of the board of inquiry into the - epa · 2019. 4. 6. · hearing dated 19 january 2014 (exhibit...

390
Draft Report and Decision of the Board of Inquiry into the Tukituki Catchment Proposal Volume 2 of 3: Appendices Produced under Section 149Q of the Resource Management Act 1991

Upload: others

Post on 14-Mar-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Draft Report and Decision of the Board of Inquiry into the

    Tukituki Catchment Proposal

    Volume 2 of 3: Appendices

    Produced under Section 149Q of the Resource Management Act 1991

  • Published by the Board of Inquiry into the Tukituki Catchment Proposal

    Dated: April 2014

  • Contents

    Appendix 1: Appearances during the hearing

    Appendix 2: Alphabetical listing of technical reports supporting Plan Change 6 and the Ruataniwha Water Storage Scheme

    Appendix 3: Board’s decisions on the matters raised in the submissions and further submissions concerning Plan Change 6

    Appendix 4: Clean copy of Plan Change 6 as the end of the Tukituki Catchment Proposal Hearing dated 19 January 2014 (Exhibit 90)

    Appendix 5: Plan Change 6 final (track changed version) as determined by the Board of Inquiry dated April 2014

    Appendix 6: The matters applied for from Hawke’s Bay Regional Council and Hawke’s Bay Regional Investment Company

  • Appendix 1

    Appearances during the hearing

  • Name of Representative Party Helen Codlin The applicants Iain Maxwell The applicants Graeme Hansen The applicants Benita Waina Wakefield The applicants Tim Sharp The applicants Husam Baalousha The applicants Robert Waldron The applicants Paul Barrett The applicants David Wheeler The applicants Richard McDowell The applicants David Wheeler The applicants Ian Millner The applicants John Hayes The applicants Anna Madarasz-Smith The applicants Chris Cornelisen The applicants Robert John Wilcock The applicants Vaughan Keesing The applicants Gerry Kessels The applicants Stuart Parsons The applicants John Craig The applicants Tim Fisher The applicants James Christopher (Kit) Rutherford

    The applicants

    Roger Young The applicants Gavin Lister The applicants Adam Uytendaal The applicants Olivier Ausseil The applicants Simon Harris The applicants Simon Bickler The applicants Rob van Voorthuysen The applicants Michelle Frey The applicants Mark Chrisp The applicants Stephen Daysh The applicants Andy Borland Mr Apple NZ Limited Richard Hill Mr Apple NZ Limited John Wilton Mr Apple NZ Limited John Bright Mr Apple NZ Limited Richard Peterson Mr Apple NZ Limited David Renouf Hawke’s Bay Environmental Water Group Lindsay Smith Ingleton Farms Ltd Ella Bacher Ingleton Farms Ltd and Bel Group Ltd John M Bostock JM Bostock Ltd Greg Sneath Fertiliser Association of New Zealand John Bright Ruataniwha Water Users Group and Mr Apple NZ Limited Julian Weir Ruataniwha Water Users Group

  • Name of Representative Party Ian McIndoe Mr Apple NZ Limited and Ruataniwha Water Users Group Andrew Bashford Ruataniwha Water Users Group Jeremy David Dunningham Jeremy David Dunningham Mike Peterson Beef and Lamb NZ Alec Mackay Beef and Lamb NZ

    Sylvia Allan Central Hawke’s Bay District Council and Hastings District Council Stephen Thrush Central Hawke’s Bay District Council

    Mike Joy Royal Forest and Bird Protection Society of New Zealand, Hawke’s Bay Environmental Water Group and Ngati Kahungunu Iwi

    Vaughan Cooper Royal Forest and Bird Protection Society — Hastings/Havelock North Branch

    Dan Elderkamp Royal Forest and Bird Protection Society — Central Hawke’s Bay Branch Stuart Ford Horticulture NZ and others Kelvin Lloyd Te Taiao Hawke’s Bay Environmental Forum John Cheyne Te Taiao Hawke’s Bay Environmental Forum Christopher Keenan Horticulture NZ and others Philip Jordan Horticulture NZ and others Tim Baker Horticulture NZ and others Kolt Johnson Horticulture NZ and others Hamish Peacock Horticulture NZ and others Peter Reaburn Environmental Defence Society Marie Brown Environmental Defence Society Kate McArthur Environmental Defence Society David Wansbrough Ministry for Primary Industries Hamish McHardy Arden Properties, Tukituki Ltd David Werrey David Werrey Brian Chambers Brian Chambers June Graham June Graham Nicholas Jones Hawke’s Bay District Health Board Xan Harding Harding Family Trust Xan Harding Hawke’s Bay Winegrowers Association Tim Aitken Steyning Deer Farm Sharleen Baird Sharleen Baird Christie Grenville Christie Grenville Patrick Kane Patrick Kane Arthur Rowlands Katoa Farm Ltd Roger Maaka Te Taiwhenua o Tamatea Jonathon Abell Hawke’s Bay and Eastern Fish and Game Council Peter McIntosh Hawke’s Bay and Eastern Fish and Game Council Russell Death Hawke’s Bay and Eastern Fish and Game Council

    Dennis Page Federated Mountain Clubs of NZ Inc Gilbert Zemansky Hawke’s Bay and Eastern Fish and Game Council Anthony Rhodes Hawke’s Bay and Eastern Fish and Game Council Alison Dewes Hawke’s Bay and Eastern Fish and Game Council

  • Name of Representative Party James Aitken James Aitken Richard and Helen Ellis Papawai Partnership Helen Marr Hawke’s Bay and Eastern Fish and Game Council Phillip Percy Hawke’s Bay and Eastern Fish and Game Council Gerard Pain Gerard Pain Adrienne Tully Adrienne Tully Quentin M Bennett Quentin M Bennett Daniel Stabler Daniel Stabler Phyliss Tichinin Phyllis Tichinin Lisa Poynton and Brent Oliver Brownrigg Agriculture Group Ltd

    Andrew Curtis Irrigation NZ Corina Jordan Hawke’s Bay and Eastern Fish and Game Council Megan Rose Megan Rose Robert Buchanan Buchanan Trust No 2 (Robert Buchanan) William Buchanan William Buchanan Larry Dallimore Larry Dallimore Richard Lawson Hawke’s Bay Deer Farmers Association Tim Aitken Hawke’s Bay Deer Farmers Association Grant Charteris Hawke’s Bay Deer Farmers Association Duncan Holden Hawke’s Bay Deer Farmers Association Richard Hilson Hawke’s Bay Deer Farmers Association Paula Fern Paula Fern Angus Robson Angus Robson Craig Preston Craig Preston Trust Paul Bailey Paul Bailey Ngapuoterangi Hohepa Koro Te Whaiti Ngapuoterangi Hohepa Koro Te Whaiti

    Amelia McQueen Amelia McQueen Christopher Perley Christopher Perley Garth Eyles Garth Eyles Ian McIntosh Ian McIntosh Sara Gerard Gerard Land Design Moana Jackson Ngāti Kahungunu Iwi Incorporated and others Tom Mulligan Ngāti Kahungunu Iwi Incorporated and others Bayden Barber Ngāti Kahungunu Iwi Incorporated and others Margie McGuire Ngāti Kahungunu Iwi Incorporated and others Te Kipa Kepa Morgan Ngāti Kahungunu Iwi Incorporated and others Hira Huata Ngāti Kahungunu Iwi Incorporated and others Ngatai Huata Ngāti Kahungunu Iwi Incorporated and others Shade Smith Ngāti Kahungunu Iwi Incorporated and others Maurice Black Ngāti Kahungunu Iwi Incorporated and others Marei Apatu Ngāti Kahungunu Iwi Incorporated and others Adele Whyte Ngāti Kahungunu Iwi Incorporated and others Rawiri Johnston Rawiri Johnston Christine Cheyne Christine Cheyne

  • Name of Representative Party Eugenie Sage Eugenie Sage Roy Boonen Roy Boonen Ann Redstone Walking on Water (WOW) Inc Mark Lawrence Mark Lawrence Alison Johnstone Silver Fern Farms Ltd Jeremy Absolom Silver Fern Farms Ltd Terry Kelly Sustaining Hawke's Bay Trust/Terry Kelly Warwick Catto Ballance Agri-Nutrients Thomas Belford Transparent Hawke’s Bay Pauline Elliot Pauline Elliot Adrian Mannering Mannering Family Trust Colin Riden Colin Riden

  • Appendix 2

    Alphabetical listing of technical reports supporting Plan Change 6 and the Ruataniwha Water Storage

    Scheme

  • Plan Change 6: Alphabetical listing of technical reports

    Report name Folder No. Section

    Baalousha, H. (2010). Ruataniwha Basin Transient Groundwater

    — Surface Water Flow Model. Internal report prepared for

    Hawke's Bay Regional Council. HBRC Plan no. 4234: 112 pp.

    3 Surface and

    Groundwater

    Quantity

    Baalousha, H. (2011). Ruataniwha Basin Groundwater/ Surface

    Water Predictive Modelling. Internal report prepared for Hawke's

    Bay Regional Council. HBRC Plan no. 4264. EMT 11/04. 27 pp.

    3 Surface and

    Groundwater

    Quantity

    Barrett, P. (2013). Tukituki River Catchment and Ruataniwha

    Basin: Consented Water Allocation. Internal report prepared for

    Hawke's Bay Regional Council. HBRC Plan no. 4411. EMT

    12/21. 42 pp.

    5 Surface and

    Groundwater Use

    and Allocation

    Benson, M., L. Coubrough, I. Millner and R. van Voorthuysen

    (2012). Nutrient Management Approaches for the Tukituki

    Catchment. Internal report prepared for Hawke's Bay Regional

    Council. HBRC Plan no. 4344. WI 12/05. 40 pp.

    5 Land

    Buchanan, F. (2011). Estimating Permitted Water Use in

    Hawke’s Bay, HBRC Plan no 4355.

    5 Surface and

    Groundwater Use

    and Allocation

    Cameron, F. (2012). Identifying native fish values. Internal

    report prepared for HBRC.

    2 Values

    Hawke's Bay Regional Council. HBRC Plan no. 4303.

    EMT12/01. 50 pp.

    Codlin, H. (2013). Tukituki Catchment: Freshwater

    Management Objectives. Internal Report Prepared for Hawke's

    Bay Regional Council. HBRC Plan no. 4407. SD

    2 Values

    Gordon, D. (2013). Ruataniwha groundwater quality: state and

    trends. Internal report prepared for Hawke's Bay Regional

    Council. HBRC Plan no. 4399. EMT12/14.

    5 Groundwater

    Harkness (2009). Flow Naturalisation for Six Hawke's Bay

    Catchments: Tutaekuri, Ngaruroro, Waipawa, Tukipo, Tukituki

    and Maraetotara. MWH client report prepared for HBRC.

    3 Surface and

    Groundwater

    Quantity

    Harper, S. (2013). Tukituki Catchment Groundwater Resources.

    Internal report prepared for Hawke’s Bay Regional Council.

    HBRC Plan no. 4452.

    3 Surface and

    Groundwater

    Quantity

  • Report name Folder No. Section

    Harris Consulting Ltd. (2012). Economic Impacts of Future

    Scenarios for the Tukituki River. Report prepared for HBRC

    5 Economic

    Harris Consulting Ltd. (2013). Tukituki River Catchment:

    Economic Impact of Minimum flow on existing Irrigators

    5 Economic

    Assessments

    Harris Consulting Ltd (2013). Economic Impact of Future

    Nutrient Reduction Scenarios for the Tukituki River. Addendum

    to Tukituki Choices: Economic Impact of Future Scenarios for

    the Tukituki River. Contract report prepared for Hawke's Bay

    Regional Council. February 2013

    5 Economic

    Assessments

    Hayes, J. (2012). Review of water allocation limits in the Tukituki

    River: hydrological and ecological concepts. Cawthron client

    letter report prepared for HBRC.

    5 Surface and

    Groundwater Use

    and Allocation

    Heath, N. (2013). Tukituki Catchment Implementation Plan.

    Internal report prepared for Hawke's Bay Regional Council,

    HBRC Plan no.4453.

    1 Plan Documents

    Hickey, C. W. (2013). Site-specific nitrate guidelines for Hawke’s

    Bay. NIWA client report prepared for Hawke’s Bay Regional

    Council for project HBR12235. HAM2012-127. 21pp.

    4 Surface Water

    Quality

    HBRC. (2013). Tukituki River Catchment - Likely implications of

    proposed nutrient management strategy on growth of

    Phormidium spp. Summary of Technical Workshop held 20

    December 2012. Prepared by Aquanet Consulting Ltd for HBRC.

    HBRC Plan no. 4461. EMT 13/03. 33 pp.

    4 Surface water Quality

    HBRC. (2013). Tukituki River Catchment - Managing Nuisance

    Growth Using Nutrient Limits. Summary of Technical Workshop

    held 19 December 2012. Prepared by Aquanet Consulting Ltd

    for HBRC. HBRC plan No. 4460. EMT 13/02. 33 pp.

    4 Surface water Quality

    Johnson, K. (2011). Tukituki Catchment Instream Flow

    Assessment. Internal report prepared for Hawke's Bay Regional

    Council. HBRC Plan no. 4248. EMT 10/36. 68 pp.

    3 Surface and

    Groundwater

    Quantity

    Lynch, B et al. (2013). Papanui Catchment: An environmental

    characterisation. Internal report prepared for Hawke's Bay

    Regional Council. HBRC Plan no. 4372. EMT 12/11. 60 pp.

    5 Land

    Lynch, B. (2013). Tukituki Catchment: Estimating Nutrient Loss.

    Internal report prepared for Hawke's Bay Regional Council.

    HBRC Plan no. 4406. EMT12/19. 25 pp.

    5 Land

  • Report name Folder No. Section

    Page Bloomer Associates (2012). Hawke’s Bay Water Demand

    2050. Client report prepared for Hawke’s Bay Regional Council.

    5 Surface and

    Groundwater Use

    and Allocation

    Reed, C. (2013). Tukituki Catchment Plan Change:

    alignment with LAWF3 recommendations, Internal

    Memorandum.

    2 General

    Rutherford, J. (2011). Computer Modelling of Nutrient Dynamics

    and Periphyton Biomass – Model Development, Calibration and

    Testing in the Tukituki River. NIWA Client report prepared for

    HBRC and CHBDC.

    4 Surface Water

    Quality

    Sharp, T. (2012). Tukituki catchment freshwater values

    assessment. Internal report prepared for Hawke's Bay Regional

    Council. HBRC Plan no. 4327. SD12/03.

    2 Values

    Unwin, M. (2012). The Tukituki River trout fishery — a

    significance assessment of the river and its catchment. NIWA

    client report prepared for Hawke's Bay Regional Council.

    2 Values

    Uytendaal, A. and Ausseil, O. (2013). Tukituki Catchment

    Recommended Water Quality Limits and Targets for Tukituki

    Plan Change 6. Internal report prepared for Hawke's Bay

    Regional Council. HBRC Plan no. 4463. EMT13/04.

    4 Surface Water

    Quality

    Wakefield, B., M. Hape, J. Maaka, B. Wakefield, H. Maaka, M.

    Apatu, D. Moffatt and D. Whitiwhiti (2012). Tukituki River

    Catchment Values and Uses. Client report prepared by Te

    Taiwhenua O Tamatea and Te Taiwhenua o Heretaunga for

    Hawke's Bay Regional Council. 92 pp.

    2 Values

    Waldron, R. (2011). Tukituki River Catchment High Flow

    Allocation Modelling. Internal report prepared for Hawke's Bay

    Regional Council. HBRC Plan no. 4258. EMT 11/02. 119 pp.

    3 Surface and

    Groundwater

    Quantity

    Waldron, R. (2012a). Tukituki Catchment Allocation Scenario

    Modelling. Internal memo prepared for HBRC.

    5 Surface and

    Groundwater Use

    and Allocation

    Waldron, R. (2012b). Tukituki Catchment Instream Assessment.

    Internal Addendum Report prepared for HBRC. HBRC Plan no.

    4363. EMT 12/10. 14pp.

    3 Surface and

    Groundwater Use

    and Allocation

    Waldron, R. (2013a). Tukituki Catchment: Modelling the

    Impacts of Groundwater and Surface Water Abstraction.

    3 Surface and

    Groundwater Use

  • Report name Folder No. Section

    Internal report prepared for HBRC. HBRC Plan no. 4410.

    EMT12/20. 58 pp.

    and Allocation

    Waldron, R. (2013b). Tukituki Catchment potential minimum

    flows and minimum flows. Internal memo prepared for Hawke's

    Bay Regional Council. 10 pp.

    3 Surface and

    Groundwater

    Quantity

    Wilding, T. and R. Waldron (2012). Hydrology of the Tukituki

    Catchment. Internal report prepared for Hawke's Bay Regional

    Council. HBRC Plan no. 4405. EMT 12/18. 77pp

    3 Surface and

    Groundwater

    Quantity

    Ruataniwha Water Storage Scheme: Alphabetical listing of technical reports

    Report Name Folder No. Section

    Ausseil, O., Hansford, J., Waldron, R., and Young, R. (2013).

    Ruataniwha Water Storage Scheme Environmental Flow

    Optimisation. Report prepared for HBRIC Ltd.

    3 K4 — Environmental

    Flow Optimisation

    Baalousha, H. (2013). Ruataniwha Basin Nitrate Transport

    Modelling. Report prepared by Resource Management Group for

    HBRIC Ltd.

    4 M5 — Groundwater

    Drinking Water

    Modelling

    Baines, T. (2013). Ruataniwha Water Storage Scheme: Social

    Impact Assessment. Prepared by Taylor Baines and Associates

    for HBRIC Ltd.

    6 A6 — Social Impact

    Assessment

    Bickler, S., and Clough, R. (2013). Ruataniwha Water Storage

    Scheme: Archaeological Assessment. Report prepared for

    HBRIC Ltd.

    6 A8 — Archaeological

    Assessment

    Butcher Partners Ltd. (2013). Regional Economic Impacts and

    Financial Cost benefit Analysis of the Proposed Ruataniwha

    Water Storage Scheme. Prepared for HBRIC Ltd.

    6 A7 — Regional

    Economic Impact

    Assessment

    Coubrough, L. (2013). Proposed Integrated Mitigation and Offset

    Approach (Final). Report prepared for HBRIC Ltd.

    3 K6 — Integrated

    Mitigation & Offset

    Approach

    Environmental Management Services Limited. (2013). Zone M

    Primary Distribution Concept. Report prepared for HBRIC Ltd.

    3 K2 — Zone M

    Headrace Concept

    Environmental Management Services Limited. (2013).

    Ruataniwha Water Storage Scheme Planning Assessment

    5 A1 — Planning

  • Report Name Folder No. Section

    (Final). Report prepared for HBRIC Ltd. Assessment

    Gibbs, M. (2013). Characterisation of Makaroro reservoir water

    quality. Report prepared by NIWA for HBRIC Ltd.

    5 A2 — Reservoir

    Water Quality

    Goodier, C. (2013). Ruataniwha Water Storage Scheme: Dam

    Break Analysis. Report prepared by HBRC for HBRIC Ltd.

    7 A13 — Dam Break

    Analysis

    Halstead, M. (2013). Ruataniwha Water Storage Scheme Noise

    Effects Assessment. Report prepared by Marshall Day Acoustics

    for HBRIC.

    7 A11 — Noise

    Assessment

    HBRIC. (2013). Ruataniwha Water Storage Scheme —

    Assessment of Environmental Effects.

    2 C — Assessment of

    Environmental

    Effects

    HBRIC. (2013). Ruataniwha Water Storage Scheme —

    Proposed Conditions.

    2 D — Proposed

    Conditions

    HBRIC. (2013). Irrigation Environmental Management Plan

    (Draft).

    3 K5 — IEMP

    (Irrigation

    Environmental

    Management Plan)

    Kessels, G., Deichmann, B., Stewart, P., Hasenbank, M.,

    Riddell, D., Clark, R., and Brandes, U. (2013). Terrestrial

    Ecology Study — Assessment of Ecological Effects. Prepared

    by Kessels & Associates for HBRIC Ltd.

    6 A4 — Terrestrial

    Ecology Assessment

    Landon-Lane, R., Uran, N., and Jones, A. (2013). Road

    Infrastructure & Traffic Assessment. Report prepared by Opus

    International Consultants for HBRIC Ltd.

    7 A10 — Road &

    Traffic Assessment

    Lister, G. (2013). Landscape and Visual Assessment (Final).

    Report prepared by Isthmus for HBRIC Ltd.

    7 A12 — Landscape &

    Visual Assessment

    Morgan, S., and Frey, M. (2013). Ruataniwha Water Storage

    Scheme Recreation Assessment. Report prepared by Opus

    International Consultants Ltd for HBRIC Ltd.

    6 A9 — Recreation

    Assessment

    Renwick, A. (2013). Climate Change and its implications for the

    Ruataniwha Water Storage Scheme. Report prepared for HBRIC

    Ltd.

    3 K3 — Climate

    Change Review

    Rutherford, K. (2013). Effects of land use on nutrients: Phase 2

    studies in the Tukituki River, Hawke’s Bay. Report prepared by

    NIWA for HBRIC Ltd.

    4 M3 — Stream

    Modelling (TRIM 2

    calibration)

  • Report Name Folder No. Section

    Rutherford, K. (2013). Effects of land use on streams – Phase 2

    modelling studies in the Tukituki River, Hawke’s Bay. Report

    prepared by NIWA for HBRIC Ltd.

    4 M4 — Stream

    Modelling (TRIM 2

    Scenario Modelling)

    Tonkin & Taylor Ltd. (2013). Ruataniwha Water Storage Scheme

    Project description report. Report prepared for HBRIC Ltd.

    3 K1 — Project

    description

    Tonkin & Taylor Ltd. (2013). Ruataniwha Water Storage Scheme

    Sedimentation Assessment. Report prepared for HBRIC Ltd.

    7 A14 —

    Sedimentation

    Assessment

    Wakefield, B., Hape, M., Maaka, J., Wakefield, B., Maaka, H.,

    Apatu, M., Moffatt, D., and Whitiwhiti, D. (2013). Tukituki River

    Catchment Cultural Values and Uses. Report prepared by Te

    Taiwhenua O Tamatea, in partnership with Te Taiwhenua O

    Heretaunga for HBRIC Ltd.

    6 Cultural Impact

    Assessments

    Waldron, R., & Baalousha, H. (2013). Assessment of potential

    effects on groundwater and surface water resources. Report

    prepared Resource Management Group for HBRIC Ltd.

    4 M1 — Ground &

    Surface Water Flow

    Modelling

    Wheeler, D., Benson, M., Millner, I., and Watkins, N. (2013).

    Overseer Nutrient budgets modelling for the Tukituki catchment.

    Report prepared by AgResearch for HBRIC Ltd.

    4 M2 — Overseer

    Nutrient Budgets

    Modelling

    Young, R., Allen, C., Shearer, K., Doehring, K., Berkett, N.,

    Holmes, R., and Hay, J. (2013). Aquatic Ecology Assessment of

    Effects. Report prepared by the Cawthron Institute for HBRIC

    Ltd.

    5 A3 — Aquatic

    Ecology Assessment

  • Appendix 3

    Board’s decisions on the matters raised in the submissions and further submissions concerning Plan

    Change 6

    The appendix contains two tables (Table A and B).

    Table A shows the decisions requested by each Submitter (sorted alphabetically). Within each submitter the decision requested is sorted by ‘statement’ number and ’topic’ reference. The

    decision requested and the Boards corresponding decision and reasons are then provided. The

    corresponding decision on any further submissions that were made on the original submission

    is then outlined.

    Table B shows decisions on further submissions that do not directly reference a particular decision requested in an original submission (as detailed in the Summary of Submissions). A

    table outlining those parties who made a further submission and their submitter number is

    detailed below.

    Notes:

    The summary of the decision requested is from the ‘Summary of Submissions — Plan Change

    6: Hawke’s Bay Regional Resource Management Plan’ August 2013, prepared for the Tukituki

    Catchment Proposal Board of Inquiry.

    As noted in the ‘Summary of Submissions — Plan Change 6: Hawke’s Bay Regional Resource

    Management Plan’ August 2013 due to database software limitations, conventional styles for

    depicting text requested to be added or deleted cannot be used in this appendix. Instead, in this

    appendix, text requested to be inserted is underlined and text requested to be deleted is

    represented as [italics in square brackets].

  • Further submission numbers

    Further submission number Further submitter

    FS001 Hawke's Bay Environmental Water Group

    FS002 Waimarama Marae on behalf of Nga Hapu o Waimarama

    FS003 Ngati Kahungunu iwi Incorporated FS004 Environmental Defence Society Inc FS005 Mills, Judith FS006 Ingleton Farms Ltd FS007 Sustaining Hawke's Bay Trust FS008 Gifford, Andrew FS009 Te Taiao HB Environment Forum

    FS010 Fonterra Co-Operative Group Limited

    FS011 TrustPower Limited FS012 Silver Fern Farms Limited FS013 Mr Apple New Zealand Limited FS014 BEL Group Limited FS015 Ruataniwha Water Users Group FS016 Rose, Megan FS017 Mangaroa Marae

    FS018 Royal NZ Forest and Bird Protection Society Inc, Hastings/Havelock North Branch

    FS019 Hastings District Council FS020 DairyNZ FS021 Horticulture NZ and others FS022 Federated Farmers of New Zealand

  • Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

    Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

  • Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

    Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

  • 3 C6 Rule TT2 No specific decision requested, but refers to opposing Rule TT2 as it is not inclusive or specific enough.Reject

    4 C6 Rule TT2 No specific decision requested, but states that the timeframes and lead-in time for compliance with environmental management plans is too generous. ‘Good practice’ is not sufficient to combat environmental degradation so specific timelines are required. Reject

    5 C6 General No specific decision requested but suggests that HBRC include in the Plan what measures and actions they will take to change the Contract terms and conditions if the agreed environmental limits or actions are not sufficient to prevent serious adverse effects on the environment including Cadmium levels, Nitrogen, Phosphorus, Sediment, aquifer contamination. Reject

    6 C6 General No specific decision requested, but asks that HBRC is held liable to prosecution if they fail to monitor, add or change the contract terms and conditions; if there are insufficient responses to identified problems and other environmental problems known as having potential or actual detrimental effect.

    Reject

    1 C6 Form 'Other'

    Other' decision requested (See in Statement #216.2).Reject

    Not practicable to be heard consecutively.

    2 C6 Gen Process

    Requests that Plan Change 6 is heard independently of RWSS resource consent applications.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 General Approve Plan Change with changes.Accept

    2 C6 New Add two new objectives: "OBJ TT6 Subject to Objective TT1 to TT3, to provide for the use of freshwater for viable primary production and processing of beverages, food and fibre.OBJ TT7 To recognise the benefits of industry good practice to land and water management"

    Accept in part

    FS019/46

    3 C6 POL TT1 No specific decision requested, but seeks a collaborative process to agree the correct balance between economic growth and safeguarding of resources. Require management of nitrogen loss to surface water to meet risk based protection levels for toxicity to native aquatic fauna with limits suitable to each catchment and sub catchment. Require management of phosphorus and sediment loss to surface water to control periphyton growth with limits appropriate to each catchment and sub catchment.

    Accept in part

    4 C6 POL TT2 No specific decision requested, but seeks a collaborative process to agree the correct balance between economic growth and development and environmental protection, and appropriate timeframes to achieve and agree limits and targets. Accept in part

    5 C6 POL TT4 No specific decision requested, but states practical application of detail within POL TT4 requires further consideration. 1. For example, certified advisor capability needs to be matched with delivery requirements and timeframes of Nutrient Management and Farm Environmental Management Plans2. Recommend 10ha of land (rather than 4ha) provides a threshold area for requirement to keep property records as specified in Schedule XXI3. Nitrogen Conversion Efficiency (NCE, as estimated by Overseer) should not be used to manage nitrogen loss to waterways.4. Agree Nutrient Budgets should be updated every three years5. Overseer model in regulation should be consistent nationally6. Submission contains evidence on Proposed Canterbury Land and Water Regional Plan, defining material change in N loss by Overseer and an alternative7. Overseer protocols should include determination of average leaching rates using average input data from a minimum of three years (not as proposed for two years).

    Accept in part

    6 C6 POL TT5 No specific decision requested, but seeks the threshold limit for providing a Phosphorus Management Plan (POL TT5(1)(d)(iv) applies to properties exceeding 10ha (not 4ha as proposed) and that realistic timeframes for monitoring the effectiveness of POL TT5(1) are allowed for.

    Accept in part

    7 C6 POL TT6 No specific decision requested, but refers to the following matters:1. Require a Nutrient Management Plan and not a Fertiliser Management Plan, and define the term2. Long-term consents are supported, to enable confidence in business growth and investment3. Where nutrient loss to water bodies is managed through Farm Environmental Plans, Nitrogen Conversion Efficiency targets should not be required by regulation, delete them from the Policy4. Nutrient budgets and nutrient management plans should be valid for three years5. Consider mechanisms which enable a land owner to comply with land use regulations where owner and land user are different.

    Accept in part

    8 C6 Rule TT1 Amend Rule TT1 so that:1. Nitrogen loss of 10% is increased to 30% in Rule TT1 condition(a)2. Amend farm size thresholds in Rule TT1 (b), ( c) and (e)3. Delete condition (k) or alternatively provide a mechanism to allow for assessing the impact of a farm's activity in combination with all other activities4. Delete condition (l) or alternatively provide a mechanism to allow for assessing the impact of a farm's activity in combination with all other activitiesAlso refers to providing national consistency for Overseer Nutrient Budget model.

    Reject

    9 C6 Rule TT2 No specific decision requested, but seeks for production land uses which do not meet the permitted activity conditions, the restricted discretionary activity matters of discretion should provide a mechanism to assess the impact of a farm's activity in combination with all other activities, or there is no basis to make them restricted or fully discretionary activities. Accept in part

    PC6 as amended contains appropriate provisions.

    172 Barrow, John 1 C6 Form 'Not Stated'

    No decision/position stated for Plan Change 6.Reject

    No response required.

    1 C6 General No specific decision requested, but expresses concern about the negative social, economic and ecological impact of intensification of dairying and the loss of sustainability for the region and the widespread destruction of natural eco systems. Accept in part

    PC6 as amended reflects this.100 Bayliss, Ian and Liz

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    216

    140

    289 Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Ballance Agri-Nutrients Limited

    Baird, Sharleen

    Baker, Jenny

    Page 2 of 105

    Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

  • 3 C6 Rule TT2 No specific decision requested, but refers to opposing Rule TT2 as it is not inclusive or specific enough.Reject

    4 C6 Rule TT2 No specific decision requested, but states that the timeframes and lead-in time for compliance with environmental management plans is too generous. ‘Good practice’ is not sufficient to combat environmental degradation so specific timelines are required. Reject

    5 C6 General No specific decision requested but suggests that HBRC include in the Plan what measures and actions they will take to change the Contract terms and conditions if the agreed environmental limits or actions are not sufficient to prevent serious adverse effects on the environment including Cadmium levels, Nitrogen, Phosphorus, Sediment, aquifer contamination. Reject

    6 C6 General No specific decision requested, but asks that HBRC is held liable to prosecution if they fail to monitor, add or change the contract terms and conditions; if there are insufficient responses to identified problems and other environmental problems known as having potential or actual detrimental effect.

    Reject

    1 C6 Form 'Other'

    Other' decision requested (See in Statement #216.2).Reject

    Not practicable to be heard consecutively.

    2 C6 Gen Process

    Requests that Plan Change 6 is heard independently of RWSS resource consent applications.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 General Approve Plan Change with changes.Accept

    2 C6 New Add two new objectives: "OBJ TT6 Subject to Objective TT1 to TT3, to provide for the use of freshwater for viable primary production and processing of beverages, food and fibre.OBJ TT7 To recognise the benefits of industry good practice to land and water management"

    Accept in part

    FS019/46

    3 C6 POL TT1 No specific decision requested, but seeks a collaborative process to agree the correct balance between economic growth and safeguarding of resources. Require management of nitrogen loss to surface water to meet risk based protection levels for toxicity to native aquatic fauna with limits suitable to each catchment and sub catchment. Require management of phosphorus and sediment loss to surface water to control periphyton growth with limits appropriate to each catchment and sub catchment.

    Accept in part

    4 C6 POL TT2 No specific decision requested, but seeks a collaborative process to agree the correct balance between economic growth and development and environmental protection, and appropriate timeframes to achieve and agree limits and targets. Accept in part

    5 C6 POL TT4 No specific decision requested, but states practical application of detail within POL TT4 requires further consideration. 1. For example, certified advisor capability needs to be matched with delivery requirements and timeframes of Nutrient Management and Farm Environmental Management Plans2. Recommend 10ha of land (rather than 4ha) provides a threshold area for requirement to keep property records as specified in Schedule XXI3. Nitrogen Conversion Efficiency (NCE, as estimated by Overseer) should not be used to manage nitrogen loss to waterways.4. Agree Nutrient Budgets should be updated every three years5. Overseer model in regulation should be consistent nationally6. Submission contains evidence on Proposed Canterbury Land and Water Regional Plan, defining material change in N loss by Overseer and an alternative7. Overseer protocols should include determination of average leaching rates using average input data from a minimum of three years (not as proposed for two years).

    Accept in part

    6 C6 POL TT5 No specific decision requested, but seeks the threshold limit for providing a Phosphorus Management Plan (POL TT5(1)(d)(iv) applies to properties exceeding 10ha (not 4ha as proposed) and that realistic timeframes for monitoring the effectiveness of POL TT5(1) are allowed for.

    Accept in part

    7 C6 POL TT6 No specific decision requested, but refers to the following matters:1. Require a Nutrient Management Plan and not a Fertiliser Management Plan, and define the term2. Long-term consents are supported, to enable confidence in business growth and investment3. Where nutrient loss to water bodies is managed through Farm Environmental Plans, Nitrogen Conversion Efficiency targets should not be required by regulation, delete them from the Policy4. Nutrient budgets and nutrient management plans should be valid for three years5. Consider mechanisms which enable a land owner to comply with land use regulations where owner and land user are different.

    Accept in part

    8 C6 Rule TT1 Amend Rule TT1 so that:1. Nitrogen loss of 10% is increased to 30% in Rule TT1 condition(a)2. Amend farm size thresholds in Rule TT1 (b), ( c) and (e)3. Delete condition (k) or alternatively provide a mechanism to allow for assessing the impact of a farm's activity in combination with all other activities4. Delete condition (l) or alternatively provide a mechanism to allow for assessing the impact of a farm's activity in combination with all other activitiesAlso refers to providing national consistency for Overseer Nutrient Budget model.

    Reject

    9 C6 Rule TT2 No specific decision requested, but seeks for production land uses which do not meet the permitted activity conditions, the restricted discretionary activity matters of discretion should provide a mechanism to assess the impact of a farm's activity in combination with all other activities, or there is no basis to make them restricted or fully discretionary activities. Accept in part

    PC6 as amended contains appropriate provisions.

    172 Barrow, John 1 C6 Form 'Not Stated'

    No decision/position stated for Plan Change 6.Reject

    No response required.

    1 C6 General No specific decision requested, but expresses concern about the negative social, economic and ecological impact of intensification of dairying and the loss of sustainability for the region and the widespread destruction of natural eco systems. Accept in part

    PC6 as amended reflects this.100 Bayliss, Ian and Liz

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    216

    140

    289 Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Ballance Agri-Nutrients Limited

    Baird, Sharleen

    Baker, Jenny

    Page 2 of 105

    Sub# Submitter Sub Stat# Topic Decision requested

    Decision ReasonsFurther

    submissions accepted

    Further submissions

    accepted in part

    Further submissions

    rejected

    Further submissions no

    response

    1 C6 General Reject Plan Change, or make changes as specified elsewhere in submission.Reject

    2 C6 POL TT9 No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in 10 year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept

    3 C6 POL TT14

    No specific decision requested, but seeks the five year restriction on irrigation consents is removed.Accept in part

    FS019/69

    4 C6 Schedule XVIII

    No specific decision requested, but seeks the pro rata seasonal allocation on water take consents is removed and retain the current weekly allowance, or if the weekly allowance is not retained adopt a model that takes the 1 in ten year drought event into account and the more specific requirements of each site based upon crops, soil types and climate. Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided. FS006/46FS014/47

    5 C6 Misc No specific decision requested, but seeks a system of subsidies for fencing along waterways to relieve some of the costs to land owners. Reject

    No response required - Outside Scope.

    6 C6 General No specific decision requested, but seeks clarification of the status of existing water take consents for on-site dams in light of Plan Change. Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT9 No specific decision requested, but objects to way POL TT9 and Schedule XVII Table 1 will affect existing irrigation.Accept

    PC6 as amended contains appropriate provisions.

    2 C6 Rule TT1 No specific decision requested, but refers to amending waterway fencing requirements.Accept in part

    3 C6 Gen Process

    Requests that the Plan Change be taken to the community for full and proper consultation.Reject

    FS002/1FS003/1

    4 C6 General No specific decision requested, but refers to private and community water consents being treated equally and fairly.Accept in part

    PC6 as amended achieves fairness.

    5 C6 General No specific decision requested, but refers to farming not requiring resource consent.Accept in part

    Rules allow for permited activities where appropriate.

    339 Allison, Sally 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    118 Arden Properties Ltd, Tukituki Ltd

    1 C6 General Reject Plan Change.Reject

    PC6 as amended has been approved.

    247 Armitage, Rebecca 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT1 Amend POL TT1, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    FS002/2FS003/2

    2 C6 POL TT4 Amend POL TT4, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Accept in part

    3 C6 POL TT5 Amend POL TT5, to set stricter limits for phosphate P (e.g. 0.004mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    4 C6 POL TT6 Amend POL TT6, to set stricter limits for phosphate P (e.g. 0.004 mg/l) and nitrate N (e.g.0.14-0.3 mg/l) concentrations.Reject

    5 C6 New No specific decision requested, but suggests a condition that additional limitations must be placed on sedimentation and nutrient loading in these sediments. Accept in part

    PC6 has been amended to reflect the Boards findings.

    6 C6 Rule TT1 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Reject

    FS002/3FS003/3

    7 C6 Rule TT2 No specific decision requested, but refers to adding a condition "that farming practices focus on reducing external harmful and non-renewable inputs with more targeted use of the remaining inputs. For example less than 60 units of N and P per year/Ha applied in conjunction to the use of biological foods, either through management changes or inputs" Accept in part

    160 Astill, Rachel 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    183 Atkinson, Nicola 1 C6 General Reject Plan Change.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Gen Process

    Requests that more time be allowed to review Plan Change and its impacts on business and community.Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    2 C6 Schedule XVIII

    No specific decision requested, but seeks total review of the schedule.

    Accept in part

    PC6 has been amended to reflect the Boards findings. New Schedule XVIII provided.

    3 C6 Schedule XX

    No specific decision requested, but seeks more detail and time to get accurate impact of this schedule.

    Reject

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    89 Bailey, Paul 1 C6 General Approve Plan Change with changes. No specific changes requested, but states that the objectives of Plan Change should be to enhance water quality in the Tukituki catchment over time, rather than increase in the levels of Nitrogen or Phosphorus in the Tukituki catchment.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 Rule TT1 No specific decision requested, but refers to opposing Rule TT1 as it is not inclusive or specific enough. Reject

    Table A

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    140

    267

    1

    2

    3

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    Addavale Produce Ltd

    Aitken, James

    Association of Biological Farmers

    Awassi NZ Land Holdings Ltd

    Baird, Sharleen

    Page 1 of 105

  • 2 C6 Section 32 Report

    No specific decision requested, but refers to concerns with the lack of consideration given to alternative economic options.Reject

    3 C6 Gen Process

    Concerned with the objectivity and rigour of the information supplied to the public and the short time frames for information sharing and submission writing. Reject

    4 C6 General No specific decision requested, but refers to concerns over the questionable validity of current measurement systems of water pollutants and the lack of acknowledgement of the importance of both phosphate and nitrate levels. Accept in part

    PC6 as amended it contains appropriate provisions.

    5 C6 POL TT5 No specific decision requested, but concerned with the extended timeframes for fencing off waterways. Reject

    6 C6 General No specific decision requested, but refers to the lack of consideration given to reduction of cow numbers and how profitable dairying could be achieved without degradation of the natural environment. Accept in part

    86 Bayliss, Kathryn 1 C6 Form 'Other'

    Other' decision requested. Refer to Submission #4 (EPA #103323) for original decisions requested. No further decisions requested included within Submission #86, but refers to it being impossible to know if she wants to have Plan Change 6 approved without seeing all the changes made.

    Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    1 C6 POL TT3 No specific decision requested, but seeks that discharge of contaminants into all our rivers be prohibited OR if not possible all rivers should have the same highest standard possible. Accept in part

    Decision on request is for the reasons as set out in the body of the Report and the identified reasons reached in each of the main findings on the principal issues in contention.

    FS015/1

    2 C6 Rule 47 No specific decision requested, but seeks that discharge of contaminants into all our rivers be prohibited OR if not possible all rivers should have the same highest standard possible. Reject

    PC6 has been amended to reflect the Boards findings. FS015/2

    3 C6 General No specific decision requested, but seeks that provisions that refer to nitrate-nitrogen being in a state of under-allocation be deleted. Accept in part

    Policy TT4 has been amended. FS002/4FS003/4

    4 C6 OBJ TT4 No specific dec