1 Odoo Experience 2015 Project Management with the lights on: Earned Value Management using Odoo Jordi Ballester Alomar (Eficent)

Upload: eficent

Post on 28-Jul-2015

275 views

Category:

Business


1 download

TRANSCRIPT

1

Odoo Experience 2015

Project Management with the lights on: Earned Value Management using Odoo

Jordi Ballester Alomar (Eficent)

Project management about Deming’s Cycle

Earned Value Management

2

Identifying patterns and trends…

….is something humans are quite good at.

And patterns and trends in the past can be good predictors of the future.

Earned Value Management

3

Earned Value Management (EVM) attempts to answer to the following questions:

...are we ahead or behind schedule?

...how efficiently are we using our time?

...when is the project likely to be completed?

...are we currently over or under our budget?

...how efficiently are we using our resources?

...what is the remaining work likely to cost?

...what is the entire project likely to cost?

...how much will we be under or over budget at the end?

Earned Value Management

4

Patterns and trends will help to identify:● Where problems are occurring● Whether problems are critical or not● What will it take to get the project back on track

Earned Value Management

5

… or go back to the usual divination techniques.

6

Work Plan

Earned Value Management

7

8

Basic Elements

9

Planned Value1

Planned Value describes how far along project work is supposed to be at any given point in the project schedule.

Constitutes the Performance Measurement Baseline

Earned Value Management

10

Budget at Completion

Planned Value

11

Earned Value2

Earned Value is a snapshot of the work progress at a given point of time. Reflects the amount of work that has actually been accomplished to date, expressed as the planned value for that work.

Earned Value Management

12

Planned Value

Earned Value

13

Actual Cost3

Actual Cost is an indication of the level of resources that have been expended to achieve the actual work performed to date.

Earned Value Management

14

Planned Value

Earned Value

Actual Cost

15

Performance Measurement

Work performance is measured periodically, such as weekly or monthly.

Discrete efforts that span one to two periods are often measured with fixed formula techniques (0-100, 50-50,..)

Discrete efforts of longer duration (greater than two periods) are measured with other techniques, including those known as weighted milestone and percent complete.

Earned Value Management

16

Mapping the % complete to project stages allows to implement fixed formula or percent complete.

Earned Value Management

17

18

Performance Analysis and Forecasting

Earned Value Management

19

20

Schedule1

Schedule Variance determines whether the Project is ahead or behind schedule.

Earned Value Management

21

Schedule Variance

Time now

Time behind

SV = EV - PV

Earned Value Management

22

Schedule Variance (Are we ahead or behind schedule?)

SV = EV - PV

Schedule Performance Index (How efficiently are we using time?)

Earned Value Management

23

SPI = EV / PV

24

Cost2

Cost Variance (Are we under or over our budget?)

Earned Value Management

25

Time now

CostVariance

CV = EV - AC

Cost Variance (CV)

Earned Value Management

26

CV = EV - AC

Cost Performance Index (How efficiently are we using our resources?)

Earned Value Management

27

CPI = EV / AC

To-Complete Performance Index (How efficiently must we use our remaining resources?)

Earned Value Management

28

TCPI = (BAC - EV) / (BAC - AC)

Estimate at Completion (What is the project likely to cost?)

Earned Value Management

29

EAC = BAC / CPI

Variance at Completion (Will we be under or over budget?)

Earned Value Management

30

VAC = BAC - EAC

Estimate to Complete (What will the remaining work cost?)

Earned Value Management

31

ETC = (BAC - EV) / CPI

32

Guidance for use of key EVM Practices

33

Establish a Performance Measurement

Baseline1

● Decompose the work to a manageable level

● Assign unambiguous management responsibility

● Develop time-phased budget for each work task

● Select the appropriate Earned Value Measurement Technique

● Maintain Integrity of Performance Measurement Baseline

Earned Value Management

34

35

Measure and analyze

performance against the

Baseline2

● Record resource usage during project execution

● Objectively Measure the Physical Work Progress

● Credit Earned Value according to Earned Value Techniques

● Analyze and Forecast cost/schedule performance

● Report performance problems and/or take action

Earned Value Management

36

Find the module: project_earned_value_task in: https://github.com/Eficent/project-earned-value