The Making of the Spallation Neutron SourceThe Making of the Spallation Neutron SourceA 25-Year JourneyA 25-Year Journey
Patricia DehmerPatricia DehmerDeputy Director for Science Programs & Acting DirectorDeputy Director for Science Programs & Acting Director
Office of Science, U.S. Department of EnergyOffice of Science, U.S. Department of Energy
Download this talk at http://www.science.doe.gov/SC-2/Deputy_Director-speeches-presentations.htm
U.S.-Sweden First Joint Consultative Group MeetingU.S.-Sweden First Joint Consultative Group Meeting 21 April 200921 April 2009
![Page 2: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/2.jpg)
2
The 1984 “Seitz-Eastman Report” of the National Academy of Sciences The 1984 “Seitz-Eastman Report” of the National Academy of Sciences The first call for a pulsed spallation neutron source in the U.S.The first call for a pulsed spallation neutron source in the U.S.
The 1984 “Seitz-Eastman Report” (a.k.a., “Major Facilities for Materials Research and Related Disciplines”) presented priorities for new facilities.
The new facilities in order of priority were:
a 6 GeV synchrotron radiation facility (the Advanced Photon Source at ANL, commissioned in 1996);
an advanced steady state neutron facility (the Advanced Neutron Source at ORNL, terminated in 1995);
a 1 to 2 GeV synchrotron radiation facility (the Advanced Light Source at LBNL, commissioned in 1993); and
a high intensity pulsed neutron facility (the Spallation Neutron Source at ORNL, commissioned in 2006).
![Page 3: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/3.jpg)
3
Evolution of Machines for Neutron Beam ScatteringEvolution of Machines for Neutron Beam Scattering
![Page 4: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/4.jpg)
FROM MATERIALS PROPERTIES … TO PROCESS AND FUNCTION
CourtesyJohn Axe & Sunny Sinha,
1997
Power requirements -- best guess at the time
![Page 5: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/5.jpg)
55
Spallation Neutron Source Primary ParametersSpallation Neutron Source Primary Parameters
![Page 6: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/6.jpg)
6
![Page 7: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/7.jpg)
8
SNS Project Site — Spring 1999SNS Project Site — Spring 1999
![Page 8: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/8.jpg)
9
Rep.Wamp
Sec.Richardson
Vice Pres.Gore
Gov.Sundquist
Sen.Frist
Rep.Gordon
ORNL Dir.Trivelpiece
SNS Dir.Moncton
Rep.Duncan
Spallation Neutron Source GroundbreakingSpallation Neutron Source Groundbreaking15 December 199915 December 1999
![Page 9: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/9.jpg)
10
October 2000 October 2000
![Page 10: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/10.jpg)
11
October 2000, Site PlanOctober 2000, Site Plan
![Page 11: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/11.jpg)
12 0168
5-20
02
12
March 2002March 2002
![Page 12: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/12.jpg)
1313
August 2002August 2002
![Page 13: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/13.jpg)
1414
August 2002August 2002
![Page 14: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/14.jpg)
1515
November 2002November 2002
![Page 15: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/15.jpg)
16
~53% complete overall (including 94% of R&D, 85% of design, 39% of technical hardware, 46% of conventional construction, and 14% of installation)
~90% of planned procurements had been awarded
Intensive conventional construction activity on site and hardware fabrication by industry under contracts to the 6 Labs
Project staffed at plan (~ 650 FTEs including Labs and AE/CM, plus over 500 construction workers on site); staffing peaked in FY 2002
Outstanding safety performance while completing ~1.6 million construction hours
November 2002November 2002
A proton’s view of the target buildingfrom the exit of the ring tunnel
![Page 16: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/16.jpg)
1717
June 2003June 2003
![Page 17: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/17.jpg)
1818
June 2003June 2003
![Page 18: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/18.jpg)
1919
April 2004April 2004
![Page 19: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/19.jpg)
20
The Spallation Neutron Source Today The Spallation Neutron Source Today
![Page 20: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/20.jpg)
Linac TunnelLinac Tunnel
![Page 21: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/21.jpg)
Looking toward the ion sourceLooking toward the ion source Looking toward the accumulator ring Looking toward the accumulator ring
![Page 22: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/22.jpg)
23
Inner Reflector Plug InstallationInner Reflector Plug Installation
![Page 23: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/23.jpg)
24
Overview of the TargetOverview of the Target –– 14 November 200514 November 2005Thom Mason, Jack Marburger, Jim Roberto
![Page 24: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/24.jpg)
![Page 25: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/25.jpg)
![Page 26: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/26.jpg)
27
Mercury Target ModuleMercury Target Module
Original target module has exceeded planned fluence goal (SNS power level is currently 700 kW) If target does not reach end of life by July 2009 shutdown, it will be removed to minimize impact on user program .
![Page 27: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/27.jpg)
SNS Energy and Power on TargetSNS Energy and Power on Target
![Page 28: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/28.jpg)
SNS – What’s Next?SNS – What’s Next?
1.1. Science outputScience output
2.2. Continuous technical improvementsContinuous technical improvements
![Page 29: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/29.jpg)
SNS Instrument SuiteSNS Instrument Suite
![Page 30: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/30.jpg)
31
Instrument CommissioningInstrument Commissioning
4 instruments operating < 2008
10 currently operating
13 will be operational in 2009
All instruments are approved through a formal processAll instruments are approved through a formal process
![Page 31: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/31.jpg)
32
SNS Power UpgradeSNS Power Upgrade
Linac beam energy upgrade to 1.3 GeV by adding 9 superconducting cryomodules. Eventual increases in H- ion source beam, improvements in target module, and other upgrades.
![Page 32: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/32.jpg)
33
SNS Second Target StationSNS Second Target Station
New spallation target and supporting systems and buildings Initial suite of neutron beam instruments Cost in the $1B range
![Page 33: OFFICE OF SCIENCE The Making of the Spallation Neutron Source A 25-Year Journey Patricia Dehmer Deputy Director for Science Programs & Acting Director](https://reader034.vdocuments.us/reader034/viewer/2022051401/56649f275503460f94c3ecc1/html5/thumbnails/33.jpg)
34
The Spallation Neutron Source – The First 25 Years’ of the JourneyThe Spallation Neutron Source – The First 25 Years’ of the Journey