![Page 1: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/1.jpg)
Ohio River Tunnel: An innovative alternative to 3
CSO Basins
Project Update Meeting
10.11.2016
![Page 2: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/2.jpg)
Discussion topics for this evening
• Overview • Ohio River Tunnel Project
Conceptual layout • Next Steps
![Page 3: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/3.jpg)
Ohio River Tunnel Overview A project to combine the volume of 3 individual Combined Sewer Overflow (CSO) basins into a single deep rock tunnel September 30, 2016 approval by MSD’s Board to move forward with design
Three basins will be eliminated by the consolidated tunnel solution
![Page 4: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/4.jpg)
Careful consideration resulted in the new solution Variety of factors considered:
– Discussions with Community leaders – Input from public meetings – Traffic disruptions along key commercial corridor – Economic impacts to downtown businesses and the emerging
Butchertown district – Consent Decree mandates for completion by December 2020 – Technological advances of deep tunnel construction over the last
decade have reduced costs – Eliminates challenges of construction and final land use planning
on a brownfield site
![Page 5: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/5.jpg)
Community meetings to date
Story & Main Lexington & Payne
Orientation June 16, 2015 January 19, 2016
Conceptual February 10, 2016 April 26, 2016
![Page 6: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/6.jpg)
Ohio River Tunnel Conceptual Layout
![Page 7: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/7.jpg)
Ohio River Tunnel Facts
• Temporary storage of sewer diluted with rain water during wet weather events
• Approximately 13,200 linear feet in length • Approximately 175-feet to 200-feet below ground • Minimum internal diameter of 20 feet • Minimum storage volume of 31.8 million gallons
![Page 8: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/8.jpg)
Ohio River Tunnel Preliminary Alignment
![Page 9: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/9.jpg)
Individual projects make up the Ohio River Tunnel Project
• Project Components: – Ohio River Tunnel – Lexington & Payne CSO Interceptor – Story and Main Connector – Downtown CSO Interceptor – Rowan Pump Station & Force Main
• The Consent Decree Deadline of December 31, 2020 remains unchanged
![Page 10: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/10.jpg)
Lexington and Payne CSO Interceptor Facts
• Sewer line to capture overflows from the 9 existing CSOs and convey that flow to the tunnel
• Interceptor will be below the concrete channel of South Fork Beargrass Creek
• Approximately 5,000 liner feet in length – From E Broadway to E Main Street – Pipe size ranging from 36-inch to 102-inch
![Page 11: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/11.jpg)
Lexington and Payne CSO Interceptor Drop Shaft
Drop Shaft
Interceptor Tunnel
![Page 12: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/12.jpg)
Story and Main Connector Facts
• Sewer line to capture overflows from the 2 existing CSOs and convey that flow to the tunnel
• Approximately 200 liner feet in length – On Franklin Street and Buchanan Street – Pipe size 36-inch
![Page 13: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/13.jpg)
Story and Main Connector
Tunnel
Drop Shaft
![Page 14: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/14.jpg)
Downtown CSO Interceptor Facts
• Sewer line to captures overflows from 12 CSOs and convey that flow to the tunnel
• Approximately 2,000 linear feet in length – Mainly north-south streets between Main Street and
River Road – Pipe size ranging from 12-inch to 48-inch
![Page 15: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/15.jpg)
Downtown CSO Interceptor
Drop Shaft
Interceptor
Drop Shaft
![Page 16: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/16.jpg)
Rowan Pump Station & Force Main Facts
• A pump station to return combined sewer flows to the existing system for treatment
• Control buildings will be constructed on northwest corner of 13th Street and Rowan Street intersection
![Page 17: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/17.jpg)
Rowan Pump Station
Pump Station Drop
Shaft
Force Main
![Page 18: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/18.jpg)
Next Steps
![Page 19: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/19.jpg)
Next Steps
• Project modification request currently under EPA review • Begin conceptual designs • Continue coordination with project partners • Conduct public update meetings as project progresses • Consent Decree Deadline to remain December 31, 2020
![Page 20: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/20.jpg)
Schedule
Project Construction Start
Construction Completion
Ohio River Tunnel Summer 2017 Spring 2020 Lexington & Payne CSO Interceptor Summer 2017 Fall 2019
Story & Main Connector Spring 2018 Winter 2019
Downtown CSO Interceptor Spring 2018 Winter 2019
Rowan Pump Station & Forcemain
Spring 2018 Summer 2020
![Page 21: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/21.jpg)
Questions you may have
• Will MSD purchase the River Metals Recycling (1371 Lexington Rd)
property or be performing any construction activities on the River
Metals Recycling property associated with this project?
• What will be the impact to neighbors of the project during
construction?
• Will there be any visible above ground structures?
• Will there be odors associated with the tunnel?
![Page 22: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/22.jpg)
Discussion
![Page 23: Ohio River Tunnel: An innovative 10.11.2016 alternative to ...msdprojectwin.org/Portals/0/Library/IOAP Public Input Meeting... · Ohio River Tunnel: An innovative ... – Technological](https://reader034.vdocuments.us/reader034/viewer/2022051801/5ae359cc7f8b9a5b348d56da/html5/thumbnails/23.jpg)