![Page 1: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/1.jpg)
MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, ODOT DIRECTOR |BOB WEAVER, DISTRICT DEPUTY DIRECTOR
SERVING ASHLAND, CRAWFORD, ERIE, HURON, LORAIN, MEDINA, RICHLAND AND WAYNE COUNTIES
Erie
Huron
Lorain
Medina
WayneRichland
AshlandCrawford
ODOT DISTRICT 3 2020 CONSTRUCTION PROGRAM
![Page 2: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/2.jpg)
CONSTRUCTION PROGRAM 2020
Ashland County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
90912 ASD US 224
11.12 Culvert
Rehabilitation US 224, just east of SR 58 09/26/19
11/18/19 10/31/20
$164,140.00 Marra
Services Inc
Traffic maintained at all times
108920 ASD SR 3 06.81
Smooth Seal
SR 3, from the Village of
Loudonville, in Ashland County, to the City of Wooster, in Wayne
County
09/26/19 04/01/20 09/30/20
$3,585,610.00
Kokosing
Traffic maintained by flaggers
102960 ASD SMOOTH
FY 2020 Smooth
Seal
US 250, from the City of Ashland
Corp. limit to Bailey Lakes/ US 60, from Village of Hayesville to US
30/ SR 179, from the Holmes County line to SR 60
12/12/19 04/01/20 10/15/20
$2,591,520.00 Shelly & Sands
Traffic maintained by flaggers
94431 ASD US 42
09.43 Bridge
Replacement US 42, between Cleveland Ave.
and Twp Rd 793 02/27/20
05/01/20 10/31/20
$848,453.00 Unknown
One lane of traffic maintained at all times
97045 ASD SR 3/SR 60
00.00/00.67 Minor
Rehabilitation
SR 3, from Knox County line to SR 39/ SR 60, from SR 3 to the
northern Corp. limits of the Village of Loudonville
04/09/20 05/20/20 08/20/20
$1,700,000.00 Unknown
Traffic maintained at all times
103016 ASD US 250/SR
58 12.22/00.00
Minor Rehabilitation
US 250, from US 42 to the northern Ashland Corp. limits/ SR 58 from US 250 Connector Rd to northern
Corp. limits
05/07/20 07/01/20 11/01/20
$1,030,457.00 Unknown
Traffic maintained at all times
106356 ASD SR 179
04.91 Culvert
Replacement SR 179, between Lake Twp Rd. 257
and Lake Twp Rd. 2300 05/21/20
07/01/20 09/01/20
$200,000.00 Unknown
30 day closure
![Page 3: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/3.jpg)
CONSTRUCTION PROGRAM 2020
110311 ASD US 250
00.00 Minor
Rehabilitation
US 250 from the Huron County line to Bailey Lakes southern Corp
limits 05/21/20
07/01/20 10/31/20
$2,347,750.00 Unknown
Traffic maintained at all times
103925 ASD SR 60
09.95 Culvert
Replacement SR 60, between Ashland Co Rd 775
and Vermin Twp Rd 2104 06/04/20
08/01/20 10/01/20
$150,000.00 Unknown
30 day closure
87729 ASD US 30
00.16 Minor
Rehabilitation US 30, from just east of SR 603 to
just past SR 511 11/19/20
01/01/21 12/31/21
$4,710,207.00 Unknown
Traffic maintained at all times
![Page 4: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/4.jpg)
CONSTRUCTION PROGRAM 2020
![Page 5: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/5.jpg)
CONSTRUCTION PROGRAM 2020
Crawford County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
104117 CRA SR 4
09.31 Resurfacing SR 4, from Perry St. to SR 19 05/16/19
07/15/19 05/29/20
$1,698,000.00 Kokosing
Traffic maintained by flaggers
102970 CRA Smooth
FY 2020 Smooth Seal
SR 19, from Galion West Corp. limit to Bucyrus East Corp. limit/ SR 4, from Bucyrus North Corp. limit to Seneca County line/ SR 97, from
Millsboro Rd. to Morrow County line
06/20/19 08/01/19 07/18/20
$3,093,000.00 Shelly & Sands
Traffic maintained by flaggers
90883 CRA SR 4
19.13 Bridge Repair
SR 4, just north of south intersection of SR4/ SR103, over
Sycamore Creek 08/22/19
05/26/20 08/31/20
$504,420.00 Rietschlin
Construction 60 day detour
101409 CRA SR 19
16.08 Minor
Rehabilitation SR 19, from CR 16 to just north of
CR 27 09/26/19
06/01/20 09/30/20
$1,596,750.00 Kokosing
Traffic maintained at all times
102635 CRA SR 19
26.18 Bridge
Preservation SR 19, between New Washington Rd.
and Feichner St. 04/09/20
05/01/20 11/30/20
$500,000.00 Unknown
45 day closure
107861 CRA US 30
10.92 Slide Repair
Various locations on US 30 eastbound from just east of Bucyrus
to SR 61 07/16/20
07/27/20 11/27/20
$1,905,200.00 Unknown
Traffic maintained at all times
103703 CRA SR 19/SR
97 01.21/00.70
Minor Rehabilitation
SR 19, from the Morrow County line to Evans Ave./ SR 97, from 6th St. to
eastern Corp. limits of Galion 07/02/20
08/01/20 09/30/20
$1,383,166.00 Unknown
Traffic maintained at all times
![Page 6: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/6.jpg)
CONSTRUCTION PROGRAM 2020
![Page 7: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/7.jpg)
CONSTRUCTION PROGRAM 2020
Erie County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
105587 ERI SR 2 14.06
Bridge Repair
The Camp Rd. overpass, between Galloway Rd. and Rye Beach Rd./ the Hahn Rd. overpass, between
SR61 and Frailey Rd./ the Joppa Rd. overpass, between
Frailey Rd. and Barnes Rd.
10/01/19 04/01/20 10/15/20
$545,640.00 BCC Ohio Inc
One lane of traffic in each direction
maintained at all times, with 45 day
detours at Camp, Hahn and Joppa Rds.
92889 ERI US 6/US 250
06.41/00.00 Minor
Rehabilitation
US 6, from Venice Rd to Sandusky eastern Corp. limit/ US 250, from
Cleveland Rd. to Butler St. 04/09/20
06/01/20 08/31/20
$1,955,827.00 Unknown
Traffic maintained by flaggers
111437 ERI SMOOTH
FY 2021 Smooth Seal
SR 13, from US 250 to the Huron Corp limit/ SR 99, the Huron
County line to SR 4 12/17/20
05/01/21 08/01/21
$1,656,085.00 Unknown
Traffic maintained by flaggers
![Page 8: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/8.jpg)
CONSTRUCTION PROGRAM 2020
![Page 9: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/9.jpg)
CONSTRUCTION PROGRAM 2020
Huron County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
90902 HUR SR 162
04.13 Bridge
Replacement SR 162. just west of Miller Rd. 09/26/19
06/08/20 08/21/20
$572,710.00 R&I
Construction 60 day detour
77529 HUR US 20
10.76 Minor
Rehabilitation US 20, from the bridge over SR
61 to the end of the Bypass 02/27/20
05/01/20 11/01/20
$6,292,260.00 Unknown
Traffic maintained at all times. Expect single lane closures on US 20, with some short-term
closures at ramps
100074 HUR SR 601
01.02 Bridge
Replacement SR 601, just south of US 20 01/23/20
08/31/20 11/06/20
$538,176.00 Unknown
60 day detour
102239 HUR SR 601
01.85 Bridge
Replacement SR 601, between US 20 and Gibbs
Rd 05/07/20
07/01/20 09/30/20
$275,000.00 Unknown
30 day detour
106353 HUR SR 60/SR 99
10.78/08.04 Culvert
Replacement SR 60, just south of Auster Rd. SR
99, just south of Dogtown Rd 05/21/20
07/01/20 09/30/20
$375,000.00 Unknown
SR 60: 30 day detour SR 99: 30 day detour
98462 HUR US 250
05.10 Minor
Rehabilitation
US 250, from eastern Corp limit of Norwalk to the Ashland County
line 11/05/20
05/15/21 07/30/21
$4,387,671.00 Unknown
Traffic maintained by flaggers
![Page 10: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/10.jpg)
CONSTRUCTION PROGRAM 2020
![Page 11: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/11.jpg)
CONSTRUCTION PROGRAM 2020
Lorain County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
82632 LOR US 20
22.19 Major
Rehabilitation US 20, from Stoney Ridge Rd to
Lear Nagle Road 11/30/17
04/02/18 11/20/20
$26,874,800.65 Fechko
One lane of traffic maintained in each direction. Various
intersecting side street closures.
92013 LOR US 6
09.67 Bridge Repair
US 6, near the intersection of US 6 and SR 57
01/25/18 04/02/18 08/15/20
$26,332,328.83 The Ruhlin Co.
One lane of traffic maintained in each
direction. Up to three different closures of
US 6, that will be limited to 7 days for operating equipment
installation
102660 LOR US 20
20.47 Bridge
Replacement US 20, over Ridgeway Ditch 04/04/19
06/01/19 05/31/20
$2,061,613.00 Schirmer
Construction
One lane of traffic maintained in each
direction at all times
84829 LOR SR 301
26.67 Major
Rehabilitation SR 301, through the City of
Sheffield Lake 05/02/19
06/15/19 05/29/20
$1,580,814.00 Fechko
Traffic maintained by flaggers
101359 LOR US 20
19.40 Roadway
Improvement US 20, from SR 301 to Case Rd. 05/02/19
07/29/19 04/30/20
$1,627,320.00 Karvo
Traffic maintained at all times, with single
lane closures as needed
![Page 12: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/12.jpg)
CONSTRUCTION PROGRAM 2020
102027 LOR SR 254
02.03 Turn Lane Addition
SR 254, eastbound at the intersection with SR 301
06/06/19 08/05/19 05/29/20
$1,479,930.00 Karvo
Two lanes of traffic in each direction
maintained at all times with single lane
closures as needed
98273 LOR SMOOTH
FY2020 Smooth
Seal Various locations throughout
Lorain County 06/20/19
08/01/19 06/30/20
$3,134,240.00 Karvo
Traffic maintained by flaggers
101387 LOR SR 301
22.33 Resurfacing
SR 301, from SR 254 to Colorado Ave. From Colorado Ave. to
Walker Rd. SR 611, from SR 301 to Miller Rd.
07/25/19 08/01/19 06/15/20
$2,099,420.00 Karvo
Traffic maintained by flaggers
94420 LOR SR 303
11.05 Minor
Rehabilitation SR 303, from Lagrange Corp. limit
to Medina County line. 11/07/19
05/01/20 07/31/20
$2,316,962.00 Kokosing
Traffic maintained by
flaggers
80121 LOR SR 113
07.76 Bridge
Replacement SR 113, just east of SR 58 02/13/20
05/01/20 07/31/20
$291,257.00 Unknown
30 day detour
98526 LOR SIGN FY 2020
Signs Various locations in Lorain County 03/12/20 05/01/20 12/31/20
$539,718.00 Unknown
Traffic maintained at
all times
104186 LOR SR 2
07.49 Slide Repair SR 2, eastbound just east of SR 58 03/12/20
04/01/20 09/01/20
$514,990.00 Unknown
Outside shoulder
closure, two lanes of traffic maintained
110815 LOR FINDLEY STATE PARK
Minor Rehabilitation
Findley State Park Main Rd 03/14/20 04/01/20 06/20/20
$650,669.00 Unknown
Traffic maintained by
flaggers
![Page 13: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/13.jpg)
CONSTRUCTION PROGRAM 2020
98574 LOR SR 83
10.50 Minor
Rehabilitation
SR 83, from just south of Mills Rd. to the southern North Ridgeville
Corp. limits 04/23/20
06/01/20 07/31/20
$1,298,247.00 Unknown
Traffic maintained with flaggers
92881 LOR SR 254
02.83 Minor
Rehabilitation
SR 254, from the western Corp. limits of the City of Avon to just
west of Clifton Way, and from just east of Nagle Rd to the Lorain
County line
05/21/20 07/01/20 10/31/20
$748,335.00 Unknown
Traffic maintained
with flaggers
77537 LOR SR 2
03.86 Minor
Rehabilitation SR 2, from just east of Baumhart
Rd to just east of SR 58 08/27/20
04/15/21 10/31/21
$5,739,014.00 Unknown
Traffic maintained at
all times
79759 LOR IR 480
00.97 Minor
Rehabilitation
IR 480, from the Ohio Turnpike Booth to the CUY County line/ The SR 10 ramp to IR 480 east
10/01/20 01/01/21 12/31/21
$2,368,900.00 Unknown
Traffic maintained at
all times
90942 LOR IR 90
17.85 Bridge
Replacement IR 90, bridge over Norfolk
Southern Railroad 12/03/20
03/01/21 11/30/21
$7,763,140.00 Unknown
Traffic maintained at all times. Nightly lane
closures as needed
![Page 14: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/14.jpg)
CONSTRUCTION PROGRAM 2020
![Page 15: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/15.jpg)
CONSTRUCTION PROGRAM 2020
Medina County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
14821 MED
N. Carpenter Road
Major Reconstruction
SR 303 to Boston Rd. 05/03/18 03/12/18 09/15/20
$11,419,901.00 Shelly & Sands
One-way traffic for 120 days
100928 MED US 224
13.47 Intersection
Improvement US 224 at Westfield Center Rd. 05/23/19
07/15/19 05/31/20
$1,281,200.00 Shelly & Sands
One lane of traffic will be maintained in each direction at all times
106876 MED SMOOTH FY2019 (A)
Smooth Seal
SR 3, from Medina Corp. limit to just north of Fenn Rd. and from just south of Odessa Rd. to the Cuyahoga County line/ SR 252,
from just north of SR 57 to Lorain County line/ SR 57, from SR 18 to
just south of SR 252
06/06/19 08/20/19 06/30/20
$3,175,531.00 Ronyak Paving
Traffic maintained with flaggers
108636 MED IR 76
08.31 Culvert
Rehabilitation I-76 eastbound between SR 57 and
SR 94 10/24/19
11/11/19 06/01/20
$539,930.00 Marra Services
No impact to traffic expected
98928 MED US 224
15.61 Culvert
Rehabilitation US 224, eastbound, just past Lake
Rd. before the I -71 on ramps 11/21/19
05/01/20 08/31/20
$194,460.00 Inland Water
Pollution Single lane closures
94436 MED SR 3
17.05 Bridge Repair SR 3 over Plum Creek TBD TBD
$671,141.00 Lockhart
Concrete Co
No impact to traffic expected
94440 MED SR 303 13.90/14.96
Bridge Replacement
Culvert just west of State Rd./ Bridge just east of State Rd., west
of Summit County line 01/23/20
02/04/20 08/31/20
$1,765,500.00 Unknown
90 day detour
![Page 16: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/16.jpg)
CONSTRUCTION PROGRAM 2020
87716 MED IR 71
06.06 Minor
Rehabilitation
IR 71, from just south of the IR 76 interchange to just north of the
interchange 04/20/20
05/15/21 08/15/21
$3,040,020.00 Unknown
Traffic maintained at all times
103924 MED SR 162
11.70 Culvert
Replacement SR 162, west of US 42 before
Lance Rd. 04/23/20
06/01/20 08/01/20
$165,000.00 Unknown
30 day detour
102738 MED SR 3
12.00 Bridge
Replacement SR 3, just north of Friendship St.
over Broadway Creek 04/23/20
05/05/20 11/30/20
$497,700.00 Unknown
60 day detour
106354 MED SR 3/SR 94
24.34/20.11 Culvert
Replacements SR 3, just north of Mattingly Rd./ SR 94, just south of Mattingly Rd.
06/04/20 07/15/20 11/13/20
$442,000.00 Unknown
SR 3: 30 day closure SR 94: 30 day closure
109232 MED SR 3
15.05 Major
Rehabilitation SR 3, from just north of Fenn Rd.
to just south of Odessa Rd. 07/30/20
05/01/21 06/01/22
$8,009,280.00 Unknown
One-way traffic will be maintained from
Hamilton Rd to Fenn Rd
100063 MED SR 162
25.43 Bridge
Replacement SR 162, between State Rd. and
Burdett Rd. 08/27/20
06/01/21 08/31/21
$1,006,500.00 Unknown
90 day detour
94437 MED US 42
02.47 Bridge
Replacement US 42, just north of Crawford Rd. 11/19/20
04/05/21 08/20/21
$1,177,000.00 Unknown
90 day detour
98395 MED SR 3
03.80 Minor
Rehabilitation SR 3, from just south of the IR 76 ramps to the Medina Corp limits
11/19/20 06/01/21 08/31/21
$2,479,064.00 Unknown
Traffic maintained by flaggers
98570 MED SR 18
00.00 Minor
Rehabilitation SR 18, from the Lorain Countyline
to the Medina Corp limit 12/17/20
05/01/21 10/31/21
$3,461,700.00 Unknown
Traffic maintained by flaggers
![Page 17: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/17.jpg)
CONSTRUCTION PROGRAM 2020
106232 MED SR 57
17.65
Drainage System
Maintenance
SR 57, around all approaches to the SR 57/Spieth Rd. roundabout
12/17/20 06/01/21 11/30/21
$1,669,200.00 Unknown
SR 57/Spieth Rd. (west of roundabout) 60 day
closure/Spieth Rd. (east of roundabout)
eastbound will have a 7 day closure with
westbound traffic maintained
![Page 18: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/18.jpg)
CONSTRUCTION PROGRAM 2020
![Page 19: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/19.jpg)
CONSTRUCTION PROGRAM 2020
Richland County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor
Maintenance of Traffic
87728 RIC US 30
04.07 Minor
Rehabilitation From 4th St. to SR 309 06/20/19
08/01/19 08/28/20
$3,427,940.00 Kokosing
Single lane closures
102058 RIC SR 603
00.05 Slide Repair Just north of SR 95 09/26/19
04/01/20 06/05/20
$395,350.00 Alan Stone Co
Inc 45 day detour
94405 RIC US 42
03.48 Minor
Rehabilitation From just south of Fox Rd., to
the Mansfield Corp. limit 10/10/19
04/06/20 07/31/20
$1,802,390.00 Shelly & Sand
Traffic maintained by flaggers
87722 RIC IR 71
00.00 Minor
Rehabilitation From the Richland County line to
SR 13 11/21/19
05/01/20 10/03/20
$9,410,670.00 Kokosing
Single and two-lane closures
100057 RIC SR 13
05.30 Bridge Repair SR 13, just south of SR 97 02/13/20
04/01/20 08/14/20
$984,331.00 Unknown
One lane traffic maintained with
signals
93455 RIC US 30
09.26 Major
Rehabilitation US 30, from SR 309 to just east
of the 5th Ave ramps 04/02/20
04/15/20 05/26/23
$79,299,900.00 Unknown
Traffic maintained at all times
101442 RIC SR 309
03.91 Minor
Rehabilitation
SR 309, from SR 314 to just east of the SR 430 ramps and SR 430
from SR 309 to the Mansfield Corp. limit
04/09/20 06/01/20 09/30/20
$1,387,171.00 Unknown
Traffic maintained at all times
![Page 20: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/20.jpg)
CONSTRUCTION PROGRAM 2020
101431 RIC SMOOTH
FY 2021 Smooth Seal
SR 61, from just north of Shelby Corp limit to the Plymouth Corp
limit/ SR 96, from the Shelby Corp limit to SR 13
05/18/20 01/01/21 12/31/21
$2,284,921.00 Unknown
Traffic maintained by flaggers
94442 RIC SR 430
03.66 Bridge Repair SR 430, just east of Pinecrest St. 06/04/20
07/01/20 09/15/20
$550,000.00 Unknown
One lane traffic maintained with
signals
87690 RIC SR 13
11.01 Minor
Rehabilitation SR 13, from Hanley Rd to just
south of East Raleigh Ave 10/01/20
01/01/21 12/31/21
$4,123,000.00 Unknown
Traffic maintained by flaggers
![Page 21: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/21.jpg)
CONSTRUCTION PROGRAM 2020
![Page 22: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/22.jpg)
CONSTRUCTION PROGRAM 2020
Wayne County Projects
PID Number
Route & Section
Work Type Location
Sale Date
Est. Start &
Est. End
Est. Cost &
Contactor Maintenance of Traffic
102109 WAY US 30
23.33 Intersection Improvement
US 30, at Wenger Rd., in the Village of Dalton
05/02/19 09/18/19 05/31/20
$644,560.00 Central-Allied
Enterprises
One lane of traffic in each direction will be maintained at all
times
88886 WAY SR 83
00.62/00.74 Bridge
Replacement
Between CR 2 (Harrison Rd.) and CR 289 (Force
Rd.) 12/12/19
05/28/20 08/31/20
$828,250.00 V O Menuez &
Sons Inc 75 day detour
105455 WAY SR 83
16.31 Resurfacing
SR 83, from the Medina County line to the northern
Corp. limits of Wooster 02/27/20
06/01/20 10/31/20
$6,445,652.00 Unknown
84 day closure
102770 WAY US 250
19.26 Bridge
Replacement
US 250, between Villard St. and Apple Ridge Dr. over
Little Apple Creek 03/12/20
06/01/20 10/31/20
$1,177,000.00 Unknown
150 day signalized lane closure
![Page 23: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/23.jpg)
CONSTRUCTION PROGRAM 2020
![Page 24: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/24.jpg)
CONSTRUCTION PROGRAM 2020
District Wide Projects
PID Number
Route & Section
Work Type Location
Sale Date Est. Start
& Est. Ed
Est. Cost &
Contactor Maintenance of Traffic
101833 D03 PM FY2019
Loop Detector Repair
Various locations throughout the District
04/04/19 05/29/19 05/31/21
$213,390.00 Perram Electric
Traffic maintained at all times
98933 D03 PM FY2019
Pavement Marking
Various locations throughout the District
05/02/19 07/01/19 07/31/20
$2,542,640.00 Oglesby
Traffic maintained at all times
104286 D03 PR FY2020
Pruning, Tree/Bush Removal
Various locations throughout the District
07/25/19 10/03/19 09/30/20
$153,110.00 Ecotree Services
Traffic maintained at all times
98275 D03 CRSEAL
FY2020 Crack Seal
Various locations throughout the District
08/22/19 10/08/19 06/30/20
$242,892.00 Bituminous
Pavement Sys Traffic maintained by flaggers
109054 D03 GR
FY2020(A) Guardrail
Maintenance Various locations throughout
the District 10/10/19
03/16/20 01/31/21
$536,270.00 Lake Erie
Construction Traffic maintained at all times
103475 D03 PR
FY2020 (B)
Pruning, Tree/Bush Removal
Various locations throughout the District
10/24/19 12/04/19 03/31/21
$240,500.00 Van Curen
Services Inc Traffic maintained at all times
105359 D03 TSG FY2020
Signals Various locations throughout
the District 11/21/19
02/01/20 08/31/20
$205,950.00 Perram Electric
Traffic maintained at all times
104148 D03 GR FY2020
Guardrail Maintenance
Various locations throughout the District
11/21/19 02/01/20 01/31/21
$739,150.00 Lake Erie
Construction Traffic maintained at all times
![Page 25: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/25.jpg)
CONSTRUCTION PROGRAM 2020
95585 D03 BH
FY2020 (A) Bridge Repair
Various locations on I-71 in Ashland and Richland Counties,
and US 30 in Ashland County 12/12/19
01/01/20 10/31/20
$386,650.00 Ohio Concrete
Paving LLC Traffic maintained at all times
105357 D03 LG FY 2020
Lighting Various locations throughout
the District 11/21/19
04/01/20 09/30/20
$105,990.00 Perram Electric
Traffic maintained at all times
95586 D03 BH FY 2020
Bridge Repair Various locations in Crawford, Huron, and Richland Counties
02/13/20 04/01/20 02/01/21
$807,460.00
Unknown
Traffic maintained at all times with one 14 day closure on HUR SR 99
101467 D03 RPM FY 2020
Raised Pavement Markings
Various locations throughout the District
03/26/20 05/01/20 12/31/20
$213,200.00 Unknown
Traffic maintained at all times
110809 D03 GR FY 2020
Guardrail Replacement
Various locations throughout the District
04/01/20 07/01/20 07/01/21
$200,000.00 Unknown
Traffic maintained at all times
101466 D03 PM FY 2020
Pavement Marking
Various locations throughout the District
04/09/20 05/01/20 12/31/20
$2,060,000.00 Unknown
Traffic maintained by flaggers
104158 D03 LG FY 2020
Highway Lighting
Various interchanges along US 20 in Lorain County
05/21/20 06/02/20 12/30/20
$1,535,000.00 Unknown
Traffic maintained at all times
98276 D03 RM FY 2020
Mill and Fill
ASD US 30, just east of SR 60 eastbound and WAY US 30, just
west of the E Lincoln Way overpass
06/04/20 08/01/20 10/31/20
$363,000.00 Unknown
Traffic maintained at all times
104288 D03 PR FY 2020
Pruning, Tree/Brush
Removal
Various locations throughout the District
07/16/20 10/03/20 09/30/21
$215,000.00 Unknown
Traffic maintained by flaggers
![Page 26: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/26.jpg)
CONSTRUCTION PROGRAM 2020
101438 D03 MICRO
FY2021 Micro
Surfacing
ASD SR 39, from the Richland County line to the Loudonville Corp. limit/ ASD SR 60, from the Loudonville Corp. limit to
SR 95/ ASD SR 89, from the Polk Corp. limit to SR 58
06/18/20 08/01/20 09/30/21
$1,989,907.00 Unknown
Traffic maintained by flaggers
101465 D03 CRSEAL
FY 2021 Crack Seal
Various locations throughout the District
06/18/20 09/01/20 10/31/20
$416,000.00 Unknown
Traffic maintained by flaggers
101429 D03 CHIP FY 2021
Preventative Maintenance
HUR SR 60, from SR 18 to the Wakeman Corp. limit and LOR SR 303, from the Huron County
line to Rowell Rd.
06/18/20 08/01/20 09/15/20
$457,343.00 Unknown
Traffic maintained by flaggers
110796 D03 TSG FY 2021
Signals Various locations throughout
the District 10/15/20
07/01/21 09/02/22
$177,620.00 Unknown
Traffic maintained at all times
101469 D03 RPM FY 2021
Raised Pavement Markings
Various locations throughout the District
11/05/20 05/01/21 11/01/21
$242,000.00 Unknown
Traffic maintained at all times
104149 D03 GR FY 2021
Guardrail Various locations throughout
the District 12/03/20
02/01/21 01/31/22
$770,000.00 Unknown
Traffic maintained at all times
101449 D03 Culvert Culvert
ERI US 250, just south of E Mason Rd/ RIC IR 71, just north of the SR 546 overpass/ WAY SR 95, between Springville Rd. and
S Jefferson Rd.
12/03/20 12/14/20 04/01/21
$137,500.00 Unknown
Traffic maintained at all times
*Highlighted projects are carry over projects from 2019.
![Page 27: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/27.jpg)
CONSTRUCTION PROGRAM 2020
![Page 28: ODOT DISTRICT 3 · 30/ SR 179, from the Holmes County line to SR 60 12/12/19 04/01/20 10/15/20 $2,591,520.00 Shelly & Sands Traffic maintained by flaggers 94431 ASD US 42 09.43 Bridge](https://reader033.vdocuments.us/reader033/viewer/2022050401/5f7ed1ddf54a1b31a8645daa/html5/thumbnails/28.jpg)
CONSTRUCTION PROGRAM 2020
We will serve, innovate, and communicate with purpose. ..
We will be productive, lean, efficient and effective. ..
We will utilize the public resources entrusted to us by..
satisfying the State's transportation needs. ..
We will be the standard of excellence for winter maintenance. ..
We will create a working environment based on trust and mutual respect. ..
We will value the diversity of all ODOT people. ..
We will work together — one team: ..
the Ohio Department of Transportation. ..
For more information, please contact the Public Information Office at (419) 207-7181.
Like us on Facebook: www.facebook.com/OhioDepartmentofTransportationDistrict3
Follow us on Twitter: www.twitter.com/ODOT_NorthCenOH
Statewide Traffic Information: www.Ohgo.com
For general information, call (800) 276-4188 or visit District 3’s Web site at: www.transportation.ohio.gov/dist3
O U R M I S S I O N
To provide safe and easy movement of people and goods from..
place to place, we will:..
• Improve safety; ..
• Take care of what we have; ..
• Make our system better; ..
• Enhance capacity. .. O U R V I S I O N