Olympic Tunnel 400kV Cable Project Hackney Substation To West Ham Substation

Upload: sivagnana-sundaram

Post on 13-Oct-2014

159 views

Category:

Documents


12 download

TRANSCRIPT

Page 1: Olympic Tunnel Presentation PGH 3

Olympic Tunnel 400kV Cable Project Hackney Substation

To West Ham Substation

Page 2: Olympic Tunnel Presentation PGH 3

Experience

Prysmian has been responsible for the design, supply, installation and commissioning of over 450Km of Supertension cables in 44 tunnels worldwide. Of which 9 are in the UK.

In January 2006 Prysmian was awarded the contract to design, supply, install and commission the 400kV XLPE cables, accessories, support systems and monitoring systems for the West Ham – Hackney tunnel.

Page 3: Olympic Tunnel Presentation PGH 3

Project scope

• Full turnkey project to design, supply, install & commission two 400kV cable circuits.

• Tunnel length 6km

• Tunnel diameter 4.15 metres

• Circuit length 6.3km

• Install and commission both circuits by September 2008.

• Tunnel to be cleared of temporary services

Page 4: Olympic Tunnel Presentation PGH 3

Prysmian Supply scope

Cables: Single core, 2500mm2 copper conductor, XLPe Insulated, Aluminium Sheath, flame retardant oversheath. 48drums, 810m section length. Cable weight 36kg/m.

Accessories: 36 sectionalised 400kV joints, 6 un-sectionalised 400kV joints, 12-400kV outdoor terminations with composite insulators.

Monitoring: Continuous Partial Discharge monitoring for all joints and terminations. Continuous monitoring for sheath voltage limiters at each joint bay.

Page 5: Olympic Tunnel Presentation PGH 3

Prysmian Supply scope

Steelwork: 210 tonnes of steelwork designed, manufactured and installed to support the cable and accessories in the tunnel and above ground.

Substations: Design and construction of:

- Cast in-situ cable troughs from the tunnel shafts to the Outdoor terminations at Hackney & West Ham.

- Associated cable support structures and foundations.

- Cable trough forced air ventilation systems.

- DAR Cable Protection.

- Surge Arrestors.

Page 6: Olympic Tunnel Presentation PGH 3

Tunnel constraints

• 4.15 metre diameter tunnel with no level base for ease of access or use of vehicles – solution was to design and manufacture vehicles to run on monorail.

• Tunnel designed for 4 circuits with the first two circuits to be installed at the top level on either side of the tunnel.

• All installation and jointing works carried out at some two metres from tunnel invert necessitating special mobile platforms for all works and large scaffold structures (26 tonnes of scaffolding per joint bay) for jointing works.

Page 7: Olympic Tunnel Presentation PGH 3

Project successes

• Installed 48 drums of cable in 12 weeks.

• 4500 cable sags completed in 12 weeks.

• 42 cable joints and 6 outdoor sealing ends installed in 17 weeks.

• 210 tonnes of steelwork installed throughout the tunnel and shafts.

• 300 tonnes of scaffolding installed into and removed from the tunnels and shafts within the 6 month cable installation and jointing programme.

• Overall installation project completed in 30 weeks due to parallel working patterns.

Page 8: Olympic Tunnel Presentation PGH 3

System Design

Page 9: Olympic Tunnel Presentation PGH 3

Rating Requirements

• Summer 1660 MVA (2396 Amps)

• Spring / Autumn 1790 MVA (2584 Amps)

• Winter 1950 MVA (2815 Amps)

• An additional two circuits would be added at a later date and the above ratings will change

Page 10: Olympic Tunnel Presentation PGH 3

2

3

4

5

6

7

8

1

1. Central filler2. Milliken conductor3. Conductor screen4. XLPE Insulation5. Insulation screen6. Semi-conducting hygroscopic binder7. Aluminium sheath8. PE oversheath

400 kV XLPE Cable with 2500 mm² Copper Conductor

Page 11: Olympic Tunnel Presentation PGH 3

Main Cable Features

• Milliken conductor with low AC resistance.

•XLPE insulation

•Thick longitudinally welded aluminium sheath.

• Flame retardent oversheath.

•Cable is light and robust.

Page 12: Olympic Tunnel Presentation PGH 3

Skin effect

Proximity effect

Reducing AC resistance

• Milliken divides conductor into sectors• Improves current density in sector• Reduces skin effect• Widely spaced cables reduces proximity effect• Reduced AC resistance means improved rating

Page 13: Olympic Tunnel Presentation PGH 3

Ref No.

Title

DWG No. Date

Drawn by

Company

Customer

Verified by

Symbols

Issue No.

E\E\901\L

GW

VJB

1

Outdoor Termination Unsectionalised Joint

Sectionalised Joint

Cable: 2500mm2 Copper Conductor, 400kV XLPE Cable

Note:- all sectionalised joints will have SVL's fitted across the sectionalisinginsulation

Detail of cross bonding andSVL connections

SVL

SVL

SVL

West Ham S/SHackney S/S

West Ham - Hackney400 kV CircuitNational Grid

STS9221/D1 issue 3 11/04/06

1LNB-2072

LBM 7A

Single core 300 mm²bonding strands Single core 500 mm²

bonding strands

B B B B B B

B: LBM 3A

Schematic Arrangement of Circuit

• 2 x sections with sheaths single point bond• 2 x major sections with sheaths cross-bonded

Page 14: Olympic Tunnel Presentation PGH 3

Single Point Bonded Sheaths

• No circulating currents in the sheath – better rating.• Sectionalising insulators protected by SVL.• Earthing interconnector to carry the return fault current

Page 15: Olympic Tunnel Presentation PGH 3

Vr 00 Vb 1200 Vy -1200+ + = 0`

• Crossed bonded cables are installed in multiples of three.• Sheaths voltages balanced out over three-sections.• No circulating currents – No sheath losses – Higher ratings.• Joints sectionalising insulators protected by sheath voltage limiters (not shown)

Cross-Bonded Sheaths

Page 16: Olympic Tunnel Presentation PGH 3

Heat FlowThrough Ground

Heat Flow byTunnel Air Ventilation

HeatGenerated

byCables

TA (inlet)

TA (outlet)

Cable Rating Assessment

•Cables will generate losses• Majority of heat removed by air ventilation.• Rating assessed by Cigre methods

•Electra 143• Electra 144

Page 17: Olympic Tunnel Presentation PGH 3

Monitoring Systems

Page 18: Olympic Tunnel Presentation PGH 3

Types of Monitoring System

• Distributed Temperature Sensor (DTS)• Sheath Voltage Limiter (SVL)• Partial Discharge (Pd)

Page 19: Olympic Tunnel Presentation PGH 3

DTS Monitoring System

• The temperature sensor is an optical fibre cable.• The characteristics of the fibres will change with

temperature.• The temperature can be measured for the complete

route.• The hot-spots can be identified. • The cable / tunnel temperatures are measured

using DTS hardware locate at one substation. • The tunnel ventilation can be adjusted to suit.

Page 20: Olympic Tunnel Presentation PGH 3

DTS Fibre Attached to Cable

•Other fibres installed top and bottom of tunnel.

Page 21: Olympic Tunnel Presentation PGH 3

SVL Monitoring

Page 22: Olympic Tunnel Presentation PGH 3

SVL Monitoring

• Optical fibre and mirror wrapped around SVL.

• Reflected signal – SVL operational.

• Loss of signal – SVL failed

Optical signal

Reflection

Page 23: Olympic Tunnel Presentation PGH 3

SVL Monitoring display

Page 24: Olympic Tunnel Presentation PGH 3

HMI - All SVL’s Operational

Page 25: Olympic Tunnel Presentation PGH 3

HMI - SVL failed on System 1 J.B. 2/3

Page 26: Olympic Tunnel Presentation PGH 3

Partial Discharge Monitoring

• All accessories monitored for PD.• Used during commissioning and in service.• No power supply in tunnel.• PD measurements sent by fibre optic cable to

the outside of the tunnel.

Page 27: Olympic Tunnel Presentation PGH 3
Page 28: Olympic Tunnel Presentation PGH 3

PD Monitoring display

Page 29: Olympic Tunnel Presentation PGH 3

Cable Installation Jointing and Testing

Page 30: Olympic Tunnel Presentation PGH 3

Project successes

• Installed 48 drums of cable in 12 weeks.

• 4500 cable sags completed in 12 weeks.

• 42 cable joints and 6 outdoor sealing ends installed in 17 weeks.

• 210 tonnes of steelwork installed throughout the tunnel and shafts.

• 300 tonnes of scaffolding installed into and removed from the tunnels and shafts within the 6 month cable installation and jointing programme.

• Overall installation project completed in 30 weeks due to parallel working patterns.

Page 31: Olympic Tunnel Presentation PGH 3

Planned Cable Arrangement at Shaft 3

Page 32: Olympic Tunnel Presentation PGH 3

Cable Installation at Shaft 3- Hackney

Page 33: Olympic Tunnel Presentation PGH 3

Tunnel layout

Page 34: Olympic Tunnel Presentation PGH 3

Schematic cable & winch arrangement

Page 35: Olympic Tunnel Presentation PGH 3

Tunnel cross section

Page 36: Olympic Tunnel Presentation PGH 3

Trial cable delivery

Page 37: Olympic Tunnel Presentation PGH 3

Trial cable delivery - Hackney

Page 38: Olympic Tunnel Presentation PGH 3

Cable convoy - Stratford

Page 39: Olympic Tunnel Presentation PGH 3

Drum storage at shaft 2

Page 40: Olympic Tunnel Presentation PGH 3

Steelwork installed ready for rollers

Page 41: Olympic Tunnel Presentation PGH 3

Shaft 2 prior to scaffolding

Page 42: Olympic Tunnel Presentation PGH 3

Looking down shaft 2 scaffolding

Page 43: Olympic Tunnel Presentation PGH 3

Base of shaft 2 ready for cable

Page 44: Olympic Tunnel Presentation PGH 3

Monorail working platform

Page 45: Olympic Tunnel Presentation PGH 3

Cable installation at height

Page 46: Olympic Tunnel Presentation PGH 3

Cable installation at shaft 2

Page 47: Olympic Tunnel Presentation PGH 3

Scaffolding at top of shaft 2

Page 48: Olympic Tunnel Presentation PGH 3

Pipes at top of shaft 2

Page 49: Olympic Tunnel Presentation PGH 3

Pipes on scaffolding at top of shaft

Page 50: Olympic Tunnel Presentation PGH 3

Back tension winch at shaft 2

Page 51: Olympic Tunnel Presentation PGH 3

Cables installed at high level

Page 52: Olympic Tunnel Presentation PGH 3

Transposition by joint bays

Page 53: Olympic Tunnel Presentation PGH 3

Transposition by joint bays

Page 54: Olympic Tunnel Presentation PGH 3

Cable transposition

Page 55: Olympic Tunnel Presentation PGH 3

Transposition at joint bay

Page 56: Olympic Tunnel Presentation PGH 3

Sagging of cables

Page 57: Olympic Tunnel Presentation PGH 3

Sagging of cables

Page 58: Olympic Tunnel Presentation PGH 3

Training area for jointing

Page 59: Olympic Tunnel Presentation PGH 3

Training area for jointing

Page 60: Olympic Tunnel Presentation PGH 3

Training area for jointing

Page 61: Olympic Tunnel Presentation PGH 3

Joint bay platform

Page 62: Olympic Tunnel Presentation PGH 3

Joint bay

Page 63: Olympic Tunnel Presentation PGH 3

Completed joint

Page 64: Olympic Tunnel Presentation PGH 3

Completed joints

Page 65: Olympic Tunnel Presentation PGH 3

Completed joint bay

Page 66: Olympic Tunnel Presentation PGH 3

HV Test Arrangement

Page 67: Olympic Tunnel Presentation PGH 3

Termination Arrangement at Hackney