
Limitations:
Infrastructure cost
Energy demand: pumping,
mixing, cooling
Temperature regulation
3
![Page 4: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/4.jpg)
O ffshore
M embrane
E nclosures for
G rowing
A lgae
4
![Page 5: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/5.jpg)
OMEGA System
Treated Wastewater/CO2
Wastewater
Nutrients/CO2
Solar Energy
Temperature Control
Treated Wastewater/CO2
Wastewater
Nutrients/CO2
Solar Energy
Oxygen
OMEGA System
5
![Page 6: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/6.jpg)
OMEGA Project Objectives
• Design, develop and build an algal cultivation system that utilizes and treats wastewater and is sufficiently scalable to be relevant for biofuels
Deploy and operate an OMEGA pilot system for repeated algal growth cycles
Develop protocols to maintain the OMEGA system under various conditions in marine environments
Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment
Develop partnerships with DoD, DoE, and/or Industry to transition and implement large scale OMEGA projects
•
•
•
•
6
![Page 7: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/7.jpg)
Project Deliverables
• Technology development for “ocean-going” photobioreactor (OMEGA)– Design, build and test OMEGA prototypes, lab and pilot scale systems
• 35% detailed design of commercial-scale OMEGA system to PDR level
Systems analyses for commercial-scale OMEGA system•
– Productivity (aviation fuels, food, fertilizers) & services (WW treatment, CO2 sequestration)
Returns on Investments (economics & energy)
Life cycle and cost benefit analyses
Greenhouse gas emissions reduction analyses
–
–
–
• Technology transfer to U.S. Navy, DOE, & private sector
7
![Page 8: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/8.jpg)
Accomplishments to Date
• Concept of Operations
PBR process design
Material selection for PBR module
PBR module concept design
PBR module structural considerations
Infrastructure design
•
•
•
•
•
8
![Page 9: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/9.jpg)
OMEGA Concept of Operations
9
![Page 10: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/10.jpg)
Baseline PBR Design• Primary material: Polyethylene (HDPE and LLDPE)
– PAR transmittance, UV resistence
Structural considerations–
• Batch or Continuous modes of operation
– Wastewater for water, carbon, nutrients, and trace elements
Internal recycle loop for nutrients
Control dissolved oxygen
Use carbon dioxide in flue gas to provide pH control and supplemental carbon
–
–
–
• Forward Osmosis membranes for dewatering
– Dewater at a rate to concentrate nutrients for optimal biomass growth
• PBR concepts are Strips or Cellular < 21,000 liters
10
![Page 11: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/11.jpg)
OMEGA Project Timeline
11
![Page 12: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/12.jpg)
Strip PBR Concept
Carbon dioxide
Air for sparging
Influent
Air/water for
hydroskeleton
Flexible
connection
between
modules (typ)
Combination air
Release valve (typ.)
Connections to
next module
12
![Page 13: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/13.jpg)
Cellular PBR Concept
Flexible Connection
Between Modules
Combination air
Release valve (typ.)
Carbon dioxide
Air for sparging
Influent
Carbon dioxide
Influent
Air for sparging
Connections to
Next module
13
![Page 14: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/14.jpg)
Santa Cruz Site (CDFG)
–
–
–
–
–
–
Process Performance:
Mixing intensity and duration
Nutrient removal efficiency
Effects of batch mode of operation vs. continuous mode of operation
Module Development:
Determination of locations for ports in PBR for process control & monitoring
Filling and harvesting methods
Placement of air, CO2 and FO membranes
14
![Page 15: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/15.jpg)
What’s NextQ3 – Q4 FY10
– OMEGA PBR Prototype Testing
CA Department of Fish & Game (CDFG) Facility–
Q1 – Q2 FY11
– OMEGA Pilot-Scale PBR Prototype Testing
Wastewater Treatment Facility (To be selected)–
Q3 – Q4 FY11
– CDR
OMEGA Pilot Test (final PBR design)
Wastewater Treatment Facility and/or wave tank facility
–
–
Q1 – Q2 FY12
– Preliminary design of full-scale OMEGA system
Perform feasibility assessment–
15
![Page 16: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/16.jpg)
Contra Costa Site Option
16
![Page 17: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/17.jpg)
SF Site Option
17
![Page 18: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/18.jpg)
Pilot-Scale Test Objectives• Continue prototype PBR module tests:
– Algae growth with wastewater and flue gas
Wastewater treatment–
• Build larger systems to determine how OMEGA modules will be assembled in place and/or deployed– Filling, incubating, mixing, harvesting, and refilling to repeat the
cycle
Productivity, rates and efficiencies in both batch and flow-through systems
Structural integrity and basic handling
–
–
• Design logistics plan for OMEGA pilot test
Collect data on PBR and sub-system performance for FE model and hydrodynamic model
Down select a final PBR Module Design for OMEGA Pilot test
•
•
18
![Page 19: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/19.jpg)
OMEGA Points of Contact
Jonathan Trent, Project Manager
(650) 604-3686
Ed Austin, Deputy Project Manager
(650) 604-2108
19
![Page 20: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/20.jpg)
Back Up Charts
20
![Page 21: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/21.jpg)
Sites Considered for PBR Design
• Selected Two Sites
– Estuary – Near Treasure Island in San Francisco Bay
Ocean – Santa Monica Bay near Hyperion Wastewater Treatment Plant
–
• Rationale for Site Selection
– Possible Full-Scale Deployment Locations
Broad Range of Conditions–
21
![Page 22: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/22.jpg)
PBR Enclosure Structural Studies
Approach
• Assumed a “Generic” PBR Module, since actual design has not been selected
Calculated loading for Hyperion (Santa Monica Bay) and Treasure Island
Performed Preliminary Structural Analysis
Assumed PBR size, e.g. 10’ x 100’, 10’ x 1000’
Determined Factor of Safety (FS) = Failure Load or Stress divided by Applied Load or Stress
Acceptance Criteria
•
•
•
•
•
– FS = 2
Lower FS may be allowed for Extreme Events–
22
![Page 23: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/23.jpg)
PBR Enclosure Structural Studies• Use external conditions from Treasure island and Hyperion as boundary
conditions
Structural analysis •
– Drag force
Anchorage
Buoyancy
Impact and inertial Loading
–
–
–
• Equipment Anchorage
Internal Stability •
23
![Page 24: OMEGA - NASA · Evaluate the OMEGA return on investment for both energy, economics, and perform a complete life-cycle analysis to determine its impact on the environment Develop partnerships](https://reader034.vdocuments.us/reader034/viewer/2022042106/5e854f1ed1f16e6a0c6b4282/html5/thumbnails/24.jpg)
Boundary Conditions for PBR Designs
• Site selections represent real-life off shore conditions
– Treasure Island in San Francisco Basin: 0.5 miles from water wateroutfall of EBMUD WWTP
Santa Monica Bay: Hyperion WWTP–
Conditions Hyperion Treasure Island
Wind (mph) Nominal 7.5 12.8Summer max 28.0Winter storm 62 60.0
Current, knots Up-coast 1.46 2.2Down-coast 1.94 3.3
Wave, ft Nominal 6-10 (8-12 sec) 0.5 (<1.5 sec)(Wave period, sec) Extreme >16 (17 sec) 1–4.5(<2 sec)
24