obstr hearing only
TRANSCRIPT
Coon Creek Watershed District
Board MeetingNovember 28, 2011
5. Hearing on the Obstruction of County Ditch 58-6 1. Convene Hearing2. Background & Presentation
4. Public Comment
6. Consider Findings7. Adjourn Hearing8. Consider and Adopt Resolution and Order
Purpose of hearing
To determine whether the Board of Managers should order the removal of an obstruction in Anoka County Public Ditch 58-6.
Held pursuant to Minnesota Statutes section 103E.075
In 1917Ditch 58 and 58-6 established
1964-1970 Crossing installed
1964 1970
Parcels in Drainage Area
313 acres
88 parcels draining to crossing
4738 feet of public ditch upstream of crossing
Affected Parcels
Carl “Dave” Turner and Sharon Turner17111 Polk Street NE
Deborah “Page” Heig17305 Polk Street NE
Dusty Esler17042 Polk Street NE
1991Mutual maintenance agreementMutual easement and maintenance agreement for
ingress and egress over Polk Street between:Eslers (parcel B)Turners (parcel D) Ashes (Heig) (parcel E)
signed and dated August 24th, 1991.
2011 Flooding
Looking downstream Looking upstream
5/23/2011
2011 Inspection
5/31/2011
Looking downstream Looking upstream
2011 Inspection
9/20/2011
Looking downstream Looking upstream
2011 Inspection
Looking downstream Looking upstream
10/17/2011
2011 Inspection
Looking downstream Looking upstream
11/1/2011
2011 Flooding
Erosion on driveway Flooding over driveway
5/23/2011
Safety and Flooding Concerns
Emergency access
Flood damage
Additional costs
Culvert
YesNoFlared End
0.06%Slope
896.8900.8Elevation
CMP or HDPECMPMaterial
40 feet longLength
42”24”Diameter
RecommendedExisting
SWMM Results
Estimated CostItem No. Item Units Quantity
Unit Cost Total
1 Mobilization LS 1 $2,000 $2,000
2 Remove and dispose 24"CMP LS 1 $300 $300
3 Furnish and install Class 5 bedding CY 12 $100 $1,200
4 Furnish and install 42"HDPE LF 24 $80 $1,920
5 F&I 42" HDPE FES LF 16 $135 $2,160
6 Driveway reconstruction Cl5 CY 60 $100 $6,000
7 Site vegetation (seed banks) LS 1 $100 $100
Total $13,680
Note:Cost estimate is based on a HDPE culvert. Other culvert materials may be used such as RCP or CMP but cost may vary.
Current Quotes42" CMP 42" HDPE
Ed Fields and Sons $8,700.00 $8,620.00Jordan Excavators* $12,760.00Forest Lake Contracting $13,960.60 $14,600.60G.F. Jedlicki Inc $23,911.00 $23,791.00Casper's Excavating**Sunram Construction Inc.
Note:*Quote obtained by Deborah “Page” Heig**Contacted by Carl “Dave” Turner, no quote yet receivedBlank cells indicate contractor was given a bid sheet but did not provide a quote