OccupationWorks GuideCamberwell - Box HillAPLT Friday 21st Continuous
to 04:00 Monday 24th June 2013
Occupation Works Guide
2
3
ContentsAbsolute Occupation Management 4
Site Management & Track Protection Roster 5
O Circular(s) 6
SW Circular(s) 7
S Circular(s) 8
Protection Diagram 12
Signal Diagrams 13
Permit to Foul Particulars 15
Permit to Foul Summary Register 26
Intergrated Works Program 27
Track Machine Movements 31
Level Crossing Disarrangement 32
Overhead Diagram 33
Bus Route Diagram 34
Permit to Work Summary 36
Environmental Sites 37
Occupation Works Guide
4
Absolute Occupation ManagementAbsolute Occupation Location & Duration
Camberwell - Box Hill, Up, Down & Centre Lines After the Passage of TD 3588 (01:35 Hours) Saturday 22nd to 04:00 Monday 24th June 2013.
O Circular IDO.966/13
SW Circular IDAccess Procedure - N/ASidings - N/A
S Circular IDService Alteration - S.2770/13 & S.2771/13
Site OfficeCommand Centre located at Up Track side Surrey Hills Station
Works Progress ReportingProgress reporting will occur at 6 hourly intervals. The Occupation Coordinator will contact each Work Group Supervisor at approx 6 hourly intervals.
Occupation Works Guide
5
Site Management & Track Protection Roster
TRACk FORCe PROTeCTION COORDINATOR ROSTeR
Friday 21st June Night Shift
Saturday 22nd June Day Shift
Saturday 22nd June Night Shift
Sunday 23nd June Day Shift
Sunday 23rd June Night Shift
Name Andrew Wahl Darren Jones Andrew Wahl Darren Jones Andrew Wahl
Mobile Number 0439 512 031 0417 416 542 0439 512 031 0417 416 542 0439 512 031
Date 21/06/13 22/06/13 22/06/13 23/06/13 23/06/13
Shift Duration 23:00 - 07:00 06:30 - 18:30 18:00 - 06:00 05:30 - 17:30 17:00 - 04:00
OCCUPATION MANAGeMeNT ROSTeR
Friday 21st June Night Shift
Saturday 22nd June Day Shift
Saturday 22nd June Night Shift
Sunday 23nd June Day Shift
Sunday 23rd June Night Shift
Name Sean Squire Dave Bates Ian Cranston Dave Bates Ian Cranston
Mobile Number 0419 202 121 0408 121 627 0410 413 656 0408 121 627 0410 413 656
Date 21/06/13 22/06/13 22/06/13 23/06/13 23/06/13
Shift Duration 23:00 - 08:00 08:00 - 20:00 20:00 - 08:00 08:00 - 20:00 20:00 - 04:00
Occupation Works Guide
6
O Circular(s)
OPeRATIONAL RAIL SAFeTY O.966/2013 O.966/2012
Page 1 of 1
DISTRIBUTION Room 301 Flinders Street, Metrol. Phone 57410. Camberwell & Box Hill 19th June 2013.
Absolute Occupation Notice
The Absolute Occupation must be issued in accordance with the instructions contained in Section 15 of the 1994 Book of Rules.
The Signallers and Train Controller must confer and agree that the section of line for which the Absolute Occupation is required is clear, and the last train has cleared the section.
The Signallers must not grant the Absolute Occupation until the necessary Blocking Facilities have been applied and the permission of the Train Controller has been obtained.
SECTION/LOCATION/ PURPOSE
CAMBERWELL – BOX HILL STATION LIMITS UP, DOWN & CENTRE LINES 22KV renewal and Signal works.
DAY, DATE AND TIME REQUIRED
FRIDAY 21/06/2013 From after passage last train continuous until 04:00 hours MONDAY 24/06/2013.
AREA OF ABSOLUTE OCCUPATION/ ISSUING SIGNALLER
the Down Line between Signal Posts CAM311 and BOX304, the Centre Line between Signal Posts CAM321 and BOX314, issued by the Signaller Camberwell the Down Line between Signal Posts BOX304 and BOX308, the Centre Line between Signal Posts BOX314 and BOX315, the Up Line between Signal Posts BOX303 and CAM335, issued by the Signaller Box Hill
SPECIAL NOTE
1. A baulk will be placed on the Up line at a point clear on the Up side of points 201D to protect Overhead isolation of Up line.
2. Signal BOX301 will be inhibited to prevent a train being signalled towards Signal BOX303.
In conjunction with the Absolute Occupation the points listed below must be secured by locking devices, The Track Force Protection Co-ordinator is responsible for ensuring the points are secured when the Absolute Occupation is granted. The Signaller must apply a Blocking Facility to the affected points. When the Absolute Occupation is to be cancelled, the Track Force Protection Co-ordinator must remove the locking devices. The Signaller must remove the Blocking Facility and test the points when the Absolute Occupation is returned.
POINTS SECURED DURING ABSOLUTE OCCUPATION
NA.
STAFFING REQUIREMENTS
A Signaller must be on duty at Camberwell & Box Hill during the period of the Absolute Occupation
Wayne Walsh, Head of Operational Rail Safety, Per:-
REQUISITION JOB ID OH-13-079 ZP008530
Occupation Works Guide
7
SW Circular(s)
N/A
8
S Circular(s)
L:\Timetables\Circulars\Circulars 2013\S Circulars\Occupation\BLY CHL Group\S13-2770 CAM-BOX (Sat 22-06-13).doc Page 1 of 26
S.2770/13 S.2770/13
Job Reference: OC 13-034 Network PlanningOccupation Requisition: OH -13-0079 Level 2, 595 Collins StreetSpecial trains unit kilometres: Melbourne, victoriaBuild up unit kilometres: -7981.74 km 14617 AshCost Centre: Metro Infrastructure Tuesday, 11 June 2013extended build up in operation: No
ABSOLUTE OCCUPATION BETWEEN CAMBERWELL AND BOX HILLSATURDAY 22ND JUNe 2013
Purpose of occupation: Renewal of 22k equipment
In connection with the above occupation, commencing with APLT Friday and until BPFT Monday, Between CAMBERWELL and BOX HILL, the alterations herein will apply tonormal services on the date shown above.
Down JourneysCommencing with the first train and until the last train inclusive, all down Lilydale and Belgrave trains will operate as per W.T.T. to Camberwell, and then
continue to Alamein as the shuttle service, operating as per W.T.T. to Alamein unless stated otherwise.
A rail replacement bus service connecting with train arrivals will convey passengers from Camberwell to Box Hill with two running pattern Stopping all stations to Boxhill express to Boxhill
Trains will operate as per W.T.T. times from Box Hill to Lilydale/Belgrave, with a new TD Number.Altered and additional trains as per schedule pages will convey passengers from Ringwood to Lilydale/Belgrave.Altered arrangements will increase journey time by up to 32 minutes.
Up JourneysCommencing with the first train and until the last train inclusive, all up Lilydale and Belgrave trains will operate as per W.T.T. to Box Hill with altered TD numbers,terminate, and form down trains.A rail replacement bus service connecting with train arrivals will convey passengers from Box Hill to Camberwell with two running pattern.
Stopping all stations to Camberwell express to Camberwell
9
S.2770/13 S.2770/13
L:\Timetables\Circulars\Circulars 2013\S Circulars\Occupation\BLY CHL Group\S13-2770 CAM-BOX (Sat 22-06-13).doc Page 2 of 26
Up Alamein shuttle trains will operate as per (or in some cases, 1” later than) W.T.T. to Camberwell and then continue through to Flinders Street as the upLilydale/Belgrave service operating as per W.T.T. to Flinders Street unless stated otherwise.Commencing from 10 30 am until 19 25 pm every alternate up service will originate at CAM Plat 02. See schedule pages for more details.Altered arrangements will increase journey time by up to 32 minutes.
Passenger NotificationOfficers in Charge are to ensure that altered train arrangements are posted a minimum of eight (8) days in advance of the date mentioned, so that the travelling public aregiven prior notice of these changes to the service. Station Supervisors are to ensure these instructions are enacted, and that all staff are familiar with the altered travelarrangements and potentially longer duration of passenger journeys. Officers in Charge at Camberwell & Box Hill,and then at late night Camberwell & Ringwood are toensure that connections are maintained between trains and the buses providing the substitute services.
Altered and additional trainsThe following trains are CANCELLED:
00 35 Up RWD (No 3562) empty
01 51 up BeG-UFG (No 3136) empty
The following additional empty trains will operate as follows:
04 25 down RWD-BeG (No 7271) formed by 04 18 arrival BeG (No 7270), RWD plat 01 depart at 04 25, FTG arr 04 34*, UFG 04 37*, UPW 04 40*, TCM 04 41*, BeG Plat02, arr 04 44 and forms 04 51 up BeG-BOX (No 3600).
04 39 down BOX-LIL (No 7221) formed by 04 34 arrival LIL (No 7220), BOX plat 03 depart at 04 39, BBN 04 42*, MCH 04 46*, RWD 04 50*, MLk arr 04 59, depart 05 02, LILarr Plat 02 at 05 08 and forms 05 29 up LIL-BOX (No 3802).
04 50 down CAM-RIv (No 2201) formed by ON, 6 cars SDG e, CAM depart 04 50, R, RIv Plat 02 arr 04 53 and forms 04 58 up RIv-CAM (No 2200) additional empty.
04 58 up RIv-CAM (No 2200) formed by 04 53 arrival CAM (No 2201), RIv depart Plat 02 at 04 58, R, CAM arrive Plat 02 at 05 01 and forms 05 12 down CAM-ALM (No2303).
05 04 down BOX-LIL (No 7201) formed by 04 59 arrival LIL (No 3800), BOX plat 03 depart at 05 04, BBN 05 07*, MCH 05 10*, RWD 05 14*, MLk arr 05 22*, LIL arr Plat 01at 05 27 and forms 05 57 up LIL-RWD (No 3302).
05 15 down CAM-RIv (No 2203) formed by ON, 6 cars SDG B, CAM depart 05 15, R, RIv Plat 02 arr 05 18 and forms 05 23 up RIv-CAM (No 2202) additional empty.
05 23 up RIv-CAM (No 2202) formed by 05 18 arrival CAM (No 2203), RIv depart Plat 02 at 05 23, R, CAM arrive Plat 02 at 05 26 and forms 05 32 down CAM-ALM (No2305).
05 38 down BOX-RWD (No 7251) formed by 05 29 arr BeG (No 3600), BOX depart plat 03 at 05 38, BBN 05 41*, RWD arr Plat 02 at 05 48 and forms 05 54 RWD-BeG (No3105).
07 00 up RWD-BOX (No 7250) formed by ON 6 cars, RWD depart at 07 00, BBN 07 07*, BOX arr Plat 03 at 07 11 and forms 07 22 down BOX-BeG (No 3005).
10
S.2770/13 S.2770/13
L:\Timetables\Circulars\Circulars 2013\S Circulars\Occupation\BLY CHL Group\S13-2770 CAM-BOX (Sat 22-06-13).doc Page 9 of 26
Bus InformationSubstitute buses are being provided by U.S.Bus Lines (Monbulk Depot: 9752 1444)
Bus schedules indicated in the schedule pages will show additional time between the second-last and final stations of the section. This time margin isderived by rounding down and transposing intermediate section times to the last leg of the section, to prevent early running at intermediate locations. Busstops are marked with special blue Metro “Train Replacement Bus Stop” flags, (see picture), at the locations below:
Bus Stopping Locations
All additional cost incurred is to be referenced to the cost centre “MTM Infrastructure“ for cost recovery purposes.
Details of all additional staff rostered in connection with this are to be entered in the Customer services/Train services overtime return section on the computer network.
Appropriate Metro Operations Departments are to arrange for the necessary staff to be on duty for the above movements.
All concerned are to note and arrange.
STATION UP STOP DOWN STOP
Camberwell At the Metro designated Bus Stop outside the stationentrance in Cookson Street (South side)
At the Metro designated Bus Stop corner of Holly &Cookson Street (North side)
East Camberwell At the regular Bus Stop in Stanhope Grove (near theroundabout) east side.
At the regular Bus Stop in Stanhope Grove (near theroundabout) West side.
Canterbury At the Metro designated Bus Stop in Canterbury Roadnear the pedestrian crossing (South side)
At the Metro designated Bus Stop in Canterbury Roadnear the pedestrian crossing (North side)
Chatham At the Metro designated Bus Stop corner of RedversStreet & Canterbury Road (South side)
At the Metro designated Bus Stop corner of StanleyTerrace & Canterbury Road (North side)
Surrey Hills At the regular Bus Stop opposite the station in WindsorCrescent (South side)
At the regular Bus Stop outside the station car park inWindsor Crescent (North side)
Mont Albert At the regular Bus Stop in Mont Albert Road (Southside) At the regular Bus Stop in Mont Albert Road (North side)
Box Hill (Terminating) At the Metro designated Bus stop on Maroondah Hwy . At the Metro designated Bus stop on Maroondah Hwy.
11
L:\Timetables\Circulars\Circulars 2013\S Circulars\Occupation\BLY CHL Group\S13-2771 CAM-BOX (Sun 23-06-13).doc Page 1 of 31
S.2771/13 S.2771/13
Job Reference: OC 13-034 Network PlanningOccupation Requisition:OH 13-0079 Level 2, 595 Collins StreetSpecial trains unit kilometres: -404.52 Melbourne, victoriaBuild up unit kilometres: km 544.18 14618 NikhilCost Centre: Metro Infrastructure Tuesday, 11 June 2013extended build up in operation:
ABSOLUTE OCCUPATION BETWEEN CAMBERWELL AND BOXHILLSUNDAY 23RD JUNE 2013
Purpose of occupation: Renewal Of 22 KV equipment
In connection with the above occupation, commencing with APLT Friday night and until BPFT Monday Morning,Between Camberwell and BOX HILL, the alterations herein will apply to normal services on the date shown above.
Down JourneysCommencing with the first train and until the last train inclusive, all down Lilydale and Belgrave trains will operateas per W.T.T. to Camberwell, and then continue to Alamein as the shuttle service, operating as per W.T.T. toAlamein.
A rail replacement bus service connecting with train arrivals will convey passengers from Camberwell to Box Hillwith two running pattern
Stopping all stations to Boxhill express to Boxhill
Trains will operate as per W.T.T. times from Box Hill to Lilydale and Belgrave, with a new TD Number.
Altered arrangements will increase journey time by up to 32 minutes.
Up JourneysCommencing with the first train and until the last train inclusive, all up Lilydale and Belgrave trains will operate asper W.T.T. to Box Hill, terminate, and form down trains. A rail replacement bus service connecting with trainarrivals will convey passengers from Box Hill to Camberwell with Two running pattern.
Stopping all stations to Camberwell express to Camberwell
Up Alamein shuttle trains will operate as per (or in some cases, 1” later than) W.T.T. to Camberwell and thencontinue through to Flinders Street as the up Lilydale/Belgrave service operating as per W.T.T. to FlindersStreet.Commencing from 10 30 am until 19 25 pm every alternate up service will originate at CAM Plat 02. Seeschedule pages for more details.
Altered arrangements will increase journey time by up to 32 minutes.
Passenger Notification
Officers in Charge are to ensure that altered train arrangements are posted a minimum of eight (8) days in advance ofthe date mentioned, so that the travelling public are given prior notice of these changes to the service. StationSupervisors are to ensure these instructions are enacted, and that all staff is familiar with the altered travelarrangements and potentially longer duration of passenger journeys. Officers in Charge at Camberwell & Box Hill,are to ensure that connections are maintained between trains and the buses providing the substitute services.
Altered and additional trainsThe following trains are CANCELLED:
07 31 Down UFG – BeG (No 3137) empty is cancelled.
19 42 Down UFG (No 3005) empty is cancelled.
12
Protection Diagram
12 13
Signal Diagrams
14
1514
Permit to Foul ParticularsWORk GROUP 1: OveR HeAD 22kv (JOHN HOLLANDS)
Work Group Limits: Structutre H399+61 to H472+45 Down Track (Up end Chatham to Box Hill)
Scope of Works: 22kv Rehabilitation WorksSaturday: 02:00 - 15:00 Between Str:426 -440+80 Down Line (Mont Albert Station to Creswick Lane Bridge)Saturday: 15:00 - 23:00 Between Str:399 - 411+11 Down Line (Up end Union Road to Signal L415)Saturday 23:00 - 07:00 Sunday Between Str 368 - 380+30 Down Line (Sig 367 to Robinson Road Bridge)Sunday: 07:00 - 01:30 Monday Between Str 440 - 472+45 Down Line (Signal L441 to Box Hill Station)
Site Access: Union Road PCR & Mont Albert Road PCR
Hi-Rail vehicles: 2 X Hi-Rail eWP’s & Tray Truck with Spider
Other Plant & equipment: various hand tools-
Wheels Free Area & Times: Wheels Free For All Work Parties Sunday 23 June @ 16:00 - 00:01 Monday
Wheels Free exception for 22kv works (As agreed by Noel McMahon.)
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Refer to P6 Program if more detail required
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Craig Baxter Rob Lord Craig Baxter Rob Lord
Mobile Number 0428 847 090 0412 105 133 0428 847 090 0412 105 133
Date 22/06/13 22/06/13 23/06/13 23/06/13
Shift Duration 02:00 - 14:00 14:00 - 02:00 02:00 - 14:00 14:00 - 02:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Matt Briggs Dean Gauci Matt Briggs Dean Gauci Matt Briggs
Mobile Number 0437 844 953 0447 649 794 0437 844 953 0447 649 794 0437 844 953
Date 21/06/13 22/06/13 22/06/13 23/06/13 23/06/13
Shift Duration 00:01 – 10:00 10:00 - 20:00 20:00 - 06:00 06:00 - 16:00 16:00 - 02:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable, eAP for 22kv Feeder N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A NO
Occupation Works Guide
16
WORk GROUP 2: OveR HeAD 22kv (JOHN HOLLANDS)
Work Group Limits: Structutre H460+77 to H472+45 Down Track (elgar Road Bridge to Box Hill)
Scope of Works: 22kv Prep works for Rehabilitation WorksSaturday: 02:00 - 08:00 Sunday Between Str 460 - 472 Down Line (Mont Albert Station to Box Hill Station)
Site Access: Mont Albert Road PCR
Hi-Rail vehicles: 1 X Hi-Rail eWP
Other Plant & equipment: various hand tools-
Wheels Free Area & Times: N/A
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Refer to P6 Program if more detail required
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Craig Baxter Rob Lord Craig Baxter
Mobile Number 0428 847 090 0412 105 133 0428 847 090
Date 22/06/13 22/06/13 23/06/13
Shift Duration 02:00 - 14:00 14:00 - 02:00 02:00 - 08:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Barry Howard Melinda Steur Sigride Paeglis
Mobile Number 0419 327 535 0411 740 727 0433 164 077
Date 22/06/13 22/06/13 23/06/13
Shift Duration 00:01 – 11:00 11:00 - 22:00 22:00 - 08:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable, eAP for 22kv Feeder N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A NO
17
WORk GROUP 3: SIGNALS (PAINTING)
Work Group Limits: Surrey Hills - Box Hill
Scope of Works: Saturday: Paint Signal Targets in a down direction L407, H407, L415, L421, H421, H433, L441, L423, L433 & BOX312
Sunday: Paint Signal Targets L410, H418, L418, H428, L428, L434, L440, H440, L450, BOX205 & BOX215
Site Access: Saturday: Mont Albert Road PCR working from Down Track and may require Centre Track.
Sunday: Mont Albert Road PCR working from Up Track and may require Centre Track.
Hi-Rail vehicles: Hi-Rail boom lift truck
Other Plant & equipment: Hand tools
Wheels Free Area & Times:
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes:
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Supervisor Troy Whiteside Steve Barrett
Mobile Number 0417 139 961 0407 364 004
Date 22/06/2013 23/06/2013
Shift Duration 07:00 - 17:00 07:00 - 17:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Level 3 Troy Whiteside Steve Barrett
Mobile Number 0417 139 961 0407 364 004
Date 22/06/2013 23/06/2013
Shift Duration 07:00 - 17:00 07:00 - 17:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
Occupation Works Guide
18
WORk GROUP 4: SIGNALS (INSTALLING & INSULATION)
Work Group Limits: east Camberwell - Canterbury
Scope of Works: Saturday & Sunday shifts: Install signals CAM345, L334, L335 & H335 on gantry between eCM & CBY
& stand signal mast L325. Remove old signal masts L325, L343 & L326
Sunday afternoon shift: Test signals L325, L343, L326, CAM345, L334, & L335 on gantry between eCM & CBY
Site Access: Union Rd PCR & Ballast Pad at eCM Substation.
Hi-Rail vehicles: Crane Truck, excavator, Tip Truck & elevated Work Platform
Other Plant & equipment: Hand tools
Wheels Free Area & Times: Wheels Free For All Work Parties Sunday 23 June 16:00 - 00:01, Occupation Limits
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Crane Truck working on Down Track, Cherry Picker working on Centre Track.
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Joe Mifsud Kon Triantafillos Jim Panayotides
Mobile Number 0408 266 419 0411 239 017 0411 239 037
Date 22/06/2013 23/06/2013 23/06/2013
Shift Duration 07:00 - 17:00 08:00 - 16:00 16:00 - 00:01
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Joe Mifsud Kon Triantafillos Jim Panayotides
Mobile Number 0408 266 419 0411 239 017 0411 239 037
Date 22/06/2013 23/06/2013 23/06/2013
Shift Duration 07:00 - 17:00 08:00 - 16:00 16:00 - 00:01
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable - 22kv Feeder N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
19
WORk GROUP 5: STRUCTUReS & FACILITIeS (GUY BASeS)
Work Group Limits: east Camberwell - Mont Albert Road
Scope of Works: Installation of New Anchor Bases
Saturday: Contruct @ Structures 320D - 322D - 339U - 360U - 366 U&D - 414 U&D
Sunday: Poor concrete for above Anchor Bases
Site Access: Mont Albert Road or Union Rd. Up Track
Hi-Rail vehicles: 1 x Hi Rail tool Truck, 1 x Sucker truck, 1 x excavator all on Up Track
Other Plant & equipment: Concrete Truck, Concrete Line Pump, Small plant And Hand Tools
Wheels Free Area & Times: Wheels Free For All Work Parties as of Sunday 23 June @ 16:00
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Concrete Truck, Concrete Line Pump will work from Rail Reserve.
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Peppi BernardiGreg kicaj
Peppi Bernardi
Mobile Number 0438 793 8970418 666 448
0438 793 897
Date 22/06/13 23/06/13
Shift Duration 05:00 - 15:0007:00 - 17:00
07:00 - 17:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Peppi BernardiGreg kicaj
Peppi Bernardi
Mobile Number 0438 793 8970418 666 448
0438 793 897
Date 22/06/13 23/06/13
Shift Duration 05:00 - 15:0007:00 - 17:00
07:00 - 17:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable - 22kv Feeder N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
Occupation Works Guide
20
WORk GROUP 6: STRUCTUReS & FACILITIeS (GUY BASeS)
Work Group Limits: Surrey Hills - Mont Albert Road
Scope of Works: Installation of New Anchor Base
Contruct @ Structure, 414 U&D. #Up Structure is between Up and Centre Tracks
Poor concrete for above Anchor Base
Site Access: Mont Albert Road
Hi-Rail vehicles: 1 x Hi Rail tool Truck, 1 x Sucker truck, 1 x excavator all on Centre and Down Tracks
Other Plant & equipment: Concrete Truck, Concrete Line Pump, Small plant And Hand Tools
Wheels Free Area & Times: Wheels Free For All Work Parties as of Sunday 23 June @ 16:00, Occupation Limits
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Concrete Truck, Concrete Line Pump will work from Rail Reserve.
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Greg kicaj
Mobile Number 0418 666 448
Date 23/06/13
Shift Duration 07:00 - 17:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Greg kicaj
Mobile Number 0418 666 448
Date 23/06/13
Shift Duration 07:00 - 17:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable - 22kv Feeder N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
21
WORk GROUP 7: TRACk (Re-RAILING THe UP LINe)
Work Group Limits: Mont Albert Road - Box Hill
Scope of Works: Re-railing of the Up Track between Mont Albert Rd to Up end Box Hill Station (Signal BOX 205) and re-sleepering elgar Road Bridge Up Track.
Working from the Centre and Up Tracks only
Site Access: Mont Albert Down end gate access & Mont Albert Road level Crossing
Hi-Rail vehicles: 2x Hi-Rail excavators
Other Plant & equipment: 1x Loader, 1x Backhoe
Wheels Free Area & Times: Wheels Free For All Work Parties as of Sunday 23 June @ 16:00
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Bridge re-sleepering will be tamped by back-hoe/excavator. Track Machines not required.
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Josh etrich Jimmy Mihail Josh etrich
Mobile Number 0448 497 879 0459 105 819 0448 497 879
Date 22/06/13 22/06/13 22/06/13
Shift Duration 02:45 - 10:00 10:01 - 20:00 20:01 - 06:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Josh etrich Jimmy Mihail Josh etrich
Mobile Number 0448 497 879 0459 105 819 0448 497 879
Date 22/06/13 22/06/13 22/06/13
Shift Duration 02:45 - 10:00 10:01 - 20:00 20:01 - 06:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
1500v Traction Cable N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A No
Occupation Works Guide
22
WORk GROUP 8: OveR HeADS (WIRe RUN)
Work Group Limits: STR 359+40 to 392+35 (Down end Caterbury to Union Road) Working on Centre Track and collecting scrap from Up Track
Scope of Works: Contact Wire Run
Site Access: Union Rd or Mont Albert Rd
Hi-Rail vehicles: 3 eWP’s & Truck 1 x Tip Truck for collecting scrap overhead wire.
Other Plant & equipment: various hand tools
Wheels Free Area & Times: N/A
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes:
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Duty Officer
Mobile Number 9619 5799
Date 23/06/13
Shift Duration 14:00 - 23:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Night Sunday Day Sunday Night
Name Duty Officer
Mobile Number 9619 5799
Date 23/06/13
Shift Duration 14:00 - 23:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
N/A N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
Occupation Works Guide
23
WORk GROUP 9: OveR HeAD (WIRe RUN)
Work Group Limits: STR 390+55 to 414+11 (Robinson Road Bridge to Mont Albert Road) Working on Centre Track and collecting scrap from Up Track
Scope of Works: Contact Wire Run
Site Access: Union Rd or Mont Albert Rd
Hi-Rail vehicles: 3 eWP’s & Truck 1 x Tip Truck for collecting scrap overhead wire.
Other Plant & equipment: various hand tools
Wheels Free Area & Times: N/A
Traffic Management: Union Road & Mont Albert will have traffic management 06:00 Saturday to 20:00 Sunday. Level Crossings will be test switch operational.
Issue Permit to Foul: Command Centre Surrey Hills
Notes:
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Duty Officer
Mobile Number 9619 5799
Date 22/06/13
Shift Duration 14:00 - 23:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Duty Officer
Mobile Number 9619 5799
Date 22/06/13
Shift Duration 14:00 - 23:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
N/A N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
24
WORk GROUP 10: OveR HeAD (SPARk GAP BONDING RePAIRS)
Work Group Limits: Occupation Limits
Scope of Works: Spark Gap Bonding Repairs
Site Access: various locations
Hi-Rail vehicles: No
Other Plant & equipment: Hand Tools
Wheels Free Area & Times: N/A
Traffic Management: N/A
Issue Permit to Foul: Command Centre Surrey Hills
Notes: Spark Gap Repairs & some Rail Drilling only
WILL WORk AROUND ALL OTHeR WORk GROUPS
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Rod Sheppard Rod Sheppard
Mobile Number 0408 838 345 0408 838 345
Date 22/06/13 23/06/13
Shift Duration 07:00 - 18:00 07:00 - 18:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Rod Sheppard Rod Sheppard
Mobile Number 0408 838 345 0408 838 345
Date 22/06/13 23/06/13
Shift Duration 07:00 - 18:00 07:00 - 18:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
No N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
25
WORk GROUP 11: SIGNALS (PRe TeST OF GR BOXeS)
Work Group Limits: east Camberwell to Canterbury
Scope of Works: Pre Test of GR Boxes
Site Access: east Camberwell Substation
Hi-Rail vehicles: No
Other Plant & equipment: Hand Tools
Wheels Free Area & Times: N/A
Traffic Management: N/A
Issue Permit to Foul: Command Centre Surrey Hills
Notes:
SUPeRvISOR ROSTeR
Friday Night Saturday Day Saturday Night Sunday Day Sunday Night
Name Noel McMahon
Mobile Number 0411 239 192
Date 22/06/13
Shift Duration 17:00 - 01:00
PeRMIT TO FOUL ReCIPIeNT ROSTeR
Friday Night Saturday Day Saturday Night Sunday Night
Name Noel McMahon
Mobile Number 0411 239 192
Date 22/06/13
Shift Duration 17:00 - 01:00
HIGH vOLTAGe PeRMIT PLANT TRAIN
No N/A
ADJACeNT LINe PROTeCTION ReqUIReD TRACk MACHINe
N/A N/A
2625
Permit to Foul Summary RegisterOCCUPATION: P.T.F. ID
Dept. Work Description Work Location Shift Details Friday 21st June Night Shift
Saturday 22nd June Day Shift
Saturday 22nd June Night Shift
Sunday 23rd June Day Shift
Sunday 23rd June Night Shift
P/O Notes
1 Over Head
(JHG)
22kv Rehabilitation Works
Up end Chatham - Box Hill. Refer to WG form for more detail
Name Matt Briggs Dean Gauci Matt Briggs Dean Gauci Matt Briggs Yes PTF Meet Point Command Centre Surrey HillsContact No. 0437 844 953 0447 649 794 0437 844 953 0447 649 794 0437 844 953 Access to Occo Union Road PCR & Mont Albert PCRTimes 00:01 – 10:00 10:00 - 20:00 20:00 - 06:00 06:00 - 16:00 16:00 - 02:00 Hi-Rail 2 X Hi-Rail eWP’s & Tray Truck with Spider
2 Over Head
(JHG)
Prep works for 22kv Rehabilitation Works
elgar Road Bridge - Box Hill.
Name Barry Howard Melinda Steur Sigride Paeglis Yes PTF Meet Point Command Centre Surrey HillsContact No. 0419 327 535 0411 740 727 0433 164 077 Access to Occo Mont Albert PCRTimes 00:01 – 11:00 11:00 - 22:00 22:00 - 08:00 Hi-Rail 1 X Hi-Rail eWP
3 Signals Paint Signal Targets Surrey Hills - Box Hill Name Troy Whiteside Steve Barrett Yes PTF Meet Point Command Centre Surrey HillsContact No. 0417 139 961 0407 364 004 Access to Occo Mont Albert Road PCRTimes 07:00 - 17:00 07:00 - 17:00 Hi-Rail Hi-rail boom lift truck
4 Signals Installing & Testing New Signals
east Camberwell - Canterbury
Name Joe Mifsud Kon Triantafillos Jim Panayotides Yes PTF Meet Point Command Centre Surrey Hills
Contact No. 0408 266 419 0411 239 017 0411 239 037 Access to Occo Union Rd PCR & Ballast Pad at eCM Substation.
Times 07:00 - 17:00 08:00 - 16:00 16:00 - 00:01 Hi-Rail Crane Truck, excavator, Tip Truck & elevated Work Platform
5 Structure & Facilities
Installation of New Anchor Bases
east Camberwell - Mont Albert Road
Name Peppi BernardiGreg kicaj
Peppi BernardiYes PTF Meet Point Command Centre Surrey Hills
Contact No. 0438 793 8970418 666 448
0438 793 897Access to Occo Mont Albert Road or Union Rd.
Times 05:00 - 15:0007:00 - 17:00
07:00 - 17:00 Hi-Rail 1 x Hi Rail tool Truck, 1 x Sucker truck, 1 x excavator all on Up Track
6 Structure & Facilities
Installation of New Anchor Base
Surrey Hills - Mont Albert Road
Name Greg kicaj Yes PTF Meet Point Command Centre Surrey Hills
Contact No. 0418 666 448 Access to Occo Mont Albert Road
Times 07:00 - 17:00 Hi-Rail 1 x Hi Rail tool Truck, 1 x Sucker truck, 1 x excavator all on Up Track
7 Track Re-Railing Up Track Mont Albert Road - Box Hill
Name Josh etrich Jimmy Mihail Josh etrich Yes PTF Meet Point Command Centre Surrey Hills
Contact No.0448 497 879 0459 105 819 0448 497 879
Access to Occo Mont Albert, Down end access gate & Mont Albert Road PCR
Times 02:45 - 10:00 10:01 - 20:00 20:01 - 06:00 Hi-Rail 2x Hi-Rail excavators8 Over Head 1500v Wire Run Down end Caterbury -
Union RoadName Duty Officer PTF Meet Point Command Centre Surrey Hills
Contact No. 9619 5799 Access to Occo Union Rd or Mont Albert Rd
Times 14:00 - 23:00 Hi-Rail 3 eWP’s & Truck 1 x Tip Truck
9 Over Head 1500v Wire Run Robinson Road Bridge - Mont Albert Road
Name Duty Officer PTF Meet Point Command Centre Surrey Hills
Contact No. 9619 5799 Access to Occo Union Rd or Mont Albert Rd
Times 14:00 - 23:00 Hi-Rail 3 eWP’s & Truck 1 x Tip Truck
10 Over Head Spark Gaps Repairs Occupation Limits Name Rod Sheppard Rod Sheppard PTF Meet Point Command Centre Surrey Hills
Contact No. 0408 838 345 0408 838 345 Access to Occo various Locations
Times 07:00 - 18:00 07:00 - 18:00 Hi-Rail N/A
11 Signals Pre Test of GR Boxes east Camberwell to Canterbury
Name Noel McMahon PTF Meet Point Command Centre Surrey HillsContact No. 0411 239 192 Access to Occo east Camberwell SubstationTimes 17:00 - 01:00 Hi-Rail N/A
12 Signals Support for Re-Railing Works & Signal Testing
Occupation Limits NameUwe Swiderski
Sergundo BurgosJim Panayotides
David Matthews Frank Dobrigna David MatthewsPTF Meet Point Command Centre Surrey Hills
Contact No.0408 266 454
0409 944 6300411 239 037
0408 593 550 0408 567 036 0408 593 550Access to Occo various Locations
Times 00:01 - 08:01 08:00 - 16:0016:00 - 23:59
00:01 - 08:00 08:00 - 18:00 20:00 - 06:00 Hi-Rail N/A
27
Activity ID Activity Name OriginalDuration
RemainingDuration
Start Finish Location Track Activity %Complete
Predecessors Successors Comments
East Camberwell to Box Hill Major Occupation ProgrammeEast Camberwell to Box Hill Major Occupation Programme 53h 53h 21-Jun-13 23:00 24-Jun-13 04:00
Occupation Start-UpOccupation Start-Up 11h 11h 21-Jun-13 23:00 22-Jun-13 10:00
Key ActivitiesKey Activities 1h 10n 1h 10n 22-Jun-13 01:35 22-Jun-13 02:45
All DisciplinesAll Disciplines 1h 10n 1h 10n 22-Jun-13 01:35 22-Jun-13 02:45
All WorksAll Works 1h 10n 1h 10n 22-Jun-13 01:35 22-Jun-13 02:45AC3570 Last Train Through Box Hill (Weekend 1) 0h 0h 22-Jun-13 01:35* 0% AC5510,
AC2940, AC5850AC2910 eCM-BOX Overhead Isolation Weekend 1 Complete 0h 0h 22-Jun-13 02:15 0% AC2940 AC5520
AC2930 All Permits Issued for Weekend 1 0h 0h 22-Jun-13 02:45 0% AC5520, AC5510
AC3090, AC3080, AC5590, A...PreliminariesPreliminaries 3h 45n 3h 45n 21-Jun-13 23:00 22-Jun-13 02:45
All DisciplinesAll Disciplines 3h 45n 3h 45n 21-Jun-13 23:00 22-Jun-13 02:45
All WorksAll Works 3h 45n 3h 45n 21-Jun-13 23:00 22-Jun-13 02:45AC5490 Pre-Start Briefing (Weekend 1) 1h 1h 21-Jun-13 23:00* 22-Jun-13 00:00 0% AC5500,
AC2940, AC5850AC5500 Pre-Work Briefing (Weekend 1) 1h 1h 22-Jun-13 00:00 22-Jun-13 01:00 0% AC5490 AC5510 Includes plant checks
AC5510 Permit to Foul Issued (Weekend 1) 0h 25n 0h 25n 22-Jun-13 01:35 22-Jun-13 02:00 0% AC5500, AC3570
AC2930, AC3170, AC6020, A...AC5520 Permit to Work & eAP Issued (Weekend 1) 0h 30n 0h 30n 22-Jun-13 02:15 22-Jun-13 02:45 0% AC2910 AC2930
All AreasAll Areas 8h 25n 8h 25n 22-Jun-13 01:35 22-Jun-13 10:00
OverheadsOverheads 0h 40n 0h 40n 22-Jun-13 01:35 22-Jun-13 02:15
IsolationsIsolations 0h 40n 0h 40n 22-Jun-13 01:35 22-Jun-13 02:15AC2940 Undertake Overhead Isolations for Weekend 1 0h 40n 0h 40n 22-Jun-13 01:35 22-Jun-13 02:15 0% AC5490,
AC3570AC2910
CitiPowerCitiPower 0h 0h 22-Jun-13 10:00 22-Jun-13 10:00IsolationsIsolations 0h 0h 22-Jun-13 10:00 22-Jun-13 10:00AC5850 CitiPower Lv Isolation at Union Rd 0h 0h 22-Jun-13 10:00* 0% AC3570,
AC5490AC3160
OccupationOccupation 47h 45n 47h 45n 22-Jun-13 02:00 24-Jun-13 01:45
OverallOverall 10h 45n 10h 45n 23-Jun-13 15:00 24-Jun-13 01:45
All DisciplinesAll Disciplines 10h 45n 10h 45n 23-Jun-13 15:00 24-Jun-13 01:45
Key ActivitiesKey Activities 10h 45n 10h 45n 23-Jun-13 15:00 24-Jun-13 01:45AC3430 Construction of New Guy Base Anchors Complete (east Camberwell to Box
Hill)0h 0h 23-Jun-13 15:00 0% SNFY46320,
SNFY46330, SNFY46340, SNFY46350...
AC3370
AC3250 Track Works Complete (east Camberwell to Box Hill) Weekend 1 0h 0h 23-Jun-13 16:00 0% AC6140 AC5910
AC3080 Wheels Free for Signals (east Camberwell to Box Hill) Weekend 1 0h 0h 23-Jun-13 16:00* 0% AC3220, AC3210, AC3090, AC2930, A...
AC3240, AC3370
AC3260 Overheads (MTM) Works Complete Weekend 1 0h 0h 23-Jun-13 23:00 0% AC5920, AC5930
AC3370
AC3200 Overhead (JHG) Works Complete (east Camberwell to Box Hill Up Track) Weekend 1
0h 0h 24-Jun-13 01:30 0% AC3130 AC3370
AC3040 Signal Works Complete (east Camberwell to Box Hill) Weekend 1 0h 0h 24-Jun-13 01:45 0% AC3240, AC5610, AC5690, AC5870, A...
AC5370, AC3370
East Camberwell to Box HillEast Camberwell to Box Hill 47h 45n 47h 45n 22-Jun-13 02:00 24-Jun-13 01:45
Overheads (JHG)Overheads (JHG) 47h 30n 47h 30n 22-Jun-13 02:00 24-Jun-13 01:3022kV AC Transmission Renewal22kV AC Transmission Renewal 47h 30n 47h 30n 22-Jun-13 02:00 24-Jun-13 01:30AC3170 On Track Plant 0h 30n 0h 30n 22-Jun-13 02:00 22-Jun-13 02:30 DN 0% AC5510
AC3120 Renew Transmission Wire @ H426+10 to H430+95 [140m, 2 Bays] 3h 3h 22-Jun-13 02:00 22-Jun-13 05:00 Mont Albert Station DN 0% AC5510 AC3150 Spider
AC3270 Prep Work at H460+77 to H472+45 30h 30h 22-Jun-13 02:00* 23-Jun-13 08:00 0% AC5510 AC3190 seperate PTF required.
AC3150 Renew Transmission Wire @ H430+95 to H433+87 2h 30n 2h 30n 22-Jun-13 05:00 22-Jun-13 07:30 DN 0% AC3120 AC3140
AC3140 Renew Transmission Wire @ H433+87 to H436+87 2h 30n 2h 30n 22-Jun-13 07:30 22-Jun-13 10:00 DN 0% AC3150 AC3100
AC3100 Renew Transmission Wire @ H436+87 to H438+37 2h 30n 2h 30n 22-Jun-13 10:00 22-Jun-13 12:30 DN 0% AC3140 AC3300
AC3300 Renew Transmission Wire @ H438+37 to H440+80 2h 30n 2h 30n 22-Jun-13 12:30 22-Jun-13 15:00 DN 0% AC3100 AC3700
AC3700 Renew Transmission Wire @ H406+68 to H408+11 [59m, 1 Bay] 2h 30n 2h 30n 22-Jun-13 15:00 22-Jun-13 17:30 DN 0% AC3300 AC3710
AC3710 Renew Transmission Wire @ H408+11 to H411+11 [91m, 2 Bays] 2h 30n 2h 30n 22-Jun-13 17:30 22-Jun-13 20:00 DN 0% AC3700 AC3160
AC3160 Renew Transmission Wire @ H399+61 to H402+01 [73m, 1 Bay] 3h 3h 22-Jun-13 20:00 22-Jun-13 23:00 Union Rd Level Crossing DN 0% AC5850, AC3710
AC5860, AC3110
Traffic management required
AC3110 Renew Transmission Wire @ H368+55 to H380+30 [328m, 6 Bays] 8h 8h 22-Jun-13 23:00 23-Jun-13 07:00 Chatham Station DN 0% AC3160 AC3190 Spider
AC3190 Renew Transmission Wire @ H440+80 to H453+05 [373m, 5 Bays] 6h 30n 6h 30n 23-Jun-13 07:00 23-Jun-13 13:30 Hood St, Creswick Ln DN 0% AC3110, AC3270
AC3180
AC3180 Renew Transmission Wire @ H453+05 to H459+05 [183m, 3 Bays] 5h 5h 23-Jun-13 13:30 23-Jun-13 18:30 DN 0% AC3190 AC3130
Fri Sat Sun Mon TueJun 17 Jun 24
Last Train Through Box Hill (Weekend 1)
eCM-BOX Overhead Isolation Weekend 1 Complete
All Permits Issued for Weekend 1
Pre-Start Briefing (Weekend 1)
Pre-Work Briefing (Weekend 1)
Permit to Foul Issued (Weekend 1)
Permit to Work & eAP Issued (Weekend 1)
Undertake Overhead Isolations for Weekend 1
CitiPower Lv Isolation at Union Rd
Construction of New Guy Base Anchors Complete (east Camberwell to Box Hill)
Track Works Complete (east Camberwell to Box Hill) Weekend 1
Wheels Free for Signals (east Camberwell to Box Hill) Weekend 1
Overheads (MTM) Works Complete Weekend 1
Overhead (JHG) Works Complete (east Camberwell to Box Hill Up Track) Weekend 1
Signal Works Complete (east Camberwell to Box Hill) Weekend 1
On Track Plant
Renew Transmission Wire @ H426+10 to H430+95 [140m, 2 Bays]
Prep Work at H460+77 to H472+45
Renew Transmission Wire @ H430+95 to H433+87
Renew Transmission Wire @ H433+87 to H436+87
Renew Transmission Wire @ H436+87 to H438+37
Renew Transmission Wire @ H438+37 to H440+80
Renew Transmission Wire @ H406+68 to H408+11 [59m, 1 Bay]
Renew Transmission Wire @ H408+11 to H411+11 [91m, 2 Bays]
Renew Transmission Wire @ H399+61 to H402+01 [73m, 1 Bay]
Renew Transmission Wire @ H368+55 to H380+30 [328m, 6 Bays]
Renew Transmission Wire @ H440+80 to H453+05 [373m, 5 Bays]
Renew Transmission Wire @ H453+05 to H459+05 [183m, 3 Bays]
Layout: Current LayoutTASk filter: Date Filter.
Metro Trains MelbourneECM - BOX Corridor Shut (Weekend 21th-24th June)
Print Date: 19-Jun-13Data Date: 12-Apr-13
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone Page 1 of 4 Date Revision Checked Approved19-Jun-13 12:... Revision 17
Intergrated Works Program
28
Activity ID Activity Name OriginalDuration
RemainingDuration
Start Finish Location Track Activity %Complete
Predecessors Successors Comments
AC3130 Renew Transmission Wire @ H459+05 to H472+45 [408m, 8 Bays] 7h 7h 23-Jun-13 18:30 24-Jun-13 01:30 DN 0% AC3180 AC3200
CitiPowerCitiPower 0h 0h 23-Jun-13 16:00 23-Jun-13 16:00ReinstatementReinstatement 0h 0h 23-Jun-13 16:00 23-Jun-13 16:00AC5860 CitiPower Lv Restoration at Union Rd 0h 0h 23-Jun-13 16:00* 0% AC3160 AC3380
Overheads (MTM)Overheads (MTM) 33h 33h 22-Jun-13 14:00 23-Jun-13 23:00
Contact Wire RenewalContact Wire Renewal 33h 33h 22-Jun-13 14:00 23-Jun-13 23:00AC5930 Contact Wire Renewal @ e Camberwell to Surrey Hills STR 390+55 TO
414+11 CTR TRACk9h 9h 22-Jun-13 14:00* 22-Jun-13 23:00 CTR 0% AC2930 AC3260
AC5920 Contact Wire Renewal @ e Camberwell to Surrey Hills STR 359+40 to 392+35 CTR TRACk
9h 9h 23-Jun-13 14:00* 23-Jun-13 23:00 CTR 0% AC2930 AC3260 AC3110
TrackTrack 38h 38h 22-Jun-13 02:00 23-Jun-13 16:00
Re-RailingRe-Railing 38h 38h 22-Jun-13 02:00 23-Jun-13 16:00AC6020 eclips and Insulators to be Removed and Stockpiled to the Side 8h 8h 22-Jun-13 02:00 22-Jun-13 10:00 Mont Albert to Box Hill UP 0% AC5510 AC6030 Shift 1
AC6030 excavators to stockpile rail lenghts in secure location within six foot to be collected by rain train at later date
7h 7h 22-Jun-13 03:00 22-Jun-13 10:00 Mont Albert to Box Hill UP 0% AC6020 AC6040 Shift 1
AC6040 New rail to lifted into position on sleepers utilising excvators and loaders 6h 6h 22-Jun-13 04:00 22-Jun-13 10:00 Mont Albert to Box Hill UP 0% AC6030 AC6050 Shift 1
AC6050 Single Bolt rail ends together 6h 6h 22-Jun-13 04:00 22-Jun-13 10:00 Mont Albert to Box Hill UP 0% AC6040 AC6060 Shift 1
AC6060 Reattatch e-clips and Insulators 6h 6h 22-Jun-13 04:00 22-Jun-13 10:00 Mont Albert to Box Hill UP 0% AC6050 AC6070 Shift 1
AC6070 excavators to stockpile rail lenghts in secure location within six foot to be collected by rain train at later date
7h 7h 22-Jun-13 10:00 22-Jun-13 17:00 Mont Albert to Box Hill UP 0% AC6060 AC6080 Shift 2
AC6080 New rail to lifted into position on sleepers utilising excvators and loaders 8h 8h 22-Jun-13 10:00 22-Jun-13 18:00 Mont Albert to Box Hill UP 0% AC6070 AC6090 Shift 2
AC6090 Single Bolt rail ends together 9h 9h 22-Jun-13 10:00 22-Jun-13 19:00 Mont Albert to Box Hill UP 0% AC6080 AC6100 Shift 2
AC6100 Reattatch e-clips and Insulators 10h 10h 22-Jun-13 10:00 22-Jun-13 20:00 Mont Albert to Box Hill UP 0% AC6090 AC6110 Shift 2
AC6110 Welding out of all joints 6h 6h 22-Jun-13 20:00 23-Jun-13 02:00 Mont Albert to Box Hill UP 0% AC6100 AC6120 Shift 3
AC6120 Destress of 330m modules 4h 4h 23-Jun-13 02:00 23-Jun-13 06:00 Mont Albert to Box Hill UP 0% AC6110 AC6130 Shift 3
AC6130 Final site cleanup of rubbish and removal of all track plant 2h 2h 23-Jun-13 04:00 23-Jun-13 06:00 Mont Albert to Box Hill UP 0% AC6120 AC6140, AC5620
Shift 3
AC6140 Signals to start reconnecting and testing 11h 11h 23-Jun-13 05:00 23-Jun-13 16:00 Mont Albert to Box Hill UP 0% AC6130 AC3250, AC3080
Shift 3
SignalsSignals 42h 45n 42h 45n 22-Jun-13 07:00 24-Jun-13 01:45Incandescent Signal Replacement with LEDIncandescent Signal Replacement with LED 33h 33h 22-Jun-13 07:00 23-Jun-13 16:00AC3090 Incandescent Signal Replacement with LeD at Signal CAM345 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 east Camberwell 0% AC2930 AC3230,
AC3220, AC3210, A...AC3210 Incandescent Signal Replacement with LeD at Signal L334 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 east Camberwell 0% AC3090 AC3080
AC3220 Incandescent Signal Replacement with LeD at Signal L335 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 east Camberwell 0% AC3090 AC3080
AC3230 Incandescent Signal Replacement with LeD at Signal H335 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 east Camberwell 0% AC3090 AC5940
AC5980 Stand and Install Signal L325 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 east Camberwell 0% AC2930 AC3040
AC5940 Incandescent Signal Replacement with LeD at Signal CAM345 9h 9h 23-Jun-13 07:00* 23-Jun-13 16:00 east Camberwell 0% AC3230 AC5950
AC5950 Incandescent Signal Replacement with LeD at Signal L334 9h 9h 23-Jun-13 07:00 23-Jun-13 16:00 east Camberwell 0% AC5940 AC5960
AC5960 Incandescent Signal Replacement with LeD at Signal L335 9h 9h 23-Jun-13 07:00 23-Jun-13 16:00 east Camberwell 0% AC5950 AC5970
AC5970 Incandescent Signal Replacement with LeD at Signal H335 9h 9h 23-Jun-13 07:00 23-Jun-13 16:00 east Camberwell 0% AC5960 AC3080
Signal TestingSignal Testing 9h 45n 9h 45n 23-Jun-13 16:00 24-Jun-13 01:45AC3240 Signal Testing & Commissioning of L325, L326, L343, L334, CAM345, H335
& L3359h 45n 9h 45n 23-Jun-13 16:00 24-Jun-13 01:45 0% AC3080 AC3040 L326 & L343 are installed in the pre-work occupation
nights
Painting of Signal Backgrounds (DOWN Track)Painting of Signal Backgrounds (DOWN Track) 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00AC3790 Painting of Signal Targets L407 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Up side of Mont Albert Rd DN 0% AC2930 AC3800
AC3800 Painting of Signal Targets H407 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Up side of Mont Albert Rd DN 0% AC3790 AC3810
AC3810 Painting of Signal Targets L415 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Up side of Mont Albert Rd DN 0% AC3800 AC3820
AC3820 Painting of Signal Targets L421 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Up side of Mont Albert Rd DN 0% AC3810 AC3830
AC3830 Painting of Signal Targets H421 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Up side of Mont Albert Rd DN 0% AC3820 AC3940
AC3940 Painting of Signal Targets H433 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Down side of Mont Albert Rd
DN 0% AC3830 AC3990
AC3990 Painting of Signal Targets L441 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Down side of Mont Albert Rd
DN 0% AC3940 AC5880
Fri Sat Sun Mon TueJun 17 Jun 24
Renew Transmission Wire @ H459+05 to H472+45 [408m, 8 Bays]
CitiPower Lv Restoration at Union Rd
Contact Wire Renewal @ e Camberwell to Surrey Hills STR 390+55 TO 414+11 CTR TRACk
Contact Wire Renewal @ e Camberwell to Surrey Hills STR 359+40 to 392+35 CTR TRACk
eclips and Insulators to be Removed and Stockpiled to the Side
excavators to stockpile rail lenghts in secure location within six foot to be collected by rain train at later date
New rail to lifted into position on sleepers utilising excvators and loaders
Single Bolt rail ends together
Reattatch e-clips and Insulators
excavators to stockpile rail lenghts in secure location within six foot to be collected by rain train at later date
New rail to lifted into position on sleepers utilising excvators and loaders
Single Bolt rail ends together
Reattatch e-clips and Insulators
Welding out of all joints
Destress of 330m modules
Final site cleanup of rubbish and removal of all track plant
Signals to start reconnecting and testing
Incandescent Signal Replacement with LeD at Signal CAM345
Incandescent Signal Replacement with LeD at Signal L334
Incandescent Signal Replacement with LeD at Signal L335
Incandescent Signal Replacement with LeD at Signal H335
Stand and Install Signal L325
Incandescent Signal Replacement with LeD at Signal CAM345
Incandescent Signal Replacement with LeD at Signal L334
Incandescent Signal Replacement with LeD at Signal L335
Incandescent Signal Replacement with LeD at Signal H335
Signal Testing & Commissioning of L325, L326, L343, L334, CAM345, H335 & L335
Painting of Signal Targets L407
Painting of Signal Targets H407
Painting of Signal Targets L415
Painting of Signal Targets L421
Painting of Signal Targets H421
Painting of Signal Targets H433
Painting of Signal Targets L441
Layout: Current LayoutTASk filter: Date Filter.
Metro Trains MelbourneECM - BOX Corridor Shut (Weekend 21th-24th June)
Print Date: 19-Jun-13Data Date: 12-Apr-13
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone Page 2 of 4 Date Revision Checked Approved19-Jun-13 12:... Revision 17
28 29
Activity ID Activity Name OriginalDuration
RemainingDuration
Start Finish Location Track Activity %Complete
Predecessors Successors Comments
AC4100 Painting of Signal Targets L423 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Down side of Mont Albert Rd
DN 0% AC5880 AC5870
AC5870 Painting of Signal Targets L433 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Down side of Mont Albert Rd
DN 0% AC4100 AC3040
AC5880 Painting of Signal Targets BOX312 10h 10h 22-Jun-13 07:00 22-Jun-13 17:00 Down side of Mont Albert Rd
DN 0% AC3990 AC4100
Painting of Signal Backgrounds (UP Track)Painting of Signal Backgrounds (UP Track) 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00AC5590 Painting of Signal Targets L410 10h 10h 23-Jun-13 07:00* 23-Jun-13 17:00 Up side of Mont Albert Rd UP 0% AC2930 AC5600
AC5600 Painting of Signal Targets H418 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Up side of Mont Albert Rd UP 0% AC5590 AC5610
AC5610 Painting of Signal Targets L418 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Up side of Mont Albert Rd UP 0% AC5600 AC3040
AC5620 Painting of Signal Targets H428 10h 10h 23-Jun-13 07:00* 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC2930, AC6130
AC5630
AC5630 Painting of Signal Targets L428 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5620 AC5640
AC5640 Painting of Signal Targets L434 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5630 AC5650
AC5650 Painting of Signal Targets L440 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5640 AC5660
AC5660 Painting of Signal Targets H440 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5650 AC5670
AC5670 Painting of Signal Targets L450 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5660 AC5680
AC5680 Painting of Signal Targets BOX205 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5670 AC5690
AC5690 Painting of Signal Targets BOX215 10h 10h 23-Jun-13 07:00 23-Jun-13 17:00 Down side of Mont Albert Rd
UP 0% AC5680 AC3040
Structures & FacilitiesStructures & Facilities 32h 32h 22-Jun-13 07:00 23-Jun-13 15:00
Guy BasesGuy Bases 32h 32h 22-Jun-13 07:00 23-Jun-13 15:00SNFY46230 Str. 320 D: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 east Camberwell DN 0% AC2930 SNFY46320
SNFY46240 Str. 322 D: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 east Camberwell DN 0% AC2930 SNFY46330
SNFY46250 Str. 339 U: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Canterbury UP 0% AC2930 SNFY46340
SNFY46260 Str. 360 U: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Canterbury UP 0% AC2930 SNFY46350
SNFY46270 Str. 366 U: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Canterbury UP 0% AC2930 SNFY46360
SNFY46280 Str. 366 D: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Canterbury DN 0% AC2930 SNFY46370
SNFY46300 Str. 414 D: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Surrey Hills to Mont Albert DN 0% AC2930 SNFY46380
SNFY46310 Str. 414 C: Construct New Guy Base 10h 10h 22-Jun-13 07:00* 22-Jun-13 17:00 Surrey Hills to Mont Albert CTR 0% AC2930 SNFY46390
SNFY46320 Str. 320 D: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 east Camberwell DN 0% SNFY46230 AC3430, AC3080
SNFY46330 Str. 322 D: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 east Camberwell DN 0% SNFY46240 AC3430, AC3080
SNFY46340 Str. 339 U: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Canterbury UP 0% SNFY46250 AC3430, AC3080
SNFY46350 Str. 360 U: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Canterbury UP 0% SNFY46260 AC3430, AC3080
SNFY46360 Str. 366 U: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Canterbury UP 0% SNFY46270 AC3430, AC3080
SNFY46370 Str. 366 D: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Canterbury DN 0% SNFY46280 AC3430, AC3080
SNFY46380 Str. 414 D: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Surrey Hills to Mont Albert DN 0% SNFY46300 AC3430, AC3080
SNFY46390 Str. 414 C: Construct New Guy Base 8h 8h 23-Jun-13 07:00* 23-Jun-13 15:00 Surrey Hills to Mont Albert CTR 0% SNFY46310 AC3430, AC3080
Occupation CompletionOccupation Completion 12h 12h 23-Jun-13 16:00 24-Jun-13 04:00
All AreasAll Areas 12h 12h 23-Jun-13 16:00 24-Jun-13 04:00
OverheadOverhead 2h 15n 2h 15n 24-Jun-13 01:45 24-Jun-13 04:00
ReinstatementReinstatement 2h 15n 2h 15n 24-Jun-13 01:45 24-Jun-13 04:00
Fri Sat Sun Mon TueJun 17 Jun 24
Painting of Signal Targets L423
Painting of Signal Targets L433
Painting of Signal Targets BOX312
Painting of Signal Targets L410
Painting of Signal Targets H418
Painting of Signal Targets L418
Painting of Signal Targets H428
Painting of Signal Targets L428
Painting of Signal Targets L434
Painting of Signal Targets L440
Painting of Signal Targets H440
Painting of Signal Targets L450
Painting of Signal Targets BOX205
Painting of Signal Targets BOX215
Str. 320 D: Construct New Guy Base
Str. 322 D: Construct New Guy Base
Str. 339 U: Construct New Guy Base
Str. 360 U: Construct New Guy Base
Str. 366 U: Construct New Guy Base
Str. 366 D: Construct New Guy Base
Str. 414 D: Construct New Guy Base
Str. 414 C: Construct New Guy Base
Str. 320 D: Construct New Guy Base
Str. 322 D: Construct New Guy Base
Str. 339 U: Construct New Guy Base
Str. 360 U: Construct New Guy Base
Str. 366 U: Construct New Guy Base
Str. 366 D: Construct New Guy Base
Str. 414 D: Construct New Guy Base
Str. 414 C: Construct New Guy Base
Layout: Current LayoutTASk filter: Date Filter.
Metro Trains MelbourneECM - BOX Corridor Shut (Weekend 21th-24th June)
Print Date: 19-Jun-13Data Date: 12-Apr-13
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone Page 3 of 4 Date Revision Checked Approved19-Jun-13 12:... Revision 17
30
Activity ID Activity Name OriginalDuration
RemainingDuration
Start Finish Location Track Activity %Complete
Predecessors Successors Comments
AC3370 Certify Overheads (Weekend 1) 0h 30n 0h 30n 24-Jun-13 01:45 24-Jun-13 02:15 0% AC3430, AC3200, AC3080, AC3040, A...
AC3380
AC3360 Overhead Power Restoration (Weekend 1) 1h 1h 24-Jun-13 03:00 24-Jun-13 04:00 0% AC3380 AC3400
SignalsSignals 0h 30n 0h 30n 24-Jun-13 01:45 24-Jun-13 02:15
ReinstatementReinstatement 0h 30n 0h 30n 24-Jun-13 01:45 24-Jun-13 02:15AC5370 Certify Signals (Weekend 1) 0h 30n 0h 30n 24-Jun-13 01:45 24-Jun-13 02:15 0% AC3040 AC3380
TrackTrack 3h 3h 23-Jun-13 16:00 23-Jun-13 19:00ReinstatementReinstatement 3h 3h 23-Jun-13 16:00 23-Jun-13 19:00AC5910 Certify Track (Weekend 1) 3h 3h 23-Jun-13 16:00 23-Jun-13 19:00 0% AC3250 AC3380
All DisciplinesAll Disciplines 1h 45n 1h 45n 24-Jun-13 02:15 24-Jun-13 04:00
Completion WorksCompletion Works 1h 45n 1h 45n 24-Jun-13 02:15 24-Jun-13 04:00AC3380 Return All Permits (Weekend 1) 0h 45n 0h 45n 24-Jun-13 02:15 24-Jun-13 03:00 0% AC3370,
AC5370, AC5860, AC5910
AC3360
AC3390 Track Handed Back to Operations (Weekend 1) 0h 0h 24-Jun-13 04:00 0% AC3400
AC3400 Occupation Complete (Weekend 1) 0h 0h 24-Jun-13 04:00 0% AC3360 AC3390
Fri Sat Sun Mon TueJun 17 Jun 24
Certify Overheads (Weekend 1)
Overhead Power Restoration (Weekend 1)
Certify Signals (Weekend 1)
Certify Track (Weekend 1)
Return All Permits (Weekend 1)
Track Handed Back to Operations (Weekend 1)
Occupation Complete (Weekend 1)
Layout: Current LayoutTASk filter: Date Filter.
Metro Trains MelbourneECM - BOX Corridor Shut (Weekend 21th-24th June)
Print Date: 19-Jun-13Data Date: 12-Apr-13
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone Page 4 of 4 Date Revision Checked Approved19-Jun-13 12:... Revision 17
Occupation Works Guide
31
Track Machine Movements
N/A
32
Level Crossing Disarrangement
33
Overhead Diagram
34
Bus Route Diagram
Camberwell Inset
BUS PICK-UP AND SET-DOWN POINTS
WARNING - Railway line may be operational Trains or track machinesmay run at any time.
Melway Reference: Maps 46
MAIN T.E.R.I MAP (SAS & EXP)
CAM-05
Stopping all stations& Express Bus Route
CAMBERWELL - BOX HILL(Map 1 of 2)
Camberwell - Opposite the station in Cookson Street.East Camberwell - Near the Roundabout in Stanhope Grove.Canterbury - Near Rochester Road Pedestrian Traffic Lights in Canterbury Road.Chatham - At Pedestrian Lights in Canterbury Road.
Stops all Stations
Express Bus Route
Bus Stop Locations
Distance 7Km
Express via Canterbury Rd directDistance 7Km
Up and Down(Same as stop or opposite)
Up stop only
Down stop only
File Name: TERI CAM-06.worBy Stephen Gray27/9/2012
CAM-06
34 35
BUS PICK-UP AND SET-DOWN POINTS
Surrey Hills - Opposite the station in Windsor Crescent.Mont Albert - At the Regular Bus Stop in Mont Albert Road.Box Hill - At the Temporary Bus Stop on Whitehorse Road (South side).
WARNING - Railway line may be operational Trains or track machinesmay run at any time.
Melway Reference: Maps 46 & 47
MAIN T.E.R.I MAP (SAS & EXP)
CAM-05
EXPRESSvia Canterbury Road
File Name: TERI CAM-06.worBy Stephen Gray27/9/2012
Stopping all stations& Express Bus Route
CAMBERWELL - BOX HILL(Map 2 of 2)
CAM-06
Stops all Stations
Express Bus Route
Bus Stop Locations
Distance 7Km
Express via Canterbury Rd directDistance 7Km
Up and Down(Same as stop or opposite)
Up stop only
Down stop only
Box Hill Inset
U-Turn here oppositeBox Hill Town Hall(See as below)
36
1500v AeRIAL PeRMIT TO WORk SUMMARY
Dept Duration Task Location Limits Recipient Mobile
Track APLT 21/06 - 06:00 23/06 Re-Railing Up Track Mont Albert to Box Hill Str 420 - Str 472 Josh etrich 0448 497 879
S&F 07:00 - 17:00 22/06 Installation of OH Structure Guy Anchors east Camberwell to Box Hill Str 318 - Str 420 Peppi Bernardi 0438 793 897
S&F 07:00 - 17:00 23/06 Installation of OH Structure Guy Anchors east Camberwell to Box Hill Str 318 - Str 420 Greg kicaj 0418 666 448
Signals 07:00 - 17:00 22/06 Install Signals east Camberwell Str 321 - Str 353 Joe Mifsud 0408 266 419
Signals 07:00 - 17:00 22/06 Paint Signals east Camberwell Str 400 - Str 455 Troy Whiteside 0417 139 961
Signals 07:00 - 17:00 23/06 Paint Signals east Camberwell Str 400 - Str 466 Steve Barrett 0407 364 004
O/H APLT 21/06 - BPFT 24/06 22kv Rehabilation Works east Camberwell to Box Hill Str 318 - Str 480 Matt Briggs 0437 844 953
O/H 02:00 22/06 - 08:00 23/06 22kv Rehabilation Works Surrey Hills to Box Hill Str 400 - Str 480 Barry Howard 0419 327 535
2.2kv PeRMIT TO WORk SUMMARY
Dept Duration Task Location Limits Recipient Mobile
- - - - - - -
22,000v PeRMIT TO WORk SUMMARY
Dept Duration Task Location Limits Recipient Mobile
Track APLT 21/06 - 06:00 23/06 Re-Railing Up Track Mont Albert to Box Hill Str 420 - Str 472 Josh etrich 0448 497 879
S&F 07:00 - 17:00 22/06 Installation of OH Structure Guy Anchors east Camberwell to Box Hill Str 318 - Str 420 Peppi Bernardi 0438 793 897
S&F 07:00 - 17:00 23/06 Installation of OH Structure Guy Anchors east Camberwell to Box Hill Str 318 - Str 420 Greg kicaj 0418 666 448
Signals 07:00 - 17:00 22/06 Install Signals east Camberwell Str 321 - Str 353 Joe Mifsud 0408 266 419
Permit to Work Summary
37
36
environmental Sites MTM HERITAGE SITE PLANS
Flags
taff
Melbou
rne
Centr
al
Parlia
men
t
North Melbourne
Foot
scra
y
Spotswood
Yarraville
Seddon
Newport
Nth Williamstown
Williamstown
WilliamstownLave
rton
Westona
Altona
SeaholmeAirc
raft
Cros
sing
Wer
ribee
West Footscray
Totte
nham
Middle Footscray
Sunsh
ineAlbion
Ginifer
Diggers Rest
Watergardens
Newmarket
Kensington
Showgrounds
Flemington
Racecourse
Ascot Vale
Moonee Ponds
Essendon
Glenbervie
Strathmore
Pascoe Vale
Oak Park
GlenroyJacana
Broadmeadows
Coburg
Moreland
Anstey
Brunswick
Royal Park
Flemington Bridge
Macaulay
Batman
Merlynston
Fawkner
Gowrie
Upfield
Jol im
ont
West Richmond
North Richmond
Collingwood
Victoria Park
Clifton Hill
Rushall
Merri
Northcote
Croxton
Thornbury
Bell
Preston
Regent
Reservoir
Ruthven
Keon Park
Thomastown
Lalor
Epping
Westgart
h
DennisFairfie
ld
Alphington
Darebin
Ivanhoe
Eaglemont
Heidelberg
Rosanna
Macleod
Watsonia
Greensborough
Montmorency
Eltham
Wattleglen
Hurstbridge
Sth Yarra
Prahran
Windsor
Balaclava
Ripponlea
Elsternwick
Gardenvale
Nth Brighton
Middle Brighton
Brighton Beach
Hampton
Sandringham
Beach
Hawks
burn
Toora
kArm
adale
Malvern
Caulfie
ld
Mordialloc
ParkdaleMentone
CheltenhamHighett
MoorabbinPatterson
BentleighMcKinnonOrmond
Glenhuntly
Aspendale Chel
sea
Bonb
each
Fran
ksto
n
To L
ong
Isla
nd
Leaw
arra
Baxt
er
Som
ervi
lle
Tyab
b
Hast
ings
Bitte
rn
Moo
rado
o
Ston
y Po
int
Crib
Poi
nt
Carnegie
Murrum
beena
Oakleigh
Hughesdale
HuntingdaleClayton
Westall
SpringvaleSandown Park
Noble ParkYarram
an
Dande
nong
Gener
al Moto
rsHall
am
Narre W
arren
Berwick
Beaco
nsfie
ldOffic
er
Merinda Park
Cranbourne
Diamond Creek
EastRichmond
BurnleyHawthorn
Glenferrie
AuburnWillis
on
Burwoo
d
Ashburto
n
AlameinRive
rsdale
Hartwell
Heyington
Kooyong
Tooronga
Gardiner
DarlingGlen Iris
East Malvern
Mount
Holmesglen
Jordanville
Syndal
Glen Waverley
East Camberwell
Canterbury
Chatham
Surrey Hills
Box Hill
Laburnum
Blackburn
Nunawading
Mitcham
Heatherdale
Ringwood
Mont Albert
Croydon
Mooroolbark
East Ringwood
Lilydale
Heathmon
tBoronia
Ferntree G
ully
Upper F
erntree G
ullyUpw
ey
Teco
ma
Belgrav
e
Craigieburn
Roxburgh Park
NewportShops
Pais
ley
Gal
vin( c
lose
d )
( clo
sed)
Southern
Flinders St
Cross
Lynbrook
St. Albans
Coolaroo
Sunbury
Carru
m
Seaf
ord
Kana
nook
Bayswate
r
Keilor Plains
Waverley
Hopp
ers
South Morang
Paken
ham
Cardini
a Roa
d
(clos
ed)
Edith
vale
Windsor Railway Station Complex
Ripponlea Railway Station Complex
Middle Brighton Railway Station
New Street Railway Gates
North Melbourne Railway Station Complex
Williamstown RailwayStation Complex
Werribee Railway Station
Yarraville - Interlocking Railay Crossing Gates,Anderson Street
Upfield Railway LinePrecinct: Park Streetto Coburg Station
Lilydale Railway Station Refreshment Rooms
Mentone Railway Station and Gardens
Caulfield Railway Station Complex
Clayton Railway Station Complex
South Yarra Railway Station
Sunshine (Devonshire Rd Footbridge) - HV McKayMemorial Gardens
Essendon RailwayStation Complex
Glenferrie RailwayStation Complex
Hawthorn RailwayStation Complex
Auburn RailwayStation Complex
Ringwood Railway Station Complex
Flinders Street RailwayStation Complex, including Signal Box A
Clifton Hill RailwayStation
Maribyrnong RiverRail Bridge
Footscray RailwayStation Complex
Malvern Railway Station
Flemington Railway SubstationFormer Tottenham Station
(archeological site undercarpark)
Aboriginal Cultural Heritage exclusion zone: Watsons Road, Diggers Rest to Jacksons Hill Bridge, Sunbury
Sunbury Railway Station - Water Tower
Sunbury: Railway bridge over Blind Creek
Sunbury Hill: Railway bridge over Jacksons Creek Tributary
Sout
hKe
nsin
gton
ALL PLACES REGISTERED WITH THE VICTORIAN HERITAGE REGISTER (VHR) OR THE VICTORIAN ABORIGINAL HERITAGE REGISTER (VAHR) ARE LEGALLY PROTECTED UNDER THE HERITAGE ACT 1995 AND THE ABORIGINAL HERITAGE ACT 2006.
This map shows network sites with a VHR or VAHR listing only.
Prior to commencing work check the most recent version of the Victorian Heritage Register in the Victorian Heritage database (Department of Planning and Community Development website) and Local Council Heritage Overlays (Local Council websites) as this list is not exhaustive.
NETWORK HERITAGE SITES L4-SQE-INF-020 Version: 1 Effective From: 15 March 2013
Camberwell
Approving Manager: Environment ManagerPRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION
Approved Date: 15/03/2013 Next Review Date: 15/03/2016Page 1 of 2
38
MTM PROTECTED FLORA PLAN
Sout
hKe
nsin
gton
Flag
staff
Melb
ourn
eCe
ntra
l
Parlia
men
t
North Melbourne
Foo t
scra
y
Spotswood
Yarraville
Seddon
Newport
Nth Williamstown
Williamstown
WilliamstownLave
rton
Westona
Altona
SeaholmeAirc
raft
Cros
sing
Wer
ribee
Wes
t Foo
tscr
ay
Totte
nham
Mid
dle
Foot
scra
y
Sunsh
ineAlbion
Ginifer
Diggers Rest
Watergardens
Newmarket
Kensington
Showgrounds
Flemington
Racecourse
Ascot Vale
Moonee Ponds
Essendon
Glenbervie
Strathmore
Pascoe Vale
Oak Park
GlenroyJacana
Broadmeadows
Coburg
Moreland
Anstey
Brunswick
Royal Park
Flemington Bridge
Macaulay
Batman
Merlynston
Fawkner
Gowrie
Upfield
Jol im
ont
West Richmond
North Richmond
Collingwood
Victoria Park
Clifton Hill
Rushall
Merri
Northcote
Croxton
Thornbury
Bell
Preston
Regent
Reservoir
Ruthven
Keon Park
Thomastown
Lalor
Epping
Westgarth
DennisFairfie
ld
Alphington
Darebin
Ivanhoe
Eaglemont
Heidelberg
Rosanna
Macleod
Watsonia
Greensborough
Montmorency
Eltham
WattleglenHurstbridge
Sth Yarra
Prahran
Windsor
Balaclava
Ripponlea
Elsternwick
Gardenvale
Nth Brighton
Middle Brighton
Brighton Beach
Hampton
Sandringham
Beach
Hawks
burn
Toora
kArm
adale
Malvern
Caulfie
ld
Mordialloc
ParkdaleMentone
CheltenhamHighett
MoorabbinPatterson
BentleighMcKinnonOrmond
Glenhuntly
Aspendale Edith
v ale
Che
lsea
Bonb
each
Fran
ksto
n
To L
ong
Isla
nd
Leaw
arra
Baxt
er
Som
ervi
lle
Tyab
b
Has
tings
Bitte
rn
Moo
rado
o
Ston
y Po
int
Crib
Poi
nt
Carnegie
Murrum
beena
Oakleigh
Hughesdale
HuntingdaleClayton
Westall
SpringvaleSandown Park
Noble ParkYarram
an
Dande
nong
Gener
al Moto
rsHall
am
Narre W
arren
Berwick
Beaco
nsfie
ldOffic
er
Merinda Park
Cranbourne
Diamond Creek
EastRichmond
BurnleyHawthorn
Glenferrie
Auburn
Willison
Burwood
Ashburto
n
AlameinRive
rsdale
Hartwell
Heyington
Kooyong
Tooronga
Gardiner
DarlingGlen Iris
East Malvern
Mount
Holmesglen
Jordanville
Syndal
Glen Waverley
East Camberwell
Canterbury
Chatham
Surrey Hills
Box Hill
Laburnum
Blackburn
Nunawading
Mitcham
Heatherdale
Ringwood
Mont Albert
Croydon
Mooroolbark
East Ringwood
Lilydale
Heathmon
tBoronia
Ferntree G
ully
Upper F
erntree G
ullyUpw
ey
Teco
ma
Belgrav
e
Craigieburn
Roxburgh Park
NewportShops
Pais
ley
Gal
vin
( clo
sed)
(clo
sed)
Southern
Flinders St
Cross
Lynbrook
St. Albans
Coolaroo
Sunbury
Car
rum
Seaf
ord
Kana
nook
Bayswater
Keilor Plains
Waverley
Hopp
ers
South Morang
Paken
ham
Cardini
a Roa
d
(clos
ed)
Camberwell
Windsor 7.758 - 8.214 Km - Down sideDandenong Road to Alma Road. Alma Park area.Unfenced.
Between Aircraft and Hoppers CrossingDSE No: 360824.55 - 25.35 Km - Up side.Forsyth Road.
SunshineDSE No: 359811.02 - 11.57 KmDown side. Near grain silos. Unfenced.
South Morang Fenced site adjacent to station on theUp side.
Heathmont28.442 - 28.473 Km - Up side.28.682 - 28.744 Km - Up side.28.796 - 29.057 Km - Up side.Three sites are Fenced.
Huntingdale18.1 - 18.183 - Up side.Huntingdale Station to Moroney St. Fenced.
Ginifer. DSE No: 359715.2 - 15.59 KmUp side. Threeseparate fenced sites.
Stony PointDSE No: 710774.00 - 74.30 Km.Up side. Fenced.
General Motors to HallamDSE No: 524036.15 - 36.70 Km - Up side.Fenced.
Officer 1. DSE No: 564048.50 - 48.6 Km - Up & Down.
Officer 2. DSE No: 5642 49.28 - 49.3 Km - Up side.
Officer 4. DSE No: 565050.3 - 50.55 Km - Down side.
PakenhamDSE No. 529959.50 - 61.60 Km - Up side59.96 - 61.66 Km - Down side.Ryan Road. Unfenced.
LangwarrinDSE No: 491748.71 - 51.97 - Up side.Langwarrin to Golf Links Road.
Merinda ParkDSE No: 513241.60 - 42.18 Km.Up side.
Cardinia Road. DSE No: 798352.92 - 53.15 Km - Down side
Greens RoadDSE No: 524534.77 - 34.89 - Up side.
St AlbansDSE No: 354618.35 - 18.50 Km - Down side18.54 - 18.73 Km - Down side18.31 - 18.50 Km - Up side Three separate fenced sites.
Calder Park (Diggers Rest 1/3)DSE No: 356829.02 - 29.30 Km - Up side
Calder Park (Diggers Rest 2/3)DSE No: 356928.90-29.25 Km - Down side
Calder Park (Diggers Rest 3/3)29.60-29.86 Km - Up side
Calder Park Rail Reserve SouthDSE No:8499: 27.64-27.86 Km - Up side & DSE No: 8435: 27.65-27.90 Km - Down side
Calder Park - Holden Road. DSE No: 8436. 28.35-28.55 Down side
Sydenham Rail Reserve 2. DSE No.8423. 24.37-25.16 Km - Up
Sydenham. DSE No.355125.50-25.77 - Down side
Barkers Creek - Sunbury Station. DSE No: 843736.68 - 37.49 Km - Down side
South Sunbury east. DSE No: 3526 36.60 - 36.85 Km - Up side
South Sunbury. DSE No: 352536.08 - 36.68 Km - Down side
Sunbury to Diggers Rest 1/5. DSE No: 3522 33.75 - 33.90 Km - Down side
Sunbury to Diggers Rest 2/5. DSE No: 352334.60 - 35.00 Km - Up side
Sunbury to Diggers Rest 3/5. DSE No: 352434.90 - 35.05 Km - Down side
Note: there is also an Aboriginal Cultural Heritage exclusion zone: Watsons Road, Diggers Rest to Jacksons Hill Bridge, Sunbury.
NETWORK PROTECTED FLORA SITES L4-SQE-INF-010 Version: 2 Effective From: 15 March 2013
Approving Manager: Environment ManagerPRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION
Approved Date: 15/03/2013 Next Review Date: 15/03/2016Page 1 of 2
BIOSITES ARE PROTECTED UNDER THE ENVIRONMENT PROTECTION AND BIODIVERSITY CONSERVATION ACT 1999 AND MAY CONTAIN RARE OR ENDANGERED PLANT SPECIES. SIGNIFICANT PENALTIES WILL APPLY IF THE VEGETATION IS DAMAGED OR DESTROYED.
Check this map and the Network Heritage Sites map (L4-SQE-INF-020) before carrying out work in the rail reserve. If in doubt, ask one of the following staff for clarification:
Tree Clearing and Conformance Officer, Infrastructure - Track Delivery
Environment Manager, HSEQ
38 39
MTM MFB/CFA BOUNDARY LIMITS