of office building at regent road, hill station, …

347
1 REHABILITATION/COMPLETION AND OUTFITTING WORKS OF OFFICE BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB) VOLUME 2: TECHNICAL SPECIFICATIONS DECEMBER, 2016

Upload: others

Post on 07-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

1

REHABILITATION/COMPLETION AND OUTFITTING WORKS

OF

OFFICE BUILDING

AT

REGENT ROAD, HILL STATION, FREETOWN

FOR

SIERRA LEONE FIELD OFFICE

OF

THE AFRICAN DEVELOPMENT BANK (ADB)

VOLUME 2: TECHNICAL SPECIFICATIONS

DECEMBER, 2016

2

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

1.0 General ---------------------------------------------------------------------------

2.0 Excavation and Earthworks ---------------------------------------------------

3.0 Concrete works -----------------------------------------------------------------

4.0 Blockwork -----------------------------------------------------------------------

5.0 Roofing ---------------------------------------------------------------------------

6.0 Woodwork and Ironmongery --------------------------------------------------

7.0 Steel work ------------------------------------------------------------------------

8.0 Metal work -----------------------------------------------------------------------

9.0 Floor, Walls and Ceiling Finishing’s -----------------------------------------

10.0 Glazing ---------------------------------------------------------------------------

11.0 Painting and Decorating -------------------------------------------------------

12.0

Electro-Mechanical And Information & Communications Technology

(ICT) System

3

ARCHITECTURAL AND CIVIL WORKS SPECIFICATIONS

4

TECHNICAL SPECIFICATIONS

DESCRIPTION OF MATERIALS, GOODS, WORKMANSHIP AND PRICING NOTES

1.0 GENERAL

1.1 Responsibility

No approval by the Consultants shall in any way relieve the Contractor of his contractual responsibility

for the quality of materials and the standard of workmanship in the finished works.

1.2 Variations

No variations to these Technical Specifications may be made unless approved by the Consultants in

writing.

1.3 Standard Specification

In all instances in which articles and materials specified by reference to a British Standard (BS)

Specification in these Bills, articles and materials complying with an alternative standard specification

may be substituted provided they are:-

a. In no respect lower in standard, grade or quality than those specified.

b. Similar in size and shape to those described.

c. Equally suitable for the purpose for which they are required.

d. Approved in writing by the Consultants prior to their incorporation into the Works.

Description of materials, goods and workmanship given in any one-work section shall apply equally to

all work sections.

All materials, goods and workmanship shall comply with the requirements and recommendations of

the relevant BS or CP where applicable, unless otherwise stated. Any reference in these Bills which is

at variance with any provision in a BS or CP shall be deemed to take precedence over and to over-ride

same.

Notwithstanding any of the foregoing the whole of the materials, goods and workmanship shall be

subject to the approval of the Consultants.

1.4 Proprietary Articles of Materials

In all instances in which articles and materials of a proprietary manufacture are described in these Bills,

articles and materials of a different manufacture may be substituted provided they are: -

a. Similar in design and details, size, shape and quality to those described

b. Equally suitable for the purpose for which they are required.

c. Approved in writing by the Consultants prior to their incorporation into the Works.

5

1.5 Defective Materials or Goods

Any materials and goods that have been damaged, contaminated or deteriorated or have not been

approved or have been condemned shall be rejected and removed from the site within 24 hours and

replaced at the Contractor’s expenses.

1.6 Defective Work

Any crack or otherwise defective work, including deviation from the working details in respect of

setting out, correct lines and levels, size or thickness of members, shall be removed and reconstructed

or otherwise rectified to the approval of the Consultants and the Contractor shall be responsible for all

additional cost incurred, all such remedial work shall be executed without undue delay.

The Consultants reserve the right to check the work executed by the Contractor and his setting out in

such cases and at such times as he may deem fit, there is, however, no duty on his part to make such

checks and any failure by him to observe errors shall not relieve the Contractor of his responsibilities

in these respects.

2.0 EXCAVATION AND EARTHWORKS, ETC

2.1 Site Clearance and Felling of Trees

The Contractor shall include in his prices for clearing the site of all unwanted trees, shrubs, roots, old

foundations and materials arising from the site clearances, etc., that may be deemed necessary by the

Consultants (unless otherwise described).

All the works are to be executed in such manner as to cause the least possible disturbance and in the

most careful manner so as to cause the minimum or annoyance and inconvenience to the owners and

occupiers of the lower floors and adjacent premises and to the public. The Contractor must provide for

properly watering and all other necessary precautions to minimise dust. Where necessary, the

Contractor will be required to provide and erect all necessary dustsheets, tarpaulins, etc.

2.2 Nature of the Ground

The Contractor is deemed to have visited the site and ascertained the nature of the ground to be

excavated and works to be done and must accept all responsibility for the cost of excavation.

The Contractor shall allow for breaking up and removing all obstructions met with in the course of the

excavations, including old foundations, drains, etc., and disinfecting wells, septic tanks and cesspits,

etc., and filling with dry hard-core well consolidated.

Where rocks or similar hard natural materials is encountered during the course of excavations the

Consultant must be notified immediately so that approval or agreement as to its extent and method of

removal is determined before the rock is actually excavated.

2.3 Site Levels

Before commencing any excavation, the Contractor shall satisfy himself that any site levels, whether

spot or contours shown on the drawings are correct. If he is not satisfied with the accuracy of these

levels, he shall at once give written notice to the Consultants; otherwise no claim will be entertained in

respect of the inaccuracy of these levels.

6

2.4 Excavation Measured Net

The quantities of excavation and filling have been ascertained by taking the net dimensions of the void

to the lines and levels shown on the drawing, no allowance has been made for increase in bulk after

excavation or for sloping sides or timbering.

2.5 Excavation Beyond True Line

No more ground shall be removed than is absolutely necessary and if loose, soft or hard ground is met,

the matter shall be reported at once to the Consultant.

Should the Contractor excavate to a greater depth or width than shown on the drawings or as instructed

by the Consultants at his own expenses he shall fill in such greater depth or width of excavation with

concrete as described for foundation.

2.6 Excavation in Rock

Quantities for excavation in rock have been shown as “extra over” the excavation in which rock occurs.

Excavations which in the opinion of the Consultants are best carried out by wedges, levers, compressed

air or other similar plants, has been described as such.

2.7 Support of Sides of Excavations

The sides of excavations shall be supported using any methods the Contractor elects in such a way as

may be sufficient to secure them from falling in and the supports shall be maintained for as long as

necessary.

The Contractor will be held responsible for upholding the sides of all excavations and earthworks and

no claim for additional excavations, concrete or other materials will be considered in this report.

2.8 Disposal of Spoil

The whole of the spoil arising from the excavation (where not required to be returned for infilling at

once) shall be moved to spoil heaps where required on the site for infilling around foundations or to

make up levels under floors and outside lines of building and any surplus is to be removed from the

site, filling has been measured separately

Selected and approved materials from excavation suitable for fill materials shall be kept separate for

re-use as directed.

2.9 Protection of Excavations

The Contractor shall provide all necessary boards or coverings and lay same to protect trenches or

excavations from the effect of inclement weather, if so required by the Consultants.

The Contractor shall allow for keeping the excavations free from water by pumping or bailing.

2.10 Termite Treatment Solution

Not applicable

7

2.11 Approval of Excavations and Concreting Foundations

The Contractor shall report to the Architect when excavations are ready to receive concrete foundation

and shall not proceed with concreting until the excavations have been approved by the Architect. Any

concrete or other work put in before this has been done shall be removed, if so required, by the

Architect. The Contractor shall not fill in over any work until it has been approved by the Architect.

2.12 Filling

Selected materials arising from excavation shall be brought back from the place where it was

temporarily deposited, and the trenches or other excavations to be filled, levelled with spoil in layers

of not more than 6” (150mm) thickness. Each layer shall be carefully rammed and further consolidated

by the addition of water.

All filling to raise the level of the site shall be done in similar layers, carefully rammed and consolidated

to the satisfaction of the Architect.

2.13 Hard-core

Sub-Base

The sub-base shall consist of selected approved laterite materials, spread to the full width of the

formation including verges, compacted as described to the finished level shown on the drawings. The

compacted thickness of the sub-base shall be 6” (150mm).

Base

The base shall consist of selected approved crushed rock spread to the fill width of the sub-base, blinded

with fine materials and compacted as described to the finished level shown on the drawings. The

compacted thickness shall be 6” (150mm).

2.14 Compaction

Compaction of sub-base shall be by means of a 3-wheel rolled weighting not less than 10 tons and

providing a compressing under the rear wheels of not less than 375lbs per roller; the number of passes

of the roller shall be determined from rolling trails and rolling shall commence at the centre line of the

road. Where necessary the materials shall be watered during connection to maintain the moisture

content at the correct level.

Inter locking paving blocks shall be pre-stressed 100mm thick laid to slight slopes to drain off rain

water into surface water drains.

Allow for making Parking Area with approved road paint of approved colour and quality to indicate

number of parking spaces.

3.0 CONCRETE WORK

3.1 General

The following terms whenever used hereafter, shall be taken to have that meanings assigned to them

below.

“Structural props” shall mean those components of the strutting to formwork, which carry the weight

of the concrete and will be retained in position when the shuttering is removed from concrete faces.

8

“Approved or Approval” shall mean, approved by or approval of the Consultants in writing.

“Required” shall mean required by the terms of this Specification or other Contract Documents.

“Satisfaction” shall mean to the satisfaction of the Consultants.

“Testing Authority” shall mean an organisation, approved by the Consultants, fully equipped to carry

out all tests and checks required by this specification. It shall be an independent firm or a laboratory.

Reinforced Concrete Design

The reinforced concrete works has been designed generally in accordance with the recommendations

contained in the Code of Practice 114, 1957, and the Contractor shall comply with the recommendations

made in section2.5 and 2.6 of the Code of Practice, unless specifically excluded or modified hereafter.

A copy of the Code of Practice 114 shall be kept permanently on the site.

Precast and unreinforced Concrete

Precast and unreinforced concrete shall comply with all relevant requirements of this specification.

Rates

The Contractor’s rates for all items relating to the concrete works and tests shall include for carrying

out the work in accordance with all the terms and requirements listed hereafter. The Contractor is to

take full responsibility for providing an adequate key for plastering etc. on the concrete, wire brushing

of timber formwork will be permitted and when metal formwork is used hacking of concrete will be

allowed. The use of a retarder on the formwork will not be permitted in any circumstances.

The Contractor should note that all reinforcement and formwork has been measured separately, except

that for precast work, the rates shall include for formwork and reinforcement as specified.

Defective Work

Where in the opinion of the Consultants any of the finished works or materials or workmanship in any

part of the works do not comply with all relevant requirements of these Preambles, that part of the

Works shall be classed as defective work.

All work classed as defective work, shall be cut and removed from the Work and replaced to the

satisfaction of the Consultant. The extent of the work to be removed and the methods to be used in the

removal and replacement of this work shall be in accordance with the Consultants’ instructions.

3.2 Materials

All materials used in the Works shall comply in all respects with the relevant BS except for any

deviations specifically authorised in subsequent clauses of these preambles.

Concrete shall be made with Portland cement, fine aggregate, coarse aggregate and water. No other

agent or ingredient shall be added to the concrete.

3.2.1 Cement

The cement shall be Portland cement complying with BS12 and shall be delivered to the site in sealed

bags. The cement shall be protected from damaged by the weather or any other causes at all times

before use. It shall be stored in weather tight and ventilated shed of adequate capacity fitted with a

boarded floor suitably raised clear off the ground. Cement shall be used in rotation in order of its

delivery to site. Any cement, which has become caked or otherwise adversely affected, shall not be

used in any part of the works and is to be removed from the site.

9

3.2.2 Aggregate

Fine aggregate shall be river or pit sand thoroughly washed with clean water until all salts and other

impurities are removed and complying with BS 882.

Coarse aggregate shall be broken synite, washed clean and free from impurities and complying with

BS 882.

Aggregate shall be stored in hard paved self-draining areas with adequate dividing walls to prevent

mixing of different types of aggregates.

For structural concrete trades the minimum size of fine aggregate shall be able to pass a Nr 7 sieve and

the coarse aggregate shall be as listed in Table 1.

The grading of coarse aggregate shall be in accordance with Table 1 BS 882, 1965. The percentage of

broken stone and sand shall be in accordance therewith, subject however, to possible modifications to

be approved by the Consultants.

If the grading of any aggregate changes, the Consultants shall approve the mix content.

All sampling and testing of aggregates shall be carried out in accordance with the relevant

recommendations of BS 882.

At the commencement of the contract, the Contractor shall deliver to the Testing Authority for

inspection and analysis three separate and sufficient samples of each type of aggregate to be used in

the structural concrete grades. For each type of aggregate, the samples shall be taken at the proposed

source of supply at intervals of not less than one day

The quality of water contained in the aggregate shall be determined by approved methods at least once

a day when concrete mixing is in progress.

3.2.3 Water

The water to be used in the works shall be clean and free from impurities.

3.2.4 Reinforcement

Bars for reinforcement shall be mild steel and or high tensile bars complying with BS 4449.

Mesh for reinforcement shall comply with BS 4483. All mesh shall be delivered as flat sheets.

Reinforcement shall be stored clear off the ground.

3.3 Test

3.3.1 Test

All test and checks carried on site shall be in the presence of, or as directed by the Consultants.

The Contractor shall send copies of all test results to the Consultants.

An item is included elsewhere in these Bills for the cost of testing.

No claims will be entertained for any tests called for by the Consultants in consequence of any failure

by the Contractor to comply with these specifications.

3.3.2 Concrete Tests

All concrete test cubes shall be made, cured and tested and the result recorded in accordance with the

recommendation of BS 1881, 1970, unless specifically modified in subsequent clauses of these

Preambles. The testing shall be carried out by the Testing Authority.

10

The test specimen shall be 150mm cubes, made in steel moulds of approved design. The test cubes

shall be taken from typical batches of concrete as directed by and in the presence of the Consultants’

representative without prior notice.

Slump tests of the mixed concrete shall be carried out at regular intervals to be directed by the

Consultant and the results recorded and kept on site.

3.3.3 Load Test

Load tests of complete parts of the structure may be called for by the Consultants whenever a dispute

arises as to the sufficiency of the work done by the Contractor.

The standard of acceptance for structure load test, as stipulated in Clause 6.05 of the BS Code of

Practice 144, is specifically excluded from these Preambles. The test procedure and the standard of

acceptance will be specified by the Consultant. Where the results of such tests indicate that any member

or part of the structure does not comply with these specifications, that part of the structure shall be

classed as defective work.

3.4 Design and Control of Concrete and Mortar Mixes

For structural concrete mixes, made with ordinary Portland Cement, the average 7 and 28 days strength

for each mix shall not be less than that specified in Table 1.

3.4.1 Preliminary Strength

For each structural concrete mix, the twenty-eight days preliminary strength shall be calculated as the

average of all the cubes tested at twenty-eight days and seven days preliminary strength shall be

calculated as the average of all the cubes tested at seven days.

If, for any mix in Table 1, the test results of one set of three cubes, tested at twenty-eight days, fall

below these requirements, the mix shall be rejected, the proportions revised by the Contractor and the

testing procedure repeated.

Results of all preliminary tests shall be sent to the Consultants as soon as they are available.

3.4.2 Work Strength

Work strength cube tests shall be carried out during the contract period.

A sample of the concrete shall be taken on each of the first four days the mix is used on the site. Six

cubes shall be made for each sample, three for tests at seven days and three for tests at twenty-eight

days, and shall be accepted as satisfactory if the crushing strength of all three cubes is greater than

specified for that mix.

Subsequently, a sample of the concrete shall be taken and six cubes made from the sample for every

day of casting of structural concrete or as directed by the Consultants and these cubes shall be tested at

seven and twenty-eight days to provide a record.

The Contractor shall maintain on the site a complete record of the date, time, grade and location in the

works of the mix from which the sample was taken and shall submit this information with the test

results to the Consultants as soon as they are available.

3.4.3 Works Test Failure

If any set of seven days tests results indicates a low twenty-eight days strength to be expected, the

Consultants shall be notified immediately and no props shall be removed from the affected part of the

structure until the cause is determined.

11

If any of twenty-eight days cube test results fall below the specified strength, the Consultants shall be

notified immediately and the cause of the failure investigated.

The extent of the area of the structure affected shall be as defined by the Consultants.

Table 1

Nominal Description

Quantity of Dry Materials

Min. Cube

Strght. 28

days

Max

Size of

agg.

Kg m3 m3 Mn/M2 mm

A. Mass Concrete 1:3:6 213 0.59 0.9

1

16 40

B. Mass Concrete 1:21/2:5 261 0.58 0.8

9

21 18

C. Reinforced and Precast

Concrete 1:2:4

317 0.56 0.8

6

25 18

D. Concrete below water

level mix 1:11/2:3

380 0.52 0.8

0

30 18

Mortar

1:2

1:3

1:4

1:6

224

224

224

224

5

71/2

10

15

3.4.4 Preliminary Strength

Preliminary strength cube tests shall be carried out to check the calculated proportions for each

structural concrete mix.

Preliminary cubes shall be made for each mix from three samples of aggregate and the samples of

cement sent to the approved Testing Authority. From each sample of aggregate six cubes shall be

made, three for test at seven days and three for test at twenty-eight days.

Each set of three cubes tested at twenty-eight days shall be accepted as satisfactory if either or all three

cubes have a crushing strength greater than the preliminary strength or the average strength of the three

cubes is greater than the preliminary strength, and the difference between the greater and the least is

not more than 10% of that average.

All costs and all charges in consequence of the courses of action, the Contractor is directed to follow,

shall be borne by the Contractor.

3.5 Formwork

3.5.1 General

Before construction commences, the Contractor shall notify the Consultants of the general method and

system of formwork he proposes to use.

All joints in the formwork and joints between the formwork and previous work shall be sufficiently

tight to prevent loss of liquid from the concrete through these joints.

Concrete tolerance as described in the general concrete specification shall be adhered to.

No metal part of any device for maintaining formwork in the correct location shall remain permanently

within the specified concrete cover to the main reinforcement.

12

Any bolt holes must be grouted with an approved mix of cement mortar slightly recessed from the

surface of the surrounding concrete.

The position and design of all spacer bolts agreed with the Consultants but under no circumstances will

wire ties passing through the finished concrete be allowed.

The use of concrete retarders or similar preparation on the formwork surfaces will not be permitted.

Shutters shall be lightly oiled immediately after manufacture and just before pouring with approved

mould oil.

The mould oil used shall not come into contact with the reinforcement.

Spacer blocks in reinforcement shall be plastic or cement mortar blocks and to a design approved by

the Consultants.

All fair surfaces and arises shall be adequately protected against damage and surface staining during

the execution of subsequent works.

Formwork shall be removed without risk of shake or vibration to the finished work.

Any finished work, which is subject to the subsequent damage or surface staining, shall be treated as

defective work.

Immediately after striking, the shuttering shall be carefully wire-brushed so as not to destroy the grain

pattern and then lightly oiled.

When not in use, all shuttering, soldiers, walling’s and shorting’s shall be stored flat and thoroughly

protected from the weather.

After removal of the shuttering, the concrete shall be cured by being kept in a wet condition for at least

seven days, in accordance with curing clause.

3.5.2 Mortises, Holes, Chases in Concrete

Fixing blocks and ends of brackets and bars and bolts etc., shall be cast in the concrete at the time of

placing and together with all mortises, holes, apertures, chases and grooves, etc., shall be accurately set

out in the formwork before the concrete is placed. No part of the concrete works shall be cut away for

any such item or for any other reason without the Consultants approval.

The Contractor shall obtain from all Public Utility Authorities complete information of their

requirements regarding conduit pipes, fixing bolts, chases, holes and any other items to be cast or

formed in concrete members subject to the conditions that failure or a sub-contractor to supply such

information shall not be allowed to delay the progress of the contract.

The Contractor shall ensure that all Public Utilities Authorities are informed of his programme for the

structural works at the commencement of the contract.

3.5.3 Propping

The vertical propping to all formwork shall be carried down sufficiently far to provide the necessary

support without damage or overstress or displacement of any part of the construction.

Structural props shall be retained in position until the new construction is sufficiently complete and

strong to support its own weight and any loads to be placed on it during the concrete period.

13

All formwork to soffits shall be constructed so that it can be removed without disturbing the structural

props.

3.5.4 Cambers

Unless otherwise detailed on the drawings, the formwork of all beams and slabs shall be constructed

with appropriate upward camber.

3.5.5 Final Preparation

The internal faces of the formwork may be coated with an approved preparation to prevent adhesion of

the concrete to the forms provided that the use of this preparation will not stain the surface of the

finished concrete.

None of this preparation shall be allowed to touch the reinforcement.

Immediately before the concrete is placed in any of the formwork, the interior of that section shall be

completely cleaned of all extraneous materials including water.

Each section of the formwork to structural members shall be inspected and passed by the Consultants

immediately before concrete is placed in that section.

3.6 Construction and Expansion Joints

3.6.1 Position of Construction Joints

The Contractor shall ensure that all construction joints are arranged to minimise the effect of shrinkage

of the concrete. Generally, the distance

The position of all joints shall be agreed with the Consultants before work is commended and all joints

shall be straight and true.

Concrete placing shall be carried out continuously between consecutive construction joints.

Immediately before the next pour, all joints must be thoroughly cleared and wetted with clean water.

To ensure uniformity of appearance, the following precautions should be taken:

1. Extreme care in uniformity of mix

2. All concrete must be properly compacted to the maximum.

Construction joints between different grades of concrete shall be made and positioned as the

Consultants will direct.

3.6.2 Treatment of Construction Joints

All horizontal joints at the exposed face shall be formed against a straight batten at least 12mm thick.

All construction joints other than horizontal joints shall be formed with proper stop boards and the stop

boards shall be fixed vertically unless otherwise directed.

All construction joints shall be hacked and laitance and honey combed concrete moved from the contact

face before adjacent section is concreted. Hacking shall be terminated 12mm away from the face to be

exposed. Air and water jetting may be used instead of hacking subject to the prior approval of the

Consultants. All loose materials shall be removed from the contact face immediately after hacking or

jetting has been completed.

When work is to be resumed at a construction joint, it shall be swept clean and dressed with neat cement

slurry immediately prior to the pour.

14

All concrete at construction joints is to be shaded from the direct rays of the sun for a period of one day

before casting adjacent concrete.

3.6.3 Expansion Joints

Expansion joints shall be positioned and formed in accordance with the details shown on the drawings.

3.7 Reinforcement

3.7.1 General

Reinforcement bending schedules will be provided if requested by the Contractor listing the cut length

and diameter or size and bending dimensions and location of each bar in the work.

Before the bars are cut to length, the Contractor must check that:-

1. Reinforcement schedules are provided for each part of the structure sufficiently in advance of his

concreting programme;

2. Each schedule includes the correct quantities of reinforcement as detailed on the drawing to which

it relates;

3. The grades of reinforcement given in each schedule correspond to those shown on the relevant

drawing.

The Consultant shall be notified of any errors disclosed by these checks.

3.7.2 Bending

All reinforcement bars shall be accurately shaped and bent in a manner that will not injure the material.

Bars shall not be bent hot.

3.7.3 Cleaning

All reinforcement shall be free of all loose mill scale and thoroughly cleaned to remove all loose rust,

oil and grease or other harmful matter immediately prior to being placed in position in the works.

3.7.4 Placing

All reinforcement shall be accurately placed with the correct cover and securely fixed in the positions

shown on the drawings by an approved method and inspected by the Consultants.

The Contractor shall supply and fix all necessary concrete spacers required to maintain the

reinforcement in the correct position. The cost of chairs shall be included in the rates for reinforcement

in these bills.

No metal part of any device used for connecting bars or for maintaining reinforcement in the correct

position against faces exposed to the elements shall remain permanently within the specified minimum

concrete cover to the reinforcement.

3.8 Concreting

3.8.1 General

The Contractor shall ensure that each stage in the contract of the reinforced concrete work including

the making and testing of cubes and the maintenance and calibration of mixing and measuring plant is

supervised and finally inspected by competent and responsible members of his site staff.

15

3.8.2 Proportions

The proportions of materials for concrete shall be accurately measured.

The cement, including bagged cement, and all aggregate shall be measured in weighing batches

approved by the Consultant.

Where aggregates are gauged by volume, accurate gauge boxes shall be constructed to the approval of

the Consultants. The boxes shall be completely filled and the top struck off level.

In measuring the water for each batch, due allowance shall be made for the water content of the

aggregates.

The water content of the aggregates shall be measured before each day’s concreting begins and when

they are to be used immediately after delivery.

3.8.3 Mixing

Concrete shall be mixed in an approved mechanical type concrete mixer. Mixing shall be continued

until there is a uniform distribution of the materials in the mixer and the mass is uniform in colour.

The mixing time for each batch shall not be less than the minimum period recommended by the mixer

manufacturer, checked by an approved timing device, and shall be continued until concrete is uniform

in colour and consistency.

The volume of mixed materials in each batch shall not exceed the rated capacity of the mixer. Each

batch of concrete shall be discharged completely before the mixer drum is recharged.

The mixer drum shall be thoroughly washed out whenever mixing ceases.

3.8.4 Transport

Concrete shall be transported as quickly as possible from the mixer to its final position without

segregation or loss of any of the ingredients.

All plant and equipment used for transporting concrete shall be kept clean. All containers used for

transporting concrete shall be thoroughly washed out whenever mixing ceases.

Runs or gangways for concrete transporting and main runs for foot traffic shall not be supported by or

allowed to bear on the fixed reinforcement.

3.8.5 Placing

Concrete shall be placed while still sufficiently plastic for adequate compaction.

At all times whenever reinforced concrete is being placed, a competent steel fixer shall be in continuous

attendance on the concrete to adjust and correct the position of any reinforcement which may be

displaced.

The Consultants shall be given due notice that concrete is to be placed in a particular part of the works

when he so directs.

The Contractor shall keep on site a complete record of the works, showing the time and date when

concrete is placed in each part of the works. The records shall be available at all times for inspection

by the Consultants.

16

Once concreting has commenced, it shall proceed continuously without a break until the forms are

filled or a designed joint is reached.

Vigilance will be necessary during pours of lift to ensure that any grout leaks or spillages are thoroughly

brushed off with clean water immediately.

Reinforcement left exposed, projecting from poured concrete, must be protected to avoid danger of rust

staining the completed work.

Subject to the Consultant’s approval, the use of foam rubber or plastic gaskets to ensure no lose of grout

at the foot of lifts will be permitted, provided they do not materially affect the appearance of the finished

work.

3.8.6 Compacting

Concrete shall be thoroughly compacted during placing and shall be carefully worked around all

reinforcement, embedded fixtures and into the sides and corners of the formwork.

All structural concrete shall be compacted by the use of approved mechanical vibrators, preferably the

internal type.

3.8.7 Curing

All surfaces of freshly placed structural concrete shall be covered with an approved material and cured

by being kept continuously moist for seven days.

Soffit and side forms left in position will be regarded as effective in keeping those surfaces moist.

The Contractor shall notify the Consultants of the system and methods of curing he proposes to use for

all structural concrete members before work is commenced.

3.9 Striking of Formwork

3.9.1 General

The structure shall not be distorted, damage or overloaded in any way by the removal of the formwork

from concrete members.

The responsibility for the safe removal of any part of the formwork shall rest with the Contractor.

3.9.2 Minimum Striking Times

The minimum time from completion of placing concrete to the removal of formwork from structural

members shall be determined from the following table or as the Consultants may direct.

LOCATION MINIMUM

STRIKING TIMES

FOR CONCRETE

IN DAYS

Beam and wall sides 1

Columns 1

Beams soffits (structural props left in) 7

Beam structural props 14

Slabs (structural props left in) 3

Slab structural props 10

17

3.10 Finished Work to Concrete Faces

3.10.1 General

After removal of the formwork, no treatment of any kind other than the application of specified finishes

and such treatment as is required for curing the concrete, shall be applied to the concrete faces.

Where rubbed down, plain smooth of fair face finish is specified, the concrete shall be brought to a

perfectly true, smooth, and even surface by rubbing with carborundum stone dipped in cement grout.

Alternatively, the Contractor is permitted at his own expense to provide smooth linings to the form,

which will achieve the required finish without rubbing down. Rubbed down surfaces shall be true to

form and free from all board marks, joint marks, honeycombing, pitting, etc.

3.10.2 Fair Face Finish

Unless otherwise specified, all concrete faces to be exposed in the finished works shall be left as struck

with a plain smooth face true to line and level within the specified tolerance for the work.

These clauses in no way vary the Preambles clause for reinforced concrete. It is essential that in both

the preparation of the formwork and in the casting of the concrete, considerable care should be taken

to achieve a first class uniform appearance. This appearance is of such importance that special effort

will be necessary to avoid staining and to achieve uniformity in colour. No repair or patching up

whatsoever will, be allowed.

After inspection of superfluous fines and similar projections shall be carefully removed. No render or

other applied finish shall be used to obtain a fair face to the concrete.

All concrete face to be exposed in the finished works shall be adequately protected against damage or

surface staining during the execution of subsequent works.

Any finished work, which the Consultant’s shall judge inferior in any respect to the standard of the

relevant, approved sample, or which is subjected to subsequent damage or surface staining shall be

rejected and treated as defective work.

3.10.3 Tolerances

Unless otherwise indicated in the drawings, the setting out dimensions, levels of the finished works,

and sizes of structural elements, shall be within the maximum tolerance given below:

Description Max. Tolerance

1. All dimensions of 3m and over 6mm (¼”)

2. All dimensions less than 3m 3mm (1/8”)

3. Slab to surface levels (all points in

surface) 6mm (¼”)

Surfaces exposed in the finished work shall not depart by more than 5mm for 1500mm straight edge

placed anywhere on the surface.

Columns and walls shall not be more than 6mm out of plumb in any one storey height and not more

than 18mm out of plump in the total height.

Unless otherwise indicated in the drawings, that tolerance to which units are to be cast shall be within

the following:-

18

Description Max. Tolerance

1. All dimensions shall be within 3mm (1/8”)

2. Maximum permissible bow 3mm (1/8”)

3. Maximum permissible twist from any

plain surface as defined by any three

exterior corners

3mm (1/8”)

3.11 Precast Concrete Work

3.11.1 General

These clauses are only intended to cover items of precast concrete work annotated as “fair finish” and

not lintels and the work, which may either be precast or cast in-situ at the contractor’s opinion.

3.11.2 Formwork

The prices of all precast work shall include formwork. Where so described, the finish achieved shall

be fair face and free from joint and board marks. The type of construction of the formwork shall be

approved by the Consultant before any prefabrication commences.

3.11.3 Approval

All panels shall be made available for checking of dimensions and surface finishes and shall be

approved by the Consultant before erection.

3.11.4 Erection

The Contractor shall submit details of the method of erection and supports for the Consultant’s approval

before manufacture of panels commence.

3.11.5 Finish

Considerable care must be taken to obtain a high quality finish.

4.0 BLOCKWORK

4.1 Materials

4.1.1 Cement

The cement shall be Ordinary Portland Cement to BS 12 as before described.

4.1.2 Sand

The sand shall be river or pit sand and as before described.

4.1.3 Water

The water shall be clean and free from impurities.

4.1.4 Precast Sandcrete/Concrete Blocks

Concrete blocks shall be manufactured in accordance with BS 2028; 1364’ 1968.

All types of blocks to be made in approved concrete blocks making machine with pallets true to shape

and square edges to all sides.

The external dimensions of the blocks within the tolerance specified shall be as follows: -

Description Max. Tolerance

1. Length 450mm (18”) 3mm (1/8”)

2. Height 200mm(8”) 3mm (1/8”)

3. Thickness of solid

blocks

225/150/100mm

(9”/6”4”) 3mm (1/8”)

19

Sandcrete blocks shall be composed of one part cement to six parts sand by volume and shall have a

minimum compressive strength of 2.8N/mm2 and an average of 3.5N/mm2” in twenty-eight days.

The cement and sand shall be mixed and unless otherwise specified or directed by the Consultants,

turned three times dry until an even colour and consistency is achieved.

Water shall then be added gently through a rose; the quantity of water added being just sufficient to

secure adhesion.

After removal from the machine, the blocks on pallets shall be matured under shade in separate rows,

one block high, with a space between each block for at least 24 hours.

They shall then be removed from pallets but shall not be stacked up or be removed from shade for at

least a further seven days, and then stacked not more than five blocks high in the shade for minimum

of fourteen days and kept well-watered at all times.

No blocks shall be built into any part of the building until they have matured for at least twenty-eight

days. The face of blocks, except where otherwise described shall be left rough for plastering or

rendering.

Blocks of special size and shape shall be cast true to shape, even in size, square and free from flaws or

blowholes with clean and sharp arrises and equal to samples approved by the Consultants. All blocks

shall be carefully handled. Blocks with broken arrises shall not be used.

4.1.5 Samples to be Submitted

At least two weeks before block laying is to commence twelve samples of each type of precast sandcrete

blocks to be used in the Works shall be submitted to the approved Testing Authority. Should the test

be unsatisfactory further samples will be required.

4.1.6 Mortar

The cement and sand mortar shall be composed of one part Portland Cement and six part of sand by

volume. An approved plastercizer additive may be used in accordance with the manufacturer’s

instruction.

The mortar shall be used within one hour of mixing. Such mortar shall not be used or mixed with any

other mortar after it has begun to set nor shall any other mortar of any kind of previous day’s mixing

be used.

A proper stage shall be provided to receive the mortar when made.

4.1.7 Block Laying

The whole of the blockwork shall be constructed as shown on the drawings. All blocks shall be well

soaked before being laid. Blockwork shall, unless otherwise described, be built in stretcher bond.

All blocks shall be levelled carefully through every second course. All corners, junctions and reveals

shall be properly bonded. All walls, perpends, quions and the like shall be left strictly true, square and

plumb.

Blockwork shall be carried out in uniform manner and no other portion shall be raised more than 1

metre above another at any one time.

Mortar joints shall not exceed 12mm thickness. Special care shall be taken that all vertical joints are

filled with mortar.

20

All faces to be rendered shall have joints raked out to a depth of 12mm.

The Contractor shall properly execute all rough cutting, bonding, weighting and trimming up to soffits,

plumbing angles, building in or cutting and pinning in ends of lintels, sills, joints and the like.

Any defective blocks found in the works shall be cut out and replaced by sound ones at the Contractor’s

expenses.

5.0 ROOFING

5.1 Roofing

Corrugated Aluminum roof sheeting shall be 0.70 thick long span aluminium of approved profile with

10/3” corrugation and to comply with the relevant BS laid and fixed with aluminum J-bolts, felt washers

in accordance with manufacturers printed instructions and or the drawings and instructions.

5.2 Protection

The Contractor is to case up, cover and adequately protect all roofing work from abrasion, impact, the

action of acid, alkalis, oils or solvents, and is to leave the roof in a sound and clean condition.

Walking on the sheet will not be permitted. Ladders or crawl board shall be used.

6.0 WOODWORK AND IRONMONGERY

6.1 General

All timber for carpenter and joiner’s work shall be approved timber properly seasoned, straight cut, free from

sap, twists, large loose or dead knots etc. and shall conform to BS 1186 Part I. Sawn timber shall hold the full

scantlings specified after being sawn.

Wrought timber shall be finished even, clean and smooth. An allowance of 1.5mm will be made for each

wrought face off the size specified unless otherwise stated.

6.2 Workmanship

All workmanship shall be of the best quality. Carpentry and joinery shall be executed in a workmanlike

manner and where not fully detailed on the Drawings, to details prepared by the Contractor but with

the approval of the Consultants, and shall conform to BS 1186 Part II.

All joinery shall be framed up and stacked in a dry place but it is not to be glued, wedged up or delivered

to site until required in the building. Any joinery, which warps or develops shakes or other defect, shall

be replaced by new one before being wedged up.

Frames shall be properly jointed at corners and mortised, tenoned and wedged in the best manner.

The Contractor shall provide all nails, brads, screws, glass paper and tools etc. for the proper execution

of the works. The heads of all nails, brads, etc. shall be punched below the surface.

The Contractor shall properly execute all fitted ends, mitres, housing, returned ends, junctions of

circular ends and straight end as may be necessary. All skirting’s, architraves and other joinery shall

be accurately scribed to any irregular surface to which they abut.

21

Hardwood fixing plugs 100 x 75mm minimum size or approved metal holdfast shall be built into the

joints of blockwork or cast into concrete for fixing door frames or other joinery at the rate of one 800mm

of height. Minimum of 3 fasteners for each side of each doorframe.

The term plugging includes the provision of hardwood plugs of adequate dimension built, or cut and

pinned, or cast into the wall surface and planted on.

Unless otherwise described on the Drawings, all joinery is to be fixed by screwing.

6.3 Preservative Treatment

All timber and joinery work not to be painted shall be treated with two coats of coloured wood

preservative, or other approved preservative before erection. This includes hidden as well as exposed

roof construction.

6.4 Protect Joinery

All fixed joinery, which, in the opinion of the Consultants, is liable to become bruised or damaged in

any way shall be completely, cased and protected by the Contractor until the completion of the works.

6.5 Cleaning Up

The Contractor is to clear out and destroy or remove all cut ends, shavings, and other wood waste from

all parts of the building and the site generally, as the work progresses and at the conclusion of the work.

6.6 Door and Window Frames

Frames shall be to the sizes and details shown on the Drawings. Frames shall be properly fixed with

iron cramps or fixing slips as detailed above under workmanship.

6.7 Plywood

The Plywood to cupboards, etc. shall be a Grade A W.B.P faced with close grained timber free from

furry patches.

6.8 Carcasing (wall plates, roof framing, etc.)

Wall plates shall be fixed with ½” (12mm) diameter mild steel rag bolts firmly grouted into the block

work beam at (2000mm) centres. All joinery shall be halved. See details Drawings.

All edges, rafters, hips, purlins and other structural woodwork shall be formed from the longest length

of timber obtainable.

Where joints are unavoidable they shall be properly scarfed and wedged, the length of the joint being

twice the depth of the member and shall be secured with 12mm diameter mild steel bolt and knots.

6.9 Defective Work

Where defects occur to joints or members generally, including framed and stored joinery, the work

shall be taken down and repaired or renewed including any necessary making good and redecoration at

the Contractor’s expense and to the satisfaction of the Consultants.

22

6.10 Iron Mongery

Ironmongery shall be supplied from an approved supplier. The ironmongery shall be fixed with

matching undamaged screws.

All joinery shall be properly morticed or worked as necessary for fixing the ironmongery.

6.11 Samples

The Contractor shall, if requested, submit samples of all ironmongery for approval before fixing.

6.12 Door signs

Door Signs shall be as specified by the Client or Consultant samples of materials shall be provided by

the Contractor for approval before use. The materials shall be as specified by Client.

6.13 Protection

All ironmongery shall be protected until completion of the works. Any damaged ironmongery shall be

repaired or renewed at the Contractor’s expense and to the satisfaction of the Consultants.

6.14 Completion

On completion all locks shall be fitted with two keys. The keys shall be properly labelled, paired

together and handed to the Consultants.

All ironmongery is to be oiled and adjusted and left in perfect working order.

7.0 STEEL WORK

7.1 Materials

7.1.1 Steel

The steel generally shall comply with BS4360 weldable structural steels. Rolled mild steel section

shall comply with BS 4848 Part 4: Equal and unequal angles. Hollow sections shall comply with

BS4848 Part 2: hollow sections.

7.2 Sundries

Black bolts, screws and knots shall comply with BS 4190

Close tolerance precision bolts, screws and plain washers shall comply with BS 3692.

Black taper washers shall comply with BS 3410.

High strength friction grip bolts shall comply with BS 4395.

Electrodes shall be grade ‘A’ best heavy coated quality and comply with BS 5639.

7.3 Workmanship

7.3.1 Fabrication

Work off-site shall conform with the appropriate Clauses of BS 449: The use of Structural Steel in

Building.

23

All surfaces in contact and all surfaces inaccessible after assembly shall be treated according to these

specifications before assembly.

7.3.2 Welding

Welding procedure shall comply with BS 1856, BS 938 and BS 2642 as appropriate.

The equipment to be used shall be of a type, which produces proper current so that the welder can

produce satisfactory welds.

Welding in shop and on site shall be carried out by experienced and well qualified welders.

Surface preparation and assembly shall be carried out strictly in accordance with BS 1856 and BS 449

and BS 2642 as appropriate.

7.4 Work on Site

All handling of Works during transport and on the site shall be planned and carried out by the Contractor

to proceed in a manner designed to protect the painted surfaces from damage.

All members stored on site shall be laid out on timber sleepers, kept clean and free from construction

dirt. Markings on individual members shall be visible when members have been stacked together.

The position of all points of support for structural steelworks shall be set so that the distances between

any two points joined by a shop fabricated component of structural steel are within ½” (12mm) of the

required dimension. Individual fabricated members shall conform to a degree of accuracy compatible

with the tolerances laid down by this clause.

The position of any column or support wall shall be set out with a tolerance of 1”(25mm) in

100ft.(30m), but no point shall be more than 1”(25mm) away from the position shown on the Drawings.

The Contractor shall erect temporary bracing as necessary to maintain all structural steelworks in the

correct position until the structure is complete.

7.5 Site Connections

The site bolting of permanent connections shall conform to BS 449.

Washers shall be provided under all knots and all bolts shall show after tightening at least two clear

threads beyond the knot. During the tightening operation, the bolt head shall be prevented from

rotating.

Welding on site will not be permitted without the Consultant’s written approval.

7.6 Protection Against Corrosion

All mill scale and rust is to be removed by hand in accordance with Clause 505f CP 2008: 1966. Two

coats red lead primer are to be applied to all structural steelworks before delivery to site. Any damaged

plain surfaces must be made good on site prior to application of a succeeding coat of paint.

Any surfaces, which will be inaccessible after erection, are to be painted before erection.

24

8.0 METALWORK

8.1 Materials

8.1.1 Steel

Steel shall be as described for structural steel works.

Stainless steel shall be of the best quality and fixing shall be in accordance with manufacturer’s

instructions

8.1.2 Aluminium

Aluminium extruded sections shall be mill finish with surfaces free from blemishes blur or other defects

and shall comply with BS 1474.

8.1.3 Sundries

All sundry items shall be as described for structural steelworks.

8.1.4 Windows and Doors

The windows and doors are to be generally to the approval of the Consultant. The Contractor shall

submit samples of windows, doors and all ironmongery for approval and once approval has been given

the quality of the sample must be strictly adhered to.

8.2 Workmanship

8.2.1 Fixing the Windows

The Contractor shall be responsible for the testing of the windows and shall ensure that sashes when

opened are perfectly horizontal and line through with corresponding blades on the façade of the

building.

On completion of the works, the Contractor shall leave the window carriers in a clean and perfect

working condition to the satisfaction of the Consultants.

Provide all necessary supports and fixing such as screws, strips, lugs and dowels.

8.2.2 Grounds for built-in Metalwork

Where metalwork is specified to be “built-in” or inserted in the position they are to occupy after the

surrounding or enclosing carcass has been constructed, it shall be the responsibility of the Contractor

to ensure that the necessary fixing are incorporated in the carcass.

8.2.3 Alternatively

Construct such ground works as are required to provide a suitable base for the metalwork. Secure built-

in metalwork so that they are plump and true to the shape and dimensions shown on the drawings and

details. Metalwork shall not be fixed in position until after all floor, wall and ceiling surfaces have

been formed or constructed unless otherwise detailed.

8.2.4 Delivery and Fixing

Manufacture, deliver to the site and fix in the buildings all metalwork described in the Bills of

Quantities and as shown on the drawings including the supply and fixing of:-

1. All metal straps, lugs, plugs and dowels

2. All on-site and off-site priming.

3. All furniture specified or shown on the drawings.

25

8.2.5 Protective Coating

All steel that does not have any other form of protective coating, shall be given one coat of red lead

oxide for internal work and two coats of red lead oxide for external work, prior to delivery on site and

the application of the decorative finish specified.

9.0 FLOOR, WALL AND CEILING FINISHES

9.1 Materials

Cement shall be ordinary Portland cement to BS 12.

Coloured cement shall also be of BS 12 and shall be obtained from an approved manufacturer.

Sand shall be sea or pit sand to BS 1199.

Water shall be clean and free from impurities.

Glazed wall tiles and fittings shall be to BS 1281.

Ceramic floor tiles and fittings shall be to BS 1286: 1974.

PVC (vinyl) asbestos floor tiles shall be to BS 3260.

Terrazzo floor tiles shall be to BS 4131.

Soft board for ceilings shall be to BS 1142: Part 3.

Adhesive shall be of approved types.

9.1.1 Storage

All cement and aggregates shall be stored in accordance with the provisions set out in Concrete Work.

If the materials become damaged or are contaminated or have deteriorated, they shall be rejected and

shall be removed from the site immediately at the Contractor’s expense.

9.1.2 Samples

Samples of all tiles and other materials shall be submitted to the Consultants for approval before

ordering.

A sample panel of any finishing shall be prepared for approval, if directed. The applied finish shall not

vary in quality or colour form the approved sample.

9.2 Workmanship

9.2.1 Rendering

Adequate drying time shall be allowed for block walls and concrete surfaces to thoroughly dry before

rendering and no rendering shall commence until the walling and concrete is thoroughly matured and

completely dried out surfaces to be rendered shall have the wall joints raked out to a depth of 10mm

and concrete surfaces shall be hacked to form a key. All surfaces should then be thoroughly brushed

down with a wire brush to remove any efflorescence and all loss and flaky particles, grease or oil

patches and then well soaked with water.

The Contractor shall allow for and perform any necessary dubbing out of surfaces in the same materials

as the render specified and leave the surface ready for rendering.

26

Rendering shall consist of one part cement to six parts of sand by volume mixed dry with sufficient

water added to make a workable consistency for immediate use; each batch shall be used within twenty

minutes of mixing or such shorter period as may be directed.

Rendering shall not be less than 12mm thick overall, unless otherwise directed, generally executed in

the best workmanlike manner and shall be finished fair, true and plump and smooth with a wood float.

Before decoration commences, the Consultant shall approve all plasterwork and any hollow areas,

crack, blisters or other defects shall be cut out and made good at the Contractor’s expense.

All making good shall be cut out to a rectangular shape with undercut edges to form a dovetail key, and

shall be finished flush with surrounding rendering.

All arises and internal angles shall be true level or plump. Angles and arrises shall be pencil round

only. Covered angles and rounded edges will only be permitted when specifically required.

Finishing’s around pipes, brackets, fittings and up to frames, skirting and the like shall be made good

as required and all fittings etc., left clean, tidy and in good perfect order on completion.

9.2.2 Wall Tiles

The walls shall be prepared for tiling in accordance with the recommendation of BS 5385: Part 1:

1976.

Glazed ceramic tiles shall be fixed to rendered surfaces with an approved adhesive in accordance with

the manufacturer’s instructions and finished true and plump. External angles and exposed top courses

shall be provided with round top edge titles.

9.2.3 Cement and Sand Beds and Backings

The cement and sand shall be mixed in the proportions specified. Immediately before laying, the

surface shall be finished over with a grout of one part of cement to one part of fine sand by volume.

The paving shall be placed, levelled with a float and thoroughly compacted with screeding board.

Surfaces shall be finished as described appropriate for the finishing materials to be laid or fixed.

Beds shall be kept damp for at least seven days after laying to allow for proper curing.

9.2.4 Vitrified Colour Ceramic Floor Tiles

Lay tiles strictly in accordance with the manufacturer’s instruction and to the satisfaction of the

Consultants using adhesive specified by the manufacturer.

On completion, run over tiles with a white cement grout, wipe off all surplus and leave clean.

9.2.5 PVC Vinyl Asbestos Floor Tiles

The cement and sand trowelled bed to receive PVC tiles must be absolutely level and to the satisfaction

of the Consultants before tiling may commence.

Lay the tiles strictly in accordance with the manufacturer’s instructions using adhesive specified by the

manufacturer. All tiles must be laid to the complete satisfaction of the Consultants.

9.2.6 Softboard Ceiling

Softboard to ceiling shall be as specified and fixed as shown on the drawings to the complete

satisfaction of the Consultants.

27

10.0 GLAZING

10.1 Materials

10.1.1 Glass

The glass shall be to BS 952; 1964 and free from all defects. Deliver glass to site in proper containers

with maker’s name, guarantee, type of glass and thickness or weight marked on the outside of the

containers. Samples of glass are to be supplied for approval.

10.1.2 Putty

The putty to be metal casement putty by an approved manufacturer. Deliver putty (and glazing

compounds) in original sealed tins, bearing the manufacturer’s labels.

10.1.3 Mirrors

Mirrors shall be 6mm silvering quality polished plate or float glass with damp-proof coating to back

and with polished edges.

10.2 Workmanship

10.2.1 Glazing

Execute all glazing in accordance with the best practices of the trade, generally as laid out in CP 152:

1966.

Timber rebates to be cleaned, primed and painted one coat lacquer. Metal rebates to be cleaned and

primed. Glass to be cut to size with a small clearance and to be back puttied, pegged for metal rebates

and neatly front puttied. Take care to ensure putty does not appear beyond sight lines.

Glass to internal doors and screens and other places where vibration may occur shall be bedded in wash

leather with beds, fixed with brass and sups and screws.

Glaze all windows except toilet windows with float sheet tinted/shatter proof glass as specified. Glaze

toilet windows generally with obscured glass as specified.

10.2.2 Louvre Blades

Carefully cut louvre blades to exact lengths, all edges and corners ground smooth and rounded and set

blades in louvre clips, which shall then be carefully adjusted to hold blades without rattling.

10.2.3 Clearing

Clean the glass inside and outside on completion to the satisfaction of the Consultants. Replace with

new, all cracked, scratched, damaged or defective glass.

10.2.4 Replacement

Provide 1 box per floor of each type of louvre blades specified and hand over to employer on

completion.

11.0 PAINTING AND DECORATING

11.1 Generally

11.1.1 Climate

Advise the manufacturers that the paint is to be used in a coastal tropical climate and obtain their

guarantee of the suitability of materials supplied.

28

11.1.2 Workmen

None other than skilled workmen are to be employed, except apprentices and labourers. A properly

trained foreman is to be constantly on the job whilst the work is proceeding.

11.1.3 Scaffolding

Provide all the necessary scaffolding, tools, appliances and everything else required for the execution

of the work.

11.1.4 Dust Sheets

Provide ample supply of clean dust sheets for the adequate protection of floors, fixtures and surfaces

not to be painted.

11.1.5 Fittings

All metal fittings and fastenings not to be painted are to be removed before the preparatory processes

are commenced, cleaned and refixed in position on completion. Switches and similar items, which

cannot conveniently be removed, shall be completely masked during the painting operations.

11.2 Materials

All paints and paint materials shall be obtained from approved supplier and be of approved brands

suitable for a coastal tropical area.

Primer for concrete, blockwork and rendered surfaces shall be alkali resisting pigmented primer (non-

saponifiable) applied in one coat.

Primer for ungalvanised, unprimed metalwork shall be leadbased priming paint to BS 2523; Type B or

Type C.

Primer for galvanised and sheradised metalwork shall be calcium plumbate primer to BS 3698 Type A.

Primer for woodwork shall be lead free primer to suite the gloss paint.

Linseed oil to be BS 242; 1969.

Stopping to be composed of nine parts putty in accordance with BS 544 to one part of stiff white lead

in accordance with BS 238; 1967.

Knotting to be to BS 1366; 1971.

Woodfiller to be paste type as approved to matching stain colour. Do not mix filler with stain.

Turpentine to be to BS 244; 1962.

Emulsion paint shall be any one of the following types; acrylic polymer, ethylene/vinyl acetate

polymer, versatate co-polymer and shall not be diluted with water except in strict accordance with the

manufacturer’s instructions. The mist coat shall be mixed with a recommended petrifying liquid instead

of water.

Gloss paint shall be ready mixed to the type approved and having a high gloss or enamel finish. The

quality used shall be either exterior or interior quality according to the position of the work. The

manufacturer’s recommended undercoating shall be used.

Proprietary types of paint such as “Sandtex” shall be from approved manufacturers.

29

Deliver paint to the site in the manufacturer’s sealed containers bearing the manufacturer’s names,

guarantees, and type of paint and quality market on the outside.

11.3 Workmanship

11.3.1 Painting Schedule

A painting schedule will be provided prior to the execution of the work to enable work to proceed at

the appropriate time. The schedule will give all the necessary information on colour, type of paint,

surfaces to be coated and method of application.

11.3.2 Combination Coats

Paints and finishes, applied in any one combination of coats for any one surface, shall be provided by

one manufacturer and be guaranteed by him to be satisfactory when used in successive coats, except

for red lead and other metal primer.

11.3.3 Mixing

All paints shall be thoroughly mixed before use, unless there is a specified instruction to the contrary

on the container e.g. does not stir. They shall be so stored as to avoid exposure to extremes of

temperature.

All paints are to be mixed, used and applied strictly in accordance with their manufacturers’

recommendations. For non-specified paints, work shall be executed in accordance with the best

practices of the trade, generally as laid out in CP 231; 1966.

11.3.4 Thinning

Paints shall not be thinned without specified approval but, when necessary, thinning shall be carried

out with the type of thinner and in the proportion recommended by the manufacturers of the paint.

Gloss paints and varnishes shall not be thinned under any circumstances.

11.3.5 Moulds and Mildew

All moulds or mildew must be thoroughly removed from surfaces to receive paint work by the

application of approved fungicidal solution.

11.3.6 Application

Primers shall be applied by brush, subsequent coats by brush, spray or roller as has been previously

agreed. Surfaces must be free from condensation and dusted or wiped with a rag to ensure freedom

from dust or dirt.

Surfaces shall be evenly coated and free from runs, skins, dirt and bristles. Remove all drips, splashes

and overpainting to edges, touch up and make good. Remove all finger marks and leave clean.

11.3.7 Dried and Rubbed Down

All coats of paint shall be thoroughly dry before the subsequent coat is applied. Each coat shall be

rubbed down with fine sand paper.

11.3.8 Weather

No painting is to be done on exterior work when atmosphere is laden with dust, during rainy or misty

weather or on surfaces not thoroughly dry.

11.3.9 Protection

Protect adjacent surfaces from damage, stain and paint splatter. Paint shall be removed from all such

surfaces where not required.

30

11.3.10 Rendered Surfaces (Concrete)

New rendered surfaces shall be allowed the maximum time possible for drying out, no paint shall be

applied until they are thoroughly dry. Efflorescence present on the surface shall be wiped down using

a dry coarse rag, followed by a rag dampened with clean water and allowed to dry off. Surface so

treated shall be inspected after four to seven days to ensure that they are fit for decoration. Each

undercoat shall be rubbed down lightly with glass paper and cleaned down before application of the

following coats. Each coat shall be hard, dry and free from condensation before the next is applied.

11.3.11 Woodwork

Shall not be painted when wet or during or immediately before rains. Joints, tongues, grooves and

inaccessible ends shall be primed before assembly. Door and window frames, etc., shall be back primed

before erection and given two coats on exposed end grains. Woodwork to be painted shall be knotted,

primed and stopped in workshop before delivery to the site or as soon as possible on site and stored.

All top, bottom and side of joinery shall be given the full number of coats specified where accessible.

Large knots to be removed and replaced with sound wood; small knots to be treated with two coats of

knotting. Fill all holes and irregularities and rub down with sandpaper to a smooth even finish. Touch

up priming where damages occur during the works before commencing painting.

Hardwood not required to be painted, clean and rub down with wire wool, apply one coat of

polyurethane and allow to dry. Rub down with wire wool again and apply a further coat of

polyurethane; allow to dry and repeat the process once more.

11.3.12 Metalwork

All unprimed metalwork which is to be painted shall be cleaned down by wire brushing and scrapping,

to remove all possible scale, dirt or grease and shall be primed immediately afterwards.

Prime interior of metalwork with one coat red lead.

Prime exterior metalwork (including stair rails and balustrades) with two coats “approved primer”,

strictly in accordance with manufacturer’s instruction.

Where galvanised surfaces have become damaged, the Contractor shall touch up the damaged areas

with an approved cold galvanising solution before painting.

31

12.0 ELECTRO-MECHANICAL AND INFORMATION & COMMUNICATIONS TECHNOLOGY

(ICT) SYSTEM SPECIFICATIONS

TECHNICAL SPECIFICATIONS FOR THE SUPPLY, INSTALLATION, TESTING AND

COMMISSIONING OF ELECTRO-MECHANICAL AND INFORMATION & COMMUNICATIONS

TECHNOLOGY (ICT) SYSTEM INSTALLATION FOR OFFICE BUILDING AT REGENT ROAD,

HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

32

ELECTRICAL ENGINEERING SERVICE INSTALLATION

CONTENTS

1.0 TENDER CONDITIONS

2.0 DESIGN CRITERIA TENDER SPECIFICATIONS

3.0 ELECTRICAL ENGINEERING SERVICE INSTALLATION

4.0 SCHEDULE OF APPENDICES

33

1.0 TENDER CONDITIONS:

1.1 Introduction

The purpose of this document and supporting drawings/data is to illustrate and describe the Contract

Works associated with the Electrical Engineering Services (EES) Systems + Applications.

The information contained in the Technical Specification and depicted on the Drawings is for the

purpose of obtaining a competitive Tender for the EES Contract Works

The Contractor must allow for liaising with other trades to ensure that the EES Installation is properly

coordinated / integrated into the Contract Works / Building Complex as a whole.

It is recommended that the Contractor visits the site in order to acquaint himself with the existing site

conditions, (access, existing site infrastructure services etc.), that might affect his Tender.

No claim arising out of any misunderstanding or neglect shall be considered.

1.2 Extent of the Contract Works

The EES Contract Works shall include all the necessary labour and materials and all

construction/building works, together with such tests, adjustments and commissioning of the electrical

engineering services systems and applications as are required to form a “complete installation”.

The BES Contract Works “Complete Installation” shall mean not only the major items of plant and

equipment detailed in this Document, but all of the incidentals/sundry components required for the

complete execution of the Contract Works.

1.3 Contract Works: Design Development

The Contractor shall be responsible for carrying out the design development work in connection with

the EES Contract Works; this is in addition to that of the fundamental design of the electrical

engineering services systems and applications specified within this Document and supporting

drawings/data.

The Contractor shall allow, within his Tender, for the following particular design development

calculations:

(i) Lighting

To determine the required number of circuits, protection devices and cable sizes, based upon the

completed lighting installation drawings developed.

(ii) Small Power Requirement

To determine the required number of circuits, protection devices and cable sizes, based the

completed small power installation drawings developed.

(iii) Distribution Boards

To determine the required rating of protection devices, cable sizes and appropriate load balancing

illustration, based upon the completed lighting and small power installation drawings developed.

(iv) Incoming Electrical Power Supply (Panel board)

To determine the required rating and size of MCCB’s and associated protection devices/cable sizes

based upon completed installation drawings and electrical schematic diagram.

The Contractor shall provide the M+E Engineer with the design development drawings / data for

his consideration, prior to the ordering of any capital plant.

The accuracy of such information, as submitted, shall remain the responsibility of the Contractor.

34

1.4 Contract Works: Named Plant, Equipment+ Materials

The fundamental design of the EES Systems + Applications has been based upon the named

manufacturers/suppliers of the plant, equipment and materials, as recorded within this

Document.

The operating characteristics, performance and overall quality of the named plant, equipment and

materials have been validated against the design criteria, setting the minimum standard to be achieved.

The overall space planning of the building complex has taken into account the physical weight

dimensions of the named plant and equipment, together with the space required around the plant and

equipment for maintenance and the future replacement of the individual components and /or their

complete renewal.

Items of plant and equipment, as named, have been sourced from a number of international

manufacturers/suppliers, acknowledged as having had experience in providing equipment suitable for

the intended use/application, with proven longevity under operation in harsh climatic conditions.

The Contractor shall be at liberty to consider alternative manufacturers / suppliers; in doing so, the

Contractor is required to complete the Tender Declaration Form – Plant + Equipment and to submit the

latter with his Tender.

In submitting alternative names, the Tenderer shall be expected to have checked that his proposed

manufacturers / suppliers’ plant and equipment satisfies the overall performance, quality and

dimensional requirements when compared to the manufacturer / supplier as named within this

Document.

The Contractor shall be required to provide, at the time of submitting his Tender, full technical details

of any proposed alternative manufacturer / supplier of the following:

(i). Main Electrical LV Panel board, Fused Switch Disconnectors + Distribution Boards

(ii). Lighting Fittings and Switches

(iii). Small Power Requirement

1.5 Contract Works : Regulations and Standards

The EES Installation shall comply with the Technical Specification (s) set out within this Document

with all relevant British Standards and Codes of Practice and with all other relevant Statutory

Instruments and Regulations current at the time of Tender.

1.6 Contract Works: Materials and Workmanship

All materials must be suitable for their intended use/application and must comply with the relevant

Standards and be installed in accordance with the Codes of Practice and Manufacturer’s

recommendations.

All site operatives must be suitable qualified and experienced for the work that they are assigned to

carry out. All workmanship must be of a good standard.

The Project Architect and the M+E Engineer shall reject poor materials and workmanship and it shall

be the contractor’s responsibility to put right such rejected Contract Works at his own expense.

1.7 Contract Works: Programme

The Contractor shall allow adequate time within his overall Contract Works Programme for presenting

and receiving comments to / from the Project Architect / M+E Engineer with respect to:

i. Design Development Information

ii. Installation Drawings

iii. Testing and Commissioning Procedures

35

1.8 Supervision of the Contract Works

The Contractor shall employ a competent, qualified and experienced Principal Resident Site Engineer,

who shall be in charge of the Contract Works during all working hours and in attendance until the

whole of the Contract Works has been completed and accepted on behalf of the Employer/User.

The Contractor’s appointed representative shall attend meetings on site and be empowered to answer

on behalf of the Contractor.

The Contractor shall appoint a Deputy Site Engineer to cover for periods of absence of the Principal

Residence Site Engineer.

1.9 Coordination of the Contract Works

The Contractor shall be responsible for the coordination of the all Electrical Engineering Services

Systems, such that each may be installed in a manner which ensures the correct performance of the

system and avoids conflict in the positioning of the various Building Engineering Services (BES)

elements.

The Contractor shall include within his Tender for the detailed development of his Installation

Drawings to contribute to a fully coordinated and integrated BES Installation.

1.10 Contract Works: Installation Drawings

The Contractor shall prepare and submit to the Project Architect/ M+E Engineer, Installation Drawings

for all of the EES systems to be installed under the Contract Works, together with such schedules, data,

calculations, systems schematics and other supplementary details necessary to execute the Contract

Works.

The Installation Drawings shall be fully detailed, depicting the positions and physical dimensions of all

of the BES Systems Components.

The minimum scale for the production of the coordinated Installation Drawings shall be:-

LV Panelboard Switch room: 1: 20

Floor Plans 1: 50

Site Services 1: 200

The Contractor shall make due allowance for the preparation of the EES Installation Drawings within

his Tender and within his Overall Contract Works Programme

1.11 Contract Works: Fixing of the Services Installation

The Contractor shall be wholly responsible for the sizing, supply and installation of all supports/fixings

for the electrical engineering services.

1.12 Contract Works: Builders Work Builders Work in connection with (BWIC) the EES Contract Works, such as duct, holes, basses, chasses

etc. shall be detailed by the Contractor as separated drawings.

The Contractor shall inform the Project Architect/M+E Engineer of any BWIC that may affect the

building structure and/or envelope.

The Contractor shall make due allowance for the detailing of the BWIC requirements within his Tender

and within his overall Contract Works Programme

36

1.13 Contract Works: Testing and Commissioning

The Contractor shall ensure that suitably qualified and experienced personnel, together with the

necessary instrumentation, are available at the time required to set to work, test and commission the

mechanical and electrical engineering services systems.

The format of the testing and commissioning procedure, together with the details to be entered on the

test sheets, shall be agreed with the M+E Engineer.

The Contractor shall agree with the Project Architect/M+E Engineer a Programme for the testing and

commissioning of the various EES Systems.

The M+E Engineer shall retain a detailed record of all the testing and commissioning procedures on

site for examination.

The testing and commissioning shall demonstrate, amongst other things, that:

(i) All electrical circuits are properly electrically and physically protected and earthed.

(ii) All electrical switchgears are neatly positioned, leveled and secured.

1.14 Contract Works: Record Documentation

The Contractor shall supply to the Project Architect/M+E Engineer, as a prerequisite to the Practical

Completion of the Contract Works, a comprehensive record of the completed mechanical and electrical

engineering services installation. This shall take the form of:-

i. AutoCAD based disk detailing all INSTALLATION DRAWINGS.

ii. 4 No. Dyeline prints of all INSTALLATION DRAWINGS.

iii. 4 No. Bound A4 copies of the OPERATING + MAINTENANCE MANUALS, to include:-

a) Copies of all testing and commissioning certificates.

b) Manufacturers/Suppliers technical data for the maintenance and operation of all plant and

equipment, together with a schedule of spares provided.

c) Schedule recording all installation drawings.

The Contractor shall maintain accurate records of all testing and commissioning procedures throughout

the course of the Contract Works for incorporation into the O + M Manuals.

The Contractor shall have available a DRAFT COPY of the Record Documentation for inspection by

the Project Architect/M+E Engineer prior to Practical Completion of the Contract Works.

1.15 Contract Works: Instruction of Employer’s Staff

The Contractor shall include within his tender, under the heading “Record Documentation”, from the

instruction of the Employer’s Appointed Maintenance Staff on the operation of the EES Systems, to

include emergency/breakdown procedures.

The instruction shall take place following the testing and setting to work of the EES Systems.

A “Draft” copy of the Operating + Maintenance Manual shall be made available for review by the

Employer’s representative during this period.

1.16 Contract Works: Variations

All instructions, variations, additions to the Contract Works are only valid when agreed to/signed for

by the Project Architect (Manager).

Should the Contractor receive, during the progress of the Contract Works, any instruction for additional

work, Which he considers may affect the completion of the Contract Works within the prescribed

Contract Period, he shall be required to formally notify the Project Architect in writing within seven

days of the receipt of such and instruction.

37

1.17 Contract Works: Practical Completion

The Contractor shall be responsible for inspecting the EES Installation and shall have prepared his own

defects inspection list and shall duly attend to the same, prior to offering the completed EES Installation

to the Project Architect (Manager) for inspection and acceptance on behalf of the Employer.

The Project Architect/M+E Engineers’ inspection shall be one of formality and should not be

considered as an inspection for the purposes of forming the Contractor’s final list scheduling the

Outstanding Works.

The Contractor shall agree with the Project Architect/M+E Engineer, a suitable date for the FINAL

INSPECTION.

1.18 Maintenance of Services

Any works necessitating interruption or termination of any services required to be maintained or

serving areas outside of the designated works area shall be thoroughly coordinated and not be initiated

until a Programme of works indicating disruption time scales and/or temporary arrangements has been

submitted and agreed fully by all concerned.

1.19 Contract Works: Defects Liability Period

The Contractor shall be responsible under the Contractor for addressing/correcting all of the EES

Contract Works defects occurring within a period of SIX MONTHS, commencing from the date of the

PRACTICAL COMPLETION CERTIFICATION.

During the Defects Liability Period, the Contractor shall provide prompt and effective “call back”

service to attend to any urgent faults which may develop and which would affect the day-to-day

function of the building complex and facilities.

The Contractor shall retain a written log on site recording the details of the defect – i e, date notified/date

attended, fault identified, action taken, together with any ongoing investigations/remedial work.

1.20 Contract Works: Provisional Sums

Provisional Sums have been entered on the Electrical Engineering Services Installation – Tender

Breakdown – Form of Tender Document.

These Provisional Sums provide for Works of Costs, which cannot be foreseen, defined or detailed at

the time of preparing the EES Contract Works Tender Documentation.

The Provisional Sums include for the Contractor’s overheads and profit and therefore are to be included

in the Tender Breakdown as net sums without any further additions.

Instructions as to the deduction of expenditure in whole or in part of the Provisional Sums shall be

instructed by the Project Architect (Manager) during the course of the Contract Works, as found

necessary.

1.21 Contract Works: Schedule of Rates The Contractor shall submit within his Tender, a priced copy of the Schedule Rates.

Each of the elemental rates shall include for all necessary labour and materials, together with overheads

and profit.

The declared Tender rates shall be used to evaluate all Works added, deleted and/ or amended against

the Contract Works Tender.

The Project Architect (Manager) reserves the right to reject any tender which does not include the

completed Schedule of Rates, returned with the Tender Submission.

38

1.22 Contract Works: Tender Breakdown

The Contractor shall, when submitting his Tender for the Contract Works, enter on the Tender

Breakdown – Form of Tender Document, Lump Sum Costs for each of the Electrical Engineering

Services elements as prescribed.

The Project Architect reserves the right to reject any Tender, which does not include the completed

Tender Breakdown.

39

2.0 TENDER SPECIFICATIONS:

2.1 Introduction:

2.2 General:

The Power Distribution System (PDS) for the Office Building at Regent Road, Hill Station, Freetown for

Sierra Leone Field Office at the African Development Bank (ADB) is to be supplied from a 250A, 12-

way MCCB LV Panelboard located in the LV Panelboard Switchroom. The entire electrical system shall

be based on a 230/400V, 3 phase and neutral, 50 Hz, Terra Neutral- Separate (TN-S) system.

2.3 Regulations and standards

The complete installation shall comply with all relevant British Standard and, where indicated, with other

standards and specifications and all amendments thereto. A Certificate of compliance shall be provided

for the Project Architect, to be included in the handover.

2.4 Design parameters

Division of installations:

The installation shall be divided into circuits as necessary to:

a. Avoid danger and minimize inconvenience in the event of a fault

b. Facilitate safe inspection, testing and maintenance

c. Take account of hazards that may arise from the failure of a single circuit such as a lighting circuit

d. Reduce the possibility of unwanted tripping of Residual Current Devices (RCD) due to excessive

protective conductor current not due to fault

e. Mitigate the effect of electro-magnetic disturbances

f. Prevent the indirect energizing of a circuit intended to be isolated

3.0 Prospective fault current (Pfc)

If a protective device is to operate safety, its rated short-circuit capacity must be not less than the

prospective fault current at the point where it is installed.

The distributor needs to be consulted as to the prospective fault current at the origin of the installation.

4.0 Earth loop impedance external (Ze)

The Ze is to comply with British Standards.

5.0 Voltage droop

The voltage drop between the origin of the installation and a lighting point should not exceed 3% of the

nominal voltage and for other current using equipment or socket outlets should not exceed 5%

6.0 Electrical installation:

6.1 General.

The contractor shall procure, install, inspect, test and commission the entire electrical system within the

proposed building as stated within this Specification and associated drawings.

6.2 Main supply.

The main supply should comprise of a TN-S system at 400V, 50 Hz. The incoming supply cable from

the Dedicated Power Transformer located within the Generator House should be run and terminated to a

250A TP&S Fused Switch Disconnector located in the Transformer Room and cable run underground

via a service duct system as shown on the drawing.

The contractor is to liaise with the Electrical Distribution Service Authority (EDSA) to arrange for a

Permit to Work for the connection of the main supply cable to and from the Power Transformer.

40

The HT cable is to have the following characteristics complete with indoor termination kits as required

and in accordance with Local Regulations:

a. Be a minimum 120mm2, 3 core, XLPE/PVC/PVC cable with wire shield rated for 0.6/11kV

b. Have a current carrying capacity of 285 Amps at 320C ambient temperature

The LV supply from the Transformer should be terminated to the ATS-2 through a TP&N Fuse

Disconnector Switch located within the Transformer Room. The LV supply cable from the ATS should

then enter the building through a uPVC pipe or similar.

The LV cable is to have the following characteristics complete with cable lug termination as required and

in accordance with International/Local Regulations:

a. Be a minimum 95mm2, 4 core, XLPE/PVC/SWA/PVC cable rated for 0.6/1kV

b. Have a current carrying capacity of 250 Amps at 320C ambient temperature

7.0 Electrical service ducts

7.1 Service duct detail.

The supply cable is to be laid or drawn through a combine services duct.

7.2 Trenching:

No work shall commence until the Contractor has taken all reasonable steps to ensure that the area is free

of all cable, drains and other services. A cable Avoidance Tool (CAT0 and Signal Generator (Genny) or

any other equivalent cable detector tool is to be used to detect services. Unless otherwise indicate the

following is required:

a. Excavations within 600mm of existing services shall be by handing digging. Any damage to

services shall be reported immediately to the Project Architect/M&E Engineer. No repairs or

replacement shall be done unless the Project Architect/M&E Engineer gives approval. All works

will be at the Contractors expense.

b. Cables shall be buried at a sufficient depth to avoid being damaged by any disturbance of the ground

reasonably likely to occur. Trenches shall be excavated to the depth specified by the Project

Engineer.

c. All cable enclosed within trenches are to be installed in accordance with the recognized

specification. The Contractor shall ensure an accurate record of the location is made and passed to

the Project Architect/M&E Engineer

d. Warning tapes and covers. A traceable warning tape shall be placed above the cable duct.

The following will be required:

e. The tape shall be laid at a depth of 300mm below the finished surface level except where the depth

of paved area exceeds 300mm in which case the tape shall be laid immediately below the base.

f. Warming tapes shall be traceable and be not less than 150mm wide and 0.1mm thick.

They shall be yellow in colour and bear continuously repeated legend ‘CAUTION ELECTRIC

CABLE BELOW’’, or similar, in black letters.

g. Service entry:

Cable entry to the building shall be installed in a cable duct. The cable duct is to be sized and located

in a suitable location. The cable duct is to be sealed with appropriate material to prevent the ingress

of moisture or vermin. The bore shall be smooth and entirely free from rough spots and sharp edges.

41

Correct size of duct shall be sized for the cable to be drawn in and the bending radius of the cable

shall comply with the manufacturer’s instructions.

8.0 LV electrical equipment

8.1 General:

All intake equipment is to be installed indoors. The main supply is to be installed via a lockable isolator

before entering the distribution board.

8.2 Main intake isolator:

The main intake isolator will be installed directly below the distribution board. The isolator is to have the

ability to be locked off in the OFF position.

8.3 Distribution board:

The distribution board shall comply with the relevant British Standards as well as the follow:

A It shall be suitable for surface mounting or concealed in blockworks, have lockable doors (supplier

with two keys) and be controlled by an on-load integral disconnector.

Keys shall be labelled and handed to the Project Architect/M&E Engineer at practical completion.

B Where spare ways are provided they shall be fitted with blanking pieces

C All neutral and earth connections shall be made to bars within the distribution board each

connection having an individual terminal. The neutral shall have a removable link to facilitate

testing.

D The connections to the neutral and earth bar shall be made to correspond with the order of the phase

connection.

E All conductors terminated at the board shall be appropriately marked with cable ring markers

indicating the circuit number and phase connection.

F All covers, doors and access plates into the distribution board shall be gasketed to achieve a

minimum protection of IP 32.

G Access for cabling shall be from the front only. Shrouding to IP2X shall be fitted to prevent

accidental contact with live parts. Warning labels shall be provided and fixed.

H There shall be a circuit schedule identifying each circuit giving reference, description, rating of

protective device and connected load located inside the distribution board

I The circuit schedule shall be typed on an A4 sheet laminated and securely fixed to the inside of the

distribution board door.

8.4 Protection. Protection against electric shock for the electrical installation will be by means of automatic

disconnection of supply. Each protective device is to be identified. Identification on neutral bus bar and

protective conductor bar shall clearly relate each terminal to its respective device. Overload protection

will be provided by the use of the following devices.

A. Miniature Circuit Breakers (MCBs) MCB shall comply with BSEN61008-1:2012 and have the

following characteristic:

(i) Doors shall have a locking system or shall require a special tool for the opening and have a

minimum rated short circuit capacity (1cn) of 10kA unless otherwise specified.

(ii) MCBs shall be capable of withstanding calculated operational and fault currents as well as

calculated power frequency stress voltages.

(iii) Three phase MCB shall trip all phases on any fault condition.

(iv) Provision shall be made to enable the operating mechanism to be padlocked in the OFF position.

42

B. Residual Current Breaker with Overload Protection (RCBO’s).

All 13A socket outlets within the Office Building at Regent Road, Hill Station, Freetown for Sierra

Leone Field Office at the African Development Bank (ADB) shall be connected through Residual

Current Breaker with Overload Protection (RCBO’s).

All RCBO’s shall comply with BS EN 61009-1:2004+14:2012 and have the following

characteristics:

(i) RCBOs shall be capable of withstanding calculated operational and fault currents as well as

calculated power frequency stress voltages.

(ii) The units shall be double or triple pole as required and mounted enclosed within the

distribution board.

(iii) The RCBO shall automatically open the protected circuit on an earth leakage fault between

phase and earth equal to or greater than the fault current sensitivity rating of the device.

(iv) The operating mechanism shall be independent trip- free and shall not be able to be held closed

against an earth fault. The units shall be complete with a test button and trip re- set device.

(v) The RCBO shall have position contact indication whereby the opening of the device is clearly

indicated by a mechanical indicator. This indicator shall be linked to the device main contacts

to show the positive opening of poles.

8.5 The ratings and type of protective devices can be found in the Electrical Distribution Board schedules.

8.6 Labelling:

The Contractor shall ensure they label the following:

a. Lighting and Emergency Exit lighting.

All emergency test key switches shall be labelled EMERGENCY LIGHT.

b. Switches and outlets.

All switches, socket outlets and isolators are to be labelled with their associated circuit numbers i.e.

DB1/1/L1.

8.9. Circuit diagram:

On completion of the electrical system installation, as built drawings of the circuit layouts are to be

produced and be included in the Health and Safety File and issued to the Authorities at the Sierra Leone

Field Office at the African Development Bank (ADB) during the handover.

9.0 Final circuits

9.1. General:

All fixtures and fittings shall be securely fixed and checked before and after Installation for defects and

damage. All defective fittings shall be replaced. All socket outlets shall be run as ring final circuit.

9.2 Sockets:

Socket outlets shall comply with the relevant British Standard for the type of outlet indicated. Socket

outlets shall be of the type and rating as indicated. PVC and metal sockets are to be selected dependent

on the room function. All other areas are to be fitted with PVC and store areas are to be fitted with metal

outlets (PVC conduit, back box and faceplate).

9.3 Mounting heights:

Socket outlets shall be mounted at a height of 400mm above FFL and located in positions shown on the

associated drawings.

43

9.4 Fixed power circuits:

All fixed power shall be supplied by redials. The split Air Conditioning Units ACU’s are to be supplied

via individual radial circuits dedicated to each ACU. The split Unit ACU’s are to have lockable rotary

isolator switches for the external condenser.

9.5 General. Lux levels are to be achieved as specified. The light fittings are to be of a sufficient IP rating to

protect against dust and insect ingress. The lights to be used are detailed in the lighting drawings, capable

of achieving the light levels as design.

9.6 Emergency lighting:

Emergency lighting systems and equipment shall comply with BS 5266-1:2011. The emergency lighting

should be integral to the entire lighting system. The emergency lighting shall have the following:

a) Emergency escape lighting:

Emergency escape lighting shall provide illumination for the safety of personnel leaving a location

or attempting to terminate a potentially dangerous process before doing so. In the event of power

failure a minimum of 1 LUX level is to be maintained at floor level for duration of 3 hours. The

emergency escape lighting is to be provided by maintained emergency luminaires that shall have

their lamps energized during normal use or in the event of power failure. The battery backup shall

be permanently connected to a circuit supply via a temper proof test switch, without interruption by

local functional switching.

b) Emergency escape route lighting:

The emergency escape route lighting shall ensure that the means of escape can be effectively

identified and safety used when the premises are occupied. The emergency escape route lighting is

to be provided by non-maintained emergency luminaires with pictogram and shall energize their

lamps during the event of a power failure. The battery backup shall be permanently connected to a

circuit supply, via a tamper proof test switch, without any functional switching. Fluorescent

Emergency Exit signs are to be located over each external access doors. The area immediately

external of the door is to be illuminated to a distance of 10m at a level of 1 Lux.

9.7 Switches:

Switches shall comply with the relevant British Standard for the type of switch indicated. Switches

shall be single pole for single phase circuits and the current rating shall be the room. All other areas are

to be in PVC and store in metal clad fittings. Switches are to be mounted at 1400mm above FFL.

10.0 Cable containment

10.1 General:

The size of the containment shall be calculated in accordance with BS 7671+A2:2013. Conduit,

including flexible and pliable conduits shall be non-metallic and comply with the relevant British

Standards. When circuits are run in containment the following shall apply:

a. Trucking shall comply with BS 4678-4; 1982 and be 50 x50mm in size

b. PVC Conduit shall comply with BS EN 50086-2-1:1996 and BS 4568-1; 1970 and be 20mm and

50mm in diameter.

10.2 Trunking general:

Where trunking is required to pass through wall fabrics it shall be fitted with suitable and approved

flame proof fire barriers.

44

10.3 Supports and joints:

The trunking shall be installed in the ceiling void and secured to the trusses and in vertical service ducts

and secured to the wall surface. Expansion couplings shall be protective where trunking crosses any

expansion joints within the building fabric.

10.4 Bonding:

The metallic trunking must be bonded to earth and tested for continuity but must not be used as a means

of providing the protective conductor

10.5 Access and covers:

Trunking and fittings shall have removable lids along its entire length. The lids shall be of the same

material, thickness and finish as that of the trunking.

10.6 Conduit general:

Metallic conduit shall have screw threads for jointing length to length and for the attachment of

accessories, PVC conduit shall use female couplers. Conduit and fittings shall be screwed to the

building fabric unless indicated and approved by the Project Architect/M&E Engineer. High impact

areas shall have galvanized steel conduit and all other areas shall be PVC. Adequate protection against

corrosion shall be provided to steel conduit.

a Supports, Junction boxes and back boxes installed in conduit runs needs to be separately fixed to

underlying surface and not rely on the efficient saddling of conduit for their support. A spacer bar

saddle shall be fixed 150mm adjacent to any junction or back box. Fixing saddles shall be positioned

at a maximum of 1200mm apart or 300mm from conduit outlet boxes or changes in direction.

b Bends. Steel conduit shall be bent on site to the required shape to allow the conduit to run around

obstacles and corners. All conduit bends shall be achieved without distorting the diameter of the

conduit. Conduit bending shall be by means of a good quality conduit bending machine, in good

condition and any poor or damaged conduit bends shall be rejected.

c Couplers, bushes ad glands. Bushes and glands used in conjunction with conduits and conduit

accessories shall be appropriate to the type used. Conduit connected to galvanize steel trunking,

back boxes and fluorescent fittings shall utilize a coupler and male brass bush. The male bush is to

be fitted by the appropriate methods.

d Saddles, Spacer bar saddles shall be used for fixing conduits to surface walls and ceilings. In all

cases the conduit is to be run parallel to the building lines and shall be fixed in position at intervals

of not more than 120mm by means of spacer bar saddles and these saddles shall be fixed by the

appropriate methods.

e Access and covers. Covers for conduit boxes shall be appropriate to the type used.

11.0 Cable

11.1 General:

All cable types shall be certified and marked in accordance with the British Approvals Services for

Electrical Cables (BASEC) or equivalent. Cables shall be segregated from other services and shall

comply with IEE Specification 034.

11.3 Cable routes:

Cables installed on the surface shall be parallel with the lines of the building construction and properly

aligned. Cables buried below ground shall, as far as is practicable, follow the features of the site such

as building lines.

45

11.4 Cable segregation:

A minimum clearance in accordance with IEE Specification 034 shall be allowed from any equipment,

pipework or ductwork. In the event of difficulty in achieving these requirements the M& Engineer shall

be consulted. Adequate space shall be left between cable runs building fabric and other services to

allow for the future removal or installation of cables.

11.5 Cable Cleats:

Cable cleats shall be made from materials that are resistant to corrosion without the need for treatment

or special finish. Plastic materials shall be non-brittle. Cable cleats shall be of a suitable size such that

they can be tightened down to grip the cables without exerting undue pressure. The spacing of cable

cleats shall comply with BS7671+A2:2013. On each side of a bend, cable cleats shall be used to secure

the cable.

12.0 Protective conductors and bonding

12.1 General:

Automatic disconnection of the supply is the method of protection utilized for basic and fault

protection. Therefore, all protective conductors and supplementary bonding is to ensure that, in the

event of a fault, sufficient current flows to operate the protective devices i.e. MCBs or RCD/RCBOs

12.2 Earth conductor:

In accordance with BS 7671+A2:2013, the minimum cross sectional area of the protective conductor

shall be half the cross sectional area of the line conductors.

12.3 Supplementary bonding:

Supplementary bonding conductors shall be installed to all exposed metal conductive parts. In any part

of the installation where the earthed metalwork of the electrical system comes into contact with the

metalwork of any other services, structure or equipment a permanent earth bond shall be formed as

close as is practicable to the point of contact.

13.0 Inspection testing and commissioning

13.1 General:

During erection, on completion and before being put into services the electrical installation shall be

inspected, tested and verified, so far as is reasonable practicable that the requirement of BS 7671 + A2

:2013 have been met. The verification shall be made by a competent person and shall include

comparison of the results with the relevant criteria and regulations. On completion of the verification

all relevant documentation shall be prepared.

13.2 Inspection:

The inspection shall precede any testing of the installation and shall be carried out by a competent

person with that part of the installation being disconnected from the electrical supply

13.3 Live testing:

Live testing shall only be undertaken once suitable precautions have been put in place. Calibrated

equipment and suitable personnel protective equipment must be used.

Although live testing is a recognized method, under no circumstances is any rectification to be carried

out live.

13.4 Safety:

It is the responsibility of the test engineer to ensure their own safety and the safety of others whilst

working through the test procedure. Prior to testing the installation the test engineer is to ensure the

following precaution, are taken:

46

a. Equipment.

The tester must have knowledge and experience of the correct application and use of the test

instrumentation, leads, probes and accessories.

b. Standards.

All test equipment must meet the safety measures and procedures laid out in Health and Safety

Executive Guidance Note GS 38 for all instruments, leads, probes and accessories.

13.5 Inspection and test procedure.

The inspection and testing of the new installation shall include the following:

a. Prior to energizing. Before energizing the following procedure is to be followed:

(1) Visual inspection as laid down within the current edition of BS 7671 +A2:2013

(2) Continuity of protective conductors, including main and supplementary bonding

(3) Continuity of ring final circuit conductors, including protective conductors

(4) Insulation resistance

(5) Polarity (by continuity method)

b. During energizing. With the supply connected and energized the following procedure is to take

place:

(1) Check polarity of the supply, using an approved voltage indicator

(2) Earth fault impedance

(3) Prospective fault current measurement

14.0 Certification and forms of completion

14.1 General:

The Contractor is to prepare all forms of completion. Current editions of forms are to be used from BS

7671+A2:2013

14.2 Commissioning:

The Contractor shall be responsible for carrying out all inspection and testing of the installation in

accordance with BS 7671+A2:2013. The Contractor is to complete their requirement sections of the

commission forms and present them to the Project Architect/Engineer for submission to the Bank.

14.3 Results.

All results obtained during the test procedure are to be recorded on the Schedule of Test Results for the

distribution board for future reference and checked for acceptability against the prescribed criteria. All

failed measurements are to be highlighted to the Engineer/Bank at the earliest prepared to accompany

the Schedule of Test Results. All documents are to be included in the Health and Safety File and issued

to the Bank during the handover board.

14.4 Emergency lighting.

All emergency lighting is to be tested and certified in accordance with BS 5266-1:2011. All test results

are to be presented as part of the H&S File. The emergency lighting system is to have the following

certificates completed and presented as part of the Health &Safety File:

a. Emergency lighting completion certificate:

To BS 5266-1:2011 Annex C emergency lighting completion certificated by the Contractor’s

Engineer

b. Design declaration of conformity:

To BS5266-1:2011 Annex C declaration of conformity to be completed by the Contractor’s

Engineer

47

c. Installation declaration of conformity:

To BS 5266-1:2011 Annex C installation declaration of conformity to be completed by

Contractor’s Engineer

d. Verification- declaration of conformity:

To BS 5266-1:2011 Annex C verification of conformity to be completed by the Contractor’s

Engineer

e. Periodic inspection and test certificate:

To BS 5266-1:2011 Annex D periodic inspection and test certificate to be completed by the

Contractor’s Engineer with assistance from the Bank Facility Manager.

48

3.0 ELECTRICAL ENGINEERING SERVICE INSTALLATION

3.1 Incoming Electrical Power supply

3.2 Low Voltage Panelboard

3.3 Low Voltage Distribution Boards

3.4 Lightning Protection System

3.5 Earthing + Bonding

3.6 Structured Cable Management System (SCMS)

49

3.1 Incoming Electrical Power Supply

System Description

System Drawings + Data

SL/ADB/E-1: Block Schematic Layout Power Supply & Distribution Network

SL/ADB/E-2: Line Schematic Layout Primary / Secondary LV Distribution Network

Appendix 1: Schedule of Incoming Electrical Power Supply from the LV Panelboard located in

Panelboard Switch Room (MCCB-1, MCCB-2, MCCB-3, MCCB-4, MCCB-5, MCCB-6, MCCB-7,

MCCB-8, MCCB-9, MCCB-10, MCCB-11, MCCB-12)

MCCB-1 Raw Power Distribution Board 1 – Basement Floor

MCCB-2 Raw Power Distribution Board 2 – Basement Floor

MCCB-3 UPS 63A, TP&N Fuse Switch Disconnector (UPS Distribution Board 1 & 2 for

all UPS Socket outlets + UPS Consumer Unit 1 – Basement Floor (Security

equipment’s)

MCCB-4 Raw Power Distribution Board 3 – Ground Floor

MCCB-5 Raw Power Distribution Board 4 – Ground Floor

MCCB-6 Raw Power Distribution Board 5 – First Floor

MCCB-7 Raw Power Distribution Board 6 – First Floor

MCCB-8 Roof Top VRV Outdoor Unit 1

MCCB-9 Roof Top VRV Outdoor Unit 2

MCCB-10 Roof Top VRV Outdoor Unit 3

MCCB-11 63A, TP&N Fuse Disconnector Switch – Lift – LV Switchroom

MCCB-12 SPARE

System Plant, Equipment + Materials

3.2 Low Voltage Panelboard:

The Low Voltage Panelboard shall be located in the LV Panelboard room at the Main Office Building.

The Panelboard shall be arranged for bottom entry of supply cable. Include for all necessary cable

termination glands required to support the cable and shall incorporate all the MCCB switches, meters,

time switches and instruments as indicated on the drawings.

The 12 Way 250A Triple Pole and Neutral MCCB Panel board Complete with 250A Four Pole MCCB

Incomer Fitted shall be designed to operate on 400 Volt, 50Hz, three phase, 4 wire TN-C or TN-C-S

systems

3.2.1 General Characteristics

Cable Entry Top and Bottom Endplates Removable For Ease of Cutting

Current Rating 250A

Depth 170 mm

Height 1450 mm

Width 900 mm

Incoming Terminal Capacity M8 Bolts 120mm Square Cable and Earth M10 Bolt

Mounting Wall Mounted

Number of Outgoing Ways 12 Way

Product Range MC Range MCCB Panelboard

Standards BS EN 61439 pt 1&2

Switchgear Fitted Four Pole MCCB Incomer 250A

Equipment Type Fixed Stationary

50

Covers/Door Screw fixed covers. Side hinged door (removable) c/w plastic

turn catches.

Enclosure 1.6mm Cold rolled steel with an epoxy paint finish to RAL7035

matt grey. Bolted construction giving Form2B type 2 and

Form3B type 2 group mounted segregation to BS EN 61439:Pt1

and 2:2011

Frequency 50HZ

Breaking Capacity 36kA Icc.

Rated Operating Voltage 230/400V ac.

Protection Class IP Rating IP3X

Operating Ambient Temperature -5 to +40 C

Terminal Tightening Torque M8 Bolt 20Nm max, M10 Bolt 40Nm max.

Short Circuit Making Capacity 36kA Icc.

Number Of Ways 12 Way

Number Of Poles Triple Pole And Neutral

3.2.2 Fault Rating

The Panelboard shall be constructed and type tested to withstand a fault level of 50KA for 1 second in

accordance with BSEN 60439-1

3.2.3 Construction General

The Panelboard shall be modular sheet steel, minimum 2mm thickness, cubicle built on a rigid,

self-supporting framework with compartments separated by barriers of a minimum 1.6mm thickness

Overall external Ingress Protection (IP) rating for the Panelboard shall not be less than IP31 as defined

in BSEN60529.

All internal live parts shall be protected to IP2X.

All parts of the Panelboard both internal and external shall be free of sharp edges and sharp corners.

3.2.4 Construction Form Type

The Panelboard shall be Form 4, Type 2 as defined in BS 60439.

Busbars shall be separated from functional units.

Terminations to functional units shall be separated from each other.

Busbar separation shall be achieved by metallic or non-metallic rigid barriers or partitions.

3.2.5 Busbars and Cabling

The busbar system shall comply with BS 159 and shall be:-

1. HDHC copper bar.

2. Fully rated allowing for any reduction in CSA where bars are drilled.

3 Inaccessible from equipment compartments and protected by sheet steel barriers or shutters.

4. Clearly and indelibly colour identified as red, yellow, blue and black respectively.

5. Tested in accordance with BS 7767

Connections between the busbars and the connected components shall have a current rating not less

than the nominal rating of the component and shall be of adequate cross section for the specified fault

level. Connections to functional units from the main busbars shall be suitably rated copper busbars to

a minimum of 250 Amps and below this rating shall be in appropriately sized single core black PVC

insulated, tri rated, copper stranded cable.

All connections shall be marked with the requisite colour identification.

51

All connections from busbars to control and instrumentation equipment shall be protected by fuses.

The fuses shall be mounted on or as close as possible to the busbars. Further fusing within the

equipment’s compartment shall be provided if necessary to ensure adequate discrimination.

Neutrals shall be full size for all busbars and cabling.

3.2.6 Earth Bar

A continuous, horizontally mounted earth bar shall be provided throughout the length of the Panelboard

of minimum size 50mm x 6mm, suitable for extension and with provision for bonding all metalwork

with bolted connections. A minimum of two connections shall be provided to the Panelboard

framework.

A minimum of two earth connections shall be provided for connection to the external main earth ring.

Earthing shall comply with BS 7430, Code of Practice for Earthing.

Vertical earth bars shall be provided in each of the wiring chambers linked to the main earth bar drilled

out and fitted with suitable fixings for the appropriate number of functional unit earth connections.

All earth bars shall be clearly identified within each wiring chamber.

Bolted copper links shall be provided to enable the switchboard earth system to be isolated from the

main earth ring for testing.

3.2.7 Wiring and Cabling

All internal wiring and cabling shall be:-

1 Terminated with suitable copper tube lugs, insulated end sleeves or PVC insulated crimp

terminals.

2. Fully insulated, PVC tri-rated grade cable to BS 6231.

3. Protected by grommets, bushes or glands where it passes through metal enclosures.

4. Protected against heat and mechanical damage.

5. Labeled at both terminations. These reference numbers shall appear on the wiring diagrams.

All power cabling shall be securely clamped to remain in place under the worst fault conditions, and

they shall not be supported by their terminations.

Small wiring shall be enclosed in trunking or other cable management system and shall be numbered

at both ends with the terminal number and wire number shown on circuit drawings.

Cable terminations at 230VAC shall be fitted with a suitable removable shroud or barrier to IP2X.

Panelboard to comply with BS 5486: Part 1, Form 4 with IP 54 degree of protection, cable mounted.

Circuit details as indicated in Appendices-1

52

System Plant, Equipment + Materials

3.3 Distribution Boards

Distribution Boards to be of totally enclosed type (IP 31) to provide protection in compliance with BS

5420 IEC 144. The location of distribution boards to be as recorded within Appendices 1a &b, 2a & b,

3a & b, 4a &b, 5a &b, and 6a & b

A multi-terminal Earthing bar shall be provided for circuit protective conductors of the insulated metal

cased boards, with one terminal for each outgoing circuit. These will be connected directly to Earthing

terminal without dependence on exposed conductive parts of enclosure.

Distribution Boards and Panelboard shall be labelled showing the area and services which are to be fed

from them, and where not otherwise immediately obvious, their source of supply. The engraving to be

in white 10mm high letters on red plastic sheet or equal and fixed external to the lids of apparatus by

screw or rivets.

Low voltage Switchgear:

(i) Moulded Case Circuit Breakers (MCCB’s)

Moulded Case Circuit Breaker ratings shall be as stated within Appendix -1. They are to be of

the 500V totally enclosed metal clad type, complying with BS 4752 (IEC 157-1) ASTA

Certified P1 or P2 rating (50/35KV, 415V).

(ii) Miniature Circuit Breakers (MCB’s)

Miniature circuit breakers for incorporation in distribution boards to comply with the

requirements of BS 3871 (IEC 898)

(iii) Switch Fuses and Isolators

Switch fuses to be of the 500V totally enclosed metal clad type, complying with BS 5414 (IEC

408) AC22 and AC23 rating. All switch fuses to be fitted with HRC fuse cartridges and to be

SP + N / TP + N, as required and as rated in Appendix 12.

(iv) Residual Current-Operated Circuit Breakers

Residual current-operated circuit breakers to comply with BS 4293 (IEC 755)

(v) Isolators

Local isolator shall be supplied and installed for the control of each power consuming fixed

appliance which is solidly connected. It is necessary to ensure that the means of isolation and

the appliance are in the same room and in direct line of vision and not more than 6 meters apart.

(vi) PVC Insulated Armoured Cables

These cables shall be of 600/1000V grade in compliance with BS 6346. The conductors to be

insulated with PVC or XLPE insulated, PVC bedded, armoured with a single layer of galvanized

steel wire or tape, and sheathed overall with PVC.

Unless specifically indicated otherwise, all cables shall have copper conductors.

Where cables enter switchgear and other apparatus, they are to be made off with suitable brass

glands which shall incorporate both a cone grip armour clamp with positive armour locking and

a resilient compression gland to firmly grip the outer PVC Sheath of the cable. A brass earth

tag to be fitted between the gland and the apparatus. A secure earthing connection to be made

between the earth tag and the main earthing terminal of the apparatus, using a suitable copper

conductor

53

(vii) PVC Insulated Single Core Cables

These cable to be of 600/1000V grade to BS 6004 and, unless specifically indicated otherwise,

to have copper conductors. Cable for all services shall be in accordance with the Appendix 11

and the latest IEE Regulations. Cables to be coloured in accordance with Table: 52A of the IEE

Regulations.

(viii) Wiring Installation

PVC Conduit (Concealed)

PVC conduit and fittings to be high impact type, heavy gauge, BS 4607 Compliant, AH grade.

No conduit to be less than 20mm dia.

PVC conduit to be concealed within walls

(ix) Flexible Metallic Conduit (Plant)

Flexible metallic conduit to be of the overlapping helically wound flexible steel type, with a

PVC outer cover in accordance with BS 731. The conduit to be fitted with heavy duty couplers

and connections and to include a bush to protect cables when drawn-in

Flexible metallic conduits on Plant and Equipment final connections

(x) Cable Trunking

Cable Trunking to be installed in floor ducts and plant rooms on routes as shown on drawings.

(xi) Cable Trunking Plastics

The cable Trunking to be constructed of heavy gauge extruded high impact PVC.

(xii) Cable trays

Cable trays to be galvanized punched metal.

Cable trays to be installed in ground floor ducts, service risers, plant room and switch rooms.

3.4 Lightning Protection System

System description

BS 6651, CP 1013 compliant Lightning Protection System, comprising air terminals to be located at

apex of roof above Bank Building, with copper, PVC covered down tapes to be installed on the outer

walls of the building and linked to the Bank Lightning Protection System Earth Point.

3.5 Earthing + Bonding

System Description

Earthing and Bonding to be undertaken in compliance with IEE Wiring Regulations and BS 7430.

Equipotential bonding to be applied to all exposed metal parts and in particular:-

Metal cable trunking and trays

3.6 Structured Cable Management System (SCMS)

System Description

A fully integrated / coordinated SCMS to be supplied / installed, arranged to accommodate cabling

system in the vertical service ducts

54

System Plant, Equipment + Materials

(i) Vertical Service Ducts

400mm wide x 25mm deep, galvanized, punched metal cable trays, fixed to the building

structure with support brackets.

(ii) Ceiling Voids (Basement Floor, Ground Floor and First Floor

Type A – 400mm wide x 50mm deep,

Type B – 300mm wide x 50mm deep,

Type C – 2mm wide x 50mm deep, high strength, electro-plated zinc, galvanized

Steel rod wire basket cable tray, fixed to ceiling with support brackets.

Wire baskets and fittings to be as manufactured / supplied by Wiremould

Cables to be secured within cable trays / baskets employing “VELCRO” type quick release

fasteners.

Dado/Skirting Trunking (Conference Room, Server Room, UPS Room, Meeting Room, and

Offices.

Type D – 135mm x 50mm deep, white finished chamfered high impact PVC manufactured in

accordance with BS 4678. Part 4 (1982)

Floor Boxes (Conference Room only)

3 module (multiple outlet) recessed floor boxes, fitted with 2Nr. twin 13 Amp switched socket

outlets, 2 x 4 Nr. RJ45 Data / Telecom outlet points, incorporating quick release reversible lid,

cable retainers.

Floor Box Type ‘Cablelink Rapide’, as manufactured by Ackermann.

55

Tender Drawings/Figure Nos

Drawing

Number

System Drawing Type Detail

SL/ADB/E-1 Low Voltage

Distribution

Block Schematic

Layout

Incoming Power Supply and Low Voltage

Distribution

SL/ADB/E-2 Low Voltage

Distribution

Line Schematic

Diagram

Panelboard locations, Incoming/Outgoing LV

Cable Routing, Fire Alarm, Door Access Control

and CCTV Camera Locations

Structured Cable

Management System

Cabling Systems in vertical service duct

TO BE READ IN CONJUNCTION WITH ARCHITECTURAL AND STRUCTURAL ENGINEERING

DRAWINGS

Contract Works: Named Plant, Equipment + Materials.

The Contractor shall enter below the names of the Manufacturers / Suppliers of the Plant, Equipment and

Materials included within his Tender Price, either by confirming his use of the ‘As Named’

Manufacturer/Supplier or by defining his proposed alternative.

Plant, Equipment, Materials As Named Manufacturer/Supplier

in this Document

Proposed Alternative

Manufacturer/Supplier

(Country of Origin)

1. Panelboard PROTEUS

2. Distribution Boards PROTEUS

3. Fused Switch Disconnectors PROTEUS

4. Luminaries Thorn Lighting Ltd +

DESIGNPLAN

5. Small Power Accessories MK Ltd Legrand

9. Structured Cable Management

System

Wiremould Ackermann Centaur

56

4.0 SCHEDULE OF APPENDICES:

Appendix DETAIL

1 Incoming Electrical Power Supply: Schedule of LV Panelboard

2a Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 1 – Basement Floor

2b Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 2 – Basement Floor

3a Low Voltage Power Distribution: Schedule – UPS Distribution Board 1 – Basement Floor (ICT)

3b Low Voltage Power Distribution: Schedule – UPS Distribution Board 2 – Basement Floor (ICT)

3c Low Voltage Power Distribution: Schedule – UPS Distribution Board 3 – Basement Floor (Security)

4a Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 3 – Ground Floor

4b Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 4 – Ground Floor

5a Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 5 – First Floor

5b Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 6 – First Floor

6 Low Voltage Power Distribution: Schedule – MCCB – 9 Roof Top VRV Outdoor Unit 1

7 Low Voltage Power Distribution: Schedule – MCCB – 10 Roof Top VRV Outdoor Unit 2

8 Low Voltage Power Distribution: Schedule – MCCB – 11 Roof Top VRV Outdoor Unit 3

9 63A, Low Voltage TP&N Fuse Disconnector Switch – Lift – LV Switchroom

10 Low Voltage Power Distribution: Schedule – Small Power Requirements

11 Schedule of Light Fittings

12 Incoming Electrical Power Supply: Schedule of Cables

13 Technical Specification - 175kVA, 400/230V, 3-Phase, 50Hz Voltage Regulator

14 Technical Specification - 200kVA Power Transformer

15 Technical Specification - 10KVA, 3-Phase Modular DPA Uninterruptible Power Supplies (UPS)

16 Technical Specification - 175kVA, 400/230V, 3-Phase, 50Hz Generator Set

17 Technical Specification – 1 x 8 Passenger Electric Elevator

18 Technical Specification – Compound Security Solar Lights

19 Technical Specification – 2 x Fire Hydrant Booster Pumps

20 Technical Specification – Addressable Fire Alarm & FM200 Fire Suppression System

21 Technical Specification – Solar Powered Borehole with Submersible Pump

22 Technical Specification – In-Ceiling Mounted VRV & Wall Mounted Air Conditioning Systems

23 Technical Specification – 30kW Roof Mounted PV Solar System

57

SCHEDULE OF LV MCCB PANELBOARD:

INCOMING ELECTRICAL POWER SUPPLY

APPENDIX 1 – SCHEDULE OF 12 way TP+N MCCB LV PANELBOARD:

1. MCCB SWITCH - 1: Reference: MCCB - 1

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: Raw Power Distribution Board 1 – Basement Floor

2. MCCB SWITCH - 2: Reference: MCCB - 2

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 25mmsq PVC/SWA/XLPE; 16mmsq cpc

Feed to: Raw Power Distribution Board 2 – Basement Floor

3. MCCB SWITCH - 3: Reference: MCCB - 3

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 25mmsq PVC/SWA/XLPE; 16mmsq cpc

Feed to: UPS Distribution Board 1 – Basement Floor

4. MCCB SWITCH - 4: Reference: MCCB - 4

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 63A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 6mmsq cpc

Feed to: UPS Consumer Unit 1 – Basement Floor (Security equipment’s)

5. MCCB SWITCH - 5: Reference: MCCB – 5

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: Raw Power Distribution Board 3 – Ground Floor

6. MCCB SWITCH - 6: Reference: MCCB – 6

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 25mmsq PVC/SWA/XLPE; 16mmsq cpc

Feed to: Raw Power Distribution Board 4 – Ground Floor

58

7. MCCB SWITCH - 7: Reference: MCCB – 7

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: Raw Power Distribution Board 5 – First Floor

8. MCCB SWITCH - 8: Reference: MCCB – 8

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 125A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 25mmsq PVC/SWA/XLPE; 16mmsq cpc

Feed to: Raw Power Distribution Board 6 – First Floor

9. MCCB SWITCH - 9: Reference: MCCB – 9

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 100A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: VRV Outdoor Unit 1 – Basement Floor

10. MCCB SWITCH - 10: Reference: MCCB – 10

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 100A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: VRV Outdoor Unit 2 – Ground Floor

11. MCCB SWITCH - 11: Reference: MCCB – 11

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 100A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: VRV Outdoor Unit 3 – First Floor

12. MCCB SWITCH - 12 Reference: MCCB – 12

Location: Building LV Panelboard Room

Type: Form 4 Construction

Outgoing: 100A TP + N

Busbar Rating: 250A TP + N

Outgoing Cable: 4C x 16mmsq PVC/SWA/XLPE; 10mmsq cpc

Feed to: 8 Passenger Electric Lift

59

APPENDIX 2 – SCHEDULE OF RAW POWER DISTRIBUTION BOARDS BASEMENT FLOOR

2a Raw Power Distribution Board 1 – Basement Floor

Location: Ground Floor

Reference: DB1

Type: 1 x 6Way 125A TP + N

Fed From: MCCB - 1

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MCB Cable Size

(mm sq.)

Load in Watts

R Y B

1 Main Entrance Lobby Area Lighting 10A 1.5-2c + E

2 Waiting Room Lighting 10A 1.5-2c + E

3 Public Information Center (PIC) Lighting 10A 1.5-2c + E

4 Corridor Lighting 10A 1.5-2c + E

5 Office Lighting 10A 1.5-2c + E

6 Server Room Lighting 10A 1.5-2c + E

7 UPS Room Lighting 10A 1.5-2c + E

8 Male /Female Toilets Lighting 10A 1.5-2c + E

9 Emergency Exit Lightning 10A 1.5-2c + E

10 Waiting Room - Ring 20A 2.5-2c + E

11 Public Information Center (PIC) - Ring 20A 2.5-2c + E

12 Main Entrance Lobby Area - Ring 20A 2.5-2c + E

13 Office Lighting – Ring 20A 2.5-2c + E

14 Server Room – Ring 20A 2.5-2c + E

15 UPS Room – Ring 20A 2.5-2c + E

16 Corridor + Archive + Tool Store – Ring 20A 2.5-2c + E

17 SPARE

18 SPARE

Phase Total (Watts)

Total Load (kVA)

[p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All 13A socket outlets within the Basement Floor to the RCBO protected

60

2b Raw Power Distribution Board 2 – Basement Floor

Location: Ground Floor

Reference: DB2

Type: 1 x 6Way 125A TP + N

Fed From: MCCB - 2

Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MCB Cable Size

(mm sq.)

Load in Watts

R Y B

1 Main Entrance Lobby Area Indoor Cooling Unit - Radial 20A 4.0 3C + E

2 Waiting Room Indoor Cooling Unit- Radial 20A 4.0 3C + E

3 Public Information Center (PIC) Indoor Cooling Unit- Radial 20A 4.0 3C + E

4 Corridor Indoor Cooling Unit - 1- Radial 20A 4.0 3C + E

5 Corridor Indoor Cooling Unit - 2- Radial 20A 4.0 3C + E

6 Office Indoor Cooling Unit- Radial 20A 4.0 3C + E

7 Server Room Indoor Cooling Unit - 1- Radial 20A 4.0 3C + E

8 Server Room Indoor Cooling Unit - 2- Radial 20A 4.0 3C + E

9 UPS Room Indoor Cooling Unit - 1- Radial 20A 4.0 3C + E

10 UPS Room Indoor Cooling Unit - 2- Radial 20A 4.0 3C + E

11 Hand Dryer Male Toilet - Radial 20A 4.0 3C + E

12 Hand Dryer Female Toilet - Radial 20A 4.0 3C + E

13 Server Room Condenser for Cooling Unit - 1- Radial 32A 4.0 3C + E

14 Server Room Condenser for Cooling Unit - 2- Radial 32A 4.0 3C + E

15 UPS Room Condenser for Cooling Unit - 1- Radial 32A 4.0 3C + E

16 UPS Room Condenser for Cooling Unit - 2- Radial 32A 4.0 3C + E

17 SPARE

18 SPARE

Phase Total (Watts)

Total Load (KVA)

[p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All 13A socket outlets within the Basement Floor to the RCBO protected

61

APPENDIX 3 – SCHEDULE OF UPS POWER DISTRIBUTION BOARDS BASEMENT FLOOR

3a UPS Power Distribution Board 1 – Basement Floor

Location: Ground Floor

Reference: DB3

Type: 1 x 8Way 125A TP + N

Fed From: MCCB - 2

Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MCB Cable Size

(mm sq.)

Load in Watts

R Y B

1 Entrance Lobby + PIC + Office – Radial 3 Sockets 40A 4.0-2c + E

2 Server Room – Radial(3 Sockets 40A 4.0-2c + E

3 UPS Room – Radial 3 UPS Sockets 40A 4.0-2c + E

4 Conference Room – Radial 3 Sockets 40A 4.0-2c + E

5 Conference Room – Radial 3 Sockets 40A 4.0-2c + E

6 Conference Room – Radial 3 Sockets 40A 4.0-2c + E

7 Conference Room – Radial 3 Sockets 40A 4.0-2c + E

8 Floor Box Conference Room – Radial 2 Floor Boxes 40A 4.0-2c + E

9 Floor Box Conference Room – Radial 2 Floor Boxes 40A 4.0-2c + E

10 Floor Box Conference Room – Radial 2 Floor Boxes 40A 4.0-2c + E

11 Floor Box Conference Room – Radial 2 Floor Boxes 40A 4.0-2c + E

8 Office (1-05) – Radial 3 Sockets 40A 4.0-2c + E

9 Office (1-05) – Radial 3 Sockets 40A 4.0-2c + E

10 Office (1-05) – Radial 3 Sockets 40A 4.0-2c + E

11 Reception + Office + CPO - – Radial 3 Sockets 40A 4.0-2c + E

12 Office (F-04) – Radial 3 Sockets 40A 4.0-2c + E

13 Office (F-04) – Radial 3 Sockets 40A 4.0-2c + E

14 Office (F-04) – Radial 3 Sockets 40A 4.0-2c + E

15 Office (F-07) – Radial 2 Sockets 40A 4.0-2c + E

16 Secretary/Waiting (F-08) – Radial 2 Sockets 40A 4.0-2c + E

17 Resident Representative (F-09) – Radial 3 Sockets 40A 4.0-2c + E

18 Reception/Waiting ) – Radial 2 Sockets 40A 4.0-2c + E

19 Office (F-11) – Radial 2 Sockets 40A 4.0-2c + E

20 Meeting Room (F-12) - Radial 3 Sockets 40A 4.0-2c + E

21 Meeting Room (F-12) - Radial 2 Sockets 40A 4.0-2c + E

22 Meeting Room (F-12) - Radial 2 Sockets 40A 4.0-2c + E

23 SPARE

24 SPARE

Phase Total (Watts)

Total Load (kVA)

[p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All 13A socket outlets within the Basement Floor to the RCBO protected

62

3b UPS Power Consumer Unit 1 – Basement Floor

Location: Ground Floor

Reference: SP - 1

Type: 1 x 6Way 63A SP + N

Fed From: MCB - 1

Feed Cable: 1 x 3C x 10mmsq XLPE/SWA/PVC; 4mmsq cpc

Cct

No

Circuit MCB Cable Size

(mm sq.)

Load in Watts

L N E

1 CCTV Multiplexer – Radial 10A 2.5-2c + E

2 Addressable Fire Alarm Panel – Radial 10A 2.5-2c + E

3 Door Access Control Panel – Radial 10A 2.5-2c + E

4 SPARE 10A 2.5-2c + E

5 SPARE 10A 2.5-2c + E

6 SPARE 10A 2.5-2c + E

Phase Total (Watts)

Total Load (kVA)

[p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All socket outlets within the Basement Floor to the RCBO protected

63

APPENDIX 4 – SCHEDULE OF RAW POWER DISTRIBUTION BOARDS BASEMENT FLOOR

4a Raw Power Distribution Board 3 – Ground Floor

Location: Ground Floor

Reference: DB3

Type: 1 x 8Way 125A TP + N

Fed From: MCCB - 5

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MC

B

Cable Size

(mm sq.)

Load in Watts

R Y B

1 Conference Room (1-07) Lighting 10A 1.5-2c + E

2 Conference Room (1-07) Lighting 10A 1.5-2c + E

3 Lobby (1-02)+ Terrace lightning 10A 1.5-2c + E

4 Reception (1-01) Lighting 10A 1.5-2c + E

5 Corridor (1-12) Lightning 10A 1.5-2c + E

6 Corridor Toilet Area + Archive Lightning 10A 1.5-2c + E

7 Office (1-03) Lightning 10A 1.5-2c + E

8 Country Program Officer (1-06) Lightning 10A 1.5-2c + E

9 Office (1-04) + Corridor (G-08) Lightning 10A 1.5-2c + E

10 Office (1-05) + Veranda Lightning 10A 1.5-2c + E

11 Male Toilet (1-09) + Female Toilet (1-10) + Kitchenette Lightning 10A 1.5-2c + E

12 Outdoor Security (5Nr.) Lightning 10A 1.5-2c + E

13 Outdoor Security (5Nr.) Lightning 10A 1.5-2c + E

14 Stair Case + Exit Porch Lightning 10A 1.5-2c + E

15 Conference Room (6Nr. Sockets) - Ring 20A 2.5-2c + E

16 Conference Room (6Nr. Sockets) - Ring 20A 2.5-2c + E

17 Office (1-04) - Ring 20A 2.5-2c + E

18 Office (1-05) - Ring 20A 2.5-2c + E

19 Reception + Lobby + Corridor - Ring 20A 2.5-2c + E

20 Office (1-03) - Ring 20A 2.5-2c + E

21 Country Program Officer (1-06) - Ring 20A 2.5-2c + E

22 Kitchenette + Archive + Corridor Toilet Area - Ring 20A 2.5-2c + E

23 SPARE

24 SPARE

Note: Circuits to be distributed between DB1 & DB2

Phase Total (Watts)

Total Load (KVA)

[ p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All socket outlets within the Basement Floor to the RCBO protected

64

4b Raw Power Distribution Board 4 – Ground Floor

Location: Ground Floor

Reference: DB4

Type: 1 x 8Way 125A TP + N

Fed From: MCCB - 6

Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MC

B

Cable Size

(mm sq.)

Load in Watts

R Y B

1 Conference Room Indoor Cooling Unit- Radial 20A 4.0 3C + E

2 Conference Room Indoor Cooling Unit- Radial 20A 4.0 3C + E

3 Lobby Indoor Cooling Unit- Radial 20A 4.0 3C + E

4 Reception Indoor Cooling Unit- Radial 20A 4.0 3C + E

5 Corridor (1-12) Indoor Cooling Unit- Radial 20A 4.0 3C + E

6 Corridor Toilet Area Indoor Cooling Unit- Radial 20A 4.0 3C + E

7 Office (1-03) Indoor Cooling Unit- Radial 20A 4.0 3C + E

8 Country Program Officer (1-06) Indoor Cooling Unit- Radial 20A 4.0 3C + E

9 Office (1-04) Indoor Cooling Unit- Radial 20A 4.0 3C + E

10 Office (1-05) Indoor Cooling Unit- Radial 20A 4.0 3C + E

11 Hand Dryer Male Toilet - Radial 20A 4.0 3C + E

12 Hand Dryer Female Toilet - Radial 20A 4.0 3C + E

13 45A Cooker Unit Outlet 45A 6.0-3c + E

14 SPARE

15 SPARE

16 SPARE

17 SPARE

18 SPARE

Note: Circuits to be distributed between DB1 & DB2

Phase Total (Watts)

Total Load (KVA)

[ p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All socket outlets within the Basement Floor to the RCBO protected

65

APPENDIX 5 – SCHEDULE OF RAW POWER DISTRIBUTION BOARDS FIRST FLOOR

5a Raw Power Distribution Board 5 – First Floor

Location: First Floor

Reference: DB5

Type: 1 x 8Way 125A TP + N

Fed From: MCCB - 7

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MC

B

Cable Size

(mm sq.)

Load in Watts

R Y B

1 Staircase Lobby + Terrace Lighting 10A 1.5-2c + E

2 Office (F-04) Lighting 10A 1.5-2c + E

3 Office (F-04) Lighting 10A 1.5-2c + E

4 Reception (F-03) + Corridor (F-14) Lighting 10A 1.5-2c + E

5 Corridor (F-05) Lightning 10A 1.5-2c + E

6 Office (F-07) + Filing Storage (F-06) Lightning 10A 1.5-2c + E

7 Secretary/Waiting (F-08) Lightning 10A 1.5-2c + E

8 Secretary/Waiting (F-08) Lightning 10A 1.5-2c + E

9 Resident Representative (F-09) Lightning 10A 1.5-2c + E

10 Resident Representative (F-09) Lightning 10A 1.5-2c + E

11 Office (F-11) Lightning 10A 1.5-2c + E

12 Meeting Room (F-12) Lightning 10A 1.5-2c + E

13 Corridor by Toilet Area + Archive Lightning 10A 1.5-2c + E

14 Male Toilet (F-15) + Female Toilet (F-16) + Kitchenette Lightning 10A 1.5-2c + E

15 Stair Case - Lightning 10A 2.5-2c + E

16 Office (F-04) 4Nr. Sockets - Ring 20A 2.5-2c + E

17 Office (F-04) 4Nr. Socket - Ring

18 Staircase Lobby + Corridor 4Nr. Socket - Ring 20A 2.5-2c + E

19 Reception (F-03) 4Nr. Socket - Ring 20A 2.5-2c + E

20 Office (F-11) 3Nr. Socket – Ring 20A 2.5-2c + E

21 Meeting Room (F-12) 4Nr. Socket - Ring 20A 2.5-2c + E

22 Meeting Room (F-12) 3Nr. Socket - Ring 20A 2.5-2c + E

23 SPARE

24 SPARE

Note: Circuits to be distributed between DB1 & DB2

Phase Total (Watts)

Total Load (KVA)

[ p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All socket outlets within the Basement Floor to the RCBO protected

66

5b Raw Power Distribution Board 6 – Ground Floor

Location: First Floor

Reference: DB6

Type: 1 x 8Way 125A TP + N

Fed From: MCCB - 8

Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc

Cct

No

Circuit MC

B

Cable Size

(mm sq.)

Load in Watts

R Y B

1 Kitchenette + Archive + Corridor Toilet Area - Ring 20A 2.5-2c + E

2 Secretary/Waiting (F-08) 5Nr. Socket - Ring 20A 2.5-2c + E

3 Resident Representative (F-09) 3Nr. Socket - Ring 20A 2.5-2c + E

4 Resident Representative (F-09) 3Nr. Socket - Ring 20A 2.5-2c + E

5 Lobby Indoor Cooling Unit- Radial 32A 4.0 3C + E

6 Office (F-04) Indoor Cooling Unit- Radial 20A 4.0 3C + E

7 Reception/Waiting (F-03) Indoor Cooling Unit- Radial 20A 4.0 3C + E

8 Corridor (F-05)) Indoor Cooling Unit- Radial 20A 4.0 3C + E

9 Corridor (F-14)) Indoor Cooling Unit- Radial

10 Corridor Toilet Area Indoor Cooling Unit- Radial 20A 4.0 3C + E

11 Office (F-07) Indoor Cooling Unit- Radial 20A 4.0 3C + E

12 Secretary/Waiting (F-08) Indoor Cooling Unit- Radial

13 Resident Representative (F-09) Indoor Cooling Unit- Radial 20A 4.0 3C + E

14 Office (F-11) Indoor Cooling Unit- Radial 20A 4.0 3C + E

15 Meeting Room (F-12) Indoor Cooling Unit- Radial 20A 4.0 3C + E

16 Hand Dryer Male Toilet - Radial 20A 4.0 3C + E

17 Hand Dryer Female Toilet - Radial 20A 4.0 3C + E

18 Hand Dryer Resident Representative (F-09) Toilet - Radial

19 45A Cooker Unit Outlet 45A 6.0-3c + E

20 SPARE

21 SPARE

22 SPARE

23 SPARE

24 SPARE

Note: Circuits to be distributed between DB1 & DB2

Phase Total (Watts)

Total Load (KVA)

[ p.f = 0.85]

Imax (A)

Io = Imax x 0.85

NOTE: All socket outlets within the Basement Floor to the RCBO protected

67

APPENDIX 6 - Raw Power MCCB 9 – LV Panelboard Room

Location: LV Panelboard Room

Reference: VRV Outdoor Unit – 1 (Roof Top)

Type: 100A TP + N

Fed From: MCCB - 9

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

APPENDIX 7 - Raw Power MCCB 10 – LV Panelboard Room

Location: LV Panelboard Room

Reference: VRV Outdoor Unit – 2 (Roof Top)

Type: 100A TP + N

Fed From: MCCB - 10

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

APPENDIX 8 - Raw Power MCCB 11 – LV Panelboard Room

Location: LV Panelboard Room

Reference: VRV Outdoor Unit – 3 (Roof Top)

Type: 100A TP + N

Fed From: MCCB - 11

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

APPENDIX 9 - Raw Power MCCB 11 – LV Panelboard Room

Location: LV Panelboard Room

Reference: 8 Passenger Electric Lift

Type: 63A TP + N

Fed From: MCCB - 11

Feed Cable: 1 x 4C x 16mmsq XLPE/SWA/PVC; 10mmsq cpc

68

APPENDIX 10a -BASEMENT FLOOR – SCHEDULE OF SMALL POWER REQUIREMENTS

BASEMENT FLOOR NUMBER OFSMALL

ELECTRICAL

POWER OUTLETS

TYPE / RATING

COMMENTS

TYPE A TYPE B

Main Entrance Lobby Area MK Logic Plus, white

finished 13Amp switch

socket outlets

Power points fitted to 3

compartment high

impact PVC dado

trunking installed at

skirting level

Waiting Room As Above As Above

Archive As Above As Above

Public Information Center As Above As Above

Corridor As Above As Above

Office As Above As Above

Server Room

As Above

Power points fitted to 3

compartment high

impact PVC dado

trunking installed below

benches

UPS Room

As Above

Separate 63A TP + N

Fuse Disconnect Switch

- Electrical Power

Supply to serve UPS

Main UPS

UPS Room

As Above

Power points fitted to 3

compartment high

impact PVC dado

trunking installed below

benches

Tool Store As Above Low level, wall mounted

power points

Notes: TYPE A – Single Switched Socket Outlet TYPE B – Double Switched Socket Outlet

Radial Circuit – 3Nr. Socket Outlets to 1Nr. 40A MCB

69

APPENDIX 10b -GROUND FLOOR – SCHEDULE OF SMALL POWER REQUIREMENTS

GROUND

FLOOR

NUMBER OFSMALL

ELECTRICAL POWER

OUTLETS

TYPE / RATING

COMMENTS

TYPE A TYPE B

Conference Room

MK Logic Plus, white

finished 13Amp switch

socket outlets

Power points fitted to 3

compartment high

impact PVC dado

trunking installed at

skirting level

Lobby As Above As Above

Reception As Above As Above

Office (1-03) As Above As Above

Country Program

Officer

As Above As Above

Office (1-04) As Above

Office (1-05) As Above

Kitchenette

1 As Above Wall mounted power

point fitted above

worktop

Cooker Point 45 Amp Wall mounted power

point fitted above

worktop

Archive MK Metalclad Plus 13

Amp switch socket

outlets

Low level, wall

mounted power points

Notes: TYPE A – Single Switched Socket Outlet TYPE B – Double Switched Socket Outlet

Radial Circuit – 3Nr. Socket Outlets to 1Nr. 40A MCB

70

APPENDIX 10c -FIRST FLOOR – SCHEDULE OF SMALL POWER REQUIREMENTS

FIRST FLOOR NUMBER OFSMALL

ELECTRICAL POWER

OUTLETS

TYPE / RATING

COMMENTS

TYPE A TYPE B

Office (F-04)

MK Logic Plus, white

finished 13Amp switch

socket outlets

Power points fitted to 3

compartment high

impact PVC dado

trunking installed at

skirting level

Lobby Area As Above As Above

Reception As Above As Above

Office (F-07) As Above As Above

Filing Storage

MK Metalclad Plus 13

Amp switch socket

outlets

As Above

Secretary/Waiting

MK Logic Plus, white

finished 13Amp switch

socket outlets

Power points fitted to 3

compartment high

impact PVC dado

trunking installed at

skirting level

Resident

Representative

As Above As Above

Office (F-11) As Above As Above

Meeting Room As Above As Above

Kitchenette 1 As Above Wall mounted power

point fitted above

worktop

Cooker Point 45 Amp As Above

Archive MK Metalclad Plus 13

Amp switch socket

outlets

Low level, wall

mounted power points

Notes: TYPE A – Single Switched Socket Outlet TYPE B – Double Switched Socket Outlet

Radial Circuit – 3Nr. Socket Outlets to 1Nr. 40A MCB

71

APPENDIX 10d: ANCILLIARY AREAS – SCHEDULE OF SMALL POWER REQUIREMENTS

OTHER AREAS NUMBER OF SMALL

ELECTRICAL

POWER OUTLETS

TYPE / RATING COMMENTS

TYPE A TYPE B

Electrical Switch Room

MK 13 Amp switched

fused spur with neon

indicator

Surface, wall mounted, 13 Amp

power supply sockets fitted to

galvanized metal conduit at low

level on side wall

Door Access Control

MK 13 Amp switched

fused spur with neon

indicator

Local power points located on

wall at high level adjacent to

each door under Access Control

Alarm Systems 2 MK Metalclad Plus

13 Amp Outlets

Outlet points fitted to galvanized

metal conduits within Control

room

Lift Installation

1

MK Logic Plus, white

finished, 13 Amp

switch socket outlet

Separate 63 Amp TP + N

electrical power supply

terminating at metal clad, wall

mounted, lockable double pole

isolator, mounted in Electrical

Switch Room

Generator House Plug and Receptacles

for Outdoor Harsh

Environments

Cleaner’s power outlet point

fitted 1m above ground level on

external wall

Notes: TYPE A – Single Switched Socket Outlet TYPE B – Double Switched Socket Outlet

Plug and Receptacles for Outdoor Harsh Environments

Radial Circuit – 2Nr. Socket Outlets to 1Nr. 40A MCB

72

APPENDIX 11: SCHEDULE OF LIGHT FITTINGS - INTERNAL / EXTERNAL AREAS

S/N AREA REF. TYPE OF FITTING/SWITCHING QTY

A Basement Floor:

1 Main Entrance Lobby Area 600 x 600mm 48W LED Ceiling Panel Lighting IP44 6

2 Waiting Room Lighting As Above 4

3 Public Information Center As Above 4

4 Corridor As Above 12

5 Office As Above 4

6 Server Room As Above 4

7 UPS Room As Above 4

8 Male / Female Toilets 18W LED Ceiling Downlight 3

9 Emergency Exit Lightning 8Watts Emergency Illuminated Exit Sign-3Hrs.

Maintain

3

10 Staircase Lighting BEGA Type No. 2743 Impact Resistance Staircase

Light

2

11 Tool Store 18W LED Ceiling Downlight 1

B Ground Floor:

1 Terrace lightning 18W LED Ceiling Downlight 1

2 Lobby (1-02) 600 X 600mm 48W LED Ceiling Panel Lighting IP44 3

3 Conference Room As Above 20

4 Reception (1-01) As Above 6

5 Corridor (1-12) As Above 6

6 Office (1-03) As Above 3

7 Country Program Officer As Above 4

8 Corridor (G-08) As Above 3

9 Office (1-04) As Above 6

10 Office (1-05) As Above 13

11 Veranda Lightning 18W LED Ceiling Downlight 1

12 Corridor Toilet Area As Above 3

13 Kitchenette Lightning As Above 1

14 Male / Female Toilet As Above 4

15 Archive Lightning As Above 1

16 Stair Case Lightning BEGA Type No. 2743 Impact Resistance Staircase

Light

4

17 Emergency Exit Lightning 8Watts Emergency Illuminated Exit Sign-3Hrs.

Maintain

3

18 Outdoor Security

Lightning

1200mm x 36W THORN AQUAFORCE II T26 HF

L840

10

C First Floor:

1 Terrace Lighting 18W LED Ceiling Downlight 1

2 Lobby Lighting 600 X 600mm 48W LED Ceiling Panel Lighting IP44 3

3 Staircase Lighting BEGA Type No. 2743 Impact Resistance Staircase

Light

4

4 Office (F-04) 600 X 600mm 48W LED Ceiling Panel Lighting IP44 12

5 Corridor (F-14) Lighting As Above 6

6 Reception (F-03) As Above 4

7 Corridor (F-05) Lightning As Above 4

8 Office (F-07) As Above 3

9 Filing Storage (F-06) 18W LED Ceiling Downlight 1

10 Secretary/Waiting (F-08) As Above

11 Resident Representative As Above 10

12 Veranda Lightning 18W LED Ceiling Downlight 1

13 Office (F-11) 600 X 600mm 48W LED Ceiling Panel Lighting IP44 3

73

14 Meeting Room (F-12) As Above 4

15 Corridor by Toilet Area As Above 3

16 Kitchenette Lightning 18W LED Ceiling Downlight 1

17 Male / Female Toilet As Above 5

18 Archive Lightning As Above 1

Note: 1. All light fittings to be manually switched.

2. MK Metalclad Plus type switches/switch plates..

3. MK Logic Plus type switches/switch plates.

4 All light fitting wiring to be contained within enclosed PVC conduit pipes and accessories.

APPENDIX 12: SCHEDULE OF CABLE

S/N FROM TO CABLE DESCRIPTION

1 Generator Set - 1 ATS - 1 4C x 95mmsq. XLPE/SWA/PVC

Cable + 35mmsq cpc

2 Generator Set - 2 ATS - 1 4C x 95mmsq. XLPE/SWA/PVC

Cable + 35mmsq cpc

3 ATS - 1 ATS - 2 4C x 95mmsq. XLPE/SWA/PVC

Cable + 35mmsq cpc

4 TRANSFORMER

LV SIDE

ATS - 2 4C x 120mmsq. XLPE/SWA/PVC

Cable + 50mmsq cpc

5 ATS - 2 VOLTAGE REGULATOR 4C x 120mmsq. XLPE/SWA/PVC

Cable + 50mmsq cpc

6 VOLTAGE

REGULATOR

12-WAY LV PANELBOARD 4C x 120mmsq. XLPE/SWA/PVC

Cable + 50mmsq cpc

7 MCCB Switch-1 Raw Power DB1 Basement Floor 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

8 MCCB Switch-2 Raw Power DB1 Basement Floor 4C x 25mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

9 MCCB Switch-3 UPS 125A, 4-way MCCB Panelboard 4C x 25mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

(i) MCCB Panelboard-1 UPS DB1 (ICT) Basement Floor 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

(ii) MCCB Panelboard-2 UPS DB2 (ICT) Basement Floor 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

(iii) MCCB Panelboard-3 UPS DB3 (Security) Basement Floor 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

10 MCCB Switch-4 DB3 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

11 MCCB Switch-5 DB4 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

12 MCCB Switch-6 DB5 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

13 MCCB Switch-7 DB6 4C x 25mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

14 MCCB Switch-8 DB7 4C x 25mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

15 MCCB Switch-9 DB8 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

16 MCCB Switch-10 DB9 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

74

17 MCCB Switch-11 DB10 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

18 MCCB Switch-12 LIFT 4C x 16mmsq XLPE/SWA/PVC

Cable + 10mmsq cpc

75

PROPOSED ELECTRICAL SWITCHGEARS

1. 250Amps, 12way Energy Management Panelboard with increasing emphasis on

energy conservation, we have offers the Proteus Switchgear range of intrinsic

energy management, varying from time switch and relay logic to electronic

microprocessor control*of lighting, heating and ventilation and fire/security

systems.

To meet these changing requirements in commercial and industrial applications,

Proteus Switchgear manufactures custom-designed energy management panels,

typically incorporating the following options:

1. Main incoming isolation / protection up to 800 amps

2. 24 hour essential services distribution•

3. Point of entry / exit key switch controlled services

4. Fire alarm interlocking•

5. Signage control / extended hours manual override

6. Emergency lighting test / battery discharge facility

7. Panels built to specification or in conjunction with Proteus Technical Department.

2. 3 Pole MOULDED CASE CIRCUIT BREAKERS TO IEC/EN 60947-2’ for use

as outgoing devices within and Panelboard.

3. THREE PHASE POWER DISTRIBUTION BOARD

TO 10kA, MCB’s up to 63A (17.5mm Module) 10kA MCB’s 10 amps to 125A

(26.3mm Module) Unique busbar arrangement to accept MCB’s up to 125A maximum outgoing*

10kA MCB’s 125 amps (26.3mm Module)

Unique busbar arrangement to accept MCB’s up to 125 amps maximum outgoing

76

4. THREE PHASE SWITCH DISCONNECTORS WITH FUSES

FEATURES

Specification as Switch Disconnectors above, plus:

Internal switching mechanism also padlockable in off position

Maximum rated fuses fitted

Fully rated at AC23A category of duty (inductive load)

Screened terminals

5. OUTDOOR PLUG AND RECEPTACLES FOR HARSH ENVIRONMENTS

6. THREE COMPARTMENT PVC DADO SKIRTING TRUNKING 3 METRE LENGTHS

3 Metre Lengths, Three Compartments 3 Compartment Dado Flat Angle

PVC Dado Trunking

77

3 Compartment Dado Flat Tee 3 Compartment Dado External Angle

The PVC Dado Trunking system has been designed to prevent communication interference, with its 3

compartments designed to separate data communication / telephone and mains 240V cables.

The 2 outer compartments are designated to the data communication and telephone cables; the center

compartment is for use with 240V mains cable.

The product is ideal for re-routing cables from horizontal position to vertical with no visible joints.

78

PV SOLAR ENGINEERING SERVICE INSTALLATION (Optional item)

79

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

ROOF TOP PV SOLAR PV SERVICES ENGINEERING FOR OFFICE BUILDING AT REGENT

ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

80

TECHNICAL SPECIFICATIONS FOR PROPOSED SOLAR PV ROOF TOP SYSTEM FOR THE

SIERRA LEONE FIELD OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB)

TABLE OF CONTENTS:

A. TECHNICAL SPECIFICATIONS:

1.0. Introduction

2.0 Scope

3.0 Standards

4.0 Solar Panels

5.0 Solar Inverters

6.0 Charge Controller

7.0 Batteries

8.0 Equivalency of Standards and Codes:

B. TECHNICAL SPECIFICATIONS FOR SOLAR PV SYSTEM COMPONENTS

1. SPECIFICATIONS FOR SOLAR PANELS, INVERTERS & BATTERY BANK

(i) Solar Panels

(ii) Solar Inverter

(iii) Charge Controller

(iii) Batteries

C. TECHNICAL SPECIFICATIONS FOR PEOPOSED SOLAR PV ROOFTOP SYSTEM

D. GRID / GENERATOR CONNECT SOLAR POWER GENERATING SYSTEM

81

A. TECHNICAL SPECIFICATIONS:

1. Introduction:

Nowadays many issues appear due to the fact of using fossil fuel as a primary resource in generating

electricity. The solution to such issues can be eliminated or reduced by means of using a renewable

energy such as a solar power system proposed for the Sierra Leone Field Office at the African

Development Bank (ADB).

The first issue that is related to use of fossil fuels is the global warming, where the increase of using

fossil fuels such as oil and natural gas in generating electricity resulted several health and environmental

problems. Natural gas gives off 50% of the carbon dioxide, the principal greenhouse gas, released by

coal and 25% less carbon dioxide than oil, for the same amount of energy produced. Coal contains about

80% more carbon per unit of energy than gas does, and oil contains about 40 percent more. Global

warming has many effects such as earth temperature increase, sea level rise.

Second issue is the air pollution. A lot of pollutants are produced by fossil fuel combustion that is used

to produce electricity such as Sulphur oxides, and hydrocarbons. In addition, suspended particles

contribute to air pollution and combine in the atmosphere to form tropospheric ozone, the major

constituent of smog.

Third issue is the cost of the fossil fuel. The electricity that is produced by the fossil fuel process is more

expensive than the electricity produced by the renewable energy such as solar power.

Another issue that is noticeable nowadays is the water and land pollution. Water spills causes harm to

plants and animals life. Coal mining also contributes to water pollution. Coal contains pyrite that is a

Sulphur compound.

On the other hand, Photovoltaic offers consumers the ability to generate electricity in a clean, quiet and

reliable way. To increase the PV utility, dozens of individual PV cells are interconnected together in a

sealed, weather proof package called a module. Modules are connected either in series or parallel. The

flexibility of the modular PV system allows designers to create solar power systems that can meet a

wide variety of electrical needs.

There are two broad categories of PV system namely:

(i) Grid-tied systems which are connected to the public electricity grid.

The grid-tied PV connected to the power grid at all times and do not require battery storage. A

solar PV system can provide power to a home or business, reducing the amount of power required

from the utility; when the solar PV system power generation exceeds the power needs, then the

surplus power automatically will be pumped back into the grid. A solar PV system will not operate

during a power outage unless it has battery backup.

(ii) Solar Stand-alone systems which are isolated system.

Standalone systems are totally self-sufficient with no connection to the utility grid system. They

generate electricity during daylight hours, and store excess for night time use.

(iii) Solar Hybrid Systems connected to Diesel Generator Set / Public Electricity Grid

In this project proposal, a design of a 24kW Hybrid Solar PV System to the rooftop of the Sierra

Leone Field Office at the African Development Bank (ADB), Freetown is introduced where

necessary components between the PV system and the load for the required design are identified.

82

The proposed system integrates with the standby generator(s) for battery charging when there is

no sun light and for powering the excess load beyond what the Solar PV can power since its

capacity is less than the required capacity of Sierra Leone Field Office at the African Development

Bank (ADB) loads

2.0 Scope:

The scope of the specifications is to cover the requirement of the design, supply, installation, testing and

commissioning of Solar Panels and Inverters/ Charge Controllers and Battery banks with all

components, instruments, fittings and accessories for efficient operation without any trouble.

3.0 Standards:

PV Modules shall be manufactured to any of the International Specifications and shall comply with any

of IEEE1262 (“Recommended Practice for Qualifications of Photovoltaic Modules”), IEC 61215/ IEC

61730 and CE Certification. The Panels shall be tested based on 1000w/s ft. irradiance at site conditions.

Inverters shall comply with IEEE 929-2000 “Recommended Practice for Utility Interface of

Photovoltaic Systems”. The Modules also shall pass Salt Mist corrosion testing as per IEC 61701

4.0 Solar Panels:

The Solar panels shall be of polysilicon type of 250W rating as required. The panels shall employ the

required PV cells and suitable for Grid Connectivity/Off grid applications. The Cells shall lay embedded

in transparent EVA behind tempered glass. The glass is inset deep in an aluminium frame, there by

offering maximum protection. The back of the module shall be sealed with a high quality back sheet.

The Wiring shall be terminated in box backside of panel and shall have no cavities and completely water

tight and is resistant to Temperature and UV radiation. The efficiency of PV panels at standard irradiance

shall be minimum 85%

The broad operational parameters for Solar panels shall be as follows. However the system parameters

with any approved product shall be in the similar lines. The Modules shall be protected against surges

and also provided with Low voltage drop bypass diodes. Module junction boxes shall be weather

protected and made out of FRP/ Thermoplastic The Solar modules shall be guaranteed for 25Years for

performance (First 10years @100%, next 15years @90% and at the end of 25years @80% Efficiency)

through a corporate guarantee and supported by Insurance is preferable

Solar Modules Basic Specs:

(i) Description: 250W

(ii) Panel Peak power: 250W

(iii) Power Tolerance: +/-3%

(iv) Max. Power Voltage: 30.8V

(v) Max. Power Current: 7.8A

(vi) Open Circuit Voltage: 37.69V

(vii) Short Circuit Current: 8.34A

(viii) Module Efficiency: 14-15%

(ix) Approx. Weight: 29Kgs

(x) Operating Conditions: -40-+55deg.C

(xi) Maximum System Voltage: 1000/600V

(xii) Cable suitability: 4sq.mm

(xiii) Junction Box: IP 65 (with Surge protection device)

83

Each PV Module shall be provided with a RFID tag, provided inside Module laminate specifying

following information

a) Name of manufacturer of Solar Module

b) Name of manufacturer of Solar Cell

c) Unique serial number and Model no of Module

d) Month and Year of manufacture

e) Country of Origin

f) I-V Characteristic

g) Peak Wattage, Im, Vm, FF of Module

h) Date and Year of Obtaining PV Module IEC qualification certificate

i) Name of Test lab issued certificate

j) Other information to trace PV module as per ISO9000

Photo Voltaic Input:

(i) Nominal Input Voltage: 700V

(ii) Input Voltage Range: 500-800V

(iii) Max PV Recommended: 80KW

MPPT Charge Controller:

(i) Switching Element: IGMT/MOSFET

(ii) Type of Charger: MPPT

(iii) Input Voltage Range: 500-700V

(iv) MPPT Voltage Range: 550-600V

(v) Efficiency: 95%

(vi)

Input:

(i) Voltage range: 900V, +10%, -15%, 3phase. 4wire

(ii) Nominal Frequency: 50HZ+/-3HZ

(iii) Nominal Power: 20KW

Battery:

(i) Recommenced no of Cells: 72Nr.

(ii) Float Voltage for VRLA: 2.25V

(iii) Boost Voltage: 2.60V

(iv) End cell Voltage: 1.75V

(v) Float Voltage stability: <1%

(vi) DC Ripple: <1%

5.0 Solar Inverters:

Solar Inverter:

The Inverter shall be suitable for indoor application and suitable for Generator/Grid Connectivity with

Input voltage and current to suit the capacity of Inverter as specified below. The Inverters shall be with

MOSFET/ IGBT/ Power transistors and with min. 92% Efficiency. It shall be possible to synchronize

number of modules to get the required output of 80KW net output „full sine wave‟ Inverter(s) having

specified DC input and 415 V, 3-ph, 50 Hz AC output to convert the solar energy in DC form to AC

along with all protection and controlling arrangement as per specification.

84

The efficiency of the Inverter shall be min. of 92%. (Based on availability 80KW or marginally higher

rating inverters shall be acceptable). The Inverter shall be suitable to receive EB supply, DG supply

(Through a changeover) and MPPT Charge Controller suitable to charge 250AH VRLA Batteries to

control charge the batteries and also to use the Battery power in case of non-availability of solar energy

along with all protection and controlling arrangement as per specification.

The Broad Specifications of Inverters are given below:

Inverter

(i) Nominal Output Voltage: 900V 3Phase, 50HZ

(ii) Voltage stability in steady state for input

(AC & DC) variations & step load 0 to nominal load): +/-1%, Based on IEC 62040-3

(iii) Voltage stability in dynamic state for input

(AC & DC) variations & step load (0 to nominal load & Vice Versa): complies with IEC 62040-

3

(iv) Voltage stability in steady state for 00% load imbalance: +/- 3%

(v) Output Frequency: 50HZ+/-3HZ

(vi) Wave Form: Pure Sine wave

(vii) Technology: MOS FET Based/ IGBC Based

(viii) Duty: Continuous

(ix) Efficiency: More than 92%

(x) Protection: IP 55

(xi) Cable entry: Bottom

(xii) Temperature& RH: 50Deg.C, Up to 95% (Non Condensing)

(xiii) Noise Level: Not more than 55dB at 1mtr distance

(xiv) Control: MCB

(xv) Indications: Array ON\ Inverter ON/ Grid ON/ Input Surge/

Input UV/OV, Low/ High Frequency/ Inverter UV/ OV/

any other as required.

6.0 Charge Controller

The proposed Solar Charge Controller MPPT 150/85 (12/24/48V-85A) shall be a current-regulating

device that is placed between the solar array output and the batteries. The device is designed to prevent

the batteries from being overcharged or overly discharged. It unit shall work to slowly reduce the amount

of charge that follow into the battery as the battery approach it’s fully charge stage.

7.0 Solar Batteries

A range of batteries is available. HOPPECKE VR L 1700 (Valve Regulated Lead Acid) batteries that is

completely sealed and do not require topping up with distilled water, spill proof, leak proof and can be

used upside down or on their side and specifically designed for solar & green energy systems and can

be used in confined or poorly ventilated spaces is proposed. Battery installations are installed to comply

with AS4509 and AS5003 and Clean Energy Council requirements.

8.0 Equivalency of Standards and Codes:

Wherever reference is made in the Contract to specific standards and codes to be met by the goods and

materials to be furnished, and work performed or tested, the provisions of the latest current edition or

revision of the relevant standards and codes in effect shall apply, unless otherwise expressly stated in

the Contract document. Where such standards and codes are notional, or relate to a particular country or

region, other authoritative standards that ensure a substantially equal or higher quality than the standards

85

and codes specified will be accepted subject to the Sierra Leone Field Office at the African Development

Bank (ADB) Project Manager’s prior review and written consent. Differences between the standards

specified and the proposed alternative standards shall be fully described in writing by the Vendor and

submitted to the Sierra Leone Field Office at the African Development Bank (ADB) Project Manager at

least 15 days prior to the date when the Vendor desires the Project Manager’s consent.

86

B. TECHNICAL SPECIFICATIONS FOR SOLAR PV SYSTEM COMPONENTS

1. SOLAR PANELS, AND OTHER COMPONENTS, TO BE INCLUDE IN THE PROPOSED KITS

a) OVERVIEW:

The solar panel industry has been going through radical changes in the last couple years. The price per

watt for solar panels has decreased more than 60% during this period. Hence, Sierra Leone Field Office

at the African Development Bank (ADB) is looking for best prices for the best panels to be installed at

its premises in Freetown.

The Sierra Leone Field Office at the African Development Bank (ADB) notes that Solar Companies

have significantly raised the standard of module efficiency in the solar industry. They introduced

innovative four busbar cell technology, which demonstrates higher power output and higher system

reliability and Sierra Leone Field Office at the African Development Bank (ADB) have embraced this

next generation of modules for their excellent performance, superior reliability and enhanced.

b) WARRANTIES

Solar panels are a semiconductor product so their reliability and stability are very high. Manufacturing

defects usually show up very quickly and after that point they seldom experience problems. The point

is that if the initial quality is good then you should have a long and trouble-free experience.

The panels provided shall come from tier-1 manufacturers that carry a 25yrs. linear warranty. This means

they are guaranteed to generate 97.5% of rated power in year 1 and 80% in year 25.

1. SOLAR PANEL SPECIFICATION SHEETS:

a) New Technology:

(i) Reduces cell series resistance

(ii) Reduces stress between cell interconnectors

(iii) Improves module conversion efficiency

(iv) Improves product reliability

b) Management System Certificates:

(i) ISO 9001: 2008 / Quality management system

(ii) ISO/TS 16949:2009 / The automotive industry quality management system

(iii) ISO 14001:2004 / Standards for environmental management system

(iv) OHSAS 18001:2007 / International standards for occupational health & safety

c) Product Certificates:

(i) IEC 61215 / IEC 61730: VDE / MCS / CE / JET / SII / CEC AU / INMETRO / CQC

(ii) UL 1703 / IEC 61215 performance: CEC listed (US) / FSEC (US Florida)

(iii) UL 1703: CSA / IEC 61701 ED2: VDE / IEC 62716: TUV / IEC 60068-2-68: SGS

(iv) PV CYCLE (EU) / UNI 9177 Reaction to Fire: Class 1

Note: Vendors shall be committed to providing high quality solar products, solar system solutions and services

d) Key Features:

a) Higher energy yield:

(i) Outstanding performance at low irradiance

(ii) Maximum energy yield at low NOCT

(iii) Improved energy production through reduced cell series resistance

b) Increased system reliability:

87

(i) Long term system reliability with IP67 junction box

(ii) Enhanced system reliability in extreme temperature environment with special cell level stress release

technology

c) Extra value to customers:

(i) Positive power tolerance up to 5W

(ii) Stronger 40mm robust frame to hold wind load up to 2400 Pa

(iii) Anti-glare project evaluation

(iv) Salt mist, ammonia and blowing sand resistance apply to seaside, farm and desert environments

250W Solar Polycrystalline Panels

Solar Polycrystalline 250W (1650 x 992 x 40mm)

• Low voltage-temperature coefficient enhances high-temperature operation.

• Exceptional low-light performance and high sensitivity to light across the entire solar spectrum.

• 25-Year limited warranty on power output and performance.

• 5-Year limited warranty on materials and workmanship.

• Sealed, waterproof, multi-functional junction box gives high level of safety.

• High performance bypass diodes minimize the power drop caused by shade.

• Advanced EVA (Ethylene Vinyl Acetate) encapsulation system with triple-layer back sheet meets the

most stringent safety requirements for high-voltage operation.

• A sturdy, anodized aluminium frame allows modules to be easily roof-mounted with a variety of

standard mounting systems.

• Highest quality, high-transmission tempered glass provides enhanced stiffness and impact resistance.

• High power models with pre wired quick-connect system with MC4 (PV-ST01) connectors.

Solar Polycrystalline Panels

Description

Net

weight

Electrical data under STC (1)

Nomina

l

Power

Max

Power

Voltage

Max

Power

Current

Open-

Circuit

Short-

Circuit

Current

PMPP VMPP IMPP Voc Isc

Kg W V A V A

250W-20V Poly 1650 x 992 x

40mm series 3a

18 250 30 8.33 36.01 9.40

Module SPP (032502400)

Nominal Power (± 3% tolerance): 250W

Cell type: Polycrystalline

Number of cells in series: 60

Maximum system voltage (V) 1000V

Temperature coefficient of PMPP (%): -0.47/°C

Temperature coefficient of Voc (%): -0.34/°C

Temperature coefficient of Isc (%): +0.045/°C

Temperature Range: -40°C to +85°C

88

Surface Maximum Load Capacity: 200 kg/m²

Allowable Hail Load: 23m/s, 7.53 g

Junction Box Type: PV-JB002

Length of Cable / connector: 900mm / MC4

Output tolerance: +/-3%

Frame: Aluminium

Product warranty: 5years

Warranty on electrical performance: 10years 90% + 25years 80% of power output

1) STC (Standard Test Conditions): 1000 W/m2, 25ºC, AM (Air Mass) 1.5

e) Electrical Data / STC*:

Electrical Data CS6P 250P

Nominal Max Power (Pmax) 250W

Opt. Operating Voltage (Vmp) 30.0V

Opt. Operating Current (Imp) 8.33A

Open Circuit Voltage (Voc) 36.01V

Short Circuit Current (Isc) 9.40A

Module Efficiency 15.54 %

Operating Temperature +15°C ~ +45°C

Max. System Voltage 1000 V (IEC) or 1000V (UL) or 600 V (UL)

Module Fire Performance TYPE 1 (UL 1703) or CLASS C (IEC61730)

Max. Series Fuse Rating 15A

Application Classification Class A

Power Tolerance 0 ~ + 5W

*Under Standard Test Conditions (STC) of irradiance of 1000 W/m2, spectrum AM 1.5 and cell temperature of 25°C

f) Electrical Data / NOCT*:

Electrical Data CS6P 250P

Nominal Max Power (Pmax) 181W

Opt. Operating Voltage (Vmp) 27.5V

Opt. Operating Current (Imp) 6.60A

Open Circuit Voltage (Voc) 34.2V

Short Circuit Current (Isc) 7.19A

*Under Nominal Operating Cell Temperature (NOCT), irradiance of 800 W/m2, spectrum AM 1.5, ambient temperature

20°C, wind speed 1 m/s.

g) Performance at Low Irradiance:

Industry leading performance at low irradiation, +96.5% module efficiency from an irradiance of 1000

W/m2 to 200 W/m2 (AM 1.5, 25°C).

h) Module / Mechanical Data:

Specification Data

Cell Type Poly-crystalline, 6 inch

Cell Arrangement 60 (6 ˣ 10)

Dimensions 1650 ˣ 992 ˣ 40mm

Weight 18kg (39.7lbs.)

Front Cover 3.2mm tempered glass

Frame Material Anodized aluminium alloy

89

J-BOX IP67, 3 diodes

Cable 4mm2 (IEC) or 4mm2 & 12 AWG 1000 V (UL 1000 V) or 12

AWG (UL 600 V), 1000 mm (650 mm is optional)

Connectors MC4 or MC4 comparable

Stand. Packaging 24 pcs, 480kg (quantity & weight per pallet)

i) Temperature Characteristics:

Specification Data

Temperature Coefficient (Pmax) -0.43% / °C

Temperature Coefficient (Voc) -0.34 % / °C

Temperature Coefficient (Isc) 0.065 % /

Nominal Operating Cell Temperature 45±2°C

As there are different certification requirements in different markets, please contact your sales

representative for the specific certificates applicable to your products. The specification and key features

described in this Datasheet may deviate slightly and are not guaranteed. Due to on-going innovation,

research and product enhancement, Manufacture’s reserves the right to make any adjustment to the

information described herein at any time without notice. Please always obtain the most recent version

of the datasheet which shall be duly incorporated into the binding contract made by the Sierra Leone

Field Office of the African Development Bank (ADB) and parties governing all transactions related to

the purchase and sale of the products described herein.

j) Shadow Analysis:

The shadow analysis of site has to be carried out by bidder and shall be submitted to Sierra Leone Field

Office of the African Development Bank (ADB), after placement of work order.

2. Quattro 48/10000/140-100/100 Inverter/Charger (Lithium Ion battery compatible):

Quattro 48/10000/140-100/100 Inverter/Charger

90

Quattro 48/10000/140-100/100 Inverter/Charger Unit Description:

1. Two AC inputs with integrated transfer switch

The Quattro can be connected to two independent AC sources, for example the public grid and a

generator, or two generators. The Quattro will automatically connect to the active source.

2. Two AC Outputs

The main output has no-break functionality. The Quattro takes over the supply to the connected loads

in the event of a grid failure or when shore/generator power is disconnected. This happens so fast (less

than 20 milliseconds) that computers and other electronic equipment will continue to operate without

disruption. The second output is live only when AC is available on one of the inputs of the Quattro.

Loads that should not discharge the battery, like a water heater for example can be connected to this

output.

3 Virtually unlimited power thanks to parallel operation

Up to 6 Quattro units can operate in parallel. Six units 48/10000/140, for example, will provide 54kW /

60kVA output power and 840 Amps charging capacity.

4 Three phase capability

Three units can be configured for three phase output. But that’s not all: up to 6 sets of three units can be

parallel connected to provide 162kW / 180kVA inverter power and more than 2500A charging capacity.

5 PowerControl – Dealing with limited generator, shoreside or grid power

The Quattro is a very powerful battery charger. It will therefore draw a lot of current from the generator

or shoreside supply (16A per 5kVA Quattro at 230VAC). A current limit can be set on each AC input.

The Quattro will then take account of other AC loads and use whatever is spare for charging, thus

preventing the generator or mains supply from being overloaded.

6 PowerAssist – Boosting shore or generator power

This feature takes the principle of PowerControl to a further dimension allowing the Quattro to

supplement the capacity of the alternative source. Where peak power is so often required only for a

limited period, the Quattro will make sure that insufficient mains or generator power is immediately

compensated for by power from the battery. When the load reduces, the spare power is used to recharge

the battery.

91

7 Solar energy: AC power available even during a grid failure

The Quattro can be used in off grid as well as grid connected PV and other alternative energy systems.

Loss of mains detection software is available.

8 System configuring

(i) In case of a stand-alone application, if settings have to be changed, this can be done in a matter of

minutes with a DIP switch setting procedure.

(ii) Parallel and three phase applications can be configured with VE.Bus Quick Configure and VE.Bus

System Configurator software.

(iii) Off grid, grid interactive and self-consumption applications, involving grid-tie inverters and/or

MPPT Solar Chargers can be configured with Assistants (dedicated software for specific

applications).

9 On-site Monitoring and control

Several options are available: Battery Monitor, Multi Control Panel, Ve.Net Blue Power panel, Colour

Control panel, smartphone or tablet (Bluetooth Smart), laptop or computer (USB or RS232).

10 Remote Monitoring and control

Victron Ethernet Remote, Victron Global Remote and the Colour Control Panel

Data can be stored and displayed on our VRM (Victron Remote Management) website, free of charge.

11 Remote configuring

When connected to the Ethernet, systems with a Colour Control panel can be accessed and settings can

be changed.

Technical Specifications Quattro 48/10000/140-100/100 Inverter/Charger

Power Control / Power Assist: Yes

Integrated Transfer switch: Yes

AC inputs (2x)

Input voltage range: 187-265VAC

Input frequency: 45 – 65Hz

Power factor: 1

Maximum feed through current (A): 2x100

A. INVERTER

Input voltage range (V DC): 9.5 – 17V, 19 – 33V, 38 – 66V

Output (1):

Output voltage: 230 VAC ± 2%

Frequency: 50 Hz ± 0.1%

Cont. output power at 25°C (VA) (3): 10000

Cont. output power at 25°C (W): 8000

Cont. output power at 40°C (W): 6500

Cont. output power at 65°C (W): 4500

Peak power (W): 20000

92

Maximum efficiency (%): 96

Zero load power (W): 55

Zero load power in AES mode (W): 35

Zero load power in Search mode (W): 20

B. CHARGER

Charge voltage 'absorption' (V DC): 57.6

Charge voltage 'float' (V DC): 55.2

Storage mode (V DC): 52.8

Charge current house battery (A) (4): 140

Charge current starter battery (A) 4: (12V and 24V models only)

Battery temperature sensor: Yes

C. GENERAL

Auxiliary output (A) (5): 50

Programmable relay (6): 3x

Protection (2): a-g

VE.Bus communication port: For parallel and three phase operation, remote monitoring and system

integration

General purpose com. Port: 2x

Remote on-off: Yes

Common Characteristics:

Operating temp.: -40 to +65˚C

Humidity (non-condensing): max. 95%

D. ENCLOSURE

Common Characteristics Material & Colour: Aluminium (blue RAL 5012)

Protection category: IP 21

Battery-connection: Four M8 bolts (2 plus and 2 minus connections)

230 V AC-connection: Bolts M6

Weight (kg): 45

Dimensions (H x W x D in mm): 470 x 350 x 280

E. STANDARDS

Safety: EN-IEC 60335-1, EN-IEC 60335-2-29, IEC 62109-1

Emission, Immunity: EN 55014-1, EN 55014-2, EN 61000-3-3,EN 61000-6-3,

EN 61000-6-2, EN 61000-6-1

Automotive Directive: 2004/104/EC

93

3. Solar Charge Controller MPPT 150/85 (12/24/48V-85A)

Solar Charge Controller MPPT 150/85 (12/24/48V-85A)

Solar Charge Controller MPPT 150/85 (12/24/48V-85A) Unit Description:

1. PV voltage up to 150V

The Solar MPPT 150/70 and 150/85 charge controllers will charge a lower nominal-voltage battery

from a higher nominal voltage PV array.

The controller will automatically adjust to a 12, 24, 36, or 48V nominal battery voltage.

2. Ultra-fast Maximum Power Point Tracking (MPPT)

Especially in case of a clouded sky, when light intensity is changing continuously, an ultra-fast

MPPT controller will improve energy harvest by up to 30% compared to PWM charge controllers

and by up to 10% compared to slower MPPT controllers.

3. Advanced Maximum Power Point Detection in case of partial shading conditions

If partial shading occurs, two or more maximum power points may be present on the power-voltage

curve. Conventional MPPT’s tend to lock to a local MPP, which may not be the optimum MPP.

The innovative BlueSolar algorithm will always maximize energy harvest by locking to the

optimum MPP.

4. Outstanding conversion efficiency

Maximum efficiency exceeds 98%. Full output current up to 40°C (104°F)

5. Flexible charge algorithm

Several preconfigured algorithms. One user programmable algorithm

Manual or automatic equalization

Battery temperature sensor

Battery voltage sense option

6. Programmable auxiliary relay

For alarm or generator start purposes

7. Extensive electronic protection

Over-temperature protection and power derating when temperature is high

PV short circuit and PV reverse polarity protection.

Reverse current protection.

94

8. CAN bus

To parallel up to 25 units, to connect to a ColorControl panel or to connect to a CAN bus network

Technical Specifications Solar Charge Controller MPPT 150/85 (12/24/48V-35A)

Nominal battery voltage: 12 / 24 / 36 / 48V Auto Select

Rated charge current 85A @ 40°C (104°F)

Maximum solar array input power 1): 12V: 1200W / 24V: 2400W / 36V: 3600W / 48V: 4850W

Maximum PV open circuit voltage: 150V absolute maximum coldest conditions

145V start-up and operating maximum

Minimum PV voltage Battery voltage plus 7 Volt to start

Battery voltage plus 2 Volt operating

Standby power consumption: 12V: 0,55W / 24V: 0,75W / 36V: 0,90W / 48V: 1,00W

Efficiency at full load: 12V: 95% / 24V: 96,5% / 36V: 97% / 48V: 97,5%

Absorption charge: 14.4 / 28.8 / 43.2 / 57.6V

Float charge: 13.7 / 27.4 / 41.1 / 54.8V

Equalization charge: 15.0 / 30.0 / 45 / 60V

Remote battery temperature sensor: Yes

Default temperature compensation setting: -2.7 mV/°C per 2V battery cell

Remote on/off: Yes

Programmable relay: DPST AC rating: 240VAC / 4A

DC rating: 4A up to 35VDC, 1A up to 60VDC

Communication port VE.Can: Two paralleled RJ45 connectors, NMEA2000 protocol

Parallel operation: Yes, through VE.Can. Max 25 units in parallel

Operating temperature: -40°C to 60°C with output current derating above 40°C

Cooling: Low noise fan assisted

Humidity (non-condensing): Max. 95%

Terminal size: 35mm² / AWG2

Material & color: Aluminium, blue RAL 5012

Protection class: IP20

Weight: 4,2kg

Dimensions (H x W x D): 350 x 160 x 135mm

Mounting: Vertical wall mount Indoor only

Safety: EN 60335-1

EMC: EN 61000-6-1, EN 61000-6-3

4. Colour Control GX ((Firmware version v1.20)

1. Colour Control GX

The Colour Control (CCGX) provides intuitive control and monitoring for all products connected

to it. The list of Victron products that can be connected is endless.

2. VRM Online Portal

Besides monitoring and controlling products on the CCGX, the information is also forwarded to

remote monitoring systems (VRM Online Portal).

95

3. Future functionality

The CCGX has endless possibilities. There are many features that can be added as a firmware

update. Firmware updates are free of charge, as with all updates of Victron products. Updating the

product is easy: the CCGX will update itself automatically, as long as it is connected to the internet.

Manual updates can be done with a USB stick and microSD cards.

4. Supported products

(i) Multis and Quattros, including split-phase and three-phase systems. Monitoring and control (on/off

and current limiter)

(ii) Solar MPPT 150/70 and the MPPT 150/85. Current solar output is visible on the overview screen,

and all parameters are logged to the VRM online portal. Note that the VRM App has a nice

overview showing data of the Solar MPPT 150/70 as well. When multiple Solar MPPTs with

VE.Can are used in parallel; the Color Control will show all information as one.

(iii) Solar MPPT Solar Chargers with a VE.Direct port (70/15, 75/15, 100/15, 100/30, 75/50, 100/50,

150/35) can be connected to the VE.Direct ports on the CCGX. Connecting multiple at the same

time is possible. They will all appear as a separate Solar Charger in the device list.

(iv) BMV-700 family can be connected directly to the VE.Direct ports on the CCGX. Use the

VE.Direct Cable for this.

(v) BMV-600 family can be connected to the VE.Direct ports on the CCGX. Use the VE.Direct to

BMV60xS cable for that.

(vi) Lynx Ion + Shunt

(vii) Lynx Shunt VE.Can

(viii) Skylla-i

(ix) NMEA2000 tank sensors

(x) A USB GPS can be connected to the USB port. Location and speed will be visible on the display,

and the data is sent to the VRM Portal for tracking purposes. The map on VRM will show the

latest position.

(xi) Wi-Fi USB.

Note that there are more options for products which use the VE.Direct ports, such as BMVs and small

MPPTs. They can also be connected through USB, useful when more than two products need to be

connected. Use an off-the-shelf USB-hub and the VE.Direct to USB interface, ASS030530000.

5. Other highlights

(i) When connected to the internet, the CCGX will update itself automatically when there is a new

software version available.

(ii) Multiple languages: English, Chinese, German, Italian, Spanish, French, Swedish and Dutch.

(iii) Use the CCGX as a Modbus-TCP gateway to all connected Victron products.

Technical Specifications Color Control GX

Power supply voltage range: 9 – 70VDC

Current draw: 12VDC 24VDC 48VDC

Switched off: 0mA, 0mA 0mA

Display off: 140mA 80mA 40mA

Display at minimum intensity: 160mA 90mA 45mA

Display at maximum intensity: 245mA 125mA 65mA

Potential free contact: 3A / 30VDC / 250VAC (Normally open)

96

Communication ports

VE.Direct: 2 separate VE.Direct ports – isolated

VE.Can: 2 paralleled RJ45 sockets – isolated

VE.Bus: 2 paralleled RJ45 sockets – isolated

USB: 2 USB Host ports – not isolated

Ethernet: 10/100/1000MB RJ45 socket – isolated except shield

3rd party interfacing

Modbus-TCP: Use Modbus-TCP to monitor and control all products connected to the Color Control

GX

JSON: Use the VRM JSON API to retrieve data from the VRM Portal

Other

Outer dimensions (H x W x D): 130 x 120 x 28mm

Operating temperature range: -20 to +50°C

5. HOPPECKE VR L 1700 Batteries:

Sun I Power VR L 1700 Valve regulated lead-acid batteries

a) Design Parameters:

(i) Design Life: >20 Years

(ii) Voltage: 2Volts

(iii) Capacity: 100Ah to 1700Ah

b) Typical applications:

(i) Village power supplies

(ii) Hybrid systems

(iii) Peak Shaving/voltage stabilization

(iv) Stations of mobile communications

(v) Sustainable tourism

(vi) Cathodic corrosion protection

97

(vii) Pumping systems

c) Benefits:

(i) Maintenance-free regarding water refilling – due to innovative Gel-technology

(ii) Very high cycle stability during PSoC1 operation – due to tubular plate design with

efficient charge current acceptance

(iii) Maximum compatibility – dimensions according to DIN 40742

(iv) Optimal space utilization – due to possibility of horizontal arrangement

(v) Higher short-circuit safety even during the installation – based on HOPPECKE system

connectors

(vi) Proven long service life

(vii) Spill proof and leak proof with triple seal terminal design

Specifications:

Series OPzV C100/1.85

V

Ah

C50/1.85

V

Ah

C24/1.83

V

Ah

C10/1.80

V

Ah

C5/1.77

V

Ah

Max.

Weigh

t

kg

Max.

Lengt

h

mm

Max.

Widt

h

mm

Max.

Heigh

t

mm

Sun I power

VR L 1700

1955 1870 1785 1545 1372 110.0 215 277 855

d) Certificate of Compliance:

BS 6290: Part 4 & IEC 60896-21/22:2004

This is a British / European standard specification for sealed type valve regulated lead acid

batteries prepared under the direction of the Light Electrical Engineering Standards Committee.

This standard is of a series of standards, specifications and requirements for all types of

stationary Lead Acid Cells or Monobloc Batteries.

e) Accessories:

All equipment required for the correct and safe installation and maintenance of each battery is

provided, and include clear terminal covers, terminal grease, interconnects, cell numbers and

installation and operation manual

f) Guarantee:

All cells are supplied with a full replacement, ex-factory, 60 months warranty, against faulty

manufacturing and workmanship, when installed and operated in accordance with SEC’s

published Installation and Operating Instructions.

ADDITIONAL PARAMETERS REQUIRED:

The electrical safety of the array installation is of the utmost importance. Array electrical configuration

shall be in such a way that, the MPPT shall operate with maximum efficiency, between the low and

high temperature of the site. Maximal Current ripple 5% PP Power Factor 0.95 inductive to 0.95

capacitive ambient room temperature 5 to 55 degree C

Housing Cabinet:

a) PCU is housed in suitable switch cabinet, with min IP 21 degree of Ingress Protection.

b) Weatherproof, rodents & insect proof

98

c) Components and circuit boards mounted inside the enclosures clearly identified with appropriate

permanent designations, which shall also serve to identify the items on the supplied drawings.

d) All doors, covers, panels and cable exists shall be gasketed or otherwise designed to limit the entry

of dust and moisture. All doors shall be equipped with locks. All openings shall be provided with

grills or screens with openings no larger than 0.95 cm (about 3x8 inch).

Other important features Electrical safety Protections:

a) General

b) Over/under voltage The PCU shall include appropriate self-protective and self-diagnostic feature

to protect itself and the PV array from damage in the event of PCU component failure or from

parameters beyond the PCU’s safe operating range due to internal or external causes.

The self-protective features shall not allow signals from the PCU front panel to cause the PCU to

be operated in a manner which may be unsafe or damaging. Faults due to malfunctioning within

the PCU, including commutation failure, shall be cleared by the PCU protective devices and not

by the existing site utility grid service circuit breaker.

a) Generator/Utility (Grid) over-under voltage protection.

b) Frequency protection.

c) Fool Proof Protection

d) Accidental open circuit

e) Internal Faults

f) Galvanic Isolation

c) Over voltage protection against atmospheric lightning

d) Protection against voltage fluctuations in the grid itself and internal faults in the power

conditioner, operational errors and switching transients.

e) Against ISLANDING:

Note: (i) MOV type surge arrestors on AC and DC terminals for over voltage

protection from lightning-induced surges

(ii) Full protection against accidental open circuit and reverse polarity at the

input.

(iii) Inbuilt protection for internal faults including excess temperature, commutation

failure, overload and cooling fan failure is obligatory

(iv) Galvanic isolation shall be provided to avoid any DC component being injected

into the grid and the potential for AC components appearing at the array.

Galvanic isolation shall be provided between the inverter/ PCU and

generator/grid to avoid any DC component being injected into the grid and the

potential for AC components appearing at the array.

The specification of the isolation transformer shall be as follows:

Capacity: 125% of capacity of the PV modules (i.e. a 12.5 kVA

transformer shall be used for a 10kW PV system, and so on)

System: 3-phase, 4-wire

Input voltage range: 320-480 V AC

Output voltage range: 380-435 V AC

99

Output voltage for single phase: 220-240 V AC

Tap change: Manual, V+/-20%, V+/-10%, V+/-0%

Operating frequency: 48-52 Hz

Efficiency; >98.5%

Impedance: 4-10%

Output waveform: Zero distortion

Insulation class: Class F

Leakage current: <20 mA

Cooling: AN

f) Earth Fault Supervision

g) Disconnection & Islanding

Enclosure: IP 21 (if indoors) IP 54 (if outdoors)

Operating Temperature: 0-60°C

Cable entry: Separate input/ output enclosed cable entry

Standard: IS 2026 - Further, it is also observed at various locations throughout the distribution grid

that the grid voltage would consistently be greater or less than the acceptable voltage window of

many inverters and PCUs.

Moreover, this variation may be only for particular days of a week, seasonal, or for a limited time. - In

such a case, the Contractor shall study/ measure the point of interconnection of the PV system

consistently for at least one week to identify the voltage range experienced at the interconnection point

of the distribution grid. Consequently, the Contractor shall adjust the input/ output of the isolation

transformer to appropriate tap settings so that the voltage on the inverter side of the transformer is always

within the acceptable voltage window of the inverter.

The appropriate tap setting shall be conveyed to Sierra Leone Field Office at the African Development

Bank (ADB) by the contractor. An integrated earth fault detection device is provided to detect eventual

earth fault on DC side and shall send message to the supervisory system Disconnection of the PV

generator in the event of loss of the main grid supply is achieved by in built protection within the power

conditioner. This may be achieved through rate of change of current, phase angle, unbalanced voltages,

or reactive load variants. Operation outside the limits of power quality as described in technical data

sheet shall cause the power conditioner to disconnect the grid.

h) Codes & Standards

The quality of equipment supplied shall be controlled to meet the guidelines for engineering design

included in the standards and codes listed in the relevant ISI and other standards, such as:

a) IEEE 928: Recommended Criteria for terrestrial PV power systems.

b) IEEE 929 Recommended practice for utility interface of residential and intermediate PV

systems.

c) IEEE 519 Guide for harmonic control and reactive compensation of Static Power Controllers.

d) National Electrical NFPA 70-1990 (USA) or equipment national standard.

e) National Electrical Safety Code ANSI C2 (USA) or equipment national standard. Inverter /

Array Size ratio

The ratio of the Inverter continuous power rating and the array peak power rating shall be between 80

to 90% or any other value found suitable. This is because better overall annual yield can be obtained by

allowing the Inverter to operate for longer periods closer to optimal efficiency. Inverter efficiency should

100

exceed 90% except when operating at less than 10% of maximum output. MPPT Maximum power point

tracker is integrated in the power conditioner unit to maximize energy drawn from the array. The MPPT

shall be microprocessor based to minimize power losses. The MPPT shall have provision (manual

setting) for constant voltage operation.

i) Metering

(i) PV array energy production: Meter to log the actual amount of AC energy generated / consumed by

the PV system shall have to be provided.

(ii) Solar irradiance:

An integrating pyranometer (Class II or better) to be provided, with the sensor mounted in the plane

of the array. Readout shall be integrated with data logging, Data Logging System

a) All major parameters available on the digital bus and logging facility for energy auditing through

the internal microprocessor and can be read on the digital front panel at any time the current values,

previous values for up to a month and the average values.

The following parameters shall be accessible via the operating interface display:

• AC voltage

• AC output current

• Output power

• DC input voltage

• DC input current

• Time active

• Time disabled

• Time Idle

• Temperatures (C)

• Converter status Protective function limits (VIZ-AC over voltage, AC under voltage, Over

frequency, under frequency, ground fault, PV starting voltage, PV stopping voltage, over

voltage delay, under voltage delay over frequency, ground fault delay, PV starting delay, PV

stopping delay. Remote Monitoring System - A remote monitoring system shall be included

with each photovoltaic system. - Usually such monitoring systems are connected and

synchronized with the inverters. - Such monitoring services are provided by many leading

inverter manufacturers and also third party service providers. - The monitoring system should

transmit the following data in real-time to a central server and store it:

• DC currents, voltages and power

• AC currents, voltages and power

• Irradiation, ambient temperature, module temperature and wind speed.

• Error logs.

This data may be transmitted either using the available LAN or GSM/ GPRS, or any other mode of

connectivity available at the site. - The contractor shall be responsible for data connectivity for

monitoring up to the warranty/ O&M period of the PV system, after which, the Contractor shall

transfer all ownership rights, SIM card, account information, instructions, etc. to Sierra Leone Field

Office at the African Development Bank (ADB). - The contractor shall ensure that the Sierra Leone

Field Office at the African Development Bank (ADB) is aware of the contracts required to maintain

connectivity post-warranty/ O&M period. - This data shall be accessible by Sierra Leone Field

Office at the African Development Bank (ADB) through a secure login account. - The stored data

should be represented through hourly, daily, monthly, etc. graphs and easily downloadable in .csv

or xls format.

101

j) Cables & accessories

For Cables & Accessories following certificates are mandatory: (Copy to be provided with tender)

General Test and Measuring Methods PVC insulated cables for working Voltages up to and

including 1100 and UV resistant for outdoor installation IEC 60189 IS 694/ IS 1554 IS/IEC 69947

All the cables which shall be supplied shall be conforming to IS 1554 / 694 Part 1 of 1988 & shall

be of 650V/ 1.1kV grade as per requirement. Only PVC copper cables shall be used. The size of

the cables between array interconnections, array to junction boxes, junction boxes to PCU etc. shall

be so selected to keep the voltage drop and losses to the minimum. Certification of cables should

be submitted in the tender.

k) Control room

The required control room shall be constructed at additional cost if required. Otherwise, PCU/ Solar

Inverter should be placed/ mounted in suitable housing.

l) Spare parts

One set of essential spares for the PCU shall be provided and made available at the plant.

m) Documentation

The Vendor shall endeavour to supply sufficient information with the systems so the client can get

a comprehensive overview of all the components, their function, interaction and the potential

challenges of an off-grid solution.

All documentations shall comply with AS5033 and Clean Energy Council

Two sets of installation manual / user manual shall be supplied along with the Vendor’s submission.

The manual shall include complete system details such as array lay out, schematic of the system,

inverter details, working principle etc. Step by step maintenance and troubleshooting procedures

shall be given in the manuals. Module layout drawing has to be submitted to the Sierra Leone Field

Office at the African Development Bank (ADB) 2 nos. set of line diagram and licensed electrical

contractors’ certificate has to be submitted to the Sierra Leone Field Office at the African

Development Bank (ADB).

102

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

COMPOUND SOLAR LIGHTING SERVICES ENGINEERING FOR OFFICE BUILDING AT

REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE

AFRICAN DEVELOPMENT BANK (ADB)

103

STANDALONE PV SOLAR COMPOUND SECURITY LIGHTING SYSTEM

1. Definition:

A standalone solar photovoltaic compound lighting system comprises a compact fluorescent lamp, lead

acid battery, PV module(s), control electronics, inter-connecting wires/cables, module mounting

hardware, battery box, operation instruction and maintenance manual.

2. Duty Cycle:

The system should be designed to automatically switch ON at dusk, operate throughout the night and

automatically switch OFF at the dawn, under average daily insolation of 5kWh/sq. m. on a horizontal

surface.

3. Lamp:

The lamp shall have following features:

a) 62W LED

(i) Power: 62W

(ii) Light Intensity: 5,000 lm

(i) Middle Lifespan: 50.000 hr.

(iv) Thread: E-40

(v) Providing quick and save re-lamping!

b) The light output from the lamp should be around 1800 +/- 5% lumens. Also please see (iii) of V

given below.

c) The lamp should be housed in a weather proof assembly suitable for outdoor use, with a reflector

on its back. While fixing the assembly, the lamp should be held in a base up configuration. OR 3

LED fixtures -Specifications for 62W LED Compound Light: (Supporting Documents Required)

1. LED Type: High power of 1W each

2. Power Consumption: 62W ± 10%, maximum 1.35 W per LED with 85% driver efficiency.

3. Luminous flux efficacy ≥ 110 lm/Watt

4. Colour Rendering Index ≥ 75

5. Colour Temperature: 5500 K- 7500K (White)

6. Circuit Efficiency: ≥ 85%

7. Life expectancy/Lumen maintenance: 50000 burning hours at ambient temperature with 70%

Lumen maintenance

8. Construction: IP 65

9. Control Circuit: Compatible with LED

10. Operating temperature: - 40 0 C to 59 0 C. Following testing parameters shall be carried out

at National/NABL accredited laboratory (For luminaries):

1. Marking

2. Luminaire Power

3. Circuit Efficiency

4. Polar Curve

5. Chromaticity co-ordinates and correlated colour temperature

6. Colour Rendering Index

Note: Polar curve is a lux distribution pattern which shows whether the luminaire matches

Pole height and pole span.

104

4. Battery:

Following IEC/IS certificates are mandatory for the battery: (Copy to be provided with tender.) General

Requirements & Methods of Test - IEC 61427 Tubular Lead Acid- IS 1651/IS 13369

(i) Flooded electrolyte type, positive tubular plate, low maintenance lead acid battery.

(ii) The battery will have a minimum rating of 12V, 100 Ah/ 100Ah (at C/10) discharge rate.

iii) 75% of the rated capacity of the battery should be between fully charged and load cut off

conditions.

5. Electronics:

(i) The inverter should be of quasi sine wave/sine wave type, with frequency in the range of

20-35 KHz-Half-wave operation is not acceptable.

(ii) The total electronic efficiency should be at least 85%

(ii) No blackening or reduction in the lumen output by more than 10% should be observed after 1000

ON/OFF cycles (two minutes ON followed by four minutes OFF is one cycle.

(iv) The idle current consumption should not be more than 10mA.

(iii) Electronics should operate at 12 V and should have temperature compensation for proper charging

of the battery throughout the year.

(iv) Necessary lengths of wires/cables and fuses should be provided and wiring of cables should be

through the pole with no open access to cables.

(v) The PV module will be used to sense the ambient light level for switching ON and OFF the lamp.

6. Electronic Protections:

(i) Adequate protection is to be incorporated under no load conditions e.g. when the lamp is removed

and the system is switched ON.

(ii) The system should have protection against battery overcharge and deep discharge conditions.

(iii) Fuses should be provided to protect against short circuit conditions.

(iv) A blocking diode should be provided as part of the electronics, to prevent reverse flow of current

through the PV module (s), in case such a diode is not provided with the solar module (s).

(v) Full protection against open circuit accident, short circuit and reverse polarity should be provided.

7. PV Module (s):

a. The PV module (s) shall contain crystalline silicon solar cells.

b. The PV module bidder should have IEC 61215-2nd Edition and IEC 61730-2 qualification

certification for PV modules. Copy to be provided with tender

c. The power output of the module (s) under STC should be a minimum of 120W.

d. The operating voltage corresponding to the power output mentioned above should be 16.4V

e. The open circuit voltage of the PV modules under STC should be at least 21.0 Volts.

f. The terminal box on the module should have a provision for opening for replacing the cable, if

required.

g. A strip containing the following details should be laminated inside the module as to be clearly

visible from the front side.

1. Name of the Bidder or distinctive Logo

2. Model or Type No.

3. Serial No.

4. Year of make.

105

8. Mechanical Hardware:

(i) Metallic frame structure (with corrosion resistance paint) with 25mm X 25mm X 3mm MS angle

to be fixed on the top of the poll to hold the SPV module (s). The frame structure should have

provision to adjust its angle of inclination to the horizontal between 0 and 45, so that it can be

installed at the specified tilt angle in the desired direction.

(ii) The pole should be made of GI medium class pipe with a height of minimum 7meters & 6mtrs

above the ground level after grouting (details shall be furnished in the offer) and final installation.

The pole, will be consisting of three portions with lower portion (length 4m) of 114.3mm dia. with

wall thickness of 3.65mm, and middle portion (length 1.5m) of 88.9mm diameter with wall

thickness of 3.25mm and top portion (length 1.5m) of 76.1mm dia. with wall thickness of 3.25mm

and base plate of 175mm X 175mm X 6mm. The 1 ½ inch dia. bend pipe for fixing up the lamp

assembly with suitable clamps to mount on the pole should be G.I. medium class pipe and should

be adjustable. The pole should have the provision to hold the weather proof lamp housing. It should

be painted with a corrosion resistant paint.

(iii) The battery box provided should be of a vented metallic with acid proof corrosion resistance paint

(epoxy paint) for housing the storage battery outdoors with locking arrangement. The battery box

should be tightly clamped with the pole. The thickness of MS Sheet of battery box shall be of

minimum 18 SWG. All hardware, nuts, bolts should be cadmium passivated.

(iv) The grouting of the pole should be done by PCC 1:2:3, pit must be 0.3 X 0.3 X 1 m deep below

ground level and a collar of 0.3m above ground level must be of 0.3m diameter.

(vi) Detailed drawings with specifications of each component should be submitted with the Technical

Bid.

9. Other Features:

(i) The system should be provided with 2 LED indicators a green light to indicate charging in progress

and a red LED to indicate deep discharge condition of the battery. The green LED should glow

only when the battery is actually being charged.

(ii) There will be a Name Plate on the system which will give

(a) Name of the Supplier or Distinctive Logo

(b) Serial Number

(iii) Components and parts used in the solar street lighting systems should conform to the latest BIS

specifications, whenever such specifications are available and applicable.

(iv) The PV module (s) will be warranted for a minimum period of 10 years from the date of supply

and the street lighting system (including the battery) will be warranted for a period of two years

from the date of supply.

General Conditions: applicable to all the systems:

PV modules used in solar power plants/systems must be warranted for their output peak watt

capacity, which should not be less than 90% at the end of 12 years and 80% at the end of the 25

years.

106

The BoS items/components of the SPV power plants/systems deployed must confirm to the latest

edition of IEC/equivalent BIS standards as specified below: BoS item/component Applicable

IEC/equivalent BIS Standard Description Standard Number Power Conditioners/Inverters*

Efficiency Measurements Environmental Testing IEC 61683 IEC 60068 2 (6,21,27,30,75,78)

Charge controller/MPPT units*

Design Qualification Environmental Testing IEC 62093 IEC 60068 2 (6, 21, 27, 30, 75, 78)

Storage Batteries General Requirements & Methods of Test Tubular Lead Acid IEC 61427 IS

1651/IS 13369 Cables

General Test and Measuring Methods PVC insulated cables for working Voltages up to and

including 1100 VDo, UV resistant for outdoor installation IEC 60227/IS 694 IEC 60502/ IS

1554(part I & II)

Switches/ Circuit Breakers/Connectors General Requirements Connectors -safety IS/IEC 60947

Part I, II, III EN 50521

Junction Boxes/Enclosures for inverter/ charge controller/ luminaries General Requirements

Enclosures IP 54 (for outdoor)/IP 21 (for indoor) as per IEC 529 * Must additionally conform to

the relevant national/international Electrical Safety Standards.

Proposed FAOSL Compound Solar Light

Foundation:

In this version the Batteries are positioned in a special, waterproof and stable plastic subterranean container.

Advantages:

The Batteries are protected against vandalism and high temperature.

In case we are reaching air temperature of 20-25°C around the Batteries (perfect temperature for the Batteries).

The assembly is very simple, pluggable and any chance of incorrect wiring.

107

The temperatures in the earth will increase hardly more than 25° degrees Celsius; through this the life time of

The batteries will increase by about 100%!

The pole is placed in a concrete pipe of 40cm in diameter and of 1m in length. The storage battery has to be

fitted into a shaft in a distance of abt. 1 meter from the pole

108

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 1

X 175kVA, 400/230V, 3-PHASE, 50Hz VOLTAGE REGULATOR FOR OFFICE BUILDING AT

REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE

AFRICAN DEVELOPMENT BANK (ADB)

109

TECHNICAL SPECIFICATIONS OF 1 X 175kVA, 400/230V, 3-Phase, 50Hz VOLTAGE

REGULATOR:

Description:

Bad power cost money! Disruptive and often damaging voltage sags and surges can cause unnecessary

downtime, costly equipment repairs, and lost productivity … all of which affect office and business

operations! AC voltage regulators and constant voltage transformers provide clean, stable power, thus

improving your equipment reliability and performance!

Controlled Power Company's line of AC voltage regulators ranges from 500VA to 1MVA, with

regulation tolerances down to 1% of nominal voltage.

To mitigate against disruptive and often damaging voltage sags and surges at Office Building at Regent

Road, Hill Station, Freetown for Sierra Leone Field Office at the African Development Bank (ADB)

The proposed 100kVA, 400/230V, 3-Phase, 50Hz voltage regulation product shall include an integral

shielded isolation transformer, providing high harmonic, line and ground noise attenuation for added

power conditioning and regulation tolerances down to 1% of nominal voltage.

Power Processor Series 700F (175kVA)

Description

The Series 700F is a front access, tap switching, power conditioning voltage regulator which features

a small footprint, high efficiency design, triple-shielded isolation transformer, tight output voltage

regulation to +/- 3%, as well as optional power quality monitoring. Digital processing provides fast,

accurate regulation within 1 cycle, without over- or under-shoot. With a unique front access cabinet

design, left, right, and rear access are not required for system installation, operation or service.

The Series 700F has been shake-table tested and meets seismic standards which satisfy the

CBC 2013, and IBC 2015 standards and been recognized and accepted by most countries.

The seismic-rated Series 700F is the perfect power conditioner to meet the power requirements of the

Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field Office at the African

Development Bank (ADB) with an input nominal voltage of 400VAC complete floor-mounting

channels.

110

Features & Benefits:

Front access only! All installation, operation, maintenance, and testing can occur from the front of

the unit — no side or rear access required.

7-tap, microprocessor-controlled for tight voltage regulation, accuracy, and stability.

Precisely maintains correct voltage to ± 3% within 1 cycle, and maintains regulation during

extended brownouts.

Extended input regulation range options including +10%, -40%; +15%, -25%; and +20%, -30%

Low output impedance transformer minimizes voltage distortion and sags commonly associated

with high surge currents.

Triple-shielded isolation transformer provides a noise-free ground, attenuates voltage spikes and

transients, and re-establishes the N-G bond.

Internal manual bypass option maintains system isolation, voltage transformation, and power

conditioning.

Superior compatibility with dynamic loads.

Increased surge capability, without the need for automatic bypassing, provides full-time power

conditioning.

High-efficiency design results in lower operating cost.

Technical Specs

Input Operating Voltage Range: +10%, - 20% from nominal (Extended regulation range

options available)

Input Frequency: 60 Hz, ± 3%

Input Power Factor: > .99 PF with resistive load

Reflected Harmonics: Triple harmonics are not reflected to the utility under

non-linear loads

Output Line Voltage Regulation: ± 3% from nominal

Response Time: < 1/2 cycle

Correction Time: 1 cycle

Load Regulation: 2.5% typical, no load to full load

Overload Rating: 200% for 10 seconds; 1000% for 1 cycle

Common Mode Noise Attenuation: 146dB

Transverse Mode: 3 dB down at 1kHz; 40 dB down per decade to below

50 dB with a resistive load

Transient Voltage Suppression: Meets ANSI C62.41 Category B-3

Efficiency: 96% - 97% typical, model and load dependent

UL 1012 Listed, C-UL Listed to CSA C22.2, No. 107.1-01

Applications

Government / Commercial Buildings

Broadcast Communications

Telecommunications

Refineries / Petro-Chemical

Aerospace

Printing Presses

Food Processing Plants

UPS Bypass & Power Distribution

111

SPECIFICATION OF 175kVA SERIES700F VOLTAGE REGULATOR

Power Processor - Series 700F 175KVA Power Conditioning and Regulation for Commercial &

Industrial Equipment General Specifications

1: GENERAL

1.1 DESCRIPTION

This specification defines the electrical and mechanical characteristics of the 175kVA

Controlled Power Voltage Regular - Series 700F

Front Access Power Processor, an AC power conditioning system with line voltage regulation.

The system specified includes all the components necessary to provide the electrical power

quality needed for the improved operation, performance and reliability of commercial and

industrial electronic equipment. Power conditioning is accomplished through use of an integral

3 phase, copper wound, triple shielded, low output impedance isolation transformer.

Integral transient voltage surge suppression is included to meet and exceed ANSI/IEEE

recommendations for surge voltages in AC power circuits. Line voltage correction is

accomplished within 1 cycle, preventing undesirable over and under voltage conditions. The

regulator incorporates microprocessor control, digital processing, and independent phase

regulation to provide the specified voltage, without any voltage over or under-shoots.

1.2 STANDARDS

The Series 700F Power Processor is designed in accordance with applicable portions of the

following standards:

A. American National Standards Institute (ANSI)

B. Institute of Electrical and Electronic Engineers (IEEE)

C. National Electric Code (NEC)

D. National Fire Protection Association (NFPA Article 70)

E. FCC Article 15, Section J, Class A

F. ANSI C62.41 Category B-3

G. UL Listed to Standard 1012

H. C-UL listed to CSA Standard C22.2, No. 107.1-01 Seismic-rated units with an input

nominal voltage of 240VAC, or 480VAC are designed and tested in accordance with

applicable portions of the following additional standards:

I. OSHPD Special Seismic Certification Preapproval (OSP)

J. ICC - AC156: “Acceptance Criteria for Seismic Certification by Shake-Table Testing

of Non-structural Components and Systems”

K. California Building Code – CBC 2013

L. International Building Code – IBC 2015

2: PRODUCTS

2.1 Input Specifications

A. Nominal AC input voltage ratings: 600VAC, 400VAC, 3 Phase.

B. Nominal operating frequency: 50 hertz, +/- 3 hertz.

2.2 Output Specifications

A. Nominal AC output voltage: 400/230VAC, wye derived.

B. Output impedance: 3-4% typical.

C. The main power conditioning transformer includes seven (7) full capacity taps per

phase, allowing for the tight output voltage regulation specified.

112

D. Continuous duty output power ratings: (175) kVA / kW.

2.3 Performance Specifications

A. Input voltage range: +10, -20% with the output voltage regulated to +/- 3% typical. Extended

input voltage range options of (+10%, -40%) (+15, -25%) or (+20, -30%) are available, with

the output voltage regulated to +5%, -6% typical.

B. Response time: < ½ cycle.

C. Correction time: 1 cycle typical.

D. Output load regulation: 2.5% typical, when stepping from no load to full load.

E. Output voltage THD: < 1% THD added to the output waveform under any dynamic linear

loading conditions.

F. Input power factor: > .99 with a resistive load, and triplen harmonics are not reflected to the

utility under non-linear loads.

G. Overload rating: 200% continuous load rating for 30 seconds, 1,000% for 1 cycle.

H. Common mode noise attenuation: 146 dB minimum.

I. Transverse mode noise attenuation: 3 dB down at 1,000 hertz, 40 dB down per decade below

50 dB with a resistive load.

J. Efficiency: 96-97% typical, excitation losses shall be less than 1.5% of the KVA.

K. MTBF: > 100,000 hours.

2.4 Main Input Circuit Breaker

A main input molded case, thermal magnetic circuit breaker, rated at 125% of the full

continuous load input current at the nominal input voltage, is furnished as an integral part of the

unit.

2.5 Standard Monitoring

A. Alert Light

An indicator light shows if the output has been disabled by one of the following conditions:

1. Transformer over-temperature

2. SCR thermal over-temperature

B. Indicating Lamps

Output ON indicating lamps are provided for each phase.

2.6 Main Transformer Construction

A. The transformer windings are of all copper conductor construction with separate primary and

secondary isolated windings.

B. Fully processed, low carbon, silicon-iron transformer steel is used to minimize losses and

provide maximum efficiency. Flux density does not exceed 14k gauss

C. Class N (200° C) insulation is utilized throughout with a 115° C maximum temperature rise.

D. The transformer has multiple (three) copper shields to minimize inner winding capacitance,

transient and noise coupling between primary and secondary windings. Inner winding

capacitance is limited to .001 pF or less.

113

2.7 Cabinet Construction

A. Design allows for front access to the status lights, input circuit breaker, serviceable parts, and

optional output circuit breaker(s), bypass switch, and metering. No side or rear access is

required for system installation, operation or service.

B. Input and output terminations are front access. Input terminations are made directly to the main

input circuit breaker and the input ground terminal provided. Output terminations are made to

the copper bus connections provided, 3 phase, neutral and ground, or the optional output circuit

breaker(s) and neutral & ground copper bus provided.

C. Conduit landing plates are provided to permit top and/or bottom entry for input and output

power connections.

D. Ventilation originates from the front of the cabinet and exhausts through the top of the cabinet.

E. The electronic control section is isolated from transformer section and power terminations.

F. Transformer section is designed for natural convection cooling.

G. The cabinet is NEMA 1 rated and constructed using a 12 gauge steel frame with 10 gauge steel

floor mounting channels. Optional locking casters, together with mounting brackets to

permanently secure the cabinet to the floor, are available.

H. Exterior panels are pre-treated and powder-coat painted with Controlled Power Company’s

standard colour

2.8 BTU’s / Hour, Weight and Dimensions

Output

kVA

Rating

Full Load

BTU’s / Hour

Weight (lbs) Dimensions

175 11,883 2014 34.5”W x 36”D x 76”H

2.9 Environmental

A. Operating temperature: -20°C to +40°C.

B. Relative humidity: 0-95% non-condensing.

C. Altitude: 5,000 feet above sea level without de-rating.

D. Audible noise: < 50 dba at 1 meter distance.

2.10 Optional Equipment

A. Remote emergency power off options includes:

1. Input breaker provided with a 24VDC or 400VAC under voltage trip relay to interface with an

on-site emergency power off circuit. An external 24VDC or 400VAC power source is supplied

by others and required to energize the breaker.

2. Input breaker provided with a 24VDC or 400VAC shunt trip coil solenoid to interface with an

on-site emergency power off circuit. An external 24VDC or 400VAC power source is supplied

by others and required to shunt trip the breaker.

3. Shunt trip input breaker provided to interface with a Remote Emergency Power Off push button

station, provided on a 50 ft. cable, which terminates within the power conditioner/regulator

enclosure.

114

B. Manually operated rotary switch provided to bypass the regulator portion of the system. The

regulator is either on-line or bypassed with one turn of the switch. The transformer, high

frequency filtering, and electrical noise suppression remain in the circuit when in the bypass

mode.

C. Digital input and/or output meters, flush-mounted on the front of the unit for ease of operation

and viewing. Options include:

1. Shark100V4 digital meter to measure and display voltage, current, kVA, kVAh, kW, kWh,

kVARs, kVARh, power factor, frequency, and % THD. Includes a % load bar, limits exceeded

alarms, and RS485 communication using MODBUS or DNP 3.0 protocols.

2. Shark200V4 digital meter to measure and display voltage, current, kVA, kVAh, kW, kWh,

kVARs, kVARh, power factor, frequency, and % THD. Includes a % load bar, data-logging

with time stamp, programmable limit alarms on all measured parameters, a waveform scope

feature to view the real-time voltage and current waveform, and RS485 communication using

MODBUS or DNP 3.0 protocols.

3. Shark200V6 digital meter to measure and display voltage, current, kVA, kVAh, kW, kWh,

kVARs, kVARh, power factor, frequency, and % THD. Includes a % load bar, data-logging

with time stamp, programmable limit alarms on all measured parameters, a waveform scope

feature to view the real-time voltage and current waveform, and RS485 communication using

MODBUS or DNP 3.0 protocols. The meter provides power quality monitoring with event

logging, advanced harmonic analysis, and a 512 samples per cycle waveform recorder.

D. Shark200V4 or V6 digital meter provided with up to two (2) of the following options:

1. Ethernet TCP and MODBUS TCP web card.

2. Two form C relay contacts to trigger on user-set alarms.

3. Four channel 4-20mA outputs, assignable to any parameter.

E. Up to two (2) output circuit breakers can be selected, ranging from 15 amps, 3-pole, to the

maximum circuit breaker rating listed below. If only one (1) output circuit breaker is selected

at 208VAC on units rated 75kVA and above, a higher amperage rating can be selected as

indicated below. KVA and voltage are output ratings.

KVA 400/415V

175 253A

F. Red LEDs (one per phase) provided to indicate if the source voltage exceeds the specified input

range of the regulator.

G. Output under/over voltage shutoff options included:

1. Output is electronically shut off if the output voltage exceeds adjustable limits. The system is

reset by cycling the input breaker.

2. Input breaker is shunt tripped if the output voltage exceeds adjustable limits, or a loss of power

is detected. A manual resetting of the input breaker is required.

2.11 Warranty

Controlled Power Company guarantees all systems to be free from defects in material and

workmanship for a period of (1) year following shipment from the factory.

115

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING

OF 2 X 10kVA, 3-PHASE MODULAR DECENTRALIZED PARALLEL ARCHITECTURE

(DPA) UNINTERRUPTIBLE POWER SUPPLIES (UPS) FOR OFFICE BUILDING AT

REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF

THE AFRICAN DEVELOPMENT BANK (ADB)

116

TECHNICAL SPECIFICATIONS OF 20kVA 3-PHASE MODULAR DPA UPS:

Specification for the Supply, Installation, Testing and Commissioning of 2 x 10KVA, 3-Phase

Modular DPA Uninterruptible Power Supplies (UPS)

PARTICULAR SPECIFICATION:

ELECTRICAL:

CONTENTS

SECTION 1 INTRODUCTION AND DESCRIPTION OF WORKS

SECTION 2 ELECTRICAL SERVICES INSTALLATION

SECTION 3 SPECIFICATIONS AND REQUIREMENTS OF 10kVA 3Phase Modular DPA UPS

117

SECTION 1: DESCRIPTION OF WORKS

1.01 General

1.02 The Site

1.03 The Building

1.04 Site Working

1.05 Site Visit

1.06 Extent of Works

1.07 Statutory Requirements and Standards

1.08 Maintenance of Services

1.09 As Installed Drawings and Operating and Maintenance Manuals

1.10 Site Clearance

118

SECTION 1 - INTRODUCTION AND DESCRIPTION OF WORKS

1.01 General:

This Particular Specification details the requirements for the supply, installation, testing and

commissioning of 2 x 10kVA 3Phase Modular DPA UPS and shall be read in conjunction with

the Conditions of Contract, Tender Forms and Equipment Specifications.

1.02 The Site:

The site is the Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field

Office at the African Development Bank (ADB).

The building is a 3 story structure located within the secure perimeter fence of the

Establishment.

1.03 Site Working:

The installation works shall be carried out under the control and supervision of the Consultant

Engineer

1.04 Site Visit:

The Contractor shall visit site prior to submitting a Tender to satisfy himself of local conditions

appertaining to this Contract, and the location and extent of existing services.

Arrangements to visit the site shall be made through the Project Architect, 72 Wellington Street,

Freetown.

1.05 Extent of Works:

The Contractor shall supply, install, test and commission 2 x 10kVA 3Phase Modular DPA UPS

Unit at the for Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field

Office at the African Development Bank (ADB)

The Scope of Works shall comprise the following:

1) Supply and installation of 2 x 10kVA 3Phase Modular DPA UPS Unit complete with

cabinets including cabling and accessories

2) Testing and commissioning of 2 x 10kVA 3Phase Modular DPA UPS

1.06 Statutory Requirements and Standards:

The Works shall include for all costs to complete the installation in accordance with this

Particular Specification as scheduled.

The following Statutory Requirements and Standards shall also be adhered to by the Vendor:

a) The Regulations for Electrical Installations 17th Edition 2000. (BS 7671: 1992 - The

Requirements for Wiring Installations)

b) The relevant British Standards and Codes of Practice where applicable.

c) Health & Safety at Work Act.

d) The Electricity at Work Regulations.

e) Any other special requirements of the Electricity Distribution Supply Authority EDSA)

1.07 Maintenance of Services:

Any works necessitating interruption or termination of any services required to be maintained

or serving areas outside of the designated works area shall be thoroughly co-ordinated and not

be initiated until a Programme of Works indicating disruption time scales and/or temporary

arrangements has been submitted and agreed fully by all concerned.

119

1.09 Working Drawings:

The Contractor shall be responsible for the preparation of fully dimensioned installation

drawings of a standard and scale suitable for indicating installation details of all works to the

satisfaction of the Supervising Engineer. The Contractor shall be responsible for setting out

services to integrate the works within the structure, taking into account all aspects of the Works.

Working Drawings shall be submitted for approval of the Supervising Engineer before the

installation works begin.

The Working Drawings shall set out all services and equipment and take into account the

positions of all building elements.

Particular care shall be taken to prevent obstruction or restriction of service positions and access

positions to engineering services.

1.10 Site Clearance:

At the end of the project, all empty packages, rubbish and unused materials and plant shall be

removed and the site left in a clean and tidy condition.

120

SECTION 2: - ELECTRICAL SERVICES INSTALLATION

2.01 General

2.02 Cable Specification

2.03 Electrical Supplies

2.04 Earthing and Bonding

2.05 Builders Work

2.06 Testing and Commissioning

121

SECTION 2 ELECTRICAL SERVICES INSTALLATION:

2.01 General:

The Electrical Works shall comprise the supply, delivery, installing, putting into operation,

testing and commissioning of the 2 x 10kVA Modular DPA UPS as detailed in this

Specification.

2.02 Cable Specification:

600/1000V cables shall be of circular or shaped stranded plain annealed copper conductors

XLPE/SWA/LSOH to BS 6724.

Power cable size shall be 16mm2 from the Main Electrical Switchroom 250A MCCB 12-way

Panelboard

2.03 Electrical Supplies:

L.V. Cables:

The incoming electrical supply from the 250A MCCB 12-way Panelboard to the 63A TP&N

Fused Switch Disconnector located in the UPS Room shall be provided by the Electrical

Contractor at 400 volts, 50Hz.

The Contractor shall provide new supply power cables from the 63A TP&N Fused Switch

Disconnector located in the UPS Room to the UPS’s.

The L.V. cables shall be laid direct on cable tray, protected and secured by cable tiles.

All builders work duct entries into the UPS Room shall be fully detailed by the Contractor as

part of his production of working drawings for approval procedures.

The Contractor shall be responsible for fully surveying the proposed cable route prior to starting

any installations. The Contractor shall check and verify the area along and surrounding the

proposed cable route, that other services shall not be impeded or disrupted by the placing and

ducting route. Where other services are found to be in close proximity to the route, the

Contractor shall ensure that ducting works are properly conducted. Such areas of risk shall be

confirmed and documented by the Contractor prior to the works commencing.

Cable jointing and final cable terminations shall be carried out by the Contractor strictly in

accordance with the cable manufacturer’s installation recommendations for handling, bending

radii, terminations, glands etc.

It shall be the Contractor’s responsibility to check and test the connected cable prior to

‘’switching on’’ to ensure its suitability for operation. Upon completion of these tests the

Contractor shall forward the schedule of results to the Project Architect/M&E Engineer.

Where sub-main cables are to be supported on cable tray prior to termination, the Contractor

shall allow for the necessary cable cleats (cable ties will not be permitted) to fix the cable onto

the cable tray, and for all tray work accessories, risers, uninstructed supports etc., to complete

the installation.

2.04 Earthing and Bonding:

General:

Supply and install an earth system for the installation.

The earth system in in the UPS room shall include an earth bar to which all Low Voltage

Switchgears and UPS cabinet shall be connected.

122

The earth bars shall be 50mm x 6mm high conductivity, hard drawn copper mounted on shock-

resisting stand-off insulators

The neutral earth terminals on the neutral bus bars of the switchgears shall be connected to the

earth bar by means of a 35mm single core, XL-LSF insulated cable.

Each of the switchgears shall have separate earthing cable connections from the earth bar. Each

section of the main Low Voltage Switchboard shall be bonded to its neighbour.

Joints may be made in the copper strips by the thermal process or be bolted, riveted or clamped.

Additionally, it shall be ensured that:

i) Copper jointing surfaces shall be tinned.

ii) All bolts, rivets and clamps shall be of brass, bronze or similar non-ferrous material.

iii) Joints not readily accessible for inspection shall be protected against moisture and

corrosion.

iv) The resistance of any length of conductor containing a joint or tap-off connection shall

not be greater than that of an equal length of similar conductor without a joint.

Earthing leads within the UPS Room shall be secured at intervals not exceeding 0.5 metre.

The earth systems shall have a maximum resistance of 0.5 ohms in dry weather conditions. The

type of electrode installed shall be of the steel cord copper clad type.

The incoming supply cable armoured sheath shall be connected to the common earth point on

the earth bar.

All cable screens, trunking and metal enclosures, switchgears, etc., are to be connected to form

a continuous bonded earth system directly connected to the earth bar.

The Contractor shall test the impedance of the incoming earthing connection and the results

shall be recorded and issued to the Engineer.

2.05 Builders Work

All builders work required in connection with the installation of services specified herein shall

be carried out under this Contract.

The Contractor shall carry out all his builders work requirements necessary for him to complete

his installation.

The builders work items generally comprises work such as mortising and minor builders work

required to existing structures.

2.06 Testing and Commissioning:

The Contractor shall allow for testing the entire UPS installation for performance.

The objectives of the T & C works are:

(i) To verify proper functioning of the equipment/system after installation.

(ii) To verify that the performance of the installed equipment/systems meet with the

specified design intent through a series of tests and adjustments.

(v) To capture and record performance data of the whole installation as the baseline for

future operation and maintenance.

123

Scope of the Testing and Commissioning (T&C) Works:

A. Preliminary Steps for Testing and Commissioning:

Before carrying out T&C, the Contractor shall take the following steps:

(a) Submit draft T&C procedures to the Engineer for approval. The draft T&C procedures

shall include essential procedures mentioned in this procedure plus additional T&C

procedures required for specific installations as well as manufacturer’s

recommendation;

(b) Obtain design drawings and specifications and to be thoroughly acquainted with the

design intent

(c) Obtain copies of approved shop drawings and equipment schedules;

(d) Review approved shop drawings and equipment schedules;

(e) Check manufacturer’s operating instructions and statutory requirements;

(f) Physically inspect the installation and equipment to determine variations from designs

and/or specifications.

(g) Check individual components, e.g. key switches, control equipment, circuit breaker

status, etc. for proper position and settings for completeness of installation.

(h) Check inclusion of manufacturer’s typical equipment testing data or factors before T&C

of particular equipment.

B. Testing and Inspection during Construction:

The purpose of these tests is to ensure that all components and systems are in a

satisfactory and safe condition before start up. Preliminary adjustment and setting of

equipment at this stage shall also be carried out at the same time to pave way for the

coming functional performance tests.

Before carrying out any test, the Contractor shall ensure that the installation complies

with all relevant statutory requirements and regulations. The T&C works shall comply

with all site safety regulatory requirements currently in force, including but not limited

to:

(i) Electricity Ordinance and other subsidiary legislation herein; IEE _TCP 2007

Edition

(ii) The Code of Practice for the Electricity (Wiring) Regulations (COP)

(iii) IEC 60364 “Electrical Installations of Building”

(iv) Electricity supply rules of the relevant power supply companies

C. Statutory Test and Inspection

The statutory test and inspection herein stated in this T&C procedure shall refer to the

Regulations Nos. 19, 20, 21 and 22 of the Electricity (Wiring) Regulations under the

Electricity Ordinance Chapter 406E.

D. Functional Performance Tests

The purpose of functional performance tests is to demonstrate that the

equipment/installation can meet the functional and performance requirements as

specified in the General/Particular Specifications. Functional performance test should

proceed from the testing of individual components to the testing of different systems in

the installation.

The Contractor may have to make temporary modifications as the test proceeds. The

specific tests required and the order of tests will vary depending on the type and size of

systems, number of systems, sequence of construction, interface with other installations,

relationship with the building elements and other specific requirements as indicated in

the General/Particular Specifications.

124

The testing of systems may have to be carried out in stages depending on the progress

of work or as proposed by the Contractor.

Any performance deficiencies revealed during the functional performance tests must be

evaluated to determine the cause and whether they are part of the contractual obligations.

After completion of the necessary corrective measures, the Contractor shall repeat the

tests.

If any test cannot be completed because of circumstances that are beyond the control of

the Contractor, it shall be properly documented and reported to the Engineer, who shall

then liaise with the relevant parties to resolve the situation. The Contractor shall resume

his testing work immediately upon the attainment of a suitable testing environment.

125

SECTION 3: - SPECIFICATIONS AND REQUIREMENTS OF 10kVA 3Phase Modular

DPA UPS

3.01 Product Description

3.02 Efficiency up – costs down

3.03 Quality Assurance

3.04 Delivery, Storage and Handling

3.05 Project Conditions

3.06 Warranty

3.07 Maintenance

3.08 Mode of Operation

3.09 Component Description

3.10 System Controls and Indicators

3.11 Mechanical Design and Ventilation

3.12 Battery

3.13 Examination

3.14 Installation

3.15 Field Quality Control

3.16 Demonstration

3.17 Protection

3.18 Typical Modular DPA UPS system

3.19 Proposed Decentralized Parallel Architecture

3.20 Technical specifications

3.21 Material Schedule

126

SECTION 3: SPECIFICATIONS AND REQUIREMENTS OF 10kVA 3Phase Modular DPA

UPS:

3.01 Product Description:

The DPA is a high-power, modular UPS system designed for today’s critical high-density ICT

environments. The UPS is built using true online double conversion technology and delivers

high quality power. When combined with complete network integration software and

communication connectivity, the DPA provides a comprehensive, easy-to-integrate power

protection for data centres and network environments.

The DPA is based on ABB’s unique and proven Decentralized Parallel Architecture DPATM.

DPA means that each UPS module contains all the hardware and software required for full

system operation. They share no common components. The major benefit of a DPA system is

very high power availability. Each UPS module has its own independent static switch, rectifier,

inverter, logic control, control panel and battery charger. Even the batteries can be configured

separately for each module if required. With all of the critical components duplicated and

distributed between individual units, potential single points of failure are eliminated. System

uptime is further maximized by the true safe-swap modularity of the modules (easy replacement

during system operation) which allows the simple addition or removal of modules without the

need to bypass the UPS.

DPA modules can be connected in parallel configuration to provide redundancy or to increase

the system’s total capacity. The DPA shall deliver power protection from 10 to 30 kVA (one to

three modules) in a single cabinet. Cabinets shall operate in parallel configuration to build a

system of up to 30kVA

Further DPA highlights:

• Power density of up to 342kW / m2 saves floor space

• Near-unity input power factor and low input harmonic distortion reduce running costs

• Safe-swap modules maximize availability and minimize upgrade costs

3.02 Efficiency up – costs down:

Lower your total cost of ownership:

The DPA boasts the lowest cost of ownership of any UPS system by offering energy efficiency,

scalable flexibility and ergonomic design to enable easy serviceability.

The DPA allows the infrastructure size to be scaled to align more closely with the prevailing IT

requirements. Scaling the infrastructure to meet present IT needs, with the ability to add on

incrementally as IT needs grow, also means that you only power and cool what you need. The

resulting savings in power usage are substantial over the service life of the UPS.

Simplify installation and service:

Its straightforward and understandable concept simplifies every step of the deployment process,

from planning, through installation and commissioning to full use. Easy set-up and maintenance

involve lower operating and maintenance costs. The DPA allows adding modules in a simple

plug-and-play procedure.

Optimize your energy efficiency:

Class-leading energy efficiency significantly reduces system running costs and site air-

conditioning costs.

127

Advanced scalable architecture:

If additional capacity or redundancy is needed, up to 30 independent modules can operate in

parallel configuration,

DPA – product range:

To ensure the ultimate in flexibility, the Conceptpower DPA is available in various

configurations. The lower power cabinets can accommodate batteries internally. External

battery cabinets are available for all product types.

DPA – safe-swap modularity:

True safe-swap modularity enables the safe removal and / or insertion of UPS modules into a

Conceptpower DPA system without risk to the critical load and without the need to either

transfer the critical load onto raw mains or remove power from the critical load. This unique

feature directly addresses today’s requirement for continuous uptime. The ability to safe swap

modules in a Conceptpower DPA system significantly reduces its mean time to repair (MTTR)

and simplifies system upgrades.

3.03 Quality Assurance:

Qualifications:

Manufacturer Qualifications:

Manufacturer shall be a firm engaged in the manufacture of solid State UPS of types and sizes

required, and whose products have been in satisfactory use in similar service for a minimum of

20 years. The manufacturer shall be ISO 9001 certified and shall be designed to internationally

accepted standards.

Installer Qualifications:

Installer shall be a firm that shall have a minimum of five years of successful installation

experience with projects utilizing solid state UPS similar in type and scope to that required for

this Project.

Regulatory Requirements:

Comply with applicable requirements of the laws, codes, ordinances, and regulations of State

and Local Authorities having jurisdiction. Obtain necessary approvals from such authorities.

The UPS shall meet the requirements of the following standards:

(i) UL listed under UL 1778.

(ii) IEC 1000 4, Level 4.

The UPS shall be designed in accordance with the applicable sections of the documents

published by:

(i) National Fire Protection Association (NFPA); NEC

(ii) International Electrical Manufacturers Association (NEMA)

(iii) Occupational Safety and Health Administration (OSHA)

Factory Testing:

Prior to shipment the manufacturer shall complete a documented test procedure to test functions

of the UPS module and batteries (via a discharge test), when supplied by the UPS manufacturer,

and warrant compliance with this Section. The manufacturer shall provide a copy of the test

report.

128

Source Responsibility:

Materials and parts comprising the UPS shall be new, of current manufacture, and shall not

have been in prior service, except as required during factory testing.

Active electronic devices shall be solid state and shall not exceed the manufacturer’s

recommended tolerances for temperature or current to ensure maximum reliability.

Semiconductor devices shall be sealed. Relays shall be provided with dust covers. The

manufacturer shall conduct inspections on incoming parts, modular assemblies, and final

products.

3.04 Delivery, Storage and Handling:

Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and

containers, labelled with supplier’s or manufacturer’s name, material or product brand name,

and lot number, if any.

Store materials in their original, undamaged packages and containers, inside a well-ventilated

area protected from weather, moisture, soiling, extreme temperatures, and humidity.

Products shall be packaged in a manner to prevent penetration by debris and to allow safe

delivery by modes of ground transportation and air transportation where specified.

Prior to shipping, products shall be inspected at the factory for damage.

Equipment shall be protected against extreme temperature and humidity and shall be stored in

a conditioned or protected environment.

Equipment containing batteries shall not be stored for a period exceeding three months without

powering up the equipment for a period of eight hours to recharge the batteries.

3.05 Project Conditions:

Environmental Requirements:

Do not install solid state UPS until space is enclosed and weatherproof, wet work in space is

completed and nominally dry, work above ceilings is complete and ambient temperature and

humidity conditions are and will be continuously maintained at values near those indicated for

final occupancy.

The UPS shall operate under the following environmental conditions:

(i) Temperature:

UPS Module Operating: 32°F (0°C) to 104°F (40°C).

Non-Operating: 4°F (20°C) to 113°F (4°C).

(ii) Relative Humidity (Operating and Storage): 0 percent to 95 percent non-condensing

(iii) Barometric Pressure:

Up to 3281 feet (1000 meters) above sea level (up to 6562 feet [2000 meters] with

ambient temperature less than 82 °F [28 °C]) / up to 39,370 feet (12,000 meters) above

sea level non-operating.

(iv) Audible Noise: 69 dBA at 3 feet (914 mm).

129

3.06 Warranty:

Special Warranty:

The Contractor shall warrant the work of this Section to be in accordance with the Contract

Documents and free from faults and defects in materials and workmanship for period indicated

below. This special warranty shall extend the one year period of limitations contained in the

General Conditions. The special warranty shall be countersigned by the Installer and the

manufacturer.

UPS Module:

The UPS shall be covered by a full parts and labour warranty from the manufacturer for a period

of 12 months from date of installation or acceptance by the Owner or 18 months from date of

shipment from the manufacturer, whichever occurs first.

Battery:

The battery manufacturer’s warranty shall be passed through to the final Owner and shall have

a minimum period of one year.

Additional Owner Rights:

The warranty shall not deprive the Owner of other rights the Owner may have under other

provisions of the Contract Documents and shall be in addition to and run concurrent with other

warranties made by the Contractor under requirements of the Contract Documents.

3.07 Maintenance:

The manufacturer shall, upon request, provide spare parts kits for the UPS module in a timely

manner as well as provide access to qualified factory trained first party service personnel to

provide preventative maintenance and service on the UPS module when required.

UPS subassemblies, as well as the battery, shall be accessible from the front. UPS design shall

provide maximum reliability and minimum MTTR (mean time to repair). To that end, the UPS

shall be equipped with a self-test function to verify correct system operation. The self-test

function shall identify the subassembly requiring repair in the event of a fault. The electronic

UPS control and monitoring assembly shall therefore be fully microprocessor based, thus doing

away with potentiometer settings. This shall allow:

(i) Auto compensation of component drift

(ii) Self-adjustment of replaced subassemblies

(iii) Extensive acquisition of information vital for computer aided diagnostics (local or

remote).

(iv) Socket connection to interface with computer aided diagnostics system.

The UPS shall be repairable by replacing standard subassemblies requiring no adjustments.

Communication via a modem with a remote maintenance system shall be possible.

The manufacturer shall offer additional preventative maintenance and service contracts

covering both the UPS and the battery bank. Accredited professional service engineers

employed exclusively in the field of critical power systems service shall perform maintenance

and service. The manufacturer shall also offer extended warranty contracts.

130

3.08 Modes of Operation

UPS module shall be designed to operate as a double conversion, on line reverse transfer system

in the following modes.

Normal:

The inverter shall continuously supply power to the critical load. The PFC rectifier shall derive

power from the utility AC source and supply DC power to the inverter while simultaneously

floats charging the battery.

Emergency:

Upon failure of the utility AC power source, the critical load shall be supplied by the inverter,

which, without any interruption, shall obtain its power from the battery.

Recharge:

Upon restoration of the utility AC power source (prior to complete battery discharge), the PFC

rectifier shall power the inverter and simultaneously recharge the battery.

Bypass Mode:

The static bypass transfer switch shall be used to transfer the load to the bypass without

interruption to the critical power load. This shall be accomplished by turning the inverter off.

Automatic retransfer or forward transfer of the load shall be accomplished by turning the

inverter on.

3.09 Component Description:

PFC Rectifier and Battery Charger:

Incoming AC power shall be converted to a regulated DC output voltage by an IGBT (insulated

gate bipolar transistor) power factor correction (PFC) rectifier. The PFC rectifier shall provide

high quality DC power to charge the batteries and power the inverter and shall have the

following characteristics:

Input Power Factor Correction (PFC):

The PFC rectifier shall be power factor corrected so as to maintain an input power factor of 0.98

lagging to unity at 75 percent or above load levels to ensure generator compatibility and avoid

reflected harmonics from disturbing loads sharing the utility power.

Input Harmonic Current Suppression:

The PFC rectifier shall produce a sinusoidal input AC current on each phase with low harmonic

content, limiting THD on the UPS input to below 3 percent. This shall eliminate the requirement

for an input filter.

Modular Assembly:

The PFC rectifier assembly shall be constructed of modular design

to facilitate rapid maintenance.

Battery Charger Current Limiting:

The UPS shall be equipped with a system designed to limit the battery recharge current (from

0.05 C10 to 0.1 C10).

131

Charging Levels:

The battery charging circuitry shall be capable of being set for automatic battery recharge

operation, float service, manual battery charge service, and equalizing or commissioning

operation.

Intermittent Charging:

The battery charge level shall be maintained by an intermittent charging technique between two

values Vfmin and Vfmax very close to the floating voltage.

This technique shall be based on a cycle made up of a short charge period (a few seconds) from

Vfmin to Vfmax followed automatically by a slow discharge period (a few minutes) from

Vfmax to Vfmin. This cycle shall be repeated continuously to maintain the battery charge level.

In this way the battery shall actually be charging only for a small part of the time, which shall

considerably increase its service life.

Temperature Compensated Charging:

The battery charger shall be equipped with a temperature probe to enable temperature

compensated charging and shall adjust the battery float voltage to compensate for the ambient

temperature using a negative temperature coefficient of 3 mV per cell per degree Celsius at a

nominal temperature of 25°C.

Battery Capacity:

The battery charger shall have sufficient capacity to support a fully loaded inverter and shall

fully recharge the battery to 95 percent of its full capacity within 6 to 8 hours.

Inverter:

The UPS output shall be derived from a variable frequency Pulse Width Modulated (PWM)

IGBT inverter design. The inverter shall be capable of providing the specified precise output

power characteristics while operating over the battery voltage range. The inverter assembly

shall be constructed as a modular assembly to facilitate rapid maintenance.

Static Bypass – 100 Percent Rated, Continuous Duty:

The static bypass transfer switch shall be solid state, rated for 100 percent continuous duty

without mechanical contactor device in parallel for higher reliability and consistent response

time and shall operate under the following conditions:

Uninterrupted Transfer:

The static bypass transfer switch shall automatically cause the bypass source to assume the

critical load without interruption after the logic senses one of the following conditions:

(i) Inverter overload exceeds unit's rating.

(ii) Battery protection period expired and bypass current is available.

(iii) Inverter failure.

Interrupted Transfer:

If the bypass source is beyond the conditions stated below, the UPS shall make an interrupted

transfer (not less than 100 milliseconds in duration) Bypass voltage greater than +10 percent,

10 percent from the UPS rated output voltage.

Bypass frequency greater than ±2 hertz from the UPS rated output frequency.

132

Automatic Uninterrupted Forward Transfer:

The static bypass transfer switch shall automatically forward transfer power, without

interruption, after the UPS inverter is turned on after an instantaneous overload induced reverse

transfer has occurred and the load current returns the UPS’s nominal rating or less.

Manual Transfer:

A manual static transfer shall be initiated from the UPS control panel by turning the UPS

inverter off.

Overload Ratings:

The static bypass transfer switch shall have the following overload characteristics:

(i) 1000 percent of UPS output rating for 0.016 seconds (one cycle).

(ii) 150 percent for 1 second

(iii) 130 percent of UPS output rating for 1 minute.

Output Static Switch – 100 percent Rated, Continuous Duty: UPS output shall be equipped with

a 100 percent rated output static switch without mechanical contactor device in parallel for

higher reliability and consistent response time of 16.66 milliseconds.

Microprocessor Controlled Logic:

The full UPS operation shall be provided through the use of microprocessor controlled logic.

Operation and parameters shall be firmware controlled, thus eliminating the need for manual

adjustments or potentiometers. The logic shall include, but shall not be limited to, a self-test

and diagnostic circuitry such that a fault shall be isolated down to the printed circuit assembly

or plug in power assembly level.

Every printed circuit assembly or plug in power assembly shall be monitored. Diagnostics shall

be performed via a PC through the local diagnostics port on the UPS.

Standard Display, Control and Indicator Panel:

The UPS shall include, but shall not be limited to, a standard easy to use control and indicator

panel.

Included shall be a backlit, colour graphic animated LCD display and LED indicators.

The UPS panel shall include, but shall not be limited to, UPS on and UPS off pushbuttons that

shall permit the Owner to safely command the UPS on or off without risk of load loss.

3.10 System Controls and Indicators:

Front Panel LCD Display:

The UPS control panel shall provide a backlit, colour graphic display with choice of over 15

operating languages for indication of UPS status, metering, battery status, alarm/event log, and

advanced operational features.

Access:

The display shall provide access to:

(i) An animated, colour mimic diagram indicating UPS power flow

(ii) Measurements, status indications and events.

133

(iii) Bar graphs and waveforms of the measured values.

(iv) Personalization menu protected by a password, used to make specific settings.

(v) Event log with time stamping.

(vi) Access to measurements.

System Parameters Monitored:

The visual display shall display the following system parameters based on true RMS metering:

Measurements:

(i) Input voltage (Ph-Ph).

(ii) Input current per phase.

(iii) Bypass voltage.

(iv) Bypass input frequency.

(v) UPS output voltage (Ph-Ph and Ph-N) (three phase simultaneously).

(vi) UPS output current per phase (three phase simultaneously).

(vii) UPS output frequency.

(viii) UPS output percent load.

(ix) UPS output kVA.

(x) UPS output power factor.

(xi) Battery voltage.

(xii) Crest factor.

(xiii) Battery current.

(xiv) Battery backup time and remaining service life.

(xv) Battery temperature.

Status Indications and Events:

(i) Load on battery.

(ii) Load on UPS.

(iii) Load on automatic bypass.

(iv) Low battery warning.

(v) General alarm.

(vi) Battery fault.

(vii) Remaining back up time during operation on battery power.

(viii) Bypass source outside tolerances.

(ix) Battery temperature.

Additional indications shall provide maintenance assistance.

Display of Operating Curves:

The graphical display shall be capable of displaying curves and bar graphs of the above

mentioned measured values for significant periods.

Time Stamped Historical Events:

This function shall time stamp and store important status changes, anomalies, and faults and

make this information available for automatic or Owner requested consultation.

134

LED Status Indicators:

The UPS control panel shall provide three LEDs that shall signal the following status

conditions:

Green LED: Load protected.

Yellow LED: Minor fault.

Red LED: Major fault, load not protected.

On/Off Switch:

The UPS shall provide the on and off buttons to start and stop the inverter. The switch shall

provide a built in time delay to eliminate the risk of inadvertent operation (additional

confirmation shall be requested). It shall be possible to remotely activate the off function via

an isolated dry contact to create an emergency power off function, resulting in:

(i) Inverter shutdown.

(ii) Opening of the automatic bypass.

(iii) Opening of the input, bypass, output, and battery switches/circuit breakers.

(v) Opening of the isolated dry contact on the programmable relay card.

Audible Alarm Reset:

The UPS shall provide an audible alarm that can be stopped using the Owner’s interface. If a

new alarm is sensed after the original alarm has been silenced, it shall reactivate the audible

alarm.

Emergency Power Off (EPO):

The UPS shall be equipped with a local emergency power off button and dry contact input that

shall be used to command UPS shutdown remotely. Activation of this command shall lead to

the following actions:

(i) Inverter shutdown.

(ii) Opening of the static bypass switch and the battery circuit breaker.

(iii) Opening of input and output switch/circuit breaker.

(iv) Opening of an isolated dry contact on the programmable relay board.

DB 9 Connector:

One DB 9 connector with serial output shall be provided for field diagnostics.

Dry Contacts:

The UPS shall be provided standard with a programmable input/output relay board. This board

shall have eight dry contacts (i.e., six for input signals and two for output signals).

Contacts shall be programmed as:

(i) UPS on line.

(ii) Load on bypass.

(iii) UPS on battery.

(iv) UPS battery low.

(v) General alarm.

(vi) Remote UPS on (input).

(vii) Remote UPS off (input).

The contacts shall be normally open and shall change state to indicate the operating status. The

contacts shall be rated at 2.0 amperes (250 volts AC/30 volts DC).

135

3.11 Mechanical Design and Ventilation:

Enclosure:

The UPS shall be housed in a freestanding enclosure with dead front construction. The

mechanical structure of the UPS shall be sufficiently strong and rigid to withstand handling and

installation operations without risk. Access to UPS subassemblies shall be through the front or

top.

The sheet-metal elements in the structure shall be protected against corrosion by a suitable

treatment, such as zinc electroplating, Bi-chromating, epoxy paint, or an equivalent.

Cable Access:

The standard UPS available shall accommodate top and bottom entry cables.

Cabinet Weights and Dimensions:

The width of the UPS shall be 730 × 1975 × 800mm) and shall have a maximum weight of 368

– 379 kg)

Ventilation and Heat Rejection:

The UPS shall be designed for forced air cooling. Air inlets shall be provided from the front

bottom of the UPS enclosure. Air exhaust shall be from the top portion of the unit. Full load

heat rejection shall be 36,000 BTUs per hour.

3.12 Battery:

General:

The UPS module shall use a valve regulated sealed lead acid heavy duty industrial battery,

designed for auxiliary power service in an UPS application. The primary battery shall be

furnished with impact resistant plastic cases and housed in a matching cabinet(s) next to the

UPS module.

Protection Against Deep Discharge and Self Discharge:

The UPS shall be equipped with a device designed to protect the battery against deep discharge,

depending on discharge conditions, with isolation of the battery by a circuit breaker. In

particular, a monitoring device shall adjust the battery shutdown voltage as a function of a

discharge coefficient to avoid excessive discharge at less than the rated output. A second device

shall avoid self-discharge of the battery into the UPS control circuits during an extended

shutdown of the UPS (over two hours).

Battery Self Tests:

The battery monitoring system shall be able to perform the following automatic functions:

(i) Battery circuit checks every 12 hours.

(ii) Open circuit battery test once a month.

(iii) Partial discharge test every three months

This self-test system shall signal faults via LEDs on the front panel or a message to remote

supervision systems.

136

3.13 Accessories:

Extended Battery Cabinet:

Matching battery cabinets shall be furnished in either adjacent or stand-alone versions. The

cabinet shall match the height and depth of the UPS module and shall have a width of 26.5

inches (673 mm) or 33.5 inches (851 mm) per battery cabinet. Power wiring and control cables

shall be included for adjacent models.

UL 924 Listed Battery Cabinets:

If UL 924 listed battery cabinets are provided for modules, the specific UPS and specific battery

cabinets shall comprise the UL 924 listed system. This system shall be in compliance with UL

924 criteria for a minimum of 90 minutes of battery operation with a full load on the UPS. UL

924 recharge criteria shall be met with both normal and reduced input voltage conditions.

The battery cabinets shall be non-matching and available in stand-alone version only. Power

wiring and control cables from the UPS to the battery cabinets shall not be included. With

multiple battery cabinets, interconnect cables shall be provided.

Automated Monitoring/Remote Power Monitoring Service:

Remote power monitoring, a 24 hours per day, seven days per week remote UPS monitoring

and reporting service, shall be provided. The system shall use standard analog telephone lines

(via modem) as the communication medium to transmit critical UPS data, alarms, and anomalies

back to a central station. In addition, the central station shall communicate with each of the

subscribing UPS on a routine basis to check equipment status, operating conditions, and

measured values. Reported anomalies and routine interrogation data shall be accumulated for

utilization in generating a quarterly Owner report.

External Control and Communications Devices:

Up to three of the following control and communications devices may be installed in the UPS

module:

RS 232/U Talk or Dry Contacts Card (66060):

The U Talk protocol shall be used with Solution Pac 2 for remote monitoring or graceful

shutdown for most popular file servers. The dry contacts shall close on predefined conditions

to monitor UPS operations. This shall require one communication slot and optional cables.

The dry contacts shall close on the conditions listed below, but shall be Owner programmable

to close on pre-set thresholds of other Owner UPS parameters:

(i) UPS on line

(ii) Load on bypass.

(iii) UPS on battery

(iv) Low battery warning

(v) Battery fault

(vi) General alarm

Two dry contact inputs shall also be provided to turn the UPS inverter on and off remotely upon

closure of the contacts. This feature may also be disabled if required.

137

RS 232 or RS 485 JBus/Modbus Card (66061):

The U Talk protocol shall be used with Solution Pac 2 for remote monitoring or graceful

shutdown for most popular file servers. The JBus protocol shall be used with third party building

management systems (BMS) to monitor detailed three phase information. This shall require

one communication slot and optional cables.

High Voltage 6 Alarm Relays Card (66069):

A second set (one set shall be provided standard with the UPS module) of six normally open

dry contact outputs rated at 2.0 amperes (250 volts DC/30 volts DC) shall be available to

monitor UPS operation.

The dry contacts shall close on the conditions listed below, but shall be Owner programmable

to close on pre-set thresholds of other Owner UPS parameters:

(i) UPS on line.

(ii) Load on bypass.

(iii) UPS on battery.

(iv) Low battery warning.

(v) Battery fault.

(vi) General alarm.

Two dry contact inputs shall also be provided to turn the UPS inverter on and off remotely upon

closure of the contacts. This feature may also be disabled if required.

Network Management Card (66074):

The network management card (NMC) shall provide a web interface, SNMP (simple network

management protocol), logging, and email capabilities. The NMC shall be used for remote

monitoring or graceful shutdown for most popular file servers.

IBM AS/400 Volt Free Contact/Remote Power Off Card (66068):

The UPS shall interface with an IBM AS400 UPS signal interface providing the following

signals via dry contacts:

(i) Load on battery.

(ii) Load on bypass.

(iii) Low battery shutdown warning.

(iv) Load powered by UPS.

Multi Slot Communications Card Expander (66071):

The Multi Slot shall provide three additional communication slots. The U Talk Acquisition Card

(66063) shall be included.

Distribution Panelboard:

A 42 pole front facing distribution Panelboard shall be provided with the UPS in a matching

adjacent wide cabinet. The Panelboard shall be a Square D, NQO panel accommodating ten 100

ampere breakers. The Panelboard shall accommodate any combination of one, two, or three

pole breakers and shall have a sub main circuit breaker (optional) feeding the Panelboard.

138

Two or Three Circuit Breaker External Maintenance Bypass Wall Mount:

The maintenance bypass option shall provide for two or three circuit breakers mounted inside a

wall mounted enclosure to provide a wraparound bypass configuration for total UPS isolation

during maintenance. Maintenance bypass transfers shall be without interruption and shall have

mechanical keyed interlocks to protect the UPS from damage in the event of out of sequence

transfers. An optional electrically based solenoid activated key release shall be available to

control the removal of the keys from the key interlocks.

Remote Alarm Status Panel (RASP):

A wall mounted panel, 17.5 inches (445 mm) high by 12 inches (305 mm) wide by 4 inches

(102 mm) deep, with eight indicating LED's shall display UPS status and any active alarms.

The alarms shall be a latching type, such that if an alarm is triggered, the LED shall stay on

(latch) even if the alarm is corrected. This feature shall provide the operator the chance to verify

the occurrence of the alarm.

The parameters monitored and controls provided on the RASP panel include, but shall not be

limited to, the following:

(i) UPS on line (green LED).

(ii) UPS on battery (yellow LED).

(iii) Load on bypass (yellow LED).

(iv) UPS summary alarm (red LED).

(v) Low battery shutdown.

The RASP shall also be equipped with:

(i) Alarm test/reset pushbutton (white LED) to reset the latching alarm.

(ii) Audible alarm for alarm annunciation.

(iii) Audible alarm reset pushbutton (white LED) to silence the audible alarm.

The RASP door shall be equipped with a key lock. The recommended maximum distance from

the UPS module shall be 500 feet (152 m).

Remote Summary Alarm Panel (RSAP):

A wall mounted panel with five indicating LED's shall display UPS status and any active alarms.

The alarms shall be a latching type, such that if an alarm is triggered, the LED shall stay on

(latch) even if the alarm is corrected. This feature shall provide the operator the chance to verify

the occurrence of the alarm.

The parameters monitored and controls provided on the RSAP include, but shall not be limited

to, the following:

(i) UPS summary alarm (red LED).

(ii) UPS on battery (yellow LED)

Seismic Anchors:

Seismic Zone 4 anchors shall be available for system cabinets.

Dual Input:

A second input terminal block shall be provided to accommodate a separate input source.

139

Internal Maintenance Bypass:

An internal manual maintenance bypass switch shall be optionally provided to isolate the UPS

inverter output and static bypass transfer switch for maintenance. This shall allow the UPS to

be tested or repaired without affecting load operation.

Bypass Input Fuses:

Bypass input fuses shall be optionally provided on the bypass for current limiting.

3.13 Examination:

Verification of Conditions:

Examine areas and conditions under which the work is to be installed, and notify the Contractor

in writing, with a copy to the Owner and the Architect/Engineer, of any conditions detrimental

to the proper and timely completion of the work. Do not proceed with the work until

unsatisfactory conditions have been corrected.

Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by

the Installer.

3.14 Installation:

Preparation and installation shall be in accordance with reviewed product data, final shop

drawings, manufacturer’s written recommendations, and as indicated on the Drawings.

3.15 Field Quality Control:

Field Service Engineer Qualifications:

The Contractor shall employ a field service Engineer, factory trained with an accredited and

proven competence to install and service three phase UPS.

Spare Parts:

Contractor / Field Engineer shall have immediate access to recommended spare parts with

additional parts storage located in the country. Additional spare parts shall be accessible on a 7

x 24 basis from the national depot and shall be expedited on a next available flight basis or via

direct courier (whichever mode is quickest).

3.16 Demonstration:

The Contractor shall provide the services of a train Engineer to provide start up service and to

demonstrate and train the Client’s personnel.

Test and adjust controls and safeties. Replace damaged or malfunctioning controls and

equipment.

Train the Client’s maintenance personnel on procedures and schedules related to start up and

shutdown, troubleshooting, servicing, and preventive maintenance.

Review data in operation and maintenance manuals with the Bank’s personnel.

The manufacturer shall make available to the Owner various levels of training ranging from

basic UPS operation to UPS maintenance.

140

3.17 Protection:

Contractor shall provide final protection and maintain conditions in a manner acceptable to the

Installer that shall ensure that the solid state UPS shall be without damage at time of Substantial

Completion.

Note: Critical loads mean power supply to VSAT System, CCTV Control Panel, Fire Alarm

Panel, Door Access Control Panel, Emergency Lighting Controls etc. as deem necessary

by the Client.

Note: In the case of decentralized parallel architecture, each module includes a CPU that is

fully autonomous. All CPUs are connected to one another via a communication bus. In

case of a CPU failure of a state of the art decentralized parallel architecture, only the

faulty module will be safely disconnected to the load, and the system will run normally

on the other modules.

Advantages:

• Higher level of availability than capacity configurations because of the extra capacity

that can be utilized if one of the UPS modules breaks down

• Lower probability of failure compared to isolated redundant because there are less

breakers and because modules are online all the time (no step loads)

• Expandable if the power requirement grows. It is possible to configure multiple units in

the same installation

• The hardware arrangement is conceptually simple, and cost effective

• Modules must be of the same design, same manufacturer, same rating, same technology

and configuration

141

3.18 Technical specifications:

GENERAL DATA DPA Triple

Maximum output power (frame) 10kVA

Number of UPS modules 2

Module type MX

Output power modules 10kVA

Output power factor 0.8

Topology True online double conversion

Parallel configuration 2 modules

UPS type Modular (DPA)

Cable entry Front access

INPUT

Nominal input voltage 2 × 400 / 230V + N, 2 × 415 / 240V + N

Voltage tolerance (Ref. to 2 × 400/230V) For loads < 100% (–23%, +15%), < 80% (–30%, +15%), < 60%

(–40%, +15%)

Input distortion THDi ≤ 3% at 100%

Frequency 35–70Hz

Power factor 0.99

OUTPUT

Rated output voltage 2 × 400 / 230 V + N, 2 × 415 / 240 V + N

Voltage distortion (Ref. to 2 × 400/230 V) < 2 %

Frequency 50Hz

Overload capability 10 min.: up to 125 % or 1 min.: up to 150 %

Unbalanced load 100 % possible

Crest factor 3 : 1

EFFICIENCY

Overall efficiency Up to 96 %

In eco-mode configuration 98 %

ENVIRONMENT

Storage temperature –25 – +70 °C

Operating temperature 0–40 °C

Altitude 1000 m without de-rating

BATTERY

Battery capacity Configurable up to several hours

Internal batteries Yes

No. of internal batteries Up to 240

COMMUNICATIONS

LCD display Yes (per module)

LEDs LED for notification and alarm

Communication ports USB, RS-232, SNMP slot, potential-free contacts

STANDARDS

Safety IEC / EN 62040-1-1, IEC / EN 60950-1

Electromagnetic compatibility (EMC) IEC / EN 61000-6-4 (IEC / EN 62040-2 limit A [C2 UPS])

IEC / EN 61000-6-2 (IEC / EN 62040-2 criterion A [C2 UPS])

IEC / EN 61000-4-2, IEC / EN 61000-4-3, IEC / EN 61000-4-4,

IEC/EN 61000-4-5, IEC / EN 61000-4-6

Performance IEC / EN 62040-3

Product certification CE

IP rating IP 20

142

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

200kVA GROUND-MOUNTED POWER TRANSFORMER FOR OFFICE BUILDING AT REGENT

ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

143

200kVA GROUND-MOUNTED POWER TRANSFORMER (ANSI/IEC STANDARDS)

1.0 General:

The proposed 200kVA Ground-mounted power transformers shall be used to step down three-

phase utility (EDSA) high voltage to low voltage for energy distribution for the Office Building

at Regent Road, Hill Station, Freetown for Sierra Leone Field Office at the African

Development Bank (ADB).

The standard version shall be three-phase hermetically sealed, free breathing with/without

conservator type that can be installed both outdoor and indoor with flexible corrugated tank

walls or radiators to enable sufficient cooling of the transformer and compensate for changes in

the oil volume due to temperature variations during operation.

2.0 Product scope

(i) Rated power: 200kVA

(ii) Rated voltage: 11kV

(iii) Cooling type: ONAN

(v) Available fluids: mineral oil and ester fluids (natural and synthetic)

3.0 Standard features

Hermetically sealed construction:

– Corrugated tank

– Medium voltage and low voltage porcelain bushings

– Off-circuit tap changer

– Oil drain valve

– Oil filling plug on the cover

– Lifting lugs

– Earthing terminals

– Rating plate

– Mineral oil

4.0 Construction with conservator:

– Magnetic oil level indicator

– Buchholz relay

– Oil filling plug on the conservator

– Dehydrating breather

5.0 Construction with air cushion for 3-phase unit.

The proposed Ground-mounted distribution transformers shall be manufactured to provide a

high quality and reliable transformer to the end user

6.0 The key production features shall include:

– Oval core

– Step lap

– Automatic cutting and stacking of core legs

– Windings directly wound on the core legs or mandrels with 2 HV coils in parallel (smallest

units)

– Epoxy diamond dotted paper insulation between LV layers

– Tapered or full width layer insulation in HV windings

7.0 Core The magnetic circuit shall be of column type with mitred joints and manufactured with first

rate, grain oriented magnetic cold-rolled silicon steel lamination or amorphous steel. The

mounted core shall be clamped down to reduce vibrations and minimize noise level.

144

8.0 Windings

The windings shall be made of two components, conductor and the insulation materials. The

conductors used shall be a high grade electrolytic copper or aluminium and insulated with pure

cellulose or double enamel. The MV windings shall be wound either with round, double enamel

insulated or rectangular, paper insulated wire. The LV windings shall be wound with

rectangular, paper insulated wire, enamelled wire or foil.

9.0 Off-circuit tap changer

The tappings of the MV windings shall be connected to the off-circuit tap changer and the

handle located on the cover and should only be operated when the transformer is de-energized.

The mechanism shall be pad-locked during normal operation.

10.0 Insulating liquids

The mineral oil – both inhibited and uninhibited types – with its electrical and chemical

characteristics shall be in compliance with IEC standards and PCB and PCT free.

11.0 Tank and cover

That Tank walls shall be made of corrugated cooling surfaces and the welds are tested for oil

tightness. The complete tank shall be tested and approved acc. to Cenelec HD 428.6 S1 standard.

12. Painting and surface treatment

All metal parts shall be carefully sand-blasted and painted for use in heavy corrosion areas.

145

TECHNICAL SPECIFICATION - 200kVA POWER TRANSFORMER

Characteristic:

Product Name: Liquid-Filled Groundmount Transformer, 3PH

200kVA, HV 11000D, LV 415yn

Country of origin:

Rated Power: [kVA] 200

Insulation Liquid Mineral Oil

High voltage [V] 1100

High voltage tappings (OFF LOAD) +2 -2 2.5%

Low voltage at no load [V] 415

High voltage insulation level [kV] L1 75 / AC 28 / Um 12

Low voltage insulation level [kV] L1 - / AC 3 / Um 1.1

Frequency [Hz] 50

Number of phases 3

Vector group Dyn11

Ambient temperature

max./monthly/annual average 0C

50 / 40 / 30

Max. average temperature rise

(Oil/Winding) [C/C]

50 /55

Surface treatment Painted, RAL 7033

Altitude (a.s.l) [m] <1000

Location Indoor/Outdoor

Performance values:

Standards IEC 60076

Impedance [%] 4(+-10%)

No load losses [W] 450(+15%)

Load losses at 750C [W] 2510(+15%)

Preliminary dimensions and weight:

Length [mm] 1300

Width [mm] 950

Height [mm] 1150

Roller distance (c/c) [mm] x

Oil Weight [kg] 160

Total weight [kg] 800

Type of design:

Tank construction Corrugation, Hermetically sealed

Cooling ONAN

High voltage winding conductor material Cu

High voltage winding conductor material Cu

Standard Features/Accessories:

Off-circuit tap changer (with 5 positions)

DIN type porcelain HV and LV bushings on tank cover

Air insulated standard cable box on HV and LV bushings

Dial type contact thermometer

Pressure relief valve (without contact)

Lifting lugs and Earthing terminals on tank

146

MECHANICAL ENGINEERING SERVICE INSTALLATION

147

SPECIFICATION FOR THE SUPPLY, INSYALLATION, TESTING AND COMMISSIONING OF

CONFORT COOLING VRV / VRF AND SINGLE SPLIT WALL MOUNTED AIR-CONDITIONING

UNITS AND CONTROL SYSTEM INSTALLATION FOR OFFICE BUILDING AT REGENT ROAD,

HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

148

PERFORMANCE SPECIFICATION THE SUPPLY, INSTALLATION, TESTING AND

COMMISSIONING OF CONFORT COOLING AIR-CONDITIONING AND CONTROL SYSTEM

FOR THE OFFICE BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA

LEONE FIELD OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB)

A. SCOPE AND GENERAL REQUIREMENTS

1 SCOPE OF SPECIFICATION 1.1 Installation to Comply with this Specification

1.2 Scope of the Work

2. STATUTORY OBLIGATIONS AND OTHER REGULATIONS

2.1 Statutory Obligations and Other Requirements

2.2 Case of Conflict

3 EXECUTION OF WORKS

3.1 International System of Units (SI)

3.2 Programme of Works

3.3 Builder’s Work

3.4 Coordination of Contract Works

3.5 Cooperation with Other Contractors

3.6 Site Supervision

3.7 Advice of Order Placed

3.8 Record of Materials Delivery

3.9 Protection of Materials and Equipment

3.10 Service Condition

3.11 Voltage Covered by this Specification

3.12 Labels and Related Instruction

3.13 Materials and Equipment

3.14 Workmanship

3.15 Surveys and Measurements

3.16 Submission of Testing and Commissioning Procedure

A4 DRAWINGS AND MANUALS

4.1 Standard Drawings

4.2 Drawings in Electronic Format

4.3 Installation Drawings

4.4 As-built Drawings

4.5 Operation and Maintenance (O&M) Manual and User Manual

B GENERAL TECHNICAL REQUIREMENTS (INSTALLATION METHODOLOGY)

1 AIR CLEANING EQUIPMENT

1.1 General

1.2 Washable Panel Filter

2 AIR HANDLING AND TREATMENT

2.1 General

2.2 Fan Coil Units

2.3 Cassette Type Fan Coil Units

3 CONTROL

3.1 Control System (CS)

149

4 ELECTRIC MOTORS AND ELECTRICAL EQUIPMENT

4.1 Low Voltage - General

4.2 Low Voltage - Electric Motors

4.3 Low Voltage - Motor Switchgear, Starter and Control Panel

5 REFRIGERATION MACHINE

5.1 General

5.2 Positioning and Isolation/Removal of Equipment

5.3 Delivery of Equipment

5.4 Refrigeration Pipework and Fittings

5.5 Air-Cooled Condenser

5.6 Vibration Isolation

5.6 Electrical Work

6 PIPEWORK

6.1 General

6.2 Air Venting

6.3 Changes in Pipe Size

6.4 Connections in Pipework

6.5 Joints and Fittings for Copper Tubes

6.6 Pipework General Details

6.7 Pipework Layout

6.8 Plastic Pipework

6.9 Supports for Pipework

6.10 Brazing

7 NOISE AND VIBRATION CONTROL

7.1 General

7.2 Equipment Bases

7.3 Vibration Isolators

7.4 Plant/Equipment Vibration Isolation

7.5 Pipework Vibration Isolation

7.6 Inspection

8 UNITARY AIR-CONDITIONER

8.1 General

8.2 Installation and Servicing

8.3 Anti-Vibration Mounting

8.4 Casing

8.5 Compressor

8.6 Supply Air Fan and Motor

8.7 Cooling and Heating Coils

8.8 Air Filter

8.9 Air-cooled Condensers

8.10 Refrigerant Piping

8.11 Condensate Drain Pipe

8.12 Minimum Installation Requirements of Safety and Operational Control for Unitary Air Conditioners

8.13 Split Condensing Unit and AHU

8.14 Variable Refrigerant Volume System

8.15 Maintenance Servicing Platform

150

C GENERAL TECHNICAL REQUIREMENTS (MATERIAL AND EQUIPMENT

SPECIFICATION)

1 AIR CLEANING EQUIPMENT

1.1 General

1.2 Standards

1.3 Washable Panel Filter

1.4 Additional Requirements (Spare Filter Media)

2. FAN COIL UNIT (FCU) AND TREATMENT EQUIPMENT

2.1 General

2.2 Cassette Type Fan Coil Unit

2.3 Energy Efficiency and Performance

3 REFRIGERATION MACHINE

3.1 General

3.2 Compressor-Rotary Type

3.3 Condenser-Air Cool

3.4 Refrigerant Pipework

4. CONTROL

4.1 Electrical Wiring

4.2 Air Cooler Control

4.3 Electrical/Electronic (Localized) Control System

4.4 Standalone Direct Digital Controllers/Outstation (DDC/O)

4.5 Digital Temperature Display

4 CENTRAL REFRIGERATION MACHINE, DIRECT EXPANSION EVAPORATOR AND

HEAT REJECTION PLANT

4.1 General

4.2 Absorption Units

4.3 Cold Storage Refrigeration

4.4 Compressors, Reciprocating Type

4.5 Compressors, Centrifugal Type

4.6 Compressors, Screw Type

4.7 Compressors, Scroll Type

4.8 Condensers, Shell and Tube-General Requirement

4.9 Condensers, Air-Cooled

4.10 Condensers, Evaporative

4.11 Evaporators, Air Cooling

4.12 Liquid Receivers

4.13 Pressure Testing

4.14 Pump Down of System

4.15 Refrigerant Pipework

4.16 Energy Efficiency Performance

5 ELECTRIC MOTORS AND ELECTRICAL EQUIPMENT

5.1 Low Voltage - General

5.2 Low Voltage - Wiring for Refrigerated Situations

5.3 Low Voltage - Electric Equipment

151

6 NOISE AND VIBRATION CONTROL

6.1 General

6.2 Equipment Bases

7 PIPE MATERIAL

7.1 Pipework Applications

8 THERMAL INSULATION

8.1 General

8.2 Types of Thermal Insulation Materials

8.3 Measure to Prevent Smoke, Noxious & Toxic Fumes Propagation in Event of Fire

8.4 Vapour Barriers

8.5 Insulation Thickness

9 UNITARY AIR-CONDITIONER

9.1 General

9.2 Equipment Suitable for Local Electricity Supply

9.3 Selection of Air-cooled Condensers and Condensing Units

9.4 Casing

9.5 Compressor

9.6 Supply Air Fan and Motor

9.7 Cooling and Heating Coils

9.8 Air Filter

9.9 Air-cooled Condensers

9.10 Refrigerant Piping

9.11 Condensate Drain Pipe

9.12 Safety Control

9.13 Operational Control

9.14 Split Condensing Unit and AHU

9.15 Variable Refrigerant Volume System

9.16 Energy Efficiency Performance

D. INSPECTION, TESTING AND COMMISSIONING 1.1 General

1.2 Testing and Commissioning – Definitions

1.3 Testing and Commissioning – General

1.4 Off-Site Tests

1.5 Site Tests

1.6 Inspection and Testing during Construction Period

1.7 Documents and Data required for Hand-over Meeting

1.8 Testing and Commissioning Procedures

E. OPERATION AND MAINTENANCE

I.1 General

I.2 Level One Services - Mandatory Responsibilities during Maintenance Period

I.2.1 Requirement for Training

I.2.2 Requirement during Maintenance Period

I.3 Level Two Services - Specified Contractor’s Maintenance Responsibilities during Maintenance Period

I.3.1 The Contractor shall be fully responsible for the following within the Maintenance Period

I.3.2 The Contractor shall provide Labour, Minor Spare Parts, Components and Consumable Materials in

the following Services during the Maintenance Period

I.3.3 Contractor’s Responsibilities for Breakdown Call-Out

I.3.4 Maintenance Programme and Schedule

I.3.5 Co-ordination

152

I.3.6 Plant Log and Breakdown/Fault Call Report

I.3.7 Monthly Works

I.3.8 Half-Yearly Works

I.3.9 Annual Works

EI.4 Spare Parts and Special Tools

F. TYPICAL VRV SYSTEM INSTALLATION LAYOUT

G. SCHEDULE OF PROPOSED CONFORT COOLING VRV IN CEILING MOUNTED AND

SINGLE SPLIT WALL MOUNTED AIR-CONDITIONING UNITS

153

1 SCOPE OF SPECIFICATION

1.1 INSTALLATION TO COMPLY WITH THIS SPECIFICATION

The air-conditioning and control system installation shall comply with this Specification which details

the intrinsic properties (including materials and workmanship) of the installation in so far as it is not

overridden by the Conditions of Contract, Special Conditions of Contract, and Particular Specification

for the Works, Drawings and/or written instructions of the Project Architect.

1.2 SCOPE OF THE WORKS

This Specification, Particular Specification, Tender Equipment Schedule and Drawings detail the

performance requirements of the Works. The Works to be carried out in accordance with this

Specification shall include the installation and supply of all materials necessary to form a complete

installation including any necessary tests, adjustments, commissioning and maintenance as prescribed

and all other incidental sundry components together with the necessary labour for installing such

components, for the proper operation of the installation.

2 STATUTORY OBLIGATIONS AND OTHER REGULATIONS

2.1 STATUTORY OBLIGATIONS AND OTHER REQUIREMENTS

The Air-Conditioning and Control System installation shall comply with the followings:-

2.1.1 Statutory Obligations

a) Building (Ventilating System) Regulation under Buildings legislations - Sierra Leone);

(b) Electricity legislation made under the EDSA Codes;

(c) Fire Service (Installations and Equipment) Regulations, Fire Services legislations;

(d) Noise Control legislation - Sierra Leone;

(e) Air Pollution legislations – Sierra Leone;

(f) Ozone Layer Protection, and other subsidiary legislation – Sierra Leone;

(g) Environmental Impact Assessment legislations – Sierra Leone;

(h) Places of work Public Law of Sierra Leone and other subsidiary legislations

2.1.2 Other Requirements

(a) Code of Practice for the Electricity (Wiring) Regulations published by Electrical Distribution and

Services Authority (EDSA) and Mechanical Services Department, Ministry of Works,

Government of Sierra Leone;

(b) Code of Practice for Energy Efficiency of Electrical Services Installations and Air Conditioning

Services Installations issued by Electrical & Mechanical Services Department, Government of

Sierra Leone;

(c) Codes of Practice issued by the following international institutions:-

- American National Standard Institute

- Air-conditioning and Refrigeration Institute

- American Society of Mechanical Engineers

- American Society of Testing and Materials

- The Institute of Electrical and Electronic Engineers

- International Organization for Standardization

- National Fire Protection Association

- Codes of Practice on Prevention of Legionnaires’ disease;

(d) Technical Memorandum to issue Air Pollution Abatement Notice to control Air Pollution from

Stationary Processes and the Assessment of Noise from Places other than Domestic Premises and

Public Places;

(e) Technical Memorandum on Environmental Impact Assessment Process.

154

2.1.3 Safety Requirements

(a) Occupational Safety and Health Ordinance and others made under the Ordinance;

(b) Construction Site (Safety) Regulations

2.1.4 Technical Standards

BS, BS EN, ISO Standards, IEC Standards and Codes of Practice, etc. shall be deemed to include all

amendments, revisions and standards superseding the standards listed herein, which are current at the

closing date of the tender of the Contract unless otherwise specified.

2.2 CASE OF CONFLICT

The documents forming the Contract are to be taken as mutually explanatory of one another but in case

of ambiguities or discrepancies the same shall be explained by the Project Architect who shall issue to

the Contractor instructions clarifying such ambiguities or discrepancies.

3 EXECUTION OF WORKS:

3.1 INTERNATIONAL SYSTEM OF UNITS (SI)

The International System of Units (System International Unites) of weights and measures shall be used

for all materials, equipment and measurements.

3.2 PROGRAMME OF WORKS

The Contractor shall submit to the Project Architect a detailed programme of the Works within

4 weeks from the acceptance of his tender showing the intended method, stages and order of work

execution in coordination with the building construction programme, together with the duration he

estimated for each and every stage of the Works. The programme shall include at least the following:-

(a) Dates for the placement of orders for equipment and materials;

(b) Expected completion dates for builder’s work requirements, i.e. when work site needs to be ready;

(c) Delivery dates of equipment and materials to Site;

(d) Dates of commencement and completion of every stage of the Works in line with the building

construction programme, i.e. each floor level and/or zone area;

(e) Dates of documents/drawings submissions to Project Architect to obtain the necessary approvals;

(f) Dates of requirement of temporary facilities necessary for testing & commissioning, e.g. electricity

supply and town gas;

(g) Dates of completion, testing and commissioning; and

(h) Short term programme showing the detailed work schedules of coming weeks and months shall

also be provided to the Project Architect. Programme shall be regularly updated to reflect the actual

progress and to meet the Contractors’ obligations under the Contract.

In addition, detailed submission schedules for installation drawings, equipment and testing and

commissioning shall be submitted to the Architect for approval.

The formats and information to be included in the schedules shall be as required by the Project

Architect.

3.3 BUILDER’S WORK

All builder’s work including openings or holes through building structure or partition walls; trenches,

ducts and cutting; and all plinths, concrete bases, supports, ducts, etc. required for the installation will

be carried out as part of the building works by the building contractor at the expense of the Employer

provided that the Contractor has submitted full details of such requirements within a reasonable time

to the Project Architect for approval, so that due consideration may be given before the building

contractor commences the building works in accordance with the building programme in the areas

concerned. After obtaining the said approval of the Project Architect, the Contractor is required to mark

out at the relevant locations of the Site the exact positions and sizes of all such works and to provide

detailed information of such works to the building contractor to facilitate him to carry out the builder’s

works as the works proceed.

155

All "cutting-away" and "making-good" as required to facilitate the Contractor’s works will be carried

out by the building contractor, except for minor provisions required for the fixing of screws, raw plugs,

redhead bolts, etc. which shall be carried out by the Contractor. The Contractor shall mark out on Site

and/or supply drawings of all "cutting-away" to the building contractor within a reasonable time.

All expenses properly incurred and losses suffered by the Employer as a result of the Contractor’s

failure to comply with the above requirements are recoverable by the Employer from the Contractor.

The Contractor shall ensure that such works are essential for the execution of the Works. In the event

that any of such works is proved to be non-essential, unnecessary and/or abortive, the Contractor shall

bear the full cost of such works including but not limited to any unnecessary or incorrect cutting-away

and making-good and shall reimburse the Employer for all cost incurred in this connection.

Upon completion of the builder’s works by the building contractor, the Contractor shall forthwith check

and examine that all builder’s works so executed have been completed in accordance with his

requirements. If at any time it becomes apparent to the Contractor that any builder’s works completed

by the building contractor does not comply with his requirements in any respect whatsoever, the

Contractor shall forthwith give notice in writing to the Project Architect and specify in details the

extents and effects of such non-compliance in that notice. The Contractor is deemed to have satisfied

with the builder’s works after a period of 7 days from the date of completion of the builder’s works if

the above notice is not served to the Project Architect within such period. All additional expenditure

properly incurred and all loss suffered in this connection by the Employer in having such works re-

executed and rectified shall be recoverable by the Employer from the Contractor.

3.4 COORDINATION OF CONTRACT WORKS

The Contractor shall coordinate the Works with those works of the building contractor and any other

contractors and sub-contractors.

The Contractor shall note that the Drawings supplied to him only indicate the approximate locations of

the works. He shall make any modification reasonably required of his programme, work sequence and

physical deployment of his work to suit the outcome of work coordination or as necessary and ensure

that all cleaning, adjustment, test and control points are readily accessible while keeping the number of

loops, cross-overs and the like to a minimum.

The Contractor shall pay particular attention to the building works programme and shall plan,

coordinate and programme his works to suit and adhere to the building works in accordance with the

building programme.

Any significant problems encountered during the coordination work, which are beyond the Contractor’s

control, shall promptly be reported to the Architect.

3.5 COOPERATION WITH OTHER CONTRACTORS

The Contractor shall cooperate at all times with the building contractor and all other contractors and

sub-contractors in order to achieve efficient workflow on Site.

Any significant problems beyond the Contractor’s control shall promptly be reported to the Project

Architect.

156

3.6 SITE SUPERVISION

The Contractor shall keep on the Site a competent and technically qualified site supervisor to control,

supervise and manage all his Works on Site. The supervisor shall be vested with suitable powers to

receive instructions from the Project Architect.

The site supervisor shall be technically competent and have adequate site experience for the Works.

The qualified and competent Supervisor shall have minimum 5 years on site experience for similar type

of installation works. The Contractor shall also refer to the Particular Specification for other specific

requirements, if any, on site supervision.

Approval by the Project Architect shall be obtained prior to the posting of the supervisor on Site. The

Contractor shall immediately replace the Site supervisor whose experience, skill or competency is, in

the opinion of the Project Architect/M&E Engineer, found to be inadequate for the particular work.

All tradesmen must be experienced in the trade and the work carried out shall be consistent with good

practice in Sierra Leone and to the satisfaction of the Project Architect.

The Contractor shall also employ a full time competent foreman on site for each trade. All trade foremen

shall be registered tradesmen of the relevant trade.

3.7 ADVICE OF ORDER PLACED

The Contractor shall submit copies of all orders placed for major items of equipment and materials to

the Project Architect for record.

3.8 RECORD OF MATERIALS DELIVERY

All materials and equipment delivered to Site shall be accurately listed and recorded in the site record

books maintained by the representatives of the Project Architect on Site.

Materials and equipment delivered to Site and paid for in interim payment shall be the Employer’s

property. Such materials and equipment shall not be removed from Site without the approval of the

Project Architect in writing and appropriate deduction shall be made in the next interim payment in

accordance with the Contract.

Where the building contractor is in overall control of the Site, the building contractor may also be

required to record details of all incoming/outgoing materials. In this case, the Contractor shall comply

with the building contractor’s arrangements.

3.9 PROTECTION OF MATERIALS AND EQUIPMENT

Unless the responsibility is clearly defined in the Contract that the protection on Site for delivered

equipment, materials and installation is solely by other contractors, the Contractor shall be responsible

for the safe custody of all materials and equipment as stored or installed by him until finally inspected,

tested and accepted. In addition, the Contractor shall protect all work against theft, fire, damage or

inclement weather and carefully store all materials and equipment received on Site but not yet installed

in a safe and secure place unless otherwise specified.

All cases of theft and fire must immediately be reported to the police, the building contractor, the

Project Architect and the representatives on Site with full details.

Where necessary the Contractor shall provide lockable steel container or other equally secure

enclosures placed within a securely fenced-in compound provided by the Building Contractor on Site

for the storage of materials and equipment.

157

The Contractor shall co-ordinate and arrange with the Building Contractor who shall provide clean,

reasonably finished and lockable secure accommodation for the storage of sensitive and/or expensive

items before installation.

If there is no Building Contractor, all the storage facilities and spaces shall be provided by the

Contractor.

3.10 SERVICE CONDITION

The following service conditions shall apply to materials and equipment’s:

Building Location

Freetown, Sierra Leone

08030’N, 13014’W, Altitude 11m

Design Criteria

1. External Environmental Conditions

High temperatures, high humidity, saline atmosphere, presence of airborne dust particles during

Harmattan, periods of high precipitation

2. External Ambient Design Conditions

330 C db. 270C wb. Average max/min daytime temperatures 300C.db / 240C.wb (Diurnal Range

60C)

References: CIGSE Design Guide

BBC Weather Data, based on readings at location for 14 years

3. Internal Environmental Design Conditions

Refer Schedules 1-3 for internal temperatures, occupancy levels and fresh air requirements.

4. Internal Noise Criteria

5. IEE Wiring Regulations

6. CIBSE Commissioning Codes

3.11 VOLTAGE COVERED BY THIS SPECIFICATION

Unless otherwise specified, all apparatus, equipment, materials and wiring shall be suitable for use with

a 3-phase and neutral, 4-wire, 400/230 V ±6%, 50 Hz ±2%.

3.12 LABELS AND RELATED INSTRUCTION

3.12.1 Labels and Related Instruction

In order to make cross reference to the Operation/Maintenance/Service Manuals and Schematic

Drawings, etc., the Contractor shall provide labels for marking all pipework, switches and other

equipment, etc. and elsewhere to facilitate maintenance or as directed by the Project Architect/M&E

Engineer with engraved multi-layer formica or similar material. Wording shall be submitted to the

Project Architect for approval before manufacture.

All labels shall be of adequate size as to give clearance between lettering and fixings to ensure an

aesthetic arrangement on completion.

All English lettering used on labels shall be "Bold" capitals (except otherwise directed) with black

letters on white labels for normal purposes. Where special colours or details are required these shall

be as specified or directed.

3.12.2 Manufacturers’ Technical Support in Sierra Leone

All equipment listed in the Equipment Schedule shall be supplied through authorised agencies of the

manufacturers in Sierra Leone or through the Sierra Leone office of the manufacturers.

158

These local agencies or offices shall have adequate technical staff to provide presale and after-sale

services to the Contractor. Unless otherwise specified in this Specification, equipment’s supplied

directly by the manufacturers which do not have local agent or office in Sierra Leone will not be

accepted. Spare parts should also be available in the local market easily.

3.12.3 Guard for Rotating Parts of Equipment

All rotating parts of equipment shall be provided with an approved guard complying with the

Factories & Industrial Undertakings (Guarding an Operation of Machinery) Regulations, published

by the Labour Department, Ministry of Works together with any amendments made thereto.

Guards shall be rigid and of substantial construction and shall consist of heavy mild steel angle

frames, hinged and latched with either heavy galvanized mild steel wire crimped mesh securely

fastened to frames or galvanized sheet metal of 1.2 mm minimum thickness.

All apertures shall be such that finger access to dangerous part is not possible. All sections shall be

bolted or riveted.

(a) Temporary Guards

During the execution of work, the Contractor shall ensure that all moving parts are adequately

guarded by temporary guards.

Adequate temporary guard railings etc. around dangerous floor/wall openings in the vicinity of

any work for the protection shall be provided.

For the safety of workers, guard railings etc. are to be provided by the building contractor, but

in case they are not provided, the Contractor shall immediately report the matter to the Project

Architect.

(b) Permanent Guards on Plant

Unless specified otherwise in the Particular Specification, the Contractor shall provide removable

guards or railing for protection from moving or rotating parts. The design and construction of

safety guards for moving parts such as belt drives shall conform to the requirements laid down in

the Factories & Industrial Undertakings (Guarding an Operation of Machinery) Regulations.

3.13 MATERIAL AND EQUIPMENT

3.13.1 Material and Equipment Standards

All materials, equipment and installation work shall be carried out by adoption of the best available

quality materials and workmanship and shall, where applicable, comply with the latest edition of the

appropriate standards and/or codes of practice issued by the relevant international Institutes and

Standards and as specified in this Specification. This requirement shall be deemed to include all

amendments to these standards and codes up to the date of tendering.

3.13.2 Compatibility of Materials and Equipment

Where different components of equipment are interconnected to form a complete system, their

characteristics of performance and capacities shall be matched in order to ensure efficient,

economical, safe and sound operation of the complete system.

3.13.3 Equipment Catalogues and Manufacturer’s Specifications

Equipment catalogue and manufacturer's specification related to proposed items of equipment shall

be specific and shall include all information necessary for the Project Architect to ascertain that the

equipment complies with this Specification and/or the Particular Specification and Drawings. Data

and sales catalogue of a general nature are not acceptable. Unless agreed to by the Project Architect

in writing, all data and catalogues submitted must be in English and in pure SI units i.e. mm, m, kPa,

m/s, Hz, kW, l/s, etc.

159

Contractor shall submit catalogues and manufacturer's specification of the proposed equipment for

the examination and approval of the Project Architect in writing before any equipment is ordered.

3.13.4 Equipment Deviations

Subsequent to the award of the Contract, and only in exceptional circumstances where it is

demonstrated in writing by the Contractor that the original equipment offered cannot be obtained, the

Project Architect may consider and accept, in writing, alternative equipment and materials proposed

by the Contractor provided always that these are fully in compliance with the relevant Specifications

and Drawings and do not impose any additional contractual or financial liabilities onto the Employer.

The Contractor shall bear in mind that submission of alternatives usually causes delay because of

additional time required by the Project Architect to process further approval. The consequences of

such delay shall be borne by the Contractor.

Subject as always to the Project Architect's approval, where the Contractor proposes to use items of

equipment other than those specified and dimensionally different from the Contract Drawings, the

installation of which items requires any redesign of the structure, partitions, foundations, piping,

wiring or any other part of the mechanical, electrical or architectural layout, then drawings showing

the layout of the proposed equipment and any redesign involved shall be prepared by the Contractor

at the Contractor’s own expenses and be submitted to the Project Architect for approval.

Where the equipment deviation involves significant changes to the building, e.g. a larger equipment,

this will unlikely be agreed unless the enlargement presents no significant problem and the Contractor

is prepared to pay for the building alterations involved.

Where such approved deviation necessitates a different quantity and arrangement of ductwork,

piping, structural supports, insulation, controls, motors, starters, electrical wiring and conduits, and

any other additional materials together with all necessary accessories from that originally specified

or indicated in the Contract Drawings, the Contractor shall supply and install such ductwork, piping,

structural supports, insulation, controls, motors, starters, electrical wiring and conduits, and any other

additional materials together with all necessary accessories required by the system at no additional

cost to the Employer. The Contractor shall also be responsible for all other expenses by other

contractors in view of the change. Any deduction of cost due to the change shall be deducted from

the contract.

The responsibility and detailed arrangement for abortive work and cost different for alternative

equipment and material shall be in accordance with the Preliminaries of the Contract.

3.13.5 Selection of Equipment

Selection of equipment shall be based on this Specification, the Particular Specification, and the

technical data contained in the Drawings for this particular installation.

Where items of equipment are interconnected to form an integral part of the complete air conditioning

installation, their characteristics of performance and capacities shall be so matched as to give safe,

reliable, efficient and economical operation of the complete air conditioning installation.

3.14 WORKMANSHIP

3.14.1 Safety on Site

Work shall be carried out in such a manner as to comply with all the regulations, standards, etc., as

listed in the ‘’Safety Requirements’’ of this Specification together with any amendments made

thereto.

160

3.14.2 Tools and Instruments

Proper tools shall be used for the works. Adequate and accurate testing/measuring instruments shall

be used to demonstrate compliance of the installations with the relevant specifications and

regulations. The Project Architect has the right to stop any work in which the correct tools and/or

instruments are not used.

Instruments used for acceptance tests shall be calibrated at an interval time of one year unless

otherwise as required in the Contract for this particular project.

3.14.3 Workmanship Standard

The installation works shall be in line with the good practice accepted by the international/local

industry and verified by commissioning and testing results.

The installation works shall be in compliance with this Specification, Particular Specification and

drawings of the project.

The installation shall be in compliance with the statutory requirements as specified in this

Specification in respect of labour safety, fire safety, structural safety, electrical safety and

environmental protection.

Apart from those requirements as stipulated in this Specification and other statutory requirements,

due care shall be taken to secure public safety and health both during the execution of the works and

in the selection of equipment and materials for the Air Conditioning installation contract.

3.14.4 Warning Notice

Warning notices shall be provided as required by the Electricity Ordinance and the Code of Practice

for the Electricity (Wiring) Regulations. In addition, the following warning notices in English shall

be provided at the appropriate positions:-

(a) A label having minimum size of 65 x 50mm marked with the words ‘DANGER – HIGH

VOLTAGE’ in red lettering not less than 5mm high to be fixed on every container or enclosure

of equipment for operating at voltages exceeding "Low voltage"; and

(b) A label to be fixed in such a position that any person may gain access to any moving parts of

an item of equipment or enclosure will notice or be warned of such a danger.

3.14.5 Space for Equipment/Plant

The Contractor shall ensure that all equipment/plants, material and equipment supplied by him can

be accommodated and installed within the spaces as generally shown on the Contract Drawings with

adequate access and space for maintenance of all items supplied.

The Contractor shall also ensure that access to plant is adequate to allow for its removal and/or

ultimate replacement. Where this is considered not possible or necessary the Project Architect shall

be consulted for alternative arrangements.

3.14.6 Water Proofing

Where any work requires piercing waterproofing layers or structures, the method of installation must

have prior approval, in writing, from the Project Architect.

Unless otherwise specified or instructed, the Contractor shall provide all necessary sleeves, caulking

and flashing as appropriate to make these penetrations absolutely watertight.

3.14.7 Quality Assurance Standards

All materials and equipment shall be manufactured by factories with acceptable quality assurance

procedures. Factories having ISO 9001:2000 certification are deemed to have acceptable quality

assurance procedures. Other similar quality assurance standards may be accepted by the Project

Architect on their individual merits. Details of such other quality assurance standards shall be

submitted with the Equipment Schedule.

161

3.15 SURVEYS AND MEASUREMENTS

The Contractor shall relate all horizontal and vertical measurements taken and/or applied, to establish

bench marks such as design drawing grid lines, finished floor levels, etc. and shall thus establish

satisfactory lines and levels for all work.

All works shall be installed to these established lines and levels and the Contractor shall verify all

measurements on site and check the correctness thereof as related to the work.

Primary bench base line, datum level, horizontal reference grid, secondary grid and transferred bench

mark on each structural level will be provided by the building contractor. The Contractor shall co-

ordinate with the building contractor to obtain all necessary datum and reference grids prior to their

surveys and measurements.

3.16 SUBMISSION OF TESTING AND COMMISSIONING PROCEDURE

Upon completion of the installation but prior to acceptance, the Contractor shall submit to the Project

Architect in good time a schedule showing the appropriate testing and commissioning procedures to be

carried out. The schedule shall be agreed by the Project Architect/M&E Engineer before any testing

and commissioning work is carried out.

Detailed requirements for testing and commissioning shall be in accordance with the relevant Sections

of this Specification.

4.0 DRAWINGS AND MANUALS

4.1 STANDARD DRAWINGS

There are standard abbreviations, symbols and standard drawings prepared by the M&E Engineer to

show details of the common standard installations. The Contractor shall refer to these standards and

drawings whenever such are mentioned or specified in the Drawings or the Particular Specification.

The same standards shall also be used in the Contractor's "as-built" drawings, etc., whenever applicable.

4.2 DRAWINGS IN ELECTRONIC FORMAT

The Contractor shall provide drawings in electronic format as required in the following clauses. These

drawings shall conform to the latest version of CAD Standard of Works Projects (CSWP) and in

accordance with the latest version of CAD Manual for Architectural Services Department Projects.

Should any technical conflict between the CSWP and the CAD Manual arise, the CSWP shall take

precedence.

4.3 INSTALLATION DRAWINGS

4.3.1 Drawing Submission Schedule

The Contractor shall submit a detailed installation drawing and programme to the Project Architect.

The Contractor shall allow reasonable time in the programme for vetting of the installation drawings

by the Project M&E Engineer and for drawing resubmissions as necessary.

The Contractor shall submit to the Project Architect a comprehensive “Submission Schedule” of

installation drawings and builders work drawings within 2 weeks after the acceptance of ‘’Tender’’,

taking into account of the overall programme of the Works including any Specialist Works to be

undertakings. No equipment shall be delivered to the Site and no work shall be executed until the

installation drawings have been approved by the Project Architect.

The Contractor shall ensure that the installation drawings and builder’s work drawings are

progressively submitted in accordance with the approved “Submission Schedule”. The Contractor shall

provide at least 4 hard copies and one electronic copy, unless otherwise specified in the Contract, of

the approved installation drawings to the Project Architect for distribution.

Unless otherwise indicated or instructed, the Contractor shall, in the stated or in adequate time before

each section of the work proceeds, prepare, and submit for acceptance by the Project Architect/M&E

Engineer, detailed installation drawings and/or shop drawings (which may also be referred to as

162

working drawings) to demonstrate how they propose to install the works both in ‘Detail’ and ‘Form’ to

facilitate the practical installation. These drawings shall be fully dimensioned and shall be based on the

basic intentions of the ‘Contract Drawings’ but shall not be simply a copy of them.

Installation drawings and shop drawings in this context shall mean the drawings of items to be

constructed by the Contractor at a workshop away from the site

4.3.2 Size of Installation Drawings

Drawings submitted by the Contractor shall only be of standard sizes A3 as stipulated in ISO 5457:1999

and for this Particular Project.

Contractor’s ‘Installation Drawings’ and/or ‘Shop Drawings’ shall be prepared to such scales that will

clearly show all necessary details.

The drawings shall be prepared to the same sheet sizes and scales as to be used for the ultimate ’As-

Installed’ record drawings.

4.3.3 Contents of Installation Drawings

In accordance with the provisions of this Specification and as stated elsewhere in the Contract

Documents, the installation drawings must incorporate details of the actual plant and equipment items

as approved by the Project Architect.

The Contractor shall ensure all installation drawings are accurate representation of the Works, before

submitting them to the Project Architect.

All installation drawings shall be fully dimensioned and suitably scaled showing construction, sizes,

weights, arrangements, operating clearances and performance characteristics.

(a) "Installation Drawings" shall generally include, but not limited to, the following:-

- Symbols and notations same as and compatible with the Employer’s own Contract Drawing

standard;

- Complete layout/assemblies including all necessary minor items and accessories;

- Positions of all fixings, hangers and supports;

- Maintenance spaces for all withdrawable items, such as coils and fan blowers, cleaning and

replacement of tubes, removal of guards, etc.

- Positions & sizes of all test holes, bends and fittings, clearances to allow for the removal of

inserted equipment where applicable;

- Lifting points and safe working weights of each item.

Note: These may be shown on separate drawings, if necessary, to avoid confusion.

(b) Fan Coil Unit (FCU) Installation Drawings

All Fan Coil Unit (FCU) installation drawings shall include details of all equipment to be

installed therein including Wall Mounted and In-Ceiling Units with withdrawal clearances;

cleaning spaces for coils; filter; detail of hinges with manufacturers type and numbers for

proprietary items; details of drains, drain traps, cleanouts, and as well as provisions made and

the necessary clearance spaces for in-situ servicing or removal.

These drawings shall also show, in outline form only, any significant adjacent building structure

and the clearances from and other equipment and/or known services no matter whether these

elements are provided by the Contractor or others. All such known positions and/or clearances

shall be dimensioned wherever possible.

163

(c) Pipework Installation Drawings

Prior to the commencement of any installation, the Contractor shall submit to the Project

Architect for technical appraisal installation drawings for the pipework installation. Generally,

the drawings shall be drawn to a scale of not less than 1:50. Subject to the Architect’s approval

a scale of 1:100 may be adopted where the installation is a simple one.

The drawings shall indicate the location, with dimensions given of all pipework in relation to

the building structure and other pipework and equipment, etc.

Details and outline of insulation shall be shown including clearances and all hangers and

supports shall be shown and the positions dimensioned.

.

(e) Control and Wiring Installation Drawings

The Contractor shall prepare and submit schematic diagrams showing the control layout with

each item clearly identified with all interlocking and related facilities.

These drawings shall include wiring diagrams showing full details including terminal and wire

numbers, colour code, etc. for all items of electrical/electronic equipment.

Installation Drawings shall also be prepared and submitted for all physical wiring and piping

systems detailing positions, fixings, support, protection, sizes and number of cores/pipes for all

runs.

The Installation Drawings shall show positions in relation to the building structure and other

plant, equipment and/or installations. In the context, the equipment and/or installations will

mean to include the Contractor’s own installed services and those installed by others. For those

services installed by others, the Contractor shall be responsible for obtaining sufficient details

of relevant information from them in order to complete the drawings.

(f) Switchgear, Starter, Control/Instrumentation/Motor Control Installation Drawings

Shop/Installation Drawings shall show the physical construction and layout, internally and

externally, of all panels/cabinets/cubicles including the physical arrangement of all major and

important components, bus-bars, phase separation barriers, interconnecting wiring, piping,

labels, etc.

Wiring diagrams and schematic diagrams shall show all internal & external wiring/piping

including all interlocks and connections from the panels to external equipment.

Operation and control philosophy shall also be included in the submission. The drawings shall

include proposed full wording of all labels to be installed in English.

4.3.4 Builder’s Work Drawings

Unless otherwise approved by the Project Architect, the Contractor shall submit to the Project Architect

in accordance with the approved “Submission Schedule”, 4 copies of drawings showing details of all

builders’ work required e.g. the weight and the load on each support of equipment.

Such drawings shall clearly indicate the details and positions of all openings, trenches, ducts, drain and

cutting required and construction details for plinths and equipment bases.

4.3.5 Manufacturer’s Shop Drawings

The manufacturer’s shop drawings are drawings for equipment to be manufactured by a specialist

manufacturing supplier in their own workshops and places away from the Site.

164

The drawings shall show detailed construction, principal dimensions, weights and clearances for

maintenance, etc. Immediately after placing of any order or at any event within 4 weeks unless

otherwise approved in writing by the Architect, the Contractor shall forward to the Project Architect

for comment, 4 copies of manufacturer’s shop drawings indicating detailed construction, principal

dimensions and weights, clearances for withdrawals and/or cleaning, etc. No work shall proceed on or

off Site unless drawings requiring approval are so approved in writing by the Project Architect.

4.3.6 Drawings for Submission to Other Authority

4.3.6.1 Checking Drawings of Other Trades

The Contractor shall follow the design intent of the Contract Drawings in planning and carrying out the

work and shall cross check with other trades in order to verify the line, level, space and sequence in

which the work is to be installed.

If directed by the Project Architect, the Contractor shall, without extra charge, make reasonable

adjustments to the proposed installation drawing layouts as are necessary to prevent conflicts with the

work of other trades or for the proper sequence of and execution of work.

Where such modifications are of a nature and of such unforeseen complexity that they involve

unreasonably extra work not covered by the Contract, they may be covered by variation order to be

issued by the Project Architect wherever such a requirement is justified.

4.4 AS-BUILT DRAWINGS

4.4.1 Submission of As–built Drawings

The Contractor shall submit 4 sets of the first draft prints of as-built drawings within 21 days of the

issuance of the certification of completion to the Project Architect/M&E Engineer for checking. The

Project Architect/M&E Engineer after checking the draft prints shall return one set of the marked up

copies of these as-built drawings to the Contractor within 14 days from the date of submission of the

Contractor’s draft prints with comments. The Contractor shall within a further 7 days from the date of

receiving the Project Architect’s comments on the draft as-built drawings re-submit to the Project

Architect for his approval another 4 sets of the second draft prints of as-built drawings with the Project

Architect’s comments incorporated. This process of submission and approval shall continue until the

final approval of the Project Architect on these as-built drawing is obtained.

The final approved as-built drawings shall be in 4 sets of hard copy and 2 sets of electronic copies.

These shall be submitted within 7 days from the date of final approval. Each electronic copy shall be

in the form of CD-ROM, labelled, with cross reference to a printed list of files explaining the contents

and purpose of each file and supplied in sturdy plastic encases.

4.4.2 Size of As-built Drawings

As-built drawings shall only be of standard sizes of A3 size as stipulated in ISO 5457:1999.

4.4.3 Content of As-built Drawings

The Contractor shall ensure all as-built drawings are accurate representation of the Works, before

submitting them to the Project Architect.

The as-built drawings required to be provided by the Contractor for various types of BS/M&E

installations shall include, but not limited to the following:-

(a) Building services layout plans such as trunking arrangement, piping arrangement, etc.

(b) System schematic diagrams, control diagrams and wiring diagrams;

(c) Concealed work layout plan such as concealed conduit routing, etc.; and

(d) Installation details drawings such as LV cubicle switchboards layout and remote control

position etc. "As-built" drawings complete with all details such as design air to be used for

commissioning purposes. Any amendments noted on these drawings during the commissioning

165

and test stage shall subsequently be transferred to the original "As-built" drawings once the

amendments have been accepted by the Project Architect.

4.5 OPERATION AND MAINTENANCE (O&M) MANUAL AND USER MANUAL

4.5.1 General

The Contractor shall provide two types of manuals to the Project Architect with all changes made to

the installation during the course of the Contract suitably incorporated.

The O&M Manual is for use by the maintenance agent of the completed installation. It shall contain

detailed technical information covering both operation and maintenance aspects of the installation.

The User Manual seeks to give users of the completed installation an overview of the essential

information of the installation. The contents of the manual should be concise and succinct for ease of

comprehension by people with a non-technical background.

4.5.2 Presentation

All manuals shall be written in English, unless otherwise specified.

The text of descriptive parts shall be kept concise while at the same time ensure completeness.

Diagrammatic materials shall also be supported by comprehensive descriptions.

The manuals shall comprise A4 size loose-leaf, where necessary, A3 size folded loose-leaves. The

loose-leaf shall be of good quality paper that is sufficiently opaque to avoid "show-through". Unless

otherwise specified in the Contract, the manuals shall be bound in durable loose-leaf 4 ring binders

with hard covers. The manuals shall have labels or lettering on the front cover and spine.

The Architect’s approval shall be obtained on this at the draft manual stage. The electronic copy of

manuals including the technical literatures shall be in PDF format readable by Acrobat Reader

Freeware.

4.5.3 Checking and Approval

The Contractor shall submit 3 sets of the first draft of O&M Manuals together with a list of

recommended spare parts for one year’s operation and a list of special tools, both complete with prices

to the Project Architect for comment within 21 days of the issuance of the certificate of completion.

The Contractor shall submit 2 sets of the first draft of the User Manual to the Project Architect for

comment at least 15 calendar days before the date of completion.

The Project Architect will check the drafts and return them to the Contractor within 14 days from the

date of submission with comments necessary for a final and approved set of document. The Contractor

shall then make all necessary amendments to the documents and resubmit them to the Project Architect

within 7 days from the date of receipt of comments.

The Contractor shall submit 4 sets of hard copies (one of which shall be the original) and one set of

electronic copy of the final approved O&M Manuals in CD-ROM within 14 days from the date of

approval by the Project Architect.

The Contractor shall submit 2 sets of hard copies and one electronic copy of the final approved User

Manuals in CD-ROM within 7 days from the date of approval by the Project Architect.

166

4.5.4 Structure and Contents of O&M Manual

The detailed requirements, structure and contents of the O&M Manual shall be as specified in elsewhere

in the Contract and shall include the following information under separate sections where appropriate:-

(a) Project Information

This shall include:-

Project title, site address, contract no., contract title, contractor/sub-contractor name, address,

contact persons and their telephone/email, contract commencement date, substantial completion

date and end date of maintenance period.

(b) System Description

- Type(s) of system(s) and equipment installed;

- Design criteria, design data and parameters;

- Locations of the system and major equipment, and what they serve;

- Description of operation and functions of the system and equipment; and

- General operating conditions, expected performance and energy and resources

consumption where applicable.

(c) List of Installed Equipment

Schedule of all items of equipment, stating the location, name, model no. manufacturer's serial

or reference no., manufacturer’s design duties and data

(d) Spare Parts and Special Tools Lists

- List of Spare Parts supplied by the Contractor:

Item descriptions, supplied quantities, model nos., manufacturer’s serial or reference nos.

and storage locations; and

- Recommended Spare Parts List and Special Tools List:

Manufacturers’/suppliers’ recommendations for spare parts and special tools with item

description, unit rate, recommended stock quantities as well as the agents for the spare parts

and special tools.

(e) Manufacturers’ Certificates/Guarantees

- Manufacturers’ certificates such as factory test certificates and guarantees and any others

where required for the equipment, etc.; and

- Originals of Statutory Inspection Certificate for various installations, including:-

- Other equipment such as surveyor’s test certificates for high pressure vessel; and

- Electrical installations (Work Completion Certificate).

[Note: Testing records & commissioning data (other than the types prescribed above), which

are required under the Contract such as the Testing & Commissioning (T&C) procedures,

etc. to verify the compliance of the BS/M&E system’s/equipment’s performance with the

Contract requirements, are checked and endorsed separately by the Project Architect and do

not form part of the O&M manuals.]

(f) Safety Precautions for Operation & Maintenance State, where applicable, hazard warnings and

safety precautions of which the operation and maintenance staff need to be aware:-

- Mandatory requirements relating to safety;

- Known hazards against which protection measures shall be taken; and

- Known features or operational characteristics of the installed equipment or systems which

may cause hazard and the related safety precautions.

167

(g) Operation Instructions

Instructions for the safe and efficient operation, under both normal and emergency conditions,

of the installed system which shall comprise:-

- An outline of the operating mode;

- Procedures and sequences for start-up and shut-down;

- Interlocks between equipment/system;

- Calling on of stand-by equipment;

- Precautions necessary to overcome known hazards;

- Means by which any potentially hazardous equipment can be made safe;

- Forms for recording plant running hours, energy consumption and energy costs; and

- Operating data such as running current, operating pressure, etc.

(h) Maintenance

a) Maintenance Instructions

The Manufacturer’ and the Contractor's recommendations and instructions for the maintenance

of the installed equipment should give a clear distinction between planned tasks (preventive

maintenance) and fault repair tasks (corrective maintenance). Instructions shall be given on each

of the following, as appropriate:-

(i) Nature of deterioration and the defects to be looked for;

- Isolation and return to service of equipment;

- Dismantling and reassembly;

- Replacement of components and assemblies;

- Adjustments and testing; and

- Special tools, test equipment and ancillary services.

- Maintenance Schedules

Proposed maintenance schedules for all the preventive maintenance tasks identified above. The

schedules shall be based on both manufacturers' recommendations and other authoritative

sources (e.g. statutory or mandatory requirements) and should include:-

- Routine servicing;

- Inspections;

- Tests and examinations; and

- Adjustments;

The frequency of each task may be expressed as specific time intervals, running hours or

number of completed operations as appropriate. Collectively, the schedules will form a

complete maintenance cycle, repeated throughout the whole working life of the installation.

(i) Drawing Lists

- A complete list of as-built drawings identified with drawing number/reference;

- A complete list of manufacturers’ shop drawings with drawing number/reference, where

applicable.

168

(j) Technical Literatures

A complete set of manufacturers' literatures for all the plants and equipment’s installed in the

system. The contents of these literatures shall cover the following areas where applicable:-

- Description of equipment with model numbers highlighted;

- Performance - behavioural characteristics of the equipment;

- Applications - suitability for use;

- Factory/laboratory test reports, detailed drawings, circuit diagrams;

- Methods of operation and control;

- Operation instructions;

- Cleaning and maintenance requirements;

- Protective measures and safety precautions for operation and maintenance; and;

- Part lists.

4.5.5 Structure and Contents of User Manual

The detailed requirements, structure and contents of the User Manual shall include, where applicable,

the following information:-

(a) Project Information

This shall include:-

Project title, site address, contract no., contract title, contract commencement date, substantial

completion date and end date of Maintenance Period

(b) System Description

i Type(s) of system(s) and equipment installed, and their purposes;

ii Locations of equipment;

iii Brief description of the operation and functions of the systems and equipment; and

iv Listing of set points which can be adjusted by the user to suit their operation needs.

(c) Schedule of equipment location and Installed Equipment

(a) Schedule of major equipment including their locations and serving areas.

(d) Safety Precautions for Operation

Any safety precautions and warnings signals that the users shall be aware of in the daily operation

of the various systems and equipment in the installation including:-

(a) Mandatory requirements relating to safety;

(b) Features or operational characteristics of the installed systems or equipment which may cause

hazard and the related safety precautions;

(c) Protective measures and safety precautions for operation; and

(d) List of warning signals and the related meanings that the user shall be aware of and the actions

to be taken.

(e) Operation Instructions

Instructions for the safe and efficient operation, under both normal and emergency conditions, of

the installed system which shall comprise:-

(a) An outline of the operating mode;

(b) Step by step operation instructions for systems and equipment that are to be operated by the

user, including at least procedures for start-up and shutdown;

(c) Means by which any potentially hazardous situation can be made safe; and

(d) Cleaning and basic maintenance procedures.

169

(f) List of Statutory Periodic Inspections and Tests

A schedule of periodic inspections and tests that owner and/or user of the installation have to

arrange to achieve compliance with the requirements stipulated in the relevant Laws of Sierra

Leone. The frequency of such inspections and tests shall be expressed in specific time intervals.

(g) Drawings

A set of selected as-built drawings shall be able to illustrate to the user the general layout of the

completed installation.

(h) Photographs

A set of photographs with suitable caption’s to illustrate to the user the appearance and locations

of devices which require their setting and operation.

4.5.6 Intellectual Property Rights

The Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field Office at the African

Development Bank (ADB) shall become the absolute and exclusive owner of the Operation and

Maintenance Manuals and the User Manual and all intellectual property rights subsisting therein free

from all encumbrances.

In the event that the beneficial ownership of any intellectual property rights subsisting in the above

Manuals are vested in anyone other than the Contractor, the Contactor shall procure that the beneficial

owner shall grant to the Employer a transferable, non-exclusive, royalty-free and irrevocable license

(carrying the right to grant sub-licenses) to utilize the intellectual property rights in the manuals for the

purposes contemplated in the Contract. For the avoidance of doubt such purposes shall, but not limited

to, include providing free copying of the materials in the manuals by any subsequent owner or user of

the installation, and/or any party responsible for the operation and maintenance of the installation in

connection with any subsequent alteration, extension, operation and maintenance of the installation.

170

B GENERAL TECHNICAL REQUIREMENTS (INSTALLATION METHODOLOGY)

1 AIR CLEANING EQUIPMENT

1.1 GENERAL

The complete air filter shall be of heavy-duty airtight factory fabrication designed to ensure a positive

seal against leakage of unfiltered air. Generally, it shall be complete with robust enclosure, holding

frames and housing, all supplied by the same manufacturer, as below:-

1.1.1 The robust enclosure shall be factory assembled in such a manner that a rigid and durable enclosure for

the filters is ensured. The periphery of the filter shall be continuously bonded to the inside of the

enclosing frame to eliminate air bypass and to ensure the optimum filtration efficiency.

1.1.2 The holding frames, which are designed to accommodate standard sized filters of the specified

efficiency, shall be factory assembled and manufactured by the filter manufacturer. It shall be

constructed and equipped with positive gasket seals at the entire length of the holding frames. The

gaskets are provided to stop the air bypass between the filter cell and the frames, between the adjacent

frames, and also between the frames and the housing. To firmly hold the filter cells against sealing

gaskets, fixtures shall be provided adequately. The above elements are to be fully supported against the

direction of airflow and become totally rigid when installed.

1.1.3 The Contractor shall provide all required new filters for all air handling equipment (FCU’s) at the time

of practical completion.

For cleanable filters, the Contractor shall provide at least 1 extra set of each type of installed filters for

spare and be responsible for the cleaning of filters when necessary during the maintenance period. This

set of filters shall be handled over to the Project Architect at the end of the maintenance period.

1.2 WASHABLE PANEL FILTER

The holding frames shall be equipped with fixtures for easy removal of the filter cells without the use

of any special tools. For filter cells installed inside air handling units (FCU’s) separate housing is not

required.

However, the holding frames shall be factory mounted in the air handling unit casing and installed to

provide service from the air side.

2 AIR HANDLING AND TREATMENT

2.1 GENERAL

Fans shall be installed using galvanized steel plate, supports, bolts, nuts and washers with all "as cast"

bearing surfaces for bolt heads and washers counterfaced. Anti-vibration mountings shall be in

accordance with Sections in this specification.

Fan guards shall be provided for all open unprotected intakes to centrifugal fans; for unprotected intakes

to and exhausts from axial flow fans; for open unprotected and easily accessible intakes to and exhausts

from propeller and elsewhere as indicated.

2.2 FAN COIL UNITS

2.2.1 The fan coil unit shall be of integrated wall mounted type which combines the supply air slot, return

air grille, fan, casing, cooling coil etc. into a single unit.

2.2.2 Remote control unit shall be provided as specified.

2.2.3 Flexible joints shall be installed for drainage pipe, conduit and other services connection to the unit to

isolate vibration generated by the unit.

171

2.2.4 Power supply will be provided by electrical contractor and terminated at fused connector unit adjacent to

each fan coil unit, all cabling from the power source (e.g. connector unit) to the control box of the fan

coil unit and fan coil room remote control and accessories at convenient position including the

termination shall be carried out by the Contractor.

2.2.5 The location of the local control box shall be within 600 mm from the terminal box of the fan coil unit.

2.2.6 All units shall be selected for wall mount to suit the space within the Server and UPS Rooms, with due

consideration to access for maintenance and servicing.

2.2.7 All blowers and motors of fan coil units shall be within the unit assembly for maintenance purpose

without causing damage to the associated pipework and insulation.

2.2.8 Insulated drain pan shall be provided for those fan coil units installed in Server and UPS Rooms and

other essential areas sensible to water damage.

Fan coil unit and its associated piping should not be mounted above essential electrical and control

equipment such as switchboard, lift machine, control panel, UPS, etc.

2.3 CASSETTE TYPE FAN COIL UNITS

2.3.1 Generally, the cassette fan coil units shall comply with of this Specification.

2.3.2 The fan coil unit shall be of integrated cassette type which combines the supply air slot, return air grille,

fan, casing, cooling coil etc. into a single unit.

2.3.3 Fan coil units shall be selected at design duty and specified noise level with fan running at medium

speed.

2.3.4 Remote control unit shall be provided as specified.

3. Cooling coil shall be constructed with copper tubes and shall be arranged horizontally.

Fins shall have smooth drawn collars of length equal to fin spacing and mechanically bonded to tubes.

Fins shall be of the plate type, corrugated to ensure maximum air contact. Working pressure of coil

shall be as manufactured to suit system pressure design.

2.3.6 Each fan coil unit shall be provided with a high grade AISI 316 stainless steel drain pan situated beneath

the cooling coil and arranged so that all moisture will collect in and drain from the pan. Drain pans

shall be insulated externally with a minimum of 25 mm approved type foamed plastic. Each drain pan

shall be fitted with a drain pipe which shall be connected via suitable runs (correctly laid to fall) to the

drainage system. Drain pans shall have copper male connectors for connection to the condensate drain.

The connector shall be positioned to ensure rapid discharge of moisture from the pan.

2.3.7 Built-in condensate pump shall be provided for the removal of condensate. A water sensing system

with low, high and warning limits shall be provided which actuates the running of condensate pump at

high water limit and trigger the alarm system at warning level.

When water level reaches the warning limit, the sensing system shall cut off the unit operation. An

alarm signal shall be triggered. The signal shall be connected to a remote indication system as design.

Condensate pump shall be designed to run and sense water level in the drain pan after the unit is

switched off as specified. The power source for condensate pump and the associated control system

shall be independent from that of the fan coil unit such that the pump can still be operated after the

units have been switched off.

172

2.3.8 The filter media shall be of the washable type and shall be enclosed in a one-piece formed frame.

2.3.9 Fan shall be of the quiet running direct driven centrifugal type with aluminium blades mounted to a

solid steel shaft. Fan motors shall be of the "split capacitor" type suitable for single phase electrical

supply.

The motor shall be resiliently mounted to the fan tray or scrolls. The motor/fan tray assembly itself

shall also be resiliently mounted to the casing structure.

2.3.10 Adjustable louvres for directional airflow shall be provided for supply air slot in each fan coil unit.

Options shall be given to choose the 4-way supply air discharge.

3 CONTROL

3.1 CONTROL SYSTEM (CS)

The Control System (CS) is the Control located within the room that controls the proper, effective and

efficient operation of the Air Conditioning System (s) within the room(s).

The CS shall be as simple as an electronic controller with built-in features for scheduling controls.

The appropriate CS shall be so designed to meet the requirements and operation needs of the end users.

The main function of the CS is for on/off controls, monitoring of operation status and alarms generation

of the connected systems in room(s). Comprehensive system controls of each individual system shall

be carried out by the system controller of each individual air conditioning in the room.

The CS shall be so designed to achieve a reliable control in performing the functions set in the design

criteria and shall be of electronic or direct digital control type as specified. Unless otherwise specified,

the CS controller shall be located inside the office were the Fan Coil Unit is installed.

3.1.2 Direct Digital Controller (DDC)

(a) Each controller shall operate as a standalone unit capable of performing its specified control

responsibilities independently of other controllers.

(b) Local keypad and display shall be provided for local viewing and operation.

(c) Power Fail Protection

All system set point, control algorithm and other parameter should be stored such that power

failure of any duration does not necessitate reprogramming the DDC controller.

3.1.3 Control of Fan Coil Unit (FCU)

Micro-processor based electronic controller or DDC as specified shall be used for the control of the

FCU and its associated equipment. The following functions shall be provided as specified:-

(a) Start-Stop Control

(i) (Manual On/Off Control (maintenance/manual mode);

(ii) On/Off Control by the CS as scheduled;

(iv) On/Off Controls by special demand overriding the pre-set schedule for dehumidification and/or cooling

during night for special duty cycles in the Server & UPS Rooms as specified;

(v) Demand On/Off Control. The operation of any FCU served by the unit shall energize the PAU.

Unit will only be cut-out when all associated FCUs are turned off by the CS as scheduled.

(b) Capacity Control

(i) Temperature Display

LCD or 7-bit segment (self-illuminated) digital display of the room temperature thermostat within

readable size from three metres apart at the appropriate locations inside the air-conditioned areas shall

be provided. Temperature display shall be setting up in steps not coarser than 0.5K.

3.1.4 Control of Zone Air Distribution Units

(a) Fan Coil Unit (FCU)

173

Unless otherwise specified, controller for FCU shall be of micro-processor based electronic type or

DDC type as specified. Backup battery shall be provided for all controllers.

Unless otherwise specified, the control functions listed below shall be performed by the controller:-

(i) Start-stop control

- Manual on/off control by the three-speed controller; c/w space temperature sensor

(ii) Temperature Control

- Cooling

Unit on/off control valve shall be turned on and off to maintain the room temperatures pre-set in

the controller.

- Temperature Display

LCD or 7-bit segment (self-illuminated) digital display of the room temperature thermostat within

readable size from three metres apart inside the air conditioned areas shall be provided.

Temperature display shall be setting up in steps not coarser than 0.5K.

4 ELECTRIC MOTORS AND ELECTRICAL EQUIPMENT

4.1 LOW VOLTAGE - GENERAL

Unless otherwise specified, the Contractor shall provide and install all low voltage electrical equipment

necessary for the complete installation under the Contract and shall carry out all necessary wiring from

the points of power supply provided by others as indicated on the Contract Drawings.

The Contractor shall be responsible for the accuracy of all installation and shop drawings and wiring

diagram and for the correct internal wiring of all pre-wired equipment supplied under the Contract.

All electrical equipment, wiring and installation work, and materials shall comply with the provisions

of the relevant parts of the Electrical Specification.

4.2 LOW VOLTAGE - ELECTRIC MOTORS

The low voltage electric motors shall comply with the latest IEE Regulations for low voltage

equipment’s.

4.3 LOW VOLTAGE - MOTOR SWITCHGEAR, STARTER AND CONTROL PANELS

The low voltage motor switchgear, starter and control panels shall comply with the latest IEE

Regulations for low voltage equipment’s.

5 REFRIGERATION MACHINE

5.1 GENERAL

All necessary refrigerants shall be supplied by the Contractor during testing and commissioning and

plant operation stages until the plant is accepted and end of maintenance period is certified complete

by the Project Architect. Each unit shall have an electronic/microcomputer control PC board factory

installed and tested.

The plant shall be so selected and installed with sufficient space allowed for effective heat dissipation

to surrounding air, and for easy maintenance and servicing.

Appropriate corrosion resistant materials shall be used including isolation of dissimilar metals against

galvanic interaction, etc.

Mounting and fixing details including details and dimensions of equipment bases, fixing bolts,

supporting steelwork, flexible connections, vibration isolators and any special builder’s work

requirements, etc. shall be provided by the Contractor to meet the contract programme.

Any damage to finishes of the equipment which may have occurred during transit, storage, installation

or other causes shall be made good in the manner recommended by the manufacturer and to the

satisfaction of the Project Architect.

174

Same type of paint shall be used for making good the damages.

All mounting and fixing supports shall be of galvanized steel and exposed metal surface after cutting

shall be treated against corrosion and painted in with anti-corrosion paint as specified in Sections of the

Specification.

5.2 POSITIONING AND ISOLATION/REMOVAL OF EQUIPMENT

The equipment position shall be so arranged that equipment may be isolated for servicing without

completely draining the refrigerant of the whole plant and shall follow the ANSI/ASHRAE Standard

15-2004 or BS EN 378-2:2000 to BS EN 378-3:2000.

All equipment shall be located within safe area indicated on the Tender Drawings and approved by the

Project Architect.

Remote control shall be installed inside the office which is free from water pipes with glazing window

for equipment provided by the building contractor.

5.3 DELIVERY OF EQUIPMENT

All equipment delivered to site shall be properly protected as detailed in Sections of this Specification

The Contractor shall take into account the site constraints when planning the delivery of the equipment.

The delivery of equipment shall be communicated with the Project Architect and Main Contractor to

coordinate the site security requirement before delivery.

Written approval for delivery of equipment to site is required from the Project Architect prior to the

transportation of the equipment to site Any temporary hoisting or handling facilities and installations

to facilitate the delivery of the equipment shall be provided and removed after use by the Contractor.

5.4 REFRIGERATION PIPEWORK AND FITTINGS

Joints in copper pipe shall be flared (up to 20mm OD only), or brazed with or without capillary fittings.

Brazing shall be carried out to the requirements of the HVCA Code of Practice - Brazing and Bronze

Welding of Copper Pipe.

Screwed joints will not be accepted in refrigerant pipes.

Plastics pipe will not be accepted for any other refrigerant pipework.

Compression fittings will not be accepted on refrigerant pipework.

The pipework shall be so install that oil in the refrigerant leaving the compressor shall be carried

through the system and back to the compressor at the lowest stage of capacity unloading.

Pipework shall be firmly supported and secured to minimize vibration.

Vibration eliminators shall be fitted to the compressor suction and discharge pipes to minimize

transmission of vibration or noise. Where indicated, a gas pulsation damper shall be fitted at the

refrigerant discharge pipe, as close as possible to the refrigeration compressor.

After completion, the refrigerant pipe work shall be pressure tested as detailed in T&C Procedure.

All parts and components containing refrigerant shall be clean and dry before they are connected to the

system. No mill scale shall be permitted in pipes and all pipes shall be capped on site until welded in.

Prior to charging refrigerant to the refrigeration system, field pressure tests shall be carried out in

accordance with Part H. Any leak found shall be repaired before the system can be considered tight.

175

Hangers, clips and other hanging or clamping studs shall be galvanized and they shall not be welded to

pipes containing refrigerant. Pipework and other parts shall be erected and clamped so that vibration

and noise are kept to minimum.

The Contractor shall pay particular attention and precaution when handling the refrigerant pipework’s

installation. For charging of refrigerant to the system, the recommendations from the supplier and the

procedures stipulated in the Testing and Commissioning Procedure for Air-conditioning and Control

Systems Installation shall be followed. The work shall also be carried out by trained and qualified

persons approved by the Project Architect.

5.5 AIR-COOLED CONDENSER

Air cooled condensers mounted outside buildings shall have weather proof fan motors. The units shall

discharge air vertically upwards.

The unit shall be installed on vibration isolation devices as specified in Sections B8 and C8. The

Contractor shall, according to the manufacturer’s recommendation, advise the requirements on strength

of the roof curb structure for supporting the unit. Selection of the vibration isolators shall be submitted

to the Architect for approval prior to execution of work.

The unit shall be installed so that air can circulate through the condenser coils without any hindrance,

and the air discharged from the condenser fans is not recycled. If the unit has to be placed near a wall

or an obstacle that may prevent satisfactory air circulation, sufficient distance as recommended by the

manufacturer shall be maintained between the unit and the obstacle.

5.6 VIBRATION ISOLATION

All equipment offered shall have minimum vibration and noise levels during operation, with particular

attention to the requirement that the sound pressure level measured at one meter from the equipment

with all fully operated shall not be more than 5 dB higher than the ambient sound level at any time, and

shall comply with any other requirements of Environmental Protection Department or other statutory

noise control requirements issued prior to tendering, whichever is more stringent.

The Contractor shall be responsible for provision of adequate vibration isolation and/or sound

attenuation measures for the refrigeration plant to meet the requirements as detailed in Sections of this

Specification and to the satisfaction and acceptance of the Project Architect.

5.6 ELECTRICAL WORK

The Contractor shall supply and install suitable power cables, cable trays, G.I. supports, starters/motor

drives, isolators, control, safety earth bonding and all necessary accessories to connect power from the

isolator to each electricity driven equipment. The Contractor shall allow for adequate cable size and

protection devices to meet the current demand and voltage drop requirements of the equipment offered.

6 PIPEWORK

6.1 JOINTS AND FITTINGS FOR COPPER TUBES

Fittings for copper pipework shall be as follows:-

B9.9.1 Size up to and including 65 mm shall be of the capillary or compression type to ISO 2016:1981.

6.1.1 Pipework shall be arranged with adequate connection points to allow easy dismantling. Connection

points in copper pipework size up to and including 65 mm size shall be unions and for pipework of size

76 mm and above shall be flanged.

176

6.2 PIPEWORK GENERAL DETAILS

6.2.1 Pipework shall follow the contours of walls and shall be suitably graded not less than 1 in 500 to

ensure proper draining.

Generally, the clearance between pipework (or the lagging) and the wall and any other fixtures shall be

not less than 25 mm. Pipework shall not run near to or above electrical appliances, cables, trunking

and conduits.

6.2.2 Where two or more pipe runs follow the same route, all pipes shall run parallel with one another and

to the building structure without prejudice to the necessary allowances for drainage or other reasonable

restrictions. Any pipework which requires subsequent insulation shall be adequately spaced to allow

for individual finish.

6.2.3 Tubes shall be reamed after cutting and shall be free from burrs, rust, scale and other defects and shall

be thoroughly cleaned before erection. Pipe ends left open during the progress of work shall be

temporarily closed with purpose-made plastic plugs or caps and protect from corrosion.

6.2.4 Joints shall not be made in the thickness of any wall, floor or ceiling and pipework shall not be

embedded in the structure of floors unless otherwise instructed by the Project Architect. Where

pipework passes through walls, floors or ceilings, sleeves shall be provided. Pipework passing through

floors shall, where specified, be provided with approved type floor and ceiling plates and fastened

securely to the sleeve. Sleeves shall be of the same material as the pipe. The space between pipework

and sleeve shall be sealed with an approved fire resisting material having FRP of not less than that of

the wall and floor and in compliance with relevant regulations and code of practices.

6.2.5 All entry and exit holes to or from a building for a pipework services shall be sealed and plugged. The

sealant shall be a mastic compound or silicone rubber. Where the pipework enters the building through

a large hole or duct, a mild steel blanking plate not less than 6mm thick shall be built into the wall of

the hole or duct. The service pipes shall pass through clearance sockets welded to the plate. The space

between pipe exterior and socket interior shall be sealed and plugged with waterproof material or

sealant having an FRP of not less than that of the wall and in compliance with the relevant regulations

and code of practices, all to the approval of the Project Architect.

6.2.6 All fittings shall, as far as practicable, be the same size as the tubes and pipes connected to them. Bushed

outlets will only be accepted if the required outlet size of a fitting is not of standard manufacture.

6.2.7 Elbows shall be used, where practicable, in preference to bends.

However, square elbows will not be permitted. Unless otherwise specified, long radius elbows shall be

used in order to minimize hydraulic resistance.

6.3 PIPEWORK LAYOUT

The Tender/Contract Drawings indicate the size and general layout of the required pipework. The exact

position may not be indicated on the drawings as for the purpose of clarity, they are generally shown

as separately spaced out from one another as if they were at the same plan level. The Contractor shall

accurately set out the various pipelines in the installation in compliance with the provisions of Clause

A3.15 and A4.3 of this specification.

6.4 PIPEWORK SUPPORTS, EXPANSION JOINTS AND ANCHOR POINTS

6.4.1 Where the Employer’s Guide Drawings & Details for pipework supports and brackets, are issued

with the specific Contract Documents or have previously been issued to Approved Contractors for

general application on the Employer’s projects, these standard details shall be followed "In-

Principle" but adjusted as to the detail in order to suit the particular circumstances.

Such adjustments shall be indicated on the Contractor’s own Installation/Shop Drawing and loading

calculation Submissions and be approved by the Project Architect before work commences.

177

6.4.2 Pipework shall be supported so as to permit movement due to expansion and contraction. Pipework

supports shall be installed as near as practicably possible to joints and changes in direction. Each

support shall take its due proportion of the load. The spacing of the supports shall not exceed the

canters given in Tables B6.8-(1) and B6.8-(2). Where there are two or more pipes, the spacing shall

be based on the canters required by the smallest bore pipework.

6.4.3 Vertical rising pipework shall be managed on cable trays within the riser.

6.4.4 Where pipework up to 50 mm size is fixed to solid wall, brackets may be of the screw-on or long

shank built-in type in case the walls are plastered; only the long shank built-in type shall be used.

For fixing to woodwork and lightweight partitions or walls, brackets shall be of the screw-on pattern

of adjustable two-piece type. Brackets for mild steel and plastic pipework shall be mild steel or

malleable iron; brackets for copper pipework shall be brass or gunmetal. The upper half of the pipe

clip shall be detachable without disturbing the fixing.

6.4.5 Brackets screwed to walls shall be secured by expanding plugs. Other purpose designed fixing

devices or softwood plugs will not be permitted.

6.4.6 Unless otherwise specified, hangers for horizontal pipework at high level shall be supported from

galvanized mild steel angle or channel sections or approved proprietary devices supplied by the

Contractor, suitable for building-in or otherwise securing to the structure by the building contractor.

Adjustable mild steel hangers shall be used. Pipe rings shall be of malleable cast iron or fabricated

steel, made in halves and secured by bolts or screws. Alternatively, malleable iron hinged pipe rings

may be used. Calliper type hooks will not be permitted.

6.4.7 Where pipework is fitted in service duct or trenches and supported from walls, the design of the pipe

supports, guides and anchors shall be in accordance with the Contract Drawings. Otherwise, the

Contractor shall submit details and proposal to the Project Architect for approval. Where roller

supports are required, they shall be of an approved type. The performed insulation shall be kept free

of the rolling surface. Load-bearing insulation at supports, where required, shall be fitted by the

Contractor at the time of erecting the pipework.

6.4.8 For copper pipework, the anchors shall be provided by wide copper straps secured to the pipework

in such a manner that the pipe is not damaged.

6.4.9 The Contractor shall supply, and fix in position ready for building-in, all cleats, brackets and

steelwork required for anchor points. Anchor steelwork secured to the bottoms of ducts or trenches

shall be coated with hot-poured bitumen to inhibit future corrosion.

6.4.10 Supports for plastics pipework may be of any approved pattern that prevents free axial movement of

pipe at all temperatures and have radial edges to prevent cutting into the pipe. The entire bearing

surface must be sufficiently wide to prevent indentation.

Valves, meters and other heavy "in-line" equipment must be supported independently.

Supports for pipes carrying water at a maximum temperature of 150C and covered with lightweight

insulation shall be spaced in accordance with Table B6.8-(2) under Clause B6.8. Alternatively, the

pipework may be continuously supported, provided that the thermal insulation covering the

pipework is sufficiently rigid to ensure that no compression or deformation of the insulation occurs.

178

6.4.11 Provision for movement due to expansion and contraction shall be generally as indicated and/or shall

be by changes in direction of the pipework, by loops or by other approved expansion devices.

6.4.12 Supports and guides shall be arranged to ensure that all movement is taken up by the change in

direction of the pipework or by the loop or device.

6.4.13 The spacing of supports for copper and plastic pipework shall be in accordance with

Tables 6.8-(1) and 6.8-(2)

6.4.14 Cold Bridge should be prevented between the insulated pipework and the associated hangers and

pipework supports.

6.5 PLASTIC PIPEWORK

Fittings for plastics pipework shall be as follows:-

6.6.1 Fittings shall be of the same material as the pipework to which they are joined. They shall be made or

approved for the solvent welding process.

As a general rule PVC pipe should only be made threaded and screwed into metal "Female" threaded

fittings.

6.6.2 Joints between pipe and pipe fittings shall be made by the solvent welding process. No cleaning fluid

or solvent cement other than that supplied or recommended by the pipe manufacturer shall be used.

6.6.3 Where it is required to form a spring in the pipe run, the pipe shall be softened by immersion in (or by

pouring on) heated brine, glycerine oil or water as recommended by the pipe manufacturer. The use of

a naked flame on the pipe surface will not be accepted.

6.6.4 Where uPVC is used for condenser cooling circuits and for the inlet and outlet to pumps, it must be

effectively isolated from the vibration of the machine. This shall be achieved by the insertion of flanged

synthetic rubber vibration de-couplers installed between uPVC pipework and plant on all connections.

6.7 'T' AND 'Y' FITTINGS Except at vent and drain points, all tees and 'Y' fittings shall be of the swept type.

The sweep radius being at least equal to that of the medium bend but where specified as a long sweep

it shall then be equal in radius to the long bend.

6.8 SUPPORTS FOR PIPEWORK

Table 6.8 – (1) Supports for Copper Pipework

Size of tube Intervals for horizontal runs Intervals for Vertical Runs

Bare Lagged Bare and Lagged

mm m m m

15 1.2 1.2 1.8

12 1,2 1.2 1.8

18 1.8 1.5 2.4

35 2.4 1.8 3.0

42 2.4 1.8 3.0

Table 6.8 – (2) Supports for Plastics Pipework

Nominal Bore of Pipe Intervals for horizontal runs Intervals for Vertical Runs

mm m m

15 0.75 1.5

22-28 1 1.8

28-35 1 2

42 1.2 2.5

179

6.9 BRAZING

The procedure and the competence of the operative shall be in accordance with the recommendations

contained in the following HVCA publications:-

6.9.1 "Code of Practice - Brazing and Bronze Welding of Copper Pipework"

Welding operations which are beyond the scope of (a) and (b) shall comply in particular with:-

6.9.2 ISO 5187:1985 and ISO 10564:1993 - Brazing (copper pipe)

Where the visual inspection and tests reveal those brazing joints which are reasonably believed to be

unacceptable, the Project Architect/M&E Engineer shall be entitled to have such brazing examined by

approved inspection method and independently assessed. The Contractor shall be responsible for the

cost of the tests and subsequently remedy the work to the satisfaction of the Project Architect/M&E

Engineer if tests prove the brazing joints to be non-compliance with the specification.

7 NOISE AND VIBRATION CONTROL

7.1 GENERAL

The Contractor shall install sufficient noise and vibration control measures on the plant/equipment, the

interconnected piping, so that when the installed plant/equipment are put into operation, the resulting

noise and vibration levels at locations within the building and at adjacent or nearby buildings shall not

exceed the acceptable limits.

Unless otherwise specified in the Specification, the total noise level in occupied areas within the

building, whether it be airborne, structure-borne or ductwork-borne, shall not exceed the following

limits when all the plant/equipment installed by the Contractor are put into operation:-

Table 8.1 Noise Control Criteria

Private offices, libraries, meeting and conference rooms NC 35

General offices NC 40

The specified noise criteria shall apply to all areas as measured at a level of 1.5m above the floor and

the measuring points shall be 1.5m away from the walls or doors of the rooms.

The Corrected Noise Level at potential Noise Sensitive Receiver in the adjacent or nearby building, if

so identified in the Contract Documents, shall not exceed the Acceptable Noise Level stipulated in the

Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises or

Public Places issued by Environmental Protection Department when the plant/equipment installed by

the Contractor are put into operation.

7.2 EQUIPMENT BASES

7.2.1 General

Floor mounted equipment shall be installed on 100 mm high concrete housekeeping pads provided by

the building contractor covering the whole floor area requirements of the equipment bases plus a

minimum of 150 mm further on each side or on inverted beams at roof.

Vibration isolators are then mounted on this concrete pad or inverted beams.

Unless otherwise specified in the Particular Specification, plant/equipment to be isolated shall either

be supported by structural steel bases or concrete inertia bases.

7.2.2 Wall Mounted Welded Structural Steel Brackets

Detailed design calculation of the base and its anti-vibration isolator arrangements plus shop drawings

for each base shall be provided for approval by the Architect before manufacture.

180

7.2.3 Concrete Inertia Bases

Detailed design calculation of the base and its anti-vibration arrangements plus shop drawings for each

base shall be provided for approval of the Project Architect before construction/manufacture.

7.3 VIBRATION ISOLATORS

The following types of vibration isolation mountings or suspensions are not exhaustive but serve to

cover the main types that shall be applied as appropriate unless otherwise stated in the Particular

Specification.

7.3.1 Double Deflection Neoprene Mounts

These mountings shall have a minimum static deflection of 8.5mm.

Bolt holes shall be provided for applications where bolting down is required. They shall be carefully

positioned such that all supporting mounts would be properly loaded and the weight load on each mount

would be evenly distributed over the entire surface.

7.3.4 'D' - Neoprene Pads

Where necessary, pads may be bolted through with bolts isolated from the machine by neoprene

grommets. Alternatively "waffled" neoprene pads can be used without holding down bolts where the

vibration is minimal and the weight of machine is such that the resultant friction is adequate and the

machine is unlikely ever to move.

They shall be carefully positioned such that all supporting pads will be properly loaded and the weight

load on each pad will be evenly distributed over the entire surface.

7.4 PLANT/EQUIPMENT VIBRATION ISOLATION

7.4.1 General

All rotating or reciprocating equipment shall be mounted on vibration isolation mountings or suspended

from vibration isolation hangers.

The Contractor shall ensure that there is no rigid connection in whatever form between the isolated

equipment and the building structure which will otherwise short-circuit the vibration isolation system

and degrade its performance. This includes the necessary coordination with other trades by the

Contractor.

All isolators shall operate in the linear portion of their load versus deflection curve. The load versus

deflection curves shall be furnished by the manufacturer, and must be linear over a deflection range of

not less than 50% above the design deflection.

All vibration isolators shall have their known undefeated heights or calibration markings so that, after

adjustment when carrying their loads, the deflection under load can be verified, thus determining that

the load is within the proper range of the device and that correct degree of vibration isolation is achieved

according to the design.

The installation of all vibration isolators, hangers and associated equipment bases shall be carried out

strictly in accordance with the approved manufacturer’s written instructions.

7.4.2 Method of Installation

The equipment structural steel or concrete inertia base shall be placed in position and supported

temporarily by blocks or shims. The machinery shall then be installed on the base and when that is

complete, the isolators are to be installed without raising the machine and frame assembly.

After the entire installation is complete and under full operational load, the isolators shall be adjusted

such that the load, are transferred from the blocks to the isolators. When all isolators are properly

adjusted, the blocks or shims will become slightly free and can then be removed.

181

Prior to start-up, remove all foreign matter underneath the equipment base and verify that the vibration

isolation system is not short circuited.

Electrical circuit connections to isolated equipment shall be looped to allow free motion of isolated

equipment.

7.5 PIPEWORK VIBRATION ISOLATION

7.5.1 General

Unless otherwise indicated, all piping having connection to vibrating equipment shall be isolated by

means of noise and vibration isolation materials.

All piping to be isolated shall neatly managed on cable trays installed within the false ceiling and freely

pass through walls without rigid connections. Penetration points shall be sleeved or otherwise formed

to allow passage of piping, with adequate clearance around the outside of the piping shall be

maintained. The clearance space shall be tightly packed with glass fiber or rock wool and caulked

airtight after installation of piping.

7.5.2 Horizontal Pipe Isolation

Where horizontal pipe isolation is required, the pipes shall be secured with cable ties on the cable tray.

7.5.3 Pipe Riser Isolation

Where pipe riser isolation is required, the pipe risers to be isolated shall be secured on cable trays

installed in the riser and anchored with pipe anchors or pipe guides.

7.6 INSPECTION

On completion of the installation of all noise and vibration control devices, the Contractor’s engineer

shall inspect the completed system and report in writing to the Main Contractor concerning any

installation errors, improperly selected isolation devices, and/or other faults that could adversely affect

the overall performance of the system.

The Main Contractor shall then submit a report to the Project Architect in which the report shall include

all findings of the Contractor’s engineer and confirmation of the satisfaction completion of all isolation

work together with any remedial actions proposal.

Where remedial action has to be taken by the Contractor, further inspections shall be carried out until

all faults are rectified.

8 UNITARY AIR-CONDITIONER

8.1 GENERAL

8.1.1 Unitary air-conditioners shall include

(a) Condensing unit and blower coils;

(b) Condensing unit with variable refrigerant volume control and indoor fan coil units;

8.1.2 Unitary air-conditioners shall be factory fabricated and assembled.

The equipment shall be rated and tested in the same country of manufacture and meet with the

requirements of the International Organization for Standardization (ISO) Standards 5151:1994 (non-

ducted air-conditioners and heat pumps) or 13253:1995 (ducted air conditioners and air-to-air heat

pumps) or 13256-1 & -2:1998 (water to- air and water-to-water heat pumps) or other internationally

recognized quality assurance standards approved by the Architect.

8.1.3 The most energy efficient model in the series shall be selected for submission and shall be referred to

Clause C12.19 of this General Specification.

8.2 INSTALLATION AND SERVICING

Installation and servicing of unitary air-conditioners shall comply with the practice set out in the ISO

13261-1:1998 & ISO 13261-2:1998 and the manufacturer’s recommendation.

182

8.3 ANTI-VIBRATION MOUNTING

Vibration mounting shall be installed in accordance with relevant clauses of Section B8.

8.4 CASING

Removable panel for casings shall be provided to give access to all working components, parts, and

connections for installation and service. The casing shall be rigid G.I. Sheets and painted.

The compartment housing for the direct-expansion coil and blower shall be adequately insulated to

prevent sweating and shall contain a suitable drip pan with a drain connection. The compartment

housing for the compressor shall be treated for effective sound insulation to ensure that the noise

emitted is within the limits as specified in the Specification.

8.5 COMPRESSOR

Each compressor shall form a separate refrigerant circuit with its own condenser, evaporator and

controls.

8.6 SUPPLY AIR FAN AND MOTOR

All fans shall be statically and dynamically balanced. Fans shall be equipped with self-aligning bearings

suitable for the installed altitude of the fan.

8.7 COOLING COILS

Adequate water collecting tray for run off and removal of the condensation shall be provided.

8.8 AIR FILTER

Air filters shall be installed in accordance with the manufacturer’s recommendation

8.9 AIR-COOLED CONDENSERS

Condenser fan shall be of propeller type arranged for either horizontal discharge.

8.10 REFRIGERANT PIPING

Refrigerant piping and insulation shall be installed in accordance with relevant Sections in this

Specification.

8.11 CONDENSATE DRAIN PIPE

Condensate drain pipe shall lead to the nearest convenient drain in the building or as indicated on the

Contract Drawings or as directed by the Architect on site.

8.12 MINIMUM INSTALLATION REQUIREMENTS OF SAFETY AND OPERATIONAL

CONTROL FOR UNITARY AIR-CONDITIONERS

Table: 12.12 Standard Provisions

Item Associated Components/Facilities Unit Cooling Capacity

Up to 7 kW 7 kW-14

kW

1 Self-contained safety and operational components of factory standard Yes Yes

2 Pressure gauges c/w stop valves, sight glass - Yes

3 Renewable filter-drier c/w accessories - Yes

4 Externally mounted adjustable Hi-Lo pressure cut-out with hand reset for High

side

- Yes

5 Anti-recycling device Yes Yes

6 Emergency Stop Switch Yes Yes

7 Crankcase Heater - Yes

8 Pump down function and facilities - -

9 Refrigerant R410a R410a

10 Mechanical and weather protection to thermal insulation which exposed to

view

183

8.13 SPLIT CONDENSING UNIT AND FAN COIL UNIT (FCU)

The Split Condensing Unit shall be air-cooled and installed outside the building. The interconnecting

refrigerant piping between condensing unit and fan coil unit (FCU) shall be field connected.

8.14 VARIABLE REFRIGERANT VOLUME SYSTEM (VRV)

The refrigerant piping shall be capable of extending up to 100 metres equivalent length with 50 metres

level difference without any oil trap. The entire system completed with all necessary piping and

accessories shall be supplied and designed by a single proprietary manufacturer who has proven record

for its product.

8.15 MAINTENANCE SERVICING PLATFORM

Where unitary air-conditioners are installed at levels that are normally inaccessible from ground these

shall be provided with an adequately sized service platform complete with railings and steel cat ladder

with safety wings.

Such platforms shall be of reasonable substantial rigid galvanized metal construction and shall be well

protected against corrosion. The design must be approved by the Project Architect before installation.

Under Labour Department Ordinance, it is required to provide working platform for activity over 3

metres. This maintenance servicing platform requirement shall apply to all equipment and installation.

184

C GENERAL TECHNICAL REQUIREMENTS (MATERIAL AND EQUIPMENT

SPECIFICATION)

1 AIR CLEANING EQUIPMENT

1.1 GENERAL

Filters shall be of proprietary product and have the specified performance and fire property in

accordance with the test methods of one or more of the standards stated hereinafter.

To improve indoor air quality and protect air conditioning equipment, outdoor air and re-circulated

indoor air shall be filtered to remove dust, bacteria, pollens, insects, soot and dirt particles before it

enters the air conditioning system. The following air cleaning devices, dependent on their compatibility

with the general air conditioning system, shall be incorporated into the system as in-duct devices or

stand-alone devices.

1.1.1 Particulate Filter

Particulate filters are the most commonly used air cleaning devices in buildings. The filter shall be

selected depending on the physical characteristics and levels of the dust to be removed, the capacity of

the system to overcome the associated pressure drop across the filter and the degree of indoor air

cleanliness required:-

The filters shall be cleaned or replaced on a regular basis according to the manufacturer’s

recommendations or when the specified maximum pressure drop is reached.

1.2 STANDARDS 1.2.1 Performance of Air Filter

The performance of air filters shall comply with one or more of the following standards:-

(a) ANSI/ASHRAE Standard 52.1-1992 – Gravimetric and Dust-Spot Procedures for Testing Air-

Cleaning Devices Used in General Ventilation for Removing Particulate Matter;

(b) ANSI/ASHRAE Standard 52.2-1999 – Method of Testing General Ventilation Air Cleaning Device

for Removal Efficiency by Particle Size;

(c) European Standard BS EN-779:2002 - Particulate Air Filters for General Ventilation;

(d) European Standard BS EN 1822-1:1998 to BS EN 1822-3:1998 and BS EN 1822-4:2000 to BS EN

1822-5:2000 –High Efficiency Air Filters (HEPA and ULPA); or

(e) Any other standards equivalent to the standards above and approved by the Architect to suit

particular project requirements.

1.2.2 Fire Property of Air Filter

The fire property of air filters and its associated accessories shall comply with one of the following

standards as well as the requirements of Fire Services Department:-

(a) British Standard Institution BS 476-4:1970 - Non-Combustibility Test for Materials;

(b) British Standard Institution BS 476-6:1989 - Method of Test for Fire Propagation for Products,

with Indices "I" ≤ 12 and "i1" ≤ 6;

(c) European Standard DIN 53438-3:1984 - Response to Ignition by A Small Flame, Surface

Ignition, Class F1.

1.3 WASHABLE PANEL FILTER

This type of filter shall be constructed to withstand washing by water or steam. The filter panel shall

be constructed from multiple layers of expanded aluminium mesh or glass, natural or synthetic fibre,

with the layers being corrugated or plain and arranged alternately at right angle at one another.

1.4 ADDITIONAL REQUIREMENTS (SPARE FILTER MEDIA)

The Contractor shall replace all filters used during testing and commissioning stage and in addition

provide the following to the Architect for use by Client’s operation staff during maintenance period:-

185

(a) For washable type filters, 20% in number of each size of filter cells provided. These shall be new

and in good condition. Besides, 10 litres of the approved cleaning detergent per filter installation

shall be provided. Regarding filters of viscous type, a drum or drums of fluid

Within one month before end of the maintenance period, all the filter cells/media shall be replaced

with new ones. In addition, 10 litres of the approved cleaning detergent per washable filter

installation shall be provided..

2 AIR HANDLING AND TREATMENT EQUIPMENT

2.1.1 GENERAL

Fan coil units shall comply with the manufacturer’s own ISO 9001:2000 quality standard in respect of

design and manufacturing and be type-tested to BS 4856-2:1975 for thermal volumetric and acoustic

performance. The Contractor shall submit the make and type of each fan together with the "type" test

certificate for the Architect’s approval. The origin of the fan shall be from the country where the "type"

test was conducted.

Fans, filters, cooling coils, motors, thermal and acoustic insulation shall comply with the appropriate

sections of this Specification and the following requirements:-

(a) Fans shall be of tangential flow types and shall be of mild steel, aluminium, reinforced glass fibers

or rigid plastic material as specified in Particular Specification;

(b) Air filters shall be as indicated in the relevant content of Section but with an efficiency of not less

than 50% when tested in accordance with BS EN 779:2002;

(c) Motors shall be quiet running and have sleeve or ball bearings factory lubricated for life. Motor

windings and electrical components shall be impregnated or protected to avoid trouble from

condensation. The fan motor shall be of the single phase permanent split capacitor type provided

with three speed tapped windings;

(d) All fan coil units capacity and air flow rate shall be selected based on the performance of the units

at medium fan speed; and

(e) In selecting the fan coil units, allowance shall be made for the actual resistance imposed on the air

flow of the units. The added resistance is to be applied to all fan coil units and shall be taken as not

less than 50 Pa external to the unit.

2.1.2 Casings

Casings shall be of factory treaded plastic with thickness not less than 1.0 mm suitably stiffened to

minimize drumming and vibration and shall be protected against corrosion and finished inside and

outside with stove primer. All corners shall be rounded off without sharp edges. Casings shall include

space for pipework connections, and there shall be ready access to the fan and motor, filter, drain pan

and pipework connections, for maintenance purposes.

The motor and fan shall be mounted on a detachable mounting chassis that can be removed from the

fan coil enclosure as one assembly (with extended cables) to facilitate fan and motor cleaning. It shall

then also be possible to remove the fan impeller scroll casing in order to properly clean the fan blades.

Fan and motor assemblies shall be completed with neoprene rubber anti-vibration mountings.

2.1.3 Coils

(a) Cooling coils shall be minimum two-row and shall include an air vent cock and drain valve.

(b) The chilled water cooling coil shall be rated in accordance with ARI 410:2001 and constructed from

seamless copper tubes mechanically bonded to aluminium fins.

186

(c) Each coil shall be provided with motorized 2-way solenoid control valve and isolation valves. Flexible

pipe connectors completed with union joints to facilitate removal of the (d) Working pressure of coils

shall suit specific requirements.

2.1.4 Components

(a) All units shall include an easily removable filter capable of treating the total air volume. Filters shall,

unless otherwise specified, be washable. It shall be supported in a stiff aluminium/stainless steel

detachable frame.

(b) Drain pans shall be made of plastics or reinforced glass fibre materials insulated with a minimum of 13

mm thick flexible closed cell elastomeric insulation. Drain pans shall be large and deep enough to

collect all condensate from the coil, return bends and pipework connections. The pan shall be removable

and have a slight fall to the drain connection to deal with the condensed moisture.

2.1.5 Controls

Fan coil units shall have a combined room temperature sensor completed with 3-speed controller and

cooling mode selector as specified.

2.1.6 Noise level

The noise data provided shall include an octave band analysis of the sound power level of each unit

when operating at its full or the stated design speed.

2.1.7 Remote control unit shall be provided as specified

2.2. CASSETTE TYPE FAN COIL UNITS

2.1.1 Generally, the cassette fan coil units shall comply with the requirements Clause of this Specification.

2.1.2 The fan coil unit shall be of integrated cassette type which combines the supply air slot, fan, casing and

cooling coil into a single unit.

2.1.3 Fan coil units shall be selected at design duty and specified noise level with fan running at medium

speed.

2.1.4 Remote control unit shall be provided as specified.

2.1.5 Cooling coil shall be constructed with copper tubes and shall be arranged horizontally. Tubes shall have

brazed copper return bends. Fins shall have smooth drawn collars of length equal to fin spacing and

mechanically bonded to tubes. Fins shall be of the plate type, corrugated to ensure maximum air contact.

Working pressure of coil shall be of a minimum of 1200 kPa and to suit system pressure design.

Connection of water piping shall be with flexible pipe connectors completed with union joints to

facilitate removal of the entire unit shall be provided. The connector shall be stainless steel braided

polymer tubing limited to 300 mm long and suitable for the system pressure.

2.1.6 Each fan coil unit shall be provided with a high grade AISI 316 stainless steel drain pan situated beneath

the cooling coil and arranged so that all moisture will collect in and drain from the pan. Drain pans

shall be insulated externally with a minimum of 25mm approved type foamed plastic. Each drain pan

shall be fitted with a drain pipe which shall be connected via suitable runs (correctly laid to fall) to the

drainage system. Drain pans shall have copper male connectors for connection to the condensate drain.

The connector shall be positioned to ensure rapid discharge of moisture from the pan.

2.1.7 Built-in condensate pump shall be provided for the removal of condensate. A water sensing system

with low, high and warning limits shall be provided which actuates the running of condensate pump at

high water limit and trigger the alarm system at warning level.

187

When water level reaches the warning limit, the sensing system shall cut off the unit operation.

Condensate pump shall be designed to run continuously. The power source for condensate pump and

the associated control system shall be independent from that of the fan coil unit such that the pump can

still be operated after the units have been switched off.

2.1.8 The air filter media shall be of the washable type.

2.1.9 Fan shall be of the quiet running direct driven centrifugal type with aluminium blades mounted to a

solid steel shaft. Fan motors shall be of the "split capacitor" type suitable for single phase electrical

supply.

The motor shall be resiliently mounted to the fan tray or scrolls. The motor/fan tray assembly itself

shall also be resiliently mounted to the casing structure.

2.1.10 Adjustable louvres for directional airflow shall be provided for supply air slot in each fan coil unit.

Options shall be given to choose from 4-way supply air discharge.

2.3 ENERGY EFFICIENCY AND PERFORMANCE

(a) The efficiency of fan and motor used for all air treatment equipment shall be in accordance with

Section detailed in this Specification and Fan System under the Code of Practice for Energy

Efficiency of Air Conditioning Installation issued by the Electrical & Mechanical Services

Department in the General Air Conditioning, Refrigeration and Ventilation specification manual as

certified

(b) The type of insulation used shall have optimized thermal conductivity, and the design of the

insulation thickness for pipe, drain pan, etc. of the air handling equipment shall be in accordance

with Section as detailed in this General Specification.

(c) The Contractor shall submit relevant factory test certificates and field test records for calculation

and assessment by the Project Architect/M&E Engineer

3 REFRIGERATION MACHINE

3.1 GENERAL

The refrigeration plant for air conditioning purposes shall generally be of the mechanical, vapour

compression type using environmental friendly refrigerants.

The refrigeration machine shall be factory assembled and tested complete "packaged" units which may

have rotary type compressors and as specified in the Particular Specification. The testing of the cooling

capacity of the refrigeration machine shall be carried out in accordance with BS EN 14511-1:2004 to

BS EN 14511-4:2004 or other international recognized standards.

The plant shall include any accessories necessary to ensure continuous and reliable operation.

Each unit shall be capable of running continuously at the lowest step of cooling capacity provided

without any adverse effect.

Compressor and motor speeds shall not exceed 50 revolutions per second for rotary type. Energy

efficient motor to optimize the system coefficient of performance shall be required. The noise level of

the refrigeration machine shall comply with the requirements as specified in the Particular Specification

or the relevant environmental protection ordinances whichever is more stringent.

Each compressor shall form a separate independent oil circuit with its own oil separator, oil filter and

positive lubrication oil safety control circuit equipped to ensure proper functioning of each compressor

and accessories.

188

All units shall comply, where applicable, with the following codes: ISO 5149:1993, ANSI ASHRAE

Standard 15 -2004; ARI Standard 550/590:2003 Testing and Ratings; BS EN 14511-1:2004 to BS EN

14511-4:2004 Testing and Ratings and Code of Practice for Electricity (Wiring) Regulations.

Characteristic curves shall show the energy consumption in kilowatts, pressure drop through the

evaporator, condenser fan speeds, etc., for each unit at 15%, 25%, 50%, 75% and 100% of full capacity.

Sound pressure level characteristic curves shall be in dB measured in accordance with ARI standard

575:1994 for 15%, 25%, 50%, 75% and 100% of full capacity.

3.2 COMPRESSORS, ROTARY TYPE

3.2.1 Rotary compressors will be acceptable where either:-

(a) The entire refrigeration system is completed and charged with refrigerant at the manufacturer’s

works; or

(b) The condensing unit incorporating the rotary compressor has a hold charge of refrigerant or

inert gas on arrival at site.

3.3 CONDENSERS, AIR-COOLED

4.3.1 Air cooled condensers shall have copper tubes with:-

- Aluminium fin coated with corrosion protection coating;

- Electro-tinned copper fins; or

- As otherwise indicated in the Particular Specification.

Corrosion protection coating of the condenser fins shall be applied in factory by the chiller

manufacturer. Fins with minor damage shall be combed straight. Units with extensive damage to fins

will not be accepted. Provision shall be made for the purging of non-condensable from the condenser.

3.3.2 Air cooled condensers mounted outside buildings shall have weatherproof fan motors. The units shall

discharge air vertically upwards.

3.3.3 Automatic control of the condensing pressure shall be incorporated.

Where modulation of air flow is by outlet dampers only, the fan motor shall be selected for this

application and arranged so that it is de-energized on complete closure of the dampers.

3.3.4 Fans shall comply with limitations on permitted noise levels where indicated in the Particular

Specification. Fans shall have sufficient static pressure to cater for the additional acoustic treatment

such as silencer, if any, in order to meet the noise requirements set out in Section C8 and the Particular

Specification.

3.3.5 The complete condenser coil shall be pressure tested at the manufacturer’s work.

3.4 REFRIGERANT PIPEWORK

3.4.1 Pipework for refrigerant systems shall be of copper or steel, which shall be internally degreased and

cleaned. Copper pipe shall be of refrigeration quality (i.e. material to BS EN 1057:2006).

3.4.2 For all chlorofluoro-methane or ethane compounds:-

(a) All pipes up to 18 mm OD shall be of fully annealed copper.

(b) All pipes from 22 mm to 108 mm OD shall be of hard drawn copper.

(c) All pipes over 108 mm OD shall be of black extra heavy seamless steel pipe to BS EN 10216-

1:2002 grade 1.0255.

(d) On fully packaged refrigeration machine, pipework other than copper, i.e. steel fitted and tested

in the factory as standard production for the units, will be acceptable subject to notification and

written approval by the Architect.

3.4.3 Size of Refrigerant Piping:-

189

Refrigerant piping shall be sized to avoid excessive pressure drop of the fluids or gases they carry. The

recommendations of the Chartered Institution of Building Services Engineers (UK) and/or the

American Society of Heating, Refrigerating and Air-conditioning Engineers/or other reputable/factory

standards approved by the Architect on the sizing of refrigerant piping shall be complied with.

4.0 ELECTRICAL/ELECTRONIC (LOCALISED) CONTROL SYSTEM

The systems shall be operated at single phase mains voltage or at extra low voltage such as 12 V or

24 V as indicated in the Particular Specification.

Where a particular manufacturer’s system is offered and accepted, the installation shall be installed to

comply with that manufacturer’s recommended technical details and methods of installation.

4.4.1 Standalone Direct Digital Controller (DDC) unless otherwise specified, the direct digital controller

shall have sufficient memory to support its own operating system.

(a) Each controller shall have sufficient memory to support its own operating system including:-

- Control Processes;

- Energy Management Applications;

- Alarm Management;

- Maintenance Support Applications;

- Operator I/O; and

- Manual Override Monitoring.

(b) Battery Backup

Battery shall be able to support programme

When the battery replacement is necessary, the open processor shall illuminate a "battery low"

status LED and replaced.

5 ELECTRIC MOTORS AND ELECTRICAL EQUIPMENT

5.1 LOW VOLTAGE - GENERAL

The mains for the low voltage electrical motors and equipment shall be suitable for a supply as specified

in Sections of the Specification.

Unless otherwise indicated, all electrical equipment shall be tropicalized and suitable for use in service

conditions as specified in Sections of the Specification. Equipment shall be protected against

atmospheric corrosion, including that caused by salt-laden air. Materials used shall not be susceptible

to mold growth or attack by vermin.

Cables for power circuits shall not be less than 2.5mm2 copper conductors and cables for control circuit

shall not be less than 1.5mm2 copper conductors.

5.2 LOW VOLTAGE - WIRING FOR REFRIGERATED SITUATIONS

All electric wiring to be installed into refrigerated situations where the temperature is to be maintained

at or below 0oC shall be either MICS or elastomeric cables that are applicable for the designed operating

environment.

5.3 LOW VOLTAGE - ELECTRIC EQUIPMENT The low voltage electric equipment shall comply with the relevant sections of the Electrical

Specification.

190

6 NOISE AND VIBRATION CONTROL

6.1 GENERAL

This section of the Specification intends to direct the Contractor to select the appropriate and sufficient

noise and vibration control measures on the plant/equipment, the interconnected piping, so that when

the installed plant/equipment are put into operation, the resulting noise and vibration levels at locations

within the building and at the adjacent or nearby buildings shall not exceed the acceptable limits as

promulgated by the statutory requirements of the Environmental Protection Department.

The Corrected Noise Level at potential Noise Sensitive Receiver in the adjacent or nearby building, if

so identified in the Particular Specification and/or Drawings, shall not exceed the Acceptable Noise

Level stipulated in the Technical Memorandum for the Assessment of Noise from Places other than

Domestic Premises, Public Places or Construction Sites issued by the Environmental Protection

Department when the plant/equipment installed by the Contractor are put into operation.

6.2 EQUIPMENT BASES

6.2.1 General

Floor mounted equipment shall be installed on 100mm high concrete housekeeping pads provided by

the building contractor covering the whole floor area requirements of the equipment bases plus a

minimum of 150 mm further on each side or on inverted beams at the roof.

Vibration isolators shall be mounted on this concrete pad or inverted beams.

6.2.2 Welded Structural Steel Bases

Bases shall be constructed of adequate "I" or channel hot dipped galvanized steel members reinforced

as required to prevent the bases from flexing at start-up and from misalignment of drive and driven

units.

All perimeter members shall be of steel sections with a minimum depth equal to 1/10th of the longest

dimension of the base but need not exceed 350 mm provided that the deflection and misalignment are

kept within acceptable limits as determined by the equipment manufacturer.

Height saving brackets shall be employed in all mounting locations to provide a base clearance of 50

mm.

6.2.3 Concrete Inertia Bases

Concrete inertia bases shall be formed within a structural steel beam or channel frame reinforced as

required to prevent flexing, misalignment of the drive and driven units or transferal of stresses into

equipment. The base shall be completed with height saving brackets, concrete reinforcement and

equipment bolting down provisions.

In general the thickness of concrete inertia bases shall be of a minimum of 1/12th of the longest

dimension of the base but never be less than 150 mm. The base depth needs not exceed 300 mm unless

specifically required.

As an indication of the standards required, minimum thickness of the inertia base shall generally

comply with the following table or be 1/12th of the longest dimension of the base, whichever is the

larger:-

Table .6.2.3 Minimum Thickness of Inertia Base

Motor Size (kW) Minimum Thickness

3.7 - 11 150 mm

15 - 37 200 mm

45 - 55 250 mm

Base forms shall include minimum concrete reinforcement consisting of 13 mm bars or angles welded

in place on 150 mm centers running both ways in a layer of 40 mm above the bottom, or additional

steel as is required by the structural conditions.

191

Unless otherwise specified, concrete inertia bases shall weigh from 2 to 3 times the combined weight

of the equipment/plant to be installed thereon.

Base forms shall be furnished with drilled steel members and with anchor-bolt sleeves welded below

the holes where the anchor bolts fall in concrete locations. Height saving brackets shall be provided in

all mounting locations to maintain a base clearance of 50 mm.

7 THERMAL INSULATION

7.1 GENERAL

7.1.1 Thermal insulation shall comply with the requirements of BS 5422:2001 and BS 5970:2001 or other

statutory standards such as IEC, ISO and etc. or equivalent.

7.1.2 Unless otherwise indicated, all thermal insulating materials used within any building shall, when tested

in accordance with BS 476-6:1989, BS 476-7:1997, BS 476-12:1991, shall comply with the following:-

(a) BS 476-12:1991: Ignitable T (Ignition Source A);

(b) BS 476-6:1989: Fire propagation I < 12, i1 < 6; and

(c) BS 476-7:1997: Surface spread of Flame Class 1 or comply with Clause C11.1.2 (a) as

mentioned above and conform to Class 'O' to UK Building Regulation 2000 certified by the

"Warrington Fire Test Laboratory" or approving organizations and standards recognized by the

Fire Services Department.

7.1.3 The insulation used for the air conditioning installation is "air" insulation which shall satisfy the

following:-

(a) Adequate strength and rigidity to maintain the thickness of air;

(b) Creating adequate number of closed air cells within the material to minimize heat loss due to

convection and conduction; and

(c) Covered on exposed surface with good quality foil to stop heat loss from radiation.

7.1.4 Insulation materials and their finishes shall be free from asbestos.

Where any work is carried out on existing insulation material or finish which contains asbestos in any

form the Contractor’s attention is drawn to the responsibilities under the provisions of the Asbestos

Regulations current in the Sierra Leone at the time of the works.

The Contractor shall also notify the Project Architect should the presence of asbestos be suspected.

7.1.5 Insulation materials and finishes shall be inherently proof against rotting, mold and fungal growth and

attack by vermin, be non-hygroscopic and in all respects be suitable for continuous use throughout the

range of operating temperatures and for the environment indicated.

7.1.6 The Contractor shall bear the cost and provide relevant certificates from an approved testing laboratory

in order to prove the physical properties of the insulation to be used in the project are conforming to

the specification.

7.2 TYPES OF THERMAL INSULATION MATERIALS

The type of insulation required for a particular installation will generally be indicated in the Particular

Specification. Where this is not so the Contractor shall include for the types described herein:-

7.2.1 Type "A" - CFC & HCFC Free Phenolic Foam Insulation

(a) Temperature range: sub-zero to 120°C;

(b) Density: 40 kg/m3;

Except at pipe and other support points where a higher density load bearing quality insulation shall

be used in accordance with the manufacturers’ recommendations. In general, phenolic foam

192

sections with 80 kg/m3 for pipe sizes of up to 125mm and 120 kg/m3 for pipe sizes of 150mm or

above and made to the same thickness as the adjacent pipe insulation;

(c) Compressive Strength: 140 kN/m2 (BS 4370-1:1988, method 3 or ISO 844:2004)

(d) Thermal Conductivity: 0.022 W/m°C at 20°C mean temperature (BS 4370-2:1993, method

7 or ISO 8302:1991);

(e) Closed Cell Content: 90% minimum (BS 4370-2:1993, method 10 or ISO 4590:2002);

(f) Vapour Transmission: 10 micron gram meter/Nh at 38°C 88% RH (BS 4370-2:1993, method 8

or ISO 1663:1999); and

(g) Fire Rating: shall have class "O" fire rating and test certificate

The above properties shall be tested independent of facings which shall be factory applied Class "O"

double sided reinforced foil vapour barrier for both condensation control and mechanical protection.

The external side shall be of white antiglare coating and the internal side shall be of aluminium foil

fully adhered to the phenolic foam. Facing with all service jackets on the outside is also acceptable.

The surface emittance of the all service jackets shall be 0.7 or greater when tested with ASTM E-408-

71:2002. In addition, the performance of both vapour barriers and all service jackets shall comply with

the requirement stipulated at Clause C11.4.2.

The manufacturer shall provide proof if required by the Architect, that the above properties of the

material supplied remains constant or are stable enough throughout the working life.

7.2.2 Type "B" - Flexible Closed Cell Elastomeric Insulation

Flexible closed Cell Elastomeric Insulation shall be CFC free, in continuous lengths, with factory

applied talc coating on inner surface.

Flexible Closed Cell Elastomeric Insulation shall comply with the following requirements:-

(a) Thermal Conductivity (at 20oC mean temperature): <0.04 W/moC;

(b) Density: 65 kg/m3 ±5%;

(c) Water Vapour Permeability (without additional vapour barrier foil): 0.28 micron gram meter/Nh;

(d) Maximum Operating Temperature: > 80oC;

(e) No putrefaction and mildew shall form on the insulation material. The water absorption properties

of the insulation shall be of not more than 1.5% after 28 days;

(f) The material, including adhesives and all accessories shall have fire properties to Class 'O' comply

with the requirements of the Building Regulation in UK. The insulation material shall be a "built-

in" vapour barrier and achieve condensation control without any additional vapour barrier foil;

(g) Smoke Visibility (ISO 5659-2:2006); and

The mean specific optical density, Dm shall be less than 500 under all test conditions. The

thickness of the test specimen shall be 25 mm and the Dm shall be the maximum value of the

specific optical density (Ds10) of the three tests computed at 10 minutes time interval.

(h) Smoke Toxicity:

The results shall comply and in accordance with either of the following standards or equivalent:-

- International Maritime Organization (IMO) – International Code for Application of Fire Test

Procedure: Part 2 – Smoke and Toxicity Test, IMO MSC 61(67); or

- Naval Engineering Specification (NES) 713 (Issue 3) – Determination of the Toxicity Index of the

Products of Combustion from Small Specimens of Material

193

7.3 INSULATION THICKNESSES

7.3.1 Refrigerant Pipe

All refrigerant pipes except pipes on high pressure side of refrigeration cycle should be insulated with

minimum insulation thickness in accordance with Table C11.5.2-(1), C11.5.2-(2) or C11.5.2-(3).

Table 7.3.1 – (1): Minimum Insulation Thickness for Indoor Refrigerant Pipe (Case 1)

Minimum Thickness of Insulation for Refrigerant Pipe Installations (mm)

Indoor Condition at 28oC, 80% RH; still air; h(3) = 10

Fluid Operating Temperature

Outer Diameter of Pipe(mm)(1) 0oC -10oC -20oC

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

0.02 0.03 0.04 0.02 0.03 0.04 0.02 0.03 0.04

6 8 10 13 10 13 16 12 16 20

8 8 11 14 10 14 18 13 17 21

10 8 11 14 11 15 18 13 18 22

12 9 12 15 11 15 19 14 19 23

15 9 12 15 13 16 20 14 20 25

22 10 13 17 13 18 22 16 22 27

28 10 14 18 13 18 23 16 28

35 10 15 18 14 19 24 17 23 29

42 11 15 19 14 20 25 18 24 30

Note: (i) The above table assumes pipes to be copper pipe of BS EN 1057:2006.

For other metal pipes, same insulation thickness is applied to comparable outer diameters.

(2) The insulation thickness in above table is based on thermal conductivity rated at 20oC mean.

(3) The surface coefficient, h = 10 is assumed for cement or black matt surfaces at indoor still air

condition.

Table 7.3.2 – (2): Minimum Insulation Thickness for Indoor Refrigerant Pipe (Case 2)

Minimum Thickness of Insulation for Refrigerant Pipe Installations (mm)

Indoor Condition at 30oC, 95% RH; still air; h(3) = 10

Fluid Operating Temperature

Outer Diameter of Pipe(mm) (1) 0oC -10oC -20oC

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

0.02 0.03 0.04 0.02 0.03 0.04 0.02 0.03 0.04

6 26 36 44 33 45 56 39 53 67

8 28 38 47 35 48 60 42 57 71

10 29 40 50 37 50 62 44 60 75

12 31 42 52 38 52 65 45 62 78

15 32 44 54 40 55 68 48 65 81

22 35 48 59 44 60 74 52 71 89

28 37 50 63 46 63 79 55 75 94

35 39 53 66 49 66 83 58 79 99

Note: (1) The above table assumes pipes to be copper pipe of BS EN 1057:2006.

For other metal pipes, same insulation thickness is applied to comparable outer diameters.

(2) The insulation thickness in above table is based on thermal conductivity rated at 20oC mean.

(3) The surface coefficient h = 10 is assumed for cement or black matt surfaces at indoor still air

condition.

194

Table 7.3.3 – (3): Minimum Insulation Thickness for Outdoor Refrigerant Pipe

Minimum Thickness of Insulation for Refrigerant Pipe Installations (mm)

Outdoor Condition at 35oC, 95% RH; wind speed = 1 m/s; h(3) = 13.5

Outer Diameter of Pipe(mm)(1) Fluid Operating Temperature

0oC -10oC -20oC

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

Thermal

Conductivity(2)

λ

0.02 0.03 0.04 0.02 0.03 0.04 0.02 0.03 0.04

6 23 32 40 29 39 49 33 46 57

8 25 34 42 30 41 52 36 49 61

10 26 36 45 32 44 54 38 51 64

12 27 37 46 33 45 57 39 53 66

15 29 39 49 35 48 59 41 56 70

22 31 43 53 38 52 65 45 61 76 76

28 33 45 56 40 55 69 48 64 80

35 35 48 59 42 58 72 50 68 85

Note: (1) The above table assumes pipes to be copper pipe of BS EN 1057:2006.

For other metal pipes, same insulation thickness is applied to comparable outer diameters.

(2) The insulation thickness in above table is based on thermal conductivity rated at 20oC mean.

(3) The surface coefficient h = 13.5 is assumed for cement or black matt surfaces at outdoor

condition with a wind speed of 1 m/s.

195

8 UNITARY AIR-CONDITIONER

8.1 GENERAL

Unitary air-conditioners shall include:-

(a) Inverter Condensing unit and Single split Wall Mounted fan coil units;

(b) Condensing unit with variable refrigerant volume (VRV) control and In-Ceiling Mounted

Cassette indoor fan coil units;

Unitary air-conditioners shall be factory fabricated and assembled. The equipment shall be rated and

tested in the same country of manufacture and meet with the requirements of the International

Organization for Standardization (ISO) Standards 5151:1994 (non-ducted air-conditioners and heat

pumps) or 13253:1995 or other internationally recognized quality assurance standards approved by the

Project Architect.

The most energy efficient model in the series shall be selected for submission and shall be referred to

Sections in Clause this Specification.

8.1.1 Equipment Suitable for Local Electricity Supply

Unless otherwise specified, the electrical equipment’s of the unitary air-conditioners shall be suitable

for use with 3-phase and neutral, 4-wire, 400/230 V, 50 Hz source for neutral earthed system with

provision of bonding.

8.1.2 Selection of Air-Cooled Condensers and Condensing Units

Air-cooled condensers and condensing units of unitary air-conditioners shall be selected to give rated

capacity with condensing temperature not exceeding 50°C for the ambient condition as specified

under Clause 3.11 of this Specification.

8.1.3 Casing

Casings of unitary air-conditioners shall be constructed of rigid galvanized sheet steel and painted in

accordance with Part G, suitably reinforced with channels and sections to form a robust cabinet.

Casing for outdoor installation shall be of weatherproof finish, preferably galvanized, painted or

anodized aluminium.

8.1.4 Compressor

Compressors shall be rotary of the hermetically sealed type. Compressor shall be complete with

internal motor protection, positive lubrication, mufflers, crankcase heater, and internal and external

vibration isolation.

8.1.5 Supply Air Fan and Motor

Supply air fans shall be of the double width, double inlet, centrifugal type of ample sized for operation

against the specified static pressure. Fan motors shall be permanently lubricated and have adequate

power so as to be non-overloading throughout the range of the fan characteristic. The motor shall be

high efficiency motor.

8.1.6 Cooling Coils

Cooling coils shall be of the direct expansion type and constructed with copper tubes and aluminium

fins to give high heat transfer performance. The coils shall have sufficient number of rows of tubes

to provide efficient dehumidification of the air in addition to its cooling.

Heating coil shall be constructed with copper tubes and aluminium fins to give high heat transfer

performance.

196

8.1.7 Air Filter

Air filters shall unless otherwise specified be of the washable panel type. The filter performance shall

be referred to Clause 1. Higher filter efficiency shall be adopted to meet with the IAQ objective

designed.

8.1.8 Air-Cooled Condensers

Air-cooled condensers shall unless otherwise specified be suitable for outdoor installation with ample

capacity to dispose of the rejected heat from the air conditioning system. Condenser coils shall be

constructed with copper tube and aluminium fins. Special corrosion resistant treatment for the

condenser coils and fins shall be considered for the equipment to be located on corrosive environment.

8.1.9 Refrigerant Piping

External refrigerant piping shall include all necessary fitting and amerflex insulation. Size of the

refrigerant pipe and fittings shall be in accordance with the recommended standards as stated in this

Specification

8.1.10 Condensate Drain Pipe

Condensate drain pipe shall be PVC and adequately insulated and mechanical protected in accordance

with the recommended standards as stated in this Specification

8.1.11 Safety Control

Controls shall be factory wired. Field wiring in conduit or trunking shall be limited to

interconnections between separate pieces of equipment and power wiring. Each unit shall be protected

and controlled by a factory built control panel incorporating all necessary devices, switches, indicator,

etc. Functions required shall include those such as interlock with lubricating oil pump and other

auxiliary components for unit starting, control circuit for compressor stop with pump down and

crankcase heaters, automatic unloading, isolating switches and emergency stop facilities.

Safety protections shall include low lubricating oil pressure cut-out, low evaporating pressure cut-

out, high condensing pressure cut-out, low refrigerant temperature cut-out, high motor coil

temperature cut-out and other protections necessary for the proper and safe operation of the unit.

Overload and motor burnout protections shall be provided as well.

8.1.12 Operational Control

For a conventional split type A/C unit, a wired or wireless remote controller shall be provided for the

selection of room temperature setting, fan speed and timer setting. For an advance multi-zone modular

split type, the remote controller shall be of the liquid crystal display (LCD) type with an on-off switch

for operational features such as speed selection, timer setting, temperature setting, self-diagnosis

function and auto restart function.

8.1.13 Split Condensing Unit and AHU

The condensing unit shall include rotary compressors, air-cooled condensing coils, fans and motors

control and safety devices, piping and all necessary accessories factory assembled in a weatherproof

painted G.I. casing. The refrigerant circuit shall be field connected to the matched AHU or fan coil

units each completed with direct expansion cooling coil, expansion valve, blower with motor and the

necessary number of air filters in a well-insulated, sturdy G.I. metal casing with paint to an attractive

appearance.

8.1.14 Variable Refrigerant Volume System

The air conditioning system shall be of the multi-zone modular split type. Each zone shall consist of

one air-cooled outdoor condensing unit connected to a group of indoor fan coil units in one single

refrigerant circuit. The outdoor unit shall not comprise more than three compressors. For multi

compressors outdoor unit, one shall be inverter control compressor. The inverter compressor shall be

197

incorporated with a frequency inverter control to achieve the optimum flow of refrigerant in response

to the actual load.

The multi-zone modular split type unit shall be provided with heating (Heat Recovery) and cooling

output simultaneously.

8.1.15 Energy Efficiency Performance

All unitary air conditioners shall be selected aiming for the highest operation efficiency. The

minimum Coefficient of Performance (COP) for Air-Cooled Unitary Air Conditioner and Water-

Cooled Unitary Air Conditioner excluding room coolers shall be as shown in the Tables below:-

Table 8.1.15(a): Minimum COP for Air-Cooled Unitary Air Conditioner

Capacity Range

(kW)

Above 10

and

Below 40

40 to 200

Minimum COP (Cooling Mode) 2.4 2.4

3 for VRV 2.9 for VRV

Minimum COP Heat Pump

(Heating Mode)

2.7

2.8

VRV: Air Conditioner with capacity control through variation of refrigerant volume flow

8.1.16 Energy Efficiency and Energy Conservation

All equipment provided by the Contractor for the air conditioning installation shall conform to the

highest efficient rating of energy efficiency and energy conservation requirement as stipulated in this

Specification, and/or the Codes of Practice for Energy Efficiency of Air Conditioning Installations

and of Electrical Installations issued by Electrical and Mechanical Services Department.

In case of any non-compliance, the Contractor shall submit full justification with technical data

supporting the deviation from the requirements as specified in this Specification and the Codes of

Practice for Energy Efficiency of Air Conditioning Installations and Electrical Installations issued by

Electrical and Mechanical Services Department.

D INSPECTION, TESTING AND COMMISSIONING

1.1 GENERAL

Throughout the execution of the installation, the Contractor shall be responsible for ensuring

compliance with the Regulations included in clause 2 and shall notify the Project Architect of any

infringement which directly or indirectly detracts from the safe and satisfactory operation of the

installation(s) whether or not such infringement relates to the works covered in the Contract or to those

associated with others.

1.12 Standards and requirements for the testing and commissioning works are listed should be in accordance

to:-

(a) Statutory Obligations and other requirements, Specifications and Standards specified in this

Specification;

(b) Building Services Branch Testing and Commissioning Procedure for Air-conditioning,

Refrigeration, Ventilation & Control System Installation

(c) Manufacturers’ recommendations and specifications.

198

1.1,3 The Contractor is required to appoint a competent and experienced testing and commissioning engineer

responsible for the overall planning, organizing, coordinating, supervising and monitoring of the testing

and commissioning works and also certifying all results and reports from the testing and commissioning

works. The Contractor shall submit, at the commencement of the Contract, information detailing

qualification and experience of the testing and commissioning engineer for the Project Architect’s

approval.

1.1.4 It is necessary to require the Contractor to provide, at no cost to the Employer, all necessary equipment,

apparatus, tools and materials for carrying out of testing and commissioning works.

(a) Master Programmed of Testing and Commissioning Works

The Contractor is required to submit a programme for testing and commissioning works shall be

submitted at the commencement of the Contract, usually within the first three months. The

programme shall indicate the tentative dates of all tests and commissioning works that will be

carried out throughout the whole contract and all necessary submissions and approval relating to

testing and commissioning and ensure that the testing and commissioning programme matches the

master programme for construction and that all testing and commissioning works are complete

before the completion date of the Contract.

(b) Inspection, Testing and Commissioning Methods and Procedures

The Contractor is required to submit detailed inspection, testing and commissioning methods and

procedures together with report formats for reporting inspection, testing and commissioning results

for the Project Architect’s approval at least three months before commencement of testing and

commissioning works, or four months after the commencement of the Contract, whichever is

earlier.

(c) Labor and Materials

The Contractor is required to be responsible for provision of all labour and both consumable and

non-consumable materials for carrying out testing and commissioning works at their expenses.

Electricity supply, water and LP gas and town gas for carrying out of testing and commissioning

works shall also be arranged and provided by the Contractor at no cost to the Employer.

(d) Supply of Inspection, Measuring and Testing Equipment

The Contractor is required to supply the calibrated equipment and instrument for testing and

commissioning works in accordance with the requirements as specified in the Particular

Specification.

(e) Readiness for Commissioning and Testing

The Contractor is required to check the completion of the works to be tested or commissioned,

the associated builder’s works and the associated building services installations to ensure that

testing and commissioning can be preceded in a safe and satisfactory manner without obstruction.

(f) "Type-test" Certificate

"Type-test" for equipment shall be carried out at the manufacturers’ works or elsewhere

appropriate in order to demonstrate their compliance with the Regulation or requirements. "Type-

test" certificates together with the corresponding drawings, sketches, reports and any other

necessary documents shall be submitted to the Project Architect for approval before delivery of

the equipment.

1.1.5 The Contractor is required to provide advanced notice for inspection, testing and commissioning works

as follows:-

(a) Off-site Inspection and Testing

An advanced notice of at least one week before commencement of the inspection or test shall be

provided.

199

(b) On-site Inspection, Testing and Commissioning

An advanced notice of at least 4 calendar days before commencement of inspection, testing or

commissioning shall be provided.

1.1.6 Documentation and Deliverables

The Contractor shall record all commissioning information and testing results at the witness of the

Project Architect or his representatives.

Commissioning and testing record shall be properly checked and certified by contractor‘s Testing and

Commissioning Engineer and signed by the Project Architect or his representative who has witnessed

the testing or commissioning before submission to the Project Architect. The Contractor shall submit

full commissioning and testing report to the Project Architect within 14 calendar days after completion

of commissioning and testing of the installation.

1.2 TESTING AND COMMISSIONING – DEFINITIONS

For the purpose of this General Specification the following definitions shall apply:-

1.2.1 Commissioning:

The advancement of an installation from the stage of static completion to full working conditions to

meet the specified requirements. This will include setting into operation and regulation of the

installation.

1.2.2 Setting to work:

The process of setting a static system into motion

1.2.3 Off-site Tests:

Tests carried out on items of equipment at manufacturer’s works or elsewhere to ensure compliance

with the requirements of Specifications and/or relevant Standards or Codes of Practice (or other

standards specified).

1.2.4 Site Tests:

Tests on static plant and systems (e.g. inspection and testing of welds, hydraulic testing of pipe work,

etc.) to ensure correct and safe installation and operation

1.2.5 Regulation:

The process of adjusting the rates of fluid flow and heat transfer in a distribution system within specified

tolerances as stated in the relevant CIBSE Commissioning Code.

1.2.6 Performance Testing:

The measuring and recording of the performance of the commissioned installation

1.3 TESTING AND COMMISSIONING – GENERAL

1.3.1 Any defects of workmanship, materials and performance, maladjustments or other irregularities which

become apparent during commissioning or testing shall be rectified by the Contractor at no cost to the

Employer and the relevant part of the commissioning or testing procedure shall be repeated at the

Contractor’s expenses.

1.3.2 The entire testing and commissioning procedure shall be undertaken by the Contractor’s own competent

specialist staff or by a competent Independent Commissioning Specialist nominated by and acting for

the Contractor and approved by the Project Architect.

1.3.3 Where specified in the Particular Specification, the Contractor shall nominate a competent independent

Specialist to conduct commissioning work.

200

1.3.4 Where specified in the Particular Specification, the Contractor shall employ an approved specialist

testing and commissioning firm who shall be named in the returned Tender Documents.

1.3.5 At the appropriate time in the Contract, usually within the first two months, the Contractor shall furnish

the Provisional Testing and Commissioning Programme, methods, procedures and formats of test

records to the Project Architect. This shall be updated as the work progresses towards completion.

1.3.6 Unless otherwise indicated, all electricity, main water and other fuels, such as town gas, necessary for

the operation of the plant during preliminary runs and for full adjustments and commissioning tests will

be provided at no cost by the Contractor unless otherwise specified in the Contract.

1.3.7 If considered appropriate, the Contractor shall be required to carry out demonstration to dismantle those

parts/components of the installation which are considered difficult/impossible for maintenance access.

The Contractor shall be responsible for carrying out all necessary modification work at no extra charge

to the Employer to alleviate the difficulties associated with dismantling or maintenance access.

1.4 OFF-SITE TESTS

Where the specified Standards or Codes of Practice stipulate, "type-tests" on items of equipment to

demonstrate compliance shall be carried out at the manufacturer’s works or elsewhere as appropriate.

In all cases, "type-tests" Certificates shall be submitted in duplicate to the Project Architect. Cases

where appropriate, "type-tests" Certificates will be accepted are as follows:-

1.4.1 Fans:

"type-tests" Certificates showing fan characteristic curves (ISO 5801:1997), "type-tests" Certificates

for sound power levels (ISO 5136:2003), fan dynamic balancing test Certificates completed with a

method of statement from manufacturer on testing to Grade 2.5, 4 & 6.3 on appropriate fan types in

accordance with ISO 1940-1:2003 and ISO 1940-2:1997.

1.4.2 Pumps:

"type-tests" Certificates for head, discharge, speed and power input (BS EN ISO 9906:2000 as

appropriate).

1.4.3 Electric motors:

"type-tests" Certificates in accordance with BS EN 60034-1:2004 and/or IEC 60072-1:1991, IEC

60072-2:1990 & IEC 60072-3:1994.

1.4.4 Low voltage starter switchgear and control gear assembly:

"Type-tests" Certificates for starter (e.g. auto-transformer) and control panels assembly as a whole in

accordance with BS EN 60439-1:1999.

1.5 SITE TESTS

F1.5.1 The Contractor shall carry out "on-site" tests in respect of all static systems to ensure safe and proper

operation as conforming to the design intent. Such tests shall include test of welds and pressure tests

on the hydraulic systems.

1.5.2 On completion of cleaning operations described in the T&C Procedure for Air-conditioning,

Refrigeration, Ventilation and Control Systems Installation, each installed unit shall be re-charged and

then subjected to gas pressure test as required.

Any items of equipment set to operate at or below the test pressure shall be isolated or removed prior

to applying this test.

201

1.6 INSPECTION AND TESTING DURING CONSTRUCTION PERIOD

1.6.1 Periodic Site Tests

Site inspections of "work in progress" will be made by the Project Architect/M&E Engineer or the

representative from time to time. The Contractor shall keep such inspection record for checking from

time to time. Works to be permanently covered up shall be subjected to inspection and test before cover

up. During the inspection, if the Project Architect/M&E Engineer discovers any work that has been

covered up before inspection and testing, this work shall be uncovered for inspection and testing to the

Project Architect’s/M&E Engineer’s satisfaction. The cost involved in uncovering the work, inspecting,

testing and re-concealing the work together with any consequential losses shall be paid by the

Contractor at no additional cost to the Employer.

1.6.2 Tests at Works yard

The Contractor shall note that the Project Architect/M&E Engineer may require witnessing tests and

inspections of locally and manufactured equipment during construction at the contractor’s works yard.

Where this requirement is indicated in the Contract Documents, the Contractor shall allow for making

the necessary arrangements; including and indicating the Project Architect’s /M&E Engineer’s time

and subsistence expenses in the Bill of Quantities.

1.6.3 Factory Test Certificates

Certificates of all unit pressure and other manufacturers" tests carried out at the manufacturers" works

shall be forwarded in duplicate to the Project Architect for approval. This approval shall normally be

required before the materials or apparatus are dispatched from the manufacturer’s works.

Where specified, the Contractor shall subject certain materials and equipment to be tested by the

recognized institutions or laboratories and submit the type test certificates to the Project Architect for

approval.

1.7 DOCUMENTS AND DATA REQUIRED FOR HAND-OVER MEETING

1.7.1 General

The Contractor shall note that the system cannot be handed over until all the foregoing requirements

(where applicable) have been carried out to the satisfaction of the Project Architect.

1.7.2 Test Certificates

Before the handover inspection, the Contractor shall provide the follow test/record certificates where

applicable:-

(a) Copies of manufacturer’s works tests/record certificates on plant items comprising air

conditioning units including motors, fans, pumps, etc.;

(b) Copies of pressure test/record certificates for works carried out on site;

(c) Copies of refrigeration plant efficiency test/record certificates;

(d) Copies of all performance test/record certificates including room conditions, etc. These

certificates shall be accompanied with all appropriate charts and diagrams; and

(e) Copies of all noise test/survey records on every noise emitting plant and machineries, individual

room/space and a statement of compliance with the statutory requirements under the current Noise

Control Ordinance.

1.7.3 "As-built" Drawings

All necessary copies of "As-built" drawings as detailed in the Contract Documents and this

Specification. (*settings of all the sensors are to be indicated)

1.7.4 Operation Maintenance and Services Manuals

All necessary copies of Operating and Maintenance Manuals as detailed in the Contract Documents

and this Specification.

The Contractor shall include functional spare parts and contact lists of the suppliers in the manual.

(*settings of all the sensors are to be indicated)

202

1.7.5 Manufacturer’s Name Plate

Every item of plant supplied by a manufacturer shall be fitted with a clearly engraved, stamped or cast

manufacturer’s name plate properly secured to the plant item and showing:-

- Manufacturer’s Name;

- Serial and/or Model No.;

- Date of Supply;

- Rating/Capacity; and

- Test and Working Pressure (where applicable)

1.8 TESTING AND COMMISSIONING PROCEDURES

For Testing and Commissioning Procedures, please refer to:-

Testing and Commissioning Procedure for Air-Conditioning, Refrigeration Ventilation and Control

System Installation as specified and detailed in the latest editions of the American Society of Heating,

Refrigerating and Air-conditioning Engineers, Inc. (ASHRAE) and the Heating and Ventilation

Contractor Association, U.K (HVCA)

203

E OPERATION AND MAINTENANCE

1.1 GENERAL

The Contractor shall provide all the Level One Services as specified in this Specification for all

installation works.

Level Two Services detailed in this Specification shall only be carried out if specified in the Particular

Specification of the Contract. The specified Level Two maintenance responsibilities shall be priced

separately in the tender with cost for each individual item.

1.2 LEVEL ONE SERVICES – MANDATORY RESPONSIBILITIES DURING MAINTENANCE

PERIOD

1.2.1 Requirement for Training

Training and familiarization for the operation and maintenance of sophisticated equipment shall be

provided and arranged by the Contractor. The training shall include all training facilities, material and

handouts, etc. The Contractor shall submit a "Training Schedule" at least two months prior to

completion of installation for the Project Architect’s Approval. The schedule shall consist of the

following requirements:-

(a) General Requirement

(i) The Contractor shall provide facilities and training programme to ensure that the Employer’s

operation and maintenance staff acquire full knowledge and operation, breakdown and routine

maintenance, diagnosis and hence operate and maintain reasonably effectively and efficiently

the system/equipment including Control and Monitoring System offered. The training proposal

shall be submitted at least two months prior to completion of the Contract and shall include all

aspects of operation and maintenance of the plant including the use of special tools. Besides,

equipment portfolio for Air-Conditioning, Refrigeration, Ventilation and Control System

offered shall be submitted together with the training proposal. The equipment portfolio shall

include quantity of equipment, equipment cost, recommended serviceable life by the

manufacturer and cycle of major overhaul;

(ii) A training proposal together with a detailed breakdown unit price for such service shall be

submitted at the time of tendering;

(iii) The training proposal shall also include details and duration of the training course(s),

qualifications of the instructor and the qualification requirements for the trainee(s);

(iv) Whenever possible, the training courses shall be held before or during the commissioning period

and shall be in Freetown.

Within two months after award of the Contract, the Contractor shall submit full details of the

training syllabus for approval of the Project Architect;

(v) To reach the required depth of appreciation, the principles and theory and practical "hands-on"

demonstration shall be lectured; and

(vi) The operation and maintenance training of the Indoor Air Quality (IAQ) equipment shall also

be included in the training programme. Any manual for the IAQ equipment shall be prepared

by qualified personnel.

(b) Particular Requirement

The training course shall contain, but not limited to, the following:-

(i) General description of the system and its associated equipment as a whole;

(ii) Start-up and shut-down procedures;

(iii) Safety precautions during start-up and shut-down;

(iv) A detailed description of the functions of all switches and indicators on control console;

(v) Trouble shooting procedures;

(vi) Preventive and corrective maintenance requirements to ensure proper operation of a system or

equipment under the maintenance programme;

(vii) Identification of all the operating parameters which affects the performance of the plant;

(viii) Adjustment of the operating parameters to achieve optimum operating conditions;

(ix) Check-list of all the periodic inspection and servicing of the plant;

(x) Illustration of the construction of major components of the plant by sectional views;

204

(xi) Dismantling and reassembling procedures during a major repair;

(xii) The use of special tools;

(xiii) Calibration for testing equipment, measurement, record and performance assessment; and

(ix) Any other items as found necessary.

1.2.2 Requirement during Maintenance Period

The Contractor shall be fully responsible for the following within the maintenance period:-

(a) Instruction to Employer’s Operation and Maintenance Staff

After the installation has been successfully handed over and put into operation, the Contractor

shall provide full time attendance for a period of at least 20 consecutive days or as stated in the

Specifications, by a qualified operator(s) who shall be fully conversant with the operation and

maintenance of the equipment. Their duties shall be to operate the systems and to guide and

instruct the Employer’s Operation Staff such that they will become fully conversant with the

operation of the complete air conditioning installation.

Note: This commitment shall be carried out where the operational responsibilities are to be

immediately transferred to the Employer’s own staff or at the end of Levels Two Service

operational arrangements.

(b) Completion of Any Outstanding Work

Within one month of receiving the Project Architect’s substantial completion certificate, the

Contractor shall complete all minor outstanding works listed thereon and rectify any defects

that have arisen up to that time.

(c) Faults and Complaints

The Contractor shall attend to faults and complaints arising from defective work materials

and/or system operation within one hour at any time during the maintenance period.

The Contractor shall also be responsible for attending emergency calls and rectifying all defects

leading to fault or breakdown of the equipment and/or system within reasonable time or

specified. The Contractor shall keep records of all the faults/breakdowns calls for submission

to the Project Architect. The costs for the attendance, labour, materials and spare parts for repair,

submission of fault/breakdown reports, etc. are deemed to have been allowed for in the

submitted tender price.

(d) Inspection during Maintenance Period

The Contractor shall, in addition to the periodic visits as stipulated in the Conditions of Contract,

make further working visit to the site one month before the end of the maintenance period to

check and, if necessary, re-adjust the systems to meet the actual operation conditions.

(e) Joint inspection at the end of Maintenance Period

The Contractor shall include for making visit(s) to the installation at the end of the maintenance

period in order to facilitate the acceptance and handing over of the installation to the Employer’s

Representatives.

Note (1): If the installation is proved to be unacceptable by the Project Architect, (d) and (e) may

have to be repeated at the Contractor’s expenses and with the effect of extending the

contractual defect liability period.

Note (2): When the installation is accepted and handed over to the Employer’s authorized

representative(s) at the end of maintenance period, the maintenance certificate will then

be issued by the Project Architect.

205

(f) Servicing, Replacement and Replenishment

During the maintenance period, the Contractor shall supply and install, without additional

charge to the Employer, replacements for all and any equipment or parts thereof or liquids or

gases, which may, in the opinion of the Project Architect, became unserviceable, especially

where the causes are attributable to faulty materials, workmanship, or inadequate performance.

The liability of the Contractor shall cover replacement of liquids or gases, oils and refrigerant

which may be lost by leakage or become contaminated or in other respects unserviceable.

(g) Record "Log Book"

For all Contract works under the maintenance period or ongoing Contract Maintenance, the

Contractor shall have maintenance staff complete the site/installation record "Log-Book" after

each visit/installation. The Log-Book may be completed in English. The Log-Book will be

supplied by the Contractor and kept in the Bank or location as agreed. Every attendance and

details of work done for the installation shall be entered into the Log-Book so as to form a

comprehensive maintenance record.

(h) Project Architect to be informed

No replacement of plant or parts of plant shall be carried out at any time unless the Project

Architect has previously been notified and approved.

(i) Annual inspection and submission of maintenance certificate

During the end of the maintenance period, the Contractor shall carry out and submit the annual

inspection and submission of maintenance certificate for the ventilation system as required

under Building (Ventilation Systems) Regulations to the ADB Resident Representative and the

Project Architect of the completed installation.

I.3 LEVEL TWO SERVICES – SPECIFIED CONTRACTOR’S MAINTENANCE

RESPONSIBILITIES DURING MAINTENANCE PERIOD

Where specifically required in the Contract Documents, the Contractor shall allow for and carry out

full and comprehensive maintenance of the installation for 12 months (or for a period as stated). The

works shall in addition to those required under the LEVEL ONE SERVICE include also the

followings:-

1.3.1 The Contractor shall be fully responsible for the following within the maintenance period:-

(a) Inspection, checking, servicing, maintenance and repair including replacement of parts and

components due to normal tears and wears;

(b) Emergency inspection, checking and servicing, repair and rectification work;

(c) Provide skilled craftsmen to assistant the start-up, control, performance monitoring and shut-

down of the plant;

(d) Test and commissioning of the installation after the completion of services, maintenance and

repair; and

(e) Submission of services record and test report.

1.3.2 The Contractor shall provide labour, minor spare parts, components and consumable materials in the

following services during the maintenance period:-

(a) Consumable materials such as re-filling of refrigerant and lubricant, renewal of for blower

motor as and when required/necessary;

(b) All cutting and waste, packing, carriage, risk, moving, hoisting and fixing at the required

position;

(c) Repairs including first line attendance, emergency and miscellaneous repairs, plants, tools,

vehicles for transportation of material for purposes of execution of work; and

(d) Preparation and submission of records/reports, compliance with miscellaneous requirements.

Upon practical completion of the construction work is certified by the Project Architect, the

Contractor shall provide competent, experienced and qualified staff and workshop facilities to

undertake the Level Two maintenance works during the maintenance period. Detailed

206

information of the organization, workshop facilities and list of contact persons of the

Contractor’s maintenance team shall be submitted to the Project Architect one month before the

commencement date of the maintenance period.

1.3.3 Contractor’s Responsibilities for Breakdown Call-out

(a) The Contractor shall offer efficient and prompt response to breakdown call-out for the

installation/equipment failure.

The expedition of response shall be in accordance with the following categories:-

(i) VERY URGENT for installation breakdown including failure of compressor, pipe burst, water

dripping, fire alarm and electricity power failure, the Contractor shall respond and attend to the

Very Urgent calls immediately of not more than 30 minutes;

(ii) URGENT for abnormality of equipment operation, the Contractor shall respond and attend to

the Urgent calls within 1 hour from the receipt of the calls; or

(iii) NON URGENT for inadequate of room condition, the Contractor shall respond and attend the

fault within 4 hours.

Investigation report and proposal for repair/improvement/modification shall be submitted.

(b) The Contractor shall promptly complete any repair necessary for resuming the breakdown installation.

In case immediate permanent repair is not possible due to safety related reason, the following "time for

repair" targets counted from the receipt of breakdown or fault call shall be complied with:-

(i) Complete temporary repair for resumption of the suspended or breakdown services to a safe

operating condition within 24 hours; and

(ii) Complete permanent rectification works within 3 and 7 working days unless long component

and parts delivery time is required.

1.3.4 Maintenance Programme and Schedule

The Contractor shall prepare, submit and seek endorsement on the maintenance program before the

commencement of the Contract maintenance period. The maintenance programme should include

Monthly Routine Service, Half-Yearly Service and Annual Maintenance.

Upon the approval of the above maintenance program, the Contractor shall prepare a comprehensive

maintenance schedule for all installations and indicate dates for routine maintenance of the installations

before the commencement of the Contract maintenance period.

1.3.5 Co-ordination

The Contractor shall co-operate and co-ordinate with the Project Architect’s Representatives, user

department for the smooth execution of maintenance works.

1.3.6 Plant Log and Breakdown/Fault Call Report

The Contractor shall submit daily record of the following documentation and reports at three months

intervals:-

(a) Record of current status of plant and major equipment, all services, maintenance and

repair/replacement carried out for the plant and equipment including the following details:-

(i) Refrigerant pressure gauge readings;

(ii) Refrigerant compressor suction and discharge pressure;

(iii) Dry and wet bulb temperature of supply air at designed offices, meeting and conference rooms

and that of return air at system return and outdoor air condition; and

(iv) IAQ audit report with monthly measurements of all IAQ parameters.

207

(b) Equipment Breakdown Report

Equipment breakdown report shall be submitted after the rectification work and shall have full

details of findings during investigation/examination on cause of breakdown, account of

repair/replacement work needed, suggested precaution and/or action required to prevent the

recurrence of similar incident.

1.3.7 Monthly Works

(a) General

(i) To check the general condition of the plant and equipment such as compressors, condensers,

heat recovery equipment, heat pumps, IAQ equipment, fan coil units and the associated

electrical, electronic, mechanical controls and circuit boards. To ensure that the plant and

equipment are satisfactorily operating within design conditions;

(ii) To drain and clean the pre-filter and after-filter of the pneumatic control system, and clean the

refrigerated drier and after-cooler, if any;

(iii) To check the lubricating system of all fan blowers, compressors, control mechanisms and any

other running parts; cleaning, greasing and oiling where necessary;

(iv) To check any water leakage from the pipework and to repair if required;

(v) To keep all supply and return grilles and louvers clean;

(vi) To check the corrosion of metal surface, framework and support/mounting brackets, etc., and

to reinstate the surface by removing rust and repaint if necessary;

(b) Refrigerant Compressors, Condensers and Heat Pumps

(i) To check for proper operation of the refrigeration machines and related controls, control circuit,

and detect any abnormal noise and vibration, repair or adjust as necessary;

(ii) To check and record on log sheets and where appropriate on system performance sheet the

refrigerant compressor suction and discharge pressures, condenser air inlet and outlet

temperature and motor current;

(iii) To check condition of operating refrigerant, liquid level and lubrication level, refill or renew as

necessary;

(iv) To examine the condition of joints and seals for leaks, repair as necessary;

(v) To remove debris and maintain the condenser in clean and tidy condition;

(vi) To check the vibration of machines as compare to the recommendations by the manufacturer

for future baseline monitoring and maintenance.

(c) Motors for All motorized Devices and Equipment

(i) To clean motor casing, grease and lubricate;

(ii) To check and report any abnormal running noise and vibration. Replace the bearings, perform

megger test on motor and repair as necessary; and

(iii) To check, adjust and rectify/repair defect on circuit protective devices such as starters, control

relay and indicators.

(d) Fan Coil Units

(i) To check that the fan coil units and its control/sensing devices are functioning properly and

inspect drain pipes to ensure no clogging and flooding. Rectify if necessary;

(ii) To check and clean the condensing water drain pan, drain pipes to ensure no clogging and

flooding.

Rectify if necessary;

(iii) To clean the supply and return air grilles and filters; and

(iv) To check the control/protective devices for proper operation. Rectify if necessary.

(g) Heat Exchanger

(i) To check on all joints for leak. Rectify if necessary;

(ii) To check the temperature settings and functioning of the controls and ensure compliance with

manufacturers’ standards.

208

(h) Mechanical Ventilation System

(i) To clean fan blade and blades for wear and damage;

(ii) To check and if necessary to lubricate fan and motor bearings;

(iii) To check flexible connections and that anti-vibration mountings are free to move, and function

properly

(iv) To clean the air filters, supply and return air grilles and to renew air filters if necessary;

(v) To check the operation and function of the control devices;

(vi) To check all electrical wiring and connections and circuit protection devices including

switchgears and starters. Rectify if required

(i) Equipment

(i) To check and service all IAQ equipment including air cleaner and other filtration and sterilizing

system and equipment for IAQ; and

(ii) The Contractor shall take measurements of IAQ parameters and submit records to the Project

Architect.

1.3.8 Half-Yearly Works

Half-yearly service and maintenance shall include the following items:-

(a) To inspect the condition of pipe fittings, supports, hangers, etc., for sign of corrosion. Remove

the rust and repaint with primer and finish coating as necessary;

(b) To check the performance of controls and safety cut-outs and check all control panel indication

lamps, rectify as required;

(c) To clean electrical panels including wiring terminals and connection points;

(d) To touch up with finish-coating where there is any rust or sign of corrosion of the equipment

by first removing the rust/corrosion;

(e) To clean all the air-cooled condenser coils by high-pressure water or steam jet with approved

cleaning detergent to ensure that high heat transfer efficiency is maintained;

(d) To clean the cooling/heating coils (excluding fan coil units) by high-pressure water or steam jet

with approved cleaning detergent to ensure that high heat transfer efficiency is maintained;

(h) To check and serve all IAQ control and sensing equipment including CO2 sensors, air movement

sensors, thermostat, humidifiers, dehumidifiers, humidistat, pressurestat and

(i) To inspect all components of ventilation system for cleanliness and microbial growth and clean

them as necessary.

1.3.9 Annual Works

(a) To inspect the condition of pipe fittings, supports, hangers, etc., for sign of corrosion. Remove

the rust and repaint with primer and finish coating as necessary;

(b) To examine, check and maintain the proper operation of associated electrical panels in the plant

room. Repair and renew as appropriate;

(c) To check, test and recalibrate or replace as necessary, all control and safety devices;

(d) To check, test, adjust, clean and repair/rectify defects if required for all electronic circuit boards

and control/ sensing/detection devices including building automation system if available in the

system;

The Contractor shall arrange the cleaning work after the building office hour;

(e) To check and re-tighten any loose bolts and nuts in proper sequence.

I.4 SPARE PARTS AND SPECIAL TOOLS

For plant and/or equipment included in the tender, the Contractor shall provide the types of spare parts

generally wherever these are appropriate to the plant and/or equipment involved plus any additional

items for the particular plant and/or equipment.

Unless otherwise specified, within two months of signing the Contract, or in such period of time as has

been agreed by the Project Architect in writing, the Contractor shall submit in respect of the proposed

plant and/or equipment a list of the manufacturer’s recommended spare parts that are likely to prove

209

necessary to service the plant and/or equipment during the first year’s operation and parts required

immediately following the completion of the Contract maintenance period.

The spare parts submission shall include diagrams or catalogue details of the parts concerned and bona-

fide manufacturer’s published price lists. The Contractor may add the net shipping costs for each item

plus a 15% margin to cover overheads and profit. Where appropriate, the prevailing exchange rate must

be stated. The Contractor should note that an unacceptable or inadequate response to this requirement

may result in their installation not being accepted.

Unless specified in detail, the criteria by which the Contractor shall judge the need for spare parts to be

included in the Schedule shall be any part or component of the plant or equipment that is subject to

frictional wear, vibration or temperature fatigue, rupturable to safety (or otherwise), corrosion, erosion,

unacceptable deposits and/or saturation by contaminants (such as for filters), normal fair wear and tear

and is likely to fail or reach an unacceptably low performance level within a period of three years or

less from its installation and/or commencement of operation excluding the Contract Testing and

Commissioning Periods.

The schedule shall include at least the following items where they are part of the installation concerned:-

- Standard replaceable type air filter media;

- Rupturable safety devices;

- Plug in relays;

- Indicator light lamps;

- Non-standard fuse cartridges; and

Any of the above spare parts and/or disposable items which are required to replace defective or

prematurely worn out parts that arise during the free maintenance period and/or defects liability shall

be replaced by the Contractor at no cost to the Employer before the Maintenance Certificate is issued.

The above items shall not be exhaustive. The Contractor shall be responsible for the replacement of

other parts and components for normal operation of the installation.

Additionally the Contractor shall submit within the same period a priced schedule for the supply of any

special tools necessary for servicing and maintenance of any part of the installation.

Instructions for purchase of any special tool shall be issued separately but the basis for charging shall

be similar to that for the Contractor’s equipment manufacturer’s recommended spare parts.

The purchase of the needed spare parts and tools shall be secured by the Project Architect’s Instruction

for which a provisional sum shall be provided in the Contract.

The exact types and quantities shall be determined by the Project Architect based on the Contractor’s

best advice and at the most appropriate time during the Contract Period when requirements can be most

realistically assessed taking account of the installation as installed or still being installed.

210

F TYPICAL VRV SYSTEM INSTALLATION LAYOUT

211

G SCHEDULE OF PROPOSED COMFORT COOLING VRV / VRF AND SINGLE SPLIT WALL

MOUNTED AIR-CONDITIONING UNITS TO BE INSTALLED FOR OFFICE BUILDING AT

REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF

THE AFRICAN DEVELOPMENT BANK (ADB)

No Room Schedule Qty. Type of Unit Cooling

Capacity

Total

Cooling

Basement Floor

1 Main Entrance Lobby Area (-B-05) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

2 Waiting Room (B-06) 1 In-Ceiling Cassette Mounted 1 x 18,000BTU 18,000BTU

3 Public Information Center (B-07) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

4 Corridor (B-11) 1 In-Ceiling Cassette Mounted 2 x 12,000BTU 24,000BTU

5 Office (B-08) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

6 Server Room (B-9) (N+1) 1 Wall Mounted 2 x 12,000BTU 24,000BTU

7 UPS Room (B-10) (N+1) 2 Wall Mounted 2 x 12,000BTU 24,000BTU

8 LV Panelboard Room 1 Wall Mounted 1 x 12,000 BTU 12,000BTU

Ground Floor

9 Conference Room (G-07) (N+1) 2 In-Ceiling Cassette Mounted 2 x 24,000BTU 48,000BTU

10 Lobby (G-02) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

11 Reception (G-01) 1 In-Ceiling Cassette Mounted 1 x 18,000BTU 18,000BTU

12 Corridor (G-12) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

13 Corridor Toilet Area + Archive (G-05) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

14 Office (G-03) 1 In-Ceiling Cassette Mounted 1 x 24,000BTU 24,000BTU

15 Country Program Officer (G-06) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

16 Office (G-04) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

First Floor

17 Lobby 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

18 Office (F-04) 1 In-Ceiling Cassette Mounted 1 x 24,000BTU 24,000BTU

19 Reception/Waiting (F-03) 1 In-Ceiling Cassette Mounted 1 x 18,000BTU 18,000BTU

20 Corridor (F-05)) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

21 Corridor (F-14)) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

22 Corridor Toilet Area 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

23 Office (F-07) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

24 Secretary/Waiting (F-08) 1 In-Ceiling Cassette Mounted 1 x 18,000BTU 18,000BTU

25 Resident Representative (F-09) 1 In-Ceiling Cassette Mounted 1 x 24,000BTU 24,000BTU

26 Office (F-11) 1 In-Ceiling Cassette Mounted 1 x 9,000BTU 9,000BTU

27 Meeting Room (F-12) 1 In-Ceiling Cassette Mounted 1 x 12,000BTU 12,000BTU

Battery Room

28 Solar Battery Room 1 Wall Mounted 1 x 18,000 BTU 18,000BTU

212

SPECIFICATIONS FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

2 x 175kVA, 140kW MODEL TYPE TGC_IV-110 COMPLETE WITH SET MOUNTED

CONTROLLER TYPE DSE7310 CONTINUOUS RATED SOUND ATTENUATED

WEATHERPROOF CANOPY VOLVO GENERATOR SETS DESIGNED FOR AUTOMATIC MODE

OPERATION FOR OFFICE BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR

SIERRA LEONE FIELD OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB)

213

2 x 175kVA, 140kW CONTINUOUS RATED SOUND ATTENUATED WEATHERPROOF CANOPY

VOLVO GENERATOR SETS DESIGNED FOR AUTOMATIC MODE OPERATION FOR OFFICE

BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD

OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB)

PARTICULAR SPECIFICATION

CONTENTS

1.0 INTRODUCTION AND DESCRIPTION OF WORKS

2.0 SPECIFICATION OF 175kVA, 140kW, 400/230V~, 50Hz, 1500RPM, MODEL TYPE COMPLETE

WITH SET MOUNTED CONTROLLER TYPE DSE7310 GENERATOR SET

3.0 SPECIFICATION OF 250A AUTOMATIC TRANSFER SWITCHES (ATS)

4.0 PROPOSED THREE SOURCE POWER SUPPLY SYSTEMS DESIGN

214

1.0 INTRODUCTION AND DESCRIPTION OF WORKS

1.1 Introduction:

This Particular Specification details the requirements for the supply, installation, testing and

commissioning of 2 x 175KVA, 140kW, 400/230V~, 50Hz, 1500RPM, Model Type VOLVO TGC

Generator sets complete with set mounted controller Type DSE7310 and shall be read in conjunction

with the latest IEE Regulations and ISO 8528.

1.2 General:

The Generator sets will be installed in a purposed built Generator House complete with all associated

Switchgears within the ADB secured perimeter fenced Complex. The entire Generator sets electrical

system shall be based on a 230/400V, 3-phase and neutral, 50 Hz, Terra Neutral- Separate (TN-S)

system.

1.3 Regulations and standards

The complete installation shall comply with all relevant British Standard and, where indicated, with

other standards and specifications and all amendments thereto. A Certificate of compliance shall be

provided for the Project Architect, to be included in the handover.

215

2.0 SPECIFICATIONS FOR THE SUPPLY, INSTALLATION, TESTING AND

COMMISSIONING OF, OF 2 x 175kVA, 140kW VOLVO GENERATOR SETS, MODEL TYPE

TGC COMPLETE WITH SET MOUNTED CONTROLLER TYPE DSE7310, CONTINUOUS

RATED SOUND ATTENUATED WEATHERPROOF CANOPY GENERATOR SETS.

2.1 Technical Data:

175kVA, 140kW GENERATOR SET:

KVA: 175

KW: 140

V: 400

Ph.: 3

Hz: 50

Pf: 0.8

A: 253

RPM: 1500

The 175kVA, 140kW, 3-Phase, 400/230V, 50Hz, 0.8pf@ 1500RPM Standby Generator sets specified

shall be supplied complete with Automatic Transfer Switches (ATS) for fully automatic mode operation

in an event the Mains (Utility) supply fails.

The Generator Sets, as specified on the ‘’Name Plate’’ shall be rated for PRIME Operation in

accordance with ISO8528, which means it’s applicable for supplying continuous electrical power (at

variable load) in lieu of commercially purchased power. There is no limitation to the annual hours of

operation and specified model shall supply 10% overload power for 1 hour in12 hours.

Fuel consumption data at indicated load with diesel fuel with specific gravity of 0.85 and conforming

to BS2869:1998 Class A2

Rating Definitions:

Prime Power Rating (PPR):

Variable load: Unlimited hour’s usage with an average load factor ≥ of 70% of the published Prime

Power rating over each 24 hour period. A 10% overload shall be available for 1 hour in every 12 hours

operation.

Governor Regulation Class conforming to ISO 8528 G2

Basic technical data:

Number of cylinders: 6

Cylinder arrangement: Vertical, in line

Cycle: 4 stroke, compression ignition

Induction system: Turbocharged, air to air charge cooling

Direction of rotation: clockwise viewed on flywheel

Lubrication system:

Recommended lubricating oil shall be 5W / 40 which adequately meets the specifications of API CG4

216

Cooling system:

Recommended coolant shall be 50% clean water with 50% VOLVO ELC.

Where there is no likelihood of ambient temperature below 10 °C, clean ‘soft’ water may be used,

treated with 1% by volume of Engine inhibitor in the cooling system.

Cyclic irregularity for engine/flywheel maximum:

1500 rev/min: 0, 0192

Ratings:

Steady state speed stability at constant load: ± 0.25%

Electrical ratings are based on average alternator efficiency and are for guidance only (0.8 power factor

being used).

Engine management system:

Full electronic engine management system controlling:

Speed governing

Air / Fuel ratio

Start sequence

Engine Protection and diagnostics.

Starting requirements:

Notes:

The battery capacity is defined by the 20 hour rate at 0 °C

The oil specification should be for the minimum ambient temperature as the oil will not be warmed

by the immersion heater

The breakaway current is dependent on the battery capacity available. Cables should be capable

of handling the transient current this may be up to double the steady cranking current.

Fuel system:

Recommended fuel: To conform to BS2869 1998 Class A2

Type of injection system: MEUI

Fuel injector pressure: 2000 bar

2.2 General Description:

A standby sound attenuated canopy generator sets shall be supplied by the Vendor for the

Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field Office at the

African Development Bank (ADB) and they shall be rated as follows:

a) 2 x 175kVA, 140kW Continuous Rating

(3 Phase, 50Hz, 400/230 Volts, 1500 rpm, 0.8pf)

The Generating sets power rating environmental conditions shall be 270C (800 F, 152.4m (500ft) A.S.L,

and 60% relative humidity.

The new sets shall have an automatic mains failure operation to accept the full load of the building and

shall be connected to alternately operate the Office Building at Regent Road, Hill Station, Freetown for

Sierra Leone Field Office at the African Development Bank (ADB).

The sets shall be arranged for 1 x 175kVA to be duty set and 1 x 175kVA to be standby “one generator

is Lead and start first at the commercial power outage, and the second generator is Lag and

start only if the Lead generator fails to start, or after a determinate amount of the Lead generator

operation hours”)

217

2.3 Operation:

In the event of a mains (utility) failure of any one phase, the selected generator set (175kVA Main Set

or 175kVA Standby Set) shall automatically start, and accept the building load.

Upon reinstatement of the mains supply the load of the building will be transferred automatically back

to the mains supply (Utility) after the operation of delay timers adjustable between 3/5 minutes.

The generator set shall continue to run on no load for a further adjustable time period of between 3/5

minutes, after which it shall shut down and be ready for the next start-up operation.

The changeover equipment shall be part of the incoming supply switch panel and shall be constituted

of automatic thermal-magnetic molded case circuit breakers rated according to the loads and electrically

interlocked to prevent paralleling of Utility and Standby supply.

2.4 Control Panel:

The control panel shall be freestanding, one section, with suitable Protection Degree IP55 or better,

enclosure shall be provided with built-in suitable ventilation system. The generator set shall have the

following controls and instruments, as a minimum requirement:

ON/OFF/AUTO Selector Switch

OFF LOAD/ON LOAD Test Switch

Voltmeter and Selector Switch

Kilowatt Hour Meter

Three Ammeters

Frequency Meter

Hours run counter and automatic LEAD-LAG selector that change automatically the LEAD generator

to LAG after a selected amount of operation hours.

Battery Charger Selector Switch - Trickle and Boost Charge Selector

Battery Charger Ammeter

Indicator - Not in Auto

- Fail to Start

- Low Oil Pressure

- High Engine Temperature

- Over speed

- Reverse Power

- Low Fuel

- On Load

Audible Alarm

Emergency Stop Button

Motor Driven Circuit Breaker

Auxiliary Fuses

Grounding Bus

The Automatic Transfer Switch (ATS) panels shall be of cubicle construction wall mounted with front

access and shall be adequately ventilated to suit the ambient temperatures of 27-320C

All the equipment shall be suitable for use in tropical conditions.

218

2.5 Sound Acoustic Enclosure:

The sound attenuated canopy shall be the fully weatherproof, sound attenuated enclosures in order to

withstand the rough weather and operation common in Freetown. It shall be supplied with sound

pressure levels (dBA) at 1500RPM (50HZ) 1M Full Load 72 dBA and NO Load 71 dBA.

The canopies features shall include:

1. Highly corrosion resistant construction

2. Excellent access for maintenance

3. Security and Safety provisions (emergency lighting, warning signs, emergency pushbuttons,

etc.)

4. Transportability

5. Residential Silencer

6. Suitable protection against dust and insect penetration

7. Adequate ventilation.

2.6 Engine Cooling:

Cooling shall be provided by an engine mounted fan assisted radiator suitably sized for tropical

conditions with pusher fan driven directly from the engine.

The cooling system shall be of the pressure type to ensure minimum water loss. Cooling system shall

be calculated and sized in accordance with PRIME rating at the outdoor temperature of 30°C.

2.6 Alternators:

AC Alternator shall be brushless screen protected, fan ventilated drip – proof, single bearing and rated

according to the aforementioned sizes at 0.8 power factor 400/230 volts, 3-phase, 4-wire, 50Hz when

operating at 1500 rpm, all as manufactured by Stamford Newage International or approved equal to BS

5000 Part 3, VDE 0530, UTE 5100 CEMA, IEC 34-1 CSA 22-2, NEMA MGI – 22 and AS 1359.

Voltage regulation shall be maintained within the limits of + 2½% from a no load to full load condition

including from cold to hot, at any power factor between 0.8 lagging and unity and inclusive of a speed

variation of 4½%.

Response to transient load changes shall be such that they recover to within 3% of the steady state value

in 0.3 seconds upon application of full load at a power factor of 0.8 lagging.

Rotor, Stator, exciters and any other winding shall be suitably impregnated with Class H thermosetting

insulating varnish to allow normal operation in tropical climates. Telephone interference suppression

shall be incorporated to comply with BS 4999 Part 4.

AC Alternator shall be fitted with Coastal Insulation Protection, direct driven centrifugal fan, and Anti

Condensation Heater

2.8 Complete Generator:

The engine and alternator shall be close coupled and mounted on a fabricated steel base frame with

built in daily fuel tank, 250 litres minimum capacity, or 12hours minimum operation at full load, with

leakage detection system and/or double wall type. The whole unit shall be mounted on at least 6 anti-

vibration mountings housed in the Weatherproof Sound Enclosure.

NOTE:

1. 1Nr. 250A ATS-1 with a selector switch, to select between 175kVA Main (Lead) Set and

175kVA Standby (Lag) Set and the common loads feed to ATS-2.

219

2. 1Nr. 250A ATS-2 to select between the common loads from Generator Sets (175kVA

Main Set & 175kVA Standby Set) and the Utility (EDSA) Supply.

2.9 Delivery, Storage, and Handling

Deliver equipment on pallets or blocking wrapped in heavy-duty plastic, sealed to protect parts and

assemblies from moisture and dirt. Plug piping, conduit, exhaust, and air intake openings. Protect and

prepare batteries for shipment as recommended by the battery manufacturer.

Store auxiliary equipment at the site in covered enclosures, protected from atmospheric moisture, dirt,

and ground water. Deliver diesel generator sets dry, and provide separate lubricant oil, cooling fluid

and other necessary fluids in separate enclosures ready for the filling at the site.

2.10 Specific Manufacturers

Specific manufacture or trade names mentioned in the Specification are to be strictly adhered to for the

purpose of indicating the required class or quality of material, design of workmanship of fittings and

equipment. In order that parity of tendering may result, the Vendor shall use any such particular fitting

or equipment as a basis of pricing. The Vendor may submit for the Project Architect’s approval any

fitting or equipment of equal quality workmanship or design from any other established manufacturer,

but none shall be ordered before written approval of it is obtained from the Project Architect and any

variation which would entail additional cost will not be permitted. The Project Architect’s decision on

whether to accept or not, an alternative make shall be deemed final.

The Vendor shall state on the Bid form any proposals that he wishes to make under this clause together

with the savings, if any. In the event of the Project Architect approving any such proposal an appropriate

Variation Order will be issued by the Project Architect to the Vendor.

The Vendor shall be responsible for the specified performance of all fittings or equipment and it is

therefore recommended that he should obtain guarantees of performance from the Suppliers.

Where the quality of materials is not specified, they shall be the best of their respective kinds and

samples or full details shall be submitted to the Project Architect for approval before use.

All plant and materials shall be new and the Vendor shall ensure that no materials or equipment are

fitted which show signs of corrosion or faults or are damaged in any way.

220

3.0 SPECIFICATIONS OF AUTOMATIC TRANSFER SWITCH (ATS)

The Power-Command transfer switches shall include unique features that provide flexibility for

the intended applications. The microprocessor-based controls shall optimize performance while

simplifying operation and service.

For the ADB Field Office Building in Freetown having two (2) standby generator sets (double standby)

and a utility feed, when the utility fails, the standby generators transfer switch (250Amps ATS-1)

controls the feeds from the 2 x 175kVA Generators based on an established priority (load demand),

send a start signal to the primary duty standby generator and transfers the load. If the primary standby

generator fails, the transfer switch with the selector switch in the right position sends a start signal to

the second generator set and transfers the load.

If both Standby Generators feeds fail, the utility transfer switch sends a signal to the utility contactor

(250Amps ATS-2) to transfers the load.

The transfer switches shall give a range of controls for safe, dependable and easy-to-use power transfers

for these modes.

It must be noted that the applications for which these generators are operated determines the

nature of the load demand control parameters. The signals are determined when the pre-

established priority (load demand) parameters on site have been established and agreed upon by

the Bank.

Open-transition transfer:

Break-before-make switching action: Independent break-before-make action is used for both

4-pole/switched neutral switches

For the most basic type of transfer; the connection to one source is opened before the connection

to the second source is closed to allow the open-transition transfer control monitors both sources

and initiates the transfer — avoiding out-of-phase closing.

For open-transition operation, transfer switches system shall incorporate Power Command

microprocessor control and a reliable High-Endurance Mechanism and shall be ideal for utility-

to-genset and genset-to-genset applications

Programmed-transition transfer:

Similar to open-transition transfer: The switch opens the connection to one source, pauses for an

adjustable delay time, and then closes the connection to the second source. The adjustable time between

sources allows the decay of residual voltage before connecting to the second source.

Bypass-isolation transfer switches:

Shall be ideal for critical-need applications where any disruption of supply power, even for routine

maintenance, is unacceptable.

The bypass-isolation automatic transfer switch shall combine features of our advanced automatic

transfer switch with a closed- door draw out isolation mechanism, a two-source bypass switch and

exclusive microprocessor-based controls. The switches allow maintenance, service and testing of the

automatic transfer switch without disrupting power to critical loads. The resulting power transfer

redundancy helps ensure constant, reliable power for critical applications

221

3.1 ATS Minimum Requirements:

ATS shall be built to withstand thousands of switching cycles, ensuring reliable operation and

meets the following minimum requirements:

(i) Microprocessor control:

Fully-featured microprocessor control is standard with all settings and adjustments

designed for easy operator use via the front display panel for ease of setup and accuracy

(ii) Easy manual operation and Manual operation handle (standard):

Allows manual operation of the switch after proper disconnection of power sources and

also allows manual transfer to any available source at any time.

Plug connections, door-mounted controls, and ample access space, compatible terminal

markings simplify access.

Manual operating handles, shielded termination and over-center type contact mechanisms

allow effective, manual operation under de-energized conditions

(iii) Easy service/access:

Door-mounted controls, ample access space and compatible terminal markings allow for

easy access:

(iv) Positive interlocking:

Mechanical interlocking prevents source-to-source connection through the power

contacts or control wiring. Also prevents simultaneous closing of normal and emergency

contacts

(v) Solenoid:

A powerful and economical solenoid power transfer switches

(vi) Advanced transfers switch mechanism:

True transfer switch mechanism with break-before-make action with Bi-directional linear

motor actuator that provides virtually friction-free, constant-force, straight-line transfer

switch action with no complex gears or linkages

(vii) Continuously rated:

Can be used in applications up to their nameplate rating

(vii) Main contacts:

Heavy-duty long-life, high-pressure silver alloy contacts with separate arcing surfaces

and multi-leaf arc chutes rated for the total system transfer including overload interruption

to withstand thousands of switching cycles without burning, pitting or welding and

provide 100% continuous current ratings

(viii) Permanently mounted instructions:

Allows easy step-by-step operation

(ix) Robust control system design:

Optically-isolated logic inputs and high-isolation transformers for AC power inputs

provide high-voltage surge protection

222

3.3 ATS Command controls

(ATS command controls optimize the reliability and performance of the power generation system

while keeping costs competitive and providing unique capabilities for the entire system)

Note: The automatic transfer switches shall incorporate Power Command microprocessor control and

a reliable High-Endurance Mechanism ideal for Utility (EDSA) – to - Genset and Genset – to -

Genset applications.

S — standard features O — optional features

Sensing

3-Phase voltage-sensing utility S

3-Phase voltage-sensing generator S

Electrical isolation from AC mains S, transformer

Voltage-sensing accuracy +/-1%

O/U voltage-sensing utility S

O/U voltage-sensing generator S

O/U frequency-sensing utility S

Voltage imbalance S

Phase rotation S

Loss of phase S

General features/serviceability

Door-mounted S

Controls isolated from switch during service S

Single control package for sensing/timing S

Voltage surge immunity S

Optically isolated customer I/O S

Method(s) for sensor/timer adjustments Front panel, LED configuration

Number of time/date-stamped events 50

Real-time clock (RTC) S

On-board diagnostics/fault detection S

Field-upgradeable software, PC diagnostics S

Fully adjustable timers, sensors and control parameters S

Mode control key switch interface with control O

Supported voltages

240V; 380-480V S

Transition modes

Programmed transition S

In-phase monitor S

Display/metering/user interface

Display offered/type O, VFD

Front-panel LED status lamps 6-fixed (8 for configuration)

Front-panel test S

Front-panel TD override S

Front-panel lamp test/fault reset S

etN/ASSFront-panel set exerciser S

Color-coded bar graph meters for voltage, current,

frequency, kW and power factor

O

Engine-exerciser clock

Calendar-based exerciser with real-time clock S

Once/week exerciser S

Exerciser via external clock module O

Number of exercise programs 1

Exercise exceptions S, 1

223

Time \delays

Displays timer delay countdown O

Field-adjustable time delays S

Time-delay engine start S

Time-delay transfer (normal to emergency) S

Time-delay retransfer (emergency to normal) S

Time-delay engine cool down S

Time-delay elevator pre-transfer S

Time-delay programmed transition (delayed neutral) S

Time-delay override/bypass feature S

Automatic generator-generator changeover timer S

Customer inputs/outputs

Remote test with load/transfer to generator O

Remote engine start O

Transfer inhibit S

Re-transfer inhibit S

Generator (source-2) common alarm S

Utility (source-1) common alarm S

Panel security lock S

Generator battery charger status input S

Remote time delay override/bypass S

Remote lamp test/fault reset O

Bypass switch position contacts S

Generator interface

Generator (1) start contact (relay) S

Generator (2) start contact S

Relay outputs

Generator Source-1 connected S

Generator Source-2 connected S

Generator Source-1 available S

Generator Source-2 available S

ATS not in auto S

Test/exercise active O

Pre-transfer/load disconnect S, relay drives

Failure to disconnect S

Failure to close/open S

Approval code/standards

UL1008 S

ISO 8528 S

IEC S

CSA, NFPA, IEEE S

IBC S

NEMA ICS 10 S

224

4.0 PROPOSED THREE SOURCE POWER SUPPLY SYSTEMS DESIGN FOR SIERRA LEONE

OFFICE AFRICA DEVELOPMENT BANK:

BLOCK SCHEMATIC

NOTE:

1. 250Amps ATS 1 shall be equipped with a selector switch to select between any of the 175KVA, 140kW

KVA Generator Sets and.

2. 250Amps ATS 2 shall operates with the common load from either 175KVA, 140kW Generator Sets

and the Mains Supply (EDSA)

225

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF 1

X 8 PASSENGER ELECTRIC LIFT FOR OFFICE BUILDING AT REGENT ROAD, HILL

STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

226

1 X 8 PASSENGER ELECTRIC LIFT FOR OFFICE BUILDING AT REGENT ROAD, HILL

STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

PARTICULAR SPECIFICATION

CONTENTS

1 CONDITION OF CONTRACT AND PRELIMINARIES

2 TERMS AND INFORMATION

3 SCHEDULE OF EQUIPMENT

4 MACHINE ROOM EQUIPMENT

5 TECHNICAL AND CONSTRUCTION DETAILS OF EQUIPMENT

6 WORK PROGRAMME

7. SUMMARY TENDER

227

1.0 Condition of Contract and Preliminaries

1.01 Names of Parties and Definitions

1.02 Instructions for Tender

1.03 Form of Contract

1.04 Regulations and Quality of Work

1.05 Drawings, Specification, Orders and Other Particulars

1.06 Equipment and Materials

1.07 Technical and Construction Details of Equipment

1.08 Site Inspection

1.09 Cost of Testing Materials

1.10 Protecting, Drying and Cleaning the Work

1.11 Defects Liability and Maintenance Period

1.12 Assignments or Sub-Letting

1.13 Target Programme

2 0 Terms and Information

2.01 Schedule of Builders and Electrical Works (To be included as part of the contract)

2.02 Builders Works in the Lift Well

2.03 Electrical Works

2.04 Sub-Contractor to Note

3.0 Schedule of Equipment

3.1 Lift 1

4.0 Machine Room Equipment

4.01 Lift Machine (Electric Lifts)

4.02 Motor

4.03 Hydraulic Lifts – Machinery and Pump Unit

4.04 Power Control

4.05 Control System

4.06 Controller

4.07 Over speed Governor to Car

4.08 Machine Location Switch

4.09 Car Enclosure and Frame

4.10 Car Frame

4.11 Safety Gear

4.12 Car Enclosure

4.13 Internal Finishes

4.14 Load Details

4.15 Signal and Operating Devices

4.16 Car and Landing Entrances Equipment

4.17 Car and Landing Door Arrangement

4.18 Automatic Power Operation of Car Door

4.19 Signal and Operating Fixtures

4.21 Locking Devices and Switches for Car and Landing Entrances

4.22 Lift Shaft, Counterweight and Pit

4.23 Guides and Fixings

4.24 Buffers

4.25 Suspension Ropes

4.26 Counterweight and Screen

4.27 Emergency Signal

4.28 Limits and Switches

4.29 Electrical Requirements

4.30 Main Switch and Wiring

228

4.31 Drawing, Notices, Painting Etc.

4.32 Plans and Drawing

4.33 Notices Etc.

4.34 Painting

4.35 Silent Operation

4.36 Entrance Barrier

4.37 Radio and Television Suppression

4.38 Schedule of Testing and Finishes

4.39 Commissioning

4.40 Finishes Schedule

4.41 Lift Maintenance

4.42 Annual Maintenance Agreement

5.0 Technical and Construction Details of Equipment

5.01 Lifts 1 and 2

6.0 Work Programme

6.01 Lift Programme

6.02 Start on Site

6.03 Summary of Tender

229

1.0 CONDITION OF CONTRACT AND PRELIMINARIES

1.1 Names of Parties and Definitions

The names of parties and definitions used in the contractor documents shall have the meanings attached

to them as defined below.

i The “Employer” shall mean African Development Bank (ADB)

ii The “Consultants Engineer” shall mean Realini Bader Associates Limited, 72 Wellington Street,

Freetown, or such person or persons as they shall appoint for the purpose of the contract.

iii The “Main Contractor” shall mean as appointed by the Employer.

iv The “Sub-Contractor” shall mean the firm appointed to carry out the total contract between the

Main Contractor and Himself.

v The “Contract” shall mean the contract between the Main Contractor and the Sub-contractor, and

shall include the specification and drawings defined herein, the completed form of tender, the letter

of acceptance of the tender, together with any related correspondence mentioned in the letter of

acceptance of the tender.

vi “Approved” shall mean approved in writing by “The Project Architect”

vii “BS or BSS” – The letters BS or BSS shall mean the latest British Standard (BS5655) – including

any amendments in force at the time of tendering) where reasonably practical as defined by the

Engineer.

viii The expression “work” shall mean to include the whole of the installation and commissioning

necessary to conform to the provisions contained in the specification including buildings and

electrical works as detailed under Section 2.

1.2 Instructions for Tender

1.2.1 A tender is invited for the installation and maintenance of one (1) 8-passenger electric lift, as detailed

and described in this specification

1.2.2 This specification indicates generally the requirements of the installation. Where the sub-contractor’s

tender, for carrying out their work is based on any deviations from the specification, in respect of any

materials, method of installation, performance, Builders work or the like which is due solely to the sub-

contractor’s own standard design requirements, such deviations shall be clearly set out in a covering

letter of schedule to be submitted with this tender.

1.2.3 No alteration to the text of these contract tender documents will be permitted. Any unauthorised

alterations or qualifications will be disregarded and may result in disqualification of the tender. Any

qualifications that may be printed on the sub-contractor’s letter paper which may accompany the tender

will not be accepted unless these are agreed in writing by the Project Architect after consultation with

the Main Contractor.

1.2.4 The Main Contractor does not bind himself to accept either the lowest or any tender, nor to reimburse

the sub-contractor for any expenses he may incur in the preparation of such tender.

1.2.5 No guarantee can be made that the work will proceed as planned or that the project will not be

postponed or cancelled and the employer will not accept any claim from the contractor for expenses,

loss of profit, or other such considerations.

230

1.2.6 In the absence of such a covering letter or schedule it will be deemed that the price quoted by the sub-

contractor includes for the whole of the work to be carried out as specified herein and no such later

requests for deviation will be considered.

1.3 Form of Contract

1.3.1 The terms and conditions applicable to this contract shall be based on the terms and conditions issued

by the Project Quantity Surveyor (QS) with the tender documents.

1.4 Regulations and Quality of Work

1.4.1 The design, manufacture and installation of the one (1) 8-passenger electric lift and associated

components shall be to the satisfaction of the Project Architect (Manager) who reserves the right to

inspect any part of the lift installation whether on the site or at the sub-contractor works yard and to

call for samples of any materials it is proposed to use on this contract. The sub-contractor shall identify

which elements of this contract will be sub-let at the time of tendering.

1.4.2 The completed installation shall comply in all respects with the latest current editions of the following

British Standards where reasonably practical, except where modified by this specification and any other

related document in the invitation to tender. Where this specification differs from those Standards and

Codes, the provision of this specification shall prevail.

(a) British Standard 5655 Electric/Hydraulic Lifts – all relevant parts thereof.

(b) British Standard 5000, the Electrical performance of rotating machines.

(c) British Standard 329, Wire Ropes for lifts and hoists.

(d) British Standard 6977, Braided Travelling cables for electric and hydraulic lifts.

(e) British Standard Code of Practice BS5655 Part 6, 1985, Electric lifts for passenger, goods and

service.

1.4.3 Additionally, the lift installation shall comply with any other British Standard not mentioned above

together with the appropriate mandatory clauses of the Health and Safety at Work Act, 1994, Building

Industries National Code of Practice for Electric Passenger and Goods Lifts, the regulations for the

Electrical Equipment of Buildings (Latest Edition). The completed installation shall also comply with

any requirements and/or regulations of the Local Electricity Board, London Fire Brigade, principal Fire

Insurance Companies, and other authorities having jurisdiction. The electrical installation shall

conform to the 17th Edition of the IEE Wiring Regulations.

1.4.4 Any work required under this specification, the quality and/or method of installation of which has not

been specified shall conform to good practice for the type of work involved.

1.5 Drawing, Specification, Orders and Other Particulars

1.5.1 This specification shall be read in conjunction with schedules, specification, and general conditions of

contract and preliminaries being construed as a whole and the sub-contractor shall carry out such work

accordingly.

1.5.2 The sub-contractor will be held responsible for the works embodied therein and shall take all necessary

particulars and provide at his own expense all other necessary work and detailed drawings of equipment

specified or to be supplied herein, copies of which must first be submitted for approval by the Project

Architect before the work is put into hand. Other drawings to be provided by the sub-contractor are set

out in Section 4.6.

1.5.3 The sub-contractor shall be responsible for any drawings, specifications, orders or any other particulars

supplied by him and for any discrepancies, errors, or omissions in the same.

1.6 Equipment and Materials

1.6.1 This contract includes for the supply and installation of one (1) 8-passenger electric passenger lifts.

Materials to be manufactured, supplied and installed and the whole of the work necessary, commencing

from the electrical mains supply board, all in accordance with the sections of this specification whether

231

specifically mentioned, inferred, or otherwise together with the remedying of defects, periods as

provided herein.

1.6.2 The sub-contractor shall base his tender on the materials and manufacturers (where indicated) as

detailed in Section 4.6 of the specification. Where materials and manufacturers have not been specified

the materials shall be of the highest possible grades of their respective kinds and shall conform where

relevant to the British Standard for such materials.

1.6.3 The Project Architect will only consider all unspecified materials proposed for use by the sub-

contractor on this contract if in his opinion the material is acceptable and is equal in all respects and is

in no way inferior to that which manufacturer has specified. The decision as to whether any material is

“equal” or “approved” will be determined solely by the Project Architect whose decision in this respect

will be final.

1.6.4 All specified materials to be used under this contract shall be new, shall comply fully with the relevant

BSS and on delivery to site shall not be removed without the consent of the Project Architect. If any

material is considered by the Project Architect to be objectionable, unsuitable or inferior in quality,

damaged, or not of the required standard it shall be removed by the sub-contractor forthwith at his own

expense. Suitable material approved by the Project Architect shall be substituted for any rejected.

1.6.5 The sub-contractor shall remove from the site all his packing cases, rubbish and other debris and prevent

the accumulation of such materials. On completion all parts shall be left clear.

1.7 Technical and Construction Details of Equipment

1.7.1 The information to be supplied by the sub-contractor in section 5 of this specification shall be

completed by the sub-contractor and submitted by him at the time of his tender together with any

illustration or other details requested herein.

1.8 Site Inspection

1.8.1 The sub-contractor shall be deemed to have visited the site before submitting his tender and to have

satisfied himself as to the local conditions with regard to accessibility of the site, the full extent and

nature of the work, the supply of and conditions affecting labour, messing, toilets, carriage, cartage,

unloading, tools, accommodation, scaffolding, hoisting, craneage, ladders and anything which may

influence his tender for carrying out the total work to the true extent of this contract, whether the work

is definitely mentioned herein, shown on the drawings, or not, providing the same are reasonably and

obviously to be inferred therefore.

1.8.2 No subsequent claims for any extra costs incurred by the sub-contractor in carrying out works not

included for in this specification but the necessity for which could have been foreseen by the sub-

contractor by inspecting the site will be considered by an Project Architect.

1.8.3 Cost of Testing Materials

1.8.4 The Project Architect shall have the power to charge against and recover (by reduction or otherwise)

from the sub-contractor the cost of testing materials or articles which may have to be submitted to the

Project Architect for testing and which upon test are found to be faulty or not in accordance with the

requirements of this specification. The cost of such testing shall be added to the contract sum where

tests for the components comply with the requirements of this contract.

1.9 Protecting, Drying and Cleaning the Work.

1.9.1 The sub-contractor shall be responsible for the protection of his work during execution and for any

necessary casing and protection after the sub-contractors work has been executed.

232

1.9.2 At the expiration of the contract, the sub-contractor shall completely clean the lift car interior, landing

entrance, all signal and operating fixtures and leave in pristine condition to the approval of the Project

Architect and the employer (ADB).

1.9.3 Where installed work is considered to have been damaged by others, the evidence shall be immediately

brought to the attention of the Project Architect. Liability of any damage will be allocated together with

the responsibility for reimbursement of any expenses.

1.9.4 The Project Architect must be notified of the damaged work, which will be subject to inspection before

remedial work commences.

1.9.5 In the event of any conduit, cable run or other items of equipment being damaged after installation and

prior to the works being handed over, the sub-contractor will be responsible for ensuring that such items

are reinstated in a perfect condition.

1.9.6 The sub-contractor shall cover up and protect the work from rough treatment, dust, grit, frost or injury

from other causes.

1.9.7 The lift equipment shall be handed over to the main contractor at the completion date by the sub-

contractor perfectly clean of all surplus oil and grease and with all finishes unimpaired.

1.10 Defects Liability and Maintenance Period

1.11 The Contractor shall be responsible under the Contractor for addressing/correcting all of the

(Mechanical Engineering Services (MES) Contract Works defects occurring within a period of SIX

MONTHS, commencing from the date of the PRACTICAL COMPLETION CERTIFICATION.

During the Defects Liability Period, the Contractor shall provide prompt and effective “call back”

service to attend to any urgent faults which may develop and which would affect the day-to-day

function of the building complex.

The Contractor shall retain a written log on site recording the details of the defect – i: e, date

notified/date attended, fault identified, action taken, together with any ongoing investigations/remedial

work.

The sub-contractor shall include for giving full instructions as to the running and operation of the lift

to the employer’s appointed staff.

1.12 Assignments or Sub-Letting

1.12.1 The sub-contractor shall not without the written consent of the Main Contractor or the Project Architect

which consent may be given subject to such conditions, if any, as the employer may think fit to impose,

transfer, assign or sub-let, directly or indirectly, the contractor or any portion thereof for the benefit or

burdens thereof to any person, company or firm.

1.12.2 Provided that nothing in this condition shall operate to prevent the sub-contractor from sub-letting any

portion of the contract where such sub-letting is customary in the trade. The Project Architect will

require written details of the major sub-contractor including a schedule of information as requested in

item 1.4.1 before orders are placed.

1.12.3 Where sub-letting takes place the sub-contractor shall be responsible for the observance of these

conditions by the sub-contractor and shall be responsible to the employer in respect of any claim

resulting from his work.

233

1.12.4 Target Programme

The agreed programme for the completion of this contract is of the essence and the sub-contractor must

ensure that he has sufficient and adequate materials and labour to meet his commitment to this contract.

2.0 TERMS AND INFORMATION

2.1 Schedule of Builders and Electrical Works (To be Included as Part of the Contract)

2.1.1 Builders Work in Machine Room

The Main Contractor shall be responsible where applicable for the cutting and forming of holes as

marked out on site by the sub-contractor.

2.1.1 All holes, within the motor room floor shall be fitted with steel plates to reduce the apertures to the

operating minimum and provide a half hour fire resistance.

2.1.2 The hoist machinery shall be protected by a fixed handrail fitted around the designated area. The

standard size of the handrail should be 1200mm from finished floor level and have an intermediate rail

fitted at 600mm from floor level.

2.2 Builders Work in The Lift Well

2.2.1 Provides substantially constructed hoardings to protect the lift erector and lift equipment. It shall be

constructed with timber framing with plywood panels. The temporary protection shall be so designed

not to obstruct the means of access or escape and shall be securely fixed to the building fabric as

required. The access door to have displayed a notice stating “DANGER – MEN WORKING” with

minimum 2” characters.

2.2.2 Provide landing push station apertures to accommodate the combined push and indicator assemblies.

2.2.3 Provide general attendance on the lift engineers throughout the installation period.

2.2.4 Make good all adjacent walls, ceilings and floor finish should they be inadvertently damaged by the

sub-contractor and redecorate around the openings. The sub-contractor shall be responsible for ensuring

that all other finishes within the immediate landing area are suitably protected against damage by his

personnel or equipment as necessary.

2.2.5 Provide an enclosed lockable area adjacent to lift motor room at basement level to create a working

area.

2.2.6 All shaft division screens to be provided to a height of not less than 2.5m.

2.3 Electrical Works

2.3.1 A mains supply shall be installed by others for the lift and shall terminate in a Fuse Switch Disconnector

mounted in the lift motor room. The supply shall be suitably rated for one lift.

2.3.2 A lift ancillary’s distribution board installed by other shall provide supplies for car signals, car lighting,

emergency lighting and shaft lighting. The position of the distribution boards shall be directly above

the mains isolator adjacent to the machine room door.

2.3.3 Provide task lighting within the machine room and lift shaft throughout the course of the erection.

2.3.4 Provide in an agreed position in the machine room an auto-recharge unit for lift car emergency lighting

and alarm bell. The supply for this facility shall be from the lift ancillaries’ distribution board and the

sub-contractor shall install the necessary wiring from the secondary side of these devices. The device

shall be activated by the loss of the car light supply.

234

2.4 Sub-Contractor To Note

2.4.1 The sub-contractor shall install all the necessary wiring for lift and accessories as defined in this

specification, in accordance with the IEE regulations and the 17th Edition and current practices. All

electricians to be Electricity Distribution Services Authority (EDSA) approved sub-contractors.

2.4.2 The sub-contractor will be responsible for hoisting, craneage, handling and off-loading the lift

equipment and moving them into position into the machine room, control area and lift well.

2.4.3 The only storage available will be in the enclosed lockable areas adjacent to the motor room at

Basement Level.

2.4.4 The sub-contractor shall be in accordance with the Health and Safety at Work Act, be responsible for

ensuring that all landing entrances are properly protected whilst his engineers/technicians are carrying

out the works detailed in this specification.

2.4.5 Access for delivery of materials by arrangement.

3.0 SCHEDULE OF EQUIPMENT

3.1 8-Passenger Electric Lifts - 1

Electric Passenger Lift (Underslung)

Load 630Kg (8p)

Speed 1.6m / s (levelling + /-6mm)

Travel 12m

Stops/Openers 3 in line

Shaft 2.5m wide x 2.5m deep (for 1 lift)

Headroom 2.1m

Pit 1500 mm

Car 1270mm wide x 1400mm deep

Car doors 800mm x 2m centre opening

Landing doors 800mm x 2m centre opening

Position indicator in car and at ground floor

Hall lanterns All floors

NOTE:

Tenderer are requested to visit the site to confirm the dimensions of the existing lift facilities at the

Bank

4.0 MACHINES ROOM EQUIPMENT

4.1 Lift Machine (Electric Lift)

4.1.1 The lift machine shall comply with the following:

(1) The worm shaft and worm shall be machined from a single steel forging and the worm wheel rim shall

be centrifugally cast phosphor bronze hobbed to provide accurate alignment with the worm.

(2) The ratio of sheave diameter to worm wheel pitch circle diameter shall not be less than 1.75:1

(3) The winding machine, motor and divertor shall be mounted on a prefabricated steel raft. The sub-

contractor shall provide and install suitable density rubber sound absorbent isolation to prevent the

transmission of noise and vibration from the machine and steelworks to the building structure.

(4) The lift shall stop with + or –6mm of the selected floor.

235

4.1.2 Motor

The hoisting induction motor shall be suitable for the supply detailed in Section 3 hereof, and shall

have a speed not exceeding 1500rpm. It shall run at all loads without appreciable noise or hum and the

rotor shall be specially constructed for variable A.C operation. The motor will bear the motor makers

nameplate.

4.1.3 The hoisting motor shall have a duty cycle of not less than 240 starts per hour.

4.1.4 Traction and Divertor Sheaves

4.1.5 The traction sheave shall have a diameter of not less than 600mm. Means shall be provided to prevent

the suspension ropes leaving their grooves.

4.1.6 Hydraulic Lifts-Machinery and Pump Unit

This equipment shall be of compact design, of ample capacity for the duty, fitted with generous size

bearings. It shall be of a type designed for the particular purpose, properly aligned and balanced to

eliminate vibration.

The lift machinery shall in general be rated for running on lift duty and be of adequate size for operating

the lift at the contract speed when carrying the contract load.

The pump unit shall be complete with valve assembly incorporating control and emergency safety

features.

Hydraulic piping and fittings shall be designed for use on hydraulic systems and shall be of first class

quality.

Hose connections shall be reinforced with wire braid and oil resistant.

The ram shall be cylindrical with a smooth external surface.

Hydraulic oil of high quality shall be used and provided under the contract.

The oil tank shall be vented to atmosphere.

4.1.7 Power Control

The lift power control system shall be of variable speed AC type, utilising full voltage control or direct

current braking.

4.1.8 Control to the motor shall incorporate adequate means to smooth the transition from high to low speed;

alternatively, a suitable flywheel will be fitted to the motor.

4.1.9 The power system shall prevent the machine starting unless the car doors are in the closed position and

all landing doors in the close position.

4.1.10 Control System

A full collective control system shall be provided with the following features:

i. The control system shall be micro-processor based.

ii. Car and landings calls should be stored in the system after operation of the respective push.

iii. The car and landings calls will be cancelled marginally before or during the opening cycle at the

appropriate landing.

iv. Car calls should be answered in the order in which destinations are reached, irrespective of the

sequence in which they are registered.

v. The car will incorporate an automatic load weighing feature which will detect the 10% overload

situation, this shall prevent the door closing and the lift moving in addition to illuminating an

indicator and sounding a buzzer fitted in the car station

236

4.1.11 Controller

The control equipment shall be totally enclosed in a steel cabinet with louvered ventilation and a hinged

door to the front only shall be fitted for exposing all components for accessibility.

4.1.12 All components, relays, contactors, fuses, overloads, etc. shall be suitably identified and a nomenclature

listing the various functions shall be provided with the circuit diagrams.

4.1.13 The control circuit voltage shall be either AC or DC but whichever system is utilised, the secondary

side of any relay circuits shall be earthed via a common link/bar on the panel. All relays and contactors

shall fail-safe.

4.1.14 Any timing devices incorporated with the design must utilize capacitors, resistors, thyristors or other

similar devices. Mechanical or oil damped timing devices will not be accepted.

4.1.15 All hoist motor windings must be protected with thermistors/overloads that are fully adjustable to trip

approximately 20 seconds after a fault condition occurs.

4.1.16 A device shall be incorporated within the panel to detect a loss of one phase or a phase reversal. Where

the device detects one of the above conditions then a switch relay or contactor shall become open circuit

removing the supply to all contactors and control panel circuitry.

4.1.17 A test facility incorporating the direction buttons only as detailed in 4.2.13 shall be incorporated in the

control panel. This facility shall not override the car top control station.

4.1.18 Over speed Governor to Car

An over speed governor with governor rope and tension pulley frame hall be provided designed to meet

the respective tripping speed specified in the current edition of the BS5655.

4.1.19 Machine Location Switch

A “stop/run” switch is to be installed adjacent to the machine. This device shall be identical to the pit

isolation switch, which is to be fitted at a height to allow easy and safe operation. The device is to be

labelled as for the pit switch.

4.2 CAR ENCLOSURE FRAME

4.2.1 Car Frame

The car frame shall sustain a fully loaded car without permanent deformation fitted with oil retardant

car isolation rubbers of suitable resistance and density. Four self-adjustable sliding types guide shoes

fitted with renewable liners shall be used.

4.2.2 The “load weighing” switch shall be fixed to the underside of the car platform. Alternatively, an

electronic measuring device fitted to the crosshead will be acceptable. A data plate expressing the lift

details shall be fixed to the car crosshead.

4.2.3 Safety Gear

The safety gear fitted to the car frame shall be of the progressive type and operated by an over speed

governor designed such that the gear will release by lifting the car. The gear to be tested to BS5655 and

requisite certificate provided.

4.2.4 Car Enclosure

The enclosure shall be constructed in timber and /or steel which shall be treated with an anti-drumming

compound. For timber cars the external surfaces to be lined in 0.018swg sheet steel painted black,

alternatively, painted with an equivalent fire retardant paint.

237

4.2.5 Special consideration shall be given to transmission of vibration from the machinery and general shaft

noises. Therefore, where steel cars are installed, anti-drumming and noise absorption pads shall be

bonded to the car exterior.

4.2.6 Internal Finishes

Side walls and Rear Wall Laminated demountable panels to approved design.

Rear wall (passenger lift only)

A tinted safety mirror of the size up to the line of suspended ceiling frame and the full width of the rear

wall shall be fitted in 13mm linish stainless steel with mitred corners.

Handrail (pass. lifts only)

Stainless steel to side and rear walls

Ceiling Indirect lighting incorporating 3 hour maintained emergency car lighting through suspended

ceiling with stainless steel frame divided into two areas, each with egg crate diffusers.

Pass lifts. Timber bumper rail – hardwood on 3 sides.

Floor covering

Pass lifts. Carpet

Pass lifts. 6mm ribbed rubber – black.

Entrance Front 16 SWG patterned/coloured stainless steel

Telephone: A suitable stainless steel carpet shall be provided to accommodate an approved

instrument.

Ventilation: The roof of the enclosure above the suspended ceiling shall have concealed

apertures provided above the line of the side and rear wall finishes fitted with

metal cowls externally.

Drapes and hooks Provide suitable drapes and hooks.

4.2.7 Final Car Details will be Subject to Approval.

The car roof shall so be designed and constructed as to withstand without permanent deformation

personnel working thereon, with at least one clear area for standing of a minimum of 0.23 metres square,

with the lesser dimension a minimum of 0.25m. It shall be extended where required to prevent any void

being created to the rear of the car.

4.2.8 The car lights will be controlled from a switch in the machine room provided under the electrical

requirements of this contract.

4.2.9 Load Details

The load details shall be engraved in the car station panel. This together with the data plate on the car

crossheads shall be expressed in metric characters to BS5655 dimensions and filled with an epoxy resin.

4.2.10 Signal and Operating Devices

The car operating station shall be fitted within the car front return and the faceplate secured by non-

visible fixings. A key operated independent service switch, door open and alarm buttons shall be

provided in addition to the call pushes.

238

4.2.11 The push buttons shall be of a single column arrangement. The key switches, door open and alarm

button and the overload indicator shall all be of the same module. All faceplates shall be of stainless

steel.

4.2.12 A call registered illuminated signal shall be incorporated within the car and landing push buttons.

4.2.13 An alphanumeric digital car position indicator will be provided within the car station panel.

4.2.14 On the car a mechanic control station containing maintenance and testing switches, direction push

buttons and a 12-ampere BS 1363 socket outlet. A 40 watt, pearl lamp of the ‘rough service’ type

complete with substantial wire guard shall be fitted on the control station for the use of maintenance

engineer, the lamp being supplied by the sub-contractor.

4.2.15 Extra costs to be indicated in the offer for the supply of Braille markings on all operation faceplates

coupled with speech synthesisers in lift car.

4.3 CAR AND LANDING ENTRANCES EQUIPMENT

CAR AND LANDING DOOR ARRANGEMENT

4.3.1 The car and landing doors shall comply with the following.

(i) Be two centre stainless steel sliding doors, treated internally with anti-drumming compound.

(ii) Have a profiled section metal sensitive edge protection device fitted to the leading edge of the car

door only, details to be supplied in Section 5 of the specification.

(iii) Give a clear opening as indicated in Section 4.3.

(iv) Sills – aluminium.

(v) Fascia boards to the landing sills of steel construction of not less than 16swg the width of the

entrance and full height from the header of one floor to the sill of the floor above.

(vi) The cars shall be fitted with a toe-guard to the car sill of steel construction of not less than 16swg,

the width of the entrance painted as detailed in clauses 5.6.6 to maximum depth to suit the existing

pit dimensions. Modify the existing as required.

(vii) The horizontal distance between the car sill and each landing sill shall not exceed 30mm.

(viii) A single infrared pencil beam light ray shall be fitted to the leading door panel; the projection of

the beam shall be through the leading edge with the smallest practical aperture onto a reflector on

the slam side of the car. The reflector shall be fitted flush within the column. The height of the

beam shall be between 300 – 400mm high. Alternatively provide a Visolux Unit, projecting a

light beam onto a landing area.

(ix) Provide and fix full depth architraves in stainless steel.

4.3.2 Automatic Power Operation of Car Door

A GAL type or equivalent automatic door operator shall be of the highest quality and shall provide

smooth harmonic motion of the car and landing doors. A solid guard shall be fitted to the operator

driving mechanism. The following requirements shall also be maintained:

(i) It shall be driven by an electric motor in both opening and closing directions and tested for

compliance with BS5655 kinetic energy by using an approved device.

(ii) Car door shall only operate on normal service while the car is in the levelling zone of a particular

floor.

(iii) The lift shall normally ‘park’ with the doors closed, but with an option to park open.

(iv) The motor shall stop, reverse and fully re-open the car door in the event of the sensitive edge

protective device or light ray being obstructed or interrupted while closing.

(v) A ‘door open’ button shall be provided in the car and it shall be operative only while the car is

stationary with the car door coupled to a landing door.

239

4.3.3 Signal and Operating Fixtures

(i) All signal and operating boxes shall be fitted with faceplates Stainless steel.

(ii) The landing stations are to consist of single riser of pushes at each floor, of same design and

manufacture as the car pushes. Each shall include indication for call acceptance.

(ii) An alphanumeric digital indicator shall be installed at ground floor, within the landing station

apertures provided.

(iii) Hall lanterns shall be provided at all other floors.

4.3.4 Locking Devices and Switches for Car and Landing Entrances

4.3.4 Provisions shall be made for fully opening each door by an authorised person by the aid of a key to fit

an unlocking device in one door panel, irrespective of the position of the lift car.

4.3.5 The key shall be of steel section material and the access to each lock shall be restricted to this key. No

fixing screws shall be accessible from the landing. The force necessary to operate and release the door

will be such that unauthorised use of the release mechanism (by the use of screw driver, pliers, etc.)

will be more difficult.

4.4 Lift Shaft, Counterweight and Pit

4.4.1 Guides and Fixings

Car and counterweight guides of machined to be as detailed in 5

4.4.2 Buffers

Energy accumulation type buffers shall be installed under the car and counterweight and the sub-

contractor shall supply and install all necessary associated steelwork for the mounting and fixing of

these buffers. The steel buffer supports shall be of robust construction securely fixed between their

respective guides and be of sufficient height to maintain the necessary over travel of the lift, to comply

with BS5655: Part 1 latest edition as far as possible within the existing parameters. The sub-contractor

shall also provide the requisite test certificate for the buffers to comply with BS5644. Concrete

supporting piers will not be acceptable.

4.4.3 Suspension Ropes

The Requirements regarding suspension ropes are as follows:

(i) At least four suspension ropes shall be used. Their normal diameter shall be not less than 11mm.

(ii) They shall be attached to the top of the car frame and the top of the counterweight by means of

bulldog grips and thimbles used with eyebolts.

4.4.4 Counterweight and Screen

The counterweight is to balance the lift car to 45/50 % of the contract load.

4.4.5 A counterweight screen shall be provided to a height not less than 2.5m high.

4.4.6 Emergency Signal

An audible alarm signal shall be fixed in an approved position above the ground floor landing entrance

within the lift shaft, and on the roof of the lift car.

4.4.7 Limits and Switches

An ‘UP’ limit is to be incorporated in the control circuit so that when the test switch is in the ‘TEST’

position and ‘UP’ button depressed, the car shall stop high enough to facilitate inspection and

maintenance of any equipment at the top of the lift shaft but low enough to ensure that a 6ft. tall person

standing on top of the car shall be in no danger of coming into accidental contact with any overhead

equipment or structure.

240

4.4.8 A robust emergency stop facility to meet the requirements of BS5655 with ‘STOP’ and ‘RUN’ positions

clearly marked shall be supplied and installed in the lift pit, in the machine room adjacent to the

machine. When placed in the ‘STOP’ position, will cause the lift to stop and prevent it being started

until placed in the ‘RUN’ position. The switches to be suitably labelled ‘STOP’ and ‘RUN’.

4.4.9 The lift will have terminal slow down switch or shaft limits to slow down or stop the lift in a controlled

manner at each terminal floor, in the event of a circuitry or selector malfunction.

4.4.10 Any inductor (proximity switch) used on this system shall be identified in Section 5 of this specification

and their proposed operation shall be outlined in the tender documents.

4.5 Electrical Requirements

4.5.1 Main Switch and Wiring

A 3 phase HRC switch fuse shall be provided. The sub-contractor shall install all necessary wiring for

the lift from these units.

4.5.2 All cables, except travelling cables, in the lift shaft shall be enclosed throughout their length in heavy

gauge galvanised steel conduit or in galvanised steel trunking.

4.5.3 All trunking, conduit and associated fittings shall have a galvanised finish and made by a manufacturer

having a licence to use the British Standard Institution Mark. All trunking runs shall be at high level

and shall not run across the machine room floor.

4.5.4 All travelling cables shall run direct from the controller to the lift car termination box. Each flex shall

be looped over a timber collar or steel bar with adequate protection to the cable coverings, excessively

tight bends will not be acceptable.

4.5.5 P.V.C. coated kopex conduit shall be used only as approved by the engineer in cases where it is

necessary to provide for the adjustment or to reduce the transmission of noise and vibration and where

approval is given the conduit shall terminate in suitable couplings which shall positively grip the

flexible conduit, and an additional earth continuity conductor shall be run inside the conduit between

lengths.

4.5.6 All cables shall be manufactured by an approved maker and only one make of P.V.C. or travelling cable

which be used on this installation. All P.V.C. cables shall have a minimum area of not less than 0.35

mm sq.

4.5.7 P.V.C. insulated cable. These cables shall be 450 / 750 grade and insulated with high temperature grade

polyvinyl chloride and shall comply with BS6004 1969.

4.5.8 All travelling cables shall be terminated in the control panel. Where round flexes are fitted they shall

be hung down the lift shaft for at least 24 hours with their ends suitably weighted and free to rotate in

order to relieve these cables from any tendency to twist during service.

4.5.9 In addition to the half way anchorage point, clamps shall be fitted so that these shall be not more than

3m pitch between clamping points above the half-way point up to the machine room.

4.5.10 Test of cables – all cables and travelling cables shall be subjected at the maker’s works to be appropriate

voltage tests, tests for thickness of insulation,

Insulation resistance, fire resistance and flexibility as set out in the appropriate British Standard.

4.5.11 All wiring must comply with the 16th Edition of the IEE Regulations where applicable.

241

4.5.12 Earthing – a separate earth conductor shall be run in all conduit and trunking to every item of electrical

equipment from the earth termination in the control panel. This termination should in turn be connected,

by means of a suitable conductor, to the mains supply earth point.

4.5.13 A separate earth conductor in at least one trailing cable should connect the lift car equipment to the

control panel earth joint. Each section of trunking should be connected to the earth conductor by means

of brass screw, clamp washers, locking washer and nut.

4.6 Drawings, Notices, Paintings Etc.

Plans and Drawings

4.6.1 The sub-contractor must take all necessary dimensions on site during the progress of the works.

4.6.2 Before putting any work in hand the following working drawings shall be submitted for approval of the

engineer.

Item No. of Copies Description

(a) 3 General arrangement and builders work detail, shaft and

machine room

(b) 3 Car enclosure, car doors, landing entrance complete with

frame fixing details. (Where applicable)

(c) 3 Car design, perspective and manufacturing drawings.

4.6.3 After approval, items (a) and (b) five copies of each shall be submitted plus one further copy of each

printed on approved type plastic not less than 0.05mm thick shall be supplied.

4.6.4 On completion of the work, the sub-contractor shall provide and fix in the machine room a suitably

mounted “straight line” and “as wired” set of wiring diagrams of all electrical apparatus of the lift as

actually wired and fitted showing the arrangement and markings of all connections. These diagrams

shall be ozakerline or equivalent finish. A complete set of manuals shall be provided for the employers’

record purposes (2 sets)

NOTICES Etc.

4.6.5 All notices to be in white ivorine or equivalent laminate, with characters 13mm high in red. The word

“Danger” to be in red, 20mm high. The size of notice and wording to meet with the Project Architect

approval

The sub-contractor shall: -

1. Provide and fix on the machine access door the permanent notice required in BS5655: Part 15.4

2. Provide and fix an electric shock notice in the machine room.

3. Provide a rubber mat in front of the controller cabinet and to the rear where access is required.

4. Provide diagrammatic and worded hand winding instructions adjacent to the machine

approximately 450mm long x 300mm high.

5. The pit adjacent to the pit stop switch, a notice warning maintenance personnel of the restricted pit

depth.

6. On car top to warn maintenance personnel of the restricted headroom.

4.6.5 Painting

All equipment shall be suitably prepared, primed, undercoated and then painted with an approved

colour before shipment to site. All shaft steel work shall be painted two coats of black machine paint

after erection.

242

4.6.5 Any steelwork that will not be accessible after erection shall be painted with red oxide paint (paint of

similar protective quality) before installation.

4.6.6 Silent Operation

Every precaution shall be taken by the sub-contractor to ensure quiet operation of the new equipment.

Every precaution shall also be taken to prevent vibration being transmitted to the building structure.

The sub-contractor must indicate in Section 5 the proposed methods he will adopt to obtain quiet

operation.

4.6.7 For the guidance of his main contractor, the sub-contractor shall, during the progress of the work, mark

out the positions of all holes that are not shown on the builders work drawings approved by the engineer.

4.6.8 Entrance Barrier

A removable entrance protection barrier, for use during the maintenance of the lift, shall be provided

and kept on site in the machine room.

4.6.9 The barrier shall be collapsible of sound construction, painted safety yellow, and shall have suitable

worded “DANGER” notices fitted.

4.6.10 Radio and Television Suppression

All electrical equipment shall be provided, as necessary with suppressors to prevent interference to

radio and television equipment within the premises. Upon completion of the lift installation, the sub-

contractor shall notify the British Telecom engineers to test the installation to confirm compliance with

BS800 and shall provide written proof to this effect to the engineer.

4.7 Schedule of Testing and Finishing

4.7.1 Commissioning

The sub-contractor will be required to fully test the whole works to BS5655 after the completion of

installation and to provide all tests weights, thermometers, instruments and personnel to fully

commission the project to the satisfaction of the engineer. Commission should include trail operation

of all parts for fine adjustment, lubrication and the like by the sub-contractor to ensure that the works

are properly commissioned.

a) Specific requirements are as follows:-

(i) The sub-contractor shall, as soon as practicable after the installation is in a state of physical

completion commission and test the same in accordance with the requirements of the

specification. In this clause the term “installation” shall be read to include any completed sub-

contract works or any part (s) thereof, which it may be required to commission, test and/or operate

as separate entities. The sub-contractor shall agree a full commissioning and testing programme

with the engineer. The engineer shall be given 10 full working days notices of the intention to test

or commission any part or section of the works. Only when the sub-contractor has satisfied

himself that the system has been properly regulated and is operating correctly may he offer this

system for inspection. During inspection he will be requested to prove compliance with design

intent.

(ii) The sub-contractor shall make complete records of the tests as carried out and when the tests have

been successfully completed he shall provide the engineer with test records and reports in a

form to be agreed.

(b) Commissioning

The sub-contractor shall be responsible for all the tests to ensure the proper functions and

operations of the lifts under this contract.

243

Before the lifts are accepted and put into service the lifts shall, under the supervision of the

engineer pass all tests, detailed within this clause or as required by the engineer during

commissioning.

i. 10% overload test

ii. 60 minutes full load test

iii. Motor current and speed test

iv. Door inspection and tests

v. Electrical insulation resistance to earth test

vi Earth continuity resistance test

vii. Full operational safety-gear tests

viii. Buffer test full load and speed

ix. Overload test (electrical)

x. Brake test 25% overload

xi. Electrical protection device tests

xii. Levelling device tests

xiii. Car balance tests.

The sub-contractor shall also carry out any other tests required by the engineer in order to prove

that the equipment complies with the contract

Documents, codes and regulations covering equipment supplied under this sub-contract.

Generally the lift shall be made to run under various loading conditions from no load to 10%

overload in order to check its operation and floor levelling accuracy.

The 10 % overload test is to ensure that the equipment installed has ample safety margin above

the rated load incorporated in the design.

The lift shall also be subject to 60 minutes test with the car fully loaded during which it shall stop

at each floor in the up and down direction opening and closing its doors at each stop. The test

shall be continuous, the stops being 10 seconds maximum duration, with the door open. During

the test, the equipment shall not overheat, spark excessively, become noisy or operate in a faulty

manner.

All the tests shall be carried out in the presence of the engineer and the results shall be signed and

recorded in a tabulated form for easy checking and reference.

4.7.2 Finishes Schedule

(i) Car mirrors to be 6mm thick toughened and tinted safety mirror as supplied by Chealsen Artisans

or approval equivalent

4.8 Lift Maintenance

i The lift contractor shall carry out servicing on a lubricate clean and adjust basis, including all

attendances to breakdowns during normal hours of working. Attendance to breakdowns during

normal hours must not exceed 2 hours from the time the call is received by the company. No

attendance unless at the specific request of the employer. Any repairs that cannot readily be

completed during normal hours shall be attended to at immediate commencement of the next

normal working day.

ii If, during the defects liability period, any defect or faults develop which, in the opinion of the

engineer is due to faulty materials, workmanship or design of components, then the lift contractor

shall replace these at his own cost.

244

iii Following acceptance of the completed lift installation, regular maintenance shall be carried out

every month and shall include the cleaning, oiling, greasing, and adjusting of all parts of the lift

and accessories as necessary to ensure satisfactory operation if the lift including checking of

levelling and making any necessary adjustments for a period of 12 months from the date of

acceptance of the lift.

iv The lift contractor will not be permitted to store cleaning materials, grease or oil in the pit or motor

room, and those areas including the lift itself to be kept clean and free from rubbish.

v The sub-contractor shall immediately renew all lamps in and on the lift cars which may be found

at the time of inspection to be defective. Including all shaft lighting lamps

vi Whenever the lift is not available for service whilst the lift contractor is working on or inspecting

it, the lift contractor shall provide and display a suitable notice at each entrance of the lift under

inspection to indicate that the lift is not available for service.

vii Following each inspection a report is to be forwarded to the engineer within one calendar month.

All reports shall:

a) Relate to one inspection of the lift.

b) State clearly the work done and adjustments made and indicate which car and/or landing

indicator lamps if any were renewed at the time of inspection.

c) Certify that the lift is or is not in satisfactory or serviceable condition.

d) Give details of attendance to any breakdowns during the period since the date of the preceding

inspection report.

viii During the maintenance and defects liability period the sub-contractor shall provide all cleaning

materials and necessary lubricants. Throughout this period the sub-contractor must be prepared if

and whenever so required, to make visits during normal hours in case of emergency and

breakdowns and shall indicate in Section 7/C telephone number(s) to be used for such calls.

ix The sub-contractor shall include for giving full instructions as to the running and operation of the

lifts to the employer’s appointed staff.

4.9 Annual Maintenance Agreement

i The successful Tenderer will be required to undertake the annual maintenance of the completed lift

on a fully comprehensive contract for an agreed term, commencing at the expiration of the defects

liability period.

ii Tenderer are to submit a ‘specimen’ maintenance contract for the above lift to accompany their

tender for the said contract works.

iii The annual maintenance agreement will be subject to a separate defects liability period.

iv The maintenance contract shall be calculated on price fluctuations in accordance with N.A.L.M.

indices and shall be received by the engineer on or before the time and date stated in the invitation

to tender.

vi The acceptance of the tender for the new lifts does not bind the employer to accept the tender for

the lift maintenance contract following expiration of the defects liability period.

245

5 TECHNICAL AND CONSTRUCTION DETAILS OF EQUIPMENT

LIFT 1

The following information shall be supplied by the sub-contractor when submitting his tender:

Where items of equipment are being retained, then the relevant details shall be provided below:

GUIDES

Car guide size …………………………………….………………………..………

Maximum pitch of fixings…………………………………….……………………………

Counterweight guide size …………………………………….…………………………

Type of existing fixings …………………………………….…………………………

BUFFERS

Car – No. and type

Counterweight – No. and type……………………………………..…………………………

Rate of retardation – car and Counterweight …………………………………………………

CAR AND FRAME

Approx. weight of new car and sling ……………………………..……………………………

Dimensions of adjustable guide shoes. …………………….……………………………

Construction of guide shoes and type of their …………….……………………………

Type of overload sensing device ……………………………..……………………………

246

DETAILS OF ELECTRO-MECHANICAL LOCKS AND OTHER DOOR SECURING

DEVICES:-

INDUCTOR SWITCHES

Type …………………………………………………………………

Maker ………………………………………….………………………

Number used in this system ……………………………………………….…………………

TYPE OF DOOR SAFETY DEVICES

Type of lock on landings ………………………………………………….………………

Type of emergency release mechanism ………………………………………..…………

Type of door safety edge ……………………………………………………….…………

Type of car/landing door coupler …………………………………………………………

Door gear manufacturer and ty…………………………………………………………………

AUTO-RECHARGE UNIT

Type …………………………………………………………………………

Maker …………………………………….…………………….…………..…

Total power output …………………………………………..………………………………

Consumption of

- Emergency lighting …………………………………………..………………………………

- Alarm bells …………………………………………..…………………………….…

Capacity

(Emergency lighting only

LIFT MACHINE

Maker of main reduction gear ………………………………………………….………………

Pitch circle diameter of worm wheel Ratio……………………………………………………..

Effective diameter of traction sheave …………………………………………………….…….

Effective diameter of divering pulleys…………………………………………………………..

Hoisting motor rating ……………………………………………………………………………

Make of hoisting motor…………………………………………………………………..………

Type of bearing …………………………………………………….……………….……..

Hoisting motor (with full load)-starting ………………ampere

-running ………………ampere

247

MOTOR PROTECTION

Supply…………………………………………………………………………………………

Type……………………………………………………..…………….……………………….

Type for overload to tip on low speed stall ……………………….……………………………

Time for overload to trip on high speed stall…………………………………..…………………

BRAKE ASSEMBLY

Manufacturer ………………………………

Size of shoes …………………………….…

Coil Voltage …………………………….…

Amperage ……………………………….

SUPPLIER OF CAR ENCLOSURE…………………………………………………….

…………………………………………………………………………………………

CONTROLLER Maker of controller ……………………………………

Type ……………………………………

Control of voltage ……………………………………

Method of achieving lamp reliability ……………………………

REGULATOR

Manufacturer (not supplier) ………………….…………………

Type ……………………….……………

248

5.1 PROPOSED METHOD OF MACHINE ISOLATION AND SUPPLIER

NAME OF BUILDER AND ELECTRICAL CONTRACTOR

TELEPHONE NUMBER(S) TO BE USED FOR EMERGENCY CALLS

NAMES AND ADDRESS OF PREMISES WHERE LIFT INSTALLATION SIMILAR TO THE

ONE BEING OFFERED MAY BE INSPECTED BY ENGINEER:

This Schedule must be completed in every particular, signed, dated and returned with the Tender and

full details of any deviations from the specification and any other required and necessary information

from the lift contractor to be clearly set out on a separate sheet as an additional schedule of particulars

to be submitted by the lift contractor with his tender.

NAME OR TRADING NAMES OF FIRM TENDERING ………………………………

…………………………………………………………………………………………………

ADDRESS……………………………………………………………………………………

…………………………………………………………………………………………………

DIRECTORS SIGNATURE…………………..…… DATE…………………...……

249

6.0 WORK PROGRAMME

6.1 LIFT PROGRAMME START ON SITE

1. Delivery date of equipment to site (from receipt of order) ………...weeks

2. Site installation for removable hoardings, builders and electrical

works before lift work commences ………………...weeks

3. Site installation of all lift works ………………...weeks

4. Total period for preparation of drawings, settlement of all details

ordering and delivery of materials and installation of equipment

from receipt of order …………………weeks

5. Lift tender open for acceptance from date of tender ………..………..weeks

We certificate that two electric passenger lifts all in accordance with the preceding specifications is (in

words and figures)

USD = = = = = = = = = = = = = = = = = = = = = =

NAME OR TRADING NAMES OF FIRM OF TENDERING ……………………………………

…………………………………………………………………………………………………..

ADDRESS……………………………………………………………………………………...

………………………………….…………………………………………………..…………..

………………………………………………………………………………………………….

DIRECTORS SIGNATURE……………………. DATE…………………………

250

6.2 SUMMARY TENDER

OFFICE BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA

LEONE FIELD OFFICE AT THE AFRICAN DEVELOPMENT BANK (ADB)

LIFT INSTALLATION TENDER

For the whole of the works including the following:-

1. Supply and installation of One Electric Passenger lifts 1

2. Any other item not covered above please detail.

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………..

……………………………………………………………………………………..……………

…………………………………………………………………………………………………

…………………………………………………………………………..………………………

Sub-Total USD………………………………………………

Add 1/39th Main Contractor’s discount.USD........................................................................

Grand Total to be carried to Form of Tender. USD = = = = = = = = = = = = = = = =

Signature of Tenderer………………………………………….

Name and Address:……………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

Telephone no……………………………………… Date…………………….……….…

251

SPECIFICATIONS FOR THE CONSTRUCTION OF BOREHOLE WITH MAINS/SOLAR

POWERED PUMP COMPLETE WITH PIPE AND ACCESSORIES FOR OFFICE BUILDING AT

REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE

AFRICAN DEVELOPMENT BANK (ADB)

252

TECHNICAL SPECIFICATIONS (CONSTRUCTION OF BOREHOLES WITH MAINS/SOLAR

POWERED PUMPS)

[FOR THE BOREHOLE CONSTRUCTION, THE CONTRACTOR SHALL REQUIRE THE SERVICES OF A SOUND AND

EXPERIENCE HYDROGEOLOGIST EQUIPPED WITH THE REQUIRED GADGETS TO ASCERTAIN THE PREFERRED

WELL LOCATION]

1. SUMMARY OF WORKS

1.1 PURPOSE

This Standard Operating Procedure (SOP) describes the process of Borehole-well construction for the

Office Building at Regent Road, Hill Station, Freetown for Sierra Leone Field Office at the African

Development Bank (ADB).

1.2 SCOPE

This SOP is a mandatory document and shall be implemented by the Contractor when constructing the

Solar Powered Borehole well for the ADB Project.

Note: Subcontractors performing work under the ADB Project shall follow this SOP for constructing

the well or may use their own procedure(s) as long as the substitute meets the requirements

prescribed by the ADB Project Quality Management Plan, and is approved by the Project

Architect before the commencement of the designated activities.

1.3 TRAINING

1.3.1 The Contractor’s personnel shall be trained by reading the procedure and the training shall be

documented in accordance with this specification for borehole construction.

1.3.2 The Contractor’s Field Team Leader (FTL) shall monitor the proper implementation of this procedure

and ensure that relevant team members have completed all applicable training assignments in

accordance with the specification.

1.4 SCOPE AND APPLICATIONS

The specifications in the Works under this Contract cover both general and particular technical

specifications with respect to civil and installation works for

(a) Drilling and testing of deep boreholes including installation of PVC casings and screens,

construction of platform for borehole. The borehole to be drilled shall be fitted with casing and

screens of internal diameter 6 inches (150mm). The borehole shall be drilled within the Sierra

Leone Field Office at the African Development Bank (ADB) where there is no existing borehole

for fitting with submersible pumps.

(b) Supplying of materials and installation of pipes and submersible pump. Armatures and fittings,

supply and installation of water distribution system components (e.g. tower/ water tanks, etc.)

and construction of and pump house for distribution networks will be undertaken by the Main

Contractor.

(c) Any other civil works involved

The quantities of works stated in the Bill of Quantities shall be considered as estimated, while the real

quantities will be the one executed, stated in measurements and approved by the Project Architect or

his representative. Payments will be made based upon measured and actually executed works.

The Contractor is obliged to perform all works in accordance with the technical specifications, the

indicated norms and standards or the instructions of the Employer or his representative.

253

1.5 CLAUSE NUMBERS

Unless otherwise stated, all clause numbers refer to the clauses in these Specifications.

1.6 DEFINITIONS

The below-stated terms used in Technical Specifications or BOQ shall be interpreted as following:

Project Architect: Supervising Officer as defined in the Contract (RBAL)

M&E Engineer Mechanical & Electrical Engineer (RBAL)

Building Contractor The Contractor employed by the Employer for the execution of

the Works as defined in the Contract or the Contractor separately

employed by the Employer to execute the builder’s work

associated with the Works as appropriate

Contractor The Contractor employed by the Employer or the Specialist Sub-

contractor employed by the building contractor or the Nominated

Subcontractor nominated by the Project Architect for the

execution of the Works as appropriate

Annular space or annulus The space between the borehole wall and the well casing, or the

space between a casing pipe and a liner pipe.

Annular seal The material, usually cement grout or bentonite, placed in the

space between the borehole wall and the well casing for zone

isolation, especially used to prevent surface contamination from

entering the borehole.

Bentonite/Bentonite annular seal A hydrous aluminium silicate (clay) in slurry, powder, granular,

or pellet form that, when hydrated, provides an impervious seal

between the well casing and the borehole wall. Bentonite may

also be used in a 2% to 5% mixture with Portland Type I, Type

II, or Type I/II cement to form a pumpable grout seal that expands

as the material hardens.

Filter pack Sand, gravel, or glass beads that are uniform, clean, and well-

rounded and generally siliceous that are placed in the annulus of

the well, between the borehole wall and the well intake in order

to prevent formation material from entering through the well.

Grout Cement or bentonite mixtures used in sealing boreholes and wells

and for zone isolation. Only Portland Type I, Type II, and Type

I/II cement is approved for use at investigative sites.

Monitoring well Any well or borehole constructed for the purpose of monitoring

fluctuations in groundwater levels, quality of groundwater, or the

concentration of contaminants in the vadose zone or

groundwater.

254

Silica Sand Washed and sieved sand of a specified size distribution or

gradation composed primarily of silica (e.g., quartz).

Site-Specific Health and Safety Plan A health and safety plan that is specific to a site or ER-(SSHASP)

related field activity that has been approved by an ER health and

safety representative. This document contains information

specific to the project including scope of work, relevant history,

descriptions of hazards by activity associated with the project

site(s), and techniques for exposure mitigation (e.g., personal

protective equipment [PPE]) and hazard mitigation.

Tremie pipe A small-diameter pipe used to carry sand pack, bentonite, or

grouting materials to the bottom of the borehole. Materials are

pumped under pressure or poured to the hole bottom through the

pipe. The pipe is retracted as the annulus is filled.

Turbidity (nephelometric) A measure of the intensity of light scattered by sample

particulates relative to a standard reference suspension. The range

of water turbidity is measured in nephelometric turbidity units

(NTU).

Vadose zone A zone between the ground surface and the water table that

contains water below atmospheric pressure and air or gasses at

atmospheric pressure. Also known as the zone of aeration or

unsaturated zone

Well casing A solid piece of pipe, typically steel, stainless steel or polyvinyl

chloride (PVC), used to keep a well open in either unconsolidated

materials or unstable rock and as a means to contain zone-

isolation materials such as cement grout or bentonite.

Well screen Perforated casing that allows fluids, while minimizing or

eliminating sediment into the well.

Humus (non-bearing surface layer) Layer of soil, which is to be removed because of the inappropriate

physical, mechanical and chemical characteristics

Lean concrete base Layer of lean concrete MB 10 of 10 cm thickness, laid in the

excavations before reinforcement and concreting of the

foundations – isolated footing, continuous footing and the slabs.

Refilling with soil Filling of loose material from the excavation (without humus and

large rocks) used for refilling and compacting to the necessary

degree of compaction

255

1.7 REQUIREMENTS OF SPECIFICATIONS, STANDARDS AND BRAND NAMES

The quality of works shall be in accordance with the Technical Specifications of International Standards

and Manuals of the Material / Equipment. Neither the following Clauses of this Specification, any

descriptions therein nor the quantities shall limit the obligations of the Contractor under the Conditions

of Contract. Where items are not included in the Bill of Quantities (BOQ) for any such requirements

or obligations, the cost of such requirements or obligations shall be deemed to have been spread over

all the items of the Bill of Quantities.

All references to specific standards and codes to be met by the goods, materials and work performed

or tested shall be to the latest edition or revision thereof unless otherwise stated

Where such standards and codes are national, or relate to a particular country or region, other

authoritative standards that ensure a substantially equal or higher quality than the standards and codes

specified will be accepted.

If the Contractor intends to use such alternative Standard, he shall notify the Project Architect/M&E

Engineer thereof, submitting with his notice two (2) copies (in English) of the proposed Standard, and

shall not order any material or perform any work unless and until he has obtained the Project Architect’s

approval of such Standard.

Brand names used in the Specification or on the drawings are only intended to define a standard of

quality and performance and the Contractor may use alternative products of at least equal quality and

capacity.

When the Contractor offers alternatives, the Contractor shall submit to the Project Architect for

approval a statement detailing the alternatives. The Contractor, shall include full technical descriptions,

drawings and specifications, and shall provide such full information as is required to demonstrate to

the Project Architect/M&E Engineer that the alternative is equivalent to the item specified. The

Contractor when called for shall produce any further information that the Project Architect may require.

1.8 RESTRICTIONS TO SPECIFICATION

The technical specifications are giving as a general guideline. Detailed notes and specifications as per

drawings and manufacturers specification as far as applicable will take preference over these technical

specifications and the Contractor shall pay close attention to these details.

The Project Architect on the advice of the M&E Engineer may adjust specifications and details of

drawings during the implementation where found necessary and applicable.

1.9 COORDINATION OF WORKS

The Contractor has to coordinate all works closely with the Main Contractor and the appointed

representative of Project Architect.

The Contractor shall not be entitled to claim any extra payment, time extension or compensation for

interference and delays caused by the adherence to the requirements of this Clause.

For the borehole drilling, the Sub-Contractor has to select the site and a respective form sheet has to be

signed by the Project Architect and the Main Contractor before drilling activities start. The Project

Architect and the Main Contractor shall also be consulted on alternate sitting in the event of an

unsuccessful borehole.

256

1.10 NOTICES, PERMITS

Well in advance of the programmed start of any work which may affect traffic or any existing utilities,

the Contractor shall give advance notice to the Project Architect and the Main Contractor indicating

the type, the exact location, the programmed starting time and the expected duration of the works and

shall provide whatever particulars may be required by the Project Architect and the Main Contractor to

issue any required permits and make all necessary arrangements. The Employer will provide whatever

assistance possible to the Contractor to facilitate the permit procedure which, however, will remain the

sole responsibility of the Contractor.

1.11 WITNESSING AND POST-CONSTRUCTION CLEARANCES

It is expected that the issue of these permits will be tied to the requirement that the work may only be

carried out in the presence of authorized inspectors from the authorities concerned i.e. Guma Water

Company (GUMA) and Electrical Distribution and Services Authority (EDSA). Their job will be to

witness and assess any damage or interference with their respective utility. Should such disturbances

occur it will be at their discretion to authorize either the Contractor to correct them or to arrange for

specialized repairs through their own personnel.

The Contractor shall be fully responsible for all costs whatever resulting from avoidable damages of or

interferences with other utilities.

As proof that the works in question have been completed to the satisfaction of the authorities concerned

the Contractor shall submit to the Engineer upon request official post-construction clearances issued

by the respective authorities.

257

2. GENERAL SPECIFICATIONS

2.1 SKILLED STAFF

The Contractor shall deploy skilled staff with knowledge relating to the Contract Requirements as

detailed and specified in the Contract Document.

The Project Architect reserves the right to have any person removed from the site if in his opinion the

quality of work executed is not satisfactory and the skill of that person are not appropriate.

2.2 ABBREVIATIONS

The following abbreviations shall be used and valid in these documents:

BoQ ........................Bill of Quantities

°C ...........................Centigrade degree

cm ...........................Centimeter

d .............................Depth

DN ..........................Nominal diameter

Hrs...........................Hours

HDPE .....................High Density Polyethylene

kg.............................kilogram

km............................Kilometer

l ...............................Liter

Ls ............................Lump sum

m .............................Linear meter

m².............................Square meter

m³.............................Cubic meter

mm...........................Millimeter

mm² .........................Square millimeter

No ............................Number

OD ..........................Outer diameter

pcs ............................Pieces

PN ...........................Nominal pressure

t ...............................Thickness

To ...........................Tone (1000 kg)

“ ..............................Inch

% .............................Per cent

Drawings in the document are an integral part of the technical specifications. The Contractor shall

revise all submitted drawings and compare with the methodology foreseen before starting the relevant

works.

The Contractor shall be responsible for the possible extra costs.

2.3 DRAWINGS

The Project Architect shall prepare design drawings of the water distribution system network and

submit it to Main Contractor

The Contractor shall prepare accurate as-built drawings and submit them prior to obtaining the

Certificate of Completion. The Contractor shall revise the drawings until approved by the Engineer.

258

The Contractor shall use commercially available PC compatible word processing and adequate graphic

software to produce its as-built deliverable documentation.

The final drawings shall be submitted as 4 hard copies (size as required by the Project Architect

authorized representative) and as electronic version on CD.

Before the Project Architect shall issue the Certificate of Completion, the Contractor shall return to the

Project Architect/M&E Engineer all Drawings, Specifications, Bill of Quantities and any other

document, which may have been supplied to the Contractor for the purpose of the work, if so requested.

2.4 POLLUTION OF POTABLE WATER

Special attention must be given to any aspects concerning a possible contamination of the potable water

caused by the works. The Contractor shall be held responsible for any pollution of the drinking water

facilities as a result of his work.

2.5 DAMAGES CAUSED BY THE CONTRACTOR

The Contractor will be held responsible for any damage to public or private property while carrying

out the work. It shall be his solitary responsibility to inform himself thoroughly enough to avoid any

damages to the existing buildings, structures and infrastructures.

2.6 WORK PROGRAM AND TIME SCHEDULE

The Contractor shall provide with his offer a work program according to the contract and bidding data,

including a time schedule to be approved by the Project Architect/M&E Engineer. Seasonal rainfall

and flow of surface water has to be taken into consideration. The program shall fully take into account

and allow, in a methodical manner, for the need to coordinate procedures with other contracts being

carried out on the site.

This approved work program shall not be changed without the written approval of the Project Architect.

In case delays, additional or unforeseen works are coming up the work program shall be updated by the

Contractor and submitted for approval to the Project Architect. A possible extension of the Contract

shall be negotiated with the Contractor.

Before commencement of work the Contractor shall submit a final work program and time schedule

for approval by the Project Architect. Changes may only be approved if they can be justified.

During execution of the works the Contractor shall submit a work program every 14 days containing

the progress, delays and the updated time schedule until the end of the Contract.

The program shall include a detailed time schedule showing the time the contractor has anticipated for

the work, whether works will be done in sequences or parallel, etc. until the completion and handing

over of the works.

All Work programs shall be submitted as hard and softcopy and are subject to written approval by the

Project Architect.

259

2.7 SITE PROTECTION & REGULATION

The contractor shall deliver, install, maintain and remove all required safety material as warning signs,

traffic signs etc. In addition to the site protection, the Contractor shall install protective guard posts in

areas where human traffic on site might pose a hazard.

The guard posts shown in Attachment E consist of steel posts that are at least 3’’ in diameter. Four

guard posts are radially located around the well vault and placed at least 2ft below the ground’s surface.

Each post will have a minimum of 4ft above the ground surface and, in cases where the borehole/well

is surrounded by high vegetation, will have a flag attached for greater visibility. Each post should be

cemented inside of a hole that has a minimum diameter of 6 in.

2.8 WORK IN VICINITY OF POWER LINES

Wherever the Works may cross an electrical power line right of way, the Contractor shall familiarize

himself with the requirements and regulations with regard to work carried out in the vicinity of power

lines. The Contractor shall comply with such requirements and regulations and obtain any permits

required.

Equipment shall not be operated where it is possible to bring such equipment or any part of the

equipment within three (3) meters of any energized electrical conductor unless the utility company has

been notified, and either the line has been de-energized, or effectively guarded against contact, or

displaced or re-routed from the work area. For high-voltage transmission lines, clearance shall be

requested from the Electricity Distribution Services Authority (EDSA) to temporary de-energized the

service line within the working area.

Where practical, metallic pipe sections shall not be stored under overhead high voltage power lines. If

pipe sections must be stored under power lines, the Contractor shall protect personnel from the effects

of induced currents by grounding pipe sections at two (2) locations with a 50mm2 copper ground

conductor and grounding rods.

2.9 CONTRACTOR’S SITE OFFICE AND CONSTRUCTION SITE MANAGEMENT

2.9.1 MOBILIZATION AND ARRANGEMENT OF SITES

The Contractor shall set up and maintain the site office, store and other constructions necessary for his

work. He shall be responsible for all the services in such constructions. Compliance with local

regulations shall be guaranteed in all aspects.

The protection and security of works and equipment of the Contractor shall be the responsibility of the

Contractor and he is responsible to the Employer for any loss or damage caused to third parties‟

property, within the site boundaries.

2.9.2 WATER SUPPLY

Water will be required for the purpose of construction of the works. The Contractor shall make his own

arrangements for obtaining supplies of water of approved quality, and shall erect and maintain all

required pumps, pipes, cocks, tanks, mobile tanks, hoses and other appliances required to distribute the

water as necessary to the various parts of the Works. The Contractor shall be solely responsible for the

supply of all water required in the works for whatever purpose and no claim for extra payment or

extension of time based on the lack or insufficient or delayed supply of water will be considered or

entertained.

260

Where permitted to connect up to existing mains and pipelines for the purpose of obtaining water, the

Contractor shall comply with all regulations and requirements of the competent authority (GUMA).

The Contractor shall obtain all related permits and make all arrangements as may be required for the

performance of the connection. The cost of supplying water for all purposes shall be uniformly spread

over all items of the Bills of Quantities.

2.9.3 ELECTRIC POWER SUPPLY

The Contractor shall make his own arrangements for all electric power supply, which will be needed

for the execution of the Works.

If necessary, the Contractor shall provide, erect, operate and maintain in good condition a diesel driven

electric generator, large enough to supply the contractual requirements. Sufficient standby is essential

to ensure the required electric power at all times. Mobile generator set with sufficient capacity for pump

testing is to be provided.

The Contractor shall also install, connect and maintain in good condition all cables, conductors and

other electrical plant and equipment required to perform his contractual obligations. All such plant and

installations as described above shall comply with the relevant requirements and regulations in Sierra

Leone. All the electrical facilities shall be erected and be maintained to the full satisfaction of the

Project Architect /M&E Engineer. The cost of providing electric power supply for all purposes shall

be uniformly spread over all items of the Bill of Quantities.

2.9.4 SITE CLEARING AND PREPARATION

The Works under this Clause include site clearance, leaving and erection of fencing that may be

required, protection of any existing structure of element that must remain intact, etc. Prior to

commencing the above Works the Contractor shall obtain all necessary licenses and permits required

for their performance.

The areas of all sites on which work is to be done shall be cleared of all standing or felled trees, stumps,

brush, logs, debris, rubbish and other objectionable matter. All trees outside the area to be cleared and

such other trees that are not to be removed shall be carefully protected from damage during the Works

operations, and no trees shall be removed without the prior consent of the Project Architect. The

Contractor shall not commence clearing any area and/or demolition without having received written

instruction to it from the Project Architect.

2.9.5 DISPOSAL OF TREES, ROOTS, ETC.

All materials required clearing shall be removed from the area during the work progress and on

completion of the Works, burned completely or disposed of in a manner satisfactory to the Project

Architect/M&E Engineer. All materials to be burnt shall be piled and all burning shall be so thorough

that the materials will be reduced to ashes. Piling for burning shall be done in such a manner and in

such locations as to cause the least fire hazard and nuisance to inhabitants of the area. The Contractor

shall have available at all time, for use in preventing and suppressing fires, apparatus and fire-fighting

equipment satisfactory to the Project Architect/M&E Engineer. When, in the opinion of the Project

Architect, the fire hazard is great, burning shall be deferred or additional fire-fighting equipment shall

be provided.

All materials not burned to ashes shall be disposed of by removal from the site of the Works, and upon

removal such materials shall become the property of the Contractor who shall dispose of them by burial

in locations and in a manner approved by the Project Architect. The Contractor shall adopt all measures

to ensure that soil erosion is avoided.

261

2.9.6 MAINTENANCE OF SITES

The Contractor shall maintain the site in clean and hygienic condition during the whole project period.

All staff and labour rooms shall be in suitable working conditions.

2.9.6.1 Release of Sites and Demobilization

Demobilization shall include the removal of all site facilities, temporary installations, equipment,

machinery and surplus materials from site and the reinstatement of all surfaces used, in at least in the

same condition as before its occupation, including all access roads. The site shall be left in a state that

does not negatively affect the environment or destroy the view.

2.9.6.2 Regulation on Safety and Public Health

The Contractor shall make sure that the places of work and the construction sites are maintained with

care and that they comply with safety and hygiene requirements. His equipment shall be cleaned

regularly. Necessary disposals shall be provided. The Contractor shall be responsible for any pollution

or sources of infection inside the area of his premises.

The Contractor must take all necessary measures to ensure that his activities, equipment, vehicles, staff,

etc., do not cause undue inconvenience, harassment nor safety or health risks to other workers. The

Contractor shall not cause any damage to agricultural crops or trees outside the site territory, nor shall

the work activities cause flooding or pollution of the environment.

a) First Aid

The Contractor shall provide and maintain on site first aid equipment consisting at least of the

following:

• A complete first aid kit with medicines, bandages, splints, etc.

• A motor car to be always available for emergency transportation

b) Fire Protection

No naked fire shall be used by the Contractor on or about the Site other than in the open air.

The term "naked fire" shall be deemed to include electric arcs and oxyacetylene or other flames

used in welding or cutting metals.

Suitable firefighting equipment shall be provided and maintained by the Contractor on site to deal

with any outbreak of fire. All possible precautions shall be taken to provide for the safe storage of

petroleum, explosives, gas bottles, and all other dangerous goods and items.

2.10 CONTRACTOR'S EQUIPMENT

The Contractor's equipment used in the performance of the works shall be of such type, size and of

such method of working as the Project Architect approves. If for any reason whatsoever the Project

Architect shall be of the opinion that any equipment or appliance employed or proposed to be employed

by the Contractor for the purpose of the works shall not be used, or that any such machine or appliance

as aforesaid is unsuitable for use in the Works or any part of them, then such equipment shall be

immediately withdrawn from use. The Project Architect shall inspect and approve the Contractor's

equipment prior to commencement of drilling operations. If equipment is not satisfactory, the

Contractor shall provide such equipment that meets the Project Architect's approval.

Any change in the method of performing the Works as a consequence of such order shall be at the cost

of the Contractor who shall have no cause for claim against the Employer on account of having to carry

out the work by different methods, or for the idleness or removal of any construction plant.

262

The cost of providing constructional plant for all purpose shall be uniformly spread over all the items

of the Bill of Quantities.

2.10.1 Descriptions of commonly used pieces of equipment are listed below.

a) Well-Construction Supplies (Some of these items are suggestions only, and the list is not all-

inclusive)

Silica sand (i.e. 30/70, 20/40, and 8/12 grain size)

Cement—Portland Type I, Type II or Type I/II only

Approved water supply, preferably untreated

Well casing, screen, cap, and bottom plug well, as required

Mechanical casing centralizers, if required

Bentonite pellets, crushed bentonite, or bentonite grout

A 5-ft length of protective steel casing—black iron or galvanized— 6-, 8-, or 10-in. in

diameter, according to needs

Guard posts

Locking cap

Padlocks

b) Well-Construction Equipment

Drill rig and accompanying equipment (augers, drill rods, casing, samplers, etc.)

Tremie pipe

Grout-mixing and pressure-pumping unit

Support equipment for maintaining 24 hr./day operation

2.11 MATERIALS and EQUIPMENT SUPPLIED BY CONTRACTOR

2.11.1 Materials and Goods to be used for the Works

All materials for execution of Works as appropriate backfill material, concrete, reinforcement steel,

pipes, fittings, armatures, etc. shall be supplied by the Contractor.

All goods to be provided shall be new, unused, of the most recent manufacture and incorporate all

recent improvements in the design and material unless provided otherwise in the Contract.

The Contractor shall take all the measures for the selection, storage and handling of natural material in

conformity with the technical specification some time before this material is used, and inform the

Project Architect accordingly.

Prior to making any order to any private entity or factory for any element / material ordered by the

Employer, the Contractor shall submit to the Project Architect, costs, names of manufacturers and

suppliers for approval.

The Contractor shall also hand in the relevant technical specifications and parameter for any type of

material before procurement in order to allow the Project Architect to assess the quality of this material.

The Project Architect may ask for testing, which shall be on the expense of the Contractor.

Should the Project Architect/M&E Engineer at any time be dissatisfied with such materials or goods or

with the method or performance of such sub-contractor's work or place of business, the Project

Architect shall be empowered to cancel his previously given approval of such sub-contractor. The

Contractor shall then obtain the said services; materials or goods from such other sub-contractor as may

be approved by the Project Architect and shall bear any additional cost therefore.

263

If during the Contract, through any reason, a supplier should increase the cost of materials above that

of other equally reputable suppliers, the Project Architect may only authorize payment for materials at

the rates of other suppliers.

2.11.2 Samples

In addition to any special provisions herein from sampling and testing of materials, the Contractor shall

submit to the Project Architect as he may require samples of all materials and goods he proposes to use

or employ in or for the Works. The Project Architect, if approved, will retain such samples, and no

materials or goods of which samples have not been submitted shall be used on the permanent works

unless and until the Project Architect has approved such samples in writing. Notwithstanding the

Project Architect’s approval as provided for herein, the Contractor shall be solely responsible for the

quantity of all materials and goods supplied unless specified otherwise.

The cost of supplying all such samples and of conveying the same to such place of inspection or testing

as the Project Architect may designate complying with the requirements of this Clause shall be deemed

to be included in the Bid rates and prices.

2.11.3 Test Certificates

Should the Project Architect not inspect any materials or goods at the place of manufacture, the

Contractor shall obtain certificates of tests performed on such materials or goods by an agency approved

by the Project Architect and shall certify that the materials or goods concerned have been tested in

accordance with the requirements of the Specification and shall give the results of all the tests carried

out. The Contractor shall provide adequate means of identifying the materials and goods delivered to

the site with the corresponding certificates.

2.11.4 Packing, Marking and Delivery

Prior to the dispatch from the factory or Contractor's works, equipment and materials shall be

thoroughly protected against corrosion and incidental damage, including the effects of vermin, rough

handling and bumpy land transportation, strong sunlight, rain, high temperature or humid atmosphere.

The equipment and materials shall be packed to withstand rough handling in transit, and packages shall

be suitable for export to and storage in the tropics, including possible delay on exposed quaysides and

field conditions. The Contractor shall be held responsible for the materials and equipment being packed

so that it reaches its destination intact and undamaged. The Contractor shall provide, and include in the

contract price the cost of all necessary packing cases and crates, properly strengthened by battens

(which shall be considered as non-returnable), hoop iron banding, and packing materials to include, but

not limited, to the use of polythene or similar waterproof wrapping, silica, etc. wherever necessary, and

required.

The Contractor shall prepare a list of all items which had been implemented during execution of the

Works. The list of materials implemented shall be handed over to the Project Architect after completion

of Works.

2.11.5 Required Documents to be submitted with Bid Documents

Each Bidder has to submit the following documents with his Bid:

Type / make of and specifications for

• Submersible pump

• Solar system for operating submersible pump

264

For the main items offered (submersible pump and solar system) the Bidder has to state the nearest

agent/ distributor of the type of service to be supplied and service and maintenance possibility in Sierra

Leone or neighbouring countries.

The information submitted with the Bid Documents is binding.

2.11.6 SUBMERSIBLE WATER PUMPS

2.11.6.1 Submersible Water Pump, suitable for solar energy.

The submersible pump should work with solar energy. The submersible pump should be supplied

with the following: 3”suction and 2’’ discharge submersible pump (suitable for 6”borehole) with all

safety devices (e.g. dry-run protection, electric protection to prevent power surge, non-return valve)

3”pump for high heads and moderate flows as shown above, suitable for 6” (150 mm ID) borehole

(explicitly confirmed in the bid). Water-tight flat cable connectors resistant to pressure equal to 2 or

more bars and water resistant flat cables have to be supplied

Pump must be equipped with over and under voltage protection, over temperature and effective dry

running protection.

• 75m rising pipes

• 100m drop cables

• Switch box

• A complete set of solar power generation system mounted on suitable support structure, including

all cables, accessories, etc.

The Contractor shall supply and install the solar powered submersible pump as specified to supply

enough power to operate the submersible pump for the Bank’s daily demand of water. The solar

panels must generate at least 50 % more Watt than the pump requires. Technical specifications for

the solar system components are given below.

• All connecting cabling and fittings, drop cable and module support structures with all necessary

components for a complete site installation shall be delivered.

• Including automatic on/off switch to stop pump when water tank is full

• Installation and maintenance manual in English for all components have to be included

• Appropriate documentation, such as technical and performance data for submersible pump and

motor, solar modules and module support structure shall be submitted with the Bid.

Submersible pump, riser pipe and fittings:

Solar powered Submersible pumps, including all equipment and accessories for solar energy supply

and energy supply to the pump, suitable for 6” (150mm) cased internal diameter boreholes

Supply shall include all materials for main pipe work from the well head to the tank and associated

valves and fittings, submersible cable, earth cables, slicing kit, earth rods and other accessories.

The details below are minimum the requirements of the submersible pump guidelines to be installed:

265

2.11.6.2 Technical Data 6” 50Hz Stainless Steel Submersible Pump for Deep Well

2.11.6.3 Material In Contact With the Liquid

DESCRIPTIONS MATERIAL

Type AISI DIN / EN

Discharge head and screws Stainless steel 304 1.4301

Valve Stainless steel 304 1.4301

O-ring Nitrile Rubber - -

Valve support Resin - -

Outer case Stainless steel 304 1.4301

Suction Strainer Stainless steel 304 1.4301

Cable guard and screws Stainless steel 304 1.4301

Motor adapter Stainless steel 304 1.4301

Pump shaft Stainless steel 304 1.4301

Coupling Stainless steel 304 1.4301

Upper journal sleeve Stainless steel 304 1.4301

Screw and washer Stainless steel 304 1.4301

Lower spacer Stainless steel 304 1.4301

Upper spacer Polycarbonate - -

Diffusers Techno-polymer - -

Secondary bearing bush Resin - -

Bearing bush Resin - -

Upper bearing guide Resin - -

Stage housing Stainless steel 304 1.4301

Impeller Polycarbonate - -

2.11.6.4 Applications:

� Water supply from well

� Municipal water works

� Water distribution and pressure boosting

� Irrigation and sprinkler systems, water treatment plants, filtration and reverse osmosis

266

� Industrial cooling and processing

� Mining industry, drainage and dewatering

� Fire-fighting equipment

� Lifting and distribution of a wide range of liquids

� Autoclave and cistern charge and discharge

� Greenhouses and nurseries

� Residential wells and drainage

� Food industry

� General industry

2.11.6.5 Features:

� Compact, reliable and suited to operate in vertical position

� Built-in check valve to protect the pump against water hammer risk

� Floating impellers to grant a better performance and longer life for the pump against abrasion

� Hydraulic design is such to enhance the overall efficiency thus reducing energy consumption and

making the pumping systems more cost effective

2.11.6.6 Specifications:

� Capacities up to 24m³/h at 50Hz

� Pumped liquid: chemically and mechanically non aggressive

� Water temperature range: from 0°C to 40°C

� Maximum allowable amount of sand 25gr/m³, solid dimension max 2mm

� Maximum pump diameter (including cable guard): 95mm

� Outlet diameter: 2"

� Rotation: counter clockwise when looking into the discharge

� Motor adapter in compliance with NEMA standard

� Pump can work continuously in vertical position

� Motors: see section Submersible Motors Product Overview

(i) Pumps with Encapsulated Motor

Pump

Model Type

Motor Dimensions [mm] Weight [Kg]

Type kW HP Lt L2

L1 Motor Pump Total

3~ 3~ 3~ 3~

VS 6/26 E4 3 4 1424,5 393,5 1031 15,0 8,7 23,7

The hydraulic characteristics shall be guaranteed, according to ISO standard 9906:2012, grade 3B

(ii) Hydraulic Performances at 50Hz.

Pump

Type

Rated Power Q = Delivery

m³/h 0 2,7 3,0 3,3

[kW] [HP] l/sec 0 0,75 0,83 0,92

H = Total Head Meters Column Of Water [m]

VS 6/26 3 4 150 143 141 139

(iii) Overview - Submersible Motor

6" Encapsulated Motor

6" Super Stainless 3 Phase SUBMERSIBLE MOTOR

The 6" encapsulated three phase motor, manufactured in ISO 9001 certified facilities, are built

for dependable operation in 4" diameter or larger Boreholes. The motor shall offer a

maintenance free long life submersible pump application.

The motor shall be filled with a special FES93 fluid, providing frost protection for lower

temperature. A special diaphragm shall ensure pressure compensation inside the motor.

267

(iv) Features:

� Hermetically sealed stator. Anti-track, self-healing stator resin prevents motor burn out

� High efficiency electrical design (low operation cost, cooler winding temperature)

� Removable “Water Bloc™” lead connector

� Cable material according to drinking water regulations (KTW approved)

� Water lubricated radial and thrust bearings

� Motor prefilled and 100% tested.

Non contaminating, FES93- filled design

(v) Specifications

� 3kW

� 4" NEMA flange

� Degree of protection: IP68

� Insulation: Cl. B

� Rated ambient temp: 30°C

� Cooling flow: Motor 2.2 kW and larger: min. 8 cm/s

� Starts/h: 20

� Mounting: Vertical

� Voltage tolerance: 380-415V/50Hz; -10% / +6% UN

[380-415V = (380-10%) – (415+6%)]

� Motor protection: Select thermal overloads according to EN 60947-4-1,

Trip time <10s at 5 x IN

� Motor complete in AISI 316SS with SiC seal

E

(vi) Performance at ~2850 rpm (Three-Phase 4" Encapsulated Motors 400V)

Pump

model

type

PN Thrust nN IN IA η cos

φ

TN TA L Weight

[kW] [HP] F [N] [min-1] [A] [A] [%] [%] [Nm] [Nm] [mm] [kg]

VS 6/26 3.0 4 6500* 2845 7,5 42,0 76 0,77 10,06 31,93 477,2 17,0

* High Thrust Version

(vii) Accessories

a) Motor Control:

Sub Monitor Motor Protection

The Sub Monitor is designed to protect 3-phase pumps with horsepower ratings between 3 - 15Hp.

Current, voltage and motor temperature are monitored using three integrated current transformers.

A digital display provides current and voltage readings for all three legs and allows the user to set

up the Sub Monitor quickly and easily. The Sub Monitor is the latest innovation in 3-phase pump

protection from Franklin Electric.

Using state-of-the-art technology, the Sub Monitor provides the ultimate protection for a pump

and motor. There is simply no better way to protect a large 3-phase submersible pump investment

than with a Sub Monitor. It‘s the protection device that can sense overheating straight from the

motor windings! And it is made by the world leader in submersible motors - Franklin Electric.

b) Features

� Quick setup to monitor a motor, simply enter the Line Frequency (Hz), Line Voltage (volts),

and Motor Service Factor Amp rating

� Digital display indicates voltage and current on all three legs at the same time, and fault

messages are in easily understandable text

� Monitors - Under/Overload; Under/Overvoltage; Current Unbalance; Overheated Moto;

Start (Chattering); Phase Reversal

268

� For motors with service factor amp ratings between 3 and 100 amps

� The unit covers the entire range from 230 to 415 Volts

� No need to make additional turns around the CT or add external CTs

� Password Protection Option

� DIN Rail Mounting Option

� Stores fault, setting changes, and pump run-time, that can be accessed through the display

� Detachable NEMA 3R display unit can be mounted on panel door

� UL 508 Listed

c) Model number

Premium Package: 586 000 5100

Input Voltage: 400VAC

Frequency: 50Hz

Motor Service Factor Amps: 3 to 100A

d) Maximum Conductor Size through Sensors

Max. Diameter: 0.920 in. (23 mm)

e) Trip Response

Motor

Under / Overload

Under / Overvoltage 3 seconds

Overheat

Unbalance

f) Control Circuit Rating : 1.5 Amp AC, up to 600 volts

g) Signal Circuit Rating: 1 Amp AC, up to 250 volts

(Incandescent: 100 watts max.)

h) Wiring Terminals

Wire Gauge: #12 to #18 AWG

Tighten to: 4.5 in-lbs

i) Weight (Sub Monitor) 3.3 lbs/7,3 kg

j) Termination Kit 6"

This proven, sturdy solution shall be the Contractor’s choice of cable joining in temporary pump

applications or when re-usage if the drop cable is desired as the flexibility and safety it provides

for under field service conditions makes it the preferred choice over conventional, not breakable

splicing kits.

k) Double Plug Lead for Termination Kit

� 3-wire

� 2,5m Lead length

� With Strain relief

� Max. Current 16 Amps

� KTW approved

269

l) Corrosion Protection 6"

Application:

The sacrificial anode attaches to the bottom end bell of Franklin Electric 6" Super Stainless

submersible motors. Since cast iron is more chemically active than the metals that make up the

motor and pump, it is the cast iron that reacts to the corrosive elements in the water. This results

in longer motor and pump life in aggressive/corrosive water conditions.

m) Motor Filling Kit

This kit offers all tools for control the level of the engine filling liquid and to fill up if necessary!

n) Surge Arrestor

Application:

These surge arrestors or their equivalents are highly recommended for protecting submersible

motors from a variety of commonly occurring high voltage spikes which can damage the motor

insulation system and cause motor winding failure. These arrestors will not, as is true of any surge

protection equipment, protect the motor from a direct lightning strike.

o) Riser pipe, fittings

Rising pipe connection: not less than 1”

Riser pipe must have facility for cabling attachments

Stainless steel security cable and fittings have to be supplied

Centralizers have to be supplied and installed at every 6 m of the riser pipe

2.12 Solar modules:

The Solar modules shall be designed for optimal efficiency operation with the pump system:

- The solar modules must generate at least 50 % more Watt than the pump requires.

- Mono- or Poly-crystalline with certified performance and lifespan values;

- Nominal power rating between 85 – 340 Wp per module

- Aluminium or stainless steel frame in weather proof glass enclosure. Must accommodate anti-theft

fittings

- Modules should be dust protected

- Weather-proofed connection boxes with watertight cable entry glands, diode protection and clearly

marked polarity terminals

- Minimum markings must indicate:

• Name or trade mark of manufacturer

• Number or reference of module

• Serial number

• Rated power (Wp)

• Rated Current IMPP

- The documentation submitted with the bid shall include following information:

Country of manufacture and nearest agent / distributor and maintenance possibility

2.12.1 Modules support structure

- Solid, hot-dipped galvanized support structure consisting of on-site assembled prefabricated

components;

- Must withstand wind speeds of up to 150km/h with modules attached

270

- All connecting and holding-down bolts and other materials to be galvanized or of other suitable,

durable and non-corrosive material;

- The modules are to be mounted with an inclination of 15% in true south direction, or as otherwise

recommended by the supplier with recommended modifications for the conditions in South Sudan;

- All connecting cables should be weather resistant, rubber sheathed; rubber insulated and should

have flexible stranded round conductors;

- The modules shall be fixed to the support structure by means of anti-theft screws, bolts or nuts.

The tenderer is free to offer alternative solutions to enhance security.

- The support structure shall be designed in a manner that will allow an average size local person to

easily clean the modules with a minimum need for arm-extending tools. If necessary, it shall include

steps and safety devices at the higher parts of the structure;

- The modules shall be mounted preferably on top of the water tank.

2.11.3 Accessories:

All connecting cabling and fittings, drop cable and module support structures with all necessary

components for a complete site installation shall be delivered.

3.0 BACKGROUND AND PRECAUTIONS

Note: This SOP is to be used in conjunction with an approved SSHASP. Also, consult the SSHASP

for information on and use of all PPE.

3.1 A properly constructed well allows access to formation fluids or gases for the collection of samples and

for determining in situ characteristics. Ideally, the well should not alter the medium that is being

sampled.

3.2 The following is a partial list of critical issues involved in well planning, design, and construction:

Preventing the spread of possible contamination;

Selecting soil-boring or rock-coring technique and hole sizes;

Selecting casing and screen materials, including composition and dimensions;

Determining screen-slot size, screen type, and screen interval;

determining filter pack composition, gradation, and dimensions; and

Choosing a grouting plan.

Refer to the site-specific documents for the location and specifications of the well to be installed. Wells

are generally installed as components of monitoring systems in accordance with Hazardous and Solid

Waste

Amendments (HSWA) and Environmental Protection Agency (EPA) guidance (EPA 1991).Well

construction, development of the wells, collection and measurement of samples, and the documentation

of data must be performed as described in this SOP.

The following steps are primarily directed at deep and intermediate depth wells (generally greater than

70m in depth) and are not necessarily requirements for hand borings or shallow boreholes.

271

3.2.1 Perform a site hydrogeological examination to estimate key parameters (for example, anticipated

aquifer depth and thickness, types of contaminants, geology and grain-size distribution).

3.2.2 Coordinate schedules/actions with the Project Architect (Consultants) Technical Representative (CTR)

and/or Project Leader and appropriate technical team.

3.2.3 The source(s) of any water used on site must be pre-approved by the CTR and/or Project Leader

before field operations begin. A potable, non-chlorinated source is preferred, and the source is to be

documented in the daily logs. At his discretion, the CTR may require analytical samples be collected

of the water source.

3.2.4 Any use of solvents, glues, or cleaners is prohibited unless approved in writing by the CTR and/or

Project Leader. If official permission is granted for their use, describe the material and include the

manufacturer and type (specification) (MSDS sheet must also be included). The on-site use of non-

environmentally safe and/or unapproved pipe-dope, grease, soap, or oil is also prohibited for any

purpose with the exception of machinery fuel and lubricants.

3.2.4 Monitor the borehole opening and the breathing zone as necessary according to the appropriate ER

SOPs and SSHASP. Perform readings as often as necessary to ensure the safety of workers, and record

all measurements on the appropriate data-collection forms.

4.0 RESPONSIBLE PERSONNEL

The following personnel are responsible for activities identified in this procedure.

4.1 Consultant Technical Representative (CTR)

4.2 Driller

4.3 Field Team Leader

4.4 Site Geologist

4.5 Contractor’s Representative

5.0 EQUIPMENT

Descriptions of commonly used pieces of equipment are listed below.

5.1 Well-Construction Supplies (Some of these items are suggestions only, and the list is not all-inclusive)

Silica sand (i.e. 30/70, 20/40, and 8/12 grain size)

Cement—Portland Type I, Type II or Type I/II only

Approved water supply, preferably untreated

Well casing, screen, cap, and bottom plug for each well, as required

Mechanical casing centralizers, if required

Bentonite pellets, crushed bentonite, or bentonite grout

A 5-ft length of protective steel casing—black iron or galvanized— 6-, 8-, or 10-in. in

diameter, according to needs

Guard posts

Locking cap

Padlocks

5.2 Well-Construction Equipment

Drill rig and accompanying equipment (augers, drill rods, casing, samplers, etc.)

Tremie pipe

Grout-mixing and pressure-pumping unit

Support equipment for maintaining 24 hr./day operation

272

6.0 PROCEDURE

Note: The Contractor’s Project personnel shall be responsibility to ensure that they are trained to and

utilizing the current version of this procedure. The Engineer may be contacted if text is unclear.

Note: Deviations from SOPs are made in accordance with Standard Operating Procedure

Development and documented in accordance with QP- 5.7, Notebook Documentation for

Environmental Restoration Technical Activities.

6.1 General Well Installation Record Keeping

6.1.1 Record all fields measurements and comments on the Borehole/Well Completion Information form

(Attachment A) or the Borehole/Well Construction Field Data Log form (Attachment B). Fill out the

forms as described in the completion instructions included with each form. A Fact Summary Sheet

(Attachment C) should also be completed.

6.1.1.1 The Field Team Leader (FTL) shall consult with the UTR and/or Project Leader before modifying an

existing well design.

Any modification must be recorded in the Borehole/Well Construction Field Data Log form

(Attachment B), the Fact Summary Sheet (Attachment C) and the Daily Activity Log form (Attachment

E in ER-SOP-1.04), or a field notebook.

6.1.2 Record pertinent information on the Borehole/Well Completion Information form (Attachment A) and

the Fact Summary Sheet (Attachment C). At a minimum, record boring/well identification number,

location of boring (coordinates if available), nominal hole diameter and depth at which diameter

changes, screen location, backfill, seals, grout, cave -in, centralizers, and the height of the riser above

the ground surface. Record the actual composition of the grout, seals, and backfill on each

Borehole/Well Construction Field Data Log form (Attachment B). Include the screen slot size (in

inches), slot configuration, and screen manufacturer. Include the protective casing detail on all well

sketches.

Typical well construction features for single screen and multi-screen completions are shown in

Attachments D and E. When installed as a piezometer, well point (for water levels only), or gas-vapour

monitor, the well configuration may vary significantly from these drawings.

After well development is complete, indicate the static water level on the well-construction diagram.

6.2 Sand Pack

A sand pack helps ensure continuous flow capability from the natural formation to the well bore. The

following is a list of instructions for using a sand pack, if required.

6.2.1 The minimum annular distance between well screen and the borehole wall is 2 inches for the ADB

Project well.

6.2.2 The specifications of the proposed sand-pack material should be approved by the FTL before use. Use

well-sorted (poorly graded) and rounded sand that is clean, inert, and siliceous and compatible with the

screen slot size in-use.

6.2.3 The average grain size of the sand is based on the grain-size distribution of the medium being monitored

in the screened formation. Use sand that has a gradation that will allow less than 10% of filter pack

material to pass through the screen slots (insert Reference).

6.2.4 Record the filter-pack size, the company from which it was purchased, and the lot number (if available)

for each installation. Be prepared to take an airtight pint size sample of filter pack material and furnished

to the UTR upon request to serve as a quality control.

273

6.2.5 Fill the annulus between the well screen and borehole wall with silica sand to a height 5ft above the

screened interval and 5ft below the screen if above a bentonite seal or as specified in applicable

Title I or II drawings if required. For wells greater than 30ft in depth, a tremied pipe will be used to

place the materials.

6.2.6 Ascertain the depth of the top of the sand with a measuring device with accuracy within 0.5ft and verify

the thickness of the sand pack. Measurements must be repeatable. If necessary, add more sand to bring

the top of the sand pack to the proper elevation.

6.2.7 Under no circumstances should the sand pack extend into any aquifer other than the one to be

monitored. In most cases, the well design can be modified to allow for a sufficient sand pack without

the threat of cross flow between producing zones.

6.2.8 If specified in the project documents, partial development of the sand pack may be required (to help

settle sand pack) before installation of bentonite seal and grout.

6.2.9 In the event that a predominantly fine-grained, water-bearing unit is encountered, it may be desirable

to construct a monitor well that uses a factory-manufactured screen and filter prepacks assembly.

Various sand-pack gradations are available. The prepacked screen subassembly is attached to the solid

well casing (riser) in the same manner as a conventional screen. The fine-grained formation materials

are allowed to collapse against the prepacked well screen.

Prepacked well screens have larger OD’s which must be considered when calculating backfill.

6.2.10 Centralizers will be placed above and below each screen or as specified in Title I design documents.

Generally, no less than one every 50ft for the uniform and complete annular filling by granular backfill,

seal, and grout materials. Centralizers may be required at 10ft intervals or less when installing angle

holes. In some cases, such as very shallow wells and where tremie-pipe placement of materials is done

through pipes or augers, the spacing of centralizers can be expanded or eliminated entirely. Fasten

centralizers to the well casing and radially space them at 120° or 90° intervals.

6.3 INTERMEDIATE BENTONITE SEAL

The following steps outline the use of an intermediate bentonite seal from the top of the sand pack to

2ft above.

6.3.1 Before placing the bentonite seal, be sure the filter pack has settled by measuring the depth of the top

of the sand with the tremie pipe or a measuring device with accuracy within 0.5ft. The sand pack should

rise to a depth of 5ft above the top of the screen.

6.3.2 In media that will not maintain an open hole, leave the casing or the hollow-stem augers in the hole

during filter-pack placement and bentonite-seal placement to the extent practical. Maintain the

bentonite in the casing/auger a small distance (1 to 2ft) above the bottom of the casing/auger for even

placement, as the casing/augers are removed. Special attention should be given to the amount of fill

material if this procedure is followed due to the risk of bridging in saturated conditions.

6.3.3 Visually check the condition of the bentonite backfill material before pumping it into the hole by

pumping a sample into a bucket. Retract the tremie pipe 3ft from the top of the sand pack and begin

pumping.

6.3.4 Place a bentonite-chip or -pellet seal above the sand pack and below the annular well seal to prevent

infiltration of cement into the filter pack and the well. Hydrate the bentonite seal and wait a minimum

of 4 hrs. before adding a slurry grout.

274

Note: Use bentonite chips, bentonite pellets, or crushed, granular bentonite. The pellets should have

a minimum purity of 90% montmorillonite clay and a minimum dry bulk density of 75lb/ft3.

No bentonite will be placed into the well bore—place a cap over the top of the well casing

before pouring the bentonite pellets.

6.3.5 In special circumstances, an open borehole may be drilled to a depth below where the screen is set. If

grout is used to seal off a lower aquifer or as backfill up to the proper level, place a bentonite seal above

the grout and hydrate for 4 hrs. before the casing, screen, and sand pack are introduced. Allow the grout

to set up for a minimum of 24 hrs. before placing the bentonite seal. Place 5ft of sand pack between

this grout and the well screen. Place the bentonite seal in the borehole as described below. The

minimum width for the annular well seal (between casing and borehole) is

2in. for the ADB Project well

6.3.6 For wells that are 30ft. or less in depth:

6.3.6.1 Pour the bentonite directly down the annulus. Pour the pellets from different points around the casing

to ensure even application. A tremie pipe may be used to redistribute and level the top of the seal.

6.3.6.2 Fill the annulus between the well casing and borehole above the filter pack with a bentonite seal at

least 2ft thick (vertically); hydrate and wait 12 hrs.

6.3.7 For wells deeper than 30ft:

The bentonite backfill material can be pumped or poured through a tremie pipe. The FTL shall

determine the method after evaluating the condition of the borehole walls. If there are no centralizers

in the upper portions of the casing, manipulate the casing to prevent pellets from hanging up in the

narrow annulus and to allow them to settle to the bottom as rapidly as possible.

6.3.8 Measure the distance to the top of the seal with an acceptable measuring device to verify that the proper

thickness of seal has been placed in the annulus.

6.3.9 Until the proper thickness of bentonite has been placed in the well annulus, repeat the application and

verification.

6.4 ANNULAR WELL SEAL

6.4.1 For placement of dry product annular backfill materials in intermediate and deep wells, refer to to

complete backfilling procedures.

6.4.2 If a cement-grout annular seal is to be installed, use only Portland Type I, Type II or Type I/II cement.

The grout must be mixed thoroughly with 2% to 5% bentonite powder to produce a non-shrinking seal.

The cement must be mechanically mixed thoroughly before it is pumped into the borehole.

6.4.3 If slurry of bentonite is used as an annular seal, prepare the slurry by mixing powdered or granular

bentonite with pre-approved potable water according to manufacturer specifications. The slurry should

be of sufficiently high specific gravity and viscosity to prevent movement of the overlying grout into

the saturated zone. Pellets may be added to solidify the surface of the bentonite slurry in order to prevent

cement intrusion.

6.4.4 In some cases a dry mixture of fine sand, silica flour, and bentonite powder or a mixture of cuttings,

sandy clay, or tight soil may be used where the fill material will have less permeability than the

formation. In general the cuttings cannot be easily emplaced because of screening and/or compacting

problems. Cuttings mixed with dry bentonite can be used for abandonment purposes.

275

6.5 SURFACE WELL SEALS MINIMUM DEPTH AND WIDTH:

The minimum depth of an annular well seal above the fill is 10ft. The minimum width of the annular

seal is 2inches. Allow a minimum of 12hrs. (HSWA requirement) after a bentonite-slurry seal has been

placed, then place cement grout from the top of the bentonite seal to the surface. Use grouts as specified

in project documents. Place grout in the annulus of the wells as described below.

6.5.1 Fill the annulus between the well casing and borehole wall with cement grout.

6.5.2 On all wells 30ft deep or deeper, pump the cement grout through the tremie pipe to the bottom of the

open annulus until undiluted grout flows from the annulus at the ground surface.

Note: The cement grout should consist of a mix of cement (Portland Type I, Type II, or Type I/II) and

2% to 5% bentonite mix. Use only grout mixed with pre-approved water.

6.5.3 When drilling in materials that will not maintain an open hole, leave the hollow-stem auger or

temporary casing in the hole during grouting to the extent practical. Remove them as the level of the

grout rises above the bottom of the auger.

6.5.4 If necessary, add more grout to compensate for the removed casing or auger and tremie pipe and to

ensure that the top of the grout is at or above the ground surface.

6.5.5 The protective casing should now be placed over the well casing.

6.5.6 After the grout has set (about 24 hrs.), fill any depression in the grout caused by settlement with a grout

mix similar to that previously described.

6.6 PLACEMENT OF DRY PRODUCT ANNULAR BACKFILL MATERIALS (INTERMEDIATE

AND DEEP WELLS)

6.6.1 The driller shall place all annular fill materials (dry products only) through a tremie pipe maintaining

a 10ft minimum buffer between the targeted backfill depth and the bottom of the tremie pipe.

6.6.2 Both the driller and the site geologist shall in accordance with QP- 5.7, Notebook Documentation for

Environmental Restoration Technical Activities, record in logbook accurate tallies of tremie pipe and

drill casing to ensure that the exact depths are known at all times.

6.6.3 Both the driller and the site geologist shall, on a scheduled basis, compare their tremie pipe and drill

casing tallies to ensure they are in agreement. In the event they are not in agreement, backfilling

activities will be suspended until an acceptable resolution is attained and the depths can be verified to

the satisfaction of both parties.

6.6.4 The driller shall use potable water (municipal supply) as a transport fluid to carry dry materials such

as bentonite pellets and silica sand down the tremie to the desired depth. A polymer such as EZ-MUD,

approved by the CTR, may be added to the transport fluid to delay hydration of bentonite chips or

pellets in deeper applications. This will reduce the potential for swelling within the tremie pipe which

commonly results in plugging.

6.6.5 If a polymer solution is used, the driller must flush the tremie with one volume of the tremie rod with

clear water prior to filter pack sand emplacement

6.6.6 The driller shall record in a field notebook the quantities of water and additives used during the

placement of annular backfill material.

6.6.7 The driller shall use silica sand that meets the specifications in the Title II design drawing (typically

fine-grained 30/70 and 20/40 grade) for filter packs and transition zones between filter packs and

bentonite seals.

276

6.6.8 Fine-grained sands (30/70, 20/40 grade) shall be allowed to settle for 15 to 30 minutes after the pour is

completed before sounding the depth.

6.6.9 If the sand level is low, the driller shall allow an additional 15 to 30 minutes for the sand to settle and

then re-sound the sand level.

Note: Sands with grades greater than 20/40 can be expected to settle more rapidly and typically can

be measured immediately after emplacement.

6.7 DRILL CASING RETRACTION DURING BACKFILL OPERATIONS (FOR

INTERMEDIATE AND DEEP WELLS)

6.7.1 The driller shall retract the drill casing in stages as backfill materials are emplaced to avoid borehole

collapse in potentially unstable formations.

6.7.2 The driller shall maintain a 10ft minimum buffer between the targeted backfill depth and the bottom

of the drill casing to prevent backfill from getting between well casing and drill casing. This may result

in sand locking the casings or smearing bentonite across well screens

6.7.3 The driller shall determine the length of drill casing to be retracted between pours based on borehole

stability, the size of the batch to be poured, and casing stickup in the rig table. The site geologist shall

provide borehole stability information to the driller based on site stratigraphic, geophysical logging

data, and video logs if available.

For large intervals of backfill in stable formations, it may be acceptable to pull 100 or more feet of

casing followed by one large or several small batches of backfill. In unstable formations, casing should

be retracted at shorter intervals of 20 to 40ft, followed by small batches of backfill, to minimize

borehole caving into the annular space. Cave-ins may result in damage to the well casing and screens,

displacement of annular fill materials, and may compromise the integrity of annular seals.

6.8 VOLUME CALCULATIONS

6.8.1 Both the driller and the site geologist shall make volume calculations of all materials introduced into

the borehole prior to emplacement. Backfilling should not proceed until the calculated volumes are in

agreement.

6.8.2 Both the driller and the site geologist shall ensure that the calculated volume for the interval to be

filled is not exceeded regardless of the character of the formation.

6.8.3 The driller shall take extreme care when backfilling with bentonite below a screened section of the

well casing to prevent impact to the screen.

6.8.4 The driller shall ensure the target depth for standard batches of bentonite are at a minimum 20ft below

the bottom of the screen. The driller shall ensure that the remainder of the bentonite interval below the

screen is poured in small batches calculated to raise the level in the annulus by 2 to 3ft per batch.

6.8.5 The driller shall sound (measure) the bentonite after each batch until the desired depth is reached. The

bentonite shall be allowed to hydrate for a minimum of 30 minutes before installing silica sand.

Note: The volume of the annular space can be determined by subtracting the volume displaced by the

well casing (outside diameter) from the total borehole volume. The borehole volume and casing

displacement is determined using drilling reference tables or the formula for the volume of a

cylinder (V= r2h). Annular space volume (Va) is determined using

Va = Vt-Vc; where a = annulus, t = total, and c = casing.

277

6.8.6 The driller or the site geologist shall perform calculations for each batch. All calculations shall be

recorded in the field logbook.

6.9 SOUNDING BACKFILL DEPTHS (FOR INTERMEDIATE AND DEEP WELLS)

6.9.1 The driller shall sound the depth to the top of the fill material using a mechanical (weighted tape/wire

line) or electronic sounding device. The site geologist shall oversee and concur with each measurement

before recording the depth in the logbook and Title II drawing. The sounding line shall be run through

a sheave suspended over the borehole and lowered through the tremie pipe. Care should be taken to

avoid entanglement of the sounding line in the well casing centralizers. The driller and site geologist

shall maintain cognizance of centralizer locations relative to the tremie pipe at all times.

6.9.2 If a mechanical sounding line is used (weighted tape or wire line), the driller will carefully monitor the

tension on the wire or tape as the weight nears the depth where the fill is calculated to be. When an

electronic sounder is used, the driller shall carefully monitor the cable-counter and slow the sounder

winch as it approaches the calculated depth of the fill.

6.9.3 Once the sounding device tags bottom, the driller will verify the measurement by repeating the

measurement process two times with the same result, or within five tenths of a foot (+/-0.5ft). The site

geologist shall then record the confirmed measurement in the field logbook to the nearest tenth of a

foot (0.1ft).

Note: Measurements read from a cable counter or graduated tape must be adjusted to account for the

length of the weight on the end of the wire or tape. The height of the tremie pipe stickup (above

ground level) must be subtracted from the each measurement when referencing depths below

ground level.

6.9.4 In the event that the calculated depth and the measured depth are significantly different, the driller and

site geologist shall evaluate the difference and resolve any non-conformance(s). The driller and site

geologist shall review the casing and centralizer configuration in the Title II well design drawing to

ensure that a well-casing centralizer is not inadvertently being tagged. If the fill is lower than expected,

the geophysical logs, the video logs, and the drillers’ logs shall be reviewed to determine if voids or

fractures are present in the subject interval.

6.9.4.1 If the non-conformance renders the condition of the well unacceptable or indeterminate, the

Non-conformance shall be resolved in accordance with QP-3.4, Managing Non-conformance’s,

Deficiencies and Corrective Actions before continuing backfill operations.

7.10 INSTALLING PROTECTIVE CASING AROUND MONITOR WELL THE MINIMUM

ELEMENTS IN THE PROTECTION DESIGN INCLUDE THE FOLLOWING:

7.10.1 The protective steel casing and locking cap should be weatherproof. The locking cap should be secured

to the casing by padlocks.

7.10.2 Set the protective casing (5ft minimum length) so that the top of the pipe is about 1.5 to 3ft above the

ground surface and grout it in place as shown in Attachments D and E.

6.10.3 Use 8-in.-diameter pipe for 4-in. well, 6-in.-diameter pipe for 2-in. well and 10-in diameter pipe for 5-

in. well (depending on approved borehole size). A drain hole near ground level that is 0.5-in. in diameter

is permitted.

7.10.4 Mark the location ID on the inside and outside of the cover with indelible ink, metal punch lettering

kit, or by writing with an arc welding machine/rod.

7.10.5 Form and pour the concrete protective pad around the protective steel casing. Pad dimensions will not

be less than 2ft × 2ft × 0.5ft.

278

The concrete pad should be sloped away from the casing for positive drainage. The standard regional

well pad configuration and design is shown in Attachment E. The brass monument shall be placed into

the concrete in the northwest corner of the pad, approximately 12 inches from the edges of the concrete.

Location and elevation coordinates and the FIMAD location I.D. number shall be clearly imprinted in

the monument.

7.11 RECORDING WELL CONSTRUCTION DETAILS

7.11.1 The driller and site geologist shall keep an accurate record of all well construction materials in the site

logbook. The records shall include at minimum the following:

Type of material,

Manufacturer name and address,

Batch or control number,

Calculations showing estimated volume of material placed during each lift

Number of packages of each product used in each interval/lift,

Size of individual packages,

Volume and composition of transport fluids,

Condition of materials and packaging; and

Any other potentially valuable information.

7.11.2 After completing a unit of backfill (i.e. filter pack interval), the site geologist shall make and record a

comparison between the calculated and actual volumes of material required in the field logbook.

Methods of installation shall also be described and recorded in the field logbook.

7.12 DOCUMENTING THE FINAL WELL CONFIGURATION

7.12.1 The site geologist shall record the final measured depth of each complete unit of annular fill on the

most recently approved Title II well design drawing and in the field logbook.

7.12.2 The site geologist shall record all observations made during backfilling and depth sounding in the field

logbook.

7.12.3 Observations should include at a minimum the following:

Differences in the design-specified and as-built fill levels of each unit of annular fill,

Anomalous depth measurements,

An evaluation of any problems encountered and the final resolutions, and

Any other information or observations that may be useful in assessing the quality of the

installation.

8. WORKS

8.1. Concrete Works

8.1.1 Materials

Materials for construction works has to comply with following specifications:

Cement: Portland cement to British Standard BS 12

Reinforcement: Bars, Plain - Reference R. to British Standard BS 4449,

Deformed, Reference T to British Standard BS 4449, Fabric to BS 4443

Sand, coarse: Clean, free from lime, clay and any organic substance, less than 5 mm

Coarse aggregate: Clean, free from lime, clay and any organic substance, passing 20 mm sieve

279

The quantity of all materials required has to be included by the Contractor in the respective items of

the Bill of Quantity.

8.1.1.1 Cement

The cement to be used shall be normal Portland cement which conforms to British Standard BS 12 or

equivalent.

The Contractor shall keep the cement in a dry place above the ground. The Engineer shall be able to

enter into the cement store of the Contractor and check the cement storage conditions. Any deteriorated

cement sacks, shall be removed and the expenses therefore shall be covered by the Contractor.

8.1.1.2 Aggregates

The aggregates to be used for concrete shall comply with the relevant British Standards.

Fine fractions shall be used from natural sand. It shall be clean and with diameter less than 5 mm,

uniformly distributed. The addition of sand produced by crushing to natural sand shall be allowed only

with the permission of the Engineer, when he considers this addition as necessary for the improvement

of granular size. The maximum content of clays, silts and powders shall not exceed 3 % of the weight

Large fractions shall not be larger than 20 mm.

8.1.1.3 Water

Water used in the work shall be from a source approved by the Engineer or his representative. It shall

be free from oil, acid, alkali and any vegetable or organic matter which is harmful to any material with

which it is used. Where available, a drinking water supply shall be used.

Additive to Concrete

The concrete used in the work shall be a homogeneous mixture of Portland cement, coarse sand, coarse

aggregate and water.

If any additive is included in the concrete mixture, they shall comply with the following requirements:

a) No reduction of the concrete strength;

b) No change of the proportion of cement with fillers

c) No corrosion of the steel bars

d) Not causing the reaction of ”alkaline-fillers”

e) The dosage has to comply with the technical specification of the additive.

280

The class of concrete to be used in each structure or part thereof shall be as detailed on the drawings or

as instructed by the Engineer. The constituents of 1 m3 of each class of concrete shall be:

Class A Class B Class C

Weight of cement (s) kg 250 300 350

Weight of sand, coarse (s): kg 760 700 650

Weight of coarse aggregate (a): kg 1150 1170 1180

Water approximate: kg 175 175 175

Crushing strength, 28 days N/mm2 10 20 25

Nominal volumetric proportion: c:s:a 1:2:5:5 1:2:4:1 1:6:3:2

Only sufficient water shall be added during mixing of the constituents to form concrete having

sufficient workability to enable it to be well consolidated to be worked into the corners of the formwork

to give the specified surface finish and specified strength.

8.1.2 TRIAL MIX AND TESTING OF CONCRETE

The Contractor shall not start preparation of concrete, without first testing a sample of concrete in

advance according to the mix design for the type of concrete desired.

The Contractor shall prepare all samples for any type of concrete with the same equipment and with

the same materials that he uses for preparation of the production concrete. He shall inform the Engineer

24 hours in advance of these tests so that he may participate in taking the samples

Every batch of concrete shall be tested for slump at the place of deposit in the presence of the Engineer

or his representative. The contractor shall provide slump cones at every place of mixing and deposit.

The maximum allowable slump shall be 15 mm. The contractor shall include the costs in his rates.

8.1.3 STEEL FOR REINFORCEMENT

Diameter, shape, strength properties and identification of the steel (ribbed steel min. 420/500 N/mm²)

should be according to BS4483.

If requested the Contractor shall submit to the Engineer the certificate of the factory, which has supplied

the steel.

All for the installation of the whole construction necessary reinforcement works incl. delivery, cutting,

buckling, laying and the necessary connections to reinforcement have to be included in the BoQ as well

as cutting losses, reinforcement spacer, S-hooks etc.

The connections between construction walls, ceilings and intermediate floor have to be executed in a

way, that they are permanently waterproof and the conditions for the crack width control can be kept.

8.1.3.1 Steel Bar Bending

The steel shall be cut and bent in accordance with drawings and tables to be delivered by the contractor

approved by the Engineer. It shall be bent in a cool state and with the suitable equipment.

281

8.1.3.2 Placing of Steel Reinforcement for Concrete

Before application, the steel has to be released from constituents, which can affect the composite, e. g.

dirt, grease, ice and loose rust.

The steel to be placed in concrete shall be clean, not damaged, not corroded and without other matter

which prevent its connection to the concrete. The steel bars shall be connected with one another with

the required overlapping to be proved by the contractor. The steel shall be placed in conformity with

the design, and shall not be moved during the concrete placement. The welding, of spacers or

connections shall be approved by the Engineer. Spacers shall be of the same quality as those of the

completed concrete. The steel bars need to be covered with concrete at minimum 3 cm.

The Constructor has to co-ordinate the reinforcement approval with the local site management.

The approval of the reinforcement works is absolutely necessary before concrete placement and shall

be carried out by the Engineer.

8.1.4 TRANSPORTING, PLACING AND COMPACTING OF CONCRETE

The contractor shall notify the Engineer when concreting is about to start on each section of the work.

No concrete shall be placed until the Engineer has approved the formwork.

Concrete shall be so handled that at the point of deposition it is of the specified quality and approved

consistency, nothing having been added to it or lost from it since leaving the mixer.

Concreting shall be carried out continuously to the positions of joints prepared prior to starting.

The compression of concrete shall be done by mechanical vibrators of the type approved by the

Engineer and the contractor has to be sure that enough vibration equipment is on site.

The Contractor shall have spare vibrators in case of failure or defects of any of them.

Shuttering shall be such as to guarantee the profile and surface required by the concrete works and such

as to preserve the rigidity during the casting of concrete. They shall comply with direction, form and

size of concrete according to the design or to the instruction of the Engineer For major works, the

Contractor shall submit to the Engineer the drawing of the shuttering.

The joints of the shuttering are to be such as not to weaken the mark of concrete, not to prevent its

vibration, when they are removed, nor to damage the concrete or its outer appearance. The shuttering

shall be very clean. The plastering of defective surfaces of concrete is not allowed.

Before beginning with the assembling the shuttering are checked and cleaned carefully. All the surfaces

of the shuttering, which are in contact with the concrete shall be painted with a solution approved by a

laboratory accepted by the Employer to avoid the sticking of concrete. This solution shall be carefully

used, to avoid the pollution of iron bars and previous concrete. The shuttering shall be removed only

as ordered by the Engineer and their removal shall be carried out by a competent specialist in order not

to damage the concrete. The cost for shuttering shall be included in the concrete price.

282

8.1.5 CURING AND MAINTENANCE OF CONCRETE

As long as the concrete is not hardened, it shall be protected from the damaging effects of wind, sun,

rain, high temperatures, or aggressive water. The concrete shall be cured by keeping it in humid

conditions. The exposed sides shall be covered and kept wet by means approved by the Project

Architect

8.1.6 Repair to Concrete

The Contractor shall make available to the Engineer all the means to inspect the works during the

execution or after the completion and to make quality tests according to the standards or specifications.

The concrete shall be repaired using a method approved by the Engineer or removed completely when

he considers it necessary. The repairs shall not be considered as a justification for the extension of

working time.

Any material resulting as waste from the repairs shall be removed from the site at the expense of the

Contractor.

8.1.7 Concreting in unfavourable weather

The contractor shall not place concrete in permanent work:

(a) During heavy rains or dust storms

(b) When the air temperature is more than 30°C.

When the air temperature exceeds 30°C, the contractor shall not place concrete in the permanent work

without taking such precautions as may be required to keep the temperature of the concrete during

mixing and setting below 38°C (e.g. keeping the concrete materials and formwork shaded from the sun,

and the aggregate and formwork sprayed with water)

Concrete shall not be poured against formwork which is hotter than 30°C without the approval of the

Project Architect

9.0 BOREHOLE DRILLING

9.1 Drilling of boreholes includes following works:

• Survey of location

• Drilling of borehole, including development of borehole, pump and water quality test

• Proper sealing of borehole in case of dry boreholes

• Mobilization and demobilization

Successfully drilled boreholes have to be equipped with submersible pump.

A concrete platform has to be constructed and the borehole has to be fenced. For some locations cattle

troughs for combined systems (for human beings and cattle) have to be constructed, if instructed by the

Engineer.

The Contractor shall provide all labor, transport, plant, tools, equipment and materials and

appurtenances, and shall perform all Works necessary to satisfactorily locate sites for drilling, construct

and complete successfully drilled boreholes including lowering of borehole assembly with PVC casing

and Screen and end cap, gravel pack at appropriate intervals and back fill, close near surface water table

aquifer, cleaning and development of said boreholes, pump test for 6 hours, chlorinate borehole,

construct a platform and drainage, fence the borehole area.

283

The Contractor shall employ only competent workmen for the execution of the Works, and all such

Works shall be performed under direct supervision of an expert driller/site supervisor.

9.2 Drilling Team

9.2.1 Inventory of Drilling Equipment and Materials

The Contractor shall specify in the Schedule of Drilling Equipment, borehole development and other

accessory equipment, its type and capacity that is to be used to undertake this work. Its capacity shall

be sufficient to cope with the Works as stated in the Contract. It shall at all times be kept in full working

order and good repair.

Prior to the commencement of the work the Employer or his representative shall have the right to

inspect the drilling and the pumping test units of the contractor. The Employer or his representative

shall also have the right to carry out a detail inventory of the materials to be supplied by the contractor

(equipment, materials, drilling tools, compressor, welding plant, casing and screens, pumps, generators,

etc.)

If the Employer considers that the drilling equipment or any accessories in use on the site of the Works

is in any way unsuitable, inefficient or inadequate in capacity, the Employer shall have the right to call

upon the Contractor to put such equipment in good order within fourteen days or alternatively to remove

such plant and replace it with additional plant or equipment which the Employer considers necessary

to meet the requirements of the Contract. In the event that this requirement of the Contract is not

satisfied, the Client reserves the right to terminate the Contract immediately.

No extra payment shall be made for the Contractor's change of drilling equipment, labor or other

equipment required to complete the Works specified, nor for any incidentals thereto, the cost being

deemed to be included in the schedule of rates.

9.2.2 Drilling Unit

The drilling unit has to comprise of the following:

• Qualified drilling crew, including a Chief Driller and Chief Mechanic

• A standard rotary drilling rig for shallow and deep well drilling

• Drilling tools accessories and relevant equipment

• A compressor

• A welding plant

• Supply truck and light vehicle

• Water tank

• Necessary casings, screens, and other construction materials.

9.2.3 Pumping Test Unit

The pump test unit has to comprise of the following:

• Experienced pumping test crew

• For deep boreholes, submersible pump which can deliver 40-100 liters per second at a 100 meter

head.

• Diesel powered generator of appropriate capacity that can run the pump.

• All the necessary equipment, tools and accessories which are necessary to carry out pumping test

operation.

284

9.2.4 Identification number

The contractor will receive identification number by the Engineer for the boreholes contracted. The

identification number of the borehole should be punched on the pump body and on the pump platform

9.2.5 Site Selection

After contract signing the Contractor will receive approval from the Project Architect to commence

work.

The Contractor shall be responsible to carry out a survey (either by geophysical / geological or

hydrogeological methods) to confirm the technical feasibility of drilling a successful borehole(s).

Special care must be taken to ensure that the sites chosen are at least 50 meters away from toilet pits or

any other sources of pollution such as garbage pits, sewerage tanks or spills / over flow from pipes.

9.3 DRILLING RECORDS

9.3.1 WORK-ON-SITE JOURNAL

The Contractor shall maintain a work-on-site journal in which all the information concerning the works

is recorded, a copy of which shall be delivered to the Engineer or his representative. The information

to be recorded by the drilling unit includes:

Well Log of Drilling Unit

Drilling cuttings from the borehole shall be collected and handled in a manner that they can easily be

identified. Samples shall be taken at 2 meter intervals. The samples shall be placed in sample bags or

boxes.

The driller shall log the samples and keeps a record on a daily log sheet including:

• Lithology

• Degree of consolidation or hardness

• If unconsolidated, nature of ground material, i.e. subjective description of grain size, degree of

rounding, clay content, colour.

In addition the Contractor shall prepare a representative sample of every distinct horizon or change of

rock type.

Daily Record of Pumping Test Unit

• Site name (name of village)

• Site location - GPS coordinates (± 20m)

• Borehole identification number

• Name of all crew members

• make, model, capacity of the test pump and generator

• Types of work performed and the duration for each type of work

• The static water level

• Pump position during testing

• Total time of the pumping test

• Total stand-by time

• Total shutdown time

• Total time on site

• Problems encountered and other noteworthy information.

285

9.3.2 FINAL REPORT (Well Completion Report)

After completing construction and pumping testing, the Contractor shall prepare a final technical report

for each well, in English, which must be submitted with the Contractor’s fee claim. The report should

include the following information:

• Site name

• Site location - GPS coordinates (± 20m)

• Borehole identification number

• Make, model, type and size of the rig

• Time and date of arrival and departure of the rig

• Number of kilometers indicated on the rig’s odometer at arrival and departure

• Time and date of the start and stop of drilling

• Compressor time for drilling, pump testing, and development

• Total shut down time (hours) due to breakdowns

• Total standby time (hours)

• Total drilling time (hours)

• Total development time (hours)

• Total time (days) rig on site

• Summary of logging results showing geologic strata and aquifer

• Static and dynamic water table

• Drilling diameter, depth, and position of casing, screens and grout

• Equipment and instruments used for the pumping test

• Data collection sheets of the pumping test and remarks about data acquisition

• The plotted graphs of the pumping test

• Summary of the analytical methods, calculations, and interpretation of the pumping test.

• Proposed pump placement

• Summary of observations, problems encountered, and recommendations

• Digital photos from the borehole site have to be taken and attached to the final report (photos must

indicate date and time):

(i) One taken before start of construction activities and

(ii) another one after completion of works (showing the borehole and punched borehole

identification number)

9.3.3 HYDRO GEOLOGICAL CONDITIONS

Hydro geological information can be obtained from the ‘Technical Guidelines and Manual for Borehole

with a Hand pump’ (UNICEF / MWR).

It should be clear that this information does not hold the Employer responsible for any locally different

conditions at the specific drilling site or for the particular problems the contractor may face while

executing his work.

The contractor will be responsible for carrying out hydro geological investigations at the sites selected

for SWDS.

9.3.4 BOREHOLE CONSTRUCTION

9.3.4.1 Borehole Design

General consideration in borehole designs can be obtained from the ‘Technical Guidelines and Manual

for Borehole with a Hand pump’ (UNICEF / MWR)

286

In addition the following considerations should be looked at when designing a borehole with a

submersible pump:

• The expected depth of the well shall be determined according to the hydrogeological structure of

the area where the well is needed to be drilled. Therefore the drilling method to be employed should

be identified and decided in order to achieve the required depth of the well.

• An apron/platform should be cast around the top of the lining (at least 1 m radius).

• Submersible pump specifications should be suitable to fit to the quality of water in the borehole.

• The screen should be properly positioned as per the attached designs in the Drawings.

• Disinfection of the borehole is required prior to commissioning of the water supply system.

Communities need to be informed about this as there might be unsubstantiated flow of information

in regard to disinfections (chlorination of water).

• Surface water diversion ditches should be provided to protect against inundation.

9.3.4.2 Drilling Rigs

In general drilling of a borehole can be executed by Rotary Drilling.

Rigs shall have air and water/mud flush facilities for drilling through the over burden and down the

hole hammer facilities for drilling in hard rock. The rig shall have sufficient working casings to drill

through the various rock types, and accessories needed for reaming, fishing, well development, pump

testing, etc.

Rigs shall be able to drill up to 150 meters deep.

The flushing medium shall be air, water or stable foam. If, at any stage mud is necessary either as a

primary fluid or as an additive to create “stiff foam”, only degradable high quality polymer will be

acceptable. Bentonites are specifically prohibited.

9.3.4.3 Drilling Diameter

A minimum diameter of 8” (inches) at the completion of the borehole and installed with 6” casings and

screens is required above and below the water-conducting layer in order to install a submersible pump

with a diameter of 3 inches.

The Engineer or his representative shall determine the final drilling depth, based on the desired yield

and site specific geological and hydrogeological conditions. The Contractor shall require the Engineer’s

approval to abandon unsuccessful boreholes and initiate drilling at an alternate location.

The Employer will not be responsible for any loss of temporary casing which the contractor is unable

to pull out or lost due to snapping or breaking from the completed boreholes.

9.3.4.4 Soil Definition

Soft soil refers to soil of poor volume stability and low strength and may be composed of loose sands

and silts, wet clays, organic soils, or combination of these materials.

Hard rock refers to soil what must be crushed or hammered using specialized mechanical equipment.

For the purpose of these tender invitation formations which can be drilled using the conventional

drilling methods such as driving, jetting auger drilling, kludging rotary drilling techniques such as direct

287

or reverse fluid circulation rotary drilling, air circulation rotary drilling or such other techniques shall

not be considered as hard rock.

The contractor shall notify the Engineer or his representative whenever he encounters drilling formation

which in his opinion may be classified as hard rock. The Engineer’s decision on the classification of

formation drilled material shall be final.

9.3.4.5 Borehole construction

The final borehole shall be of the following type, depending on the lithology and formations:

Type A - open hole in stable rock or formation, unscreened with plain casing through the overburden

only

1) Percussion, air rotary or mud rotary through overburden (alluvial, laterite, weathered or soft

bedrock), minimum final drilling diameter is 8" in overburden.

2) Percussion or rotary/percussion ("down the hole hammer"), using stabilizers (foam) where

necessary, in consolidated hard rock, minimum final diameter is 6"

3) Boreholes should be drilled at least 6 meters below any water bearing fractures to allow sufficient

space for a sedimentation sump.

4) Fractured bedrock considered not collapsing and left open

5) Installation of casing for overburden: minimum diameter 6”, sealing of casing with grouting, back-

filling, cementation of top 5 meters.

Type B - protected borehole in collapsing rocks in fractured or broken bedrock encountered in

otherwise stable formations, as above with slotted casing for formation support and plain casing

extended to the bottom.

1) Percussion, air rotary or mud rotary through overburden (alluvial, laterite, weathered or soft

bedrock), minimum final drilling diameter is 8" in overburden.

2) Down the hole hammer in consolidated hard rock, minimum final diameter is 6"

3) Fractured bedrock - water-bearing - considered to be collapsing and needs to be protected with

casing/screen (minimum inner diameter 6"

4) If necessary to prevent collapsing of overburden, installation of casing minimum diameter 6",

sealing of casing with grouting, backfilling, cementation of top 5 meters.

5) Installation of casing for overburden: minimum diameter 6", sealing of casing with grouting, back-

filling, cementation of top 5 meters.

Type C – Screened boreholes

In unconsolidated sediments, soft or very broken bedrock, supported by casing and screen, installed

with filter pack: C1 = formation filter, C2 = artificial gravel pack (sieved)

Type C1 - Screened borehole with formation filter

If a formation is not uniform and well sorted, a screen with a properly chosen slot size will result in a

natural development of a formation filter, close to the screen. This technique should be avoided because

of some required conditions not met in the context of South Sudan: a) a wide range of slots or screens

is not available to the contractors, b) sieve analyses of aquifers cannot be carried out at the moment.

Type C2 - Screened borehole with artificial gravel pack

1) Percussion, air rotary or mud rotary through alluvial or unconsolidated rocks, minimum final

drilling diameter is 8".

288

2) A minimum annular space of 1-2" between casing and borehole walls is required for gravel pack

installation.

3) Installation of screen or slotted casing with minimum inner diameter 6"

4) Installations of gravel pack at least 3 meters above the top of the first screen, topped with a one

meter clay seal, with backfilling material and cementation of the top 5 meters.

9.3.4.6 Bottom of the borehole

Boreholes should be drilled at least 6 meters below any water bearing layers or fractures to allow

sufficient space for sump. As far as possible, boreholes shall be drilled into the underlying bedrock or,

if the depth to the bedrock is too deep, drilling should stop in an impervious formation underlying the

aquifer - a clay layer for example.

The bottom of the hole acts as a sedimentation sump and a support for the casing and screen. The sump

shall be a bottom plain casing of at least 1.5 meter length - 3 meters recommended - with the same

diameter as the screen, and with its underside sealed with a bottom plug (wooden or PVC).

9.3.4.7 Casing Pipe and Sand Trap:

The boreholes shall be fully cased up to bottom of the borehole. The threads both male and female shall

be properly cleaned with a brush and cloth before they are joined. If the pipes used are with bell and

socket, these shall be cleaned using fluids and cemented with recommended solvent cement by the

manufacturers of the casing pipes and screen. Before lowering into the borehole the recommended time

for the joint set firmly has to be taken into consideration.

All necessary precautions during the transportation and storage of casing pipes to the drilling site have

to be taken to prevent distortions, bending or deformation of the pipe that could result in eccentricity

along the length of the pipe.

Pipes and screens must be stored on a proper location and should be kept away from prolonged sunlight

exposure

9.3.4.8 Screen

Screen design shall be determined in order to avoid drawdown of the water level into the screened

section of the well or below the first water strike in the water-bearing layers.

The screen should normally be installed within the coarsest section provided that the calculated

pumping drawdown does not reach below the top of the screen or below the main water strike.

Screening design

Notwithstanding the above, normally only the lowest 2/3 of the saturated strata (or parts thereof) should

be screened.

The length and position of the screened section affects the yield of the borehole. When the nature of

the aquifer is well identified, the screened section shall be designed conformably to the nature and

hydrostatic pressure in the aquifer.

A first minor water strike shall be sealed off with plain casing if it can be estimated that pumping will

lead to dewatering of the water strike.

Casings and screens shall have the same inner diameter and wall thickness.

289

The quality and standard of the casing and screens shall be in accordance with the standards set by the

American Petroleum Institute or the American Soil Testing and Materials Association or any other

international acceptable Institute.

Screen shall have a slot size of 0.75 mm to 2 mm depending on the aquifer material, as determined by

the Engineer. The open area of the screens shall be at least 30% of the surface area of the pipe, and

maximum entry velocity shall not exceed 0.03 m/sec.

Slots, which are prepared by using hacksaw, welding or oxy-acetylene, are not allowed.

Damaged and deformed casings and screens will not be accepted for installation.

Centralizers of suitable size (certified by the Engineer) shall be fitted to both casings and screens at 6m

intervals.

A 1-inch ID galvanized observation pipe shall be installed on the outside of the casing and screen before

the gravel pack is applied. Six to twelve meters of the observation pipe, as determined by the Engineer,

shall be slotted.

9.3.4.9 Filter pack

Artificial gravel pack (filter pack) is required to prevent particles entering the well and to improve

hydraulic properties in and around the catchment section of the borehole.

Gravel pack shall consist of siliceous material with rounded, smooth and uniform particles. Unstable

minerals such as feldspars, calcite (limestone), laterite, etc. will easily decompose and change the

properties of gravel pack. Flaky particles such as schist and micas will clog the screens.

Gravel pack should be clean and well-sorted, i.e. there must be no particles of clay or silt adhering to

the individual sand or gravel grains of the packs. Filter material should be treated with care to avoid

any kind of contamination.

The gravel shall be of appropriate size for the openings of the screen and type of geological formation.

The Engineer shall approve samples prior to placing. To avoid bridging of the gravel must be filled-in

by hand slowly and carefully. Mechanized equipment may not be used to fill-in the gravel. The correct

placing of gravel shall be controlled by continuous recording of the volume of gravel consumed and by

repeated measurement of the achieved level of packing.

The artificial gravel pack is combined with a suitable screen. Installation of gravel pack in the annular

space between screens and borehole walls, plus 3 meters above the top of the first screen. Gravel pack

shall be topped with a one-meter clay seal.

9.3.4.10 Grouting

Grouting is a standard practice for all public water supply boreholes. Typically, boreholes should be

grouted from the surface down to a depth of at least 5 meters to prevent leakage and percolation of

contaminants from the surface. Because of logistics constraints, grouting of the top 1.5 meter can be

admitted.

Following practices are optional in the existing context of South Sudan:

• Boreholes drilled in rocks that are overlain by thin overburden shall be grouted from the surface to

the rock.

• Boreholes drilled in sandy aquifer overlain by an impervious overburden shall be grouted from the

surface to the aquifer.

290

• in some formations where poor-quality aquifers are interspersed with high-quality water zones, the

poor-quality aquifers shall be completely sealed off in order to keep the water from the aquifer to

remain free from harmful bacteria or other contaminating factors.

• the minimum thickness for satisfying grouting or clay seal is 0.5 m, but a thickness of 1 m should

be used whenever possible to minimize contamination risks.

• Clay and backfilling material must be thoroughly compacted in order to avoid cracks between the

slab and the concrete cover afterwards.

9.3.4.11 Head of the borehole

The top casing and observation pipe shall come out between 55 cm and 60 cm above of the ground

level. It will be correctly cemented in the ground. If a submersible pump is not installed immediately,

then the top of the borehole must be sealed adequately to prevent the entrance of foreign materials.

9.3.4.12Borehole verticality

Installed casing shall be round and straight. Straightness and plumpness should be tested at the end of

the casing screen installation. The minimum standard of quality can be controlled by lowering down

a standard hand pump cylinder to the final depth of the borehole without opposing any resistance.

Any delays encountered in running casing and screen considered to be due to poor whole alignment

shall be at the Contractor's expense.

9.3.4.13 Soil sampling

During drilling, formation should be sampled at least every 2 m or less depending on the changes of

geological formation. Aquifer formation should be logged on the borehole completion form.

For collection, the Contractor shall cease drilling, circulate all cuttings to the surface, resume drilling

and collect the cuttings then brought to the surface. The Contractor shall take every possible precaution

to guard against sample contamination due to poor circulation, borehole erosion, or caving. Cutting

samples shall be bagged, labeled with borehole depth at time of collection, and stored in a position

where they will not be contaminated by site conditions or drilling operations. The Contractor shall

supply strong, transparent sample bags and labels as required. The driller in-charge shall also record

the drill time logs/penetration rate of each rod or at every three-meter interval

9.3.4.14 Interim Yield Tests

Interim yield tests shall be carried out at the first strike of water and at each stage during drilling when

the flow of water increases. The depths of measurement and the yield of water shall be recorded on

the daily log sheet. Interim yield tests should be carried out for at least 30 minutes to establish the

sustained yield at that depth of drilling.

9.4 BOREHOLE DEVELOPMENT

9.4.1 Borehole development

Borehole development improves the borehole performance and the quality of water. All boreholes must

be developed to the satisfaction of the Engineer or his representative on completion of drilling and after

casing, screen, grouting and filter pack are installed. The minimum requirement is the "air-lift" method

until the ground water runs clean and turbidity free, but in any case for a minimum of 3 hours. If this

condition is not achieved after 6 hours, air-lift will be carried-out until the water becomes limpid, but

up to a maximum of 12 hours with any extra hours on top of 6 hours to be invoiced accordingly if

approved by the Engineer.

291

Surging and jetting are acceptable standard methods in borehole development. Boreholes drilled in hard

rock formations shall be developed using compressed air after well completion until such time as clean

water without drill cutting or clay is obtained.

Routine evaluation of the borehole yields should be limited to the air-lift capacity test after development

of the well.

9.4.2 Pumping Test

The client or his representative shall decide the discharge rates at which pumping tests shall be carried

out. An electric water level indictor shall be used for the measurements of the water level.

Discharge measurements could be done either by standard v-notch, calibrated water meter, or by simple

container of known volume. Measurements by water meter are preferred.

Interruption caused by the negligence or technical defects of the pump, generator, or water level

indicator and other pertinent measuring equipment may cause repetition of the test at the expense of

the contractor.

No bulk spilling of water is allowed to re-infiltrate in the vicinity of the well. The discharged water has

to be carried away by means of discharge pipe towards a natural drain.

After completing the development, a pump should be installed inside the well at a depth above the well

screen. Some measurements should be taken before and after starting the pump and these include static

water level before pumping, the rate of discharge, dynamic water levels at various intervals during the

pumping period, time of starting the pump, time of any change in the discharge rate and time of stopping

the pump.

Following measurement should be recorded:

• Measuring pump rates: Control of the pumping rate during the testing by a suitable and accurate

device for measuring the discharge rate of the pump, e.g. by a valve in the discharge pipe. The size

of the discharge pipe and the valve should be such that the valve will form one half to three fourths

open when pumping at the desired rate.

• Step Draw Down Test (Water level measurement): The depth to water shall be measured several

times during the course of pumping test. The depth shall be measured during the course of Step

Draw Down Test lasting 30 minutes each.

• Constant Rate Test shall be carried out for a minimum of 12 continuous hours and recovery

measurement taken. Readings shall be taken at close intervals during the first two hours of the test

with the time between readings being gradually as the test continues. Measurement should be made

every ½ minute during the first five minutes after starting the pump, then every 5 minutes for an

hour, then every 20 minutes for about 2 hours. From this point on, reading taken at hourly intervals

are sufficient until the borehole reaches the state of equilibrium i.e. no changes in drawdown.

292

9.4.3 Water Quality Test

A sample of water from each borehole shall be taken at the end of the constant rate test for both

chemical and bacteriological analyses.

The sample container shall be clean and clearly marked showing

• The name of the community,

• Number of the borehole, and

• Date of sampling.

The chemical analysis shall determine the following:

• pH

• Fluoride

• Arsenic

• Temperature

• Manganese

• Total iron

• Colour

• Lead

• Total hardness

• Chloride

• Zinc

• Total dissolved solids

• Total nitrates

• Copper

• Total suspended solids

• Sulphate

The bacteriological analysis shall determine

• Total coliform and

• Total fecal coliform.

Temperature and pH shall be measured when samples are taken.

Chemical tests shall be done at a recognized laboratory or with a recognized portable testing kit

previously approved by the client. Results of chemical water tests shall form part of borehole

completion reports and shall be on the headed paper of the laboratory signed by the chief chemist with

the stamp of the laboratory.

9.4.4 Borehole Disinfection

All successful boreholes shall be disinfected after completion. This can be achieved by placing a

chlorine solution into the well so that a concentration of at least 50 mg/l (0.005%) of active chlorine

exists in all parts of the well at static conditions. All borehole parts above the water level should be

completely flushed with the solution. The solution shall remain in the well for a minimum of 4 hours

at the specified concentration before pumping the well to waste.

9.4.5 Successful / Unsuccessful Borehole

Unless in very specific geological context (highly confined aquifers) or preliminary agreed between

the parties (installation of electric/mechanic pumps for example), the maximum drilling depth shall be

150 meters below the ground level.

293

A borehole is considered productive, positive or successful if a minimum yield of 3-6m3 (3000-6000

litres per hour) is measured at the end of the development process. If a pump cannot be used, then the

"air-lift" discharge shall be at least 800 litters per hour. Boreholes with capacity less than 3-6 m3/hour

shall not be fitted with a submersible pump.

A successful borehole must be plumbed and vertical to be considered successful.

A borehole is considered unsuccessful

• If the drilling depth has reached 150 m and the yield of the borehole is less than the quantity stated

above or

• if for any reasons due to drilling problems, collapsing conditions, breakdown of the machine or any

other reasons the borehole cannot be completed.

In that case another drilling attempt has to be made. Payment is done for the successful borehole only.

In case that both drilling attempts are unsuccessful only 50% of actual costs done for the second

borehole will be paid.

Back Filling Unsuccessful Boreholes

All unsuccessful boreholes shall be filled with drill cuttings or other suitable material to 1m below

ground surface and a 1m grout seal placed on top to properly cover the hole.

294

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

COLD WATER AND FIRE HYDRANT PLUMBING SERVICES ENGINEERING FOR OFFICE

BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE FIELD

OFFICE AT THE AFRICAN DEVELOPMENT BANK (ADB)

295

AFRICAN DEVELOPMENT BANK (ADB) – PERFORMANCE SPECIFICATION

CONTENTS PAGE:

PART 1.0: Tender Conditions

PART 2.0: Design Criteria

PART 3.0: Mechanical Engineering Services Installation (Plumbing)

PART 4.0: Tender Drawings

PART 5.0: Tender Declaration

PART 6.0: Tender Schedule of Rates

PART 7.0: Tender Breakdown

296

2.0 TENDER CONDITIONS

1.1 Introduction

The purpose of this document and supporting drawings/data is to illustrate and describe the Contract

Works associated with the Building Engineering Services (BES) Systems + Applications.

The information contained in the Technical Specification and depicted on the Drawings is for the

purpose of obtaining a competitive Tender for the Mechanical Engineering Services (MES) Contract

Works

The Contractor must allow for liaising with other trades to ensure that the MES Installation is properly

coordinated / integrated into the Contract Works / Building Complex as a whole.

It is recommended that the Contractor visits the site in order to acquaint himself with the existing site

conditions, (access, existing site infrastructure services etc.), that might affect his Tender.

No claim arising out of any misunderstanding or neglect shall be considered.

1.12 Extent of the Contract Works

The MES Contract Works shall include all the necessary labour and materials and all

construction/building works, together with such tests, adjustments and commissioning of the

mechanical and electrical engineering services systems and applications as are required to form a

“complete installation”.

The MES Contract Works “Complete Installation” shall mean not only the major items of plant and

equipment detailed in this Document, but all of the incidentals/sundry components required for the

complete execution of the Contract Works.

1.13 Contract Works:

Design Development

The Contractor shall be responsible for carrying out the design development work in connection with

the BES Contract Works; this is in addition to that of the fundamental design of the mechanical and

electrical engineering services systems and applications specified within this Document and supporting

drawings/data.

The Contractor shall allow, within his Tender, for the following particular design development

calculations:

Cold Water Plumbing

To determine the required lengths of Cold Water Pipes, Control devices and Valves sizes, based upon

the completed plumbing installation drawings developed.

Sanitary Fixtures

To determine the required lengths of Soil Pipes and Control devices based the completed Soil Pipes

installation drawings developed.

1.14 Contract Works:

Regulations and Standards

The MES Installation shall comply with the Technical Specification (s) set out within this Document

with all relevant British Standards and Codes of Practice and with all other relevant Statutory

Instruments and Regulations current at the time of Tender.

297

1.15 Contract Works:

Materials and Workmanship

All materials must be suitable for their intended use/application and must comply with the relevant

Standards and be installed in accordance with the Codes of Practice and Manufacturer’s

recommendations.

All site operatives must be suitable qualified and experienced for the work that they are assigned to

carry out. All workmanship must be of a good standard.

The Project Architect/M&E Engineer shall reject poor materials and workmanship and it shall be the

contractor’s responsibility to put right such rejected Contract Works at his own expense.

1.16 Contract Works:

Programme

The Contractor shall allow adequate time within his overall Contract Works Programme for presenting

and receiving comments to / from the Project Architect / M&E Engineer with respect to:

(i) Design Development Information

(ii) Installation Drawings

(iii) Testing and Commissioning Procedures

1.17 Supervision of the Contract Works

The Contractor shall employ a competent, qualified and experienced Principal Resident Site Engineer,

who shall be in charge of the Contract Works during all working hours and in attendance until the

whole of the Contract Works has been completed and accepted on behalf of the Employer.

The Contractor’s appointed representative shall attend meetings on site and be empowered to answer

on behalf of the Contractor.

The Contractor shall appoint a Deputy Site Engineer to cover for periods of absence of the Principal

Residence Site Engineer.

1.18 Coordination of the Contract Works

The Contractor shall be responsible for the coordination of the mechanical engineering services

systems, (Plumbing) such that each may be installed in a manner which ensures the correct performance

of the system and avoids conflict in the positioning of the various BES elements.

The Contractor shall include within his Tender for the detailed development of his Installation

Drawings to contribute to a fully coordinated and integrated BES Installation.

1.19 Contract Works:

Installation Drawings

The Contractor shall prepare and submit to the Project Architect/ M&E Engineer, Installation Drawings

for all of the MES systems to be installed under the Contract Works, together with such schedules, data,

calculations, systems schematics and other supplementary details necessary to execute the Contract

Works.

The Installation Drawings shall be fully detailed, depicting the positions and physical dimensions of all

of the MES Systems (Plumbing) Components.

The minimum scale for the production of the coordinated Installation Drawings shall be:

Plant locations + Switch rooms: 1: 20

Floor Plans 1: 50

Site Services 1: 200

298

The Contractor SHALL MAKE due allowance for the preparation of the MES Installation Drawings

within his Tender and within his Overall Contract Works Programme

1.20 Contract Works:

Fixing of the Services Installation

The Contractor shall be wholly responsible for the sizing, supply and installation of all supports/fixings

for the mechanical engineering services.

1.21 Contract Works:

Builders Work

Builders Work in connection with (BWIC) the MES Contract Works, such as duct, holes, basses,

chasses etc. shall be detailed by the Contractor as separated drawings.

The Contractor shall inform the Project Architect/M&E Engineer of any BWIC that may affect the

building structure and/or envelope.

The Contractor shall make due allowance for the detailing of the BWIC requirements within his Tender

and within his overall Contract Works Programme

1.22 Contract Works:

Testing and Commissioning

The Contractor shall ensure that suitably qualified and experienced personnel, together with the

necessary instrumentation, are available at the time required to set to work, test and commission the

mechanical and electrical engineering services systems.

The format of the testing and commissioning procedure, together with the details to be entered on the

test sheets, shall be agreed with the Project Architect/M&E Engineer.

The Contractor shall agree with the Project Architect/M&E Engineer a Programme for the testing and

commissioning of the various Plumbing Systems.

The M&E Engineer shall retain a detailed record of all the testing and commissioning procedures on

site for examination.

The testing and commissioning shall demonstrate, amongst other things, that:-

(i) All Plumbing and Sanitary Installations are properly install and physically protected.

1.23 Contract Works:

Record Documentation

The Contractor shall supply to the Project Architect/M&E Engineer, as a prerequisite to the Practical

Completion of the Contract Works, a comprehensive record of the completed mechanical and electrical

engineering services installation. This shall take the form of:-

(i) AutoCAD based disk detailing all INSTALLATION DRAWINGS.

(ii) 4 No. Dyeline prints of all INSTALLATION DRAWINGS.

(iii) 4 No. Bound A4 copies of the OPERATING + MAINTENANCE MANUALS, to include:

d) Copies of all testing and commissioning certificates.

e) Manufacturers/Suppliers technical data for the maintenance and operation of all plant and

equipment, together with a schedule of spares provided.

f) Schedule recording all installation drawings.

The Contractor shall maintain accurate records of all testing and commissioning procedures throughout

the course of the Contract Works for incorporation into the O + M Manuals.

The Contractor shall have available a DRAFT COPY of the Record Documentation for inspection by

the Project Architect/M&E Engineer prior to Practical Completion of the Contract Works.

299

1.24 Contract Works:

Variations

All instructions, variations, additions to the Contract Works are only valid when agreed to/signed for

by the Project Architect (Manager).

Should the Contractor receive, during the progress of the Contract Works, any instruction for additional

work, Which he considers may affect the completion of the Contract Works within the prescribed

Contract Period, he shall be required to formally notify the Project Manager in writing within four (4)

days of the receipt of such and instruction.

1.25 Contract Works:

Practical Completion

The Contractor shall be responsible for inspecting the MES Installation (Plumbing) and shall have

prepared his own defects inspection list and shall duly attend to the same, prior to offering the

completed MES Installation to the Project Manager for inspection and acceptance on behalf of the

Employer.

The Project Architect/M&E Engineers’ inspection shall be one of formality and should not be

considered as and inspection for the purposes of forming the Contractor’s final list scheduling the

Outstanding Works.

The Contractor shall agree with the Project Architect/M&E Engineer, a suitable date for the FINAL

INSPECTION.

1.16 Maintenance of Services

Any works necessitating interruption or termination of any services required to be maintained or

serving areas outside of the designated works area shall be thoroughly coordinated and not be initiated

until a Programme of works indicating disruption time scales and/or temporary arrangements has been

submitted and agreed fully by all concerned.

1.26 Contract Works:

Defects Liability Period

The Contractor shall be responsible under the Contract for addressing/correcting all of the Plumbing

Contract Works defects occurring within a period of TWELVE MONTHS, commencing from the date

of the PRACTICAL COMPLETION CERTIFICATION.

During the Defects Liability Period, the Contractor shall provide prompt and effective “call back”

service to attend to any urgent faults which may develop and which would affect the day-to-day

function of the building complex.

The Contractor shall retain a written log on site recording the details of the defect – i: e, date

notified/date attended, fault identified, action taken, together with any ongoing investigations/remedial

work.

1.27 Contract Works:

Provisional Sums

Provisional Sums have been entered on the Mechanical Engineering Services Installation – Tender

Breakdown – Form of Tender Document.

These Provisional Sums provide for Works of Costs, which cannot be foreseen, defined or detailed at

the time of preparing the MES (Plumbing) Contract Works Tender Documentation.

The Provisional Sums include for the Contractor’s overheads and profit and therefore are to be included

in the Tender Breakdown as net sums without any further additions.

300

Instructions as to the deduction of expenditure in whole or in part of the Provisional Sums shall be

instructed by the Project Manager during the course of the Contract Works, as found necessary.

1.28 Contract Works:

Spares

The Contractor shall include within his Tender, recorded as separately identified costs, the supply of

spares for the:

I. Plumbing installation works

II. Sanitary Fixtures

1.29 Contract Works:

Schedule of Rates

The Contractor shall submit within his Tender, a priced copy of the Schedule Rates.

Each of the elemental rates shall include for all necessary labour and materials, together with overheads

and profit.

The declared Tender rates shall be used to evaluate all Works added, deleted and/ or amended against

the Contract Works Tender.

The Project Manager reserves the right to reject any tender which does not include the completed

Schedule of Rates, returned with the Tender Submission.

1.30 Contract Works:

Tender Breakdown

The Contractor shall, when submitting his Tender for the Contract Works, enter on the Tender

Breakdown – Form of Tender Document, Lump Sum Costs for each of the Mechanical and Electrical

Engineering Services elements as prescribed.

The Project Architect reserves the right to reject any Tender, which does not include the completed

Tender Breakdown.

3.0 Cold Water Service

2.1 System Description

The Bank building complex to be served with a potable cold water supply service drawn from the main

GUMA and dedicated Solar Powered Borehole water supply distribution pipework.

An incoming GUMA valves mains cold water connection to be installed within the secured perimeter

fenced Bank building as shown on the drawings.

A cold water supply connection to be made to this point to supply the 10m3 MDPE Water Tanks located

on a 9m high Water Tower to service the sanitary appliances and kitchen fixtures as set out in the

Architectural Drawings

(Refer to Architect’s Drawing for details of sanitary fittings).

75mm dia. Cold water supply connection to be made to the 10m3 MDPE Water Tanks connecting the

Fire Hydrant Booster Pumps and 50mm dia. MDPE pipe and associated fittings further reduced to

32mm MDPE pipe and associated fittings connected as shown on the pipework drawings to be installed

to the pressurized water purification system supplying cold treated water to the building.

301

2.3 System Equipment + Materials

(a) Pipework

Heavy duty polyethylene (HDPE) pipework to BS6572, BS6570, WIS4.32.03 @12 bar

(120metres), (174psi) with screwed joints, hydraulic pressure tested.

(b) Valves

(i) Main Isolation

Loose jumper isolating stopcocks to be installed on all cold water service principal distribution

points.

(ii) Local Isolation

Screw operated ball valves to be installed on cold water service to Individual / groups of sanitary

fittings and cold water service to stand pumps.

(c) Thermal Insulation

All internal cold water service pipework to be thermally insulated and vapour sealed by the

application of 38mm minimum thickness of pre-formed rigid CFC free phenolic foam sectional

pipework insulation with aluminum foil outer covering, having a thermal conductivity of 0.02

W/moC

2.4 General Standard of Pipework and Fittings

(a) Pipework Generally

All pipework shall be run at least 10” from any electrical conduit or lighting and power cables. Pipes

shall be spaced in ducts, ceilings and voids, trenches and below floors in a manner that permits

subsequent access to any pipe for maintenance or removal without disturbance to the remaining

pipework.

Branches from mains in horizontal ducts shall be kept clear of vertical ducts.

Pipes shall not be solidly built into walls or plaster and joints shall not be positioned within the thickness

of walls, floors or in any other inaccessible position. Pipes shall be fixed with a minimum clearance of

1” and a maximum of 1½” between the surface of pipe or covering and the finished surface of walls

and a minimum clearance of 4“ from finished surface of floor or ceiling at the lowest or highest points,

within a building.

Gradients on all pipes shall not be less than 1” in 20’0” in the case of domestic hot water service, except

where otherwise specified or detailed on the drawings or with the written approval of the Project

Architect/Engineer. All mains shall be laid to the gradients to ensure venting and drainage of the

service. All screwed joints shall be clean threaded and the bore carefully reamed to ensure the pipe is

free from burns or obstructions.

b) CAULKING OF JOINTS WILL NOT BE ALLOWED

All cold water rising mains into the building for sanitary and kitchen use shall be treated and disinfected

as shown in the drawings by the Sub-Contractor after completion of the installation and testing and

prior to handover.

The treatment and disinfection process shall be in accordance with the World Health Organization

(WHO) recommendations and the Sub-Contractor shall obtain from the Sierra Leone Guma Water

Company a written statement certifying that the treatment and disinfection has been satisfactorily

undertaken.

The Sub-Contractor shall include in his Tender for all labour and material costs associated with the

treatment and disinfection including any costs incurred by the Sierra Leone Guma Water Company

particularly with regards to an analysis of a water sample.

302

Efficient plugs shall be inserted in all open ends during the progress of the work. Plugs of wood, paper

or rag etc., shall NOT be used.

The Sub-Contractor shall be responsible for the location and removal of any stoppage due to foreign

matter or air lock which is found to impede the flow of fluid after the systems are put into use, including

the cost of making good all pipework, insulation, building decorations or other damage caused in

locating and making good these defects.

All pipework shall be run in accordance with the working drawings and shall be run clear of other

services, only where it is unavoidable shall the Sub-Contractor be allowed to neatly set round to avoid

ventilation trunking, cable trunking, drainage and other services, structural beams and other

obstructions.

Long sweep bends shall be used in preference to round elbows. Square elbows shall NOT be used. All

made or set bends shall have as large a radius as possible and shall be free from deformation of the bore

and the tube or any undue thinning of the wall of the tube.

All bends and sets shall be pulled cold on pipework up to 2” nominal bore, using a bending machine

with the correct formers for the size of pipe used.

Where the Project Architect/Engineer has given permission for fire pulled bends or sets these shall be

carried out using a forge and the whole length of the bend or set shall be heated and formed in one

operation. Any bend or set found to have been burnt or overheated shall be removed and replaced.

Tees shall be of the easy or twin elbow pattern except where square tees are installed to facilitate venting

and drainage.

Where a gradual reduction or increase in pipe diameter is required, i.e. pump connections, reducing

valve assemblies, etc., this shall be done by means of tapered pieces at least 6” long.

Reduction in pipe size shall be by reducing sockets, tees or taper pieces. These shall be of the eccentric

pattern to ensure proper drainage and the elimination of air pockets. Pipes shall be erected and provided

with flanges or unions as specified in in the document.

Flanges or unions shall be provided in runs of pipework at intervals of 12m and at all changes of

direction to facilitate maintenance. Flanges or unions shall be provided in plant rooms to enable any

items of plant or run of pipework to be dismantled. Mating flanges shall be mild steel on black ferrous

pipework and non-dezincification type gunmetal on copper pipework.

All pipework shall be in accordance with the BS given, in random lengths unless otherwise called for,

straight and free from blemish and damage. Ends shall be screwed to the correct length to the BS where

screwed pipe is called for and the ends shall be protected from damage by means of half sockets firmly

screwed on.

All black steel tubing shall receive one coat of primer protecting paint before leaving the works.

Water seals to be provided on drains from cooler condensate trays and any other items where the drains

are subject to pressure differentials.

Note that in all cases, the drains from pumps and cooling coils will not be less than ¾ “ size, with ample

rodding points suitable for maintenance.

303

(c) Pipework and Fittings

SERVICE PIPING FITTING

Mains cold water supply

/ cold water

MDPE (PE 80) to BS6572,

BS6570, WIS4.32.03 @12

bar (120metres), (174psi)

MDPE (PE 80) to BS6572, BS6570,

WIS4.32.03 @12 bar (120metres),

(174psi

Drain pipework all other

vents and exhaust piping

UPVC – BS 4514 As for cold water mains/cold water down

service/hot water service supply

Hose reel installation dry

riser

Galvanized steel tube to BS

1387 heavyweight quality

Screwed galvanized malleable iron

fitting up to and including 2” diameter.

Flanged 2½” diameter and above.

Note: The mechanical Sub-Contractor shall ensure that there is no contact between ferrous and non-

ferrous materials.

If through any accident, defect or burst, pipes become fractured the Sub-Contractor shall replace the

same, free of charge to the Client.

All drains, and overflow pipework etc., from the cooler batteries, pumps, etc., shall be provided and

taken to the nearest gulley.

(d) Screwed and Flanged Joints

Screwed joints shall be used on pipework up to 2” diameter.

Flanged joints shall be used on pipework 2½” and above, except where exposed to view in corridors or

rooms when pipework up to and including 3” diameter shall be fitted with unions in lieu of flanges.

Flanged or union joints shall be fitted to all pipework 64mm diameter and above, except where exposed

to view in corridors or rooms when pipework up to and including 3” diameter shall be fitted with unions

in lieu of flanges.

Flanged or union jointed shall be fitted to all pipework at interval not exceeding 40’0” and at all changes

of direction, to facilitate erection and dismantling pipework.

All flanges on steel pipe shall be wrought iron of mild steel machines on face and edge with dimensions

and bolt holes drilling as follows to BS No. 10 Table ‘E’.

All flanges shall be truly parallel on face and bolts proved free in holes before pulling up.

Flanged joints shall be made with Taylor’s copper corrugated rings or Klingerite joints of the full face

pattern 2mm thick. Flanges shall be bolted together with hexagonal bolts and nuts to BS 916 of the

same material and finish as the flanges. Each bolt shall have washers and when pulled up the bolts shall

NOT protrude more than one thread through the nut.

Flanges on copper pipework shall be Admiralty quality gunmetal.

All joints on mild steel pipework in tank rooms and plants rooms shall be flanged. On cooper pipework

in tank rooms and plants rooms’ flanges shall be provided on all items of plant.

Silver alloy welding will only be permitted in special circumstances and must be agreed with the M&E

Engineer, prior to use.

304

(e) Unions

Unions shall be generally of malleable iron with two bronze seats as the Navy Pattern for service 2”

and under and below 50psi

Unions shall be fitted on the outlet of each screwed valve where installed, except in the case of draw –

off points and on pipework connections to items of plant.

The use of connectors or long screws and back nuts will not be permitted under any circumstances.

(f) Valves and Cocks

Valves and cocks shall be provided where called for on the drawings and as specified.

All valves and cocks in tanks and plants shall be flanged with the exception of drip point assemblies.

All valves and cocks on all services 2½” and above shall be flanged with the exception of drip point

assemblies.

Flanges shall be dimensioned and drilled in accordance with the details in the document.

Valves and cocks installed in normally visible positions in rooms and corridors shall be chromium

planted.

All chromium plated valves shall be of the easy clean type with composition disc hand wheels,

elsewhere hand wheels shall be of malleable iron.

All valves and cocks shall be fitted in such a manner that they are readily accessible for operation and

maintenance.

Stopcocks shall be provided for isolating individual sanitary fittings, and shall be chromium plated

screw down easy clean type with lock-shield and dust caps.

Washers suitable for the duty they shall be fitted. All stopcocks shall be in accordance with BS 1010

manufactured from Admiralty quality gunmetal.

The Sub-Contractor shall ensure that valves listed in the following schedules comply with the Water

Authority’s requirements and shall include the cost of all stamping necessary.

Service Hattersley Fig No. 0r Equal

Low Pressure Cold and Hot Water 33 X

Services up to and including 2” 35 F-D

Low Pressure Cold and Hot water

Services 2½” and above 599/1E-D

Cold Water Rising Main Internal to 33

Buildings up to and including 2” 35 F-D

Cold Water Rising Main Internal to 599/1E-D

Buildings 2½” and above

Pressured Tapped Measuring Orifice Valves 1432

Ball Valves

Ball valves shall be of the equilibrium type with cast iron bodies, copper ball float mild steel lever and

gunmetal working parts as Glenfield and Kennedy Ltd.

305

Non-Return Valves

Non – Return valves shall be of the swinging flap type gunmetal bodies with screwed or flanged ends,

Hattersley Fig. No. 47 or equal and approved.

Non – return valves on hot water supply mains between the section and delivery of the circulating

pumps shall be of cast iron with flanged connections and gunmetal (Admiralty quality). The valve shall

be so designed that its action is sensitive to the slightest pressure difference Holden and Brooke

‘Senflux’ pattern.

Emptying Cocks

Emptying cocks shall be provided at all low points and on the dead side of all main section isolating

valves as Hattersley.

Emptying cocks shall be fitted to all items of plant and shall be lubricated plug type with cast iron

bodies and flanged connections Audco Fig. No. 62.

The outlets of these cocks shall be extended and hose unions with caps shall be fitted.

Three Way Cocks

Three way cocks fitted as escape taps on calorifier vent pipes shall be Hattersley.

(g) Strainers

Strainers where indicated on the drawings or specified to be fitted into pipework runs shall be of the

‘Y’ type in all cases and shall be of Hattersley manufactured in bronze to 2” diameter. Above 2”

diameter strainers shall be manufactured in cast iron by Hattersley.

Cast steel strainers shall be suitable for pressures up to 125 psi.

All strainers except where otherwise stated shall be flanged.

Where strainers are used to protect reducing valves they shall be provided with mesh gauze of the size

recommended by the manufacturers of the equipment they are to protect.

(h) Pressure and Altitude Gauges

Pressure and altitude gauges shall be provided where indicated on the drawings and specified herein.

Gauges shall be provided on the suction and discharge connections of each pump.

Gauges shall be mounted between the pumps and the pump isolating valves.

Pressure gauges shall be of the Bourden tube type 6” diameter brass cased. The gauges shall conform

to the relevant BS and shall be calibrated from zero to twice the working head in meters. The gauges

shall be complete with and adjustable red pointer and a bronze cock.

Gauges shall be installed such that they can be readily removed and such that they can be easily read.

Altitude gauges shall be fitted where shown on the drawings.

Pressure and altitude gauges shall be as manufactured by Sir W H Bailey, Hopkinson or Dewrance.

(i) Thermometers

Indicating thermometers shall be of the mercury in rigid stem type having 6” dial with needle pointer.

They shall be calibrated 500 F to 2480 F for hot water services. Where fitted on cold water mains they

shall be calibrated 500 F to 1040 F.

306

All thermometers shall have suitable oil filled well to enable them to be removed from pipework or

plant without draining down. Where such wells are installed in pipework the free cross-sectional area

of the pipe the flow should not be unduly restricted. This may necessitate a larger section of pipe to

take the well. This also applies to any other items taper pieces shall be provided at any pipe diameter

change.

All thermometers shall be tested to read alike, between 1000 F and 2000 F in the case of hot water

thermometers, when bulbs are immersed in water and the discrepancy between the highest and lowest

reading shall be not more than 120 F.

Thermometers shall be installed such that they can be readily removed and such that they can easily be

read. Thermometers shall be installed on all main hot water service flow and returns on each hot water

service calorifier.

(j) Air Eliminators and Air Cocks

The Sub-Contractor shall provide and fix where indicated on the drawings and at all high points in the

pipework that require venting, automatic air vents of the Chas. Winn & Co. Ltd. Manufacture type ‘A’

with type outlet 2 or type ‘B’ with lockshield cut –off valve. Eliminators shall be complete with air

bottles, isolating valves and discharge pipes.

(k) Expansion

All pipework shall be arranged so that expansion may be readily taken up by bends or changes in

direction. Where expansion cannot be accommodated in this manner and where indicated on the

drawings then expansion joints with flanged ends shall be used.

Where expansion joints are called for and fitted these shall be capable of the full expansion of the pipe

and shall be able to withstand both axial and transverse stresses when in operation and shall be installed

strictly in accordance with the manufacturer’s instructions.

Expansion joints shall be fitted in accordance with the drawings and in other positions where in the

Sub-Contractor’s opinion the use of an expansion joint will obviate undue stress being set up in the

pipelines.

The pipework shall be stressed initially when cold by leaving gaps at the appropriate points equal to

50% of the total expansion calculated for that section. This cold draw shall be taken up only after all

anchor points and brackets are grouted in and are rigidly fixed and proved firm by the Engineer or his

Representative.

Before the final pull up is made the amount of cold draw allowed shall be checked by the Engineer and

proved correct.

All pipes shall be fixed with sufficient clearance from walls, joints, floors or other obstructions capable

of resisting lengthwise expansion and special care shall be taken to avoid pipe fixings or supports near

junction with main pipe runs preventing movements of branches.

Connections of branch mains wherever possible shall be taken as near to anchor points as is practicable

to avoid undue movement or stress in the branch connection.

Where such connections are impracticable the branches shall be pre-stressed by cold drawing and due

allowance made for movement of the main pipe at that point.

Approved guides as required by the manufacturer of the expansion devices shall be provided to ensure

that the pipe expands co-axially with the pipe run and that the expansion joint takes up the full

expansion of the pipe without any undue bowing of the pipe. Expansion joints shall be fitted in the

horizontal plane unless otherwise specified. Positions of the guides shall be approved by the Engineer.

307

Expansion bellows shall be of suitable thickness for the pipe to which they are fixed and where fitted

to hot water services shall be manufactured from stainless steel.

Each expansion joint shall be flanged either side to the appropriate BS Flange Table, or as detailed in

Claus 2.1.03 of this Specification.

Anchors shall be provided as shown on the drawings and as necessary for any additional changes in

direction or additional expansion joints authorized by the Engineer.

Anchors shall be positioned such, that the pipe expansion is controlled in the direction intended.

Anchors shall be either forged steel clamps of adequate cross sectional area, bolted to a sole plate, or

formed of MS sections welded to the pipe and bolted to a sole plate.

The sole plate in each case shall be rigidly fixed to the building structure, subway or duct wall by means

of raw bolts or rag bolts firmly grouted in.

Anchors shall NOT be fixed to structural steelwork unless the written approval of the Engineer is

obtained.

Wherever possible the forces on any anchor shall be equal in both directions, but in any case the out of

balance thrust shall not exceed 20 KN.

(l) Pipe Supports

The Sub-Contractor shall provide for all pipe supports on all runs of pipework. Supports shall be pipe

hangers and rods, clips, rollers and chairs etc., as required for the particular duty and for stable and

efficient support. The supports shall be chosen for the particular duty they are to perform and shall

allow free movement and expansion of the pipework. All supports shall be grade to the required levels

for air elimination and drainage.

Pipe fixings and supports shall be arranged at intervals not greater than the following distances apart:

Pipe Size Horizontal Vertical

Pipework Inches Runs Feet Runs Feet

Mild Steel ½” 6’6” 6’6”

¾” 7’9” 9’9”

1” 8’9” 9’9”

1¼” 8’9” 9’9”

1½” 9’9” 11’6”

2” 11’0” 11’6”

2½” 12’0” 14’6”

and above

Vertical pipes shall be stayed from the wall with a minimum of two clips spaced equally between floors

and ceiling.

Flanges, sockets and unions where installed shall coincide with support positions as far as is practicable.

Where vertical takeoff from horizontal pipes and mains occur, the horizontal main shall have a support

positioned at this point.

308

Supports shall be positioned adjacent to all valves and other special components to be removed for

maintenance leaving the pipework adequately supported at the free ends.

Pipework installed in the main vertical ducts and false ceiling areas shall be supported from channel

iron supports provided by the Sub-Contractor firmly bolted to the structural tabs. The Sub-Contractor

shall also include in his Tender for providing and installing all necessary nuts and bolts and for drilling

the flanges of channel iron as necessary for fixing all supports. The Sub-Contractor shall provide all

hanger rods, clips, ‘U’ bolts, roller and chairs etc.

The design and manufacture of supports shall be submitted to the Engineer for approval before they are

manufactured or installed.

Pipes fixed both horizontally and vertically to walls in rooms shall be supported by malleable iron

schoolboard pattern brackets with split pipe holders into walls or with drilled back plates where they

are to be screwed to wood or ironwork.

For copper pipework, pipe holders or supports shall be of gunmetal or brass or prefabricated mild steel

brackets or clips which shall be lined with brass or copper strip where contact is made with the pipe.

Where pipework is covered with non-conducting covering, supports shall be as described above, except

that the design shall be such that the face of the covering shall be supported at least 1” clear of the

building structure.

All brackets, hanger rods, clips and roller and chairs shall be arranged to give ample movement for

expansion of the pipework.

All necessary ‘U’ bolt or other guides shall be provided to counteract side or vertical movement of

piping due to expansion.

The Sub-Contractor shall be responsible for position and alignment of all built in brackets and supports

before concreting by the Main Contractor commences and the positions are maintained until the

concrete is set.

(m) Pipe Sleeves and Floor Plates

Sleeves must be fitted to pipes at all points where the pipes pass, through walls floors and ceilings.

Sleeves shall be of the “Armac” or other approved telescopic type for all ferrous pipework.

Sleeves for cooper, brass or gunmetal. Ferrous sleeves shall NOT be used.

All sleeves through floors shall project ¼” above finished floor surface except to the kitchen area where

the projection shall be 1¼” unless otherwise instructed and shall be fitted with split hinged floor plates

chromium plated finish. The Sub-Contractor shall arrange for the Main Contractor to haunch the

grouting or floor finish to support this projection.

The Sub-Contractor shall provide and fix chromium plates split hinged wall plates where pipes pass

through walls and are visible from within the room (s).

The Weight of the pipes shall not be borne by the sleeves and all sleeves shall be set concentric with

the pipes. Clearance all round shall be left to allow for free movement.

Sleeves passing through external walls and roofs to outside must be watertight and weatherproof using

asbestos yarn and lead wool caulked between the pipe and the sleeve, to the satisfaction of the Engineer.

309

The Sub-Contractor shall be responsible for ensuring that no pipes are bedded in the sleeves so as to

restrict movement, by any making good by the Main Contractor or others, or by any cause whatsoever.

The Sub-Contractor shall also be responsible for the accuracy and correct alignment and levels of all

holes required to be left or cut for the fitting of sleeves.

All sleeves required to be built into or embedded in structural concrete shall be placed in position by

the Sub-Contract before the concrete is placed. The proper care shall be taken by the Sub-Contractor

to check and ensure that the sleeves remain in the correct; position whilst concreting takes place and

until the concrete is set.

(n) Painting and Labeling

(i) Painting

The painting of all insulated and uninsulated pipework, steelwork used for supports, hangers and

brackets where exposed in rooms and corridors, other than in the tank room and main vertical duct,

shall be carried out by others to match the decorations, but the Sub-Contractor shall supply and apply

one primer coat other than that provided by the manufacturers, ready for receiving the finishes.

Where ferrous pipework is to be insulated the Sub-Contractor shall first paint the pipework with one

coat of red –oxide paint prior to the application of the insulation.

The Sub-Contractor shall paint, all uninsulated ferrous pipework, steelwork, used for supports, hangers

and brackets in the tank room, duct, false ceilings with one coat of red – oxide paint.

The Sub-Contractor shall thoroughly clean down, wire brush and paint with one coat of red – oxide

followed by one coat of black bituminous paint al external steel work erected under this Contract.

The Sub-Contractor shall include in his Tender for making good any paintwork damaged before

handover.

(ii) Labeling

Valves with metal hand wheels:

The Sub-Contractor shall provide a black ivorine label for each with the duty and identification of the

valve shown in white letters. This information shall be repeated as in the valve charts. The labels shall

be secured within the hand wheels by the spindle nut.

Valves and composition handwheels and cocks with fixed operating Keys shall be provided with and

ivorine label for each valve or cock engraved with duty of the valve or cock and secure by means of a

brass ring loosely fitted around the spindle and retained by the valve hand wheel or cock key.

The brass ring and label shall be such that they cannot interfere with the correct operation of the valve

or cock, and the label shall be clearly seen when in position.

All labels shall be of black ivorine with white lettering.

Exceptions to above:

The following valves and cocks shall not have labels fitted:

(a) Valves on branch circuits in rooms

(b) DHWS and CW service stopcocks to draw-offs.

The Sub-Contractor shall not remove, cover paint over, deface or alter any labels fixed to items of plant

or equipment by the manufacturer.

The Sub-Contractor shall provide on all insulated and uninsulated pipes, except in occupied rooms

identification colour bands, at not more than ½” intervals on long straight runs of piping, near to all

valves, at all inlets and exits of trenches, ducts and building at all tees and unions.

310

Pipelines in plant rooms, ducts, voids, false ceilings etc., shall have detailed identification in accordance

with the latest British Standard and including arrows indicating the direction of flow, contents of pipe

and the pipe bore.

All identification bands shall consist of painted non-ferrous metal bands clipped securely to the pipe or

pipe insulation.

(o) Washing Out

Before being put into regular service, all installations shall be blown through and washed out to the

satisfaction of the Engineer and the Sub-Contractor shall include for all the necessary disconnections

and reconnections of pipework and plant to enable this to be done.

(p) Spares

The Sub-Contractor shall supply, in suitable containers, sufficient lubricating motor oil and lubricating

grease, together with all filling can and grease guns, suitable for all plant and equipment supplied under

the Sub-Contract to last over a period of six months from the date of handing over. In addition to the

aforementioned items the Sub-Contractor shall supply the following spares at the time of handover:

3 Air Cock Keys

3 Keys for Lock shield Valves

6 Valve Packings for each type of Valve installed

1 Gland packing for each Pump

3 Sets of Joint Rings for each size of Flange installed

1 Set of Spanners to fit all Nuts on Plant and Pipework

1 Set of Spare fuses for all Control Equipment

1 Complete set of Replacements for all Filters including Grease Filters.

2.5 Plant and Pipework Services

(a) General Description of Installation

The Pipework Services and Associated Plant Installation shall comprise the following:

i Boosted Cold Water Mains and Firemain Service to Hose reels via Pressure Booster Pumps Sets.

The Cold Water Mains Pump located within the Water Treatment and Disinfection containment at

the basement level of the Water Tower and the Firemain Service Pumps located on concrete plinth

by the Water Tower and protected by secured metal fencing and covering from inclement weather.

ii Dry Riser Installation complete with individual inlets and inlet Breechings on each floor level

piped from rising mains water service.

iii Cold Water Down Service to all Sanitary Fixtures, Sinks in kitchenette and Standpipes from the

Cold Water Mains Pump

iv HVAC Air Handling unit condense lines piped to drain.

v Firemain Service to Hose reels for Firefighting including pipework and accessories from Firemain

Service Pumps

(b) Boosted Cold Water Mains (CWM) and Firemain Service (FMS)

The combined cold water/fire mains services shall be provided by 2 x 5m3 MDPE Cold Water Service

Tanks located at the top of the Water Tower.

The combine water tanks shall supply cold water to the Water Treatment and Disinfection containment

(Water Purification Unit) located at the basement level of the Water Tower supplying treated cold water

through a package pressure boosting pump set to all sanitary facilities and kitchenettes on ground and

first levels, Security post and Standpipes located within the secured perimeter fenced and cold water

Firemain Service via Pressure Booster Pumps to Hose reels as shown on the drawings

311

The cold water storage tanks located at top of the Water Tower is also supplied with incoming Guma

Valley Water Company (GUMA) mains water to ball valves and from the incoming Borehole mains

water to ball valves via Borehole Submersible Pump as shown in the drawings.

Pressure reducing valves shall be installed as shown on the drawings to balance the pressure required

at the various outlets on the booster pump systems.

(c) Cold Water Mains (CWM) Package Boosting Pump Unit

(i) BS MXV Fixed Speed Vertical Multi-Stage Pressure Boosting Pump Unit.

The Cold Water Mains (CWM) Package Booster Pump Unit shall be type BS1F 1MXV 25-210/C

Model as manufactured by CALPEDA or similar, the duty as specified below:

Voltage: 400V

Phase: 3~

kW: 1.5

Hp: 2

Suction (DN1): 37mm

Discharge (DN2): 37mm

This unit shall be complete with all necessary valves and interlocking controls to provide automatic

operation.

(d) Firemain Service (FMS)

(i) BS2F-2NMD 32/210C/A Fixed speed Horizontal Centrifugal Pressure Boosting Pump Unit

The Firemain Service (FMS) Package Booster Pump Unit shall be type BS2F-2NMD 32/210C/, Model

as manufactured by CALPEDA or similar, the duty as specified below:

Voltage: 400V

Phase: 3~

kW: 5.5

Hp: 7.5

Suction (DN1): 75mm

Discharge (DN2): 50mm

The unit will incorporate duplicate pumps for run and standby operation.

All interconnecting pipework within unit is shall be in 50mm galvanized steel tube to BS 1387: 1985

heavy weight quality.

(e) Pressure Reducing Valves

All pipework from booster pump unit to fixtures within the building shall be run in a medium density

polyethylene (MDPE) pipes for the Cold Water Mains (CWM) supplies and galvanized steel pipes to

BS 1387: 1985 heavy weight quality for the Firemain Service supplies.

Pressure reducing valves shall be installed in the branch connection to the drinking water coolers on

each floor level. The pressure reducing valves are to be type LRV 151 as manufactured by Spirax.

All valves to be selected by manufacturer to obtain a maximum outlet pressure at the water cooler of

60 psi

(e) Drinking Water Coolers

Package drinking water coolers will be supplied and installed in the positions shown on the drawings

type SF 200 as manufactured by Acro-Kool Limited.

312

Units to be provided with PRV and isolating stopcock on each branch connection thereto.

(f) Local Water

The Sub-Contractor shall make himself fully conversant with the Local Water Authority Bye-Laws and

it is the responsibility of the Sub-Contractor to inform the Water Authorities when work commences.

(g) Incoming CWM Supply

The Sub-Contractor shall commence the installation after the Water Board’s stopcock at basement level

as shown on the drawings.

(h) Final Connections

Taps and sanitary fittings shall be supplied and fixed under the Main Contract, but all final connections

to sanitary fixtures shall be carried out by the Sub-Contractor.

2.6 Cold Water down Service

(a) General Description

The cold water storage tanks located at the top of the Water Tower on a purpose made tank area

supplying cold raw water to the Water Treatment and Disinfection containment (Water Purification

Unit) located at the basement level of the Water Tower and supplying cold raw water to the Firemain

Service (FMS) Package Booster Pump Unit.

The Booster CWM connects to the tank via a delayed action Ball Valve. The cold water down service

distributes to all sanitary fixtures within the building via the floor areas and service riser ducts.

(b) Cold Water Storage Tank

The tank shall be of supplied and installed on pre-formed concrete floor on the top of the Water Tower

as shown on the drawings.

The tank shall be MDPE pressed construction as manufactured by Millar Tanks & sons Ltd, Kissy

Dockyard, Freetown or similar. Size 2M long x 1M wide x 1M deep and nominal capacity 5000 and

2000 liters respectively as shown for the cold raw water tank and the Water Treatment and Disinfection

tanks.

The tank is to be supplied with all necessary components for erection on site and shall be complete with

cover and access manhole and cowl ventilator.

The Sub-Contractor is to allow for all necessary pipe connection to all tanks including draincock,

CWM, CWDS headers, vent cowl, overflow and warning pipe, as shown on the drawings.

The Sub-Contractor shall check all builders work in connection with the tank installations to ensure

compatibility and ensure acceptance of same.

(c) Final Connections

Taps and sanitary fittings will be supplied and fixed under the Main Contract, but all final connections

to sanitary fixtures shall be carried out by the Sub-Contract.

2.7 First Aid Fire Fighting Equipment

(a) General Description

First aid firefighting Extinguishers are to be provided on each floor level including the electrical switch

room area at the basement level where portable C02 fire extinguishers will be provided under the

contract.

A dry riser installation will be provided within the compound in protected areas for use by the Fire

Brigade.

313

(b) Hose reels Installation

Hose reels will be supplied and installed on each floor level of the automatic recessed swinging reel

pattern type FM as manufactured by Kidde Thorn.

Each hose reel to be complete with isolating stop valve with adequate labels identifying same.

(c) Dry Riser Installation

A 2” diameter dry riser will be supplied and installed as shown on the drawings complete with 1½”

diameter landing outlet valves, 1½” diameter double inlet breaching at ground level and all necessary

drain points etc. All dry riser equipment shall be as manufactured by Kidde Thorn with the dry riser

pipe in galvanized steel tube to BS 1387 heavy weight quality. All pipe joints to be in accordance with

the Standard Pipework Specifications.

All landing boxes for outlet valves and box for inlet breaching shall be as manufactured by Kidde

Thorn, as shown on the drawings.

(d) Portable Extinguishers and Fire Blanket

Portable C02 fire extinguishers will be supplied and installed as indicated on the floor drawings, in the

kitchen and adjacent the electrical switch room areas at basement level of the types and sizes as shown

on the drawings.

2.8 OVERFLOWS AND CONDENSE DRAIN LINES

(a) AHU Condense Drains

Condense lines from the cooling coil trays within each air handling unit shall be run in ¾” galvanized

pipe to BS 1387.

The condense line shall incorporate an anti-siphon loop and dirt pocket plug etc., as shown on the

drawings. The condense line shall run to a PVC pipes connecting to a central drain riser in 2” galvanized

tube to BS 1387, as shown on the Drawings. The condense drain riser shall connect to the drainage

system at basement level. The Sub-Contractor is to allow for all connectors to drain condense from the

AHU’s.

3.0 WATER PURIFICATION (optional item)

3.1 Basic System Design:

Water Treatment processes vary from relatively simple treatment methods to complex and sophisticated

processes.

This system below provides general design and requirements for the construction of a safe water

purification system for the Sierra Leone Field Office at The African Development Bank (ADB) to

remove chemical contaminants by using simple, inexpensive and locally abundant materials. The

system also incorporates ultraviolet disinfection to neutralize biological contaminants.

3.2 Biological Decontamination:

Contaminants that compromise the safety of water are both biological and chemical and different

strategies are required for their neutralization or removal. Strategies for removing biological

contaminants include filtration with ceramic filters, chemical treatment (e.g. with chlorine or iodine),

and exposure to ultraviolet (UV) radiation.

UV water treatment and water disinfection is environmentally-friendly and energy-saving water

treatment and water disinfection process for water and drinking water. Water treatment and water

disinfection with high-energy UV radiation is an environmentally-friendly method established for more

than 100 years. It uses no chemicals, with no added chlorine or ozone.

Special UV lamps destroy microorganisms such as bacteria, viruses and parasites and help decompose

chemicals harmful to health.

Neither smell nor taste of the water is impaired.

This UV solution is used e.g. for process and drinking water.

314

3.3 Advantages with UV light

No impairment of taste and smell

No added chemicals

No environmental pollution

Short exposure time

Effective against chlorine-resistant pathogens

Simple handling

Low-maintenance method

Very low operating costs

UV radiation is the surest method for biological decontamination, though until recent years it has been

too delicate, expensive, complicated and resource intensive for use at the household or community scale

in developing societies.

3.4 Chemical Decontamination

Biological contamination of water is only part of the problem, especially when considering

contaminants and other agricultural runoff. Filtration with ceramics, chemical treatment and UV

radiation will not remove contaminants from water.

Charcoal (graphite carbon) is an inexpensive material that has been manufactured worldwide for

millennia, and because of its electrochemical surface properties has great potential for effectively

removing agrichemical contaminants from water. Charcoal water filtration is in fact an ancient

technique, and today is employed at the municipal scale for water treatment. The charcoal that is used

in water treatment plants, however, is a high-grade material produced using an industrial process to

increase its reactivity and enhance its capacity as a filtration medium (often called “granular activated

carbon,” or GAC).

The World Health Organization and numerous academic studies identify granular activated carbon

(GAC) as the best available technology for the control of many agrichemicals and synthetic organic

chemicals in water for drinking or otherwise.

The charcoal filtration system design proposed utilizes basic, garden-variety charcoal that can be

purchased in local markets here in Freetown.

This material performs nearly as good as industrial GAC as a filtration medium. For example, studies

have shown low-grade char from the burning of crop residues to be about one-third as efficient for

adsorbing dissolved contaminants when compared with industrial-grade GAC.

Since the wheat straw was exposed to air during the charring process, it is likely that proper charcoal

manufactured in an earthen kiln or brick oven is of appreciably higher quality than wheat straw char

and exhibits a significantly larger capacity for adsorption of water contaminants.

3.5 Treatment System Design

The amount charcoal necessary to treat a given volume of drinking water depends on the concentration

of contaminants in the water as well as the chemical adsorption capacity of the pulverized charcoal.

The water filtration system described here is designed around a general set of parameters, making

conservative estimates regarding its capacity for contaminant adsorption. In place of experimental data

using specific agrichemical contaminants, we regard dissolved organic carbon (DOC) as our general

contaminant and design the system around its removal. Several studies have shown that DOC

adsorption by granular carbon can block or displace other adsorbed organics such as contaminants.

Therefore, the estimated capacity of charcoal to absorb DOC in general, assuming a modest propensity

for absorption on the part of the charcoal and a generous concentration of DOC in the local water supply

315

Conservatively assuming 10 mg DOC/g charcoal as the absorption capacity of charcoal and 50 mg

DOC/L as the DOC concentration in natural surface waters, we estimate that 5 grams of charcoal are

needed to sufficiently purify 1 liter of water: With this ratio, and assuming the EPA recommended daily

water intake of 30 liters per person per day, roughly 54 kilograms of charcoal are required to supply

drinking water to one person for one year.

Cartoon illustration of the treatment system design

Design for a gravity-fed system will employ a sand pre-filter followed by pulverized charcoal filter medium supported on a

bed of gravel. Exposure to UV radiation after filtration will neutralize biological contaminants. A photovoltaic panel can

provide electricity for the UV lamp.

Conservative estimates suggest that the sand layer should be about 50 centimeters thick. The sand acts

both as a pre-filter to remove particulates and to precipitate aqueous iron complexes, which can

interfere with UV disinfection.

A diffuser plate is placed over the sand to reduce the turbulence of the influent and prevent channels

forming through the sand. The thickness of the charcoal layer will depend upon how many people are

using the system as well as its desired lifetime (i.e. the time until the charcoal has to be replaced). The

purpose of the gravel layer is to prevent clogging of the perforated pipe by carbon granules – this layer

need only be about 20 centimeters in thickness.

3.6 BS MXV Vertical Multi-Stage Pressure Boosting Pump with 1 Fixed Speed

3.6.1 Construction

The Pressure Boosting Pump with automatic operation shall consisting of 1 Vertical Multi-Stage

Pressure Boosting Pump with 1 Fixed speed on a common baseplate, with suction and delivery

manifolds, gate and non-return valves, pressure switches, pressure gauge, control panel and 200 liters

diaphragm tank.

3.6.2 Operation

The control panel, with electronic card, manages the pump operation, the changeover of pump starting

sequence and it stops the system when there is no air in the tank (patented system).

Pumps starting in a cascade sequence, with a signal from the pressure switches.

3.6.3 Electrical control panels for fixed speed pump units.

Electrical control panels for pressurization units, all with electronic card with microprocessors, for

managing pump operation.

316

The microprocessor carries out continuous secure checks during all the various work phases of the

pumps and incorporates all necessary functions, thus reducing electrical and electronic components

inside the panel.

3.6.4 Maximum clarity for all signals

The status of the unit shall be easily identified on the front of the electronic card with the following

signals:

- Power on led.

- No water led.

- Failure led.

- Pump running led

- Pump automatic operation led

- Pump stop led

3.6.5 Maximum simplicity of control

The front of the electronic card shall feature the following signals and controls:

- AUT-STOP push-button (1 for each pump)

- MAN push-button (1 for each pump)

- RESET push-button.

3.6.6 Performance - Fixed speed Pressure boosting set with 1 Vertical Multi-Stage Pump

Fixed speed pump

Mains: 400V 3~

Motor: 400V 3~

Motor Pres. switch 1

bar

Maximum capacity* Membrane

litre

Vessel

litre

kW HP min max Q l/min H m

BS1F 1MXV 25-210/C 1.5 2 6,5 8.5 60 66 100 200

3.6.7 Dimensions - Fixed speed Pressure boosting set with 1 Vertical Multi-Stage Pump

Fixed speed pump

TYPE Connection mm Weight

kg

DN 1 DN 2 Hf Hv h1 L1 m1 BS1F 1MXV 25-210/C 37mm 37mm 1065 1345 120 625 410

Dimensions not binding to be verified when ordering

3.6.8 The Fixed speed Vertical Multi-Stage Pressure boosting pump furnished for water supply service to the

building shall be supplied with the specified drivers, controls and pump accessory items by the pump

manufacturer. The pump, driver and control shall be:

� Guaranty by manufacturer against any defects

� Factory Mutual Research Corporation (FM) Approved

� Listed for water supply service.

4.0 SCOPE OF WORK

4.1 The Water Purification System at the Sierra Leone Field Office at the African Development Bank

(ADB) shall include treatment and disinfection. The system to be installed shall comprised of 2 x

2000Liter MDPE Cold Water Tanks, The first tank shall be design for a gravity-fed system and will

employ a sand pre-filter followed by pulverized charcoal filter medium supported on a bed of gravel.

Exposure to UV radiation after filtration will neutralize biological contaminants. Power from the

Bank’s photovoltaic panel can provide electricity for the UV lamp. The treated and disinfected water

will be stored in the second MDPE Cold Water Tank and ready to be pumped to the building with a

1.5kW (2HP) Fixed speed Vertical Multi-Stage Pressure Boosting Pump.

317

The pressure boosting pump sets model BS1F 1MXV 25-210/C shall be furnished with driver,

controllers and accessories as detailed in this specification. Pump manufacturer shall have unit

responsibility for the proper operation of the complete unit assembly as indicated by field acceptance

tests.

4.2 Supply and installation, erection, testing and commissioning of the Sierra Leone Field Office at the

African Development Bank (ADB) Water Purification System with mechanical and electrical

equipment, instrumentation, pipes, valves, fittings, supports, cables etc. complete in all respects, and

preparation & submission of drawings/other documents to the Project Architect & obtaining interim &

final Approval/Sanction/NOC (No Objection Certificates), during and after execution of work as

required.

4.3 Field Acceptance Test:

A field acceptance performance test shall be conducted upon completion of pump installation.

The test shall be made by flowing water through calibrated nozzles; approved flow meters or other such

accurate devices as may be selected by the Project Architect. Test shall be carried out in the presence

of:

� The installing contractor

� The Project Architect/M&E Engineer

� The owner's representative

TENDER DRAWINGS/FIGURE NOS - Mechanical Engineering Services Installation

The Contractor’s attention is drawn to Tender Conditions, Clause 1.4. Contract Works: Named

Plant, Equipment + Materials.

The Contractor shall enter below the names of the Manufacturers / Suppliers of the Plant, Equipment

and Materials included within his Tender Price, either by confirming his use of the ‘As Named’

Manufacturer/Supplier or by defining his proposed alternative.

Plant, Equipment, Materials As Named Manufacturer/Supplier

in this Document

Proposed Alternative

Manufacturer/Supplier

(Country of Origin)

1.Drinking water coolers – Acro – Kool

Model:SF200

Acro – Kool Limited

2.Cold water storage tank- 5000Ltr. Millar or Shankerdas & Sons Limited

3.Pressure reducing valves Type LRV

151 (CWDS and boosted CWM)

Spirax Sarco Limited

4.Valves / Strainers Hattersley Newman Hender Limited

5 Boosted cold water packaged pump

unit model BS1F 1MXV 25-210/C

CALPEDA - BS1F 1MXV 25-210/C

6 Hose reels Type: FM

Dry riser equipment

Kidde Thorn Fire Protection Ltd

To form a complementary part of the Tender Submission

Signed: ………………………………….. Date: …………………………………

For:………………………………………..

Position: …………………………………..

318

SCHEDULE OF RATES - Mechanical Engineering Services Installation

To Supply, install, set to work, test and commission the complete systems

Clause System US $ Lump Sum Cost

1.0

a)

b)

c)

2.0

a)

b)

c)

d)

e)

f)

g)

3.0

a)

4.0

a)

b)

c)

d)

e)

5.0

a)

6.0

7.0

Cold Water Service:

To include:

Cold Water Pipework, valves + fittings & Accessories

2 x 5,000 liters Cold water storage tanks + fittings & Accessories

Drinking water coolers Acro-Kool Model: SF200

Water Purification:

To include:

UV radiation

Photovoltaic panel to provide electricity for the UV lamp.

Pre-filter sand

Pulverized charcoal filter medium

Bed of gravel.

Insulated pipework, valves + fittings

2 x 2,000 liters Cold water storage tanks + fittings & Accessories

Waste Water Pipes:

To include:

100mm Waste (Soil) Pipes + fittings & Accessories

Hydrant Firefighting Services

To include:

pipework, valves + fittings

Boosted cold water packaged pump unit model Hydropak

Hose reels Type: FM, Dry riser equipment

Pressure reducing valves Type LRV 151 (CWDS and boosted CWM

Valves/Strainers

CO2 Fire Extinguishers

To include:

9kg Portable CO2 Fire Extinguishers

Testing + Commissioning

To undertake setting to work, testing and commissioning of the complete

Mechanical Engineering Services Installation, as described and detailed in

the Specifications.

Record Documentation

To prepare ‘As Installed’ Record Drawings together with Operating and

Maintenance Manuals and Tender Conditions

TOTAL LUMP SUM TENDER PRICE: US$

CARRY TO FORM OF TENDER

Signed:…………………………………. Date:

For:……………………………………

Position:……………………………….

319

SPECIFICATIONS FOR THE SUPPLY, INSTALLATION, TESTING AND

COMMISSIONING OF 2 X FIXED SPEED HORIZONTAL PRESSURE BOOSTING FIRE

HYDRANT PUMPS FOR OFFICE BUILDING AT REGENT ROAD, HILL STATION,

FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN DEVELOPMENT

BANK (ADB)

320

SPECIFICATIONS FOR HORIZONTAL FIRE HYDRANT PUMPS

1.0 GENERAL

This document shall be read in conjunction with all relevant commercial documents. In case of

contradiction between technical specification and other documents, data in technical specifications

shall prevail.

1.1 All work under this contract shall be carried out in accordance with the Technical Specification and the

latest revisions of International Standards & Codes, the Sierra Leone Fire Force Services and Norms,

the Electrical Distribution and Supply Authority (EDSA) Rules and Regulations.

BS 2F - 2 Fixed speed pressure boosting pump sets for civil use with 2 MXH

1.2 Construction

The Pressure Boosting Sets with automatic operation shall consisting of 2 (N+1) pumps on a common

baseplate, with suction and delivery manifolds, gate and non-return valves, pressure switches, pressure

gauge, control panel and 800 litres diaphragm tank.

1.3 Operation

The control panel, with electronic card, manages the pump operation, the changeover of pump starting

sequence and it stops the system when there is no air in the tank (patented system).

Pumps starting in a cascade sequence, with a signal from the pressure switches.

1.4 Electrical control panels for fixed speed pump units.

Electrical control panels for pressurization units, all with electronic card with microprocessors, for

managing pump operation.

The microprocessor carries out continuous secure checks during all the various work phases of the

pumps and incorporates all necessary functions, thus reducing electrical and electronic components

inside the panel.

321

In particular:

- Pumps starting in a cascade sequence according to water demand

- Changeover of pump starting sequence.

- Delay start-up of the 2nd pump in case of breakdown of pressure switch 1 or after a power cut

- Avoid pump starting in case of water hammering.

- Activate the alarm when pressure 1 fails.

- Activate the alarm when air cushion in the vessel drops.

- Stop the pump when air cushion is over*.

* Patent pending

1.4 Maximum clarity for all signals

The status of the unit shall be easily identified on the front of the electronic card with the following

signals:

- Power on led.

- No water led.

- Failure led.

- Pump running led (1 for each pump).

- Thermal block led (1 for each pump).

- Pump automatic operation led (1 for each pump).

- Pump stop led (1 for each pump).

1.5 Maximum simplicity of control

The front of the electronic card shall feature the following signals and controls:

- AUT-STOP push-button (1 for each pump)

- MAN push-button (1 for each pump)

- RESET push-button.

1.6 Performance - Fixed speed Pressure boosting sets with 2 Horizontal Centrifugal Pumps

Fixed speed pump Mains: 400V 3~

Motor: 400V 3~

Motor Pres. switch 1 bar Pres. switch 2 bar Maximum

capacity*

Membrane

litre

Vessel

litre

kW HP min max min max Q l/min H m

BS2F-2NMD

32/210C/A

5.5 x 2 7.5 x 2 6 8 5,5 7.5 500 56 500 800

* Maximum pumps flow at minimum setting pressure of 2nd pressure switch.

1.7 Dimensions - Fixed speed Pressure boosting sets with 2 Horizontal Centrifugal Pumps

Fixed speed pump TYPE Connection mm Weight

kg

DN 1 DN 2 Hf Hv h1 h2 L1 L2 m1 B B2

BS2-2NMD

32/210C/A

G 3 G 21/2 890 1370 272 380 460 440 550 700 800 -

Dimensions not binding to be verified when ordering

1.8 The Fixed speed pumps furnished for fire protection service shall be supplied with the specified drivers,

controls and pump accessory items by the pump manufacturer. The pump, driver and control shall be:

� Guaranty by manufacturer against any defects

� Factory Mutual Research Corporation (FM) Approved

� Listed for firefighting and protection service.

322

2.0 SCOPE OF WORK

2.1 The pumping equipment shall be installed at the Sierra Leone Field Office at the African Development

Bank (ADB) as recommended in the National Fire Protection Association (NFPA), Sierra Leone Fire

Force Services Standard for the Installation of Horizontal Centrifugal Fire Pumps. The fire pump shall

be designed to deliver 500 litres per minute.

The fire pump shall also be capable of delivering not less than 150% of rated flow at not less than

65% rated head.

The pressure boosting pump sets model BS2-2NMD 32/210C/A shall be furnished with driver,

controllers and accessories as detailed in this specification. Pump manufacturer shall have unit

responsibility for the proper operation of the complete unit assembly as indicated by field acceptance

tests.

2.1.1 Preparation of firefighting scheme drawings and submission to the Project Architect and M&E

Engineer for their approval prior to execution of work.

2.1.2 Supply and installation, erection, testing and commissioning of the Sierra Leone Field Office at the

African Development Bank (ADB) Fire Hydrant System with mechanical and electrical equipment,

instrumentation, pipes, valves, fittings, supports, cables etc. complete in all respects, and preparation

& submission of drawings/other documents to the Project Architect, concerned authority the Sierra

Leone Fire Force Services & obtaining interim & final Approval/Sanction/NOC (No Objection

Certificates), during and after execution of work as required.

2.2 Manufacturer's Factory Tests:

Each individual pump shall be hydrostatically tested and run tested prior to shipment. The pump shall

be hydrostatically tested at a pressure of not less than one and one-half times the no flow (shut off)

head of the pump's maximum diameter impeller plus the maximum allowable suction head but in no

case less than 250 psig.

2.3 Field Acceptance Test:

A field acceptance performance test shall be conducted upon completion of pump installation.

The test shall be made by flowing water through calibrated nozzles, approved flow meters or other such

accurate devices as may be selected by the Project Architect and the Sierra Leone Fire Force Services

authority having jurisdiction. The test shall be conducted as recommended in NFPA Pamphlet 20 by

� The installing contractor

� The Project Architect/M&E Engineer

� The owner's representative

� Concerned authority the (Sierra Leone Fire Force Services) having jurisdiction and with that

authority's final approval and acceptance.

Failure to submit documentation of factory and field tests will be just cause for equipment

rejection.

3.0 HORIZONTAL CENTRIFUGAL PUMPS:

The fire booster pumps shall be of horizontal centrifugal fixed speed (single stage) construction

specifically labelled for fire service and shall be an approved Fire Pump Model

The pumps shall be connected to an underground 75mm fire main system. The suction supply for the

fire pump shall be from an elevated 10m3 storage tanks at a maximum pressure of pounds per square

inch (psig) and a minimum pressure of psig. The pump casing shall be cast iron with inch 125 pound

ANSI rated suction and inch (125), (250) pound ANSI rated discharge flanges machined to

International/National Standards dimensions.

323

4.0 ELECTRIC MOTORS:

The pump driver shall be horizontal foot mounted ball bearing induction motor rated horsepower, 3-

phase, 50Hertz with open drip-proof NEMA enclosure for operation on volt phase service. The motor

locked rotor current shall not exceed the values stated in NFPA Pamphlet 20. The motor shall be

mounted on a steel base common to the pump and shall be connected to the pump with a flexible

coupling protected by a suitable guard. The fire pump manufacturer shall accurately align the pump

and motor shafts prior to shipment. After field installation but prior to grouting the base, a millwright

or similarly qualified person shall check and verify or correct the shaft alignment.

5.0 ELECTRIC MOTOR CONTROLLERS:

The automatic electric motor controller shall be (UL listed), (FM approved) specifically for fire pump

service. The controller shall be designed for

� Full voltage

� Part winding

� Primary resistance reduced voltage

� wye-delta open transition

� wye-delta closed transition

� Auto-transformer

� Solid state (soft start) type starting

The controller shall be rated for the horsepower specified in this specification’s electric motors

section. The controller shall be capable of interrupting a short circuit current at least equal to the

available short circuit current in the controller supply circuit. This fire pump controller installation

requires to withstand ratings of not less than amps RMS symmetrical at an operating voltage of

volts.

The controller shall be:

� Floor or wall mounted for electrical connection to the motor by the equipment installer.

� Mounted on a common base with the fire pump and wired to the motor by the pump manufacturer.

6.0 FITTINGS:

The pump manufacturer shall furnish piping accessory items for the pump installation which will adapt

the pump connections to the fire protection system and test connection as follows.

Fittings subjected to pump discharge pressure shall be ANSI (125), (250) pound rating. Fittings

subjected to suction pressure shall be ANSI 125 pound rating.

� Eccentric tapered suction reducer

� Concentric tapered discharge increaser

� Hose valve test header

� Hose valves with caps and chains

� pump casing relief valve

� Automatic air release valve

� Hose valve head drain valve

� Suction and discharge pressure gauges

7.0 TECHNICAL PARAMETERS

7.1 Brief Description of Fire Hydrant System

7.1.1 Full Scheme (For general information of the tenderer)

2 No. Fire Hydrants Pumps (each electric motor driven) shall be installed in the pump chamber below

ground, pumping water from the 10m3 MDPE above ground water tank. The common outlets of fire

pump delivery system shall cater to the following:

i) Internal First Aid Hose Reels in each floor.

ii) External Fire Hydrants.

324

At the top of each Wet Riser an Air Vessel assembly with Air Relief Valve, a Drain-valve, pressure

gauge etc. shall be provided to take care of pressure surges and also for letting out entrapped air in the

system.

7.2 Operation

Fire Hydrant System & Sprinkler System

Water supply header and main pipe up to hydrant valve/landing valves shall be kept pressurized by the

jockey pump which shall start automatically on receiving the impulse from the pressure switch in case

of any pressure drop in the header. It shall stop at a pre-set pressure as soon as pressure builds up in the

header.

For smaller fires, first aid hose reel would be used; while hydrant valve would be used for bigger fires.

In the event of fire outbreak, opening of hydrant valve/hose reel will result in fall of pressure in the

header and electric motor driven fire pump shall come into operation automatically through the impulse

from the pressure switch. The fire pump shall be stopped manually only.

The setting of the pressure switches shall be done keeping the above sequence in consideration.

a) End suction type, horizontally mounted centrifugal pump, TAC approved, capable to deliver 500

litres per minute (lpm) of clear water at minimum 70 M TDH, coupled to a suitably electric motor

mounted on a common base frame and anti-vibration pads coupling, coupling guard and fixing

bolts etc. Motor HP shall be suitably selected to suit minimum discharge and residual head at the

top most hydrants. The characteristic curve should have a large range of discharge points for

different heads.

7.3 C I Sluice Valve

C I components of the sluice valve shall be of Grey cast iron. The valves shall be flanged having solid

wedge gate valve, inside screw, gate valve with open-close indications etc. all conforming to

International/National but of nominal pressure rating of PN 1.6 as per TAC norms.

Test Pressure at manufacturer’s works

Flange drillings shall normally be as per pump manufacturer standards. However, if the manufacturer

drills the flanges to other standard specifications, the valves shall be supplied with a pair of matching

flanges, nuts, bolts, washers; rubber insertion etc. and such flanges shall have inside threads to suit

pipes of same nominal size as that of the valve.

The quoted price of the valves shall also include cost of arrangement for securing the valves in `open'

or `closed' positions by padlock/rivetted strap, where required per TAC norms.

7.4 G M Valves

Gun metal components of the peets valves i.e. Gate Valves, Check Valves i.e. non-return valves, and

Globe valves etc. shall be of Gun Metal conforming to Grade 2. The valves shall be having flanged or

screwed ends, gate valves with open-close indications etc. all conforming to ASTM and the Sierra

Leone Fire Services Codes.

325

7.5 C I non return valves

C I reflux valves, i.e. swing check type non-return valves, shall be conforming to manufacturer

standards. Test pressures shall be same as per CI sluice valves.

7.6 M S Pipes and Fittings

All M S pipes shall be heavy/medium quality as mentioned in the schedule of items up to 150 mm N

B, (minimum 6 mm thick) construction approved by Fire Standard.

All pipes outside the building shall be laid underground at a depth of 0.6m (approx.) and laying shall

be as per layout drawing, excavation, back filling of earth, cutting holes in existing structure where

necessary, providing puddle collars/pipes as required & making good the damages including making

the concerned portion of the structure water tight.

Erection of over-ground piping shall be complete with necessary pipe supports hangers with MS

angles/plate/nut bolts/clamps etc. with fabrication as required including providing MS puddle

pipes/collars as required for punctures through walls/slabs etc.

Erection of pipe lines shall also include chipping of wall; making holes inside RCC or brick walls, slabs

and necessary civil works for restoration of the surface after completion of erection. The quoted tender

rate shall include all the above works, as well as the cost of route markers for underground pipe lines

as per following specifications.

Route marker with cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate 20 mm

nominal size) of size 600mm x 600mm at bottoms and 500mm x 500mm at the top with a thickness of

100mm including inscription duly engraved as required (spacing approx. 15m or as directed at site).

No extra payment will be made on this account.

7.7 Gauges/ Switches

a) Pressure Gauges

Pressure gauges with controlling cocks etc. shall be of approved make having pressure range, bourdon

material and dial size as specified in schedule of items.

b) Pressure Switches

Pressure switches with accessories shall be of approved make and design and shall actuate (cut-off'

and/or `make contact' as required) at pre-set pressures.

7.8 Landing Valves (Hydrant Valve)

Gun metal landing valve (Internal/External Fire Hydrants) with oblique type single outlet as per

schedule of quantities complete with hose coupling adaptor of 63mm size, instantaneous spring lock

arrangement and blank cap with chain conforming to International & National Standards. External Fire-

Hydrants to be provided with stand posts as specified in schedule of quantities. Orifice plates may be

provided where inlet pressure is required to be reduced as per WBFS requirement.

7.9 Branch Pipe

Gun metal, short type, instantaneous pattern branch pipe to suit fire hose delivery coupling of 63mm

size complete with G M nozzle of 20mm nominal size conforming to International & National

Standards

326

7.10 Hose with Coupling

63mm nominal internal dia. hose, rubber lined wooven-jacketted coupling with Type-II (Reinforced

Rubber lined type), firefighting delivery hose 25M long each, fitted with gun metal coupling of 63mm

size with multi serrated tail and double instantaneous spring lock arrangement comprising of male half

at one end and female half at other end complete with rubber cup washer and conforming to

International & National Standards.

7.11 Hose Reel

Swinging hose reel conforming to IS 884 & comprising of 3 ply rubber hose of length specified in

schedule of items, 20mm (3/4") nominal bore (25kg/cm2/350psi bursting pressure), mild steel pressed

reel with 170 degree swinging, nozzle of G M chromium plated, with non-jamming controlling handle

which shall stay at the `ON' `OFF' position as set, wall brackets with `U' shaped reel carrier made of C

I complete with 25mm NB G M valve at the inlet, and orifice plates (if necessary for reducing pressure).

7.12 Air Vessel

Mild steel air vessel adequate size to take care of pressure surges during operation of the system and

venting of entrapped air in the system shall be complete with air relief valve, pressure gauge, drain

valve and shut-off valve at the inlet.

7.13 Valve Chamber

Valve chamber of adequate size to accommodate external valves shall be constructed as directed per

site condition.

7.14 Fire-Brigade Connections

Fire-Brigade connections (inlets) to Riser and Above Ground Storage Tanks shall be with one number

of 63mm instantaneous inlets. Other aspects of the connection shall be as the Sierra Leone Firefighting

Codes.

7.15 Painting

All external steel surfaces shall be thoroughly cleaned to remove rust, scale etc. before applying the

primer.

a) All underground piping shall be provided protective wrappings as per TAC norms.

b) All over ground piping/hose boxes/landing valves/hose reel, M S frames etc shall be painted with

two (2) coats of RED LEAD primer or equivalent followed by two coats of Post Office Red

coloured Synthetic enamel finish paint.

c) All other equipment shall be given a red oxide/zinc chromate primer and two (2) coats of synthetic

enamel.

8.0 SPECIFICATION (ELECTRICS)

8.1 Controls

i) Electric Motor driven fire & jockey pumps & diesel engine driven fire pump shall start

automatically through pre-set pressure switches in proper sequence as elucidated in Cl. 4.2

above.

ii) Stopping of all fire pumps shall be manual only.

iii) Audio visual alarm shall be sounded when fire pumps start/starts.

iv) Power supply 'ON' indication shall be provided in the Fire Pump Control Panel.

327

8.2 Electric Motors:

The pump driver shall be horizontal foot mounted ball bearing induction motor rated 7.5.horsepower,

3-phase, 50Hz with open drip-proof NEMA enclosure for operation on 400 volt phase service. The

motor locked rotor current shall not exceed the values stated in NFPA Pamphlet 20.

The motor shall be mounted on a steel base common to the pump and shall be connected to the pump

with a flexible coupling protected by a suitable guard. The fire pump manufacturer shall accurately

align the pump and motor shafts prior to shipment. After field installation but prior to grouting the base,

a millwright or similarly qualified person shall check and verify or correct the shaft alignment.

The A C motor shall be approved type & totally enclosed fan cooled and shall have Class B insulation

with degree of protection IP55 conforming to manufacturer’s standards and frame.

The motor shall be suitable for both DOL and STAR/DELTA starting, as required. The motor terminal

box shall be suitable for receiving aluminium/copper cables and suitable for positioning on the motor

body at intervals 90 degree as required for the particular application. The motor shall have also two

distinct terminals for earthing. The motor shall be suitable for 415V (- 15% to + 5% variation) 3-phase

50HZ plus/minus 3% AC supply.

8.3 Motor Control Centre (MCC)

The MCC shall be made of sheet steel of thickness not less than 2mm, totally enclosed, self-supporting,

floor or wall mounted dust and vermin proof cubicle type construction with multitier compartmental

arrangement with degree of protection IP54.

It shall have a panel of uniform height placed with front access for operation as well as cabling. MCC

panel shall be completely front wired type having all device/termination etc., approachable from front

without any requirement of back access for maintenance repairs and cabling. Provision of cable entry

shall be from the top or bottom to match with cable layout of the pump room.

Main fire pump motor shall have star/delta or DOL starting as per TAC requirement. The motor control

circuit shall be provided with test facilities so that it is possible to test the control circuit with the main

motor circuit disconnected. Control voltage shall be 240 V, A C single phase derived from an isolating

MCCB.

The main busbar of the MCC shall be of electrical grade copper and shall have continuous current

rating as required but in no case less than the current rating of incoming switch fuse unit. The busbar

shall be easily accessible from the front of the cubicle and shall be colour coded for phase identification.

A copper earth busbar of adequate cross sectional area shall be provided in the bottom or top part of

the cubicle and shall run for the entire length of the MCC.

Start/stop push button, auto/manual selector switch and indication shall be provided and the MCC for

control of the motor.

Incomer cubicle shall incorporate voltmeter, ammeter with respective selector switches, power factor

meter and phase indication lamps.

Each outgoing cubicles shall have ammeter with selector switch and on/off, trip indication lamps.

Ammeters for incoming/outgoing cubicles, for motor it shall be suppressed scale type beyond full load

rating up to 8 times of full load current for taking care of starting current kicks.

328

8.4 Cables

All power cable types shall be certified and marked in accordance with the British Approvals Services

for Electrical Cables (BASEC) or equivalent. Cables shall be segregated from other services and shall

comply with IEE Specification 034.

All power cables shall be 4-core, XLPE/PVC/SWA/PVC armoured power cable rated for 0.6/1kV with

copper or aluminium conductor cables manufactured and tested as per BS 6724.

8.5 Installation accessories and earthing materials

One lot of installation accessories and earthing material shall be installed for equipment and cables and

earthing of equipment.

8.6 Power supply

For MCC one 415 V, A C 3-Phase and neutral 50HZ feeder of adequate capacity shall be made available

at the MCC incomer.

If the equipment is required to operate at any other voltage, necessary transformers & converters shall

be included in the scope of the tenderer.

329

Item Materials Name of Brand

1. Electrical Motor Driven Fire Pump

a) Pump BS2-2NMD 32/210C/A or Equal approve

b) Motor CROMPTON or Equal approve

2. Anti-vibration Pads Approved quality and make.

3. C I Valves Approved quality and make.

4. G M Valves Leader/Kitz or Equal approve

5. Hydrant valves, Fire Brigade connections, GM

branch pipes, couplings etc.

Minimax/Fireshield or any good brand with

Approved

Certification

6. Fire Hoses Approved make with ISI mark.

7. Hose Cabinet Good quality fabricated as per specification (sample

cabinet to be approved).

8. First Aid rubber hose (for swinging hose reel) Approved quality and make.

9. Power/Control Cables Havell’s or Equal approve

10. Push buttons Siemens/Schneider or Equal approve

11. Pressure Gauge H Guru/Fiebig.

12. Pressure Switches Fiebig.

13. Auto Transfer Switch Havell’s/GE/Emerson.

14. Indicators Lamps Essen/L & T/Siemens or Equal approve

15. Ammeters and Voltmeters Automatic Electric/IMP or Equal approve

16. Portable Extinguishers Approved make bearing relevant BS EN marking on

body as well as the 1st charge of chemicals/gases.

17. Star Delta/DOL Starter Siemens/Schneider/ABB

18. Contractors (Main and Auxiliary) Siemens/Schneider/ABB

19a) Bimetal O/L Relay with single phasing

preventor, combined unit

Siemens/Schneider/ABB

b) Single phasing preventor (Negative sequence

current sensing type)

Schneider/ABB/Siemens

20. XLPE/PVC/SWA/PVC armoured power cable

rated for 0.6/1kV with copper or aluminium

conductor cables manufactured and tested as

per BS 6724 and flexible cables

All cable types shall be certified and marked in

accordance with the British Approvals Services for

Electrical Cables (BASEC) or equivalent.

21. Voltmeter, Ammeter Selector Switch Kaycee or Equal approve

22. Steel Conduits (conforming to IS in all respects

a) Galvanized BEC/NIC/AKG.

b) Black Enamelled BEC/NIC/AKG.

23. MCCB and Accessories Schneider (Compact NSX)/ ABB (T-Max) /Siemens

(3 VL)

24. C T Kappa/Matrix or Equal approve

25. MCB DB, MCB ABB/Schneider/Siemens

All the materials shall be BS/EN/ NFPA marked wherever available from the list of manufacturer given above,

wherever the BS/EN/ NFPA marked materials are not available, the materials shall be from the best quality

available in the market, subject to submission of satisfactory test report with prior approval from the Project

Architect.

330

SPECIFICATIONS FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

FM200 GAS FIRE SUPPRESSION SYSTEM FOR OFFICE BUILDING AT REGENT ROAD, HILL

STATION, FREETOWN FOR SIERRA LEONE FIELD OFFICE OF THE AFRICAN

DEVELOPMENT BANK (ADB)

331

TECHNICAL SPECIFICATIONS:

FM200 GAS FIRE SUPPRESSION SYSTEM (Optional item)

Product Description:

HFC-227 finds use in fire suppression systems in data processing and telecommunication facilities, and

in protection of many flammable liquids and gases. HFC-227 falls in the category of Clean Agents and

is governed by NFPA 2001 - Standard for Clean Agent Fire Extinguishing Systems. Effective fire

suppression requires introducing a concentration of the HFC-227 agent between 6.25% and 9%

depending on the hazard being protected. Its NOAEL level for cardiac sensitization is 9%.

Environmental Protection Agency allows concentration of 9% volume in occupied spaces without

mandated egress time, or up to 10.5% for a limited time. Most fire suppression systems are designed to

provide concentration of 6.25-9%.

FM-200 Storage Components - Storage components consist of the cylinder assembly(s), which contains

the FM-200 chemical agent, and the cylinder bracket(s), which holds the cylinder assembly securely in

place.

FM-200 Distribution Components - Distribution components consist of the discharge nozzles used to

introduce the FM-200 into a protected hazard along with the associated piping system used to connect

the nozzles to the cylinder assembly.

Trim Components - Trim components complete the installation of the FM-200 system and consist of

connection fittings, pressure gauge, low-pressure supervisory switch, electric valve actuator, and

manual valve actuator.

Slave Arrangement Components - Slave arrangement components consist of the pneumatic valve

actuator(s), actuation check valve, vent check, actuation hose, and fittings required for a multiple

cylinder (slave) arrangement.

332

Supplemental Components - Supplemental components include the discharge pressure switch and

manifold check valve. They supplement the core equipment or complete a specific multi-cylinder

configuration.

Control Panel - This device monitors the condition of the electric actuator, detectors, warning devices,

cylinder pressure, and any manual release and abort stations. All electric or electronic devices must

connect to the control panel in order to function.

Early Warning Detection and Alarm Devices - Early warning detection devices coupled with manual

release and abort stations maximize system efficiency while audible and visual alarm devices alert staff

of alarm conditions.

FIRE DETECTS AND ALARMS

Fire control panel +smoke and heat detectors

Fire alarm bell +manual button,

Light warning gas discharging

Working pressure 4.2 Mpa or 2.5Mpa

Discharge time ≤ 10s

Filling density: ≤ 950kg/m3

System working power: AC 220V DC 24V 1A

System working pressure: 10c~55C

Working method Manual, auto, and electrical

Product Details (Basic Info.)

Model No: ZF-150

Agent: Hfc-277ea

Type: Transportable Fire Extinguisher

Size: 70kg

Power Source: Pressure Fire Extinguisher

Retirement Life: 10 Years

Portable Extinguisher: Hfc-277ea

Effective Range: 5m

Certification: CE

Dry Powder Type: Ordinary Dry Powder

Object: Class A Fires

Colour: Red

Fire Extinguishing Means: 5.3MPa ~ 5.4MPa

Design Pressure of the Nozzle: Normal 0.7MPa, Min.0.40MPa

Working Temperature: -10 to +60

Discharging Time: Less 10s

Gas Filling Rate (Density): Less 1.15kg/L

Power Supply: DCV 24, 0.5A

Max Protected Area: Max 800m², Max Volume 3600m³

Polit Valve Powder Supply: 6.0± 1.0 Mpa (20c)

System Working Pressure: -10c~55c

333

Installation:

A clean power line directly from Generator Room / Public Power source will feed a control panel in

dedicated room housing UPS system

Power system will include multiple 3-phase online backup units in a redundant parallel configuration

UPS output will be feed to a distribution panel located in the UPS room from where power will be

cabled to servers, lighting, switches, controllers and accessories

Low power overhead lighting will be located in UPS rooms, server rooms and adjacent corridors, all

of which will be powered by UPS

Heat, optical, ionization and carbon monoxide alarms will be installed in server rooms, UPS rooms and

adjacent corridors, and connected to ports on the NetCommander central monitoring system

Automatic Inert Gas Fire extinguishers will be installed in server rooms and UPS rooms in addition to

manual fire extinguishers. Manual fire extinguishers will be installed in corridors

Server rooms will be fitted with a fireproof, fire sealed doors. Windows and other unsealed openings

will also be fire sealed. Seals will be rated for up to 60 minutes. This will allow any gas discharged

from automatic extinguishers in the event of a fire emergency while the room is unoccupied to be

retained within the discharged area long enough to permeate racks and equipment cases where fires

may have started. Poorly sealed rooms incapable of retaining gases long enough and in sufficient

concentrations may render automatic inert gas fire extinguishers less effective.

Multiple IP Cameras will be installed in server rooms, UPS rooms and adjacent corridors. They will

connected to the network and configured to be monitored directly from any authorized computer on the

LAN or across the Internet

At least one IP Camera focused on the entry door will be configured to work with NetCommander to

send a photo alert to designated email accounts every time the door is opened.

Infrared Motion Detectors configured to work with NetCommander will send similar email alerts every

time someone enters the server room.

334

INFORMATION & COMMUNICATIONS TECHNOLOGY (ICT) SYSTEM INSTALLATION

335

SPECIFICATION FOR THE SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

INFORMATION & COMMUNICATIONS TECHNOLOGY (ICT) SYSTEM INSTALLATION FOR

OFFICE BUILDING AT REGENT ROAD, HILL STATION, FREETOWN FOR SIERRA LEONE

FIELD OFFICE OF THE AFRICAN DEVELOPMENT BANK (ADB)

336

ICT Terms of Reference

1) WAN Connectivity

The Bank has two type of WAN and Internet connectivity at the current site of Serra Leone Field Office.

VSAT connectivity

Internet Connectivity through local Provider.

The Bank has a contract agreement with the different connectivity providers. The move or transfer of

the VSAT and Internet links will be handled separately by the BANK and the existing connectivity

providers.

2) Network Active Devices

The current network actives devices such as Routers, Switches, Firewalls, Access Points, and servers,

others IT equipment’s and Racks will be transferred from the current site to the new location.

In addition to the existing equipment, the Bank will provide required complementary network

equipment for the new building. When the construction of the building will be on progress, in line with

the Global framework agreement with CISCO and partners to order directly from Cisco the required

network active devices.

The procurement of additional network active device will be handled directly by the BANK.

3) Unified Communication (UC) equipment’s (Voice & Video)

The existing Unified Communication equipment for Voice and Video at the current location will be

transferred to the new location.

In addition to the existing equipment, the Bank will provide required complementary UC equipment

for the new building. When the construction of the building will be on progress, in line with the Global

framework agreement with POLYCOM - MICROSOFT, and partners, The BANK will handle directly

the procurement from POLYCOM - MICROSOFT the required additional UC equipment.

4) Local Area Network Data & Voice Cabling infrastructure standards

To streamline the cabling the Bank has adopted the followings as reference standards among others:

1. ISO/IEC 24764 (Generic cabling for data centers)

2. ISO/IEC 11801:2002 A1 & A2 (Generic cabling for customer premises)

3. and the CENELEC EN 50173-5 (Cabling for data centers)

4. TIA 606-A (Labeling Standard For Networks)

337

Section Cabling system

structure

information

Spécifications Commets G

ener

al

Support Voice, Video and Data

Standard (response

to proposal and

installations will be

tested against the

standard)

Cat 6A, 7, 7A ( cat 7 preferred)

(ISO/IEC 11801:2002 category 7/class F)

Require data sheet from the

service provide.

Installation

requirement

Trucking shall follow the approved color

codes

Trucking facility to allow for

future demands, the cabling

system must be easy to

expand and maintain.

Passive

Components

All proposed components including the

patch cords have to be produced by the same

manufacturer:

The number of passive end

points shall be determined by

the possible number of staff

to be accommodated in any

given area + an increase of 30

%.

Hori

zon

tal

Cab

lin

g

Minimum cabling

type

The horizontal 4 pair cable shall be Category

7 UTP to meet the quality and performance

criteria necessary to ensure correct operation

of the installation for frequencies to 500

MHz and to ensure the compliance with the

warranty. The same standard shall be applied

to patch cords.

The installation design and

routing of all cables shall take

account of the manufacturer

limits as specified in the data

sheet.

Category 7 cable (CAT7), (

are specified in ISO/IEC

11801:2002 category 7/class

F), It is a cable standard for

Ethernet and other

interconnect technologies

that can be made to be

backwards compatible with

traditional CAT5 and CAT6

Ethernet cable.

Network Outlets

(TO)

The RJ45 connector shall be screened to

ensure protection against EMI and for Alien

cross-talk compliance

cabling should take into account the esthetic

and should have a minimum distance of

90cm to 1m between the cables and energy

sources that can cause electromagnetic

disturbances such as energy transformers,

air conditioners

The horizontal cable length

shall not exceed 100 m

copper

300+ m for fiber

Network Outlets

Copper Patch

Panels (RJ45)

Each connector shall provide both T568A

and T568B color code identification for the

pins at the rear of the connector. The punch

down is to be in accordance with the T568B

color code. Reassignment of pairs shall not

be accepted

The number of network

outlets shall be dependent on

the number of staff per given

area.

To avoid installation errors, the wire

organizer of the snap-in connector must be

identified by the same standard color coding

as the wires.

338

All network outlets shall be provided with

labeling and identification. A transparent

window shall protect the labeling tag.

Cable labeling matrix shall be

part of the infrastructure

acceptance test

Patch panels must have 19” equipment

practice dimensions to permit mounting in

standard cabinets, racks or bays

Copper Patch

Panels (RJ45)

Patch Cords

All patch panels must be equipped with a

cable management mechanism that provides

strain relief, earthling and grounding features

The presentation of the Patch Panel must

provide for sliding mechanism for proper

labeling.

In the rack, the Patch Panels shall be

separated by metallic patch-guides that have

a closed front to protect the patch cords. The

height of these guides will be 1U or 2U

depending on the layout of the rack.

The Patch Panel shall provide an automatic

contact with the metal frame of the cabinet in

order to ensure grounding.

To achieve a Class EA Channel

performance all Patch Cords shall be

minimum of Category 7.

Uplinks

All uplinks must be color coded in RED

AND BLUE to differentiate the links to the

core ( backbone)

The uplink connects the core

(backbone in the server

Room) to the Floor

Distribution switches for the

Voice, data video services.

Back

bon

e C

ab

lin

g

All up links shall be with multimodal optical

fiber

The service provider shall provide the choice

between the 2 different types of fibers

described below:

.The Enhanced OM2 or OM3 fibers

providing warranted extended distance for

the transmission of high rate data, voice and

video signals and which shall be available to

avoid limitations due to bottlenecks in the

longest building and campus backbone links.

The choice of fiber will be made according

to the present and future bandwidth needs for

the longest OF backbone links

For interconnecting

buildings, exterior cabling,

single mode fiber should be

used.

The OM3 or OM3 enhanced fibers shall be

used to ensure the transmission of the signal

over 300 (or 450 m) meters at 850nm. Please

refer the table for the fiber below.

This is to allow for distances

between buildings.

Optical fiber Patch Panels shall be mounted

in 19” frames of the cabinets. The patch

panels shall be supplied with adaptors fitted

and equipped with a mechanism that ensures

the retention and support of incoming cables.

339

Direct Termination of the connectors (LC) on

to the fibers as well as splicing of pigtails

(LC) should be possible

Active equipment

& panels

connections

In order to trace patching between the active

equipment ports and the cabling termination

patch panels, the ports of the active

equipment should be properly documented

and labelled. Fixed permanent label are

required

Identification/labeling

scheme should be in line with

TIA-606-A

All equipment room cabinet shall be in 42U

cabinet

For an orderly cord storage and easy to

management of cable installation, the

following accessories may be used:

Closed 1 or 2 HU patch guides between the

patch panels;

Lateral cable rings installed at both sides of

the frames. The patch rings should be easily

removable by rotation and have to be located

on the front rails of the 19” frames in the

cabinets.

The cabinets shall be able to

host all standard types of

active and passive

equipment and provide

facilities for extension to

form a suite of cabinets with

no modification to the

structure.

All equipment room cabinet

shall be 42U

(600x800mm)minimum

340

Cab

inet

an

d R

ack

s in

stall

ati

on

Cabinet

arrangement

sample as shown in

the diagram below.

Please the arrangement of the cabinets

should ensure that:

1. Front rails of cabinets must be recessed

to provide adequate room for patch

cables and Wire management

accessories.

2. Adequate space for cable management

3. Arrange switches and minimize patching

between cabinets & racks

4. Perforated tiles at front cabinets

5. One edge of cabinets placed at edge of

tile

W

irel

ess

Wi-Fi survey to be

undertaken for the

locations. Cabling

should however be

internal as

standard

The Wireless access points should be

installed based on Wi-Fi survey and should

meet 801.1n standard

Sp

ace

im

pact

of

cab

lin

g s

yst

ems

1. Allocate adequate space and careful plan

location of network areas (MDA HDAs,

Entrance Rooms, Telecom

2. Provide adequate space and coordinate

location of cabling pathways.

3. Space in server cabinets for patch panel

and cable management

En

ergy E

ffic

ien

cy –

Path

ways

Overhead cabling

as standard.

Overhead cabling requirement should be

considered in the design of the Ceiling

heights to permit rails.

The overhead cabling will

reduce losses due to airflow

obstruction and turbulence.

For old Data centers where

overhead cabling was not

part the requirement, all

improvement work must

ensure that :

all cabling under floor use

smaller diameter cable

conduits or alternative

network architectures to

reduce cabling volumes

• the cabling network must

avoid blocking airflow

to/from cabinets,

ventilated tiles, A/C, IT, and

telecom equip

En

ergy

Eff

icie

ncy

Tem

per

atu

re

& H

um

idit

y DC Rooms, Equipment Rooms,

– Temperature: 18 – 27 °C (64 – 81 °F)

– Max Relative Humidity: 60%

– Max dew point: 15 °C (59 °F)

– Min dew point: 5.5 °C (42 °F) to control

ESD

341

Ele

ctri

cal

cab

lin

g s

ecuri

ty

The electrical cabling used to power

Network and the telecommunications

infrastructure should comply with industry

best practices. Especially the following

must be observed:

-Electrical cabling will be run separately

from data cabling

-There should be a telecommunication

earthing different from the building general

earthing.

-All the active devices should be connected

to the earthing

-All the telecommunications cabinets,

closets

should be connected to the earthing

-All the telecommunications devices should

be powered though double conversion UPS

system.

There should be lightening arrestor to

Protect the building and surge protection to

Protect the Infrastructure. Especially, there

should be a surge protector on all PSTN

lines.

342

Docu

men

tati

on

The provider

should provide

documentation in

soft and hard copies

The physical installations of network passive

and active devices must have detailed

documentation that include information:

All products used

The entire system as implemented and

based on the validated initial design

A diagram of each type of distribution

points relative to MDA

A comprehensive overview of the

installation.

A ground plane locating each sub-system

installation.

The plans of the different levels of the

building with the location and

designation endpoint relative to HDA

The installation shall be subjected to test on

completion:

The set of tests that may be conducted may

include:

The connectivity test of the copper

The test made fiber ( end-to-end)

The type and serial number of the testing

devices used must be specified.

The name of the operators ( Service provider

Engineers and approving officer)

Cabling should be certified against category

6A or 7 specifications and full tests This

certification will provide the length of each

cable, the rate of packet loss, the resistance,

impedance result made available in

electronic format

343

5) IT CABLING - REQUIREMENTS

A. Cabling base principles:

1. The trucking shall be made of 3 compartments inside.

2. Each network position workstation has one cable that extends to the equipment room. This

cable, known as the cables UTP category 7 will be used for horizontal cabling requirements.

3. Each uplink will operate at 1000 Mbps. The Uplinks will connect the different switches from

the floors to the servers Rooms. The uplink is multimodal optical fiber.

4. All the network points and cables from each floor will be connected to the patch panel located

in a VDI room at the same floor. The DVI room will be connected by fiber to the server room

located at the ground floor.

5. Total Positions shall be based on the design (site drawing) and number of staff regarding offices

allocation.

I. IT NETWORK CABLING

Required functions

Minimal

technical

compliance

Quantity Unit

Price

Total

price

Country

of origin

Identification

Supply, installation and

commissioning of all the cabling,

trucking and outlets for a

1000Base T network.

UTP Cat 7

A - Each Office will be equipped with positions configured as follows

PS PSLT LT

Each Network position is composed

of:

2 RJ-45 Outlets (LAN and Phone)

2 Regulated Power Supply(UPS)

outlets

01 normal power outlet ( not on

UPS )

Number of Network positions per office according to Staff allocation

Office for 1 person 2

Office for 2 persons 3

Office for 3 persons 4

Videoconference / Meeting Room

according to the number of sets. 8- 10

344

i. List of the equipment for the ground Floor

Designation Unit Quantity Unit

Price

Total

Price

Country

Origin

Supply and installation of a 19-inch rack 42U,

800 x 800 with integrated 4 PDU of 6 power

Socket for each PDU.

Unit 1

Supply and installation of Cat 7 UTP Cable for

cabling

ML

Supply and installation of RJ45 data port Cat 7

UTP for each position

Unit

Supply and installation of Regulated Power

and normal power cable and outlets for each

position

Unit

Supply and installation of trucking 180x50

with 3 compartments

ML

Supply and installation of connection cable for

workstations 3m UTP RJ45 Cat 7

Unit

Supply and installation of patch cord 1m UTP

RJ45 Cat 7

Unit

Supply and installation of RJ45 and ripple

curent support

Unit

Supply and installation of patch panel 24 port

RJ45 UTP Cat 7

Unit

Supply and installation of ferrules, elbows, tea Ens 1

Provision of labeling, certification and wiring

diagrams

Ens 1

Grounding of all equipment and connect all

ground together to main grounding.

Ens 1

Network point for Wireless Access points. will

be fixed at the walk or under the ceiling for

the ground Floor

Unit 2

Server Room cabling Ens

Supply and installation of optical fiber patch

panel LC/LC with integrated connector 24

ports

Supply and installation of optical fiber patch

cable LC/LC connector 05 m

Unit 12

IP TV (walk mounted) Network position at the

ground floor for information display

Unit 02

Total for all Items i

NB: refer to the design (plan & drawing) and site visit to confirm the required quantities.

345

ii. Dedicated UPS for IT equipment

Basic Features

Quantity

Unit

Price Total price

Country

Origin

Identification

10 kVA UPS, furniture, installation, and maintenance.

UPS will be switched to the regulated power coming from

the main Regulated Power Supply equipment. Online

Technology double convection; should be racked in the

Server room (Ground Floor). Input/output 3 phase/3

phase; 380 volt. Management RJ45 port with SNMP

capability

1

Services

Installation Lumpsum

Warranty period 2 years

Maintenance cost per year after Warranty Lumpsum

Sub-total ii

iii. List of the equipment for First Floor

Designation Unit Quantity Unit

Price

Total

Price

Country

Origin

Supply and installation of a 19-inch rack 12U, 600 x

600 with integrated 2 PDU of 6 power Socket for each

PDU.

Unit 1

Supply and installation of Cat 7 UTP Cable for cabling ML

Supply and installation of RJ45 data port Cat 7 UTP

for each position

Unit

Supply and installation of Regulated Power and

normal power cable and outlets for each position

Unit

Supply and installation of trucking 180x50 with 3

compartments and accessories

ML

Supply and installation of connection cable for

workstations 3m UTP RJ45 Cat 7

Unit

Supply and installation of patch cord 1m UTP RJ45

Cat 7

Unit

Supply and installation of RJ45 and ripple current

support

Unit

Supply and installation of patch panel 48 port RJ45

UTP Cat 7

Unit 02

Provision of labeling, certification and wiring

diagrams

Ens

Grounding of all equipment at First Floor and connect

to the main grounding.

Ens

Network point for Wireless Access points. will be

fixed at the walk or under the ceiling for the Ground

Floor

Unit 3

Supply and installation of optical fiber patch panel

LC/LC with integrated 12connectors

Unit 01

Supply and installation of multimodal optical fiber

patch cable LC/LC connector 05 m

Unit 3

Supply and installation of multimodal optical fiber

Cable with 06 optical fiber strands connecting First

Floor to Server room at Ground floor

ML

346

IP TV (walk mounted) Network position at the First

floor for information display

Unit 02

Total for all Items iii

NB: refer to the design (plan & drawing) and site visit to confirm the required quantities.

iv. List of the equipment for Second Floor

Designation Unit Quantity Unit

Price

Total

Price

Country

Origin

Supply and installation of a 19-inch rack 12U,

600 x 600 with integrated 2 PDU of 6 power

Socket for each PDU.

Unit 1

Supply and installation of Cat 7 UTP Cable for

cabling

ML

Supply and installation of RJ45 data port Cat 7

UTP for each position

Unit

Supply and installation of Regulated Power

and normal power cable and outlets for each

position

Unit

Supply and installation of trucking 180x50

with 3 compartments and accessories

ML

Supply and installation of connection cable for

workstations 3m UTP RJ45 Cat 7

Unit

Supply and installation of patch cord 1m UTP

RJ45 Cat 7

Unit

Supply and installation of RJ45 and ripple

current support

Unit

Supply and installation of patch panel 48 port

RJ45 UTP Cat 7

Unit 02

Provision of labeling, certification and wiring

diagrams

Ens

Grounding of all equipment at First Floor and

connect to the main grounding.

Ens

Network point for Wireless Access points. will

be fixed at the walk or under the ceiling for

the Ground floor

Unit 3

Supply and installation of optical fiber patch

panel LC/LC with integrated 12 connectors

Unit 1

Supply and installation of multimodal optical

fiber patch cable LC/LC connector 05 m

Unit 3

Supply and installation of multimodal optical

fiber Cable with 06 optical fiber strands

connecting second floor to Server room at

Ground floor

ML

IP TV (walk mounted) Network position at the

Second floor for information display

Unit 02

Total for all Items iv

NB: refer to the design (plan & drawing) and site visit to confirm the required quantities.

347

TECHNICAL SPECIFICATIONS:

Raised Server Room Floor:

A raised floor is provided for in the equipment room. Raised floors in equipment rooms usually serve

the following purposes:

A distribution system for conditioned cold air

Tracks, conduits, and/or supports for data cabling

Conduits for power cabling

A copper ground grid for grounding of equipment

For this option to be warranted, an equipment room at least four times the size of the current extended

space combined with space utilization at least ten times the present level will be required. Even if an

equipment room of the present size reached its equipment saturation point, the number of racks in a

row will be limited by the maximum width of the room to no more than three deep. At that depth cold

air blowing across the room will still be adequate for cooling. Only racks in the middle of the room will

benefit from under floor cabling, which can be achieved as easily from overhead, through the ceiling

and via overhead trays.

The proposed optional raised floor will consist of:

600 sq. mm modules constructed with a high density

particle board core enclosed by four pieces of PVC

strips and galvanized steel sheets on top and bottom

Top finish in anti-static HPL, fire retardant material

Pedestal mount with locator pad and stringer with

fasteners

Designed to provide electrical continuity, excellent rigidity, durability, and acoustic

performances