Office of Facilities Development (OFD) Capital Projects Status Report
3rd
Quarter CY 2014
November 5, 2014 The Office of Facilities Development (OFD) is pleased to provide the third quarter Capital Projects Status Report for calendar year 2014. This report provides summary level information on all projects managed by OFD, both Capital Projects and Capital Maintenance Projects. The third quarter was an exhilarating time for the OFD team!! Substantial completion was achieved on the Seminole Trail Fire Station Addition/Renovation project and an Occupancy Permit was issued October 3rd. Additionally, OFD supported maintenance projects in seventeen schools this summer with substantial completion reached on time for school opening this fall (one project involved security improvements at 13 school entrances). The Crozet Streetscape project is nearing completion and will improve
pedestrian connectivity within downtown Crozet as well as providing economic benefits and increased vitality for business owners. Notable projects currently under construction include: Northside Library and Storage Facility; Agnor-Hurt Elementary School Addition/Renovation; and the completion of Belvedere Boulevard from Rio Road to Free State Road (at the railroad bridge). The design of the Regional Firearms Training Center is progressing in the construction-drawing phase with the regional partners finalizing the Operating Agreement, Land Lease, and final budget appropriations. The following sections provide a summary on all projects and more detailed information of select Capital Projects. Based on feedback from the Board requesting budget history on a project, OFD staff has added a sample report to the Regional Firearms Training Center detailed report. We are interested in feedback on how the budget history information is shown and if the Executive Office and Board would like the incorporation of this additional information for the other major CIP projects. We hope you find this report useful and informative as the OFD team is proud of the work it does for the County and its citizens.
“Helping to Build a Better Albemarle”
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 1 of 12
CAPITAL PROJECTS Substantially Complete Scope Status Project Budget Key Milestone
Seminole Trail Volunteer Fire Department (STVFD)
Addition/Renovation
Addition (7,500 sq. ft.) to STVFD and full renovation of
the existing facilities (~7,500
sq. ft.). Includes 2-bay addition, expansion of living
quarters and full renovation of existing facility to bring it to
code and improve the facilities
to properly support the highest call volume station in the
County.
Occupancy permit issued October 3rd!!
Volunteers have moved
into new facility. Punch list work in progress
– final completion November 2014.
$4,046,615
Substantial Completion 10/3/14
Occupancy permit
Western Albemarle High
School (WAHS) Stormwater
Impacts
Design and construct a
stormwater management
(SWM) facility and improve head of channel at the back of
WAHS. SWM facility will provide storm water attenuation/
treatment in the form of a
biofilter for the stormwater runoff from the driver's
education parking lot.
Contractor worked with
Luck Stone to replace
biofilter material (at Luck Stone’s cost) since biofilter
was not draining properly. Remediation work
completed and accepted.
Final punch list work in progress.
$184,346 Substantial Completion
September 2014
School Security Improvements
Design and construction of improved entrances at thirteen
(13) schools to create a more secure entrance. The project
was bid with four Base Bids: Base Bid A (5 schools); Base
Bid B (4 schools); Base Bid
C (1 school); Base Bid D (3 schools).
Substantial completion achieved on 8/8/14.
Punch List work complete. Construction Contracts
awarded to 3 contractors totaling $376,287; change
order work - $3,902.
Project completed $119,000+ under
appropriated budget.
$500,000 Substantial completion August 2014
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 2 of 12
In Construction Phase Scope Status Project Budget Key Milestone
Crozet Streetscape Phase II Relocation of overhead electric
and utility lines from Crozet Avenue, new stormwater
drainage system, first block of
Main Street (Library Avenue), and pedestrian, vehicular, and
streetscape enhancements along Crozet Avenue from The
Square to Tabor Street.
Final asphalt, concrete
corrective work, and landscaping complete.
Installation of crosswalk
pavers in progress and nearing completion.
Final pavement striping dependant on weather.
Anticipate October 2014 substantial completion
(contractually Nov 18).
$4,539,014
Streetscape –
Substantial Completion November 2014
Northside Library and Storage Facility
Provide a permanent location for the Northside Library and
long-term County warehouse/
storage space. The new facility (repurposing of existing
building) would provide approximately 30,000 sq. ft. of
library space, and over 20,000
sq. ft. of warehouse space.
Construction approximately 55% complete as of
September.
Schedule extension of 40 calendar days necessary to
accommodate construction delays from unexpected
site, building, and
structural issues related to existing conditions.
Albemarle Square Library 2-month lease extension
necessary. Low bid on furniture $90k
under budget.
Lower and library level dry wall complete and prime
coat painting started in lower level.
Finalizing completion date
for storage area. Meeting with JMRL and
City IT personnel.
$11,843,740
Substantial completion February 2015
Occupancy permit
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 3 of 12
Belvedere Bond Default
Project
Complete the Belvedere
Boulevard and Residential
"Block" roads, drainage, water, sanitary sewer and related
construction according to the approved development plans.
Phase 1 of the work is
Belvedere Boulevard from Rio Road to Free State Road (RR
bridge); Phase 2 is the remaining Belvedere Boulevard
(Free State Rd. to the Village Green) and the residential
"Blocks" (3, 4A, 5A, 6B & 9A).
Funds for this project are from the developer’s performance
bonds.
Phase 1 Work:
Board appropriated funds
to complete work. Curb demo/replacement &
cross drains completed. Work planned Oct/Nov
includes milling and base
asphalt replacement, final surface asphalt, and
pavement markings. Phase 2 Work: comprised of
multiple development bonds necessitating dividing project
into individual Bid Items for
each bond resulting in award of four contracts.
All road and utility work substantially complete.
Compiling information and
plans (test reports, plats, as-builts) necessary for
VDOT and ACSA acceptance.
Change order pending to
correct outlet pipe leakage in Basin #4 forebay.
$3,675,790
(Bond Default
Funds)
$500,000 (County Funds)
Phase 1 Work –
Substantial Completion
November 2014 Phase 2 Work –
Improvements substantially complete.
Submittals to VDOT and
ACSA for acceptance 4th Quarter 2014
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 4 of 12
Lewis & Clark Exploratory
Center
Construction of an educational
building (including
transportation exhibits and river history), an access road
and parking area, and a connecting trail network, all
located at Darden Towe Park.
Funded by a grant through the VDOT Transportation
Enhancement Fund Program ($800,000) combined with
other funds raised by the Lewis & Clark Exploratory Center
(LCEC).
Board approved 3rd loan
extension request 10/1.
Final mechanical, electrical, and water and sewer line
inspections approved. LCEC’s project manager to
address items required to
pass remaining final inspections (plumbing and
building). LCEC to work cooperatively
with contractor to coordinate project
completion.
Final grant reimbursement will not be issued until
VDOT has inspected and signed-off on the project.
$800,000
(Grant only)
Completion anticipated
4th Quarter 2014
Agnor Hurt Elementary School
Addition & Renovations
Construction of 11,200 s.f.
addition consisting of seven (7) classrooms, one (1) full-sized
SPED classroom, faculty
workroom, offices and associated support spaces.
Renovations of 3,500 s.f. consist of security
improvements at front entrance, upgrades to media
center, and addition of air
conditioning to the kitchen. Replacement of existing chiller,
exhaust fans, roof top units and boilers. Site improvements
include additional parking and
modifications to student drop-off areas.
Phase I construction
substantially complete August 2014 (site work for
new road and bus loop and
relocated playgrounds). Phase II construction
underway (complete new entrance, bus loop, cooling
tower - structure & relocation, begin classroom
addition, underground
utilities relocation). Extremely low contingency
to start project; current contingency includes future
anticipated changes
including removal of more unsuitable school than
anticipated. Schools notified of contingency
concern.
$5,968,285 Construction to be
completed incrementally in successive Phases:
Ph. 1 – August 2014
Ph. 2 – December 2014 Ph. 3 – June 2015
Ph. 4 – August 2015
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 5 of 12
Church Road Basin
Stormwater Management
Facility Retrofit
Maintenance/enhancements to
existing regional stormwater
management facility including survey, design, and
construction. Project will help the County meet required
pollutant reductions mandated
for the Chesapeake Bay watershed.
Easement plat and deeds
executed and recorded.
Notice to Proceed issued to contractor 10/8/14.
Work to commence 10/20/14.
$426,919 Substantial Completion
2nd Quarter 2015
In Bid/Award Phase Scope Status Project Budget Key Milestone
Voter Registrar Office Renovations
Expansion and limited redesign of the Voter Registrar office
suite at COB-5th. The project will expand the office suite
from 1,140 sf to 1,373 sf,
including a modest expansion for storage into the existing
Office of Housing and floor plan redesign of the suite to
maximize functionality,
optimize work flow process, and alleviate congestion during
absentee voting.
Project currently being advertised for construction.
Bid opening scheduled for 10/30/14.
Construction starts January
2015.
$106,660 Substantial Completion 1st Quarter 2015
In Design/Planning Phase Scope Status Project Budget Key Milestone
Crozet Elementary School
Safe Routes to School (SRTS) Sidewalk
Provide improved walking and
bicycling routes to Crozet Elementary School for students
from residential neighborhoods
by constructing curb and sidewalk on the west side of
Crozet Avenue from Ballard Drive to the school. The
improvements also include installation of a manually
activated crosswalk warning
system at the pedestrian crossing to the school.
Additional appropriation
(proffer revenue) approved by Board to fully fund
construction.
Plan redesign complete and revised plans
submitted to VDOT for approval.
Obtain VDOT approval of revised final plans and
authorization to advertise.
$293,000
Re-advertise 4th
Quarter 2014 ~ 2-3 months construction
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 6 of 12
Crozet Avenue North Sidewalk Replacing or constructing
approximately 1100 feet of
sidewalk and drainage improvements along the west
side of Crozet Avenue from Saint George Avenue to Crozet
Elementary School. Partially
funded with FY13 Revenue Sharing Funds.
Board approved right-of-
way and easement
acquisitions. County Attorney’s office
finalizing deed and recordation.
Obtain VDOT approval of
Final Plans & Project Manual and authorization
to advertise.
$755,878
Bid/award 4th Quarter
2014 ~ 6 months
construction
South Pantops Drive/State
Farm Boulevard Sidewalk
Improvements
Construction of 3500 feet of
curb, gutter and sidewalk which
will serve several residential, business, and commercial
establishments. Partially funded with FY13 Revenue Sharing
Funds.
Appraisals approx. 90%
complete.
Work with County Attorney Office to complete deeds for
required acquisitions. Obtain BOS approval of
acquisitions.
Obtain VDOT approval of Final Plans & Project
Manual and authorization to advertise.
$1,019,408
Bid/award 4th Quarter
2014 ~ 6 months
construction
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 7 of 12
Hydraulic Road and Barracks
Road Sidewalk Improvements
Partially funded with revenue
sharing funds and supports
pedestrian safety by providing sidewalk improvements.
Hydraulic Road - construction of approx. 1700 feet of
sidewalk on the north side
between Commonwealth Drive and Georgetown Road.
Barracks Road: 1) construction of approx. 1000 feet of
sidewalk on the north side from Barracks West
apartments to existing
sidewalk west of Georgetown Road intersection;
2) construction of crosswalks and two segments of sidewalk
(650 ft total) on the south side
between Georgetown Road intersection & Westminster
Road, and between South Bennington Road & 29/250
Bypass ramps.
Surveys for both projects
completed.
Design plans are currently in progress.
Barracks Road – cemetery investigation beginning in
October 2014 – expected
completion in November 2014.
Public engagement meeting to be held once cemetery
investigation is complete.
$1,588,600
Bid/award 3rd Quarter
2015 ~ 5 months
construction
Fontaine Avenue Sidewalk Construction of a short sidewalk (~160') from the end
of the Fontaine Research Park paved path to the end of
sidewalk at the City line. This
project closes the walkway gap which may create safety issues
if left unconnected.
Sketch plan and detail and Project Manual about 95%
complete. Submit sketch and detail to
VDOT (permit section) to
assure its acceptable prior to bidding.
$102,189 Bid 4th Quarter 2014 ~ 2 months construction
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 8 of 12
Hollymead-Powell Creek Drive
Sidewalk
Completion of the sidewalk
connection from Hollymead to
Sutherland Schools. The required right-of-way has been
donated.
Staff will provide a minimal
design plan sheet based on
survey base map since proposed sidewalk is within
existing right-of-way. Provide a design that
complies with the new
stormwater / TMDL requirements.
$209,164 Bid 1st Quarter 2015
~ 2 months construction
FY14 Revenue Sharing Projects - Pedestrian/Sidewalk
Improvements
1. Old Lynchburg Road Walkway Upgrade
2. Avon Street Walkway/
Crosswalks Phase 1 3. Rio Road (Meadowcreek
Pkwy to Stonehenge)
4. US Rte 250 West, Crozet
(Harris Teeter)
Worked with VDOT to split projects into 2 separate
UPCs (Old Lynchburg Road
project has a separate UPC from the other three
projects). Expenditure line items
established and Board
appropriated funding. Consultant secured to
provide support for administration of VDOT’s
Local Administration
Program (LAP) requirements.
Internal Project SharePoint site currently being
developed for each UPC project.
$1,500,000 Secure civil engineering firm for design services
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 9 of 12
Regional Firearms Training
Center
Design and construction of a
regional indoor firearms
training facility, which includes a 50-yard qualification range
and 50-yard tactical range, 16 shooting lanes (original scope
20-24 shooting lanes),
classroom, office, bathrooms and storage areas (control
platforms eliminated from original scope). The range will
be located on property owned by UVA on Milton Road.
Total project cost estimate
based on schematic
drawings and refined project needs ~$6.8M.
Conclusion of executive meeting with fiscal
management staff from
County, City, and UVA was agreement to establish a
not to exceed (NTE) total project budget of $6M.
Request Board approval of additional funding to
establish NTE budget.
Design Development plans submitted and under
review by project design team.
Initial site plan meeting
results in VDOT requiring modifications to the
entrance which could be $50k-$100k in additional
costs.
Finalize operating agreement and land lease
terms and request Board approval.
$4,865,422
(Proposed $6M)
Agreement in place for
operations & funding –
4th Quarter 2014 Complete design/site
plan approval – 4th Quarter 2014
Bid/award – 1st Quarter
2015 ~ 6-9 months construction
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 10 of 12
Carrsbrook Pipe Repair The corrugated metal pipe
(CMP) drainage pipes of the
Carrsbrook Drive dam have corroded and a large eroded
hole has formed on the downstream side of the dam as
a result of the failing pipes. The
pipes are located on two private properties and partially
within the VDOT right-of-way of Carrsbrook Drive. The large
eroded hole is located within private property and, if not
repaired, could damage
Carrsbrook Drive, and is a life safety concern.
Temporary repair complete
(hole filled in and rip-rap
swale installed). Permanent repairs will be
within an easement to be acquired by the County.
Easement plats submitted
to CDD for review and County Attorney office
working on draft deeds. Analyzing drainage area
and completing runoff calculations to confirm
replacement pipe size is
adequate. County Attorney office
working with VDOT on agreement for work in
right-of-way.
$167,236 Substantial Completion
1st Quarter 2015
MAINTENANCE PROJECTS
Substantially Complete Scope Status Project Budget Key Milestone
Yancey Elementary School
Roof Replacement
Replace existing ballasted roof
systems at Yancey Elementary School main building and 1990
addition (29,320 SF). New roofing system will be adhered
EPDM roofing system with new insulation.
Punch list work completed.
No contingency used.
$473,364 Substantial completion
August 2014
Stone-Robinson Elementary
School Roof Replacement
Replace existing ballasted roof
at Stone Robinson Elementary School. New EPDM roof
system (23,295 sf).
Punch list work 99%
complete. No contingency used.
$261,730 Substantial completion
August 2014
Cale Elementary School Roof Replacement, Phase II
Replace 2nd half of ballasted school roof. New roof system
will be same as Phase 1,
insulation self adhering EPDM roof.
Punch list work completed. No contingency used.
$357,600 Substantial completion August 2014
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 11 of 12
Cale Elementary School
Parking Lot Expansion
Design and construction of an
additional twenty-five (25)
parking spaces on the southeast side of the school.
Punch list work completed. $158,633 Substantial completion
August 2014
Monticello High School Track
Replacement
Design and construction
services to demolish and replace existing track at
Monticello High School football stadium.
Punch list work in progress.
Construction Contract - $129,798, Change Orders -
Deduct ($57.50); no contingency used.
$165,000 Substantial completion
September 2014
Vehicle Maintenance Facility
(VMF) Lift Replacement Phase III
Phase III of multi-year phased
replacement of bus and vehicle lifts originally installed
with the construction of the VMF in the early 1980’s. This
phase replaces one (1) bus
lift.
Punch list work completed. $198,000 Substantial completion
August 2014
Ivy Creek School Exterior
Masonry Wall Repairs
Evaluate cracking and
deterioration of exterior c.m.u.
walls at various areas around perimeter of school, prepare
plan for repair, and initiate construction to remedy the
situation.
Punch list work completed. $26,620
Substantial completion
August 2014
Office of Facilities Development Capital Projects Status Report – 3rd Quarter, CY 2014
Page 12 of 12
In Construction Phase Scope Status Project Budget Key Milestone
Stormwater Multi-Facility
Maintenance Projects
Includes maintenance
(sediment removal/dredging) and upgrades to existing
regional stormwater
management facilities and channel (Four Seasons Lower
Basin dredging, Four Seasons Upper channel improvements,
and the Branchlands (Hillsdale Road) forebay sediment
removal). Phase 1 scope is
complete and included surveying and analysis of
existing facilities to determine required improvements and
possible enhancements.
Phase 2 scope includes design and construction of
recommended improvements/enhancements.
Four Seasons Upper Pond
Dredging: Project complete; fish pond restocked.
Branchlands (Hillsdale Road)
Forebay: Notice to Proceed pending Contractor securing
off-site waste area. Four Seasons Channel:
Secure and record required easement and then execute
construction contract. HOA
sent out mailing for 2/3 homeowners to approve
project. Response expected within 60 days.
$373,404 Four Seasons Upper
Pond Dredging – Complete
Branchlands Forebay –
Substantial Completion Fall 2014
Four Seasons Channel – Substantial
Completion Spring 2015
Court Square Air Handling
Units (AHU) and Controls Replacement
Replace existing AHU’s with
new and replace pneumatic controls with digital.
All duct work associated with
new units has been cleaned. AHU serving Circuit Court has
been installed and is operational.
One of two units to be
replaced in General District Court has been removed with
installation of new unit in progress.
$429,689 Substantial completion
November 2014
In Design/Planning Phase Scope Status Project Budget Key Milestone
COB-McIntire AHU Replacement
Replace existing air handling units along with main duct
cleaning. Humidity control to
be included.
Final design documents under review.
Advertise for bid mid-
November.
$700,217 Substantial completion 2nd Quarter 2015
Page 1 of 2 November 5, 2014
Project: Seminole Trail Volunteer Fire Department Addition/Renovation
Description: Addition (7,500 sq. ft.) to Seminole Trail Volunteer Fire Department (STVFD) and full renovation of
the existing facilities (~7,500 sq. ft.). Total scope includes a 2-bay addition, an expansion of living
quarters and full renovation of the existing facility to bring it to code and improve the facilities to
properly support the highest call volume station in the County.
Status: Occupancy permit issued October 3, 2014!! Volunteers have moved in new facility. Punch list work in
progress – final completion November 2014. Grand Opening Ceremony planned for November 23,
2014.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Pre-design Complete 01/11/13 01/18/13 7
Design Complete 03/22/13 04/26/13 35
Bid Opening Date 04/11/13 05/31/13 50
Notice of Intent to Award 04/18/13 07/23/13 96
Notice to Proceed 04/29/13 08/26/13 119
Renovation Demo Complete 06/14/13 10/13/13 121
Excavation - Addition Complete 07/05/13 10/04/13 91
Structural Elements Complete 09/06/13 05/22/14 258
Building Dried-In 11/29/13 06/13/14 196
Finishes Complete 02/28/14 09/12/14 196
Site Work Complete 03/21/14 09/29/14 192
Substantial Completion 04/04/14 10/03/14 182
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[May 2012]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 3,836,670 $ 4,046,615 $ (209,945)
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 3,836,670 $ 4,046,615 $ (209,945)
Use of Funds
Soft Costs $ 426,320 $ 546,812 $ (120,492)
Hard Costs $ 3,126,500 $ 3,386,796 $ (260,296)
Contingency $ 283,850 $ 113,007 $ 170,843
Total $ 3,836,670 $ 4,046,615 $ (209,945)
Balance = Funding - Costs $ - $ -
Encumbered: $ 164,973
Paid to Date: $ 3,531,837
A/E Contract (DJG, Inc. – includes Add. & Renov.) Construction Contract (Kenbridge Construction)
Original Agreement $428,444 Bid Award $3,001,754
Approved Changes $ 10,946 Approved Changes $ 138,671
Pending Changes $ 0 Pending Changes $ 91,010
TOTAL $439,390 TOTAL $3,231,435
A/E Change Orders:
Construction Change Orders:
No. & Brief Description Amount No. & Brief Description Amount
1 – MEP redesign for Value
Engineering changes
$10,946 1 – Underground sewer lines under
engine bay floor; sanitary pipe to tie-
in washer boxes to sewer line; add
mop sink
2 – Replace various doors/ hardware
to comply with code requirements
3 – Dumpster rental for volunteers
demo; add section of concrete
footing to CMU wall
4 – Underground water line to riser;
add an energy recovery ventilator
5 – Schedule extension (18 days)
6 thru 9 – Various changes due to
unforeseen site/field conditions, or
owner requested
10 thru 16 –Various structural,
electrical, HVAC & site work
Pending – Final change orders for
various revisions, upgrades, and
changes
$ 10,882
$4,330
$2,386
$10,080
$0
$29,505
$81,488
$91,010
Page 1 of 2 November 5, 2014
Project: Northside Library and Storage Facility
Description: Provide a permanent location for the Northside Library and long-term County warehouse/storage space
by repurposing an existing building located on property recently purchased at 705 Rio Road West
(formerly Phillips Building Supply). The new facility would provide approximately 30,000 square feet
of library space, and over 20,000 square feet of warehouse space. The Northside Library is currently
located in leased space at Albemarle Square, and the County warehouse/storage space is currently
located in leased space at the former Comdial building on Seminole Trail. The new facility will
eliminate the need for those two leased spaces.
Status: Construction work underway and approximately 55% complete as of September 2014. A construction
schedule extension of 40 calendar days is necessary to accommodate delays in construction over the
summer from unexpected site, building, and structural issues related to existing conditions. Substantial
completion is planned for February 2015. Because the new library will not be ready for occupancy by
January 2015, when the current library lease at the Albemarle Square location expires, a lease extension
through March 2015 is necessary.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Schematic design Complete 09/15/13 09/15/13 0
Design Complete 12/31/13 12/31/13 0
Bid Opening Date 01/31/14 02/12/14 12
Notice to Proceed 02/15/14 03/31/14 44
Demolition Complete 03/01/14 05/07/14 67
Site Work Complete 05/01/14 01/30/15 274
Substantial Completion:
Basement Storage Area 05/01/14 11/26/14 209
Library 09/30/14 02/24/15 147
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[May 2013]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 11,820,373 $ 11,843,740 $ (23,366)
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 11,820,373 $ 11,843,740 $ (23,366)
Use of Funds
Soft Costs $ 3,764,625 $ 4,221,247 $ (456,622)
Hard Costs $ 7,402,498 $ 7,475,489 $ (72,991)
Contingency $ 653,250 $ 147,004 $ 506,246
Total $ 11,820,373 $ 11,843,740 $ (23,367)
Balance = Funding - Costs $ - $ -
Encumbered: $ 3,427,538
Paid to Date: $ 7,547,408
A/E Contract (HB+M Architects) Construction Contract (Kenbridge Construction)
Original Agreement $736,500 Bid Award $6,773,500
Approved Changes $ 14,100 Approved Changes $ 169,891
Pending Changes $ 0 Pending Changes $ 29,932
TOTAL $750,600 TOTAL $6,973,323
A/E Change Orders:
Construction Change Orders:
No. & Brief Description Amount No. & Brief Description Amount
1 – Traffic & access analysis
2 – Extended bid phase
assistance
$ 3,450
$10,650
1 – Delete re-roofing scope; delete
sprinkler system standpipe
2 – Mezz duct frame, stair walls, VA
Power conduits
3 – Unilateral Change Order for steel
beam
4 – Various changes due to unforeseen
site/buiding conditions or Building Code
required; credit for deleting painting in
select basement areas
5 – Additional casework
6 thru 8 – Various changes due to
unforeseen site/building conditions,
owner requested or Building Code
required; credit for skylight changes
9 – Schedule extension General
Conditions cost
Pending – Additional changes due to
unforeseen site/buiding conditions
$(73,100)
$43,721
$75,000
$22,349
$43,000
$34,645
$24,276
$29,932
Page 1 of 2 November 5, 2014
Project: Regional Firearms Training Center
Description: Design and construction of a regional indoor firearms training facility, which includes a 50-yard
qualification range and 50-yard tactical range, 16 shooting lanes (original scope 20-24 shooting lanes),
classroom, office, bathrooms and storage areas (control platforms eliminated from original scope). The
range will be located on property owned by UVA on Milton Road.
Status: Total project cost estimate based on schematic drawings and refined project needs is approximately $6.8
Million. Conclusion of an 8/15/14 executive meeting with fiscal management staff from the County,
City, and UVA was an agreement to establish a not to exceed (NTE) total project budget of $6 Million.
Request for Board approval of additional funding to establish NTE budget scheduled for 11/5/14
meeting. Potential bid deductive alternates being identified/evaluated. Design Development plans
submitted and under review by project design team. Initial site plan meeting results in VDOT requiring
modifications to the entrance which could be $50k-$100k in additional costs.
Regional Operating Agreement and Ground Lease terms have been finalized by the partners. Request
for Board approval of agreement and lease terms scheduled for 11/5/14 meeting.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
A/E Procurement Complete 04/07/14 04/21/14 14
Pre-design Complete 05/26/14 07/10/14 45
Design Complete 09/29/14 12/17/14 79
Bid Opening Date 10/30/14 01/19/15 81
Notice to Proceed 11/27/14 02/16/15 81
Excavation Complete 0
Site Work Complete 0
Substantial Completion 08/25/15 11/25/15 92
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[January 2014]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 4,865,422 $ 4,865,422 $ -
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 4,865,422 $ 4,865,422 $ -
Use of Funds
Soft Costs $ 509,191 $ 670,992 $ (161,801)
Hard Costs $ 4,024,824 $ 5,890,504 $ (1,865,680)
Contingency $ 331,407 $ 279,457 $ 51,950
Total $ 4,865,422 * $ 6,840,953 $ (1,975,531)
Balance = Funding - Costs $ - $ (1,975,531)
Encumbered: $ 345,450
Paid to Date: $ 227,039
* Total project budget based on schematic design
A/E Contract (Clark Nexsen) Construction Contract
Original Agreement $514,137 Bid Award $
Approved Changes $ 42,276 Approved Changes $
Pending Changes $ 5,154 Pending Changes $
TOTAL $561,167 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 – Well and septic design and
analysis
$42,276
Pending – Tier 3 groundwater
assessment
$5,154
Date
Design / Soft
Costs
Construction
(including contingency) Total
Changes (Baseline -
Current Estimate) Scope Changes
Project Budget
Information Source
OUTDOOR RANGEBaseline Estimate Outdoor Range
(Original CP Budget)Feb-12 163,904.00$ 976,396.00$ 1,140,300.00$
Original CIP for Outdoor Range at old (closed) Keene Landfill, two 18
lane, 50 yd. rangesOriginal CIP
Revised Estimate Outdoor Range Nov-12 186,627.00$ 1,427,579.00$ 1,614,206.00$ 473,906.00$
Estimate revised to account for additional cost of road, further sound
study, wetlands, additional 100 yd. range. Note: Board stopped
outdoor range project at 6 Feb 2013 meeting.
Revised CIP
INDOOR RANGE
Indoor Range (Regional Firearms
Range Training Center) Baseline CIP
Estimate
Jan-14 509,191.00$ 4,356,231.00$ 4,865,422.00$
Re-start of Indoor Range Project, formally titled Region+A1al Firearms
Range Training Center. Joint partnership with the City of Charlottesville
and UVA to build and run an indoor Firing Range at UVA's Milton Site.
Project assumed 20-24 lanes, an administrative area for training,
storage and weapons cleaning and the site development. CIP estimates
were based upon Concrete Masonry Wall construction, concrete ceiling
and meeting noise ordinance at property line.
Revised CIP
Indoor Range (Regional Firearms
Range Training Center) Current
Project Estimate
Post Schematic Design Cost Estimate
Jul-14 670,992.00$ 6,169,961.00$ 6,840,953.00$ 1,975,531.00$
Post Schematic design estimate shows anticipated cost increases
related primarily to market costs increasing for construction and
material, change of construction material from CMU block to Concrete
Panels and a decision to fully enclose the HVAC units. The material
change and enclosing of the HVAC units will significantly reduce noise
and ensure maximum environmental projection. In order to moderate
the cost increases the scope of ranges have been reduced to 2, 8 lane
ranges with independent HVAC systems and a smaller footprint
attached Admin building. Conclusion of an 8/15/14 executive meeting
with fiscal management staff from the County, City, and UVA was an
agreement to establish a not to exceed (NTE) total project budget of $6
Million.
Executive Summary
REGIONAL FIREARMS RANGE TRAINING CENTER PROJECT BUDGET TRACKER
Page 1 of 2 November 5, 2014
Project: Church Road Basin Stormwater Management Facility Retrofit
Description: The Church Road Basin project includes maintenance and enhancements to the existing regional
stormwater management facility. The project scope includes survey, design, and construction. The
County is required (through the DCR-issued stormwater permit) to reduce pollutant discharges
(nitrogen, phosphorus and sediment) to impaired waters having approved TMDLs, or pollution diets.
This project will help the County meet required pollutant reductions mandated for the Cheasapeake Bay
watershed.
Status: Notice to Proceed issued 10/8/14 to North State Environmental. Work to commence 10/20/14. Work to be
substantially complete within 180 consecutive calendar days from the date of commencement, which is
4/18/15. This project is partially funded by a grant through the Department of Environmental Quality’s
(DEQ’s) Stormwater Local Assistance Fund, a new funding program for stormwater pollution reduction
efforts related to Total Maximum Daily Loads (TMDLs).
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Charrette Mtg 05/31/13 06/12/13 12
60%-design Complete 07/26/13 10/25/13 91
100% Design Complete 11/08/13 02/28/14 112
Project Out-to-bid 01/10/14 06/15/14 156
Bid Opening Date 02/28/14 07/21/14 143
Notice to Proceed 04/01/14 10/08/14 190
Substantial Completion 12/14/14 04/18/15 125
Grading Plan
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[April 2013]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 449,739 $ 426,919 $ 22,820
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 449,739 $ 426,919 $ 22,820
Use of Funds
Soft Costs $ 98,739 $ 101,181 $ (2,442)
Hard Costs $ 265,000 $ 298,491 $ (33,491)
Contingency $ 86,000 $ 27,247 $ 58,753
Total $ 449,739 $ 426,919 $ 22,820
Balance = Funding - Costs $ - $ -
Encumbered: $ 309,641
Paid to Date: $ 77,352
A/E Contract (Kimley-Horn & Associates) Construction Contract (North State Environmental)
Original Agreement $72,772 Bid Award $298,491
Approved Changes $ 2,310 Approved Changes $
Pending Changes $ Pending Changes $
TOTAL $75,082 TOTAL $298,491
A/E Change Order:
No. & Brief Description Amount
1 – Easement plat preparation &
grant application assistance
$2,310
Page 1 of 2 November 5, 2014
Project: Crozet Streetscape Enhancements Phase II
Phase 2 (Crozet Avenue) and 2A (Main Street and Alleys)
Description: Phase 2 and 2A of the Crozet Streetscape Enhancements includes relocation of overhead electric and
utility lines from Crozet Avenue, new stormwater drainage system, first block of Main Street (Library
Avenue), and pedestrian, vehicular, and streetscape enhancements along Crozet Avenue from The
Square to Tabor Street.
Status:
Phase 2 – Crozet Avenue:
Project web page maintained to provide project information and construction updates. Final asphalt,
concrete corrective work, and landscaping is complete. Installation of crosswalk pavers in progress and
nearing completion. Final pavement striping dependant on weather. Substantial completion is
contractually November 18th but is expected during the month of October.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 08/30/12 02/28/13 182
Right-of-Way / Easements Complete 08/30/12 07/31/13 335
VDOT Approval to Advertise 09/30/12 09/04/13 339
Utility Relocation Complete 10/30/12 10/25/13 360
Advertise 09/30/12 09/11/13 346
Bid Opening Date 10/30/12 10/16/13 351
VDOT "Authorize to Award" 11/30/12 11/13/13 348
Pre-construction Meeting 11/30/12 12/11/13 376
Sign Contract; Issue NTP 11/30/12 01/16/14 412
Community Meeting 11/30/12 12/03/13 368
Groundbreaking Ceremony 04/01/14 04/01/14 0
Ph-A Curb, Drainage & Sidewalk Complete 06/01/13 06/27/14 391
Ph-B Curb, Drainage & Sidewalk Complete 11/01/13 09/22/14 325
Paving Complete 12/01/13 10/03/14 306
Substantial Completion 01/30/14 11/18/14 292
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[March 2007]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 3,700,000 $ 4,539,014 $ (839,014)
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 3,700,000 $ 4,539,014 $ (839,014)
Use of Funds
Soft Costs $ 590,000 $ 955,131 $ (365,131)
Hard Costs $ 2,770,000 $ 3,578,575 $ (808,575)
Contingency $ 340,000 $ 5,308 $ 334,692
Total $ 3,700,000 $ 4,539,014 $ (839,014)
Balance = Funding - Costs $ - $ -
Encumbered: $ 290,967
Paid to Date: $ 4,218,867
A/E Contract (Kimley-Horn & Associates) Construction Contract (Ph 2A – Library Ave)
Original Agreement $379,000 Piedmont Concrete Contractors
Approved Changes $163,761 COMPLETE (FY11) $780,168
Pending Changes $0
TOTAL
A/E Change Orders:
$542,761 Construction Contract (Ph 2 – Crozet Ave)
Linco, Inc.
No. & Brief Description Amount
1 – Jarmans Gap Road interim storm
system & historic resources (FY09)
$41,500
2 – Additional plats & transportation
planning services (FY09)
$12,625
3 – Main Street extension to proposed
Library entrance (FY09)
$24,000
4 – Conceptual Downtown Plaza
improvements (FY09)
$ 9,750
5 – Additional plats (FY10) $ 2,750
6 – Temporary tie-in of new Main
Street (FY10)
$21,000
7 – Water & sewer relocation design
(FY10)
$ 7,300
8 – Library storm sewer advance work
(FY12)
$ 5,961
9 – Finalize const. documents (FY13) $38,875
Bid Award $1,474,350
Approved Changes $ 75,408
Pending Changes $ 2,773
TOTAL $1,552,531
Construction Change Orders:
No. & Brief Description Amount
1 – Retaining wall construction;
storm piping changes
$17,248
2 – Bio-filter modifications;
drainage structure corrections; tree
removal; striping
$32,217
3 – Bio-filter curb plates; various
changes/corrections at various
properties
$25,944
4 – Various changes due to
unforeseen site/field conditions,
unused allowance credit
$2,773
Page 1 of 2 November 5, 2014
Project: Crozet Elementary School Safe Routes to School Sidewalk Project
Description: Provide improved walking and bicycling routes to Crozet Elementary School for students from residential
neighborhoods by constructing curb and sidewalk on the west side of Crozet Avenue from Ballard Drive to
the school. The improvements also include installation of a manually activated crosswalk warning system at
the pedestrian crossing to the school. This project is partially funded by a VDOT Safe Routes to School
grant. A separate Revenue Sharing project extends the sidewalk from Crozet School to Saint George
Avenue.
Status: Additional appropriation (proffer revenue) approved by Board on October 1, 2014, to fully fund construction.
Plan redesign complete and revised plans submitted to VDOT for approval. Obtain VDOT approval of revised
final plans and authorization to advertise - target 4th quarter 2014; approximately 3 months construction. Staff
and the contractor will evaluate whether to start construction over the winter or delay until early spring
depending on weather conditions.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 04/30/12 02/20/13 296
Right-of-Way / Easements Complete 05/31/12 12/30/12 213
VDOT Approval to Advertise 06/30/12 07/30/13 395
Bid Opening Date 08/15/12 10/28/13 439
Re-advertise Project 01/08/14 10/21/14 286
Notice to Proceed / VDOT Approval of Contract
( * ) 09/15/12 12/20/14
826
Waterline Relocation Complete 04/15/14 06/15/14 61
Curb/Drainage Complete ( * ) 11/15/12 01/30/15 806
Sidewalks Complete ( * ) 11/30/12 02/15/15 807
Paving Complete ( * ) 12/15/12 02/28/15 805
Substantial Completion ( * ) 12/15/12 02/28/15 805
* Staff and the contractor will evaluate when to start construction which could occur as soon as
December or may be delayed until early spring at the latest, depending on weather.
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[January 2012]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 190,000 $ 190,000 $ -
Future Appropriations $ - $ 103,000
$
(103,000)
Additional Source $ - $ - $ -
Total $ 190,000 $ 293,000 $ (103,000)
Use of Funds
Soft Costs $ 43,300 $ 88,432 $ (45,132)
Hard Costs $ 134,500 $ 186,025 $ (51,525)
Contingency $ 12,200 $ 18,544 $ (6,344)
Total $ 190,000 $ 293,000 $ (103,000)
Balance = Funding - Costs $ - $ -
Encumbered: $ 15,368
Paid to Date: $ 40,064
A/E Contract (Anhold Associates)
Original Agreement $20,697
Approved Changes $15,325
Pending Changes $ 0
TOTAL $36,022
A/E Change Orders:
No. & Brief Description Amount
1 – Prepare documents to relocate
existing waterline conflicting with
proposed stormwater utilities
$2,524
2 – Redesign plans and construction
documents
$12,801
Construction Contract
Bid Award $
Approved Changes $
Pending Changes $
TOTAL $
Page 1 of 2 November 5, 2014
Project: Crozet North Sidewalk
Description: Provide for pedestrian safety by replacing or constructing approximately 1100 feet of sidewalk and drainage
improvements along the west side of Crozet Avenue from Saint George Avenue to Crozet Elementary
School. This project is partially funded with Revenue Sharing funds. A separate Safe Routes to School
(SRTS) Grant project provides improved pedestrian crossing at the school and extends sidewalk to Ballard
Drive.
Status: Board approved right-of-way and easement acquisitions on September 3, 2014. County Attorney’s office is
finalizing deed. Obtain VDOT approval of Final Plans & Project Manual and authorization to advertise - target
4th quarter 2014; approximately 6 months construction. This project and the South Pantops/State Farm
Boulevard Sidewalk Improvement Project are considered “one project” by VDOT under the FY13 Revenue
Sharing award so the two projects must be bid and awarded as a single project. Required VDOT approvals
(design, right-of-way, authorization to advertise) for both projects are necessary before the project can be bid.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 02/14/13 02/28/14 379
Right-of-Way / Easements Complete 03/15/13 09/30/14 564
VDOT Approval to Advertise 04/15/13 10/30/14 563
Bid Opening Date 05/31/13 12/15/14 563
Notice to Proceed / VDOT Approval of Contract 06/30/13 01/10/15 559
Curb & Drainage Complete 08/31/13 04/01/15 578
Sidewalks Complete 09/30/13 05/30/15 607
Paving Complete 10/15/13 06/20/15 613
Substantial Completion 10/15/13 06/30/15 623
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 661,400 $ 815,878 $ (154,478)
Future Appropriations * $ - $ (60,000) $ 60,000
Additional Source $ - $ - $ -
Total $ 661,400 $ 755,878 $ (94,478)
Use of Funds
Soft Costs $ 104,200 $ 268,526 $ (164,326)
Hard Costs $ 497,200 $ 424,674 $ 72,526
Contingency $ 60,000 $ 62,678 $ (2,678)
Total $ 661,400 $ 755,878 $ (94,478)
Balance = Funding - Costs $ - $ -
Encumbered: $ 10,178
Paid to Date: $ 128,424
* Future transfer to South Pantops Drive/Sate Farm Boulevard revenue sharing sidewalk project
A/E Contract (Kimley-Horn & Assoc.) Construction Contract Original Agreement $40,000 Bid Award $
Approved Changes $ 1,600 Approved Changes $
Additional Agreement $31,596 Pending Changes $
TOTAL $73,196 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 - Eliminate bid/construction
observation; add plats & final
engineering services.
Additional Agreement: Waterline
relocation design, right-of-way
acquisition and construction phase
services.
$ 1,600
$31,596
Page 1 of 2 November 5, 2014
Project: South Pantops Drive/State Farm Boulevard Sidewalk Improvements
Description: Provide for pedestrian safety along the north side of South Pantops Drive and west side of State Farm
Boulevard by constructing 3500 feet of curb, gutter and sidewalk which will serve several residential,
business, and commercial establishments. Construction will be partially funded with FY13 Revenue
Sharing Funds.
Status: Appraisals approximately 90% and consultant preparing determinations of just compensation. Board approval
of acquisitions is required. Obtain VDOT approval of Final Plans & Project Manual and authorization to
advertise - target 4rd quarter 2014; approximately 6 months construction. This project and the Crozet Avenue
North Sidewalk Improvement Project are considered “one project” by VDOT under the FY13 Revenue Sharing
award so the two projects must be bid and awarded as a single project. Required VDOT approvals (design,
right-of-way, authorization to advertise) for both projects is necessary before the project can be bid.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 12/31/12 10/01/13 274
Right-of-Way / Easements Complete 03/15/13 9/30/2014 564
VDOT Approval to Advertise 04/15/13 10/30/2014 563
Bid Opening Date 06/01/13 12/15/2014 562
Notice to Proceed / VDOT Approval of
Contract 07/01/13 1/10/2015 558
Curb & Drainage Complete 09/01/13 4/1/2015 577
Sidewalks Complete 10/01/13 5/30/2015 606
Paving Complete 10/15/13 6/20/2015 613
Substantial Completion 10/31/13 6/30/2015 607
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[July 2008]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 512,000 $ 959,408 $ (447,408)
Future Appropriations * $ - $ 60,000 $ (60,000)
Additional Source $ - $ - $ -
Total $ 512,000 $ 1,019,408 $ (507,408)
Use of Funds
Soft Costs $ 60,000 $ 313,343 $ (253,343)
Hard Costs $ 410,000 $ 645,424 $ (235,424)
Contingency $ 42,000 $ 60,641 $ (18,641)
Total $ 512,000 $ 1,019,408 $ (507,408)
Balance = Funding - Costs $ - $ -
Encumbered: $ 18,906
Paid to Date: $ 138,274
* Future transfer from Crozet Ave North revenue sharing sidewalk project.
A/E Contract (Kimley-Horn & Associates) Construction Contract Original Agreement $ 39,116 Bid Award $
Approved Changes $ 9,369 Approved Changes $
Additional Agreement $ 49,595 Pending Changes $
Approved Changes $ 22,088 TOTAL $
TOTAL $120,168
A/E Change Orders (Original Agreement):
No. & Brief Description Amount
1 – Update survey (FY09) $ 600
2 – Additional survey (FY09) $ 6,950
3 – Add topo survey, plats & final
engineering; eliminate bidding/
construction observation (FY12)
$ 1,819
A/E Change Orders (Additional Agreement): No. & Brief Description Amount
1 – Temporary easement plats $8,888
2 – Additional right-of-way and
easement acquisition services
$13,200
Page 1 of 2 November 5, 2014
Project: Hydraulic Road and Barracks Road Sidewalk Improvements
Description: Provide for pedestrian safety by making sidewalks improvements along Hydraulic Road and Barracks
Road. The Hydraulic Road sidewalk improvement involves the construction of approximately 1700 feet
of sidewalk on the north side of Hydraulic Road between approximately 300 feet east of Commonwealth
Drive and Georgetown Road. The Barracks Road sidewalk improvement involves: 1) the construction of
approximately 1000 feet of sidewalk from the Barracks West apartments on the north side of Barracks
Road to the existing sidewalk west of the Georgetown Road intersection; and 2) the construction of
crosswalks and two segments of sidewalk (650 ft total) on the south side of Barracks Road between the
Georgetown Road intersection and Westminster Road, and between S. Bennington Road and the 29/250
Bypass ramps. This project is partially funded with FY13 and FY15 Revenue Sharing Program funds.
Status: Survey for both projects is complete and design plans are currently in progress. Two burial sites were
found during the survey process; a sub-consultant has been authorized to verify the limits of the sites.
Once confirmed, construction impacts will be ascertained, if any. Public engagement meeting to seek
public input on project will be held as soon as possible after the burial site impacts have been
determined.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Pre-design Complete 10/01/14 10/01/14 0
Design Complete 05/01/15 05/01/15 0
Bid Opening Date 06/01/15 06/01/15 0
Notice to Proceed 07/01/15 07/01/15 0
Right-of-Way / Easements Complete 04/01/15 04/01/15 0
Substantial Completion 12/01/15 12/01/15 0
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[January 2014]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 1,588,600 $ 1,588,600 $ -
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 1,588,600 $ 1,588,600 $ -
Use of Funds
Soft Costs $ 617,600 $ 624,020 $ (6,420)
Hard Costs $ 873,900 $ 873,900 $ -
Contingency $ 97,100 $ 90,680 $ 6,420
Total $ 1,588,600 $ 1,588,600 $ 0
Balance = Funding - Costs $ - $ 0
Encumbered: $ 196,374
Paid to Date: $ 148,067
A/E Contract (Kimley-Horn Construction Contract
Original Agreement $323,256 Bid Award $
Approved Changes $ 13,164 Approved Changes $
Pending Changes $ Pending Changes $
TOTAL $336,420 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 – Assist support public meeting
process
$13,164
Page 1 of 2 November 5, 2014
Project: Agnor-Hurt Elementary Additions & Renovations
Description: Construction of an 11,200 sq. ft. addition consisting of seven (7) classrooms, one (1) full-sized SPED
classroom, faculty workroom, offices and associated support spaces. Renovations of 3,500 sq. ft. consist
of security improvements at front entrance, upgrades to media center, and addition of air conditioning to
the kitchen. Replacement of existing chiller, exhaust fans, roof top units and boilers. Site improvements
include additional parking and modifications to student drop-off areas.
Status: Construction to be completed incrementally in four successive Phases. Phase I construction (site work
for new road and bus loop and relocated playgrounds) substantially complete. Phase II construction
(complete new entrance, bus loop, cooling tower - structure & relocation, begin classroom addition,
underground utilities relocation) underway with substantial completion planned for December 2014.
Extremely low contingency to start project; current contingency includes future anticipated
changes/work including removal of more unsuitable school than anticipated. Schools have been notified
of contingency concern.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Schematics Complete 11/14/13 11/14/13 0
Construction Docs Complete 03/31/14 04/02/14 2
Bid Opening Date 04/30/14 05/08/14 8
Notice to Proceed 06/05/14 06/18/14 13
Start Construction 06/16/14 06/19/14 3
Phase 1 - Start 06/16/14 06/19/14 3
Phase 1 - Finish 08/18/14 08/18/14 0
Phase 2 - Start 08/19/14 08/19/14 0
Phase 2 - Finish 11/26/14 12/19/14 23
Phase 3 - Start 12/20/14 12/20/14 0
Phase 3 - Finish 06/12/15 06/12/15 0
Phase 4 - Start 06/13/15 06/13/15 0
Phase 4 - Finish 08/01/15 08/01/15 0
Substantial Completion 08/01/15 08/01/15 0
Final Completion 09/01/15 09/01/15 0
Page 2 of 2 November 5, 2014
Project Budget:
Baseline
[January 2014]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 5,868,285 $ 5,930,503 $ (62,218)
Future Appropriations $ 37,782 $ (37,782)
Additional Source $ - $ - $ -
Total $ 5,868,285 $ 5,968,285 $ (100,000)
Use of Funds
Soft Costs $ 616,772 $ 588,062 $ 28,710
Hard Costs $ 4,913,694 $ 5,327,722 $ (414,028)
Contingency $ 337,819 $ 52,501 $ 285,318
Total $ 5,868,285 $ 5,968,285 $ (100,000)
Balance = Funding - Costs $ - $ - $ -
Encumbered: $ 4,486,057
Paid to Date: $ 915,102
Appropriation includes schools maintenance money for HVAC, paving. Future appropriation represents
estimate of reallocation of project management services from maintenance account.
A/E Contract (SHW Group) Construction Contract (Haley Builders)
Original Agreement $400,500 Bid Award $4,947,000
Approved Changes $ Approved Changes $
Pending Changes $ 10,000 Pending Changes $ 75,622
TOTAL $410,500 TOTAL $5,022,622
A/E Change Orders:
No. & Brief Description Amount
Pending – Rework utility
relocations in courtyard; site plan
revisions
$10,000
Construction Change Orders:
No. & Brief Description Amount
Pending – Additional
unsuitable soil removal;
various changes/revisions
$75,622
Project Vendor Contract Type Amount CO No. Scope
Date Approved
by CE Office
Reason:
>25% or >$50K
Southern Albemarle Convenience Center Site
Due Diligence (Keene & Mill Creek
Properties)
Draper Aden Associates Planning $5,885.50 1Reconciliation of expenses incurred to perform due
diligence on Keene and Mill Creek sites as directed by
the Board.
04/23/14 >25%
Northside Library and Storage Facility Kenbridge Consruction Construction $75,000.00 1
Unilateral Change Order - Add steel beam at central
column line per Architect’s Bulletin #14 (final cost to
be based on time and materials, Not-To-Exceed
$75,000.)
07/23/14 >$50k
Crozet Streetscape Phase II A. Morton Thomas & AssociatesConstruction
Inspection$35,211.92 1
Inspection services to allow full-time inspection on
VDOT Revenue Sharing project for the duration of the
project.
08/28/14 >25%
State Farm Boulevard and South Pantops
Drive SidewalkKimley-Horn & Associates Design $13,200.00 2
Additional services required to secure right-of-way
and temporary construction easements09/03/14 >25%
Crozet Elementary School SRTS Sidewalk and
Crossing ImprovementsAnhold Associates Design $12,801.00 2
Prepare re-design of plans and construction document
to reduce construction costs09/15/14 >25%
Change Orders Requiring County Executive Office Approval
January 2014 - September 2014