ohio creek project update - norfolk
TRANSCRIPT
Ohio Creek Project Update
Katerina Oskarsson Ph.D., Deputy Resilience Officer
City Manager’s Office of Resilience
Norfolk City Council
October 10, 2017
2
3
4
5
6
Community Meetings
7
Coastal Defense
8
9
Stormwater
11
Connectivity & Amenities
13
14
Project Schedule
• Sept. 21, 2017—Community feedback on final design
• Winter 2018—Permittable drawings
• Fall 2019—Bid packages for construction
• Summer 2022—Construction completed