ohio power plant foundation

19
Page 0 of 15 Ohio Power Plant Foundation Project ID: CEEn_CPST_011 by The U.S./Guam Alliance Austin Kennedy Taylor Emmertson Will Berger Chloe Gogue A Capstone Project Final Completion Report Submitted to Jaren Knighton Kiewit Engineering, Inc. Department of Civil and Environmental Engineering Brigham Young University April 12, 2021

Upload: others

Post on 06-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 0 of 15

Ohio Power Plant Foundation

Project ID: CEEn_CPST_011

by

The U.S./Guam Alliance

Austin Kennedy

Taylor Emmertson

Will Berger

Chloe Gogue

A Capstone Project Final Completion Report

Submitted to

Jaren Knighton

Kiewit Engineering, Inc.

Department of Civil and Environmental Engineering

Brigham Young University

April 12, 2021

Page 1 of 15

Executive Summary

PROJECT TITLE: Ohio Power Plant Foundation

PROJECT ID: CEEn_CPST_011

PROJECT SPONSOR: Kiewit Engineering, Inc.

TEAM NAME: U.S./Guam Alliance

The project requires that group members analyze the soil stresses and provide

recommendations for suitable foundation systems and ground improvement techniques for a power

plant in Ohio. Each member will perform the necessary research, calculations, and analysis needed

to determine how best to approach building the foundations of said power plant. The required load-

bearing capacities of the soil for each area of the power plant will be used to formulate proposed

foundation systems. The project timeline extends from September 2020 to April 2021. Meetings

are to be held regularly; and consistent communication is to be maintained with Jaren Knighton, a

Kiewit Engineering liaison, and the team’s project advisor. A detailed benefit analysis will be

presented comparing multiple options for each section of the power plant. The team will deliver

their final recommendations for the foundation systems on each section of the power plant

determined by Jaren Knighton based on the geotechnical tests performed by Kiewit Engineering.

Performance Standards

The team will provide work for this Capstone project “as is” using best practices and with

best effort. Project results cannot be construed as work performed by licensed professionals and

cannot be used as “stamped deliverables” without first being reviewed, approved, and stamped by

a qualified and relevant licensed professional engineer.

Page 2 of 15

Table of Contents

List of Figures 3

List of Tables 4

Introduction 6

Schedule 7

Assumptions & Limitations 8

Design, Analysis & Results 9

Lessons Learned 11

Conclusions 12

Recommendations 133

Appendix A 144

Page 3 of 15

List of Figures

Figure 1 - Required soil bearing capacity for sections of power plant

Figure 2 - Boring test pit locations and site conditions

Page 4 of 15

List of Tables

Table 1 - Foundation options with advantages and drawbacks

Foundation System Application Advantages Drawbacks

Spread footing with

slab

- Wall loads present

- Shallow

- Cost-effective

- Non-skilled labor

- Simple

construction

- Higher settlement

- Requires higher soil

bearing capacity

- May cause

irregularity in future

structure

Pier and Beam - Shallow

- Steel buildings

- Swelling soils

- Applicable in a

variety of site

locations

- Allows room for

crawl space/

basement

- More expensive

shallow option

Pile - Deep

- Large Structures

- Areas with

unsuitable shallow

soil

- Areas with high

groundwater table

- Bypasses shallow

soil

- High load

capacity

- Corrosion-

resistant

- Possible pile

damage during

construction

- Located below

ground level

- Custom pile lengths

common (increased

cost)

Matte foundation - Large distributed

loads

- Areas with weak soil

- Buildings with

basements

- Resists

differential

settlement

- Very strong

- Low cost when

doubled as floor

slab

- Swelling soils cause

uplift

- May need heavy

reinforcement

- Experienced labor

needed

Page 5 of 15

Table 2 - Ground improvement techniques with advantages and drawbacks

Technique Application Advantage Drawback

Grouting - Filling pores in soil

or rock

- Decreased

permeability

- Higher shear strength

- Quality assurance

is unknown

- Difficult in

shallow depths

Deep Dynamic

Compaction

- Densifies soil by

dropping heavy

steel/concrete

weight with crane

- Increased density

- Increased strength

- Decreased settlement

- Lower liquefaction

potential

- Higher bearing

capacity

- Non-applicable in

areas with soft

cohesive soils

- Non-applicable

within 100ft of

existing building

Vibro-compaction/

Vibro- Replacement

- Course aggregate

added to existing

hole and compacted

using vibration

- Increased density

- Reduced

differential/total

settlement

- Higher bearing

capacity

- Granular soil

contains more

than 12-15% silt

or more

Rammed Aggregate

Piers

- Aggregate/grout

columns added

below slab

- No dewatering

- Short construction

time

- Increased soil

stiffness

- Limited Bearing

capacity per pier

- Increased cost per

additional pier

Wick Drains - Drainage path for

excess pore water in

soft/compressible

soil

- Reduced long term

settlement

- High equipment

cost

- Only viable in

shallow depths

Page 6 of 15

Introduction

The project requires that team members provide recommendations based on geotechnical

data provided by Kiewit Engineering for a power plant foundation in Ohio. The power plant is

broken up into sections based on the required bearing capacity of the soil, thus analyses and

recommendations will be made for each section. A final report will be provided to Kiewit

Engineering and Capstone Leadership. This report will detail multiple options for foundation

systems for each section of the power plant differing in cost and ease of construction. The team’s

recommendation will be provided explaining why Kiewit Engineering should construct that

specific type of foundation. A detailed schedule is provided below to aid in showing the approach

in delivering the final recommendations by the end of April 2021.

Page 7 of 15

Schedule

Monday, Oct 26

Week 1 (Oct 26-31)

Week 2 (Nov 2-7)

Week 3 (Nov 9-14)

Week 4 (Nov 16-21)

Week 5 (Nov 23-28)

Monday, Nov 30

Week 6 (Nov 30-Dec 5)

Week 7 (Dec 7-12)

Week 8 (Dec 14-19)

Weeks 9-11 (Dec 21-Jan 9)

Week 12 (Jan 11-16)

Week 13 (Jan 18-23)

Week 14 (Jan 25-30)

Week 15 (Feb 1-6)

Week 16 (Feb 8-13)

Week 17 (Feb 15-20)

Week 18 (Feb 22-27)

Week 19 (Mar 1-6)

Week 20-22 (Mar 8-27)

Week 23 (Apr 1)

Week 24 (Apr 12)

Submit Statement of Work

Print data sheets to bring to the meeting with Dr. Rollins

Schedule meeting with Dr. Rollins

Print data and begin organizing it into sections

Meet with Jaren to clarify questions concerning scope

Research options for foundation systems and their criteria

30% completion report.

Continue research for foundation systems

Begin soil analysis to classify sections with

foundation options

Continue to classify sections with foundation options

Christmas Break

Continue soil analysis/label sections with foundation options

Verify current project direction with Jaren

Bring analysis to Dr. Rollins for verification on numbers

Begin comparing options

Compare options in regards to cost/ease of construction

Gather recommendations

Organize findings

Begin work on final presentation and meeting with

Dr. Rollins

Continue with final presentation/report

Present at Capstone seminar

Present final powerpoint to Jaren

Page 8 of 15

Assumptions & Limitations

Due to the limited nature of the project, all loadings listed in Figure 1 are assumed to be

distributed or line loads. All recommended foundation systems will be based on this assumption

with little to no regard towards specialized foundation systems required by power plant equipment,

if any.

Page 9 of 15

Design, Analysis & Results

The design of the project has been determined under the guidance of the group mentor and

project representative. Analysis of the power plant was done in separate sections, where team

members focused on one building per week. Each building had unique circumstances and data

sheets that were produced from test pits (Figure 2). This data played a vital role in determining

which ground improvement technique (Table 2) and foundation type (Table 1) to use.

Provided below is a list of the soil conditions and expected settlement of each building

(Figure 3). Please note that the settlement calculations are based on raw soil data alone and do

not account for ground improvement techniques. Therefore, the values listed provide a “worst-

case” settlement scenario.

The final list of recommended foundation types and ground improvement techniques for

each building can be found in the “Recommendations” section.

Figure 3: Settlement and bearing capacity equations

Page 10 of 15

Table 3: Soil conditions and anticipated settlement of buildings

Structure Soil Conditions Anticipated

Settlement

Water Treatment

Building

- Sandy clay

- High water table due to entrapped water

⅝ in.

Tank Farm - Sandy gravel

- Entrapped water

⅝ in.

Cooling Tower - Sandy gravel

- Half lies on entrapped water

½ in.

Admin Building - Clayey silty sand ½ in.

GSU/UAT - Gravelly sand

- Must excavate top portion of clay so that deep

dynamic compaction reaches intended soil layers

⅝ in.

Turbine Building - Mostly well-graded gravel, with a patch of clay in

the middle

⅝ in.

AUX BRL Building - Gravelly sand with a top layer of clay

- Entrapped water

⅝ in.

HRSG - Well graded gravel with thin layer of lean clay with

fine gravel

⅞ in.

Electrical/Ammonia

Building

- First two feet are clay and need to be excavated

- The soil underneath is gravelly sand

½ in.

Page 11 of 15

Lessons Learned

This project has taught us many lessons in communication and collaboration. The greatest

challenge we faced was our limited knowledge and general inexperience. Therefore, we

emphasized reaching out to our mentors, leaders, and professionals in the field to help us gain a

basic understanding of the principles we employed in our calculations for this project. These

circumstances have helped us maintain communication with our faculty mentor for help and

direction in interpreting data and choosing an ideal foundation system.

Given our busy schedules and the current world social state, we have also learned how to

effectively communicate within the team via social media messaging and Zoom calls. This formed

part of our Wildly Important Goal, which was to maintain regular communication. We predicted

that by doing so we could best complete the project. Over the course of the project, we have also

come to better understand the importance of meeting attendance and the crucial role that each team

member plays. Additionally, we have learned how to properly reach out to professionals to seek

advice and coordinate meetings.

Through this collaboration, we have learned more about computing differential settlement

and have applied this new knowledge over the course of this project. We have also had the

opportunity to look over various charts, graphs, tables, and other compilations of data collected

from the field where our project is being built. We have been interpreting the data and comparing

the plots to see how different soil characteristics relate to each other. As we have neared the end

of our project and begun to make final decisions, we have come to understand that practice and

real-world experience are essential in this field. Armed with the knowledge, advice, and insights

from professional civil engineers, we feel confident in the recommendations we have made.

Page 12 of 15

Conclusions

As the end of the project approaches, conclusions have been made concerning the results

of the soil analysis. Each building has been recommended a foundation type and ground

improvement technique to be used in order to reduce total soil settlement under each building.

These results have been reached via intensive research and collaboration with professionals. The

list of recommendations can be found in the following section of this report.

Page 13 of 15

Recommendations

Below is a compiled list of the recommended foundation system, ground improvement

technique, and anticipated settlement (Table 4). Recommendations were decided via group

collaboration and based on the soil conditions and anticipated settlement found in Table 3.

Projected settlement and the possible effects of preventative settlement techniques were also taken

into account. These conclusions were made based on thorough research and study, and to the best

of the team’s ability.

Table 4 -Ground improvement techniques and foundation type

recommendations per site area

Page 14 of 15

Appendix A

Chloe Gogue

275G Farenholt Ave. Suite S-366, Tamuning, GU 96913

1(801) 577-8302 · [email protected]

https://www.linkedin.com/in/chloe-gogue-a1a0b616b/

EDUCATION

Bachelor of Science in Civil Engineering December 2021

Brigham Young University Provo, UT

● 2.56 GPA

SKILLS/ACTIVITIES

● Proficient in: Geographic Information Systems (ArcMap, ArcGIS), AutoCAD, Microsoft Office

● Familiar with: Autodesk Revit, SAP 2000

● Undergraduate Seismic Design Competition (2020)

RELEVANT EXPERIENCE

Civil Engineering Intern June - July 2020

N.C. Macario & Associates Inc. Tamuning, GU

● Created engineering diagrams (architectural, structural, electrical, and plumbing) in AutoCAD for

residential buildings

● Improved understanding of AutoCAD through daily use

OTHER EXPERIENCE

Earthquake Engineering Research Institute Club Officer August 2019 – Present

Co-President (August 2019 - April 2020), President (April 2020 – Present)

● Seismically designed and tested a scale-model balsa wood skyscraper to compete internationally

● Participated in the Undergraduate Seismic Design Competition 2020

● Performed managerial tasks such as, organizing meetings and ensuring deadlines were met

Full-time Volunteer Representative December 2014 – July 2016

The Church of Jesus Christ of Latter-day Saints Denver, CO

● Built relationships with individuals through communication in both English and Spanish

● Developed both interpersonal and multicultural skills through interactions with people of diverse

cultures and backgrounds

● Taught goal-setting and problem-solving skills to local residents

Page 15 of 15

Taylor Emmertson ∙ (251)-490-2821 ∙ [email protected]

∙ https://www.linkedin.com/in/taylor-emmertson ∙

Education Bachelor’s Degree in Civil Engineering December 2021

Brigham Young University, Provo, UT GPA: 3.25

● Relevant Courses - Statics, Engineering Drafting with CAD Applications, Computational Methods,

Sustainable Infrastructure, Mechanics of Materials, Statistics for Engineers, Geomatics, Global

Leadership, Introduction to Transportation Engineering, Dynamics, Hydraulics and Fluid Flow Theory,

Technical Writing, Structural Analysis, Elementary Soil Mechanics, Materials Analysis

● Student Leadership - 2012 BYU ASCE Student Chapter Vice President, BYU Southern Students’

Association Committee Member

● Scholarships - Brigham Young University Academic Scholarship, Douglas R. & Nancy P. Ferrell

Scholarship

● Student Membership - BYU Society of Women Engineers, BYU Society for Women in Civil Engineering,

BYU ASCE Student Chapter, BYU Southern Students’ Association, BYU Honor Society - Phi Eta Sigma

Engineering Experience Intern - Utah Department of Transportation May - August 2020

● Tested asphalt samples from road construction projects and recorded information to verify the sample

materials met project standards.

● Inventoried and organized concrete cylinder samples for load-bearing tests, which assessed the strength

of the concrete material and its concurrence with regulation requirements.

● Supervised road construction projects and kept track of the progress in reference to deadlines and

completion requirements.

● Collaborated with employers and other coworkers to discuss important project matters and foster

internal growth as an engineering team.

Projects

● Strawberry Reservoir Mill and Fill: road reconstruction May-July 2020

● Mayflower Mountain Resort: bridge construction May-July 2020

● Traffic Signal Installation projects in Heber and Charleston, Utah: May-July 2020

● Kiewit Engineering Group Inc.: Ohio power plant foundation Sept 2020 - April 2021

Skills/Certifications

● ArcGIS

● AutoCAD/Revit

● VBA Spreadsheet Coding

● Oral and Written Presentation Skills

● Proficiency in Microsoft Office

● ASCE BYU Student Chapter Member

Additional Work/Service Experience Humanities 202 Teaching Assistant - BYU Online August 2019 - Present

● Review textbook material and information with students to prepare them for tests. Tutoring and academic support are

offered through video chat, collaborative documents, and other study aids.

● Discuss with 20th-percentile students how they might improve their writing skills for routine assignments. Students’

writing grades have improved by up to 27%.

● Attend weekly meetings with the professor to discuss expected learning outcomes and calibrate the grading curve.

● Completed frequent surveys to evaluate my performance as an online TA and record my work hour

Page 16 of 15

Page 17 of 15

Austin Kennedy (970) 274-6202 ∙ [email protected] ∙ linkedin.com/in/austin-kennedy-b973b817a/

EDUCATION

Brigham Young University Jun 2021

Bachelor of Science: Civil Engineering, Emphasis in structures Provo, UT GPA 3.59

BYU President’s Leadership Council Scholarship

ASCE member

Structural Analysis, Computational Methods, Engineering with CAD Apps, Structural Steel Design,

Foundations of Global Leadership, Geomatics, Technical Writing

INTERNSHIPS

Summer Intern, Instrument Person May 2019-Aug 2020

High Country Engineering Glenwood, CO Assisted party chiefs in 50+ surveying jobs to improve efficiency over the course of two summers

Utilized surveying instruments such as GPS and total station to conduct As-Builts, ILC’s, and ISP’s

Created hand-drawn sketches of 10 buildings for ISP CAD work

LEADERSHIP EXPERIENCE

Team Lead Sep 2020-Apr 2021

Brigham Young University Capstone Project Provo, UT Coordinated with Kiewitt Engineering to design a foundation system for a power plant in Ohio

Reported hours to client and faculty mentor to maintain a consistent schedule

Directed team efforts in research and design to generate foundation ideas

Custodian, Floor Lead Sep 2018-Apr 2019

Missionary Training Center Provo, UT Oversaw cleaning procedures for several floors of a building to maintain a pleasant learning environment

Instructed and interacted with 10 volunteers per day in additional cleaning services

Reported weekly supply needs to maintain sufficient stocks

EXPERIENCE IN SERVICE

Volunteer Sep 2020

Humanitarian Experience for Youth Salt Lake City, Utah

Managed a station in Reservoir Park for 6 hours for youth to color a section of sidewalk

Engaged with and tutored 120 teenagers in how to use chalk to create images about hope for the future

Full-time Volunteer, Secretary July 2016-June 2018

Religious Organization Lima, Peru

Conducted training meetings for 20+ representatives

Managed inventory of supplies in office and in 180+ representatives’ living quarters

Planned and reported daily, weekly, and monthly goals to improve efficiency and impact

Collaborated with organizational members to increase efficiency and minister to new members

SKILLS/INTERESTS/ACHIEVEMENTS/ABILITIES

Fluent Spanish International Baccalaureate programme graduate, Life rank as Boy Scout

HazCom Training

Personal talents and interests include hiking in the outdoors, making sketches of architecture and nature,

writing, learning new topics

Page 18 of 15