OCA IT Audit & Consulting Workshop—Session One

Guangzhou Asian Games Organizing Committee( GAGOC)

OCA Expert Committee Meeting

June 25th, 2007

SecuritySecurity

By Elaine Pang ,

Games Security Department

@GAGOC 2007

Mission

To ensure safety of all Asian Games

participants

To ensure security of the Asian Games

@GAGOC 2007

Programmes Included

Games Security

Accreditation

Traffic Management

@GAGOC 2007

Games Security

Mission

To ensure security & safety of Asian

Games venues, official hotels, Asian

Games Town, special events and

Asian Games guests and audience

To cooperate with the public security

authority in enhancing crackdown,

control and management on crimes

@GAGOC 2007

Games Security

Scope of Services1. To set standards for security facilities in

venues (including official hotels and Asian

Games Town)

2. To follow up and update the information

regarding construction of security facilities &

temporarily constructed buildings

3. To collect all related public security

information

4. To develop emergency response plan

@GAGOC 2007

Games Security

Work Breakdown Structure

Operational Plan of Venue Security

Residential Areas Security

Deployment of Security Staff

Operational Plan of Residential Areas Security

Standards for Security Facilities

Deployment ofAnti-explosion Facilities

Standards for Security Facilities

Venue Security

Fire Fighting Inspection on Residential Areas

Operational Plan of Fire Fighting

Concept of Operations

Operational Plan of Games Security

Fire Fighting

Venue Operational Plan

Regular Report

Post-Games Report

Inspection on Security Facilities

Deployment of Security Staff

Deployment ofAnti-explosion Facilities

Opening/Closing Ceremony Security

Inspection on Security Facilities

Deployment ofAnti-explosion Facilities

Operational Plan of Opening/Closing Ceremony Security

Fire Fighting Inspection on Venues

Fire-fighting Inspection on Opening/Closing Ceremony Venues

Planning & Management

Emergency Response Plan

Games Security

Operational Plan of Special Events Security

Deployment of Security Staff

Deployment of Anti-explosion Facilities

Temporarily Constructed Buildings Supervised

Special Events

Deployment of Security Staff

Inspection on Security Facilities

Standards for Security Facilities

@GAGOC 2007

Programme Deliverables & Key Dates

Key Dates Deliverables

Nov. 30, 2007 Concept of Operations for Games Security finished

Dec. 31, 2008 Operational Plan of Games Security finished

Dec. 31, 2009

Inspection Report on security facilities of special events and venues (including Asian Games Town, official hotels, Opening/Closing Ceremony Venue) finished

Inspection Report on fire fighting facilities of special events and venues (including Asian Games Town, official hotels, Opening/Closing Ceremony Venue) finished

Master Plan of Games Security Services developed

June 30, 2010

Operational Plans of special events and venues (including Asian Games Town, official hotels,

Opening/Closing Ceremony Venue) security developed

Operational Plans of special events and venues (including Asian Games Town, official hotels,

Opening/Closing Ceremony Venue) information and telecommunications security developed

Games Security

@GAGOC 2007

Key Dates Deliverables

June 30, 2010

Deployment Plan of anti-explosion facilities in special events and venues (including Asian Games Town, official hotels, Opening/Closing

Ceremony Venue) developed

Deployment Plan of security staff in special events and venues (including Asian Games Town, official hotels, Opening/Closing

Ceremony Venue) developed

Emergency Response Plan developed

Sept. 30, 2010

Deployment of security staff in special events and venues (including Asian Games Town, official hotels, Opening/Closing Ceremony Venue)

completed

Deployment of anti-explosion facilities in special events and venues (including Asian Games Town, official hotels, Opening/Closing

Ceremony Venue) completed

Safety notice for Games audience / Games guests / Opening Ceremony / Closing Ceremony compiled

Nov., 2010 Games-time Operation initiated

May 30, 2011 Post-games Report on Games Security developed

Games Security Programme Deliverables & Key Dates

@GAGOC 2007

Mission

To develop Asian Games

accreditation policies;

To produce and issue accreditation

cards to all Asian Games participants.

Accreditation

@GAGOC 2007

Accreditation

Scope of Services1.To establish Accreditation Center/Sub-centers

To establish Accreditation System

To train Accreditation Staff

2. To produce and issue Accreditation Cards

To handle and check on information of card holders

To produce and issue Accreditation Cards

3. To manage Accreditation System

To develop Accreditation Guideline

To develop Accreditation management policies

4. To cooperate in Access Control System Construction of IBC, MP

C and Asian Games Town

To make IC cards applicable to access control system

@GAGOC 2007

Accreditation

Work Breakdown Structure

Plan & Policies

Concept of Operations

Operational Plan

Accreditation Guideline &Management Policies

Submission of Progress Report

Post-Games Report

Design of Accreditation Cards

Category & Format of Accreditation Cards

Pattern of Accreditation Cards

Sample of Accreditation Card

Accreditation Information Management

Information Collection of Card Holders

Information Check on Card Holders

Operation of Accreditation Center/Sub-centers

Construction Standards for Accreditation Center/Sub-centers

Procurement of Accreditation Equipments and Raw Materials

Establishment of Accreditation Center/Sub-centers

Commissioning of Accreditation Center/Sub-centers

Training of Staff & Volunteers

Games-time Operation

Accreditation

@GAGOC 2007

Programme Deliverables & Key Dates

Key Dates DeliverablesNov. 30, 2007 Concept of Operations for Accreditation completed

Aug. 31, 2008 Plan of Accreditation cards design developed

Dec. 31, 2008Operational Plan of accreditation finished

Construction Standards of Accreditation Center/Sub-centers set

Jun. 30, 2009 Location of Accreditation Center /Sub-centers taken over

Sept. 30, 2009 Accreditation Guideline developed

Dec. 30, 2009 Accreditation facilities and raw materials procured

Mar. 31, 2010 Construction of Accreditation Center/Sub-centers finished

Accreditation Staff installed

Oct. 30, 2010Games-time Accreditation Plan developed

Commissioning of Accreditation Center / Sub-centers initiated Nov., 2010 Games-time Operation initiated

Apr. 30, 2011Post-games Report on Accreditation developed

Accreditation

@GAGOC 2007

Mission

To provide the Games with a

safe & smooth traffic environment

by utilizing Guangzhou

Intellectual Traffic Management

and Control System

Traffic Management

@GAGOC 2007

Traffic Management

Scope of Services1. To follow up and supervise the construction of

parking lots and transportation support facilities

around venues

2. To ensure a smooth & safe traffic around venues

during the Games

3. To open Green Passages for the round-trip route

between Games residential areas & venues

4. To enhance the road patrol to avoid traffic jams

5. To enhance education and publicity about traffic

safety

6. To develop emergency response plan

@GAGOC 2007

Traffic Management

Work Breakdown Structure

Games-time Traffic Management Policies

Traffic Management

Planning & Management

Traffic Management at Opening Ceremony

Traffic Management at Closing Ceremony

Development of Traffic Management Policies

Supervision on Venue Traffic Facilities Construction

Concept of Operations

Research Report on Traffic Organization Plan

Games-time Traffic Management

Games-time Traffic Security

Escort of police wagonsTraffic Services

ConsultationTraffic Security for special eventsEducation on Traffic

Safety

Evaluation on Traffic Security operation

Traffic Improvement

Publicity of Traffic Organization

@GAGOC 2007

Programme Deliverables & Key Dates

Key Dates DeliverablesNov., 2007 Concept of Operations finished

Jan., 2008Collection and Analysis of Traffic Organization Methods of Previous Asian Games & Olympic Games initiated

Mar., 2009 Research Report on Traffic Organization compiled

Sept., 2009Research Report on Traffic Management (first draft) finished

Oct., 2009 Suggestions on Improving Traffic Facilities Construction provided

Mar., 2010Research Report on Traffic Management (final draft) finished

May, 2010

Operational Plan of Games Residential Areas Traffic Security developed

Operational Plan of Traffic Security for the Route between Venues and Games Residential Areas developed

Operational plan of Venue Traffic Organization developed

Traffic Management

@GAGOC 2007

Programme Deliverables & Key Dates

Key Dates Deliverables

Sept., 2010 Publicity of Traffic Organization Measures launched

Oct., 2010 Measures of Traffic Improvement executed

Oct., 2010 Sub-plans of Traffic Security completed

Opening Ceremony Day Traffic Security of Opening Ceremony completed

Nov., 2010 Games-time Operation initiated

Closing Ceremony Day Traffic Security for Closing Ceremony completed

Jan., 2011Evaluation Report on Games-time Traffic Management completed

Traffic Management

@GAGOC 2007

Thank you

Mar 23, 2007

OCA Expert Committee Meeting

Guangzhou Asian Games Organizing Committee( GAGOC)